Brownfields RLF Webinar Series:

Davis-Bacon ActJanuary 24, 2013

Speakers:Joe Ferrari – EPA Region 1

Kate O’Hara – Land of Sky Regional Council, NCLaura Clark – Cuyahoga County Department of

Development, OH

Page 2: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

2

Topics

• Background• Davis Bacon Related Acts• Cleanup Activities Subject to DBA• Petroleum Cleanups• Laborers and Mechanics• Site of the Work• Davis Bacon Process• Federal, RLF Recipient & Borrower/Subgrantee Roles• Contractor /Subcontractor Roles• Jobsite Postings, Forms & Interviews• Additional Resources

Page 3: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

3

Background

• Enacted in 1931 and amended in 1935 & 1964.• Applies to Federal construction contracts over

$2,000.• The Act is “site-based”.• Covers alteration, repair, painting & decorating

activities.• Applies to laborers & mechanics.• Requires payment of prevailing wages.• Requires weekly payment of wages.

Page 4: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

4

Davis-Bacon Related Acts

• Davis-Bacon requirements extend to numerous “Related Acts” that provide federal assistance:

Grants/Cooperative AgreementsLoans & SubgrantsLoan guaranteesInsurance

Page 5: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

5

Cleanup Activities Subject to DBA

• Excavation of Contaminated Soils• Construction of Caps and Barriers• Construction of structures to house treatment

equipment• Abatement of Contamination in Buildings

(Some Exceptions)• Demolition (if followed by new construction)• Installing Water Supply

Wells/Piping/Connections

Page 6: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

6

Petroleum Cleanups

• Unless followed by paving or concrete replacement, the following petroleum cleanup actions generally don’t trigger DBA:

Tank removal In situ remediationSoil excavation/replacementSite assessment activities

Page 7: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

7

Laborers and Mechanics

• Defined as workers whose duties are manual or physical in nature.

• Includes Apprentices, Trainees and Helpers• Job types not covered:

Supervisory position at the job site

(<20% time in skilled labor) ClericalProfessionalsVolunteers

Page 8: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

8

Site of the Work

• Davis-Bacon applies only to laborers and mechanics employed “directly upon the site of the work.”

• Site of the work is:

Physical place remediation occursOther site where significant portion

of remediation occurs

Page 9: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

9

Davis-Bacon Process

• Cleanup Planning - Prevent labor and budget problems, set up protocols to ensure compliance

• Cleanup Period - Follow posting, payroll, and monitoring protocols

• Post Cleanup - Document payroll and certifications, and retain records

Page 10: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

10

Planning Step #1

• Refer to the terms and conditions of your cooperative agreement.

• Identify if DBA applies to your remediation tasks.

• Identify the project State and County.

Page 11: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

11

Planning Step #2

• Construction TypesResidential – houses, townhouses, and apartments

up to 4 storiesBuilding – most other structures and apartments

over 4 storiesHighway - roadways, sidewalks, parking areas, etc.Heavy - other projects, generally public works

• Most Brownfields cleanups will be classified as “Heavy” except for asbestos or lead paint removal which would most likely be classified as “Building”.

Page 12: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

12

Planning Step #3

• Obtain Wage Determinations – Available at http://www.wdol.gov Wage Determinations online

Specific to geographic area (county or a group of counties)

Specific to 4 types of construction: Residential, Building, Highway, Heavy

Modified periodically

Include in bid documents and contract for construction

Page 13: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

13

Planning Step #4

• All bid/contract documents for prime contractors and all applicable subcontractors must contain:Applicable Davis-Bacon Wage DeterminationFederal labor standards clausesEPA Davis-Bacon T&Cs

• Once the contracts are awarded, the Davis-Bacon wage rates are “locked” and stay in effect for the duration of the project.

Page 14: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

14

Federal Government Role

• EPA - Responsible for enforcement of Davis-Bacon and Davis-Bacon related acts for your RLF.

• DOL – Establishes regulations and investigates compliance.

Page 15: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

15

RLF Recipient Role

• Conduct onsite interviews with laborers and mechanicsWithin 2 weeks of initial and final payrolls.

• Conduct spot-check payrolls/related records Within 2 weeks of initial and final payrolls.

• Report potential violations.

• Maintain full documentation (3 years).

• Grant recipients may request exceptions to the frequency of payroll spot checks and interviews.

Page 16: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

16

Borrower/Subgrantee Role

• Obtain wage determinations from DOL.

• Ensure all bid/contract documents contain wage determination and labor provisions (prime and subcontractors).

• Ensure no contracts are awarded to ineligible contractors.

• Ensure submission of certified payrolls.

Page 17: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

17

Prime Contractor Role

• Prepares and submits certified payrolls for its own employees.

• Submits certified payrolls for all subcontractor employees.

• Reviews wage determination and requests additional classifications when needed.

• Provides subcontractors with forms and guidance concerning Davis-Bacon requirements.

• Provides Davis-Bacon Poster and interviewer confidential access to employees on site.

• Instructs lower-tier subcontractors of their responsibilities.

Page 18: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

18

Subcontractor Role

• Prepares & submits certified payrolls each week for its own employees.

• Instructs any lower-tier subcontractors of responsibilities.

• Reviews wage determination and requests additional classifications if needed.

• Provides Davis-Bacon Poster and interviewer confidential access to employees on-site.

Page 19: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

19

If Federal and State Wages Apply

• Contract must contain both Federal and State wage decisions/contract standards.

• Employers must pay higher of two rates.

• Payrolls must carry Federal statement of compliance (reverse of payroll form WH-347).

Page 20: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

20

Job Site Postings

• Notice to All Employees (WH1321)

• Protected from elements• Accessible to all laborers

and mechanics• Easy for all parties to see

Page 21: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

21

Job Site Postings

• Davis-Bacon wage decision OR Project Wage Rate Sheet

• Protected from elements• Accessible to all laborers

and mechanics• Easy for all parties to see• Prepared after wage

decision locked in

Page 22: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

22

Certified Payroll

• Optional form WH 347, Payroll • Compliance statement (w/original signature of

corporate official or designee)• Payrolls required weekly • Identify first and final payroll • Prime contractor reviews

prior to submission• Payroll retention = 3 years

Page 23: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

23

Interviews

• Perform on-site verification interviews with workers

• Use SF 1445 to document interviews

• Conduct within 2 weeks after start of work and 2 weeks prior to scheduled end of work

Page 24: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

24

Common Problems

• Misclassification of laborers and mechanics.

• Failure to pay full prevailing wage, including fringe benefits, for all hours worked (including overtime).

• Inadequate recordkeeping.

• Failure to submit certified weekly payrolls.

• Failure to post the Davis-Bacon poster and applicable wage determination.

Page 25: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

25

Tips

• Make sure your RLF funded cleanup contracts are separate from your redevelopment contracts.

• When in doubt, check it out at www.dol.gov .

• Ask your EPA Project Officer for help if you are not sure what to do.

• Get your environmental professional to help you.

Page 26: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

26

Additional Resources

• EPA Davis-Bacon Regional Coordinators: Region 1 - Ms. Valerie Marshall 617-918-1674  [email protected]

Region 2 - Mr. Anthony Tao 212-637-3372 [email protected]

Region 3 - Ms. Lorraine Fleury 215-814-2341 [email protected]

Region 4 - Ms. Dorothy Rayfield 404-562-9278 [email protected]

Region 5 - Ms. Sharon Green 312-353-5661  [email protected]

Region 6 - Mr. Dannell Brown 214-665-7279  [email protected]

Region 7 - Ms. Lee A. Thomas 913-551-7739 [email protected]

Region 8 - Ms. Maria Houston 303-312-7022  [email protected]

Region 9 - Mr. Joe Ochab 415-972-3761 [email protected]

Region 10 - Ms. Socorro Rodriguez 206-553-6296  [email protected]

Headquarters – Ms. Julie Milazzo 415-972-3687 [email protected]

Brownfields Program - Debi Morey 202-566-2735 [email protected]

Page 27: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

27

Additional Resources

• EPA Administrative and Davis-Bacon Cooperative Agreement Terms and Conditions > www.epa.gov/ogd/tc.htm

• DOL Davis-Bacon Fact Sheet > www.dol.gov/esa/whd/regs/compliance/whdfs66.pdf

• General Davis-Bacon Act requirements and applicability > www.dol.gov/compliance/laws/comp-dbra.htm

• Wage determinations on line > www.wdol.gov/

• Selecting a wage determination > www.wdol.gov/dba.aspx#0

• Wage rate posting requirements > www.dol.gov/esa/whd/programs/dbra/wh1321.htm

Page 28: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

28

Additional Resources

• Performing a review of certified payrolls > http://www.dol.gov/esa/whd/forms/wh347.pdf

• Conducting labor interviews > http://contacts.gsa.gov/webforms.nsf/0/12BF5D0E2DC4484685256CBC0062F375/$file/sf1445.pdf

• Davis-Bacon Reference Material > http://www.gpo.gov/davisbacon/referencemat.html

• Prevailing Wage Resource Book > http://www.dol.gov/esa/whd/recovery/pwrb/toc.htm

Page 29: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

29

Questions?

Page 30: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

Davis Bacon ComplianceGrantee Tips

EPA Brownfields Webinar SeriesJanuary 24, 2013

Page 31: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

Who are we?The Regional Brownfields Initiative (RBI) provides :Technical and financial assistance to prospective developers for Phase I & Phase II assessments.Low interest loans to non-causative developers for remediation of Brownfields (soil, groundwater, lead paint, asbestos).Subgrants to local municipalities and non-profits; andWe serve four counties & their 19 municipalities in western North Carolina for assessment assistance.We serve all areas west of I-77 in North Carolina for RLF projects*

Page 32: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

Grantee Responsibilities Designate appropriate staff. Ensure that bid documents, contracts, and

subcontracts contain labor standard provisions & the applicable wage decision.

Ensure that no work is awarded to an ineligible (debarred) contractor.

Conduct onsite interviews. Review payroll reports. Maintain good documentation. Follow up with contractor on issues; follow DB

guidance for complex issues.

Page 33: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

Working with Sub-grantees

Local governments & non-profits Often inexperienced or understaffed Grantee may need to help! Time charged to loan or grant

operations** check with your PO

Page 34: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

Check to make sure remediation contractor is eligible:

The General Services Administration discontinued the Excluded Parties List System on November 21, 2012. Exclusions can now be found at www.sam.gov.

• System for Awards Management

Davis Bacon Quick Guide

Page 35: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

www.sam.govRegister for an AccountSelect User Name & PasswordOnce registered: Search Records by:•DUNS Number (nine-digit identification number provided by the commercial company Dun & Bradstreet (D&B)

•Business Name•CAGE Code (used by Feds)

Page 36: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

Sample Contractor Approval Letter

“Upon the Brownfields cleanup award recommendation made by Dudley Doright PE, I ran a check on Tigermix, Inc. on the System for Awards Management (SAM). SAM is the Internet web site which lists contractors who are debarred from dealing with the federal government (or being paid by federal funds). As shown on the attached printout from the search I made, Tigermix, Inc. has a clean record on SAM. Therefore, I concur with Mr. Doright’s recommendation to award the contract to Tigermix, Inc. “

Attach printout to letter

Page 37: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

• Debarment: SAMPLE FORM

Federal Executive Order (E.O.) 12549 “Debarment and Suspension” requires that all contractors receiving individual awards, using federal funds, and all sub recipients certify that the organization and its principals are not debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded by any Federal department or agency from doing business with the Federal Government.

Your signature certifies that neither you nor your principal is presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded by any Federal department or agency.

• Name• Company• Address • Phone/ Fax • Email• Signature, Date

Page 38: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

Get wage rates at: http://www.wdol.gov/dba.aspx

Click on most recent dates & print.

Give a copy of rates & other DB language to your Engineer or Qualified Environmental Professional to include in cleanup specs.

Payroll, debarment and other forms are available through the Dept. of Labor website:

www.dol.gov

Page 39: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

Enter State Enter County Enter Type of Construction from

dropdown menu Most BF projects are “Heavy” Lead & Asbestos are “Building” **

Page 40: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

Davis Bacon & Your Contractor

If necessary, conduct a preconstruction meeting to go over Davis Bacon regulations.

Provide the wages poster- DB DavisBacon and Related Acts Poster for the worksite.

Forms & instructions available at DOL website. Payroll forms can be filled in & submitted

electronically. DB applies to subcontractors too.

Page 41: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

Conducting Employee Interviews• Conduct interviews regularly, or if there are new people working on site- (new employees or subcontractor); individual agency requirements may vary. SF- 1445 Labor Standards Interview

• Interview employees performing different jobs (truck driver, laborer, equipment operator).

• Interview form can be translated into Spanish/other; ask employee to read & fill out or ask another employee to help.

Page 42: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

Wage Verification & Documentation

• Check employee interview answers regarding number of hours worked & hourly rate against wage determinations &

contractor payroll.• Identify discrepancies or violations & make corrections;• Refer potential criminal or complex investigations to

EPA/DOL;• Prepare & submit Labor Standards Enforcement Report

to DOL as required (29 CRF Part 5 §5.7);• Maintain full documentation.

Page 43: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

General Tips• Ask contractors to submit payroll directly to

you.• Withhold payment if no payroll is received.• Verify payroll often.• Don’t count on QEP to conduct interviews.• If possible, show your subgrantee how to

perform these tasks.• Questions? Contact your PO or EPA DB

Regional Coordinator.

Page 44: Brownfields RLF Webinar Series: Davis-Bacon Act January 24, 2013 Speakers: Joe Ferrari – EPA Region 1 Kate OHara – Land of Sky Regional Council, NC Laura

For more information on Davis Bacon:“Making Davis Bacon Work: A Practical Guide for State, Indian Tribes and Local Agencies” available at:

ftp://ftp.epa.gov/r8/brownfields/2009_National_RLF_Meeting/

Kate O'HaraSenior Planner/Brownfields Project ManagerLand of Sky Regional Council339 New Leicester Highway, Suite 140 Asheville, NC 28806828-251-6622828-251-7454 (direct)  828-251-6353 (fax) www.landofsky.org