142
Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller, Mercedes Beaudoin, and Reid Ewing University of Utah, Metropolitan Research Center

BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

  • Upload
    others

  • View
    15

  • Download
    1

Embed Size (px)

Citation preview

Page 1: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

 

   

 

   

   

 

Provo/OremBRT

BeforeandAfterStudy:

InitialConditionsReport

MatthewM.Miller,

MercedesBeaudoin,

andReidEwing

UniversityofUtah,

MetropolitanResearchCenter

Page 2: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     2 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

 

   

Report No. UT‐17.XX 

PROVO-OREM TRANSPORTATION IMPROVEMENT PROJECT (TRIP)

Prepared for:

Utah Department of Transportation

Research Division

Submitted by:

University of Utah,

Metropolitan Research Center

Authored by:

Matthew M. Miller, Mercedes Beaudoin,

and Reid Ewing

Final Report

June 2017

Page 3: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     3 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

DISCLAIMER 

The authors alone are responsible for the preparation and accuracy of the information, 

data, analysis, discussions, recommendations, and conclusions presented herein. The contents 

do not necessarily reflect the views, opinions, endorsements, or policies of the Utah 

Department of Transportation or the U.S. Department of Transportation. The Utah Department 

of Transportation makes no representation or warranty of any kind, and assumes no liability 

therefore. 

ACKNOWLEDGMENTS 

The authors acknowledge the Utah Department of Transportation (UDOT) for funding 

this research through the Utah Transportation Research Advisory Council (UTRAC). We also 

acknowledge the following individuals from UDOT for helping manage this research: 

Jeff Harris  

Eric Rasband  

Brent Schvanaveldt 

Jordan Backman 

Gracious thanks to our paid peer reviewers in the Department of Civil & Environmental 

Engineering, Brigham Young University: 

Dr. Grant G. Schultz, Ph.D., P.E., PTOE.   

Dr. Mitsuru Saito, Ph.D, P.E., F. ASCE, F. ITE  

While not authors, the efforts of the following people helped make this report possible. 

Data Collection    Proof Reading/Edits  

Ethan Clark Ray    Debbie Weaver 

Thomas Cushing    Clint Simkins 

Jack Egan      Debolina Banerjee 

Katherine A. Daly    Katherine A. Daly 

 

 

     

Page 4: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     4 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Technical Report Documentation Page (Form DOT 1700.7)

1. Report No.

2. Government Accession No. 3. Recipients Accession No.

4. Title and Subtitle

Effects of Bus Rapid Transit on Traffic in a Travel Corridor: Provo/Orem BRT: 

Before and After Study: Initial Conditions Report.

5. Report Date

2017‐06‐13 5:00:00 PM

6. Performing Organization Code

7. Author(s) 

Matthew M. Miller,      Mercedes Beaudoin,               and Reid Ewing  

8. Performing Organization Report No.

9. Performing Organization Name and Address

University of Utah,                                        Metropolitan Research Center  375 S. 1530 E. Room 235 AAC Salt Lake City, Utah 84112

10. Work Unit No.

11. Contract (C) or Grant (G) No.

12. Sponsoring Organization Name and Address

Utah Department of Transportation, Research Division 4501 South 2700 West, PO Box 148410 Salt Lake City, UT 84114‐1265 

13. Type of Report and Period Covered

Peer Reviewed Report; Final Report; 2015 14. Sponsoring Agency Code

15. Supplementary Notes

This project was funded by the Utah Department of Transportation (UDOT), the Utah Transit Authority (UTA), 

Salt Lake County (SLCo), the Wasatch Front Regional Council (WFRC), and the Mountainland Association of 

Governments (MAG). 

16. Abstract (Limit: 200 words)

This report presents the initial conditions for the Provo‐Orem Transportation Improvement Project (TRIP). TRIP consists of a number of transportation improvements, including the construction of new Bus Rapid Transit. Traffic counts of Average Annual Daily Traffic were obtained for the project alignment and identified diversion corridors. Data on the ridership of all bus lines and rail lines within the study area was collected. To make it possible to establish trend lines for growth in traffic and in transit ridership, data from at least five years prior to BRT construction was collected for both AADT and transit ridership. To control for changes in traffic, it was necessary to control for traffic generation within the study area. County tax assessor data was used to determine initial levels of development within the study area, and these data were checked against aerial photo imagery. Each parcel in the assessor database was matched with the Institute of Transportation Engineers (ITE) Trip Generation Manual code it best resembles. Using the associated trip rate, trips generated for each parcel were estimated. The trips from all parcels in the study area were summed to estimate the total number of trips generated within the study area. For Brigham Young University and Utah Valley University, data on student enrollment and faculty and staffing levels were gathered to establish a baseline for travel demand. 

17. Key  Words 

Bus Rapid Transit, Safety, 

Environmental Quality, 

Capacity, Congestion  

18.Availability Statement

Metropolitan Research Center, University of Utah, Salt Lake City 84102 Phone: 801.587.9483 < http://plan.cap.utah.edu/research/metropolitan‐research‐center>. 

19. Security Class (this report)

Unclassified 

 

20. Security Class (this page) Unclassified 

21. No. of Pages

142 

22. Price NA 

Page 5: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     5 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Table of Contents   2 

PROVO-OREM TRANSPORTATION IMPROVEMENT PROJECT (TRIP) ....................... 2 

Technical Report Documentation Page .......................................................................................... 4 

Table of Contents ............................................................................................................................ 5 

Table of Figures ............................................................................................................................... 9 

Acronyms & Abbreviations ........................................................................................................... 12 

Executive Summary ....................................................................................................................... 14 

1  Introduction ........................................................................................................................... 16 

1.1  Study Overview .............................................................................................................. 16 

1.2  Report Objectives ........................................................................................................... 17 

1.3  Previous Research .......................................................................................................... 17 

1.4  Report Structure ............................................................................................................. 17 

1.4.1  Report Structure Outline ............................................................................................ 18 

2  Project Context ...................................................................................................................... 19 

2.1  Urban Context ................................................................................................................ 19 

2.2  Transportation Context .................................................................................................. 19 

3  Project Description ................................................................................................................ 21 

3.1  Running Ways ................................................................................................................. 21 

3.2  Stations & Stops ............................................................................................................. 21 

3.3  Vehicles .......................................................................................................................... 21 

3.4  Fare Collection ................................................................................................................ 22 

3.5  Intelligent Transportation Systems ................................................................................ 22 

3.6  Service and Operations Plans ......................................................................................... 24 

3.7  Roadway Improvements ................................................................................................ 24 

3.8  Active Transportation Improvements ............................................................................ 25 

4  System Costs .......................................................................................................................... 26 

4.1  Project Costs ................................................................................................................... 26 

Page 6: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     6 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

4.2  Project Funding .............................................................................................................. 27 

5  Planning, Design & Implementation ...................................................................................... 28 

5.1  Institutional Context ....................................................................................................... 28 

5.2  Project Development History ......................................................................................... 28 

5.3  Project Design & Implementation .................................................................................. 30 

5.4  Station & Guideway Planning ......................................................................................... 31 

5.4.1  Station Changes Over Time ........................................................................................ 38 

5.4.2  Guideway Changes Over Time .................................................................................... 38 

5.4.3  Changes due to Campus Unification Plan................................................................... 39 

6  Research Approach ................................................................................................................ 40 

6.1  Quasi‐Experimental Research Design ............................................................................ 40 

6.1.1  A Natural Experiment ................................................................................................. 40 

6.1.2  Interrupted Time Series .............................................................................................. 40 

6.2  Null Hypothesis Testing .................................................................................................. 41 

6.3  Conceptual Framework .................................................................................................. 41 

6.4  Data Collection Plan ....................................................................................................... 44 

6.5  Study Bounds – Geographic Extents .............................................................................. 44 

6.5.1  Diversion Corridors ..................................................................................................... 44 

6.5.2  Future Alignment ........................................................................................................ 48 

6.5.3  Buffered Alignment .................................................................................................... 49 

6.6  Data Source Limitations ................................................................................................. 51 

6.7  Timing of Traffic and Ridership Changes ........................................................................ 51 

7  Evaluation of System Performance ....................................................................................... 53 

7.1  Travel Times ................................................................................................................... 53 

7.2  Schedule Reliability ........................................................................................................ 53 

7.3  Identity & Image ............................................................................................................. 53 

7.4  Safety & Security ............................................................................................................ 54 

7.4.1  Safety .......................................................................................................................... 54 

7.4.2  Security ....................................................................................................................... 55 

7.5  Capacity .......................................................................................................................... 55 

Page 7: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     7 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

8  Assessment of System Benefits ............................................................................................. 57 

8.1  Transit Ridership............................................................................................................. 57 

8.1.1  Methods & Data ......................................................................................................... 61 

8.1.2  Results & Discussion ................................................................................................... 62 

8.1.3  Data Limitations .......................................................................................................... 71 

8.2  Capital Cost Effectiveness .............................................................................................. 73 

8.3  Operating Cost Efficiency ............................................................................................... 74 

8.4  Transit Supportive Land Use Development ................................................................... 74 

8.4.1  Current Land Uses ...................................................................................................... 74 

8.4.2  Potential Future Land Use .......................................................................................... 75 

8.4.3  Timing of Land Use Changes ....................................................................................... 75 

8.5  Environmental Quality (Vehicle Emissions) ................................................................... 78 

8.5.1  Methods & Data ......................................................................................................... 78 

8.5.2  Results & Discussion ................................................................................................... 81 

8.5.3  Data Limitations .......................................................................................................... 83 

9  System Effects on Roadway Network .................................................................................... 85 

9.1  Traffic Counts ................................................................................................................. 85 

9.1.1  Methods & Data ......................................................................................................... 85 

9.1.2  Results & Discussion ................................................................................................... 87 

9.1.3  Data Limitations .......................................................................................................... 92 

9.2  Trip Generation by New Development .......................................................................... 96 

9.2.1  Methods & Data ......................................................................................................... 96 

9.2.2  Results & Discussion ................................................................................................... 96 

9.2.3  Data Limitations .......................................................................................................... 97 

9.3  New Transportation Infrastructure .............................................................................. 100 

9.4  Student Enrollment & Employment ............................................................................. 102 

9.4.1  Methods & Data ....................................................................................................... 102 

9.4.2  Results & Discussion ................................................................................................. 103 

9.4.3  Data Limitations ........................................................................................................ 106 

9.5  Land Development ....................................................................................................... 106 

9.5.1  Method & Data ......................................................................................................... 106 

Page 8: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     8 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

9.5.2  Results & Discussion ................................................................................................. 107 

9.5.3  Data Limitations ........................................................................................................ 107 

9.6  Parking Supply & Occupancy ........................................................................................ 109 

9.6.1  Methods & Data ....................................................................................................... 109 

9.6.2  Results & Discussion ................................................................................................. 113 

9.6.3  Data Limitations ........................................................................................................ 116 

9.7  Crash Rates within Study Area ..................................................................................... 117 

9.7.1  Methods & Data ....................................................................................................... 117 

9.7.2  Results & Discussion ................................................................................................. 117 

9.7.3  Data & Methodology Limitations ............................................................................. 119 

10  Summary .......................................................................................................................... 120 

PROVO-OREM TRANSPORTATION IMPROVEMENT PROJECT (TRIP) APPENDICES........................................................................................................................... 121 

11  APPENDIX A. LITERATURE REVIEW .................................................................................. 122 

11.1  Introduction .................................................................................................................. 122 

11.2  Bus Rapid Transit and Safety ........................................................................................ 122 

11.2.1 BRT & Traffic Crashes ............................................................................................... 122 

11.2.2 BRT Literature Attempting to Measure Safety ......................................................... 123 

11.2.3 BRT Design and Safety .............................................................................................. 125 

11.3  Bibliography.................................................................................................................. 127 

12  APPENDIX B.: ITE Trip Generation Rates .......................................................................... 129 

13  APPENDIX C.  Crash Locations .......................................................................................... 132 

 

Page 9: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     9 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Table of Figures  

FIGURE 2‐1: PROJECT CONTEXT MAP ................................................................................................................................... 20 

FIGURE 3‐1: LOCATION OF TRANSIT SIGNAL PRIORITY IMPROVEMENTS ....................................................................................... 23 

FIGURE 4‐1: 2011 EA SYSTEM COSTS BY TRANSIT ELEMENT .................................................................................................... 26 

FIGURE 4‐2: 2011 EA SYSTEM COSTS BY CATEGORY .............................................................................................................. 27 

FIGURE 5‐1: 2007 MAG ALIGNMENT AND 2015 EA LOCALLY PREFERRED ALTERNATIVE .............................................................. 29 

FIGURE 5‐2: JANUARY 2015 PROJECT TIMELINE .................................................................................................................... 30 

FIGURE 5‐3: THE NOVEMBER 2016 PROJECT TIMELINE ........................................................................................................... 30 

FIGURE 5‐4: 2010 UTA PROJECT INFO SHEET ....................................................................................................................... 32 

FIGURE 5‐5: 2011 EA LOCALLY PREFERRED ALTERNATIVE ....................................................................................................... 33 

FIGURE 5‐6: 2011 MAG 2040 PROJECT MAP ...................................................................................................................... 34 

FIGURE 5‐7: 2013 PROJECT INFO SHEET .............................................................................................................................. 35 

FIGURE 5‐8: 2014 EA LOCALLY PREFERRED ALTERNATIVE ....................................................................................................... 36 

FIGURE 5‐9: DECEMBER 2016 PROJECT MAP ........................................................................................................................ 37 

FIGURE 6‐1: CONCEPTUAL FRAMEWORK ............................................................................................................................... 43 

FIGURE 6‐2: THE NOVEMBER 2016 PROJECT TIMELINE ........................................................................................................... 44 

FIGURE 6‐3: MAP OF DIVERSION CORRIDORS AND SCREEN LINES .............................................................................................. 47 

FIGURE 6‐4: MAP OF HOV EXCHANGE AT 800 SOUTH IN OREM ............................................................................................... 48 

FIGURE 6‐5: MAP OF STUDY AREA DEVELOPMENT BOUNDARIES ............................................................................................... 50 

FIGURE 7‐1: PEAK HOUR TRANSIT CAPACITY ......................................................................................................................... 55 

FIGURE 8‐1: TRANSIT ROUTES NEAR UVU ............................................................................................................................ 58 

FIGURE 8‐2: TRANSIT ROUTES AND HEADWAY IN STUDY AREA 2015 ......................................................................................... 59 

FIGURE 8‐3: TRANSIT ROUTES IN STUDY AREA 2016 .............................................................................................................. 60 

FIGURE 8‐4: TRANSIT ROUTES NEAR BYU 2015 .................................................................................................................... 61 

FIGURE 8‐5: TRANSIT RIDERSHIP IN UTAH COUNTY ................................................................................................................. 62 

FIGURE 8‐6: FRONTRUNNER RIDERSHIP 2009—2015 FOR OREM CENTRAL AND PROVO CENTRAL STATIONS ................................... 63 

FIGURE 8‐7: UTAH COUNTY BUS RIDERSHIP BY MONTH 2010‐2015 ........................................................................................ 63 

FIGURE 8‐8: ANNUAL AND DAILY RIDERSHIP FOR THE BRT ....................................................................................................... 64 

FIGURE 8‐9: ROUTE 830, APRIL 2011 ................................................................................................................................. 65 

FIGURE 8‐10:  ESTIMATED AVERAGE DAILY RIDERSHIP, DRIVER COUNTS, ROUTE 830 ................................................................... 66 

FIGURE 8‐11: ESTIMATED AVERAGE DAILY RIDERSHIP, APC, ROUTE 830 ................................................................................... 66 

FIGURE 8‐12: FORECAST ROUTE RIDERSHIP, IN RIDERS/DAY ..................................................................................................... 67 

FIGURE 8‐13: THE RYDE ROUTES 2016 ............................................................................................................................... 69 

FIGURE 8‐14: THE RYDE ROUTES 2015 ............................................................................................................................... 70 

FIGURE 8‐15: BOARDINGS AND ALIGHTINGS FOR ROUTES 830 AND 838 IN 2015 ........................................................................ 72 

FIGURE 8‐16: EQUIVALENT ANNUAL COST CALCULATION ......................................................................................................... 73 

FIGURE 8‐17: CAPITAL COST EFFICIENCY BASED ON 2011 FORECAST ......................................................................................... 74 

FIGURE 8‐18: STUDY AREA LAND USES CIRCA 2015/2016 ..................................................................................................... 77 

FIGURE 8‐19: VMT BY FACILITY TYPE AND GEOGRAPHY .......................................................................................................... 78 

FIGURE 8‐20: SHARE OF VMT BY VEHICLE/FUEL TYPE AND GEOGRAPHY .................................................................................... 79 

FIGURE 8‐21: EMISSIONS IN GRAMS PER MILE BY VEHICLE AND FUEL TYPE ................................................................................. 80 

FIGURE 8‐22: SHARE OF EMISSIONS BY VEHICLE TYPE ............................................................................................................. 81 

FIGURE 8‐23: AVERAGE ANNUAL EMISSIONS BY VEHICLE TYPE FOR DIVERSION CORRIDORS IN GRAMS ............................................. 82 

Page 10: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     10 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

FIGURE 8‐24: SHARE OF VEHICLES BY VEHICLE AND FUEL TYPE ................................................................................................. 84 

FIGURE 9‐1: INTERSECTIONS ALONG BRT ALIGNMENT ............................................................................................................. 86 

FIGURE 9‐2: ESTIMATED AADT ON DIVERSION CORRIDORS 2010—2015 ................................................................................. 87 

FIGURE 9‐3: ESTIMATED AADT BY DIVERSION CORRIDOR 2010‐2015 ...................................................................................... 88 

FIGURE 9‐4: ESTIMATED AND FORECAST AADT 2010‐2020 ................................................................................................... 89 

FIGURE 9‐5: ESTIMATED AADT BY SCREEN LINE 2010—2015 ................................................................................................ 90 

FIGURE 9‐6: ESTIMATED AADT AND CHANGES BY SCREEN LINE 2010‐2015 .............................................................................. 91 

FIGURE 9‐7: TRAFFIC SIGNAL COUNTS .................................................................................................................................. 91 

FIGURE 9‐8: MAP OF DIVERSION CORRIDORS AND SCREEN LINES .............................................................................................. 94 

FIGURE 9‐9: ‘BLOOD VESSEL’ MAP OF 2015 AADT ............................................................................................................... 95 

FIGURE 9‐10: TRIP GENERATION TOTALS BY LAND USE CLASS .................................................................................................. 97 

FIGURE 9‐11: MAP OF STUDY AREA LAND USE ...................................................................................................................... 99 

FIGURE 9‐12: PROJECT AREA TRANSPORTATION IMPROVEMENTS ............................................................................................ 100 

FIGURE 9‐13: STUDENT HEADCOUNT, FTE, AND FULL‐TIME STUDENTS FOR UVU ...................................................................... 103 

FIGURE 9‐14: STUDENT HEADCOUNT, FTE, AND FULL‐TIME STUDENTS FOR BYU ...................................................................... 103 

FIGURE 9‐15: STUDENT HEADCOUNT, FULL‐TIME EQUIVALENT, AND FULL‐TIME STUDENTS FOR BYU & UVU ................................ 104 

FIGURE 9‐16: FULL‐TIME AND PART‐TIME EMPLOYMENT FOR UVU AND BYU 2010‐2015 ........................................................ 105 

FIGURE 9‐17: FULL‐TIME AND PART‐TIME EMPLOYMENT FOR BYU ......................................................................................... 105 

FIGURE 9‐18: FULL‐TIME AND PART‐TIME EMPLOYMENT FOR UVU ........................................................................................ 106 

FIGURE 9‐19: STUDY AREA POPULATION & HOUSING UNITS PER ACRE .................................................................................... 107 

FIGURE 9‐20: EXAMPLE OF ‘DOTTED’ PARKING STALLS .......................................................................................................... 109 

FIGURE 9‐21: UVU PARKING MAP ................................................................................................................................... 110 

FIGURE 9‐22: MAP OF PARKING AT BYU, 2015 .................................................................................................................. 111 

FIGURE 9‐23: PARKING SUPPLY AND OCCUPANCY ................................................................................................................ 114 

FIGURE 9‐24: PARKING OCCUPANCY PATTERN ..................................................................................................................... 115 

FIGURE 9‐25: MAP OF ALIGNMENT AND DIVERSION CORRIDOR CRASH RATES ........................................................................... 118 

FIGURE 11‐1: COMMON BRT CRASHES .............................................................................................................................. 123 

FIGURE 11‐2: VECINO‐ORTIZE AND HYDER'S REVIEW OF BRT SAFETY STUDIES ........................................................................... 125 

 

   

Page 11: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     11 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Page 12: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     12 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Acronyms & Abbreviations  

AA    Alternatives Analysis 

AADT    Annual Average Daily Traffic 

ACS    American Community Survey 

APC    Automatic Passenger Counter 

BRT     Bus Rapid Transit 

BYU     Brigham Young University 

CBD    Central Business District 

CH4    Methane 

CNG    Compressed Natural Gas 

CO    Carbon Monoxide 

CO2    Carbon Dioxide 

EA     Environmental Assessment 

EPA     U.S. Environmental Protection Agency 

FHWA    Federal Highway Administration  

FONSI     Finding of No Significant Impact  

FTA     Federal Transit Administration  

GREET    Greenhouse Gases, Regulated Emissions, and Energy Use in Transportation 

HOV    High Occupancy Vehicle 

HOT    High Occupancy Vehicle or Toll 

I‐15     Interstate 15  

IDTP     Institute for Transportation and Development Policy 

ITE    Institute of Transportation Engineers 

KML    Keyhole Markup Language 

LDS     Church of Jesus Christ of Latter‐day Saints  

Page 13: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     13 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

LBCS    Land Based Classification System 

LRTP    Long Range Transportation Plan 

LPA    Locally Preferred Alternative 

MAG     Mountainland Association of Governments  

MOVES  Motor Vehicle Emissions Simulator 

NOx    Nitrous Oxides 

NO2    Nitrous Dioxide 

O3     Ozone      

PER_DU  Per Dwelling Unit 

PER_KSF  Per Thousand Square Feet 

PM2.5    Particulate matter with a diameter of 2.5 microns or less  

PM10     Particulate matter with a diameter of 10 microns or less parts per million 

RFP    Request For Proposal 

SO2     Sulfur Dioxide  

TIP    Transportation Improvement Program 

TOD     Transit‐oriented Development  

TRIP    Transportation Improvement Project 

TSP     Transit Signal Priority      

UDOT     Utah Department of Transportation  

UTA     Utah Transit Authority  

UVU     Utah Valley University 

VMT    Vehicle Miles Traveled 

VOC    Volatile Organic Compounds 

 

Page 14: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     14 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Executive Summary  

This report documents the initial conditions for the Provo‐Orem Transportation 

Improvement Project (TRIP) alignment. The intent of the project is to analyze four outcomes:  1) 

Traffic Counts; 2) Transit Ridership; 3) Land Development; and 4) Crash Rates while controlling 

for changes in university enrollment, new trip generation from land development, and parking 

supply. Collecting data on these factors prior to the improvements makes it possible to make 

before and after comparisons, while controlling for other factors makes it possible to determine 

the effects of the bus rapid transit (BRT). The default (“null”) hypothesis is that TRIP will have 

no significant effects on any of the outcomes after controlling for other factors. This study uses 

a quasi‐experimental design. A quasi‐experimental research design takes advantage of a 

“treatment” applied to one group but not to another and compares the differences before and 

after the treatment for both groups. In this case, the treatment consists of the improvements 

included in the Provo‐Orem TRIP. To ensure the rigor of the analysis, the results are subject to 

the critical review of independent experts who were not involved with the production of the 

report.  

Performing this quasi‐experimental analysis requires collecting data before and after the 

treatment. In the case of this study, data for multiple years prior to the study were collected to 

determine initial conditions for the initial conditions report. Following a gap year for the 

construction period, data will be collected for three years of operations with a report issued for 

each year, making an effective before and after comparison. Collecting this multiple‐year time 

series makes it possible to project current trends into the future. In later reports, this will also 

make it possible to compare projected trends to actual values. Initial conditions data collection 

took place in 2015. After operations begin (circa 2019), a second round of data collection will 

occur and a second report will be released. A third and fourth round of data collection are 

planned for the following years.  

For annual average daily traffic (AADT) counts on the BRT alignment and identified 

diversion corridors, the trend line is flat for all corridors except Orem 820 North and I‐15. 

Page 15: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     15 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

According to screen line counts, total traffic parallel corridors continue to grow. This suggests 

that many of the corridors in the study area are at capacity and that traffic is already diverting 

to alternate routes.  

Overall, transit ridership is growing in Utah County. Much of that growth is FrontRunner 

ridership. Total bus ridership was in decline before the advent of FrontRunner, but stabilized 

thereafter, and is now rising. Ridership on Route 830 (the BRT alignment) has dropped 

substantially since 2010. As a consequence, the forecasts from the 2011 Environmental 

Assessment appear high.  Possible reasons include changes in route alignment and changes in 

BYU’s transit policy. The largest number of boardings for Route 830 take place at Orem 

FrontRunner, Utah Valley University (UVU), the Timpanogas transit center, the southwest 

corner of Brigham Young University (BYU), and Provo FrontRunner. Student enrollment and 

staffing has recovered to its 2011 level, following a 2012‐2014 dip. UVU experienced a 

substantial increase in enrollment and employees between 2008 and 2011, but has not 

surpassed maximum ridership since. 

All census blocks in the study area (a 1/4‐mile buffer around the alignment) were 

queried to determine the number of housing units and population. This will be checked against 

future census years, and will be used to gauge the effects of land development against current 

population and housing units. All parcels within the study census blocks were assigned an ITE 

trip generation code. Using data from the Utah County Assessor database, the number of 

dwelling units and square footage of residential parcels was estimated to compare against 

future conditions. Substantial additional data, such as the number of stories and other metrics, 

was created using Google Earth. In future reports, changes in the Utah County Assessor 

database can be checked against this data set to detect land use changes. The land uses within 

the study area (6,219 acres) generate a very large number of trips, of which the majority can be 

attributed to commercial uses.  

 

Page 16: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     16 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

1 Introduction This section provides an overview of the study, detailing the purpose of the study, the history 

and background of Bus Rapid Transit in America, the report objectives, and the structure of the 

report.  

1.1 Study Overview 

This report investigates how the addition of bus rapid transit (BRT) affects roadway traffic using 

a case study of a new BRT planned and designed for the cities of Orem and Provo in Utah 

County, Utah. The project consists of 18 stations along a 10.5‐mile BRT alignment that connects 

the Orem Intermodal Center with the Novell Provo Campus. Intermediate destinations include 

Utah Valley University (UVU), Utah Valley Medical Center, University Mall, Brigham Young 

University (BYU), the Provo Central Business District (CBD), the Provo Intermodal Center, and 

Provo Town Center Mall. 

Following the success of the Emerald Express BRT in Eugene, Oregon, many metropolitan areas 

are making plans for BRT. At the same time, most cities are also experimenting with packages of 

service and infrastructure improvements, frequently labeling these upgrades as BRT even 

though few routes actually meet these criteria.  

A 2011 report by the Institute for Transportation & Development Policy1 found that there are 

only five bus corridors in the United States that meet the Bus Rapid Transit Standard: Eugene, 

Las Vegas, Los Angeles, Cleveland, and Pittsburgh.2 Seattle’s SODO bus tunnel and San 

Bernardino’s SBX met the BRT standard as of 2014.3 The Federal Transit Administration (FTA) 

itself acknowledges two grades, BRT and BRT‐lite, with the former requiring 51 percent of the 

alignment consisting of exclusive guide‐way. While BRT has long been suggested as a solution 

to the urban transportation problem,4 the concept has only recently become popular in 

American transportation policy. Cities across the nation are experimenting with ways to make a 

“better bus.” Like other forms of rapid transit, BRT has been promoted as a means to reduce 

congestion, improve air quality, reduce automobile dependence, and induce redevelopment.5 

                                                       

1 Weinstock, A., Hook, W., Replogle, M., & Cruz, R. (2011, May). Recapturing Global Leadership in Bus Rapid Transit: A Survey of Select U.S. Cities. Retrieved from https://www.itdp.org/wp‐content/uploads/2014/07/20110526ITDP_USBRT_Report‐LR.pdf 2 Institute for Transportation and Development Policy. (2014). The BRT Standard: 2014 Edition. Retrieved from https://www.itdp.org/wp‐content/uploads/2014/07/BRT‐Standard‐2014.pdf 3 Institute for Transportation and Development Policy. (2014). BRT Standard Scores. Retrieved from https://www.itdp.org/publication/brt‐standard‐scores/ 4 Meyer, J. R., Kain, J. F., & Wohl, M. (1966). The Urban transportation Problem. London: Harvard University Press. 5 Thole, C., & Samus, J. (2009). Bus Rapid Transit and Development: Policies and Practices that Affect Development Around Transit (No. FTA‐FL‐26‐7109.2009. 5). 

Page 17: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     17 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

While there is a growing literature on BRT, studies are largely focused on ridership outcomes 

and/or economic development. This study expands the scope of research to include the effects 

of BRT on a number of other factors. This research is intended to provide generalizable 

information about the effects of BRT. 

1.2 Report Objectives 

The objectives of this study are to determine the impacts of the Provo‐Orem BRT on both travel 

demand along the corridor and the travel capacity of the corridor. The specific objectives are to 

measure changes in:  

Automobile traffic in the corridor between baseline and forecast conditions; 

Land uses along the corridor; 

Parking occupancy at the two universities; 

Transit ridership; 

Other co‐benefits of reduced automobile traffic, such as reduced vehicle emissions and 

reduction in the number and severity of traffic collisions. 

1.3 Previous Research 

The analysis of the BRT project began with a review of academic and professional literature on 

the effects of arterial BRT on traffic, congestion, and safety. The amount of literature available 

proved to be extremely limited. Most before‐and‐after studies have focused on the effects on 

transit ridership, travel‐time, reliability, and passenger satisfaction. Only four articles related to 

BRT safety were found. The literature review can be found in APPENDIX A. LITERATURE 

REVIEW.  

1.4 Report Structure 

This evaluation is organized in accordance with the framework outlined in the Characteristics of 

Bus Rapid Transit for Decision‐Making6 report. This framework covers ridership, vehicle 

emissions, and traffic crashes. This evaluation includes an additional sub‐section under 

“Assessment of System Benefits” to address parking occupancy.  

Additionally, the section “System Effects on Roadway Network” has been added to evaluate 

other factors that we anticipate the Provo‐Orem Bus Rapid Transit will affect. These include the 

                                                       

6 Chang, M., Darido, G., Kim, E., Schneck, D., Hardy, M., Bunch, J., ... & Zimmerman, S. (2004). Characteristics of bus rapid transit for decision‐making (No. FTA‐VA‐26‐7222‐2004.1). 

Page 18: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     18 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

effect of the BRT on automobile traffic volumes after controlling for new interchanges, land use 

changes, university staffing and enrollment, and other factors. 

1.4.1 ReportStructureOutline

Introduction 

Project Context 

Project Description 

a. Running Ways 

b. Stations/Stops 

c. Vehicles 

d. Fare Collection 

e. Intelligent Transportation Systems (ITS) 

f. Service and Operations 

g. Marketing & Community Outreach 

System Costs 

Planning, Design & Implementation 

Evaluation of System Performance 

a. Travel Time 

b. Reliability 

c. Identity & Image 

d. Safety & Security (Crashes) 

e. Capacity 

Assessment of System Benefits 

a. Ridership 

b. Capital Cost Effectiveness 

c. Operating Cost Efficiency 

d. Transit Supportive Land Development 

e. Environmental Quality (Vehicle Emissions) 

System Effects on Roadway Network 

a. Traffic Counts and Trends 

b. New Development 

c. New Transportation Infrastructure 

d. Student Enrollment 

e. Parking Supply & Occupancy 

f. Crash Rates 

Conclusion 

   

Page 19: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     19 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

2 Project Context This section covers the context for the project, both in terms of geographic location and in 

terms of recent and ongoing transportation investments. 

2.1 Urban Context 

Utah County is the heartland of the state of Utah. It is currently experiencing rapid population 

growth with an increase of 11.3 percent between 2010 and 2015.7 While the county is large, 

the vast majority of the population is located in the linear corridor between Utah Lake and the 

Wasatch Mountains. Most of the metropolitan population is distributed along Interstate‐15 (I‐

15), the major limited‐access highway in the county. Other major highways include Highway 89 

and Highway 189. The contiguous urbanized area (by incorporated boundaries) now stretches 

from the edge of Salt Lake County south to Spanish Fork, and westward from the Wasatch 

mountains to the cities of Eagle Mountain and Fairfield. The urbanized area is continuing to 

expand, with additional cities incorporating and existing cities continuing to densify. Traffic 

congestion has been a significant problem along I‐15 resulting in it being widened in 2014—

2016. Significant future travel demand is expected. 

2.2 Transportation Context 

Several major transit investments have recently been made in Utah County as part of the 

strategy for meeting future travel demand caused by the expected population growth. With the 

advent of FrontRunner Commuter Rail service in 2012, rapid transit returned to Utah County for 

the first time in decades. The FrontRunner South project extended the existing FrontRunner 

terminus from downtown Salt Lake City (in northern Salt Lake County) 44 miles south into the 

middle of Utah County. As part of the extension, eight new stations were constructed, including 

four in Utah County. As detailed in sub‐section 8.1, this extension resulted in a large increase in 

total ridership on FrontRunner. Ridership at the Provo and Orem stations have increased each 

year. 

Like most modern commuter rails, FrontRunner re‐used a pre‐existing freight railway corridor, 

which means that many of its stations are distant from major activity centers in the metro area. 

The Provo‐Orem BRT helps solve this problem. It connects to both the Orem and the Provo 

FrontRunner stations, and it provides a ‘last mile’ service connecting passengers using 

                                                       

7 United States Census Bureau. (n.d.). Quick Facts‐Utah County, Utah. Retrieved May 21, 2017, from 

https://www.census.gov/quickfacts/table/PST120215/49049,00 

Page 20: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     20 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Frontrunner with major destinations within Utah County. Figure 2‐1 shows the location of the 

planned BRT alignment, its connection to FrontRunner, and its relationship to major roadways. 

Figure 2‐1: Project Context Map 

 

Page 21: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     21 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

3 Project Description This section describes the characteristics of the Provo‐Orem Bus Rapid transit. Specifically, it 

covers the running way, stations and stops, vehicles, fare collection, Intelligent Transportation 

System elements, and the service and operation plan.  

3.1 Running Ways 

“The Project is approximately 10.5 miles long and consists of exclusive bus lanes (51 percent), 

the majority of which are center lanes.” 8 The majority of the exclusive bus lanes are along 

University Parkway between 400 West and US‐189. Much of the remainder is on US‐189 

between Provo 700 North and Provo 300 south. 

3.2 Stations & Stops 

“The Project…consists of…18 stations, nine (9) center platforms, seven (7) side stations 

consisting of 12 split side platforms, and two (2) intermodal centers.”9 The stations include 

“pedestrian ramp improvements adjacent to proposed BRT stations to meet current Americans 

with Disabilities Act (ADA) standards.” 10 

3.3 Vehicles 

According to the 2014 Findings of No Significant Impact (FONSI),11 the vehicles will have the 

following characteristics: 

The Project vehicles will be articulated buses (i.e., two rigid buses linked together by a 

pivoting joint in the middle) capable of holding 200 persons each. Since most stations 

are planned as center platforms, vehicles will provide two‐sided boarding, with left‐side 

and right‐side doors. Vehicles will be either hybrid‐electric or clean‐diesel powered; the 

                                                       

8 U.S. Department of Transportation Federal Transit Administration. (2015, March 27). Provo‐Orem Bus Rapid Transit Project. Retrieved from http://www.rideuta.com/uploads/ProvoOremBRTFONSI32715Finalwocomments.pdf 9 U.S. Department of Transportation Federal Transit Administration. (2015, March 27). Provo‐Orem Bus Rapid Transit Project. Retrieved from http://www.rideuta.com/uploads/ProvoOremBRTFONSI32715Finalwocomments.pdf 10 U.S. Department  of  Transportation  Federal  Transit Administration.  (2015, March  27).  Provo‐Orem  Bus  Rapid Transit  Project.  Retrieved  from http://www.rideuta.com/uploads/ProvoOremBRTFONSI32715Finalwocomments.pdf 11 U.S. Department  of  Transportation  Federal  Transit Administration.  (2015, March  27).  Provo‐Orem  Bus  Rapid Transit  Project.  Retrieved  from http://www.rideuta.com/uploads/ProvoOremBRTFONSI32715Finalwocomments.pdf 

Page 22: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     22 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

type of vehicle will be determined during final design. Twenty‐five vehicles will be 

needed to meet the frequency and length of the route, plus the spare ratio. 

Two hundred persons is a very large number of passengers. Articulated buses can typically hold 

twice as many persons as a regular bus. The New Flyer used for the EmX in Eugene holds about 

90 passengers, and the Iris Civicbus used for the Las Vegas Max holds about 120 passengers. 

3.4 Fare Collection 

According to the 2014 FONSI,12 the project will use off‐board fare collection (using ticket 

vending machines) for faster boarding. The Utah Transit Authority (UTA) already uses ticket 

vending machines for TRAX light rail and FrontRunner commuter rail systems; presumably the 

same software and hardware will be used. Electronic fare payment using ‘tap on/tap’ off cards 

is also already in use by UTA, using magnetically‐stripped cards. While distance‐based fares 

have been considered, there are no plans for them at this time.  

3.5 Intelligent Transportation Systems 

The system will use transit signal priority (TSP) at most signalized intersections; it will be a 15‐

second early/extend TSP.13  Figure 3‐114shows the intersection locations proposed to have 

transit signal priority. 

                                                       

12 U.S. Department of Transportation, Federal Transit Administration. (2015, March 27). Provo‐Orem Bus Rapid Transit Project. Retrieved from http://www.rideuta.com/uploads/ProvoOremBRTFONSI32715Finalwocomments.pdf 13 U.S. Department of Transportation, Federal Transit Administration. (2015, March 27). Provo‐Orem Bus Rapid Transit Project. Retrieved from http://www.rideuta.com/uploads/ProvoOremBRTFONSI32715Finalwocomments.pdf 14 Adapted from Utah Transit Authority. (2014, December). Provo‐Orem Bus Rapid Transit Environmental Assessment: Executive Summary. Retrieved from http://www.rideuta.com/uploads/05_Provo_Orem_BRT_EA_Dec2014_ExecSummary.pdf 

Page 23: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     23 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 3‐1: Location of Transit Signal Priority Improvements 

 

 

   

Page 24: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     24 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

3.6 Service and Operations Plans 

Modern articulated buses will operate at five‐minute headways during peak travel time.15 

According the 2015 FONSI,16 peak periods are defined as the periods from 6:30 a.m. to 10:00 

a.m. and from 3:30 p.m. to 6:00 p.m. Monday through Friday. The BRT system will operate 

under the following plan: 

Twelve buses per hour run in each direction with 5‐minute headways (6:30 a.m. to 10:00 a.m. and 3:30 p.m. to 6:00 p.m.). 

Six buses per hour run in each direction with 10‐minute headways during mid‐day (10:00 p.m. to 3:30 p.m.). 

Six buses per hour run in each direction with 10‐minute headways during early evening (6:30 p.m. to 8:00 p.m.). 

Four buses per hour run in each direction with 15‐minute headways during early morning (4:30 a.m. to 6:30 a.m.) and late evening (8:00 p.m. to 11:00 p.m.). 

Two buses per hour run in each direction with 30‐minute headways during late night (11:00 p.m. to 2:00 a.m.).  

An existing maintenance depot located near the Orem Intermodal center will be used as a 

maintenance center. According the 2015 FONSI: 17  

In conjunction with the Project, but independent of the BRT lane and station 

construction, UTA is expanding the existing Timpanogos Maintenance Facility located on 

Geneva Road in Orem. The expansion of the Timpanogos facility will accommodate 25 

additional 60‐foot articulated buses needed for the Project. 

3.7 Roadway Improvements 

The roadway elements of the project include adding a lane on University Parkway from 800 

East to University Avenue, replacing the University Parkway Bridge over the Provo River, and 

making intersection improvements at 

University Parkway at 400 West, 

University Parkway at Main Street, 

                                                       

15 Utah Transit Authority. (n.d.). Provo‐Orem Transportation Improvement Project. Retrieved May 17, 2017, from https://i4.rideuta.com/mc/?page=Projects‐Provo‐Orem‐Transportation‐Improvement‐Project 16U.S. Department of Transportation Federal Transit Administration. (2015, March 27). Provo‐Orem Bus Rapid Transit Project. Retrieved from http://www.rideuta.com/uploads/ProvoOremBRTFONSI32715Finalwocomments.pdf 17 U.S. Department of Transportation Federal Transit Administration. (2015, March 27). Provo‐Orem Bus Rapid Transit Project. Retrieved from http://www.rideuta.com/uploads/ProvoOremBRTFONSI32715Finalwocomments.pdf 

Page 25: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     25 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

University Parkway at 200 East, 

University Parkway at 800 East, 

University Parkway at 2230 North,  

University Parkway at Freedom Boulevard, and 

University Avenue at 300 South. 18 

3.8 Active Transportation Improvements 

New and improved bicycle and pedestrian facilities through the corridor include: 

New and/or wider sidewalks in many areas where sidewalks were narrow in width or in 

disrepair; 

Upgraded pedestrian ramps in locations where the current ramps do not meet the most 

recent standards; 

Wider pedestrian ramps at intersections along the College Connector Trail; 

A bike lane in each direction along University Avenue from 400 South to 700 North 

A safer gutter adjacent to the bike lanes along 700 North in Provo; 

A median curb along 700 North directing pedestrians and bicyclists to cross only in 

designated areas; 

A crossing in Provo at 200 East that directs bicyclists into their own lane across 700 

North; 

Improvements to widen existing sidewalks along 900 East in Provo to 10‐foot‐wide 

multi‐use paths; and 

Increased width and height for the Provo River Trail where it crosses under University 

Parkway. 19

 

                                                       

18 Utah Transit Authority. (n.d.). Provo‐Orem Transportation Improvement Project. Retrieved May 17, 2017, from https://i4.rideuta.com/mc/?page=Projects‐Provo‐Orem‐Transportation‐Improvement‐Project 19 Utah Transit Authority. (n.d.). Provo‐Orem Transportation Improvement Project. Retrieved May 17, 2017, from https://i4.rideuta.com/mc/?page=Projects‐Provo‐Orem‐Transportation‐Improvement‐Project 

Page 26: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     26 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

4 System Costs This section covers project cost and funding of the Provo‐Orem BRT.  

4.1 Project Costs 

The 2011 Environment Assessment capital costs for the project in 2013 dollars amounts to 

$158.95 million.20 Figure 4‐1 shows the project elements by cost category. Figure 4‐2 provides a 

breakdown of construction and non‐construction expenses. 

Figure 4‐1: 2011 EA System Costs by Transit Element 

 

                                                       

20 Federal Transit Admininistration, Region VIII. (2011). Environmental Assessment, Provo‐Orem Rapid Transit Project, Utah County, Utah. Salt Lake City, Utah: Utah Transit Authority. 

Page 27: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     27 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 4‐2: 2011 EA System Costs by Category 

 

4.2 Project Funding 

The Provo‐Orem BRT project is part of a larger project called Provo‐Orem TRIP. TRIP includes 

related roadway and intersection improvements. These costs were not included in the FTA 

grant. The TRIP project is funded from a variety of local, regional, state, and federal sources. 

This includes $3 million of local sales tax, $7 million in donated leases of right of way in Provo 

and Orem, $40 million state funding of UDOT improvements (on University Parkway), a $65 

million local sales tax revenue bond, and $75 million from a federal transit grant. The total 

project cost for TRIP is $190 million.21 The $40 million state funding UDOT improvements is part 

of the project but not part of the FTA grant.22   

 

                                                       

21 Brown, K. (2016, March 4). What to Expect: The Provo‐Orem Transportation Improvement Project. [Blog post]. Retrieved May 17, 2017, from http://www.thechamber.org/blog/utah‐valley‐chamber‐221/post/what‐to‐expect‐the‐provo‐orem‐transportation‐improvement‐project‐2255 22 Federal Transit Administration. (n.d.). UT Provo‐Orem BRT Profile FY16. Retrieved May 17, 2017, from https://www.transit.dot.gov/sites/fta.dot.gov/files/docs/UT__Provo‐Orem_BRT_Profile_FY16.pdf 

FTA SCC 

NUMBERDescription Dollars

10 Guideway and track elements 30,762,000$                 

20 Statons, stops, terminals, intermodal centers 14,353,000$                 

30 Support facilities: yards, shops, buildings 1,996,000$                   

40 Site work and special Conditions 24,410,000$                 

50 Systems 10,910,000$                 

82,431,000$                 

60 Rights‐of‐way, land, existing improvements 3,797,000$                   

70 Vehicles 33,262,000$                 

80 Professional Services 18,532,000$                 

90 Unallocated Contingency 6,751,000$                   

100 Finance Changes 14,177,000$                 

158,950,000$              

Construction Subtotal

Total

Page 28: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     28 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

5 Planning, Design & Implementation This section covers the planning, design, and the beginning of the construction of the Provo‐

Orem BRT. 

5.1 Institutional Context 

The Provo‐OREM BRT is part of a larger transportation improvement project known as the 

Provo‐Orem Transportation Improvement Project (TRIP), which is a coordinated effort by 

UDOT, UTA, Utah County, Mountainland Association of Governments (MAG), Provo City, and 

Orem City to make improvements in the corridor. The project is located in Provo and Orem 

Cities, which are part of the MAG Metropolitan Planning Organization. UTA is the transit 

authority for the area. University Parkway is a state highway (SR 265). 

5.2 Project Development History 

The first published planning for a BRT in Utah County, the Inter‐Regional Corridor Alternatives 

Analysis23 completed in 1999,24 suggested a BRT connecting the Provo and Orem FrontRunner 

stations. The consulting firm Carter‐Burgess completed the Provo‐Orem Rapid Transit Feasibility 

Study in 2005, and recommended an alignment along University Parkway and University 

Avenue.25 In November of 2006, Utah County passed a ballot initiative to fund transportation.26 

A BRT on University Avenue and University Parkway alignment was included in the 2007 

regional transportation plan for MAG.27 Work on an Environmental Assessment began in 2007 

and was completed in 2011.28 An Alternatives Analysis (AA) was completed as part of the 

Environmental Assessment (EA) for the project. The Locally Preferred Alternative (LPA) from the 

EA differed from the earlier MAG alignment; in the latter, the BRT wrapped around the eastern 

edge of the BYU campus, along University Parkway, 900 East, and 800 North. Figure 5‐1 

compares the two.  

                                                       

23 FrontRunner Commuter Rail: The Early Studies. (2006, June 13). Retrieved May 17, 2017, from http://utahrails.net/uta/uta‐frontrunner‐studies.php 24 Jackson, A. (n.d.). Utah.gov. Retrieved May 17, 2017, from https://www.utah.gov/pmn/files/145987.pdf 25 Utah Transit Authority. (2011, April 12). Provo‐Orem Bus Rapid Transit Environmental Assessment‐ Chapter 1. Retrieved from http://www.rideuta.com/uploads/06_Provo‐Orem_BRT_EA_April2011_Ch1_PN.pdf 26 2016 Transit Ballot Measures. (n.d.). Retrieved May 17, 2017, from http://www.cfte.org/elections/639/utah‐county 27 Utah Transit Authority. (2011, April 12). Provo‐Orem Bus Rapid Transit Environmental Assessment‐ Chapter 1. Retrieved from http://www.rideuta.com/uploads/06_Provo‐Orem_BRT_EA_April2011_Ch1_PN.pdf 28 Curtis, J. (2015, May 4). The Bus Rapid Transit Story. Retrieved May 17, 2017, from http://provomayor.com/2015/05/04/the‐bus‐rapid‐transit‐story/ 

Page 29: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     29 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 5‐1: 2007 MAG Alignment and 2015 EA Locally Preferred Alternative 

 

In 2011, the LPA was included in the MAG 2040 Metropolitan Transportation Plan. In 2011 the 

project received a FONSI from Federal Highway Administration (FHWA), making the project fully 

eligible for Federal funding. Project Development for a Smart Starts grant began in April 2013,29 

and the project was rated medium‐high by the FTA in 2014. The same year, the FTA asked UTA 

to prepare another EA in response to changes in project description.30 Utah County funded the 

EA and a 30 percent design plan about that time. In 2015, the project again received a medium‐

high rating for small starts. It was recommended for $71 million of funding in 2015.31 The 

project received an additional FONSI on March 27, 2015.32 Full funding was approved by the 

                                                       

29 Federal Transit Administration. (n.d.). UT Provo‐Orem BRT Profile FY17. Retrieved May 17, 2017, from https://www.transit.dot.gov/sites/fta.dot.gov/files/docs/UT__Provo‐Orem_BRT_Profile_FY17_0.pdf 30 Pugmire, G. (2014, May 20). Provo Council hears timeline report on BRT. The Daily Herald. Retrieved May 17, 2017, from http://www.heraldextra.com/news/local/central/provo/provo‐council‐hears‐timeline‐report‐on‐brt/article_ef68cb55‐ba74‐5f27‐9b5f‐0bace00fe2a5.html 31 Federal Transit Administration. (n.d.). Proposed FY 2016 Funding for FTA Capital Investment Grant Program. Retrieved May 17, 2017, from http://www.apta.com/gap/legupdatealert/2015/Documents/New%20Starts%20list_FY16‐BudgetHighlights_USDOT.pdf 32 Federal Transit Administration. (2017, April 7). Environmental Decision Document. Retrieved May 17, 2017, from https://www.transit.dot.gov/regulations‐and‐guidance/environmental‐programs/environmental‐decision‐documents 

Page 30: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     30 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

UTA board in July 2016,33 and in December of that year, the U.S. Department of Transportation 

awarded the project a $75 million Small Starts grant.34  

5.3 Project Design & Implementation 

Initial design work for cost estimation was provided in 2013.35 A proposed preliminary design 

map book was included as an appendix to the LPA in the 2014 EA.36 A Request for Proposals 

(RFP) for design services was issued in January 2015.37 Figure 5‐2 shows that timeline. 

Figure 5‐2: January 2015 Project Timeline 

 

The current timeline is shown in Figure 5‐3; it shows final design being complete as of summer 

2016, with the start of operations planned for early 2019.38  

Figure 5‐3: The November 2016 Project Timeline 

                                                       

33 Lee, J. (2016, July 16). UTA approves funding for Provo‐Orem bus rapid transit system. KSL. Retrieved May 17, 2017, from https://www.ksl.com/?sid=40671034&nid=148 34Associated Press. (2016, December 20). $75M DOT grant to Utah Transit for new Provo‐Orem BRT line. Salt Lake Tribune. Retrieved May 17, 2017, from http://www.sltrib.com/home/4735641‐155/75m‐dot‐grant‐to‐utah‐transit 35Eliot, S. (2013, June 6). Proposed Utah county Transportation Taxes Project Selection Process. Retrieved May 17, 2017, from https://www.mountainland.org/img/minutes/Regional_Planning/2013/2013_06_06/Agenda%20Staff%20Reports.pdf 36 Federal Transit Administration & Utah Transit Authority. (2011, April 12). Provo‐Orem Bus Rapid Transit: Environmental Assessment‐ Appendix A Proposed Preliminary Design Map Book. Retrieved May 17, 2017, from http://www.rideuta.com/uploads/11_Provo_Orem_BRT_EA_Dec2014_AppdxA_Proposed_Design.pdf 37 Utah Legal Notices. (n.d.). Retrieved May 17, 2017, from http://www.utahlegals.com/notice.php?id=238305 38 Utah Transit Authority. (n.d.). Provo‐Orem Transportation Improvement Project: Project Overview. Retrieved May 17, 2017, from http://www.rideuta.com/About‐UTA/Active‐Projects/Provo‐Orem‐Transportation‐Improvement‐Project/Project‐Overview 

Page 31: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     31 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

 

5.4 Station & Guideway Planning 

In the LRTP, the project was envisioned as connecting two FrontRunner Stations, two 

universities (UVU and BYU), and two malls (University Mall & Provo Town Center Mall). The 

location of the two intermodal centers were anchored by the necessary proximity to 

FrontRunner platforms. However, the number, location, and type of the platforms (center‐

median vs side) have changed over time. Changes to the stations and guideway over the length 

of project development are shown in the following series of maps. An explanation of the 

changes follows the maps.  

The map for the 2010 UTA Project Info Sheet is shown in Figure 5‐4 

The map for the 2011 EA LPA is shown in Figure 5‐5 

The map for the 2011 MAG 2040 Project Map is shown in Figure 5‐6 

The map for the 2013 Project Info Sheet  is shown in Figure 5‐7 

The map for the 2014 EA LPA  is shown in Figure 5‐8 

The map for the 2016 Project Map is shown in Figure 5‐9 

Page 32: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     32 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 5‐4: 2010 UTA Project Info Sheet 

 

   

Page 33: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     33 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 5‐5: 2011 EA Locally Preferred Alternative 

 

   

Page 34: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     34 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 5‐6: 2011 MAG 2040 Project Map 

 

 

   

Page 35: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     35 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 5‐7: 2013 Project Info Sheet 

 

   

Page 36: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     36 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 5‐8: 2014 EA Locally Preferred Alternative39 

 

                                                       

39 Adapted from Utah Transit Authority. (2011, April 12). Provo‐Orem Bus Rapid Transit Environmental Assessment: Executive Summary. Retrieved from http://www.rideuta.com/uploads/05_Provo_Orem_BRT_EA_Dec2014_ExecSummary.pdf 

Page 37: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     37 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 5‐9: December 2016 Project Map40 

 

   

                                                       

40 Utah Transit Authority. (n.d.). Provo‐Orem Transportation Improvement Project: Project Overview. Retrieved May 17, 2017, from http://www.rideuta.com/About‐UTA/Active‐Projects/Provo‐Orem‐Transportation‐Improvement‐Project/Project‐Overview 

Page 38: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     38 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

5.4.1 StationChangesOverTime

This section details changes in the number, location, and type of stations along the alignment 

over the course of project development. Figure 5‐4: 2010 UTA Project Info Sheet depicts two 

intermodal stations, three stations near UVU, two on University Parkway (Orem 400 West and 

Main Street), one at University Mall, one at University Parkway, one north of BYU, one east of 

BYU, two South of BYU, four on University Avenue, one at Provo Town Center Mall, one north 

of the East Bay Technology Park, and one south of it. Figure 5‐5: 2011 EA Locally Preferred 

Alternative omits one station south of BYU and moves one of the stations on University 

Boulevard from Provo 300 South (US‐89) to 400 South. Figure 5‐6: 2011 MAG 2040 Project Map 

shows no stations. Figure 5‐7: 2013 Project Info Sheet omits the loop north of UVU and its 

stations. Figure 5‐8: 2014 EA Locally Preferred Alternative is a map that denotes which stations 

are proposed as side stations and which are proposed as center stations. The station east of 

BYU has been “split” into two stations: One northeast of BYU, closer to the Missionary Training 

Center, and one further south at Provo 900 East. Figure 5‐9: December 2016 Project Map 

shows no changes from the prior map.  

5.4.2 GuidewayChangesOverTime

A significant change was the removal of the HOT interchange over I‐15. It appeared in Figure 

5‐4: 2010 UTA Project Info Sheet but it was delayed until “Phase 2” in Figure 5‐5: 2011 EA 

Locally Preferred Alternative and dropped thereafter. The location of exclusive lanes also 

experienced substantial changes. In Figure 5‐6: 2011 MAG 2040 Project Map 900 East in Provo 

had an exclusive lane, while there was none near the SouthGate Center.  Figure 5‐8: 2014 EA 

Locally Preferred Alternative also shifts part of the alignment from University Parkway to Orem 

1200 South. Figure 5‐6: 2011 MAG 2040 Project Map omits the loop at the southern part. The 

2013 Project info sheet (Figure 5‐7: 2013 Project Info Sheet) has only one change from the 

2011 LPA: Orem 400 West from Orem 1200 South to University Parkway had an exclusive lane. 

In Figure 5‐8: 2014 EA Locally Preferred Alternative, the alignment appears slightly altered. A 

new road permits it to be shortened near the Orem FrontRunner station, and is “indented” 

near BYU so that it turns north along Provo 700 East and then east at Provo 900 North, rather 

than continuing on Provo 700 North to Provo 900 East. The 900 North segment is designated as 

exclusive lanes. Provo 1860 East (near Novell) is also designated as having an exclusive lane. 

Figure 5‐9: December 2016 Project Maps shows no changes. Over the course of project 

development, the amount of exclusive guideway on University Avenue increased, while the 

amount adjacent to BYU dropped by over half. Given that the BYU segment is in the middle of 

the alignment, this reduction will likely have a negative impact on travel time reliability with a 

corresponding effect on ridership.   

Page 39: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     39 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

5.4.3 ChangesduetoCampusUnificationPlan

In 2013, BYU closed a portion of East Campus Drive as part of the Campus Unification Plan, 

relocating a UTA station near the Wilkinson Student Center to a more remote location on the 

edge of campus at about Provo 800 North & 900 East. This resulted in a relocation of the 

planned BRT station, as well as changes in the location of the median guideway. The change 

faced substantial neighborhood opposition. As a result, the portion of dedicated running way 

along BYU was reduced.41 In February 2014, the Provo City Council voted against the LPA 

(“Option 4”) in favor of an alignment following the 2007 MAG University Parkway/University 

Avenue (“Option 0”).42 This decision was then provisionally reversed in March 2014, pending 

additional information. A decision was made to hire an outside expert43 to perform an 

independent analysis of the travel demand modeling of the alternatives.44 While the analysis 

turned up some data errors in student and employment numbers as well as assumptions about 

the subsidy BYU would provide, the final projections differed by about 10%, and the LPA was 

recommended as the best option.  

 

                                                       

41 FAQ ‐ Provo‐ Orem Bus Rapid Transit Project. (n.d.). Retrieved May 17, 2017, from http://www.provo.org/Home/ShowDocument?id=3001 42 The Bus Rapid Transit Story. (May 4, 2015). Retrieved May 17, 2017, from  

http://provomayor.com/2015/05/04/the‐bus‐rapid‐transit‐story/ 43 Provo City to Hire Third Party Researcher. (n.d.)Retrieved May 17, 2017, from http://provobuzz.com/provo‐city‐hire‐third‐party‐research‐brt/ 44 Rose, A. (2014, April 29). Independent report backs 900 East BRT route. Utah Valley 360. Retrieved May 17, 2017, from http://utahvalley360.com/2014/04/29/independent‐report‐backs‐900‐east‐brt‐route/ 

Page 40: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     40 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

6 Research Approach This section details the characteristic of the quasi‐experimental research design, the use of the 

Provo‐Orem TRIP improvements as a “natural experiment,” and the use of an interrupted time 

series for some variables. Null hypothesis testing is discussed and the conceptual framework is 

explained. Finally, the data collection plan is detailed along with the geographic extent of the 

analyses performed.  

6.1 Quasi‐Experimental Research Design 

In order to rigorously compare before and after conditions, this study uses a quasi‐

experimental design with non‐equivalent control groups. A quasi‐experimental research design 

is an experimental research design that recognizes the impossibility of exactly replicating the 

same experiment, but otherwise maintains all possible experimental controls. The control 

group is considered non‐equivalent because of the lack of random assignment. Without 

random assignment, quasi‐experiments rely on statistical control variables and sample 

matching to show that alternative explanations are implausible. A causal inference from any 

quasi‐experiment must meet the basic requirements for all causal relationships: that cause 

precedes effect; that cause co‐varies with effect; and that alternative explanations for the 

causal relationships are implausible.45  

6.1.1 ANaturalExperiment

Experimental research design requires a pre‐test, a “treatment,” a post‐test, and a control 

group. A natural experiment takes advantage of conditions where a treatment is applied to a 

subset of a larger population. That subset is considered the treatment group, and the large 

population becomes the control group. The control group is non‐equivalent because of the lack 

of random assignment. In this case, the treatment consists of the improvements included in the 

TRIP.  

6.1.2 InterruptedTimeSeries

Performing quasi‐experimental analysis requires collecting data before and after the treatment. 

Some variable data (e.g. traffic counts, transit ridership) for multiple years before the study 

(2010—2015) were collected as part of the initial conditions report. Collecting this multiple‐

year time series makes it possible to project current trends into the future. Following the 

                                                       

45 Shadish, W. R., Cook, T. D., & Campbell, D. T. (2002). Experimental and quasi‐experimental designs for 

generalized causal inference. Houghton, Mifflin and Company. 

Page 41: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     41 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

construction period and the first year of operations, more data will be collected, extending the 

time series. It will then be possible to compare the projected trends from the Initial Conditions 

Report to actual values. 

6.2 Null Hypothesis Testing 

Confirmation bias is the tendency to favor information or evidence that supports a prior 

hypothesis.46 Scientific research follows a series of rigorous protocols to avoid this, the most 

common of which is the null hypothesis testing. The null hypothesis is an explicit declaration of 

the expected relationship between cause and effect in the phenomena of interest. The formal 

phrasing is that “there is no significant relationship between the two variables”. For this report, 

the null hypothesis is that the project improvements will have no significant effect on any of the 

outcome variables. Hypothetically, the level of development, parking occupancy, crash rates, 

and total emissions should remain constant, while traffic growth and transit use should 

continue to change in accordance with their previous trends.   

6.3 Conceptual Framework 

Conceptual framework is a term used to explicitly describe how different elements within a 

system under study interact with one another. Figure 6‐1 shows the conceptual framework of 

this study. Red (closed) arrows indicate a negative relationship between the elements; more of 

one means less of the other, and vice versa. Black (open) arrows indicate a positive 

relationship; more of one means more of the other. Green cylinders contain study variable 

quantities. Blue ovals indicate unmeasured conceptual quantities. Green circles indicate ratios, 

and yellow boxes indicate tables of rates. 

Transportation demand on the alignment consists of three elements: background or through 

travel, travel generated by other land uses along the corridor, and travel generated by the 

universities. University‐induced travel demand is assumed to be a function of university faculty, 

staff, and student enrollment. Total university parking occupancy is assumed to be a function of 

parking supply and parking demand. Total parking supply is affected by University policies, 

including the allocation for different classes of parking. Total parking demand is affected by gas 

prices, the price of parking, and transit ridership. The location of parking lots in relation to 

lecture buildings is expected to significantly influence location‐specific demand for parking. If 

parking is not available near campus, other alternatives become more attractive.  

                                                       

46 Nickerson, R. S. (1998). Confirmation bias: A ubiquitous phenomenon in many guises. Review of general 

psychology, 2(2), 175. 

Page 42: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     42 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

The amount of traffic congestion is a function of the difference between traffic on the 

alignment (measured as AADT) and capacity on the alignment. The level of traffic congestion is 

presumed to cause divergence to other times, modes, and routes. The dedicated guideway on 

the BRT alignment is conceptualized to encourage a mode shift from automobile to transit, thus 

reducing automobile traffic on the alignment, and thus lowering congestion on the BRT 

alignment. AADT determines VMT, and thus vehicle emissions.  

   

Page 43: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     43 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 6‐1: Conceptual Framework 

 

Page 44: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     44 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

6.4 Data Collection Plan 

Data collection about the initial conditions took place in 2015 and 2016. After construction 

finishes, and a year of operations occurs, a second round of data collection will occur and a 

second report will be released. A third round of data collection will occur the following year, 

and a fourth round the year after that. Figure 6‐2 shows the current anticipated timeline for the 

start of system operations. 

Figure 6‐2: The November 2016 Project Timeline 

 

6.5 Study Bounds – Geographic Extents 

Different analyses make use of different geographic extents. Traffic counts, VMT, and vehicle 

emissions were analyzed for the alignment and the identified diversion corridors. Crash rates 

were analyzed for the alignment itself. For land development and trip generation, a ¼‐mile 

buffer around the alignment was used based on 2010 Decennial Census Tracts/MAG 2010 

Traffic Analysis Zones. For parking supply, all dedicated parking for the two universities was 

considered. The following subsections contain additional information about the diversion 

corridors, corridor changes, and the buffered alignment.  

6.5.1 DiversionCorridors

On facilities near capacity, or at capacity during peak times, a phenomenon known as diversion 

occurs. This is where drivers choose to drive a longer amount of time along indirect routes on 

less congested roads. Diversion represents a “latent demand” for travel capacity on one street 

that is being met by capacity on parallel streets. It has been speculated that BRT operations 

may impair traffic flow, thus increasing congestion and causing drivers to divert to other roads. 

There is already substantial diversion from the most direct routes, according to local planners. 

For example, while the University Parkway exit is the most direct route to University Mall and 

BYU, using it still requires miles of travel along surface streets to reach BYU. Consequently, 

travelers are already diverting to alternate routes miles away, making use of all alternative 

roads leading eastbound from I‐15 interchanges.  

Page 45: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     45 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

To determine if the BRT is causing additional diversion, it is necessary to measure the traffic 

volumes on potential diversion corridors. The possibility of diversion was investigated by 

quantifying changes in traffic volumes on alternate routes near the BRT corridor, including I‐15. 

These routes were identified in consultation with local planners in Provo and Orem.  

In addition to diversion corridors, screen lines and cordon lines were used to capture changes in 

automobile volumes. A screen line cuts across the whole of an area and sums the total volume 

of all roads along that line. A cordon line is like a screen line, except it wraps around all sides of 

a district. In this study, BYU has a cordon line. The diversion corridors, screen lines, and BYU 

cordon are shown in Figure 6‐3. 

The east‐west diversion corridors are: 

Orem 800 North,  

Orem Center Street, 

Orem 800 South, 

Orem 1200 South, 

University Parkway, 

Provo 2230 North, 

Bulldog Boulevard/Provo 1230 North, 

Provo 820/800 North, 

Provo Center Street, and 

Provo 300 South. 

The north‐south diversion corridors are: 

Geneva Road, 

I‐15, 

State Street/Highway 89, 

Orem 800 East, 

Provo 500 West, 

Provo 200 West/Freedom Boulevard, 

University Avenue/Highway 189, and 

Provo 900 East. 

Page 46: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     46 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Orem 800 South was included due to the planned interchange.47 Highway 189 was also 

included as a diversion corridor to guard against the possibility of traffic diverting from 

University Avenue. Provo Center Street has also been included, as it provides another 

alternative path. However, substantial diversion to Provo Center Street is unlikely, due to the 

traffic calming techniques (on‐street parking, narrow lanes, and lowered speeds) applied in the 

Provo CBD.  

                                                       

47 Wasatch Front Regional Council. (2013). Utah’s Unified Transportation Plan 2011‐2040. Retrieved from: http://www.wfrc.org/new_wfrc/UnifiedPlan/Unified%20Plan%20Booklet%20Web%20Version%20Final%206%20Aug.%202013.pdf  

Page 47: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     47 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 6‐3: Map of Diversion Corridors and Screen Lines 

 

Page 48: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     48 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

6.5.2 FutureAlignment

There is a possibility that the alignment of the BRT may change during the evaluation period. A 

new high occupancy vehicle (HOV) or high occupancy toll (HOT) interchange at I‐15 and Orem 

820 North may be constructed.48  This is shown in Figure 6‐4. 

Figure 6‐4: Map of HOV Exchange at 800 South in Orem 

 

                                                       

48 Utah Transit Authority, & Mountainland Association of Governments. (2010, May 31). Provo‐Orem Rapid Transit Environmental Assessment: Project at a Glance. Retrieved May 17, 2017, from https://www.mountainland.org/img/minutes/Regional_Planning/2010/2010_09_02/BRT%20Project%20Info%20Sheet.pdf 

Page 49: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     49 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

The HOV/HOT interchange were under study in April 2014.49 They were included in the 2011 

EA, and they show up on MAG’s TranPlan40 map50 as “Unfunded” in Phase 1 (2015—2024), but 

only corridor preservation is included in the 2017‐2022 Transportation Improvement Program 

for the MAG 2040 plan.51 A new HOV/HOT interchange would permit vehicles to access UVU 

more directly from I‐15, removing some UVU‐bound traffic from University Boulevard. It would 

also improve the operations of the Provo‐Orem BRT by avoiding several congested 

intersections, thus improving travel time and route attractiveness.  

6.5.3 BufferedAlignment

For land development and trip generation, a ¼‐mile buffer around the alignment was used 

based on 2010 Decennial Census Block Groups. Census geography was used for the buffer to 

provide a control total for changes in population and employment. Block Groups were the 

finest scale of geography for which the five‐year American Community Survey Data was 

available.52 The Block Groups selected include those adjacent to both the initial year of 

alignment and final year of alignment. In most cases, the 2010 block group polygons are the 

same as MAG traffic analysis zone geometry. The buffered alignment used is shown in Figure 

6‐5. 

                                                       

49 Mountainland Association of Governments. (n.d.). Transportation studies Recommended. Retrieved May 17, 2017, from https://www.mountainland.org/img/minutes/Regional_Planning/2014/2014_04_03/Transportation%20Studies%20Recomended.pdf 50 Mountainland Association of Governments. (2016, August). TransPlan40. Retrieved from http://mag‐gis.maps.arcgis.com/apps/MapSeries/index.html?appid=b7bc635f4a6c445886b29e0ce25a19ac 51 Mountainland Association of Governments. (2016, August 4). Mountainland MPO TIP 2017‐22 Program. Retrieved May 17, 2017, from http://mountainland.org/img/transportation/TIP/2017%20TIP/2017%20TIP%20Final.pdf 52 US Census Bureau. (2016, October 17). Selected Geographic Areas Published in the 2015 American Community Survey 1‐year and 5‐year estimates. Retrieved May 17, 2017, from https://www.census.gov/programs‐surveys/acs/geography‐acs/areas‐published.html 

Page 50: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     50 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 6‐5: Map of Study Area Development Boundaries 

 

Page 51: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     51 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Using a buffer to select polygons automatically was problematic as it consistently resulted in 

inappropriate selections. Using the “select by intersect” option allowed for selected polygons 

with only a small portion adjacent to the alignment, while using “select by centroid” excluded 

large polygons adjacent to the alignment. The final selection was created by using a ¼‐mile 

buffer to select 2010 census block group polygons, and then excluded a limited number of 

insufficiently related polygons. Blocks excluded as insufficiently related were those with the 

following GEOIDs: 490490014012, 490490022011, 490490028021, and 490490022073. This 

selection was used to select parcels for the land development and trip generation analyses.  

Controlling for the effects of new development in other locations (such as the diversion 

corridors) would require tracking land use changes for a much larger area. Controlling for the 

complex interactions between trip generation and roadway volumes over a larger area is a task 

more suitable for a travel demand model. The data acquisition and processing costs of doing so 

were also deemed prohibitive. Within the buffered alignment alone, there were about 14,600 

parcels that were classified by land use.  

6.6 Data Source Limitations 

The analyses in this report include data for the five years prior to the beginning of construction. 

Utility work for construction on the Provo‐Orem BRT began in late 2015 and early 2016. In 

some cases, data for all of 2015 was not yet available, therefore data were collected for as long 

as was available. In other cases, due to limited data availability, data were collected for 2010—

2014. Specifics on data source limitations are included in their respective sections in the 

Findings section. This report presents the data collected to date since evaluation activities 

commenced on May 30, 2015. 

6.7 Timing of Traffic and Ridership Changes 

Previous research suggests that drivers rapidly adapt to new roadway capacity, altering routes 

and travel patterns in a matter of weeks.53 Transit riders tend to be less adaptable. Many riders 

are familiar with only a single route rather than the entire transit system. Consequently, the 

short‐run elasticities of change in ridership in response to service are much less than the long‐

run elasticities54 ‐ it takes longer for riders to discover a new service. The amount and quality of 

public information provided is critical to facilitating service uptake for choice riders. Travelers 

                                                       

53 Dowling, R. G., & Colman, S. B. (1995). Effects of increased highway capacity: results of household travel behavior survey. Transportation Research Record, 1493, 143-149. 54 Litman, T. (2004). Transit price elasticities and cross-elasticities. Journal of Public Transportation, 7(2), 3. 

Page 52: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     52 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

tend to switch between modes when familiar commuting patterns are disturbed, such as when 

changing place of work or place of residence55. As the Provo‐Orem BRT will serve two 

universities, there will be substantial turnover in the population of travelers. Each year there 

will be a fresh batch of students trying out different travel arrangements. 

   

                                                       

55 Frank, L., Bradley, M., Kavage, S., Chapman, J., & Lawton, T. K. (2008). Urban form, travel time, and cost relationships with tour complexity and mode choice. Transportation, 35(1), 37-54. 

Page 53: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     53 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

7 Evaluation of System Performance This section provides an evaluation of the system performance as measured by travel time, 

reliability, image and identity, safety and security, and capacity.  

7.1 Travel Times 

Scheduled travel time from the Orem Intermodal Center to the Provo Intermodal Center on 

Route 830 is 37 minutes, although Route 830 does not cover the whole alignment. Travel time 

for the No‐Action/Enhanced Bus alternative in the 2011 EA was 45 minutes,56 and 34 minutes 

for the Bus Rapid Transit. End‐to‐end travel time was forecast to be 38 minutes for the 2014 EA 

alignment.57  

7.2 Schedule Reliability 

Operating in mixed traffic, Route 830 is currently subject to traffic congestion and thus to 

congestion‐induced delays that any driver suffers from. The need to make regular stops to pick 

up and drop off passengers slows bus travel further. Without special boarding stations, busses 

typically must leave a traffic lane to pick up passengers and then suffer delays merging back 

into traffic. All of these delays are worse during the peak hour as congestion is worse, the 

number of passengers is larger, and higher traffic makes merging more difficult. The BRT can be 

expected to enjoy substantial schedule reliability over a normal bus route. UTA forecasts its 

reliability to be greater than 95 percent.58 

7.3 Identity & Image 

Utah currently operates only non‐articulated buses. The Provo‐Orem BRT will operate modern 

articulated buses59 that will make them immediately distinguishable from regular buses. UTA’s 

other Bus Rapid Transit Route is branded as “MAX” and has a special route designation (35M), 

but the agency otherwise uses standard buses. The S‐line Streetcar is branded as the “Silver 

                                                       

56 Utah Transit Authority. (2011, April 12). Provo‐Orem Bus Rapid Transit Environmental Assessment‐ Chapter 5: Comparisons of Alternatives. Retrieved May 20, 2017, from http://www.rideuta.com/uploads/10_Provo‐Orem_BRT_EA_April2011_Ch5_Alts_Comparison.pdf 57 Rahlf, R. (2015, May 31). Provo‐Orem Bus Rapid Transit system is the right investment. Deseret News. Retrieved May 20, 2017, from http://www.deseretnews.com/article/865629773/Provo‐Orem‐Bus‐Rapid‐Transit‐system‐is‐the‐right‐investment.html?pg=all 58 Utah Transit Authority. (2011, April 12). Provo‐Orem Bus Rapid Transit Environmental Assessment‐ Chapter 5: Comparisons of Alternatives. Retrieved May 20, 2017, from http://www.rideuta.com/uploads/10_Provo‐Orem_BRT_EA_April2011_Ch5_Alts_Comparison.pdf 59 Utah Transit Authority. (n.d.). Provo‐ Orem Transportation Improvement Project. Retrieved May 20, 2017, from https://i4.rideuta.com/mc/?page=Projects‐Provo‐Orem‐Transportation‐Improvement‐Project 

Page 54: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     54 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Line” and while it uses standard light rail vehicles, they have a special livery and are never 

coupled into multiple car trainsets. Intended branding and livery for the Provo‐Orem BRT have 

not yet been announced, and no vehicles have yet been purchased.  

7.4 Safety & Security  

This subsection covers the safety and security of bus rapid transit systems.  

7.4.1 Safety

Riders on mass transit vehicles are typically safer in a crash than most automobile passengers. 

The combination of professionally trained drivers and the greater mass of the vehicles means 

that collisions are both less frequent and less impactful. However, rapid transit systems without 

fully grade‐separated guideways are less safe than systems with grade‐separated guideways 

(such as underground and elevated metro systems). Rapid systems without grade separation 

make do with much cheaper “time separation” via stop‐control provided by railroad gates and 

traffic lights.  

Some of the most severe crashes for both BRT and light rail tend to occur at railroad gates, 

either when the gate malfunctions or a driver attempts to bypass the gate. This typically results 

in a high‐speed collision between the automobile and the much larger transit vehicle. Fatalities 

often result. Such crashes tend to occur early on in operations, before drivers learn to expect 

the transit vehicles.  

Stop‐controlled intersections where automobile traffic is perpendicular to the transit vehicle 

constitute the second most dangerous conflict point. Drivers running red lights or making illegal 

turns are a common cause, especially on higher speed streets. High speeds result in limited 

peripheral vision and reduce time available to react. TSP measures may worsen this effect; 

triggered priority may rearrange the signal phases of a traffic signal so that the signal acts 

contrary to driver expectations of phase length or signal sequence. Again, this problem is most 

prevalent when operations first begin. To avoid this issue, drivers should be directed to proceed 

slowly when entering a newly “green” intersection. 

The next most likely location of conflicts between transit vehicles occurs where a vehicle 

leaving an exclusive guideway merges with shared traffic. For the Provo‐Orem BRT, almost all 

transitions from exclusive to shared guideways will take place at intersections, which should 

help mitigate this issue. However, shared turn‐pockets are a common conflict location (the left 

turn lanes for center‐running BRT and/or and right turn pockets for side‐running BRT). 

 For more detail about safety and Bus Rapid Transit, consult APPENDIX A. LITERATURE REVIEW.  

Page 55: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     55 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

7.4.2 Security

The reduced number of stops along the BRT should improve the perception of safety by 

reducing likelihood of riders waiting alone at a stop.60 Most train cars, platforms, and buses 

have installed security cameras. Which stations of the Provo‐Orem BRT will have cameras has 

not been decided or announced. UTA has its own police force, the Utah Transit Authority Public 

Safety Department, and the agency has been commended for its level of commitment to 

security.61 

7.5  Capacity 

The recently purchased New Flyer Xcelsior buses may or may not be intended for the BRT.62 

Assuming an articulated bus is purchased, passenger capacity per bus can be estimated at 90 

passengers for an articulated New Flyer vehicle,63 or 108 for an Xcelsior vehicle. If the IRIS Civic 

Bus, used for the Las Vegas MAX, were purchased, each bus would have a capacity of 120 

persons. With five‐minute peak headways, this equates to 12 buses per hour per direction. 

Figure 7‐1 shows the maximum capacity such vehicles could provide. Also included are the 2011 

EA estimates of peak hour utilization.64 

Figure 7‐1: Peak Hour Transit Capacity 

 

                                                       

60 Schimek, P., Darido, G., & Schneck, D. (2005, September). Boston Silver Line Washington Street BRT Demonstration Project Evaluation. Retrieved May 20, 2017, from https://nbrti.org/media/evaluations/Boston_Silver_Line_final_report.pdf 61 Transportation Security Administration. (2013). TSA commends 16 mass transit and rail agencies for highest security levels [Press release]. Retrieved May 20, 2017, from https://www.tsa.gov/news/releases/2013/07/10/tsa‐commends‐16‐mass‐transit‐and‐rail‐agencies‐highest‐security‐levels 62 Utah Transit to add 35 more 60‐foot New Flyer Xcelsiors. (2016, December 15). Metro Magazine. Retrieved May 20, 2017, from http://www.metro‐magazine.com/bus/news/719169/utah‐transit‐to‐add‐35‐more‐60‐foot‐new‐flyer‐xcelsiors 63 Thole, C., Cain, A., & Flynn, J. (2009, April). The EmX Franklin Corridor BRT Project Evaluation. Retrieved May 20, 2017, from https://www.nbrti.org/docs/pdf/EmX_%20Evaluation_09_508.pdf 64 Utah Transit Authority. (2011, April 12). Provo‐Orem Bus Rapid Transit Environmental Assessment‐ Chapter 5: Comparisons of Alternatives. Retrieved May 20, 2017, from http://www.rideuta.com/uploads/10_Provo‐Orem_BRT_EA_April2011_Ch5_Alts_Comparison.pdf 

…per direction Total

New Flyer 90 12 1080 2160

New Flyer Xcelsior 108 12 1296 2592

Iris Civic Bus 120 12 1440 2880

UTA Forecast Bus ? 12 164‐330 328‐660

UTA Forecast BRT ? 12 720‐960 1440‐1920

Passengers per hourBuses per 

Hour, per CapacityVehicle

Page 56: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     56 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Together, this suggests that an articulated New Flyer vehicle might be able to handle peak 

loads, but with a very low margin for error (about 10 persons per bus), while an New Flyer 

Xcelsior will have a margin of error of 28 riders and be able to handle the heaviest of peak 

loads. 

 

Page 57: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     57 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

8 Assessment of System Benefits This section contains analyses of transit ridership, capital cost effectiveness, operating cost 

efficiency, transit supportive land use development, and environmental quality.  

8.1 Transit Ridership 

Total transit ridership is affected by a large number of factors. Mode choice decisions are made 

on the basis of time and the financial costs of different modes. Given that transit vehicles must 

make stops to pick up and drop off passengers, transit is often much slower than a personal 

automobile. However, it is possible to bypass congestion if transit vehicles can make use of a 

dedicated guideway.65 Better service frequency reduces the average wait time for a transit 

vehicle, bringing it closer to parity with the private automobile. Service frequency determines 

the average wait time for transit, and thus much of the overall travel time for a trip. Thus, the 

service levels can significantly affect ridership. As service provision fluctuates so does ridership.  

Figure 8‐166 shows the location and frequency of bus routes near UVU in August 2015.67 Green 

indicates 15‐minute service, Yellow 30‐minute service, Blue 60‐minute service, and Red peak‐

hour service. Figure 8‐268 shows transit routes for the study area in 2015, Figure 8‐3 shows the 

routes for 2016, and Figure 8‐4  shows transit routes around BYU. 

                                                       

65 Dittmar, H., & Poticha, S. (2004). Defining Transit Oriented Development. In Presentation for TOD Seminar, School of Architecture, The University of Texas at Austin. Spring. 66 Utah Transit Authority. (n.d.). Utah County Systems Map‐April 2016. Retrieved May 20, 2017, from https://www.rideuta.com/‐/media/Files/System‐Maps/2016/Utah‐County‐System‐Map.ashx 67 Utah Transit Authority. (n.d.). Utah County Systems Map‐April 2015. Retrieved May 20, 2017, from https://www.rideuta.com/‐/media/RideUTA/Maps/UtahcountymapApril2015.ashx 68 Utah Transit Authority. (n.d.). Utah County Systems Map‐April 2016. Retrieved May 20, 2017, from 

https://www.rideuta.com/‐/media/Files/System‐Maps/2016/Utah‐County‐System‐Map.ashx  

 

Page 58: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     58 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 8‐1: Transit Routes near UVU 

 

Page 59: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     59 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 8‐2: Transit Routes and Headway in Study Area 2015 

 

 

Page 60: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     60 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 8‐3: Transit Routes in Study Area 201669 

                                                       

69 Utah Transit Authority. (n.d.). Utah County Systems Map‐April 2016. Retrieved May 20, 2017, from https://www.rideuta.com/‐/media/Files/System‐Maps/2016/Utah‐County‐System‐Map.ashx 

Page 61: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     61 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 8‐4: Transit Routes near BYU 201570 

 

8.1.1 Methods&Data

Data for all transit routes within the study area were collected, including FrontRunner. All data 

are UTA counts. For bus ridership, data prior to 2014 are driver counts and are only available at 

the route level. Passenger counts for 2014—2015 are Automatic Passenger Counter (APC) data.  

Driver counts are available only at the route level, while APC counts are available at specific 

locations. Line‐level data for 2014—2015 are sums of boardings/alightings. FrontRunner began 

operations in Utah County in 2012. For FrontRunner, passenger counts for 2012—2015 were 

available at the station level. (Passenger counts for FrontRunner prior to December 2012 are 

only available at the system level.) 

                                                       

70 Utah Transit Authority. (n.d.). Utah County Systems Map‐April 2016. Retrieved May 20, 2017, from https://www.rideuta.com/‐/media/Files/System‐Maps/2016/Utah‐County‐System‐Map.ashx 

Page 62: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     62 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

8.1.2 Results&Discussion

Ridership analyses in this section include system level ridership for Utah County, analysis of 

FrontRunner ridership for the Provo and Orem Stations, analysis of total FrontRunner ridership, 

and analysis of Utah County bus ridership. 

8.1.2.1 SystemwideRidership

Figure 8‐5 shows data for transit ridership in Utah County for both bus and FrontRunner. (Prior 

to the advent of FrontRunner, total ridership and bus ridership were identical). The total trend 

line is the trend line for the system from 2008‐2015. Data are monthly totals, excepting UTA’s 

thrice‐yearly ‘change day’ counts, when there are two counts in a single month. 

Figure 8‐5: Transit Ridership in Utah County 

 

The trend line shows that bus ridership was in decline 2008‐2012, but trends changed in 2013 

when FrontRunner South began operations. Post initiation of FrontRunner South, Utah County 

bus ridership rose. FrontRunner South ridership over time for the two stations within the study 

area (Orem Central and Provo Central) are shown in Figure 8‐6. 

Page 63: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     63 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 8‐6: FrontRunner Ridership 2009—2015 for Orem Central and Provo Central Stations 

 

Six years of data for bus ridership in Utah County is shown in Figure 8‐7. The monthly ridership 

for each year is presented as a distinct line.  

Figure 8‐7: Utah County Bus Ridership by Month 2010‐2015 

 

Total ridership is about the same for 2010 and 2011, while 2012 ridership is lower and 2013 

ridership the lowest of all. There was an increase from May onward for 2014, while 2015 bus 

Page 64: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     64 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

ridership is nearly identical to 2014. Changes in ridership pre‐ and post‐FrontRunner South can 

be clearly seen. After the opening of FrontRunner South in 2012, UTA heavily reorganized the 

bus system, cutting half a dozen routes and combining others. Many of the routes that were cut 

were inter‐county express routes. The graph also clearly demonstrates the effect that school 

enrollment (such as at major universities) has on transit usage. Ridership drops substantially 

between May and August while schools are out of session.  

For the BRT alignment, Route 830 is most comparable. Figure 8‐8 shows the annual ridership71 

of Route 830. It shows two different data series, as UTA switched its data collection method 

from driver counts to Automatic Passenger Counters. 

Figure 8‐8: Annual and Daily Ridership for the BRT 

 

Route 830 ridership rose from 2000 to 2004, and has declined since. In 2011, when forecasts 

were made, it had remained steady at about 50,000 annual riders for several years. Post 2011, 

ridership declined until 2014 when it stabilized at a new low. Much of this change can be 

attributed to changes in service and routing.  

8.1.2.2 ChangesinTransitSupplyandRoutingoverTime

UTA makes changes to routes and route frequency 3 times a year, an event known as “Change 

Day,” and UTA uses a spreadsheet to track these changes. Change Day Inventory shows that at 

the end of 2011, extra trips to BYU were discontinued, which seems to be the cause of the drop 

in ridership between 2011 and 2012. Then, at the end of 2012, route 830 was extended to serve 

                                                       

71 For driver counts, these represent riders. For automatic passenger counters, these represent boardings. 

Page 65: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     65 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

the Orem and Provo FrontRunner stations. In 2013, route 830 was then realigned to serve a 

new bus stop, and then changed to be identical to the BRT alignment. In April 2014, it was re‐

routed to use Geneva Road, rather than passing through Wolverine Crossing (UVU student 

housing), which is about 550 feet away. All of these changes appear to have resulted in reduced 

ridership. Figure 8‐9 features a map of the April 2011 Route 830. 

Figure 8‐9: Route 830, April 2011 

 

As can be seen, the route was considerably different. It included detours to reach the 

Timpanogas Transit Center and Wyview Park. It passed by Carriage Cove Apartments, the Utah 

Valley Hospital, Provo High School, and ran along Campus Drive through BYU. 

8.1.2.3 ComparingCountsandForecasts

Page 66: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     66 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Average daily ridership for Route 830 is shown in Figure 8‐10. The “Weekday” line represents 

daily ridership on an average weekday, while the “Daily” line represents an average ridership 

across all days of the week. The data are based on driver counts, which occur once or twice a 

month. 

Figure 8‐10:  Estimated Average Daily Ridership, Driver Counts, Route 830 

 

The average weekday count is uniformly higher than the average daily count, reflecting higher 

usage on workdays than on weekends. The ratio between the two is roughly constant.   

Daily Ridership for the APCs is shown in Figure 8‐11. Unlike driver counts, the automatic counts 

are performed continuously. This makes is possible to provide monthly totals, and to provide 

totals both before and after UTA’s thrice‐annual Change Day. 

Figure 8‐11: Estimated Average Daily Ridership, APC, Route 830 

 

Page 67: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     67 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

The APC counts show a wider range of monthly variation in transit ridership than the driver 

counts. However, the average ridership for APC counts (2,470 for 2014 and 2,404 for 2015) are 

very similar to the driver count for 2014 of 2,457.  

These counts are substantially different from the forecast daily ridership for an enhanced bus 

and the BRT from the 2011 EA.72, show in Figure 8‐12. 

Figure 8‐12: Forecast Route Ridership, in riders/day 

 

The forecasted 2014 ridership of 6,800 appears high when compared to the 2014 estimates of 

actual ridership. This can be explained by a number of factors: First, the timing of projections. 

The forecast was made in 2011, which meant 2010 data would have been the most recent 

available. Second, in 2010 ridership was at what proved to be a 5‐year peak, of about 3,400 

riders. Third, the alignment used for these forecasts is not identical to route 830; it runs the 

entire BRT alignment, from Orem FrontRunner to the technology park, and includes what is 

currently route 838. Including the ridership on route 838, which represents a total daily 

ridership of about 3,500 riders. The final (and likely more significant) factor, concerns changes 

University support for transit. 

8.1.2.4 ChangesinUniversitySupportforTransit

From 200273 to 2010, BYU participated in the UTA Eco Pass and Ed Pass programs. In 2003—

2004, the passes were free to students and $60 annually for employees.74 In 2008—2009, the 

pass was available to students for $120 a semester when a regular monthly pass was $160.75 In 

2010, changes in the UTA Ed Pass program resulted in an increase in the cost per pass provided, 

and BYU ceased to subsidize the passes. BYU continued to offer passes at a 25 percent discount 

                                                       

72 Utah Transit Authority. (2011, April 12). Provo‐Orem Bus Rapid Transit Environmental Assessment‐ Chapter 5. Retrieved from http://www.rideuta.com/uploads/10_Provo‐Orem_BRT_EA_April2011_Ch5_Alts_Comparison.pdf 73 Warnock, C. (2002, March 22). BYU to join UTA's Eco Pass program. The Daily Herald. Retrieved May 20, 2017, from http://www.heraldextra.com/news/byu‐to‐join‐uta‐s‐eco‐pass‐program/article_67be06a8‐170f‐58c4‐85d6‐3d5fab8943cd.html 74 Jenkins, C. P. (2003, April 13). Student UTA stickers available April 18. BYU News. Retrieved May 20, 2017, from https://news.byu.edu/news/student‐uta‐stickers‐available‐april‐18 75 Jenkins, C. (2008, June 22). BYU continues to offer UTA Ed Pass at a bargain price. BYU News. Retrieved May 20, 2017, from https://news.byu.edu/news/byu‐continues‐offer‐uta‐ed‐pass‐bargain‐price 

Year/Alternative 2014 2030

Enhanced Bus 6,800           8,400          

Preferred Alternative BRT 12,900        16,100       

Page 68: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     68 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

UTA then offered universities.76 In 2011, a regular monthly pass was $134, so a student pass 

would have been $100. Accordingly, the cost of the pass to users increased from $240 a year to 

an estimated $1,200 a year ($100 a month). In late 2011, UTA began to offer semester‐long 

passes for $212, of which BYU offered a limited number of $50 subsidies,77 with a total limit of 

$150,000 (about 3,000 passes). This program was continued in 201278 and continued in 2015. 

At UVU, passes cost $20 in 2011 as part of the Ed Pass program.79 In 2012, passes were $50, 

and have been rising $10 each year.80 In fall 2015, UVU sold UTA transit passes (valid on all 

services except Ski Bus and Para‐transit) for $90 per year.81 In 2015, the rate for an adult pass 

was $198, and the price for a K‐12 student was $150, representing a substantial subsidy. The 

same system was continued in 2017.82  Hence, while UVU continues to provide a pass, it 

continues to increase the price to students. 

8.1.2.5 TheRyde

A fourth factor affecting ridership is The Ryde. Beginning in 2012, this private shuttle service 

began to provide a series of short‐distance shuttle routes in a limited area near BYU.83 It runs 

three times an hour84 and students are able to use their student IDs as pass cards.85 There are 

five routes,86 which are shown in Figure 8‐13 and Figure 8‐14. Two routes terminate at the 

                                                       

76 Leonard, W. (2011, May 31). UTA in Ed Pass negotiations with colleges, universities. Deseret News. Retrieved May 20, 2017, from http://www.deseretnews.com/article/705373652/UTA‐in‐Ed‐Pass‐negotiations‐with‐colleges‐universities.html?pg=all 77 Call, A. (2011, September 5). UTA’s Newest Student Transit Pass. The Daily Universe. Retrieved May 20, 2017, from http://universe.byu.edu/2011/09/05/utas‐newest‐student‐transit‐pass/ 78 Fielding, C. (2012, August 14). BYU employees can purchase UTA passes for upcoming school year beginning Aug. 20. BYU News. Retrieved May 20, 2017, from https://news.byu.edu/news/byu‐employees‐can‐purchase‐uta‐passes‐upcoming‐school‐year‐beginning‐aug‐20 79 Rosenlof, C. (2011, February 28). Thrown Under the Bus. The UVU Review. Retrieved May 20, 2017, from http://www.uvureview.com/recent/opinions/thrown‐under‐the‐bus/ 80 Frandsen, T. (2014, October 6). UTA Raises Price for Student Pass. The UVU Review. Retrieved May 20, 2017, from http://www.uvureview.com/recent/news/uta‐raises‐price‐student‐pass/ 81 Frandsen, T. (2014, October 6). UTA Raises Price for Student Pass. The UVU Review. Retrieved May 20, 2017, from http://www.uvureview.com/recent/news/uta‐raises‐price‐student‐pass/ 82 Utah Valley University Campus Connection. (n.d.). Retrieved May 20, 2017, from https://www.uvu.edu/campusconnection/id/index.html 83 Jenkins, C. (2014, December 4). BYU Announces Student Shuttle Service and Changes to Student Parking. BYU News. Retrieved May 20, 2017, from https://news.byu.edu/news/byu‐announces‐student‐shuttle‐service‐and‐changes‐student‐parking 84 BYU OneStop. (n.d.). Retrieved May 20, 2017, from https://onestop.byu.edu/view‐transportation‐options 85 The Ryde. (n.d.). Retrieved May 20, 2017, from http://studentmovement.com/ 86 The Ryde. (n.d.). Retrieved May 20, 2017, from The Ryde. (n.d.). Retrieved May 20, 2017, from http://studentmovement.com/ 

Page 69: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     69 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

roundabout at East Campus Drive and 1100 North. Three routes terminate at the BYU Museum 

of Art Parking lot.  

Figure 8‐13: The RYDE routes 2016 

 

 

Page 70: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     70 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 8‐14: The RYDE routes 2015 

 

A model made using assumptions of 2010 conditions (2010 ridership, 2005—2010 trend, 2010 

travel times, 2010 university support, the absence of The Ryde) would over‐predict 2011 

ridership, being unable to incorporate information about changed conditions in 2011. 

8.1.2.6 BoardingLocations

Boardings and alightings on the current Route 830 and Route 838 are shown in Figure 8‐15. The 

largest numbers for Route 830 take place at Orem FrontRunner, UVU, the Timpanogas transit 

center, the southeast corner of BYU, and Provo FrontRunner. For Route 838, the largest 

number of boardings take place in the East Bay Technology Park.  

 

Page 71: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     71 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

8.1.3 DataLimitations

From 2000 to 2014, UTA made use of two counts: a monthly driver count and an FTA‐approved 

random sampling plan by system monitors. The two counts initially differed significantly. 

During this audit, we found that UTA reached adequate sampling levels in 2010 (as 

prescribed by the Federal Transit Administration (FTA)) and that the difference between 

the system monitor and bus driver counts has decreased from large variations of 30 

percent in 2004 and 12 percent in 2007. It should be noted that a smaller percent of 

variation indicates more reliable data.87 

Part of the divergence was found to be a result of system monitors including themselves in the 

passenger total. The amount of variance also fell over time. "After adjusting for the system 

monitor count overstatement of 6 percent, it appears that the variance between bus driver 

counts and system monitor counts was actually 8 percent in 2010.88 

In 2014, UTA equipped all buses with automatic passenger counters. An evaluation of ridership 

counts in 2014 found the APC counts to be very similar to the adjusted driver counts (about 

2.7%89). Hence, while older counts can be questionable, recent counts should be accurate and 

unbiased. In 2015, the FTA approved the use of the automatic passenger counters for sampling, 

and UTA discontinued the use of driver counts and system monitor counts. Hence, there are 

two different data series in ridership data.  

The latter data is of better quality. For UTA, ridership data prior to 2014 was only recorded at 

the route level, so the locations of boardings and alightings can only be known for 2014 and 

2015.  

No data on ridership for The Ryde is currently available, so it is unknown how the addition of a 

private (but subsidized) transit service has affected total transit ridership. 

 

 

 

                                                       

87 Office of the Utah Legislative Auditor General. (2012, January). A Performance Audit of the Utah Transit Authority. Retrieved May 20, 2017, from https://le.utah.gov/audit/12_01rpt.pdf 88 Office of the Utah Legislative Auditor General. (2012, January). A Performance Audit Oif the Utah Transit Authority. Retrieved May 20, 2017, from https://le.utah.gov/audit/12_01rpt.pdf 89 Utah Transit Authority. (n.d.). Comprehensive Annual Financial Report‐ For Fiscal Year Ended December 31, 2014 and 2013. Retrieved May 20, 2017, from https://www.rideuta.com/uploads/UTA2014CAFRReport.pdf 

Page 72: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     72 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 8‐15: Boardings and Alightings for Routes 830 and 838 in 2015 

 

Page 73: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     73 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

8.2 Capital Cost Effectiveness 

FTA guidelines for cost effectiveness vary by project type90: 

The cost effectiveness measure for New Starts projects is the annual capital and 

operating and maintenance (O&M) cost per trip on the project. For Small Starts projects, 

the cost effectiveness measure is the annualized capital federal share of the project per 

trip on the project. The number of trips on the project is not an incremental measure but 

simply total estimated trips on the project. 

The Provo‐Orem BRT project was funded under a Small Starts grant, so the appropriate 

measure is annualized federal share of the project per trip on the project. Totals from a 2011 

forecast provided counts in terms of daily linked trips on the project91. The annualized federal 

share was calculated on a $75 million federal grant. The capital share was annualized to obtain 

an equivalent annual cost by dividing the net present value of the present value of an annuity. 

In accordance with FTA guidance, a 2.0 percent discount rate was used, with a 20 year horizon. 

Figure 8‐16 shows the calculation used92. 

Figure 8‐16: Equivalent Annual Cost Calculation 

 

This calculation provides a value of $4,586,754 for the annualized cost.  The resultant capital 

cost effectiveness is shown in Figure 8‐17. 

                                                       

90 Federal Transit Administration (2013) “New Starts and Small Starts Evaluation and Rating Process Final Policy Guidance 2013”. Retrieved from: http://www.apta.com/gap/fedreg/Documents/NS‐SS_Final_PolicyGuidance_August_2013.pdf 91 Federal Transit Admininistration, Region VIII. (2011). Environmental Assessment, Provo‐Orem Rapid Transit Project, Utah County, Utah. Salt Lake City, Utah: Utah Transit Authority. 92 Federal Transit Administration (2013) “New Starts and Small Starts Evaluation and Rating Process Final Policy Guidance 2013”. Retrieved from: http://www.apta.com/gap/fedreg/Documents/NS‐SS_Final_PolicyGuidance_August_2013.pdf 

Page 74: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     74 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 8‐17: Capital Cost Efficiency based on 2011 Forecast 

 

8.3 Operating Cost Efficiency 

Efficiency is defined as the unit cost of inputs necessary to produce a unit of output. From a 

transit perspective, this is typically the operating cost per passenger. While the system has not 

yet begun operations, this can be estimated for the project by dividing the annual operating 

costs by the annual linked trips to get the cost per trip. The annual operating cost was forecast 

to be $3.59 million93. This generates a cost per trip of $1.02.  

Other operating cost metrics include cost effectiveness, such as cost‐per‐vehicle‐hour or vehicle 

mile, farebox recovery ratio, or net subsidy per passenger are not presented here. Measures of 

service productivity such as passengers per vehicle mile or vehicle hour, while valuable, are not 

relevant to operating cost efficiency. 

8.4 Transit Supportive Land Use Development 

This section contains information on current land uses, potential future land uses, and the 

timing of land uses changes. 

8.4.1 CurrentLandUses

The major land use near the project alignment is educational. Educational land uses include 

UVU, BYU, and Provo High School. Commercial land uses make up the next largest category, 

followed by residential uses.    

                                                       

93 Federal Transit Administration. (2017) Provo‐Orem Bus Rapid Transit: Provo‐Orem, Utah Small Starts Development. Retrieved from: https://www.transit.dot.gov/sites/fta.dot.gov/files/docs/UT__Provo‐Orem_BRT_Profile_FY17.pdf 

Metric Value Cost Effectiveness

Daily Linked Trips 11,300             405.91$                        

Annual Linked Trips 3,533,200       1.30$                             

Page 75: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     75 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 8‐18 shows the study area land uses. 

8.4.2 PotentialFutureLandUse

Almost all the land within the study area has already been urbanized, so almost all new 

development must be redevelopment of existing urbanized land. For most urban land, 

redevelopment tends to occur only when the value of existing structures is negligible. A 

substantial portion of the area near the project alignment consists of single‐family homes, 

which rarely depreciates to such a level, and thus are extremely unlikely to redevelop into 

transit‐supportive land uses. However, much of the land consists of automobile‐oriented 

commercial use, which tends to depreciate rapidly.94 Accordingly, it seems likely that these 

parcels will redevelop most quickly. Depending on the real estate and regulatory context, this 

may result in subdivision into smaller parcels, the construction of additional structures closer to 

the roadway, and may include the addition of parking garages. It may also result in a transition 

to multi‐family apartment houses. Low‐rise commercial use tends to generate a very large 

number of trips of very short duration. Apartments, especially those with limited parking, tend 

to generate more transit trips.  

For non‐market actors such as universities, the allocation of real estate follows different 

principles. In general, it tends to transition from lower intensity uses to higher intensity uses 

over time, typically from lawns and other open space to parking lots and then to buildings and 

parking garages.  

8.4.3 TimingofLandUseChanges

The timing of land use changes in response to transit improvements is highly variable. Research 

suggests that the timing of redevelopment depends on four factors:95 

The discount rate applying in the real estate market; 

The earnings in any interim use; 

The way in which the highest and best use of the land is expected to change in the 

future; and 

The property tax rate. 

                                                       

94 Marshal Valuation Service. (2007). Life Expectancy Guidelines, February 2007. Section 97, page 6. Los Angeles, 

CA. 95 Shoup, D. C. (1970). The optimal timing of urban land development. Papers in Regional Science, 25(1), 33-44. 

Page 76: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     76 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Lower costs of borrowing tend to drive new investment. However, the location of new 

development depends on local market demand for new structures. Without that demand no 

new development occurs.  

Land must also be available for development. Redevelopment occurs when the value of the 

structures on the land approaches zero; ie, when the parcel most nearly approximates 

competing vacant land. This occurs when the earnings of the current use are very low, such as 

the case for agricultural land. The reliable rents from single family detached homes means only 

non‐habitable structures are likely to be redeveloped. 

Transit cannot make the market. Development near transit responds to zoning and regulatory 

changes made in response to transit, rather than responding to the transit itself96. When 

market and regulatory conditions are right, development can occur very rapidly, in some cases 

preceding the opening of transit operations.  

Finally, property taxes influence redevelopment. For an investor, property taxes effectively 

reduce the income from a property. The lower the income of a property’s current use, the more 

likely it will be redeveloped. Under this logic, effects that increase property values or property 

taxes near transit (such as Transit Benefit Districts) may help spur redevelopment. 

   

                                                       

96 Chatman, D. G. (2013). Does TOD need the T? On the importance of factors other than rail access. Journal of the American Planning Association, 79(1), 17‐31. 

Page 77: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     77 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 8‐18: Study Area Land Uses Circa 2015/2016 

 

Page 78: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     78 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

8.5 Environmental Quality (Vehicle Emissions) 

Vehicle emissions refer to a range of pollutants. The criteria for pollutants for most air quality 

analyses includes volatile organic compounds (VOC), carbon monoxide (CO), nitrogen oxides 

(NOx), sulfur dioxide (SO2 ), particulate matter under 10 microns in diameter (PM10), particulate 

matter under 2.5 microns in diameter (PM2.5), methane (CH4), and nitrogen dioxide (NO2). 

Neither carbon dioxide (CO2) or fuel consumption were included in these calculations. 

8.5.1 Methods&Data

8.5.1.1 VehicleMilesTraveled

Emissions were estimated by multiplying VMT by emissions per mile traveled. The total amount 

of VMT on the BRT alignment and other roads in the project area were estimated by multiplying 

the AADT by road mileage. Figure 8‐19 shows the estimated VMT by facility type (arterial or 

freeway) for the BRT alignment, Diversion Corridors, and the rest of Utah County. The method 

has been validated by comparing VMT estimates using this method for 2011 to official counts 

for 2011.97  

Figure 8‐19: VMT by Facility Type and Geography 

 

The BRT alignment consists of over 10 miles of some of the highest volume roads in Utah 

County. Correspondingly, the total VMT on those roads is a very large number, equal to about 

1/3 of the arterial volumes on the diversion corridors. Of the diversion corridors, I‐15 

represents about half the volume, a relationship that holds for I‐15 and Utah County as a whole. 

Different facilities have different shares of VMT by vehicle classes. The share of VMT by Vehicle 

Type data was for Utah County98 for 2014. It was expanded by fuel type using the ratios from 

GREET for MOVES.99 UTA does not currently have any gasoline buses, and is in the process of 

                                                       

97 Mountainland MPO (2015). 2040 Regional TRANSPORTATION PLAN: Appendix A, CONFORMITY DETERMINATION REPORT. Retrieved from: http://mountainland.org/img/transportation/TransPlan40/Appendix%20A%20‐%20AQ%20Conformity%20Report.pdf (May 30, 2017). 98 Provided by Kip Billings at WFRC, 18 January 2017. Data is input data for the travel model.  99 Cai, H., Burnham, A. & Wang, M. (2013). Updated Emission Factors of Air Pollutants from Vehicle Operations in GREET Using MOVES. Retrieved from: https://greet.es.anl.gov/publication‐vehicles‐13, table 24 

Row Labels Arterial Freeway Grand Total

Alignment 400,985      ‐                400,985            

Diversion Corridors 1,245,436  1,404,757   2,650,193        

Utah County, Remainder 4,986,620  4,662,477   9,649,097        

Grand Total 6,633,041  6,067,234   12,700,275      

Page 79: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     79 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

replacing all diesel buses with CNG buses. The BRT buses are anticipated to be CNG/clean diesel 

buses. A CNG bus produces less than 1% as much VOC, CO, NOx as a diesel vehicle, and only 

about two thirds as much PM10 and PM2.5. UTA currently has over 400 buses, of which 65% 

are currently clean diesel or CNG100. As of March 2016, UTA had 47 CNG buses101. For initial 

conditions, a service miles mix matching this fleet mix was used. VMT for vehicle/fuel type for 

the BRT alignment, Diversion Corridors, and the Remainder of Utah County are presented in 

Figure 8‐20.  

Figure 8‐20: Share of VMT by Vehicle/Fuel Type and Geography 

 

8.5.1.2 EmissionsperVMT

Mobile emission were estimated using emissions by vehicle class and fuel type as inputs into 

the Greenhouse gases, Regulated Emissions, and Energy use in Transportation (GREET) model 

for the Environmental Protection Agency (EPA) Motor Vehicle Emissions Simulator (MOVES).  

                                                       

100 Piellisch, R. (2016, January 5). Utah Transit Opens CNG Fueling. Fleets and Fuels. Retrieved May 20, 2017, from http://www.fleetsandfuels.com/fuels/cng/2016/01/utah‐transit‐opens‐cng‐fueling‐facility/ 101 Utah Transit Authority (2016). Transit and Air Quality. Retrieved from: https://www.rideuta.com/‐/media/Files/Publications/Transit_and_Air_Quality_Facts_2016_p.ashx?la=en, on May 30, 2017. 

Alignment

Arterial Arterial Freeway Arterial Freeway

Combination long‐haul trucks diesel 23,270                  72,274           81,520              304,395                 284,608                 766,067            

Combination short‐haul trucks diesel 7,759                    24,098           27,181              101,493                 94,895                   255,426            

Combination short‐haul trucks gasoline ‐                         ‐                  ‐                     ‐                          ‐                          ‐                     

Intercity buses diesel 369                        1,145              1,292                4,823                     4,510                     12,139              

Light commercial trucks diesel 3,431                    10,656           12,019              42,292                   39,543                   107,942            

Light commercial trucks gasoline 29,276                  90,931           102,563            360,896                 337,436                 921,102            

Motor homes diesel 399                        1,240              1,398                5,222                     4,882                     13,141              

Motor homes gasoline 399                        1,240              1,398                5,222                     4,882                     13,141              

Motorcycles gasoline 801                        2,487              2,805                9,871                     9,229                     25,193              

Passenger cars diesel 693                        2,152              2,428                8,542                     7,987                     21,801              

Passenger cars gasoline 180,344                560,139         631,794            2,223,142             2,078,632             5,674,051        

Passenger trucks diesel 2,991                    9,291              10,480              36,875                   34,478                   94,116              

Passenger trucks gasoline 125,626                390,188         440,103            1,548,624             1,447,959             3,952,501        

Refuse trucks diesel 877                        2,724              3,073                11,473                   10,727                   28,874              

Refuse trucks gasoline ‐                         ‐                  ‐                     ‐                          ‐                          ‐                     

School buses diesel 1,916                    5,950              6,711                25,059                   23,430                   63,066              

School buses gasoline 135                        419                 473                    1,765                     1,650                     4,441                 

Single‐unit long‐haul trucks diesel 826                        2,567              2,895                10,810                   10,107                   27,206              

Single‐unit long‐haul trucks gasoline 354                        1,100              1,241                4,633                     4,332                     11,660              

Single‐unit short‐haul trucks  diesel 14,550                  45,192           50,973              190,332                 177,959                 479,005            

Single‐unit short‐haul trucks  gasoline 6,228                    19,343           21,817              81,464                   76,169                   205,020            

Transit buses CNG 99                          306                 345                    1,290                     1,206                     3,247                 

Transit buses  diesel 447                        1,388              1,566                5,846                     5,466                     14,713              

Transit buses  gasoline 294                        912                 1,029                3,843                     3,593                     9,671                 

400,985                1,245,436     1,404,757        4,986,620             4,662,477             12,700,275      

Utah County, RemainderDiversion Corridors

FuelVehicle Type Grand Total

Page 80: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     80 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Different classes of vehicles/fuel types have different operational characteristics, and therefore 

different emissions. A common model year will be used for all analyses, in order to determine 

differences in emissions due to change in VMT, rather than improving because fleet emissions 

are improving. For emissions estimates, 2018 was used. As the model data for VMT shares are 

provided only in five‐year increments,102 data for 2018 was interpolated from 2015 & 2020 VMT 

shares using a linear relationship. The grams per mile rate by Vehicle/Fuel type103 for the 2018 

model year is shown in Figure 8‐21. Colored databars are used to call attention to vehicle/fuel 

type that produces the most of each pollutant. 

Figure 8‐21: Emissions in Grams per Mile by Vehicle and Fuel Type 

Per mile, Refuse Trucks (gasoline) produce the most VOC, NOx, and SO2. School Buses (gasoline 

produce the most CO and N2O. Combination long‐haul trucks produce the most Nitrous Oxide, 

PM2.5, and CH4. This can be attributed to their operation pattern, which involves repeated 

acceleration and braking. Gasoline transit buses also produce substantial emissions. 

                                                       

102 Cai, H., Burnham, A. & Wang, M. (2013). Updated Emission Factors of Air Pollutants from Vehicle Operations in GREET Using MOVES. Retrieved from: https://greet.es.anl.gov/publication‐vehicles‐13, table 24 103 Cai, H., Burnham, A. & Wang, M. (2013). Updated Emission Factors of Air Pollutants from Vehicle Operations in GREET Using MOVES. Retrieved from: https://greet.es.anl.gov/publication‐vehicles‐13, tables 2‐23 

Vehicle Fuel VOC CO NOx S02 PM10 PM2.5 CH4 NO2

Combination long‐haul trucks diesel 0.4051 1.6523 4.5835 0.0149 0.14497 0.08604 0.4635 0.002

Combination short‐haul trucks diesel 0.0926 0.4301 1.4192 0.0135 0.12067 0.06724 0.0472 0.0021

Combination short‐haul trucks gasoline 0 0 0 0 0 0 0 0

Intercity buses diesel 0.0949 0.6535 1.4222 0.0119 0.16566 0.08413 0.0567 0.0024

Light‐duty commercial trucks diesel 0.0784 1.2486 0.9698 0.0045 0.04802 0.02671 0.0936 0.0029

Light‐duty commercial trucks gasoline 0.2966 6.1397 0.4245 0.0054 0.05193 0.03053 0.027 0.0084

Motor homes diesel 0.0816 0.9402 0.9892 0.0073 0.08592 0.04161 0.0671 0.0026

Motor homes gasoline 1.5606 33.8175 3.3031 0.0143 0.07828 0.03418 0.0165 0.0067

Motorcycles gasoline 1.4575 13.0641 0.677 0.0056 0.08033 0.07143 0.0602 0.0071

Passenger cars diesel 0.0722 2.7352 0.2324 0.002 0.02804 0.01434 0.0927 0.0007

Passenger cars gasoline 0.1682 2.8611 0.12 0.0042 0.03322 0.01862 0.0111 0.0044

Passenger trucks diesel 0.077 1.32 0.942 0.0045 0.04653 0.02642 0.0916 0.0028

Passenger trucks gasoline 0.2725 4.9144 0.3088 0.0054 0.05213 0.03093 0.025 0.0078

Refuse trucks diesel 0.0932 0.6575 1.3056 0.0115 0.15473 0.07711 0.0586 0.0026

Refuse trucks gasoline 1.7536 29.4382 4.5224 0.0225 0.07143 0.03062 0.015 0.0061

School buses diesel 0.1129 2.9455 1.1158 0.0065 0.10977 0.05045 0.1147 0.0044

School buses gasoline 1.6931 85.7948 2.7719 0.0132 0.08018 0.04147 0.0856 0.0242

Single‐unit long‐haul trucks diesel 0.0749 0.9398 0.8931 0.0066 0.10298 0.04596 0.0707 0.0029

Single‐unit long‐haul trucks gasoline 0.965 30.6937 3.0315 0.0132 0.07968 0.03187 0.0261 0.0089

Single‐unit short‐haul trucks diesel 0.0772 1.0199 0.9388 0.007 0.1039 0.04669 0.0755 0.0031

Single‐unit short‐haul trucks gasoline 0.9124 33.0264 3.1204 0.014 0.08008 0.03208 0.04 0.0108

Transit buses CNG 2.1E‐05 0.019175 0.00206 0.0089 0.06865 0.03257 0.0642 0.00019

Transit buses diesel 0.0868 1.0895 1.2096 0.0089 0.08914 0.05222 0.0642 0.0029

Transit buses gasoline 1.6719 39.2963 3.537 0.0176 0.0688 0.0321 0.0338 0.01

Page 81: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     81 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

To determine total emissions, VMT was apportioned in accordance to the lifetime VMT for each 

vehicle class and fuel type for model year 2018. The apportioned VMT was then multiplied by 

the emissions rate for each vehicle/fuel class to get total emissions for each vehicle class, which 

was then summed to obtain total emissions for the BRT alignment and the study area.  

8.5.2 Results&Discussion

Figure 8‐22 shows the results broken out by vehicle and fuel types as percentages, to 

demonstrate which types of vehicles in the anticipated 2018 fleet will generate the most 

pollution. The cells in Figure 8‐22 have been colored to call out the largest contributor in each 

category, with red being the largest and green the least. 

Figure 8‐22: Share of Emissions by Vehicle Type  

 

As expected, emissions are largely proportional to the share of VMT; passenger cars and trucks, 

which represent about 75 percent of the VMT traveled, are the major share of most emissions. 

Combination long‐haul trucks emit a large share of the total NOx and CH4. Transit buses emit 

only a miniscule share of emissions. 

Total emissions in grams for the BRT corridor is quantified in Figure 8‐24. It shows emissions by 

the share of each pollutant emitted by vehicle type to identify which vehicle/fuel types are the 

most severe emitters of each type of pollutant. The cells have been colored‐coded to call out 

the largest contributor in each category, with red being the largest and green the least. 

Vehicle Fuel VOC CO NOx S02 PM10 PM2.5 CH4 NO2

Combination long‐haul trucks diesel 10% 2% 44% 15% 16% 17% 55% 2%

Combination short‐haul trucks diesel 1% 0% 5% 5% 4% 4% 2% 1%

combination short‐haul trucks gasoline 0% 0% 0% 0% 0% 0% 0% 0%

Intercity buses diesel 0% 0% 0% 0% 0% 0% 0% 0%

Light‐duty commercial trucks diesel 0% 0% 1% 1% 1% 1% 2% 0%

Light‐duty commercial trucks gasoline 9% 11% 5% 7% 7% 7% 4% 11%

Motor homes diesel 0% 0% 0% 0% 0% 0% 0% 0%

Motor homes gasoline 1% 1% 1% 0% 0% 0% 0% 0%

Motorcycles gasoline 1% 1% 0% 0% 0% 0% 0% 0%

Passenger cars diesel 0% 0% 0% 0% 0% 0% 0% 0%

Passenger cars gasoline 32% 31% 9% 33% 28% 28% 10% 35%

Passenger trucks diesel 0% 0% 1% 1% 1% 1% 1% 0%

Passenger trucks gasoline 36% 37% 16% 29% 31% 32% 16% 44%

Refuse trucks diesel 0% 0% 0% 0% 1% 1% 0% 0%

Refuse trucks gasoline 0% 0% 0% 0% 0% 0% 0% 0%

School buses diesel 0% 0% 1% 1% 1% 1% 1% 0%

School buses gasoline 0% 1% 0% 0% 0% 0% 0% 0%

Single‐unit long‐haul trucks diesel 0% 0% 0% 0% 0% 0% 0% 0%

Single‐unit long‐haul trucks gasoline 0% 1% 0% 0% 0% 0% 0% 0%

Single‐unit short‐haul trucks diesel 1% 1% 6% 4% 7% 6% 6% 2%

Single‐unit short‐haul trucks gasoline 6% 12% 8% 4% 2% 2% 1% 3%

Transit buses CNG 0% 0% 0% 0% 0% 0% 0% 0%

Transit buses diesel 0% 0% 0% 0% 0% 0% 0% 0%

Transit buses gasoline 1% 1% 0% 0% 0% 0% 0% 0%

Page 82: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     82 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 8‐24: Average Annual Emissions by Vehicle Type for BRT Corridor in Grams 

 

As the table shows, emissions from passenger cars and trucks are the primary sources of VOCs 

and NOx, both of which are precursor chemicals to ozone. Passenger cars and trucks are also 

the main emitters of PM2.5 (with combination long‐haul trucks the next most severe). The 

Provo‐Orem Metropolitan Area is currently in Serious Non‐Attainment for PM2.5.104 

For the analysis of emissions, the study area consists of the diversion corridors. Figure 8‐23 

shows the emissions by vehicle/fuel type for each category of emissions. The cells have been 

colored‐coded to call out the largest contributor in each category, with red being the largest 

and green the least. 

Figure 8‐23: Average Annual Emissions by Vehicle Type for Diversion Corridors in Grams 

                                                       

104 Environmental Protection Agency (May 2015) Determinations of Attainment by the Attainment Date, Determinations of Failure To Attain by the Attainment Date and Reclassification for Certain Nonattainment Areas for the 2006 24‐Hour Fine Particulate Matter National Ambient Air Quality Standards 

Vehicle Fuel VOC CO NOx S02 PM10 PM2.5 CH4 NO2

Combination long‐haul trucks diesel 9,427         38,449           106,657      347          3,373         2,002         10,786  47           

Combination short‐haul trucks diesel 718            3,337             11,011         105          936            522            366        16           

Combination short‐haul trucks gasoline ‐             ‐                  ‐               ‐           ‐             ‐             ‐         ‐          

Intercity buses diesel 35               241                 524               4               61               31               21           1              

Light‐duty commercial trucks diesel 269            4,284             3,327           15            165            92               321        10           

Light‐duty commercial trucks gasoline 8,683         179,748         12,428         158          1,520         894            790        246         

Motor homes diesel 33               375                 395               3               34               17               27           1              

Motor homes gasoline 623            13,499           1,318           6               31               14               7             3              

Motorcycles gasoline 1,167         10,461           542               4               64               57               48           6              

Passenger cars diesel 50               1,895             161               1               19               10               64           0              

Passenger cars gasoline 30,334      515,983         21,641         757          5,991         3,358         2,002     794         

Passenger trucks diesel 230            3,949             2,818           13            139            79               274        8              

Passenger trucks gasoline 34,233      617,378         38,793         678          6,549         3,886         3,141     980         

Refuse trucks diesel 82               577                 1,145           10            136            68               51           2              

Refuse trucks gasoline ‐             ‐                  ‐               ‐           ‐             ‐             ‐         ‐          

School buses diesel 216            5,643             2,137           12            210            97               220        8              

School buses gasoline 228            11,574           374               2               11               6                 12           3              

Single‐unit long‐haul trucks diesel 62               777                 738               5               85               38               58           2              

Single‐unit long‐haul trucks gasoline 342            10,871           1,074           5               28               11               9             3              

Single‐unit short‐haul trucks diesel 1,123         14,840           13,660         102          1,512         679            1,099     45           

Single‐unit short‐haul trucks gasoline 5,682         205,675         19,433         87            499            200            249        67           

Transit buses CNG 0                 2                      0                   1               7                 3                 6             0              

Transit buses diesel 39               487                 541               4               40               23               29           1              

Transit buses gasoline 491            11,544           1,039           5               20               9                 10           3              

TOTAL 94,068      1,651,585     239,757      2,327      21,432      12,095      19,589  2,247     

Page 83: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     83 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

 

The results suggest that transit buses are minimal contributors to overall pollution. Switching 

automobile miles to transit bus miles should significantly reduce pollution; this is especially true 

for CNG buses.  

8.5.3 DataLimitations

The same VMT mix was used for all arterials in Utah County and the BRT alignment, as no 

specific VMT mix exists for the BRT alignment. Nor is the VMT mix an exact match to actual 

conditions. The share of VMT mileage data used is for 2014, rather than 2018. While it provides 

an inferior match in terms of the modeling year, it provides a better match for mileage in the 

geography than using GREET/MOVES defaults. Figure 8‐24 shows the differences between the 

two rates; Utah County has more light trucks than the national average, and fewer passenger 

cars. It also has more combination long‐haul trucks. UTA’s exact fleet mix, fleet mix in Utah 

County, or mix of service miles by fuel type are unknown.   

 

 

 

 

Vehicle Fuel VOC CO NOx S02 PM10 PM2.5 CH4 NO2

Combination long‐haul trucks diesel 62,302      254,115         704,917      2,292      22,296      13,232      71,284     308         

Combination short‐haul trucks diesel 4,748         22,055           72,775         692          6,188         3,448         2,420       108         

Combination short‐haul trucks gasoline ‐             ‐                  ‐               ‐           ‐             ‐             ‐           ‐          

Intercity buses diesel 231            1,593             3,466           29            404            205            138           6              

Light‐duty commercial trucks diesel 1,778         28,312           21,990         102          1,089         606            2,122       66           

Light‐duty commercial trucks gasoline 57,390      1,187,991     82,138         1,045      10,048      5,907         5,224       1,625     

Motor homes diesel 215            2,480             2,610           19            227            110            177           7              

Motor homes gasoline 4,117         89,216           8,714           38            207            90               44             18           

Motorcycles gasoline 7,713         69,137           3,583           30            425            378            319           38           

Passenger cars diesel 331            12,526           1,064           9               128            66               425           3              

Passenger cars gasoline 200,483    3,410,239     143,032      5,006      39,596      22,194      13,230     5,245     

Passenger trucks diesel 1,522         26,097           18,624         89            920            522            1,811       55           

Passenger trucks gasoline 226,254    4,080,384     256,394      4,484      43,283      25,681      20,757     6,476     

Refuse trucks diesel 540            3,811             7,568           67            897            447            340           15           

Refuse trucks gasoline ‐             ‐                  ‐               ‐           ‐             ‐             ‐           ‐          

School buses diesel 1,429         37,293           14,127         82            1,390         639            1,452       56           

School buses gasoline 1,510         76,496           2,471           12            71               37               76             22           

Single‐unit long‐haul trucks diesel 409            5,133             4,878           36            562            251            386           16           

Single‐unit long‐haul trucks gasoline 2,259         71,847           7,096           31            187            75               61             21           

Single‐unit short‐haul trucks diesel 7,424         98,078           90,279         673          9,991         4,490         7,260       298         

Single‐unit short‐haul trucks gasoline 37,554      1,359,350     128,434      576          3,296         1,320         1,646       445         

Transit buses CNG 0                 12                   1                   6               45               21               42             0              

Transit buses diesel 256            3,218             3,573           26            263            154            190           9              

Transit buses gasoline 3,246         76,294           6,867           34            134            62               66             19           

TOTAL 621,713    10,915,679   1,584,603   15,377    141,646    79,936      129,471  14,853   

Page 84: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     84 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 8‐24: Share of Vehicles by Vehicle and Fuel Type 

 

   

Page 85: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     85 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

9 System Effects on Roadway Network This section provides information on the initial conditions of the roadway network, prior to the 

construction of the Provo‐Orem BRT. Baseline conditions for Annual Average Daily Traffic 

(AADT) are documented. Initial conditions for factors that might affect AADT, such as new 

development, new transportation infrastructure, and student enrollment, are also covered. 

Data on parking supply and occupancy was collected. Finally, baseline data for other factors 

that might be affected by the new BRT (automobile crash rates and vehicle emissions) were 

collected. This section thus contains the following sub‐sections: 

1. Traffic Counts 

2. New Development 

3. New Transportation Infrastructure 

4. Student Enrollment 

5. Parking Supply & Occupancy 

6. Crash Rates 

9.1 Traffic Counts 

This section details the methods and data used for traffic counts. Counts (AADT) for the 

alignment, diversion corridors, and Utah County are provided as both graphs and tables. 

Additionally, counts for ‘multi‐corridor screen lines are shown. Data limitations regarding count 

frequency and coverage are then discussed. 

9.1.1 Methods&Data

Historical traffic counts of AADT were obtained for at least five years prior to BRT construction 

for all roads within the study area. The point counts of AADT were assigned to road segments. 

Road segments along a route were summed to provide corridor counts. Counts from multiple 

parallel corridors were summed to provide counts for screen lines. Screen lines (i.e., cut‐lines) 

are lines cutting across segments of numerous corridors intended to measure the sum total of 

all traffic flows across the entire study area. Projections on future AADT were made using a 

linear estimator for the previous five years to each year on a compounding basis.  This was used 

in preference to average annual compound change because it is less sensitive to year‐specific 

counts. Because the counts were proportional to the number of road segments, the counts 

were divided by the number of road segments to produce an average count for each corridor or 

screen line. Because the BRT alignment does not exactly match roads with AADT counts, the 

segments of roads with counts best approximating the BRT alignment were combined to 

Page 86: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     86 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

provide an equivalent. The source data was UDOT’s Traffic on Utah Highways, which is 

distributed through their Open Data Platform.105  

To validate these counts, additional data from the web based Automated Traffic Signal 

Performance Measurement System (SPMs) was used. Data for all intersections in the study area 

were requested106, but this request was non‐feasible due to the magnitude of the associated 

data. Data for signals along the BRT alignment were provided107 in 15 minute bins. No signal 

data is available prior to 2012; 2012‐2013 data are only available for signals 6315 and 6316. 

Data for most signals are available in 2014 and 2015 (excepting signals 6427 and 6436). For 

some intersections, the detector channels that count vehicles either had not started operation, 

or were out of operation for part of the year. As it furnished the most complete data, 

intersection counts from 2015 were used. Many of the channels were available lacked the 

relevant channels to compare to the UDOT AADT count. The data that remained available is 

shown in Figure 9‐1. 

Figure 9‐1: Intersections along BRT Alignment 

 

To compare with AADT along the BRT alignment, an AADT analogue was created. This was 

created by the available 15 minutes counts for each channel to get an average count, and then 

                                                       

105 Sellers, Adrian (March 2017). AADT (Open Data). Utah Department of Transportation. Retrieved May 30, 2017, from http://www.udot.utah.gov/main/f?p=100:pg:0::::V,T:,528 106 Signal #’s: 6315, 6316, 6317, 6318, 6319, 6320, 6321, 6322, 6324, 6324, 6328, 6338, 6401, 6402, 6403, 6404, 6405, 6406,6407, 6408, 6409, 6410, 6411. 6417, 6427, 6435, 6436, 6619, 6623, 6625, 6627, 6628, 6633, 6634, 6635, 6651, 6652, 6654, 6655 107 Jamie Mackey, P.E., PTOE. Statewide Signal Engineer, <[email protected]>

 

Signal Number Intersection 2015 MISSING DATES Relevant Channels

6315 Geneva Road @ 1000 South NA All

6316 Geneva Road @ University Parkway Ends July 16 Missing

6317 University Parkway @ I‐15 SPUI NA Missing

6328 University Pkwy @ 680 E (University Pl) NA Missing

6401 University Avenue @ 1860 South End July 29 Missing

6402 University Avenue @ East Bay Boulevard Ends Feb 26 All

6404 University Avenue @ 920 South NA Missing

6405 University Avenue @ 300 South NA Missing

6407 University Avenue @ Center Street Ends Dec. 22 Missing

6408 University Avenue @ 100 North Ends Dec. 22 Missing

6417 University Avenue @ University Parkway NA All

6427 200 S @ University Ave (US‐189) No 2015 Data NA

6436 University Parkway @ 2230 North No 2015 Data NA

Page 87: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     87 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

multiplying that count by four (4 counts per hour) and by 24 (24 hours in a day). The channel 

counts were then summed to create ‘leg’ counts in the following way: For the north leg, all thru 

movements for northbound or southbound traffic was summed. Right‐turning east‐bound 

traffic and left‐turning westbound traffic was then summed and added to that total. This 

procedure was then repeated for all legs of an intersection.  

9.1.2 Results&Discussion

9.1.2.1 Alignment&DiversionCorridors

To detect changes in corridor traffic over time, the averaged AADT counts for all line segments 

of the alignment and diversion corridors from 2010—2014 are shown in Figure 9‐2.  

Figure 9‐2: Estimated AADT on Diversion Corridors 2010—2015 

 

Page 88: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     88 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Averaged counts are the sum of counts on all segments, divided by the number of segments. I‐

15 is omitted for reasons of magnitude; Figure 9‐9 shows the relative magnitude of traffic 

volumes in the study area. 

Figure 9‐3 shows the data table for the preceding graph, and includes the 2010‐2015 changes 

as average annual numeric and percentage changes, as well as linear estimates of numeric and 

percentage changes. Average annual changes have been included for familiarity, but the linear 

estimate is more robust, as it includes information from all five years. Numeric and percentage 

changes have been color‐coded to highlight significant changes. For numeric changes, a red‐

blue spectrum indicates the magnitude of changes; red is increase, blue is decrease. For 

percentage changes, a red‐yellow‐green spectrum indicates the magnitude of changes; green is 

positive, red is negative. 

Figure 9‐3: Estimated AADT by Diversion Corridor 2010‐2015 

 

Overall, AADT is increasing across Utah County. Orem 800 North, I‐15, and Geneva Road saw 

increases of over 2 percent per year. However, only on Orem 800 North did AADT increase at 

percentage rate faster than the rest of Utah County. The largest numeric increases occur on 

Orem 800 North and I‐15. As part of the I‐15 Core project, I‐15 was rebuilt between 2012 and 

2015. The rebuild included widening the freeway by two lanes in each direction, the addition of 

# % # %

BRT Alignment 13,944       13,520        13,475      14,283     14,795      15,678        347           2.5% 380            2.7%

Freedom Boulevard 12,939       12,909        12,494      12,183     12,317      12,931        (2)              0.0% (61)             ‐0.5%

Geneva Road (Highway 114) 11,679       11,410        12,383      12,318     12,454      12,989        262           2.2% 275            2.4%

HWY 189 26,716       27,001        26,108      26,048     27,481      28,812        419           1.6% 339            1.3%

I‐15 118,218     112,434      110,045    119,128  124,208    133,696      3,096        2.6% 3,480        2.9%

Orem 1200 South 6,202          6,230          6,103        5,422       5,480         5,717           (97)            ‐1.6% (153)          ‐2.5%

Orem 800 East 13,588       13,546        13,275      13,061     13,205      13,772        37              0.3% (9)               ‐0.1%

Orem 800 N (Highway 52) 22,848       22,961        25,468      26,114     27,229      28,558        1,142        5.0% 1,200        5.3%

Orem Center Street 22,356       22,298        21,852      20,911     21,510      22,506        30              0.1% (73)             ‐0.3%

Provo 2200 N 16,040       15,588        14,733      14,365     14,523      16,225        37              0.2% (75)             ‐0.5%

Provo 700 N 11,883       11,300        7,905        7,708       7,793         8,125           (752)          ‐6.3% (843)          ‐7.1%

Provo 900 E 19,470       19,325        18,351      17,893     18,090      18,868        (121)          ‐0.6% (205)          ‐1.1%

Provo Center Street 27,240       26,778        26,480      26,545     27,318      28,583        269           1.0% 240            0.9%

State Street (HWY 89) 30,390       29,937        28,678      29,683     30,990      32,509        424           1.4% 422            1.4%

University Ave (HWY 189) 30,948       30,414        30,561      29,470     31,092      32,874        385           1.2% 302            1.0%

University Parkway 32,565       32,168        31,428      31,463     32,643      34,347        356           1.1% 296            0.9%

Utah County, Remainder of 11,062       11,201        11,201      11,586     12,188      12,988        385           3.5% 371            3.4%

Utah County 13,782       13,817        13,744      14,114     14,786      15,716        387           2.8% 370            2.7%

Changes 2010‐2015

Street 2010 2011 2012 2013 2014 2015 Linear EstimateAverage Annual

Page 89: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     89 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

an express lane (HOV) from Orem to Spanish Fork AADT on I‐15, and the rebuilding of 10 

interchanges.108  

 Several of the diversion corridors saw lower AADT over time: Orem 1200 South (near UVU) saw 

dropping AADT over time. This may represent diversion to University Parkway. Provo 700 N saw 

notable declines, both numerically and as a percentage, but this decline was constrained to the 

eastern third of that route (between Provo 700 East and 900 East).  AADT on the BRT alignment 

is increasing at percentage rates approaching that of Utah County as a whole, but without 

major numeric changes. The MAG Long Range Transportation Plan (LRTP) calls for widening 

Orem Center Street to six lanes. Current AADT on that route is flat, which may indicate either a 

lack of demand, or that the route is operating at capacity.  

Figure 9‐4 provides estimated and forecast AADT for 2010‐2015 to compare actual future 

accounts against. 

Figure 9‐4: Estimated and Forecast AADT 2010‐2020 

 

Projections on future AADT were made using a linear estimator for the previous five years to 

each year on a compounding basis. This makes it possible to compare trend forecasts to actual 

future year counts and detect deviations from the expected AADT trend for each road. These 

projections are not travel model numbers but merely trend extrapolation. They are not capacity 

constrained and should be used with care. 

                                                       

108 Mountainland Association of Governments. (n.d.). TransPlan40 ‐ Regional Transportation Plan [2015‐2040 Plan for the Provo/Orem Metropolitan Area. Retrieved May 20, 2017, from http://mountainland.org/img/transportation/TransPlan40/TransPlan40.pdf 

Street 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

BRT Alignment 13,944       13,520        13,475      14,283     14,795      15,678        16,105       16,545       16,996       17,459       17,935       

Freedom Boulevard 12,939       12,909        12,494      12,183     12,317      12,931        12,871       12,810       12,750       12,690       12,631       

Geneva Road (Highway 114) 11,679       11,410        12,383      12,318     12,454      12,989        13,294       13,607       13,927       14,255       14,590       

HWY 189 26,716       27,001        26,108      26,048     27,481      28,812        29,177       29,548       29,922       30,302       30,686       

I‐15 118,218     112,434      110,045    119,128  124,208    133,696      137,632     141,683    145,854     150,147     154,567     

Orem 1200 South 6,202          6,230          6,103        5,422       5,480         5,717           5,576          5,438         5,304         5,173          5,045         

Orem 800 East 13,588       13,546        13,275      13,061     13,205      13,772        13,763       13,754       13,744       13,735       13,726       

Orem 800 N (Highway 52) 22,848       22,961        25,468      26,114     27,229      28,558        30,057       31,636       33,297       35,046       36,886       

Orem Center Street 22,356       22,298        21,852      20,911     21,510      22,506        22,432       22,359       22,286       22,213       22,141       

Provo 2200 N 16,040       15,588        14,733      14,365     14,523      16,225        16,149       16,073       15,997       15,922       15,847       

Provo 700 N 11,883       11,300        7,905        7,708       7,793         8,125           7,549          7,013         6,515         6,053          5,624         

Provo 900 E 19,470       19,325        18,351      17,893     18,090      18,868        18,669       18,472       18,278       18,085       17,895       

Provo Center Street 27,240       26,778        26,480      26,545     27,318      28,583        28,834       29,088       29,344       29,603       29,864       

State Street (HWY 89) 30,390       29,937        28,678      29,683     30,990      32,509        32,960       33,417       33,881       34,351       34,827       

University Ave (HWY 189) 30,948       30,414        30,561      29,470     31,092      32,874        33,195       33,519       33,847       34,177       34,511       

University Parkway 32,565       32,168        31,428      31,463     32,643      34,347        35,498       36,687       37,917       39,187       40,500       

Utah County, Remainder of 11,062       11,201        11,201      11,586     12,188      12,988        13,423       13,873       14,338       14,818       15,315       

Utah County 13,782       13,817        13,744      14,114     14,786      15,716        16,138       16,571       17,016       17,472       17,941       

ForecastEstimates

Page 90: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     90 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

9.1.2.2 ScreenLines

The screen line sum counts on all roads, not just diversion corridors, controlling for diversion 

onto smaller roads. The averaged AADT counts for screen lines are shown in Figure 9‐5 as a 

graph. A reference map of screen line locations is shown in Figure 9‐8. 

Figure 9‐5: Estimated AADT by Screen Line 2010—2015 

 

Page 91: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     91 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

The counts for screen lines and the rate of growth/decline in AADT over time is shown in Figure 

9‐6. The name of each screen line gives its approximate location. Numeric and percentage 

changes have been color‐coded to highlight significant changes. For numeric changes, a red‐

blue spectrum indicates the magnitude of changes; red is increase and blue is decrease. For 

percentage changes, data bars indicate magnitude of change; red is negative and green is 

positive.  

Figure 9‐6: Estimated AADT and Changes by Screen Line 2010‐2015 

 

Growth along the screen lines ranges from ‐0.4 percent to 3.0 percent. Traffic crossing the 

North‐South screen line across BYU declines. The screen line at Provo 1140 South (crossing both 

University Avenue and State Street) shows the largest percentage of growth. Numerically, the 

screen line at Provo 1800 South shows the largest charge, which is likely because it intersects 

both I‐15 and State Street.  

9.1.2.3 AutomaticSignalPerformanceMeasuresSystem

As mentioned previously, there were only 3 signals with data for 2015 and channels relevant for 

comparison with AADT segments. The totals for those intersections are shown in Figure 9‐7.  

Figure 9‐7: Traffic Signal Counts 

 

# % # %

Bluff 23,008     22,308   22,235     23,568    24,413  25,869     572              2.5% 627          2.6%

BYU Cordon 17,590     17,590   16,616     16,803    17,402  18,221     126              0.7% 79             0.8%

East‐West at about 1100 S. in Orem 21,696     21,147   20,427     21,661    22,461  23,884     438              2.0% 461          2.1%

East‐West at about 1140 S. in Provo 17,562     18,575   18,195     18,358    19,247  20,185     525              3.0% 437          2.9%

East‐West at about 1500 S.  In Orem 23,964     23,171   21,084     22,882    23,802  25,272     262              1.1% 292          1.2%

East‐West at about 1800 S. in Provo 61,080     58,543   58,073     60,503    62,810  66,623     1,109          1.8% 1,227       1.9%

East‐West at about 200 N. in Orem 26,633     25,771   25,996     24,532    25,442  27,049     83                0.3% (11)           0.3%

East‐West, across BYU Campus 19,631     20,487   19,781     19,511    20,102  21,029     280              1.4% 159          1.4%

East‐West, south of BYU campus 18,997     19,312   18,912     20,095    20,799  21,773     555              2.9% 558          2.9%

East of I‐15 in Orem 17,600     18,443   18,256     18,341    19,034  19,945     469              2.7% 388          2.6%

East of I‐15 in Provo 11,669     11,449   11,608     11,592    12,005  12,693     205              1.8% 193          1.8%

North‐South, across BYU Campus 15,066     14,446   14,003     13,653    13,803  14,783     (57)               ‐0.4% (106)         ‐0.4%

Changes 2010‐2015

Average Annual Linear Estimate201520142013201220112010Cutlines

North East South West

6315 Geneva Road   1000 South  12,280     NA 12,280     NA 12,280                                   

6402 University Avenue   East Bay Boulevard 33,110     7,085       33,110     NA 24,435                                   

6417 University Avenue   University Parkway  27,040     17,810    32,475     40,870        29,549                                   

North East South West

6315 Geneva Road   1000 South  6,244        4,972       5,965        5,490           30,193                                   

6402 University Avenue   East Bay Boulevard 26,622     7,094       29,828     8,721           45,748                                   

6417 University Avenue   University Parkway  20,887     16,537    17,909     13,086        43,027                                   

Street Crossstreet

AADT Leg Volumes

AverageCrossstreetStreetSignal

AADT Analogue Leg Volumes

All MovementsSignal

Page 92: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     92 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

While there are areas of agreement, the traffic signal counts differ significantly from AADT 

counts. This is likely because AADT counts are mid‐segment counts, while the traffic signal 

provides point counts.  As can be expected, signal counts are substantially lower, as they do not 

count vehicle movements that either begin or end on the AADT segment. For a segment with a 

high activity density, (jobs & homes) this can represent a large number of trips.  

There is also a geographic mis‐match issue. The AADT count for the segment signal 6315 is on 

extends from Orem Center Street to Orem 1200 South. The AADT count for the segment signal 

6401 is on extends from Provo 600 south to I‐15. The segment for signal 6417 is relatively small, 

but also has the highest activity density. Several of the intersection legs lack AADT counts; they 

have been labeled ‘NA’. 

9.1.3 DataLimitations

For traffic counts, the data source was UDOT’s Traffic Statistics109 webpage (a time‐series of 

traffic counts using a combination of permanent and spot counters). The differences between 

counts at different points are reconciled to form segment‐level counts. Spot counts occur on a 

three‐year cycle, and intermediary counts are interpolated from this data.110 The data requires 

processing and was not immediately available; 2015 data became available only in early 

February 2017. The data are available for all federal aid and state aid highways in the state of 

Utah. A major limitation is that the data set only tracks the largest roads and so cannot track 

diversion onto minor roads. 

Not all roads have counts for all years for two reasons. First, only roads with relatively high 

volumes are counted, and counts only begin when roads reach sufficient volumes. Second, 

routes change. The closure of Campus Drive divided the previous UDOT route into two sections 

that were renumbered as new routes. No counts were available for Campus Drive in 2015. 

9.1.3.1 Wavetronix

Apart from permanent count stations, roadway counts of AADT are performed only every third 

year. Consequently, additional data sources were sought to validate AADT counts. One of these 

suggests data sources were WaveTronix ‘sidefire’ traffic counters, located in both Orem and 

Provo. Shane Winters, Principal Engineer at Provo City, indicated that there is no historical data 

o the detectors, saying:   

                                                       

109 Utah Department of Transportation ‐ Traffic Statistics. (n.d.). Retrieved May 20, 2017, from https://www.udot.utah.gov/main/f?p=100:pg:0::::V,T:,507 110 Traffic counts near Saratoga Springs are uncertain due to construction and changing conditions.  

Page 93: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     93 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

“We are able to pull data from these devices, but only the data that can be stored on the 

device themselves.  Which is usually only a week or two at most of data storage, before 

it begins to over right itself. We currently don’t have any current (last few months) 

data.”111.…. “The data must be manually downloaded (as we currently do not have them, 

or are interested in purchasing the current Wavetronix software to automate the 

process)”… “When we need traffic data from these areas we will use these devices and 

manually download the data, but we haven’t needed traffic data from these areas from 

quite some time…..The data from these devices are stored on our TOC desktops… We 

replaced our TOC desktop computers in late 2015 and all the data went with the old 

computers as well as our Wavetronix software….the most recent data that was on the 

old computers was from 2009 and we didn't feel that data was necessary to keep”.112  

The detectors do exist, and despite construction, many are still operating. According to Shane 

Winters, “We do have about 26 (16‐20 that are actually working)”.113 It is recommended that future 

years of analysis reports should obtain and analyze this data. 

Orem, Utah, also has a Wavetronix system, but many of the sensors are not currently online. Current 

planning is to repair them, beginning in July 2017114.  The Orem network is integrated into the UDOT 

signal network.  

   

                                                       

111 Shane Winters, January. 3 2017, email. 112 Shane Winters, June. 1 2017, email. 113 Shane Winters, June. 1 2017, email. 114 Taylor Forbush, June 6, 2017, email. 

Page 94: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     94 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 9‐8: Map of Diversion Corridors and Screen Lines 

 

Page 95: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     95 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 9‐9: ‘Blood Vessel’ Map of 2015 AADT 

 

Page 96: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     96 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

9.2 Trip Generation by New Development 

This section covers the trips generated within the study area. All land uses within the study area 

were assigned an ITE trip generation code, and the number of trips each parcel produced was 

estimated. This is intended to provide an estimate of the total trips generated within the study 

area, in order to control for changes in traffic volumes in the study area.  

9.2.1 Methods&Data

The data used for land use was parcel‐level land use data provided by the Utah County 

Assessor. Each parcel was assigned a land use type from the ITE Trip Generation Manual. The 

assessor data does not differentiate between different types of commercial land uses. For 

several thousand parcels, an ITE land use code was assigned based on the inspection of aerial 

images and/or Google Street View. Total trips generated by parcels within the study area were 

estimated using the average trip‐generation rates published in the ITE Trip Generation Manual. 

The trip generation rates for each land use can be found in APPENDIX B.: ITE Trip Generation 

Rates. Trips were estimated per thousand square foot (PER_KSF), per dwelling unit (PER_DU), 

or per other unit (PER MISC). Vacant parcels use an invented ITE code of 1000. The average trip 

rate is “a weighted average of the number of trip ends,” with “trip end” referring to a one‐way 

movement from a point of origin to a point of destination.115  

9.2.2 Results&Discussion

Due to the large number of parcels, and large number of ITE codes for parcels within the study 

area, the resulting tables of trips are very large. Rather than present them here, a summary 

table of trip generation by 1‐digit land use type is presented in Figure 9‐10. The Land Use Class 

Code indicates the general three‐digit ITE code for the land uses in question and the related 

Land Use Class. Parcel Count indicates the number of parcels in each land use class. Total Trips 

is the sum of all trips for that land use class. The Acres column shows all acres for all parcels in 

each land use class. The Trips per Acre column provides a measure of the relative “density” of 

trip making by land use class. 

                                                       

115 ITE Technical Council Committee. (October 1976). Trip Generation. Traffic Engineering, 42‐47. Retrieved May 20, 2017, from https://nacto.org/docs/usdg/trip_generation_ite.pdf. 

Page 97: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     97 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 9‐10: Trip Generation Totals by Land Use Class 

   

While the number of trips is very large, so is the study area. The alignment is more than 10.5 

miles long, and the area in proximity thousands of acres. The majority of trips are generated by 

commercial land uses, both overall and on a trips‐per‐acre basis. Schools (high schools and 

universities) also generate a considerable number of trips. 

An estimation of trip ends within the study area cannot account for the total amount of traffic 

in a study corridor, which contains a substantial number of through trips generated by uses 

outside the study corridor. In the context of this study, the most important element is the 

change in the total magnitude of trips generated. As long as the same trip generation rates are 

applied in both the before and after land use data, the difference in trip generation should be 

accounted for.  

Figure 9‐11 shows a map of land uses using Land Based Classification Standard (LBCS),116 at the 

1‐digit level. As shown, the primary land use is residential with institutional uses a close second. 

Commercial uses situated along major roadways make up the majority of the remaining land 

area.  

9.2.3 DataLimitations

This study relies on trip generation rates from the 9th edition of the ITE Trip Generation Manual. 

The 9th edition included 5,500 data points spread over 172 different land uses.117 These rates 

have been assumed to be reasonable. However, ITE trip generation studies represent an 

accumulation of data going back decades. For some land uses, the trip generation rates have 

experienced substantial changes. ITE trip generation rates have been used without controlling 

                                                       

116 American Planning Association. (n.d.). Land Based Classification Standard. Retrieved May 20, 2017, from https://www.planning.org/lbcs/ 117 Institute of Transportation Engineers. (n.d.). Trip Generation Publications. Retrieved May 20, 2017, from http://www.ite.org/tripgeneration/trippubs.asp 

Land Use Class Code Land Use Class Parcel Count Total Trips Acres Trips per Acre

0 Rail Station 2                       899              14        66                      

100 Utilities 1,499              59                 878      0                        

200 Residential 10,852            132,717      2,283  58                      

400 Parks & Rec 16                    172,147      212      812                    

500 Schools 454                  342,406      1,612  212                    

600 Hospital 17                    22,984        75        307                    

800 Commercial 1,356              5,583,186  1,145  4,874                

Totals 14,196            6,254,398  6,219  1,006                

Page 98: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     98 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

for effects associated for mixed‐use development.118 At some point in the next few years, ITE is 

likely to publish a 10th edition of the manual, and trip generation rates for many land uses may 

change. However, for the purposes of consistency, the 9th edition trip generation rates will 

continue to be used in further analysis years.  

The Utah County Assessor data contains limited land use information. Within the study area, 

many parcels lack data and many parcels are missing data. Total number of units in apartment 

complexes were not counted; instead, a range was provided. Total number of units was 

estimated using the middle of the range of units provided. 

 

 

                                                       

118 Ewing, R., Greenwald, M., Zhang, M., & Walters, J. (September 2011). Traffic Generated by Mixed‐Use Developments—Six‐Region Study Using Consistent Built Environmental Measures. Journal of Urban Planning and Development, 137(3). Retrieved May 20, 2017, from http://ascelibrary.org/doi/abs/10.1061/(ASCE)UP.1943‐5444.0000068 

Page 99: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     99 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 9‐11: Map of Study Area Land Use 

 

Page 100: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     100 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

9.3 New Transportation Infrastructure 

The Mountainland Association of Government’s fiscally constrained transportation plan 

(“TransPlan”) calls for a series of improvements in the project area. They are shown in Figure 

9‐12. The projects are color‐coded by phase, and symbolical‐coded by type. Only Phase 1 

projects (colored red) are considered, as other phases are beyond the evaluation period. 

Figure 9‐12: Project Area Transportation Improvements119 

 

                                                       

119 Mountainland Association of Governments. (n.d.). TransPlan40 ‐ Regional Transportation Plan [2015‐2040 Plan for the Provo/Orem Metropolitan Area. Retrieved May 20, 2017, from http://mountainland.org/img/transportation/TransPlan40/TransPlan40.pdf 

Page 101: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     101 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Presently, there are two interchanges within the project area. Two new interchanges have been 

proposed for the project area: 

#51: Half HOV interchange 800 South Orem and  

#15: Full interchange 820 North Provo.  

The half HOV interchange would substantially improve access to UVU from both I‐15 and 

Wolverine Crossing. It would also provide a more direct route to UVU from the Orem 

Intermodal Center and FrontRunner station. This route would also be less congested by 

avoiding the I‐15/University Parkway interchange and associated University Parkway/Campus 

Drive intersections. While identified as a Phase 1 project, it is also identified as unfunded.  

The addition of a full interchange at 820 North in Provo can be expected to substantially affect 

travel patterns. The proposed interchange lies between the one at University Parkway in Orem 

and the one at Center Street in Provo.  

The planned Lakeview Parkway is a two‐ to four‐lane roadway running from Geneva 

Road/Orem 1400 South to I‐15/Provo 1860 South. The southern portion running east to west 

from I‐15 to Provo Municipal Airport is currently under construction. It is shown on the map as 

#16. It will affect traffic volumes on both Geneva Road and I‐15. 

Project #22 is the widening of University Parkway between 800 East in Orem and University 

Avenue in Provo. This project is part of the Provo‐Orem TRIP, and is currently underway. The 

additional roadway capacity should induce a triple convergence effect, and traffic volumes 

should be expected to increase. This increase will be contingent on Project #21, which is a 

planned grade‐separated intersection at State Street and University Parkway. Project #21 

should substantially increase capacity at that intersection, reducing congestion on both State 

Street (Highway 89) and University Parkway. Traffic that has already diverged to alternate 

routes and times will converge to these roads until the network again reaches equilibrium.  

Project #19 widens Provo 820 North from Geneva Road to University Avenue, from two lanes to 

four lanes. In combination with Project #15 (a new interchange) this will significantly alter the 

geography of accessibility for the area. It will provide a more direct route to BYU from I‐15, 

inducing drivers to divert from other routes. Provo 820 North becomes Provo 800 North, which 

is the southern boundary of BYU. It will be the most direct route for automobile traffic bound 

for both BYU and Utah Valley Hospital.  

Project #20 is planned to widen Provo Center Street from Geneva Road to Provo 1600 West. It 

is not expected to significantly affect traffic volumes along the diversion corridors. 

Page 102: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     102 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

9.4 Student Enrollment & Employment 

This section contains information about student enrollment and employment totals. It includes 

the sources of data, and the specific metrics used to measure enrollment and employment. It 

presents data for the 2011—2015 period.  

9.4.1 Methods&Data

There are several different metrics used to track enrollment. Full‐time students are enrolled in 

a course of study that will result in graduation in four years. The “headcount” metric is the total 

count of part‐time and full‐time students. “Full‐time equivalent” is an estimate of enrollment 

levels if the fractions of part‐time students were combined to be full‐time students. Enrollment 

totals throughout the year are not uniform. There is substantial attrition in student attendance 

over the course of year. The highest enrollment is in fall, then winter, then spring, then 

summer. The counts of students for the fall semester have been used, as representative of peak 

transportation demand. UVU enrollment data track enrollment by semester and were available 

from their metrics dashboard website.120 BYU enrollment data was drawn from a number of 

sources. Data from 2000‐2014 is the count of all‐day enrollment.121 Data for 2015 was drawn 

from the local news.122  

Employment is categorized by full‐time and part‐time employment. Secondary sources (such as 

the UVU Factbooks123) did not provide consistently categorized totals. Instead, the data was 

obtained from Human Resource Services at BYU,124 and Institutional Research & Information at 

UVU.125 These same sources also provided information on the amount of overlap between 

students and staff, suggesting an overlap of about 1,200 a year for BYU and an overlap of about 

500 for UVU.  

   

                                                       

120 Utah Valley University Institutional Research & Information. (n.d.). Retrieved May 20, 2017, from http://www.uvu.edu/iri/enrollment/student.html 121 Ashley Urquhart, Compensation Assistant, BYU. Retrieved: Jan 27, 2017 122 Johnson, S. (2015, September 16). BYU sees 17 percent increase in returned missionaries on campus. The Daily Herald. Retrieved May 20, 2017, from http://www.heraldextra.com/news/local/education/college/byu/byu‐sees‐percent‐increase‐in‐returned‐missionaries‐on‐campus/article_b1b69750‐7522‐5181‐9bb3‐7a3ce5b1328c.html 123 Utah Valley University Institutional Research & Information. (n.d.). Retrieved May 20, 2017, from http://www.uvu.edu/iri/additionalresources/annualreports.html 124 Ashley Urquhart, Compensation Assistant, BYU. Retrieved: Jan 27, 2017 125 Geoff Matthews, Associate Director – Institutional Research & Information, Utah Valley University

Page 103: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     103 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

 

9.4.2 Results&Discussion

A graph of student enrollment is shown in Figure 9‐13 for UVU and Figure 9‐14 for BYU. A table 

with full tabulation is shown in Figure 9‐15. Headcount refers to a count of all students; FTE 

refers to an aggregation of the total credit hours from all students to the equivalent load for 

full‐time students. 

Figure 9‐13: Student Headcount, FTE, and Full‐Time Students for UVU 

 

Figure 9‐14: Student Headcount, FTE, and Full‐Time Students for BYU 

 

Total student enrollment throughout the study period is largely flat for BYU. Total student 

enrollment at BYU has been capped for years. The decline in enrollment in both 2013 and 2014 

at BYU can be explained by a change in LDS policies regarding eligible ages of young adults 

serving an LDS religious mission. The ages of eligibility lowered was from 19 to 18 for males and 

from 21 to 19 for females. Historically, many young adults would take a year of university 

classes before leaving on a mission, but this change in policy indicates that many would‐be 

students are leaving immediately after graduating high school. While the effect may last several 

years, due to the cohort effect, it should vanish over time. 

 ‐

 10,000

 20,000

 30,000

 40,000

'00 '01 '02 '03 '04 '05 '06 '07 '08 '09 '10 '11 '12 '13 '14 '15

UVU Headcount UVU Full Time Equivalent UVU Full Time

 25,000

 27,000

 29,000

 31,000

 33,000

 35,000

'00 '01 '02 '03 '04 '05 '06 '07 '08 '09 '10 '11 '12 '13 '14 '15

BYU Headcount BYU Full Time Equivalent BYU Full Time

Page 104: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     104 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

UVU was also affected by this change in policy, but to a lesser degree. However, in contrast, 

UVU can be expected to see substantial increase in students in future years. In July, 2008, UVU 

converted from a State College (Utah Valley State College) to a full University. While it has 

experienced regular increases in enrollment prior to its conversion, enrollment increased 

significantly between 2007 and 2010. Further, UVU still has both the desire and land to 

substantially grow and develop its campus.  

Figure 9‐15: Student Headcount, Full‐Time Equivalent, and Full‐Time Students for BYU & UVU 

 

A graph of employment for both UVU and BYU, divided by part‐time and full‐time, is shown in 

Figure 9‐16. Tabular counts of employment by full and part time for BYU are shown in Figure 

9‐17. Tabular counts for UVU, for full and part time (as well as additional categories) is shown in 

Figure 9‐18. 

Headcount Full Time Equivalent Full Time Headcount  Full Time Equivalent  Full Time 

'00 32,554                 31,726                                         30,069           20,946                  13,504                                           10,892            

'01 32,771                 31,925                                         30,234           22,609                  15,163                                           11,757            

'02 32,408                 31,537                                         29,796           23,609                  16,261                                           12,277            

'03 33,008                 32,129                                         30,372           23,803                  16,312                                           12,378            

'04 33,427                 32,496                                         30,633           24,149                  16,339                                           12,557            

'05 32,920                 32,111                                         30,492           24,487                  16,081                                           12,733            

'06 32,679                 31,816                                         30,090           23,305                  15,662                                           12,119            

'07 32,964                 32,118                                         30,426           23,840                  16,135                                           12,397            

'08 32,992                 32,161                                         30,500           26,696                  17,910                                           13,882            

'09 32,955                 32,148                                         30,533           28,765                  19,670                                           14,958            

'10 32,947                 32,151                                         30,558           32,670                  21,825                                           16,988            

'11 32,980                 32,166                                         30,539           33,395                  22,448                                           17,200            

'12 33,336                 32,495                                         30,814           31,562                  21,616                                           16,745            

'13 30,243                 29,417                                         27,766           30,564                  20,697                                           15,755            

'14 29,672                 28,854                                         27,217           31,332                  21,335                                           16,296            

'15 32,615                 31,781                                         30,114           33,211                  22,592                                           17,214            

Year

BYU UVU

Page 105: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     105 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 9‐16: Full‐Time and Part‐Time Employment for UVU and BYU 2010‐2015 

 

Figure 9‐17: Full‐Time and Part‐Time Employment for BYU 

 

Category 2010 2011 2012 2013 2014 2015

BYU Full Time  Staff/Admin/Faculty 3,969            4,011            3,995            4,057            4,072           4,183           

BYU Part Time  Staff/Faculty 1,656            1,730            1,752            1,811            1,855           1,928           

Total Employees 5,625            5,741            5,747            5,868            5,927           6,111           

Page 106: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     106 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 9‐18: Full‐Time and Part‐Time Employment for UVU 

 

9.4.3 DataLimitations

Data does not track students who are part of online‐only or night school programs. The 

difference between full‐time and part‐time students in terms of trip chains is unknown ‐ some 

part‐time students only make the trip every other day, while other part‐time students may 

make multiple trips in one day. 

9.5 Land Development 

This section provides detailed information about land use change within the study area. 

Detecting land development relies on comparing parcels before and after the Provo‐Orem TRIP. 

This is accomplished by using data from the county assessor and satellite imagery to compare 

changes in land uses. Census geography also aids in detecting differences. 

9.5.1 Method&Data

The assessor's data includes a GIS shapefile containing the bounds of all parcels in the county as 

polygons, and a table of attributes describing aspects of each polygon. After selecting and 

excluding public right‐of‐way polygons from the data set, 14,236 polygons remained. Of these 

polygons, 8,345 had attribute data about the year buildings on each parcel were built. All 

parcels in the assessor’s records also contain a unique ID number, variously noted as SERNO or 

SERIAL. Based on that key, parcels from county assessor’s data from before the Provo‐Orem 

BRT can be matched to the same parcels in a dataset after operations begin. For new 

Employee Classification 2010 2011 2012 2013 2014 2015

Full Time

Executives 29                  31                  34                  34                  32                 33                 

Exempt Salaried Staff 553               585               601               601               616              681              

Faculty 519               553               582               576               590              642              

Nonexempt Salaried Staff 400               416               447               462               483              502              

Early Retiree 28                  26                  22                  20                  14                 13                 

Total Full‐Time 1,529            1,611            1,686            1,693            1,735           1,871           

Part Time

Adjunct/Overload Teaching 989               1,058            996               979               978              840              

Part‐Time Staff 746               689               714               726               808              793              

Student 950               1,033            1,041            1,028            1,192           1,235           

Work Study Student 254               273               175               130               133              181              

Stipend or Temporary Agreement 5                    7                    4                    2                    ‐               6                   

Public Service Instructors 38                  29                  ‐                56                  36                 218              

Total Hourly 2,982            3,089            2,930            2,921            3,147           3,273           

Total Employees 4,511            4,700            4,616            4,614            4,882           5,144           

Page 107: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     107 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

development, changes in the Year Built attribute field should detect new development. For 

rehabilitation, changes in the Improvement Value attribute field should detect changes.  

Changes in development can also be detected by comparing aerial/satellite images. Aerial 

images from 2011 were compared to aerial images from 2014. Overlaying the images in 

ArcMap at 50 percent transparency shows where the two aerial images contradict one another, 

making it simple to spot differences, such as the appearance of a new classroom building along 

College Drive at UVU. A shapefile of building footprints from 2011 aided in the comparison.  

The use of census geography to select parcels provides a control total. American Factfinder126 

releases data only for the tract level, but the TIGER/Line data releases selected demographic 

and economic data at the block level.127 Therefore, it is possible to compare Decennial Census 

block population with the five‐year American Community Survey (ACS) estimate. For the year 

2010, counts from blocks were aggregated to the block group level. From the ACS, TIGER/Line 

data was used with the field “B01003e1” used for population and “B25001e1” used for housing. 

9.5.2 Results&Discussion

Housing and population characteristics for the study area are shown in Figure 9‐19. A 

substantial amount of population resides in group quarters, such as dorms. The area is the area 

of census block groups, therefore the housing density and population density represent gross 

density in units‐per‐acre.  

Figure 9‐19: Study Area Population & Housing Units per Acre 

 

9.5.3 DataLimitations

A new version of the parcel file database is available on an annual basis. Not all data within the 

database are updated on an annual basis. A typical assessment cycle is three years. Comparison 

of certain fields, such as Year Built and Improvement Value, should make it possible to 

recognize most land use changes.  

                                                       

126 United States Census Bureau. (n.d.). American Fact finder. Retrieved May 20, 2017, from http://factfinder.census.gov/faces/nav/jsf/pages/index.xhtml 127 United States Census Bureau. (n.d.). TIGER/Line. Retrieved May 20, 2017, from https://www.census.gov/geo/maps‐data/data/tiger‐data.html 

Survey   Housing Units   Population  Housing 

Density 

Population 

Density  Acres 

 2010 Decennial Census  19,684 70,989 2.84 10.24 6,935

 2014 American Community Survey  19,330 67,761 2.79 9.77 6,936

Page 108: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     108 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

A large number of records lack data. The GIS shapefile of the study area contained about 14,600 

parcel polygons. After manually removing public right‐of‐way polygons from the data set, about 

14,000 polygons remained. Of these polygons, 8,345 had Year Built data. Many are sliver 

polygons, so database cleaning and data creation was necessary. Detecting some changes 

required inspection of aerial images, but aerial images were not available for all years. Aerial 

images from 2011 can be compared to aerial images from 2014, with another vintage likely to 

be available from state sources in 2017. For the years 2018 and 2019, recourse to Google Earth 

and ESRI aerial images is likely be required.  

The only timely form of census data is the American Community Survey, which uses a limited 

sample. Data are only released at the county level on an annual basis. Annual updates for 

smaller geographic units (tracts, block groups, blocks) rely on combining multiple years of 

sampling. Thus, for each year, only one fifth of the data is a new sample. American Factfinder128 

releases data only for the tract level, but the TIGER/Line data releases selected demographic 

and economic data at the block level.129 They are available in geodatabase format for 2013, 

2014, and 2015,130 and so can reasonably be expected to be available for future years, albeit on 

an estimated two‐year time lag (2015 data in 2017, 2017 data in 2019, etc.). 

   

                                                       

128 United States Census Bureau. (n.d.). American Fact finder. Retrieved May 20, 2017, from http://factfinder.census.gov/faces/nav/jsf/pages/index.xhtml 129 United States Census Bureau. (n.d.). TIGER/Line. Retrieved May 20, 2017, from https://www.census.gov/geo/maps‐data/data/tiger‐data.html 130 United States Census Bureau. (n.d.). TIGER Geodatabases. Retrieved May 20, 2017, from https://www.census.gov/geo/maps‐data/data/tiger‐geodatabases.html 

Page 109: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     109 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

9.6 Parking Supply & Occupancy 

This section discusses parking conditions. The data and methods sub‐section provides maps of 

parking locations for each university. It also details pricing and regulation. The results and 

discussion sub‐section provides information about the count of stalls, the count of occupied 

stalls, and occupied stalls by lot type.  

9.6.1 Methods&Data

For each campus, all known parking lots were located and traced in GIS as polygons. All 

automobile stalls were dotted for all parking lots. Additional points were included to represent 

parking garages. Figure 9‐20 shows an example of how the stalls were dotted. 

Figure 9‐20: Example of ‘Dotted’ Parking Stalls 

 

A copy of the file was made, and all points representing vacant spaces were deleted. This 

process was then repeated for different aerial images. Figure 9‐21 shows the type and location 

of parking lots at UVU, including both the lots on the main campus and the lots west of I‐15. 

Page 110: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     110 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 9‐21: UVU Parking Map 

 

Parking Lots at UVU are divided into five classes, with four classes of parking passes. Green lots 

are reserved for employees and are provided free of charge. Yellow lots are $90 a year or $60 a 

semester (as are disabled lots). The parking garage is $750 a year. The purple lot, the most 

distant, is a free lot. 

As of fall 2016, parking lots at BYU are divided into nine classes: Student, Graduate Student, 

Faculty/Staff, Restricted Visitor, Visitor, Timed, Motorcycle, Student Housing, and Free. 

Motorcycle parking has been disregarded for the purpose of this study. Prior to 2015, all 

parking was free on the BYU campus. Since 2015, the student and graduate lots require a pass, 

costing $60 per semester. Three outlying lots remain free. All student parking lots at BYU are 

outside the Campus Drive orbital ring road, and (barring two lots at 600 East and University 

Parkway) all student lots are on the periphery of the BYU campus, so that access to the core of 

campus requires between 1,600 and 3,200 feet of walking. The free lots are about 2,500 feet, 

4,000 feet, and 4,600 feet from the center of campus. Parking is also free during spring and 

summer terms. The parking map for BYU is shown in Figure 9‐22. 

Page 111: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     111 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 9‐22: Map of Parking at BYU, 2015 

 

Page 112: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     112 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

9.6.1.1 Data

Data on parking supply and availability were derived from aerial images. Four different sources 

of aerial imagery data were used: 

2016 National Agricultural Imagery Program 1 Meter Orthophotography 

Google Statewide Aerial Photography (~6” pixels) 

Microsoft Bing Maps Imagery Layer for ArcMap, hosted by ArcGIS Online 

ArcMap Basemap ‘World Imagery’, hosted by ArcGIS Online 

All of these sets of aerial images have different flaws and different virtues; this is typically 

trade‐off between recentness and resolution.  

Data from ArcMap World Image Data was initially used. While typically high resolution (6” or 1’ 

pixels) it is quite dated. Construction for BYU’s Campus Unification Project (2013‐2016) is not 

shown on the map. According to the meta‐data for the Arcmap World Image Data131: 

World Imagery provides one meter or better satellite and aerial imagery in many parts of 

the world and lower resolution satellite imagery worldwide…..The map features 0.3m 

resolution imagery in the continental United States and 0.6m resolution imagery in parts 

of Western Europe from Digital Globe. Recent 1m USDA NAIP imagery is available in 

select states of the US. 

Data from Bing Maps (also hosted by ArcGIS Online) was used to validate this map. While not 

data is provided, the state of construction of the BYU Heritage Halls suggests mid‐2012. 

Most image service provide a mosaic of images, with different time‐stamps at different 

resolution, with limited meta‐data. The NAIP data is a collected for a specific time and day, but 

at lower resolution that the other image services (1 meter vs 1’ or 6”). 

National Agricultural Imagery Program is color aerial photography typically collected 

ever 2 or 3 years in the middle of the summer. The resolution is usually 1 meter with a 

horizontal positional accuracy of 5 meters.132  

The NAIP aerial imagery for the western portion of UVU was obtained August 19, 2016 at about 

11:27; for the eastern portion, August 8, 2016 11:49 was the datestamp. For BYU, the imagery 

                                                       

131 Environmental Systems Research Institute (2017). World Imagery. Retrieved June 4, 2017, from http://www.arcgis.com/home/item.html?id=10df2279f9684e4a9f6a7f08febac2a9 132 Utah AGRC [Automated Geographic Reference Center]. (n.d.). Google Imagery Information. Retrieved June 4, 2017, from https://gis.utah.gov/data/aerial‐photography/ 132 Utah AGRC [Automated Geographic Reference Center]. ( 

Page 113: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     113 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

is from August 8, 2016 at 11:29. For UVU, this data falls just before the start of Fall Semester 

(August 22). For BYU, it falls just before the end of summer term (August 11th). While most 

current, 1m resolution is not always sufficient to differentiate a car from a small shed. 

The Google Imagery is much higher resolution than the NAIP imagery. With 6” pixels rather 

than 1 meter pixels, pixel density is effectively 36 times higher. However, it is a mosaic, with no 

meta‐data documenting year, day or date or the imagery. Like the NAIP imagery, the Google 

License was hosted by the AGRC133.  

AGRC owns a public sector license to Google's statewide 6" aerial photography. Contractors and partners may also qualify. The Google license is for color aerial photography, typically collected within 3 years, from the spring, summer or fall. The imagery is statewide. The resolution is 6 inch or better with a horizontal positional accuracy to achieve or exceed one meter (C90) in most areas without significant vertical relief. 134 

The dynamic layer file at the AGRC was used to count occupied parking stalls. The AGRC 

maintains and has made available an archived annual snapshot of the dynamic layer. For future 

counts, using the snapshot layer is recommended, as the dynamic layer changes over time, due 

to updates.  

The parking garages at BYU are typically 100% full during the peak hours135. The same was 

assumed for UVU. 

9.6.2 Results&Discussion

2016 National Agricultural Imagery Program 1 Meter Orthophotography 

Google Statewide Aerial Photography (~6” pixels) 

Microsoft Bing Maps Imagery Layer for ArcMap, hosted by ArcGIS Online 

ArcMap Basemap ‘World Imagery’, hosted by ArcGIS Online 

A summary of parking stalls available and occupancy is shown in Figure 9‐23. The count 

includes all stalls at any location for either university, and for all types of parking stalls 

(including those reserved for police or University Administration).  

                                                       

133 Utah AGRC [Automated Geographic Reference Center]. (n.d.). Google Imagery Information. Retrieved June 4, 2017, from https://gis.utah.gov/data/aerial‐photography/ 134 Utah AGRC [Automated Geographic Reference Center]. (n.d.). Google Imagery Information. Retrieved June 4, 2017, from https://gis.utah.gov/data/aerial‐photography/ 135 Bob Ross, BYU Facility Services, by email June 6, 2017. 

Page 114: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     114 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 9‐23: Parking Supply And Occupancy 

 

The four different aerial images yield different counts of stalls, reflecting differences in the 

vintage of aerial images. The same is true of occupied stalls, reflecting different conditions. ESRI 

and BING counts are generally very similar. Counts based on Google Earth are generally the 

highest. 

BYU has a significant housing program, with university owned housing consisting of the 

Helaman Halls, the Heritage Halls, Wyview, and Wymount Terrace. Helaman Halls has capacity 

for about 2,100 students.136 Heritage Halls have a capacity of about 2,400 students. Wymount 

Terrace has about 900 two and three bedroom units. Wyview was estimated to have about 

1,000 beds. Both the Helaman and Heritage Halls are within a walkable distance (about 2,000 

feet and 1,600 feet respectively) from the center of campus (the Harold B. Lee Library). The 

other BYU residence halls are more distant. They are a longer than comfortable walk (Wyview 

(average of 5,600 feet) and Wymount Terrace (average of 4,100 feet), and so many students 

drive. None of the residential parking is available for commuting students. UVU has no on‐

campus housing. 

Evidence suggests that both campuses have an abundant supply of parking. There are more 

than 40 lots to park in at UVU, and more than 100 at BYU of varying sizes. Patterns in parking 

occupancy suggest that students make efficient use of the parking stalls nearest to their 

destinations. The most central lots are filled first, then the nearest stalls in the outlying lots, and 

finally the far stalls in the outlying lots. This pattern (at UVU) is demonstrated in Figure 9‐24. 

                                                       

136 Omics International (n.d.). List of Brigham Young University Residence Halls. Retrieved from: http://research.omicsgroup.org/index.php/List_of_Brigham_Young_University_residence_halls. May 25, 2017. 

Type NAIP Google ESRI BING NAIP Google ESRI BING NAIP Google ESRI BING

BYU 17,213    16,583       17,785    18,012    7,488     8,203         6,185     6,037     44% 49% 35% 34%

Faculty/Staff 5,735      5307 6,112       5,955      3,693     3714 3,642     3,445     64% 70% 60% 58%

Student C 242          216 244          248          33           38 6             3             14% 18% 2% 1%

Field 577          617 649          670          75           160 41           47           13% 26% 6% 7%

Grad 751          1067 786          827          549         702 490         492         73% 66% 62% 59%

Housing 2,431      2444 2,501       2,775      803         1114 592         666         33% 46% 24% 24%

Police 35            36 36             38            27           28 26           26           77% 78% 72% 68%

Timed 123          92 123          137          47           73 35           21           38% 79% 28% 15%

Visitor 478          139 444          462          144         118 240         238         30% 85% 54% 52%

Student (Y) 6,841      6665 6,890       6,900      2,117     2256 1,113     1,099     31% 34% 16% 16%

UVU 7,896      8,306         7,405       7,509      1,770     3,824         2,152     2,067     22% 46% 29% 28%

Garage 458          458             ‐           ‐          458         458             ‐         ‐         100% 100% 0% 0%

Green 1,618      1964 1,687       1,568      764         956             1,018     841         47% 49% 60% 54%

Purple 1,344      697 1,343       695          50           30               104         14           4% 4% 8% 2%

Visitor 147          343 157          352          51           124             137         190         35% 36% 87% 54%

Yellow 4,329      4844 4,218       4,894      447         2,256         893         1,022     10% 47% 21% 21%

Stalls OccupiedUniversity % Occupied

Page 115: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     115 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 9‐24: Parking Occupancy Pattern 

 

Both Universities use a parking permit system that allows unlimited parking use, rather than a 

pay‐for‐service model that charges on an hourly basis. To some extent, this is a necessity due 

the large number of dispersed lots, which would otherwise require metering or a traffic gate 

and parking booth. Permit systems have two limitations: they provide no incentive for students 

to limit use of parking on a daily basis, and they provide an incentive to spend time searching 

for the best possible spot in an array of possibilities. At BYU, there are almost 60 locations 

available using an “A” parking permit. Searching for parking may be generating substantial 

congestion from vehicles circling for parking. Research suggests that in business districts, this 

search may represent as much as 20 percent of total traffic volume.137  

 

                                                       

137 Shoup, D. C. (2005). The high cost of free parking (Vol. 206). Chicago: Planners Press. 

Page 116: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     116 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

9.6.3 DataLimitations

Counts were estimated from aerial images. Historically, the state of Utah has obtained aerial 

images every few years. However, for 2015 and later years, imagery is being obtained through a 

contract with Google Imagery.138 Unlike a single aerial image, Google Imagery is a mosaic of 

images, with different scales displaying imagery from different dates and years. Hence, it is 

impossible have photos taken at consistent times of day and year for all parking lots. Using 

aerial imagery to count occupied stalls may understate the occupancy rate due to variation in 

time of day, and time of year. Tree cover may also bias the count. 

Aerial images are not real‐time. Historically, Google Imagery is between one and three years 

old.139 For a growing urban area, the imagery is likely updated more frequently than average, so 

an updated aerial photograph is estimated to be available every other year. Typically, the 

newer imagery is higher‐resolution photography, and the closest level of zoom should 

represent the most recent data. Correspondingly, different levels of zoom represent different 

time periods.  

There is substantial construction at both campuses. UVU has added new buildings and new 

parking lots in the past year. At BYU, the construction of new housing, new buildings, and the 

“Universe” project (which included the closure of part of Campus Drive) have caused 

substantial changes in parking availability on campus. Finally, since the parking count, BYU has 

begun charging for parking, so only the most peripheral lots remain free. This will likely have an 

effect on parking behavior. 

Ideally, to be most accurate, future counts should be done on‐site, during fall semester, on the 

same day of the week, and at a consistent time of the day. To do so would require counting 

about 24,000 parking stalls in over 150 occupied lots within a few hours on the same day. Due 

to the large number of stalls and lots, this was felt not to be feasible.  

   

                                                       

138 Utah AGRC [Automated Geographic Reference Center]. (n.d.). Google Imagery Information. Retrieved May 20, 2017, from https://gis.utah.gov/data/googleimagery/ 139 Google Maps. (n.d.). See 3D Images with Earth View. Retrieved May 20, 2017, from https://support.google.com/maps/answer/2789536?hl=en 

Page 117: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     117 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

9.7 Crash Rates within Study Area 

9.7.1 Methods&Data

Data on crashes was obtained from UDOT’s open data repository then mapped and symbolized 

for diversion corridors.140 The Crash Rate Score (2011—2013) was used as the most applicable 

measure. The Crash Rate Score was estimated using the following methodology. 

The Crash Rate Score indicates which road segments have the highest crash rate when 

compared to the statewide average crash rate for roadways of similar functional class and 

traffic volume. The crash rate is calculated from the most recent three years of data (2011—

2013), while statewide average crash rates reflect five years of data (2009—2013). Crash Rate 

Scores are reported on a 0 to 5 scale, with 5 representing the group of road segments with the 

highest ratio of actual crash rate vs statewide average crash rate (weighted by roadway center 

line miles).141  

Secondly, all crashes in Utah County were geocoded and then assigned to the nearest road 

segment to provide a count of crashes. Using the AADT and length of each segment, a Crash 

Rate Score was calculated for all roadway segments. The data was provided by Clancy Black at 

UDOT, in May 2016, for 2010—2015. The average crashes displayed are five‐year averages 

(2011—2015).  

9.7.2 Results&Discussion

The map of Crash Rate Score is presented in Figure 9‐25.The map shows which project 

segments are disproportionately dangerous compared to roads with similar functional classes 

and AADTs throughout Utah.  

The section of University Parkway intersecting I‐15 has the highest crash rate on BRT alignment. 

Starting in 2012, the area has been under construction, including signal work at the 

interchange, ramp reconstruction, and the addition of a continuous flow intersection at the 

intersection with Sandhill Drive, south of UVU.142  

                                                       

140 Utah Department of Transportation. (n.d.) Crash Rate Score. Retrieved July 6, 2016 from: http://udot.uplan.opendata.arcgis.com/datasets?q=Crashes 141 Utah Department of Transportation (2016). Open Data Guide. Retrieved July 6, 2016 from: 

http://www.arcgis.com/home/item.html?id=e2f0216b81b14fe0b41bfe628b6dbf9e 

142 Davidson, L. (2012, April 13). I‐15 rebuild shifts focus to interchange work. Salt Lake Tribune. Retrieved May 20, 2017, from http://archive.sltrib.com/story.php?ref=/sltrib/politics/53901609‐90/cfi‐close‐construction‐interchange.html.csp 

Page 118: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     118 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 9‐25: Map of Alignment and Diversion Corridor Crash Rates 

 

Page 119: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     119 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

The intersection of University Parkway with University Avenue and the intersection of 

University Avenue with 800 North in Provo are also likely crash hotspots. Two segments of the 

alignment have a high Crash Rate Score: University Parkway between Orem Main Street and 

Orem 800 East and University Avenue south of 800 North in Provo. The first is a major 

commercial corridor with a large number of access points, and the second passes through the 

Provo central business district (CBD). Both sections are slated for exclusive BRT lanes, replacing 

median turn lanes. Exclusive lanes typically involve a separation barrier, which eliminates a 

driver’s ability to make dangerous left turns across traffic. This, in turn, should improve safety. 

In Provo’s CBD, intersection density is high enough that the street grid could satisfy the demand 

for left turns at other intersections. Along University Parkway, alternate means of satisfying the 

demand for left turns should be explored.  

The count of actual crashes and the calculated Crash Rate Score for all roads in the project area, 

along with their expected Crash Rate Score based on their VMT and functional class, can be 

found in APPENDIX C.  Crash Locations. 

9.7.3 Data&MethodologyLimitations

Crash Rate Scores are based on analysis performed for 2009—2013. No update is currently 

pending. If UDOT does not update the Crash Score Rating, doing so independently will be 

necessary. Given the simplicity of the methodology, this is feasible. Doing so would require 

obtaining data on crashes at a statewide level, which is already collected. The Utah Motor 

Vehicle Crash Report is produced annually, as part of an ongoing reporting scheme mandated 

by both state and federal governments. It began decades ago, and seems likely to continue into 

the foreseeable future. The data has latitude‐longitude codes, but will need to be geocoded 

and then assigned to the relevant road. Only with an updated Crash Rate Score will it be 

possible to detect these types of changes on roads in the study area.  

Once this data has been collected, it will become possible to map the results, with one map for 

expected crash rates, one map with the actual average crashes per year, and one map with the 

deviance between them, including a metric to gauge the differences.  

With a calculated crash rate for all study years, additional and more rigorous analyses would be 

possible. It would be possible to conduct an analysis of variance (ANOVA) on the data inputs to 

the Crash Rate Score. A step beyond that would be a negative binomial model of the crashes, 

based on a variety of roadway, traffic, and weather conditions, which would have substantially 

greater predictive capacity. 

 

Page 120: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     120 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

10 Summary The Provo‐Orem BRT before and after study uses a quasi‐experimental design with a pre‐test 

and post‐test to determine the effect on traffic, development, safety, and air quality of the 

opening of the Provo‐Orem Bus Rapid Transit Project. This type of research design is known as a 

natural experiment. The intent of the Initial Conditions Report is to provide a complete and 

comprehensive account of the initial conditions along the BRT alignment. This will make it 

possible to compare conditions before and after the introduction of BRT service. 

The specific objectives are to measure changes in:  

Automobile traffic in the corridor between baseline and forecast conditions; 

Land uses along the corridor; 

Parking occupancy at the two universities; 

Transit ridership; and 

Other co‐benefits of reduced automobile traffic, such as reduced vehicle emissions and 

reduction in the number and severity of traffic collisions. 

Automobile traffic counts from UDOT AADT were validated with Automatic Traffic Signal 

Performance Measure counts. The initial conditions suggest that automobile traffic is flat on 

many corridors, but that total traffic on all parallel corridors, as measured by cut‐lines, is rising. 

The land use type of all parcels in the study area were identified. Each was assigned an ITE land 

use code. Trip generation was estimated using ITE trip‐generation data. The number of parking 

stalls available at each university was measured using multiple aerial imagery counts. A 

procedure to estimate vehicle emissions has been devised using Federal Air Quality 

measurement models (GREET and MOVES) and were used to estimate the volume of current 

emissions by type. Crashes are associated with road segments using latitude‐longitude point 

data of accident locations. 

This is the first report in a series, the “Before”’ report. In the years following the start of BRT 

operations, a series of “After” reports will be written. They will compare the conditions before 

and after the BRT began to affect transportation and land use conditions. One of the key 

elements of this report is documenting confounding or potentially confounding factors that 

could affect the later analyses. Subsequent reports will control for potentially confounding 

factors and offer conclusions on the changes in conditions caused by the Provo‐Orem BRT 

project.  

Page 121: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     121 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

   

PROVO-OREM TRANSPORTATION IMPROVEMENT PROJECT (TRIP) APPENDICES

Prepared for:

Utah Department of Transportation

Research Division

Submitted by:

University of Utah,

Metropolitan Research Center

Authored by:

Matthew M. Miller, Mercedes Beaudoin,

and Reid Ewing

Final Report -

June 2017

Report No. UT‐17.XX 

Page 122: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     122 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

11 APPENDIX A. LITERATURE REVIEW 11.1  Introduction 

The use of arterial Bus Rapid Transit (BRT) and BRT‐type systems is a relatively recent 

development in the United States, although there are several systems currently in operation 

and many more in the planning process (Perk et al. 2010). The literature on BRT is vast, yet a 

majority it focuses on operational performance, project implementation, or economic 

development components. Unfortunately, this means there is a large gap in the BRT literature 

regarding its effects on traffic safety, capacity, and congestion. Thus, this literature review uses 

peer‐reviewed articles, technical reports, and U.S. BRT case studies to provide an overview of 

the impacts of arterial BRT on safety, congestion, and traffic volumes. A majority of these BRT 

peer‐reviewed studies are conducted in Latin American and other developing countries. This 

review focuses on studies in North America. 

Several reports in the literature have stated that BRT provides benefits such as reduced crashes, 

illness, crime, and environmental pollutants that effect human health (Wright & Fjellstrom, 2003). 

Nevertheless, the topic of BRT traffic safety is nascent and undeveloped compared to 

traditional BRT literature focused on operational performance and project implementations (Hidalgo & Carrigan 2010); (CERTU 2009); (Levinson, Zimmerman, Clinger, & Gast, 2003). 

11.2  Bus Rapid Transit and Safety 

This section provides an overview of BRT crash types, a review of existent literature attempting 

to measure BRT’s effect on safety, and a brief description of the various design 

recommendations for BRT safety. The effects of BRT systems improving road safety remain 

unclear, as very few empirical studies test this and those that do provide mixed evidence (Vecino‐Ortiz & Hyder, 2015). 

11.2.1 BRT&TrafficCrashes

BRT systems have been pronounced to improve road safety for three reasons. First, BRTs 

organize transportation systems, reduce their motorization, and refurbish their surrounding 

infrastructure (Vecino‐Ortiz & Hyder, 2015). Second, BRTs typically separate buses from other 

vehicles and pedestrians, which not only helps to prevent contact but decreases the speed in 

mixed traffic (Vecino‐Ortiz & Hyder, 2015). Finally, BRTs improve fleet quality and typically provide 

transport drivers training (Cordeiro, Schipper, & Noriega, 2006; Vecino‐Ortiz & Hyder, 2015) Still, as 

arterial BRTs are not entirely separated from general traffic, crashes do occur (Nikitas & Karlsson, 

2015). Thee six most common BRT crash types (Duduta, Adriazola, Hidalgo, Lindau, & Jaffe, 2015) are 

identified in Figure 11‐1 

Page 123: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     123 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 11‐1: Common BRT Crashes 

Type of Crash  Description 

Pedestrians in the bus lane 

Pedestrians may cross through slow or stalled mixed traffic only to be struck by a bus travelling on a dedicated bus lane. Bus drivers also have little time to react as their view of pedestrians crossing through traffic is often obstructed by the vehicles on the road. This type of crash usually results in fatal injuries. 

Left turns across a bus lane 

This is one of the most common types of collision between buses and general traffic when median bus lanes are used. If left turns at intersections are not restricted or controlled, a vehicle when making a left turn cuts across the bus lane and can be struck by a bus going straight through the intersection. 

General traffic in bus lanes 

This is a common crash type when dedicated bus lanes are provided. The lack of a physical barrier between bus lanes and general traffic lanes can allow other vehicles to illegally enter the bus lanes and collide with buses. 

Crashes between buses and cyclists 

Cyclists sometimes use dedicated bus lanes, because they perceive them to be safer than mixed traffic lanes but can face serious injury when hit by fast moving buses. Cyclists sometimes also attempt evasive maneuvers into other lanes when buses approach, which may cause them to be hit by a vehicle from the opposite direction or lose control and hit the dividers. At curbside bus stops, buses merging into mixed traffic may potentially be dangerous to cyclists. 

Rear‐end collisions at a bus stop or station 

This occurs when a bus is lining up behind another bus at a station platform but is coming in too fast and collides with the bus in front. 

Crashes between buses at stations 

These crashes occur on multi‐lane busways with express lanes. Buses leaving the station and merging onto the express lane collide with buses in the express lane, either traveling through or attempting to access the station. A collision with an express bus is more severe as they travel at higher speeds. 

11.2.2 BRTLiteratureAttemptingtoMeasureSafety

While there have been claims that BRT systems improve road safety, the evidence of these 

claims has not been scientifically assessed. There is one notable exception(Vecino‐Ortiz & Hyder, 

2015); they conducted a literature search using a strict protocol that includes papers whose 

primary theme is BRT road safety, were peer‐reviewed, and that also presented quantitative 

empirical data. Their results: out of 879 entries, only four entries met the protocol and were 

Page 124: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     124 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

selected for evaluation: (Bocarejo et al., 2012) (Duduta, Adriazola, Hidalgo, Lindau, & Dos Santos, 2013), 

(Chun Keong Goh & Logan, n.d.), and (Duduta, Adriazola, Hidalgo, Lindau, & Jaffe, 2012). Most of the 

excluded literature either did not directly address the effect of BRT on road safety and/or did 

not provide data to empirically support such effects.  

Issues identified with these studies(Vecino‐Ortiz & Hyder, 2015):  

(1) the heterogeneity of BRT systems’ surrounding environments is seldom considered and 

therefore challenging to compare different BRT systems’ effects;  

(2) many cities which implement BRT concurrently invest in other road safety infrastructure 

and policies which implies unobserved actions may also affect reduced death rates; 

(3) many studies lack appropriate tools to infer causality with observational and non‐

experimental data, especially using before‐and‐after studies without bona fide 

counterfactuals; and 

(4) instead of empirical data, some BRT support is founded on modeling infrastructure 

changes which implies an urgent need for real world evaluations.  

While this research supports Vecino‐Ortize and Hyder’s (2015) conclusions, the authors want to 

identify another issue: no known comprehensive before‐and‐after studies have been conducted 

on the safety effects of arterial BRT systems in the U.S. context.  

After conducting our own literature review of peer‐reviewed articles and system‐specific 

technical reports, we found no U.S.‐oriented BRT systems analyzed for safety effects. In fact, 

few documents identify important safety measures (e.g., the number of crashes that occurred 

on the corridor prior to or after the BRT intervention. Figure 11‐2 provides an overview of the 

findings from these system‐specific reports.  

   

Page 125: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     125 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Figure 11‐2: Vecino‐Ortize and Hyder's review of BRT safety studies 

 

11.2.3 BRTDesignandSafety

BRT systems, if designed appropriately, can curtail adverse traffic and pedestrian impacts 

(Levinson et al., 2003); (Santos‐Reyes & Ávalos‐Bravo, 2014).While some claim or repeat others’ claims 

that a BRT system improves safety (Bocarejo et al., 2012); (Cervero, 2013);(Duduta et al., 2012); (Duduta et al., 2013); (Echevvery et al 2005); (Chun Keong Goh & Logan, n.d.); (Hidalgo & Yepes, 2005); (Hidalgo et al., 2012); 

(Singhal, Kamga, & Yazici, 2014) (Yazıcı, Ilıcalı, Camkesen, & Kamga, 2013) from a review (Vecino‐Ortiz & Hyder, 

2015) it is apparent that there is no systemic evidence of these claims. Even with their analysis, 

this section is used to briefly review the BRT system design elements that are considered to 

influence traffic, and pedestrian safety. 

Authors and 

DateMethod/Model

BRT System 

/LocationFindings

Vecino‐Ortize and Hyder’s (2015) 

critique/comment

Bocarejo et 

al., 2012

Before/after analysis of the road 

safety implications between 1998 

and 2008 using Geographic 

Information Systems (GIS)

Transmilenio/Ca

racas corridor in 

Bogota, 

Colombia

Mixed: The BRT was correlated to an 

overall reduction (60%) in traffic crashes 

along its corridor, yet crashes increased 

around some areas seemingly related to 

higher speeds in mixed traffic and more 

pedestrians around stations.

Given a before/after analysis was used with 

multiple confounders, in addition to the mixed 

findings, it cannot be concluded that the BRT 

caused road safety improvements.

Duduta et al., 

2012

Mixed‐methods including a 

before/after and regression count 

data analyses with crash data to 

evaluate the effect of BRT on road 

safety including road safety 

inspections and interviews with 

employees in nine BRT systems. On 

three of the systems, the authors 

conducted difference of means 

tests to estimate the changes in 

road crashes before and after the 

implementation of the study. 

Bogota 

(Colombia); 

Guadalajara 

(Mexico); Delhi 

(India)

BRT is correlated with a reduction in 

crashes, but not statistically significant. 

The safety benefits occurred from 

changes in street geometry (the debut 

of a BRT lane) which (a) reduced the 

number of legs at certain intersections, 

(b) reduced the number of lanes to 

accommodate stations, (c) restricted left 

turns, and (d) the central median 

shortened pedestrian crossings. In 

Bogota, fatalities decreased by 60 %. In 

Guadalajara, monthly crashes along the 

corridor decreased by nearly 50 %. 

However, in Delhi, traffic fatalities more 

than doubled after the BRT possibly due 

to increased pedestrian exposure to 

buses.

The variability of findings across the cities 

demonstrates there is no a “one‐fits‐all 

formula” for BRT systems.

Duduta et al., 

2013

Authors created a Bayesian model 

to retrospectively estimate crashes 

and injuries around BRT systems.

Macrobus, 

Guadalajara 

(Mexico)

The BRT reduced road crashes by 56 % 

over a period of three years.

One assumption of their model is that road 

safety changes are a direct function of the 

BRT system, therefore there was no empirical 

proof that those changes would not have 

happened regardless due to unobserved 

factors.

Goh et al., 

2013

Mixed‐methods: an analyses of 

aggregated data and a safety audit.

Melbourne, 

Australia

A 14 % reduction in road crashes in the 

city. The audit review also found 

negative qualitative impacts of the BRT 

such as more complex side street exits.

As the analyses were based on aggregated 

crash data and on before/after analyses, 

causal implications cannot be made as to the 

effect of BRT.

Page 126: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     126 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

BRT System Lanes: (Duduta et al., 2015) estimate that nine percent of all crashes occur in the BRT 

lanes, while the vast majority of traffic crashes occur in the general traffic lanes and do not 

involve buses at all. One of the worst designed lanes one could have for a BRT is a counter‐flow 

(meaning, going the opposite way as traffic) lane. Counter‐flow BRT lanes have been correlated 

with higher crash rates for both vehicles and pedestrians (Duduta et al., 2015); (Duduta et al., 2013);  

(Miller, 2009); (Vecino‐Ortiz & Hyder, 2015). Contrarily, center lane‐configurations for BRT systems 

have repeatedly been said to reduce collisions. Then again, (Miller, 2009) simply states that any 

fully grade‐separated, segregated BRT lane has highest level safety (among other 

characteristics—highest cost, reliability, etc.) of any BRT running way type. 

Intersections: (Duduta et al., 2015) found that size and complexity of intersections as well as road 

width are the most reliable predictors of crash frequencies along BRT corridors. The number of 

approaches per intersection, the number of lanes per approach, and the maximum pedestrian‐

crossing distance are some of the key factors that influence intersection safety. 

Pedestrian safety: Designing a safe BRT system not only involves its running ways, but its surrounding urban context including a city’s population. Pedestrians account for a majority of traffic fatalities long BRT corridors (Duduta et al., 2012), particularly when pedestrians attempt to cross the street and are struck by vehicles. Mid‐block signalized crossings and/or traffic calming measures have made positive safety impacts in other traffic studies (Diogenes & Lindau, 2010); (Duduta et al., 2012); (Duduta et al., 2013); (Elvik and Vaa, 2004) but have not been measured for BRT operations. Still, this reflects how the design of the walking environments around BRT systems are equally as important as BRT lanes and traffic intersections. In fact, some researchers (Wright 

& Fjellstrom, 2003) believe that smart design of dedicated pedestrian zones around BRTs can be mutually beneficial for both pedestrians and the BRT system. Crosswalks should reach median bus lanes, bus lanes should be positioned at signalized locations when possible, and all components should be designed to discourage errant crossings (Miller, 2009).    

Page 127: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     127 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

11.3 Bibliography 

Bocarejo, J. P., Velasquez, J. M., Díaz, C. A., Tafur, L. E., Bogotá, L., Bocarejo, J. P., … Tafur, L. E. (2012). Impact of Bus Rapid Transit Systems on Road Safety. Transportation Research Record: Journal of the Transportation Research Board, 2317, 1–7. https://doi.org/10.3141/2317‐01 

Cervero, R. (2013). Bus Rapid Transit (BRT): An Efficient and Competitive Mode of Public Transport. IURD Working Paper 2013‐01, (October), 1–36. Retrieved from http://escholarship.org/uc/item/4sn2f5wc.pdf 

Chun Keong Goh, K., & Logan, D. (n.d.). Investigating the Road Safety Impacts of Bus Priority Using Experimental Micro‐Simulation Modelling. TRB. Retrieved from http://docs.trb.org/prp/14‐1894.pdf 

Cordeiro, M., Schipper, L., & Noriega, D. (2006). Measuring the Invisible Quantifying Emissions Reductions. Queretaro case study. World Resources Institute, (March). Retrieved from http://www.wri.org/publication/measuring‐invisible‐1 

Diogenes, M., & Lindau, L. (2010). Evaluation of Pedestrian Safety at Midblock Crossings, Porto Alegre, Brazil. Transportation Research Record: Journal of the Transportation Research Board, 2193(2193), 37–43. https://doi.org/10.3141/2193‐05 

Duduta, N., Adriazola, C., Hidalgo, D., Lindau, L. A., & Dos Santos, P. M. (2013). The Relationship Between Safety , Capacity , and Operating Speed on Bus Rapid Transit Case Study : Transoeste Brt , Rio De Janeiro. In CONFERENCE (pp. 1–21). 

Duduta, N., Adriazola, C., Hidalgo, D., Lindau, L. A., & Jaffe, R. (2015). Traffic safety in surface public transport systems: a synthesis of research. Public Transport, 121–137. https://doi.org/10.1007/s12469‐014‐0087‐y 

Duduta, N., Adriazola, C., Hidalgo, D., Lindau, L., & Jaffe, R. (2012). Understanding Road Safety Impact of High‐Performance Bus Rapid Transit and Busway Design Features. Transportation Research Record: Journal of the Transportation Research Board, 2317, 8–14. https://doi.org/10.3141/2317‐02 

Levinson, H. S., Zimmerman, S., Clinger, J., & Gast, J. (2003). Bus Rapid Transit Synthesis of Case Studies. Transportation Research Record. 

Miller, M. A. (2009). Bus Lanes/Bus Rapid Transit Systems on Highways: Review of the Literature. REPORT. 

Nikitas, A., & Karlsson, M. (2015). A Worldwide State‐of‐the‐Art Analysis for Bus Rapid Transit: Looking for the Success Formula. Journal of Public Transportation, 18(1), 1–33. https://doi.org/10.5038/2375‐0901.18.1.3 

Santos‐Reyes, J., & Ávalos‐Bravo, V. (2014). A preliminary analysis of two Bus Rapid Transit 

Page 128: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     128 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

accidents in Mexico City. Procedia Engineering, 84, 624–633. https://doi.org/10.1016/j.proeng.2014.10.479 

Singhal, A., Kamga, C., & Yazici, A. (2014). Impact of weather on urban transit ridership. Transportation Research Part A: Policy and Practice, 69, 379–391. https://doi.org/10.1016/j.tra.2014.09.008 

Vecino‐Ortiz, A. I., & Hyder, A. A. (2015). Road Safety Effects of Bus Rapid Transit (BRT) Systems: a Call for Evidence. Journal of Urban Health, 92(5), 940–946. https://doi.org/10.1007/s11524‐015‐9975‐y 

Wright, L., & Fjellstrom, K. (2003). Sustainable Transport: A Sourcebook for Policy‐makers in Developing Cities. Module 3a: Mass Transit Options. Retrieved from https://trid.trb.org/view.aspx?id=788294 

Yazıcı, M. A., Ilıcalı, M., Camkesen, N., & Kamga, C. (2013). A Bus Rapid Transit Line Case Study : Istanbul’s Metrobus System. Journal of Public Transportation, 16(1), 153–177. https://doi.org/http://dx.doi.org/10.5038/2375‐0901.16.1.8 

   

Page 129: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     129 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

12 APPENDIX B.: ITE Trip Generation Rates ITE Code 

Description  Per_DU  PER_KSF  Per_Misc  Misc_Metric 

22  General Aviation Airport        1.97  Flight 

90  Park&Ride w/ Bus Service        4.5  Parking Space 

110  General Light Industrial       6.97       

120  General Heavy Industrial     1.5       

130  Industrial Park     6.83       

140  Manufacturing     3.82       

150  Warehousing     3.56       

151  Mini Warehouse        2.5       

160  Data Center     0.99       

170  Utilities     8       

210  Single Family Homes     9.52          

220  Apartment      6.65          

221  Low Rise Apartment  6.59          

222  High Rise Apartment  4.2          

223  Mid‐Rise Apartment  4.4          

230  Resd. Condo/Townhouse  5.81          

240  Mobile Home Park    4.99          

245  Student Housing  2.82          

251  Senior Adult Housing‐Detached  3.68          

252  Senior Housing‐ Attached  3.44          

253  Congregate Care Facility  2.02          

254  Assisted Living        2.74  Occ. Beds 

260  Recreational Homes  3.16          

310  Hotel        8.17  Rooms 

311  All Suites Hotel               4.9  Rooms 

312  Business Hotel        6.2  Occ. Room 

320  Motel               5.63  Rooms 

411  City Park        1.89  Acres 

430  Golf Course         35.74  Holes 

437  Bowling Alley         33.33  Lanes 

441  Live Theater        0.2  Seats 

444  Movie Theater w/ Matinee         267  Movie Screens 

465  Ice Rink         1.26  Seats 

495  Recreational Community Center     33.82       

520  Elementary School      15.43       

522  Middle/Jr. High School      13.78       

530  High School      12.89       

536  Private School (K‐12)           Students 

Page 130: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     130 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

ITE Code 

Description  Per_DU  PER_KSF  Per_Misc  Misc_Metric 

540  Junior/ Community College      27.49       

550  University/College         1.71  Students 

560  Church         9.11       

561  Synagogue      10.64       

565  Daycare Center         74.06       

580  Museum     6.6       

590  Library      56.24       

591  Lodge/Fraternal Organization          0.29  Members 

610  Hospital     6.95       

620  Nursing Home      7.6       

630  Clinic      31.45       

710  General Office          11.03       

715  Single Tenant Office Building     11.65       

731  State Motor Vehicles Department     166.02       

732  US Post Office      108.19       

733  Gov. Office Complex      27.92       

750  Office Park     11.42       

810  Tractor Supply Store     14       

811  Construction Equipment Rental Store     9.9       

812  Building Materials/Lumber       45.16       

813  Free‐Standing Discount Superstore     50.75       

815  Free‐Standing Discount Store     57.24       

817  Nursery (Garden Center)        68.1       

820  Shopping Center     42.7       

823  Factory Outlet Center      26.59       

826  Specialty Retail Center     44.32       

841  Automobile Sales     32.3       

842  Recreational Vehicle Sales     25.4       

843  Automobile Parts Sales     61.91       

848  Tire Store      24.87       

850  Supermarket       102.24       

853  Convenience Market w/Gas Pumps     845.6       

857  Discount Club       41.8       

861  Sporting Goods Superstore     18.4       

862  Home Improvement Store      30.74       

864  Toy/Children's Superstore     49.9       

866  Pet Supply Superstore     33.8       

867  Office Supply Superstore     34       

872  Bed and Linen Superstore     22.2       

876  Apparel Store      66.4       

Page 131: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     131 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

ITE Code 

Description  Per_DU  PER_KSF  Per_Misc  Misc_Metric 

880  Drugstore w/o Drive‐Thru     90.06       

881  Drugstore w/ Drive‐Thru     96.91       

887  Medical Equipment Store     6       

890  Furniture Store       5.06       

911  Walk‐in Bank        121.3       

912  Drive‐in Bank       148.15       

918  Hair Salon     19.3       

920  Copy, Print, and Express Ship Store     122.7       

931  Quality Restaurant        89.95       

932  High Turnover/Sit Down Rest     127.15       

933  Fast Food w/o Drive Thru      716       

934  Fast Food w/ Drive Thru      496.12       

937  Coffee/ Donut Shop w/ Drive Thru     818.58       

939 Bread/ Donut/ Bagel Shop w/o Drive Thru 

   702.2       

940 Bread/ Donut/ Bagel Shop w/ Drive Thru 

   386       

941  Quick Lube Shop         40  Service Bays 

942  Automobile Care Center      35.1       

943  Automobile Parts and Service Center     44.6       

944  Gasoline/Service Station           168.56  Fuel Position 

945 Service Station w/ Convenience Market  

      162.78  Fuel Position 

946 Service Station w/ Convenience Market and Carwash 

      152.84  Fuel Position 

947  Self‐Service Carwash        108  Stalls 

1000  Vacant  0  0       

 

   

Page 132: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     132 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

13 APPENDIX C. Crash Locations

Road Functional 

Class Total 

Crashes

 Average AADT  

Actual Crash Rates 

Expected Crash Rates 

Difference

1700 N via Sandhill Rd ‐ SR 265   Collector  0 1,837 0 2.68  ‐2.68

Jct SR 114 via Independence Blvd. 

 Collector  0 1,952 0 2.68  ‐2.68

SR 189 University Avenue via 3700 North 

 Collector  17 7,986 1.51 2.68  ‐1.17

SR 265 via 2100 W (Main St) ‐ 800 S Orem 

 Collector  5 3,625 2.1 2.68  ‐0.58

1460 North via 200 W Provo/2100 W Orem ‐ 2000 S Orem 

 Collector  10 4,580 1.44 2.68  ‐1.24

3650 N (Quail Valley Dr) ‐ 4525 North Street via Timpview Drive 

 Collector  1 798 1.53 2.68  ‐1.15

2200 North viaTimpview Drive (650 East) Provo 

 Collector  19 5,353 2.51 2.68  ‐0.17

Jct 600 South ‐ SR 114 via 2050 West 

 Collector  2 2,617 1.27 2.68  ‐1.41

Jct 200 West ‐ SR 89 via 600 South in Provo 

 Collector  6 3,645 1.55 2.68  ‐1.13

Center Street via 400 East Orem   Collector  11 6,197 3.24 2.68  0.56

800 South via 400 East Orem   Collector  17 4,454 3.45 2.68  0.77

Center Street via Orem Boulevard 

 Collector  17 8,292 3.6 2.68  0.92

1100 W via 200 N ‐ 700 E Provo   Collector  17 2,607 3.61 2.68  0.93

400 South via Orem Boulevard   Collector  27 9,515 4.8 2.68  2.12

800 South via Orem Boulevard   Collector  24 8,158 4.98 2.68  2.3

Jct SR 114 ‐ Carterville Road via 400 South in Orem 

 Collector  51 4,593 3.36 2.68  0.68

1860 South ‐ SR 189 via East Bay Boulevard 

 Collector  14 6,880 2.69 2.68  0.01

Grandview Lane via Columbia Lane ‐ SR 89 Orem 

 Collector  15 11,178 1.48 2.68  ‐1.2

SR 189 (University Ave) ‐ Freedom Blvd via 1230 N. Provo 

 Collector  111 17,981 6.2 2.68  3.52

450 E via Campus Dr ‐ Canyon Rd (150 E) Provo 

 Collector  28 16,786 3.54 2.68  0.86

700 North (Route 3030) via 700 East Provo 

 Collector  25 13,036 1.99 2.68  ‐0.69

300 South (SR 89) via 700 East Provo 

 Collector  16 4,929 3.26 2.68  0.58

4000 North Quail Valley Drive via Foothill Drive 

 Collector  7 3,002 1.84 2.68  ‐0.84

Page 133: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     133 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Road Functional 

Class Total 

Crashes

 Average AADT  

Actual Crash Rates 

Expected Crash Rates 

Difference

1700 N via Sandhill Rd ‐ SR 265   Collector  0 1,837 0 2.68  ‐2.68

Jct SR 114 via Independence Blvd. 

 Collector  0 1,952 0 2.68  ‐2.68

SR 189 University Avenue via 3700 North 

 Collector  17 7,986 1.51 2.68  ‐1.17

SR 265 via 2100 W (Main St) ‐ 800 S Orem 

 Collector  5 3,625 2.1 2.68  ‐0.58

1460 North via 200 W Provo/2100 W Orem ‐ 2000 S Orem 

 Collector  10 4,580 1.44 2.68  ‐1.24

3650 N (Quail Valley Dr) ‐ 4525 North Street via Timpview Drive 

 Collector  1 798 1.53 2.68  ‐1.15

2200 North viaTimpview Drive (650 East) Provo 

 Collector  19 5,353 2.51 2.68  ‐0.17

Jct 600 South ‐ SR 114 via 2050 West 

 Collector  2 2,617 1.27 2.68  ‐1.41

Jct 200 West ‐ SR 89 via 600 South in Provo 

 Collector  6 3,645 1.55 2.68  ‐1.13

Center Street via 400 East Orem   Collector  11 6,197 3.24 2.68  0.56

800 South via 400 East Orem   Collector  17 4,454 3.45 2.68  0.77

Center Street via Orem Boulevard 

 Collector  17 8,292 3.6 2.68  0.92

1100 W via 200 N ‐ 700 E Provo   Collector  17 2,607 3.61 2.68  0.93

900 East via Temple View Drive   Collector  12 1,850 2.74 2.68  0.06

400 South via 400 West Orem   Collector  21 7,996 2.4 2.68  ‐0.28

700 East via 700 North Provo   Collector  14 5,717 4.22 2.68  1.54

800 South via 400 West Orem   Collector  7 6,000 2.13 2.68  ‐0.55

SR 189 University Avenue via 700 North Provo 

 Collector  39 8,792 6.43 2.68  3.75

Jct Campus Drive ‐ 900 East via Heritage drive 

 Collector  0 1,837 0 2.68  ‐2.68

SR 265 University Parkway (BYU Diagonal) via 400 West 

 Collector  26 4,723 8.24 2.68  5.56

Seven Peaks Blvd. via 300 North Provo 

 Collector  0 1,932 0 2.68  ‐2.68

Jct 600 South ‐ 500 North via 900 West in Provo 

 Collector  12 2,755 3.98 2.68  1.3

Jct Campus Drive ‐ 1650 North via 450 East 

 Collector  1 9,650 0.45 2.68  ‐2.23

1600 West Provo at 1150 South   Collector  13 1,038 9.77 2.68  7.09

Columbia Lane via 1460 North Provo 

 Collector  30 11,836 2.86 2.68  0.18

Page 134: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     134 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Road Functional 

Class Total 

Crashes

 Average AADT  

Actual Crash Rates 

Expected Crash Rates 

Difference

1700 N via Sandhill Rd ‐ SR 265   Collector  0 1,837 0 2.68  ‐2.68

Jct SR 114 via Independence Blvd. 

 Collector  0 1,952 0 2.68  ‐2.68

SR 189 University Avenue via 3700 North 

 Collector  17 7,986 1.51 2.68  ‐1.17

SR 265 via 2100 W (Main St) ‐ 800 S Orem 

 Collector  5 3,625 2.1 2.68  ‐0.58

1460 North via 200 W Provo/2100 W Orem ‐ 2000 S Orem 

 Collector  10 4,580 1.44 2.68  ‐1.24

3650 N (Quail Valley Dr) ‐ 4525 North Street via Timpview Drive 

 Collector  1 798 1.53 2.68  ‐1.15

2200 North viaTimpview Drive (650 East) Provo 

 Collector  19 5,353 2.51 2.68  ‐0.17

Jct 600 South ‐ SR 114 via 2050 West 

 Collector  2 2,617 1.27 2.68  ‐1.41

Jct 200 West ‐ SR 89 via 600 South in Provo 

 Collector  6 3,645 1.55 2.68  ‐1.13

Center Street via 400 East Orem   Collector  11 6,197 3.24 2.68  0.56

800 South via 400 East Orem   Collector  17 4,454 3.45 2.68  0.77

Center Street via Orem Boulevard 

 Collector  17 8,292 3.6 2.68  0.92

1100 W via 200 N ‐ 700 E Provo   Collector  17 2,607 3.61 2.68  0.93

Main Street / 2100 West at 1460 North Provo 

 Collector  15 4,393 2.78 2.68  0.1

900 West ‐ 700 East via 500 North in Provo 

 Collector  53 9,082 3.63 2.68  0.95

900 East via Center Street   Collector  7 4,380 3.24 2.68  0.56

3110 West Road to Airport ‐ Geneva Road (SR 114) 

 Collector  8 5,075 1.52 2.68  ‐1.16

1150 South ‐ Center Street (SR 114) Provo via 1600 West 

 Collector  4 3,670 0.95 2.68  ‐1.73

2050 West ‐ 900 West via 600 South in Provo 

 Collector  6 918 5.58 2.68  2.9

SR 189 via 1860 South   Collector  23 3,316 2.45 2.68  ‐0.23

Center Street Provo at 3110 West 

 Collector  2 2,058 1.07 2.68  ‐1.61

Jct SR 114 ‐ Columbia Lane via 2000 South 

 Collector  19 2,217 4.06 2.68  1.38

SR 75 North Springville/Provo   Interstate  251 98,647 1.48 1.12  0.36

SR 189 University Avenue Provo   Interstate  199 90,245 0.91 1.12  ‐0.21

SR 265 BYU Diagonal/University Pkwy 

 Interstate  250 131,855 1.11 1.12  ‐0.01

Page 135: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     135 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Road Functional 

Class Total 

Crashes

 Average AADT  

Actual Crash Rates 

Expected Crash Rates 

Difference

1700 N via Sandhill Rd ‐ SR 265   Collector  0 1,837 0 2.68  ‐2.68

Jct SR 114 via Independence Blvd. 

 Collector  0 1,952 0 2.68  ‐2.68

SR 189 University Avenue via 3700 North 

 Collector  17 7,986 1.51 2.68  ‐1.17

SR 265 via 2100 W (Main St) ‐ 800 S Orem 

 Collector  5 3,625 2.1 2.68  ‐0.58

1460 North via 200 W Provo/2100 W Orem ‐ 2000 S Orem 

 Collector  10 4,580 1.44 2.68  ‐1.24

3650 N (Quail Valley Dr) ‐ 4525 North Street via Timpview Drive 

 Collector  1 798 1.53 2.68  ‐1.15

2200 North viaTimpview Drive (650 East) Provo 

 Collector  19 5,353 2.51 2.68  ‐0.17

Jct 600 South ‐ SR 114 via 2050 West 

 Collector  2 2,617 1.27 2.68  ‐1.41

Jct 200 West ‐ SR 89 via 600 South in Provo 

 Collector  6 3,645 1.55 2.68  ‐1.13

Center Street via 400 East Orem   Collector  11 6,197 3.24 2.68  0.56

800 South via 400 East Orem   Collector  17 4,454 3.45 2.68  0.77

Center Street via Orem Boulevard 

 Collector  17 8,292 3.6 2.68  0.92

1100 W via 200 N ‐ 700 E Provo   Collector  17 2,607 3.61 2.68  0.93

Orem Center Street   Interstate  179 129,177 1.27 1.12  0.15

SR 189 University Avenue Provo   Interstate  199 90,245 0.91 1.12  ‐0.21

SR 114 Provo Center Street   Interstate  448 104,198 1.14 1.12  0.02

Orem Center Street   Interstate  179 129,177 1.27 1.12  0.15

SR 75 North Springville/Provo   Interstate  251 98,647 1.48 1.12  0.36

SR 265 BYU Diagonal/University Pkwy 

 Interstate  250 131,855 1.11 1.12  ‐0.01

SR 114 Provo Center Street   Interstate  448 104,198 1.14 1.12  0.02

400 West Orem via 1200 South  Minor Arterial 

59 5,371 7.96 2.69  5.27

Carterville Rd via 3700 N (800 S) ‐ University Ave (SR 189) 

 Minor Arterial 

30 12,373 2.77 3.4  ‐0.63

SR 89 (State Street) via 800 South Orem 

 Minor Arterial 

75 14,970 4.58 3.4  1.18

400 West (Route 2958) via 800 South Orem 

 Minor Arterial 

57 8,643 7.09 2.69  4.4

800 West via 800 South Orem  Minor Arterial 

8 8,008 1.82 2.69  ‐0.87

1200 West (Route 2980) via 800 South Orem 

 Minor Arterial 

8 3,940 3.71 2.69  1.02

Page 136: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     136 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Road Functional 

Class Total 

Crashes

 Average AADT  

Actual Crash Rates 

Expected Crash Rates 

Difference

1700 N via Sandhill Rd ‐ SR 265   Collector  0 1,837 0 2.68  ‐2.68

Jct SR 114 via Independence Blvd. 

 Collector  0 1,952 0 2.68  ‐2.68

SR 189 University Avenue via 3700 North 

 Collector  17 7,986 1.51 2.68  ‐1.17

SR 265 via 2100 W (Main St) ‐ 800 S Orem 

 Collector  5 3,625 2.1 2.68  ‐0.58

1460 North via 200 W Provo/2100 W Orem ‐ 2000 S Orem 

 Collector  10 4,580 1.44 2.68  ‐1.24

3650 N (Quail Valley Dr) ‐ 4525 North Street via Timpview Drive 

 Collector  1 798 1.53 2.68  ‐1.15

2200 North viaTimpview Drive (650 East) Provo 

 Collector  19 5,353 2.51 2.68  ‐0.17

Jct 600 South ‐ SR 114 via 2050 West 

 Collector  2 2,617 1.27 2.68  ‐1.41

Jct 200 West ‐ SR 89 via 600 South in Provo 

 Collector  6 3,645 1.55 2.68  ‐1.13

Center Street via 400 East Orem   Collector  11 6,197 3.24 2.68  0.56

800 South via 400 East Orem   Collector  17 4,454 3.45 2.68  0.77

Center Street via Orem Boulevard 

 Collector  17 8,292 3.6 2.68  0.92

1100 W via 200 N ‐ 700 E Provo   Collector  17 2,607 3.61 2.68  0.93

1230 North via 200 West Provo  Minor Arterial 

42 10,165 4.34 3.4  0.94

500 North via 200 West Provo  Minor Arterial 

45 16,190 3.63 3.4  0.23

SR 89 300 South via 200 West Provo 

 Minor Arterial 

63 14,644 5.31 3.4  1.91

4525 North via Canyon Road ‐ SR 189 

 Minor Arterial 

4 3,367 1.09 2.69  ‐1.6

3650 North via Canyon Road  Minor Arterial 

14 5,462 3 2.69  0.31

1650 North via Canyon Road  Minor Arterial 

34 10,185 1.61 3.4  ‐1.79

University Avenue (SR 189) at 1100 North Provo 

 Minor Arterial 

28 9,728 4.53 2.69  1.84

920 South ‐ SR 89 300 South via 500 West 

 Minor Arterial 

5 7,603 1.09 2.69  ‐1.6

300 W via 4800 N ‐ University Ave (SR 189) Provo 

 Minor Arterial 

16 13,059 1.65 3.4  ‐1.75

800 East via Center Street Orem  Minor Arterial 

17 18,372 1.19 3.4  ‐2.21

Page 137: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     137 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Road Functional 

Class Total 

Crashes

 Average AADT  

Actual Crash Rates 

Expected Crash Rates 

Difference

1700 N via Sandhill Rd ‐ SR 265   Collector  0 1,837 0 2.68  ‐2.68

Jct SR 114 via Independence Blvd. 

 Collector  0 1,952 0 2.68  ‐2.68

SR 189 University Avenue via 3700 North 

 Collector  17 7,986 1.51 2.68  ‐1.17

SR 265 via 2100 W (Main St) ‐ 800 S Orem 

 Collector  5 3,625 2.1 2.68  ‐0.58

1460 North via 200 W Provo/2100 W Orem ‐ 2000 S Orem 

 Collector  10 4,580 1.44 2.68  ‐1.24

3650 N (Quail Valley Dr) ‐ 4525 North Street via Timpview Drive 

 Collector  1 798 1.53 2.68  ‐1.15

2200 North viaTimpview Drive (650 East) Provo 

 Collector  19 5,353 2.51 2.68  ‐0.17

Jct 600 South ‐ SR 114 via 2050 West 

 Collector  2 2,617 1.27 2.68  ‐1.41

Jct 200 West ‐ SR 89 via 600 South in Provo 

 Collector  6 3,645 1.55 2.68  ‐1.13

Center Street via 400 East Orem   Collector  11 6,197 3.24 2.68  0.56

800 South via 400 East Orem   Collector  17 4,454 3.45 2.68  0.77

Center Street via Orem Boulevard 

 Collector  17 8,292 3.6 2.68  0.92

1100 W via 200 N ‐ 700 E Provo   Collector  17 2,607 3.61 2.68  0.93

Orem Boulevard via Center Street Orem 

 Minor Arterial 

57 22,831 2.35 3.4  ‐1.05

SR 189 (University Avenue) at University Parkway (SR 265) 

 Minor Arterial 

67 15,278 4.88 3.4  1.48

Timpview Drive (650 East) via 2200 North 

 Minor Arterial 

62 14,632 3.69 3.4  0.29

1430 North Provo via 900 East  Minor Arterial 

64 23,713 3.12 3.4  ‐0.28

700 North Provo via 900 East  Minor Arterial 

76 22,775 4.48 3.4  1.08

Center Street Provo via 900 East  Minor Arterial 

41 17,272 3.39 3.4  ‐0.01

SR 89 at 900 East Provo  Minor Arterial 

6 10,332 0.9 3.4  ‐2.5

Center Street via 800 East Orem  Minor Arterial 

22 10,523 3.67 3.4  0.27

400 South via 800 East  Minor Arterial 

11 15,607 1.31 3.4  ‐2.09

500 West ‐ SR 189 via 920 South  Minor Arterial 

14 8,270 3.`51  2.69  0.82

Page 138: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     138 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Road Functional 

Class Total 

Crashes

 Average AADT  

Actual Crash Rates 

Expected Crash Rates 

Difference

1700 N via Sandhill Rd ‐ SR 265   Collector  0 1,837 0 2.68  ‐2.68

Jct SR 114 via Independence Blvd. 

 Collector  0 1,952 0 2.68  ‐2.68

SR 189 University Avenue via 3700 North 

 Collector  17 7,986 1.51 2.68  ‐1.17

SR 265 via 2100 W (Main St) ‐ 800 S Orem 

 Collector  5 3,625 2.1 2.68  ‐0.58

1460 North via 200 W Provo/2100 W Orem ‐ 2000 S Orem 

 Collector  10 4,580 1.44 2.68  ‐1.24

3650 N (Quail Valley Dr) ‐ 4525 North Street via Timpview Drive 

 Collector  1 798 1.53 2.68  ‐1.15

2200 North viaTimpview Drive (650 East) Provo 

 Collector  19 5,353 2.51 2.68  ‐0.17

Jct 600 South ‐ SR 114 via 2050 West 

 Collector  2 2,617 1.27 2.68  ‐1.41

Jct 200 West ‐ SR 89 via 600 South in Provo 

 Collector  6 3,645 1.55 2.68  ‐1.13

Center Street via 400 East Orem   Collector  11 6,197 3.24 2.68  0.56

800 South via 400 East Orem   Collector  17 4,454 3.45 2.68  0.77

Center Street via Orem Boulevard 

 Collector  17 8,292 3.6 2.68  0.92

1100 W via 200 N ‐ 700 E Provo   Collector  17 2,607 3.61 2.68  0.93

800 South via 800 East Orem  Minor Arterial 

17 15,407 2.02 3.4  ‐1.38

SR 265 University Parkway (BYU Diagonal) 

 Minor Arterial 

70 17,180 5.91 3.4  2.51

500 West (SR 89) via 800 North  Minor Arterial 

18 9,575 3.82 2.69  1.13

SR 114 at 820 North  Minor Arterial 

28 6,250 2.61 2.69  ‐0.08

SR 89 (500 West) at Center Street Provo 

 Minor Arterial 

76 11,213 4.87 3.4  1.47

SR 189 via 1860 South  Minor Arterial 

21 10,857 1.29 3.4  ‐2.11

Center Street Orem via 1200 West 

 Minor Arterial 

11 9,410 2.18 2.69  ‐0.51

400 South Orem via 1200 West  Minor Arterial 

27 12,730 3.87 3.4  0.47

800 South Orem at 1200 West 2980 turns North 

 Minor Arterial 

28 11,443 4.47 3.4  1.07

400 West via Center Street Orem  Principal Arterial 

123 27,530 7.7 3.92  3.78

Page 139: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     139 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Road Functional 

Class Total 

Crashes

 Average AADT  

Actual Crash Rates 

Expected Crash Rates 

Difference

1700 N via Sandhill Rd ‐ SR 265   Collector  0 1,837 0 2.68  ‐2.68

Jct SR 114 via Independence Blvd. 

 Collector  0 1,952 0 2.68  ‐2.68

SR 189 University Avenue via 3700 North 

 Collector  17 7,986 1.51 2.68  ‐1.17

SR 265 via 2100 W (Main St) ‐ 800 S Orem 

 Collector  5 3,625 2.1 2.68  ‐0.58

1460 North via 200 W Provo/2100 W Orem ‐ 2000 S Orem 

 Collector  10 4,580 1.44 2.68  ‐1.24

3650 N (Quail Valley Dr) ‐ 4525 North Street via Timpview Drive 

 Collector  1 798 1.53 2.68  ‐1.15

2200 North viaTimpview Drive (650 East) Provo 

 Collector  19 5,353 2.51 2.68  ‐0.17

Jct 600 South ‐ SR 114 via 2050 West 

 Collector  2 2,617 1.27 2.68  ‐1.41

Jct 200 West ‐ SR 89 via 600 South in Provo 

 Collector  6 3,645 1.55 2.68  ‐1.13

Center Street via 400 East Orem   Collector  11 6,197 3.24 2.68  0.56

800 South via 400 East Orem   Collector  17 4,454 3.45 2.68  0.77

Center Street via Orem Boulevard 

 Collector  17 8,292 3.6 2.68  0.92

1100 W via 200 N ‐ 700 E Provo   Collector  17 2,607 3.61 2.68  0.93

1200 West via Center Street Orem 

 Principal Arterial 

79 28,235 2.56 3.92  ‐1.36

SR 114 via Center Street Orem  Principal Arterial 

68 13,424 9.25 2.74  6.51

SR 89 500 West Provo  Principal Arterial 

119 28,702 3.57 3.92  ‐0.35

4200 North Provo  Principal Arterial 

44 26,548 2.52 3.92  ‐1.4

1860 South Provo  Principal Arterial 

61 22,110 1.81 3.92  ‐2.11

SR 265 BYU Diagonal/University Parkway Orem 

 Principal Arterial 

198 41,910 6.64 3.92  2.72

Center Street Orem  Principal Arterial 

38 15,753 2.16 2.74  ‐0.58

SR 114 Orem  Principal Arterial 

243 30,663 9.91 3.92  5.99

500 South via University Avenue  Principal Arterial 

274 29,979 7.07 3.92  3.15

SR 114 Center Street Provo via 500 West 

 Principal Arterial 

170 27,416 4.88 3.92  0.96

Page 140: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     140 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Road Functional 

Class Total 

Crashes

 Average AADT  

Actual Crash Rates 

Expected Crash Rates 

Difference

1700 N via Sandhill Rd ‐ SR 265   Collector  0 1,837 0 2.68  ‐2.68

Jct SR 114 via Independence Blvd. 

 Collector  0 1,952 0 2.68  ‐2.68

SR 189 University Avenue via 3700 North 

 Collector  17 7,986 1.51 2.68  ‐1.17

SR 265 via 2100 W (Main St) ‐ 800 S Orem 

 Collector  5 3,625 2.1 2.68  ‐0.58

1460 North via 200 W Provo/2100 W Orem ‐ 2000 S Orem 

 Collector  10 4,580 1.44 2.68  ‐1.24

3650 N (Quail Valley Dr) ‐ 4525 North Street via Timpview Drive 

 Collector  1 798 1.53 2.68  ‐1.15

2200 North viaTimpview Drive (650 East) Provo 

 Collector  19 5,353 2.51 2.68  ‐0.17

Jct 600 South ‐ SR 114 via 2050 West 

 Collector  2 2,617 1.27 2.68  ‐1.41

Jct 200 West ‐ SR 89 via 600 South in Provo 

 Collector  6 3,645 1.55 2.68  ‐1.13

Center Street via 400 East Orem   Collector  11 6,197 3.24 2.68  0.56

800 South via 400 East Orem   Collector  17 4,454 3.45 2.68  0.77

Center Street via Orem Boulevard 

 Collector  17 8,292 3.6 2.68  0.92

1100 W via 200 N ‐ 700 E Provo   Collector  17 2,607 3.61 2.68  0.93

800 East Orem via BYU Diagonal  Principal Arterial 

59 30,623 1.93 3.92  ‐1.99

2230 North Provo  Principal Arterial 

46 28,598 1.96 3.92  ‐1.96

820 North  Principal Arterial 

54 10,757 1.74 2.74  ‐1

I 15 via Center Street  Principal Arterial 

91 24,500 6.78 3.92  2.86

800 South Orem  Principal Arterial 

183 47,080 3.29 3.92  ‐0.63

800 North Provo  Principal Arterial 

277 33,049 9.81 3.92  5.89

3080 North Provo  Principal Arterial 

59 28,323 1.9 3.92  ‐2.02

1230 North Provo via 500 West  Principal Arterial 

387 40,170 4.78 3.92  0.86

550 West Orem  Principal Arterial 

30 35,775 1.13 3.92  ‐2.79

SR 265 1200 South Orem  Principal Arterial 

92 11,927 4.43 2.74  1.69

Page 141: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     141 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report  

Road Functional 

Class Total 

Crashes

 Average AADT  

Actual Crash Rates 

Expected Crash Rates 

Difference

1700 N via Sandhill Rd ‐ SR 265   Collector  0 1,837 0 2.68  ‐2.68

Jct SR 114 via Independence Blvd. 

 Collector  0 1,952 0 2.68  ‐2.68

SR 189 University Avenue via 3700 North 

 Collector  17 7,986 1.51 2.68  ‐1.17

SR 265 via 2100 W (Main St) ‐ 800 S Orem 

 Collector  5 3,625 2.1 2.68  ‐0.58

1460 North via 200 W Provo/2100 W Orem ‐ 2000 S Orem 

 Collector  10 4,580 1.44 2.68  ‐1.24

3650 N (Quail Valley Dr) ‐ 4525 North Street via Timpview Drive 

 Collector  1 798 1.53 2.68  ‐1.15

2200 North viaTimpview Drive (650 East) Provo 

 Collector  19 5,353 2.51 2.68  ‐0.17

Jct 600 South ‐ SR 114 via 2050 West 

 Collector  2 2,617 1.27 2.68  ‐1.41

Jct 200 West ‐ SR 89 via 600 South in Provo 

 Collector  6 3,645 1.55 2.68  ‐1.13

Center Street via 400 East Orem   Collector  11 6,197 3.24 2.68  0.56

800 South via 400 East Orem   Collector  17 4,454 3.45 2.68  0.77

Center Street via Orem Boulevard 

 Collector  17 8,292 3.6 2.68  0.92

1100 W via 200 N ‐ 700 E Provo   Collector  17 2,607 3.61 2.68  0.93

SR 75 (Road to Ironton)  Principal Arterial 

96 19,432 2.37 2.74  ‐0.37

2050 West (Geneva Road) SR 114 turns North 

 Principal Arterial 

24 9,710 3.05 2.74  0.31

I 15 University Ave  Principal Arterial 

133 30,263 2.77 3.92  ‐1.15

Center Street Orem via State Street 

 Principal Arterial 

228 43,935 4.43 3.92  0.51

SR 189 University Avenue via 300 South 

 Principal Arterial 

73 23,710 3.8 3.92  ‐0.12

Main Street Orem  Principal Arterial 

337 44,999 6.77 3.92  2.85

SR 265 University Parkway (BYU Diagonal) 

 Principal Arterial 

39 22,292 3.07 3.92  ‐0.85

4800 North Provo (Center Street Orem) 

 Principal Arterial 

52 20,623 2.13 3.92  ‐1.79

900 East Provo  Principal Arterial 

74 13,332 5.02 2.74  2.28

Sand Hill Road  Principal Arterial 

243 44,117 5.19 3.92  1.27

Page 142: BRT Before and After Study - University of Utahmrc.cap.utah.edu/wp-content/uploads/sites/8/2015/...Provo/Orem BRT Before and After Study: Initial Conditions Report Matthew M. Miller,

                     142 of 142 

______________________________________________________________________________ Provo/Orem BRT                         Before and After Study: Initial Conditions Report