Monday, January 13, 2020

Broadway Improvement Project Update Meeting

Page 2: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

One of 35 roadway improvement projects included in the Regional Transportation Authority (RTA) Plan Approved by Pima County voters in 2006

Page 3: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

Meeting Overview

Here is the layout for today’s meeting

Brief Presentation

Please visit the tables for more information after the presentation

Page 4: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

Thank You to theCitizens Task Force Members

Neighbor Interests - NW Colby Henley, Rincon Heights NA (Historic District)

Neighbor Interests - NE Mary Durham-Pflibsen, Sam Hughes NA (Historic District), CTF Chairperson

Neighbor Interests - SE Shirley Papuga, Broadmoor-Broadway Village NA

Neighbor Interests - SW Michael J. “Jamey” Sumner, Miles NA

Business Interests - North Anthony R. DiGrazia, Rocco’s Little Chicago

Business Interests - North Bruce Fairchild, Bruce’s Lock Shop, CTF Vice Chairperson

Business Interests - South Diane Robles, Child & Family Resources, Inc.

Citizens Transportation Advisory Committee (CTAC) - Dale Calvert, CPA

Tucson Pima County Bicycle Advisory Committee - Anne Padias, PhD

Tucson Planning Commission - Shannon McBride-Olsen

Special Needs - Jon Howe, PhD, Sam Hughes NA

Regional Interests (RTA appointment) - Michael Butterbrodt, Inglis Florists

Business Interests - South Bob Belman, Arizona Auto Refrigeration(deceased)

Page 5: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

Total amount of funds allocated is $71.3 million Approximately $42 million provided by the RTA $25 million from the 1997 Pima County

Transportation Bond Improvement Plan $3 million from the City of Tucson

Project Funding

Page 6: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

Six (6) Lanes Medians Bike Lanes Sidewalks

Bus Pullouts Improved Drainage HAWK Crossings Public Art

Broadway Corridor – Project Elements

Page 7: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

Six Lanes

Page 8: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

Medians

Page 9: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

Bike Lanes

Page 10: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

Sidewalks

Page 11: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

Bus Pullouts

Page 12: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

Improved Drainage

Page 13: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

HAWK CrossingsHAWK beacon (High-Intensity Activated crossWalK beacon)

Total of 4 HAWK Crossings along the project: Park Avenue Cherry Avenue Norris Avenue Treat Avenue

Page 14: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

Public ArtDirk Arnold

Page 15: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

Construction Schedule

Construction is scheduled to begin late January 2020 The project will take approximately 20 months to complete Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained throughout

construction

Page 16: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

Project Start – Traffic shifted to north side of roadway (approximately 2 months to complete) in order to build the temporary detour on the south side – Euclid to Campbell

After temporary detour along the south side of roadway is built, traffic will shift to south side of roadway from Euclid to Campbell while storm drain is installed

East half of project from Campbell to Country Club will stay on north side of roadway while water line is installed

Side Street closures will occur as work progresses through the project limits

Upcoming Construction Activities

Page 17: Broadway Improvement Project Update Meeting · Access to residents and businesses along Broadway will be maintained At least one lane of traffic in each direction will be maintained

Thank you for coming!Broadway: Euclid to Country Club Improvement Project