46
BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Embed Size (px)

Citation preview

Page 1: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

BRIDGE CONSTRUCTION INSPECTOR

Practice Questions

Next

Page 2: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

1.

a) 29 cyb) 58 cyc) 71 cyd) 102 cy

An 8 ft. diameter drilled shaft has a tip elevation of 197 ft. With a top elevation of 235 ft., what is the theoretical quantity of concrete for this shaft?

Page 3: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

1. An 8 ft. diameter drilled shaft has a tip elevation of 197 ft. With a top elevation of 235 ft., what is the theoretical quantity of concrete for this shaft?

CORRECT!CORRECT!

Next

Page 4: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

1. An 8 ft. diameter drilled shaft has a tip elevation of 197 ft. With a top elevation of 235 ft., what is the theoretical quantity of concrete for this shaft?

INCORRECT! The correct answer is “C,” 71 cy.

Next

Page 5: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

2. Air entrained concrete is highly resistant to the destructive effects of freeze-thaw cycling due to the presence of large air bubbles in the paste.

a) Trueb) False

Page 6: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

2. Air entrained concrete is highly resistant to the destructive effects of freeze-thaw cycling due to the presence of large air bubbles in the paste.

CORRECT!CORRECT!

Next

Page 7: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

2. Air entrained concrete is highly resistant to the destructive effects of freeze-thaw cycling due to the presence of large air bubbles in the paste.

INCORRECT! The correct answer is “False.”

Next

Page 8: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

3.

a) 54 cyb) 78 cyc) 92 cyd) 133 cy

A footing is 8 ft. wide by 13 ft. long. The bottom of the footing is at elevation 211.00 and the original ground is at elevation 225.00. The finish grade of the deck is 235.00. What is the amount of structure excavation?

Page 9: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

3. A footing is 8 ft. wide by 13 ft. long. The bottom of the footing is at elevation 211.00 and the original ground is at elevation 225.00. The finish grade of the deck is 235.00. What is the amount of structure excavation?

CORRECT!CORRECT!

Next

Page 10: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

3. A footing is 8 ft. wide by 13 ft. long. The bottom of the footing is at elevation 211.00 and the original ground is at elevation 225.00. The finish grade of the deck is 235.00. What is the amount of structure excavation?

INCORRECT! The correct answer is “B,” 78 cy.

Next

Page 11: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

4. The vibrator should not be used to move concrete laterally.

a) Trueb) False

Page 12: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

4. The vibrator should not be used to move concrete laterally.

CORRECT!CORRECT!

Next

Page 13: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

4. The vibrator should not be used to move concrete laterally.

INCORRECT! The correct answer is “True.”

Next

Page 14: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

5.

a) Not worry about wind as it will help to cool the concrete surface.

b) Assure that the curing water is as cold as possible.

c) Take appropriate steps to lower the mix temperature when it approaches 90°F.

d) Use clear/white plastic as part of the cure process.

During hot weather concrete placement, the inspector should

Page 15: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

5. During hot weather concrete placement, the inspector should

CORRECT!CORRECT!

Next

Page 16: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

5. During hot weather concrete placement, the inspector should

INCORRECT! The correct answer is “D,” use clear/white

plastic as part of the cure process.

Next

Page 17: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

6. For footings and seals, the bottom elevation shown on the plans serves as the lower pay limit. Should the contractor over excavate below that limit or should the need arise to excavate below that limit to attain the necessary bearing value, the situation must be corrected in a manner that the construction Project Manager must approve.a) True

b) False

Page 18: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

6. For footings and seals, the bottom elevation shown on the plans serves as the lower pay limit. Should the contractor over excavate below that limit or should the need arise to excavate below that limit to attain the necessary bearing value, the situation must be corrected in a manner that the construction Project Manager must approve.CORRECT!CORRECT!

Next

Page 19: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

6. For footings and seals, the bottom elevation shown on the plans serves as the lower pay limit. Should the contractor over excavate below that limit or should the need arise to excavate below that limit to attain the necessary bearing value, the situation must be corrected in a manner that the construction Project Manager must approve.INCORRECT!

The correct answer is “True.”

Next

Page 20: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

7.

a) Must be near the surface to reduce deflection.b) Must start out on firm but yielding material.c) Is of no particular importance in the bridge’s

stability.d) Relies on structural design, not mass.

A bridge foundation must bear the weight of traffic and the considerable weight of the structure itself. Therefore, its foundation

Page 21: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

7. A bridge foundation must bear the weight of traffic and the considerable weight of the structure itself. Therefore, its foundation

CORRECT!CORRECT!

Next

Page 22: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

7. A bridge foundation must bear the weight of traffic and the considerable weight of the structure itself. Therefore, its foundation

INCORRECT! The correct answer is “D,” relies on structural

design, not mass.

Next

Page 23: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

a) Need not be concerned with levelness of materials encountered at the bottom of seal excavation.

b) Should never feel responsible for monitoring the positioning of the internal supports for the sheet pile walls.

c) Should arbitrarily lessen the seal depth if hard rock is encountered while excavating for the bottom of seal elevation.

d) None of the above.

8. When excavating inside a cofferdam, the Bridge Construction Inspector

Page 24: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

8. When excavating inside a cofferdam, the Bridge Construction Inspector

CORRECT!CORRECT!

Next

Page 25: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

8. When excavating inside a cofferdam, the Bridge Construction Inspector

INCORRECT! The correct answer is “D,” none of the above.

Next

Page 26: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

9.

a) Is critical to a bridge’s load bearing strength.

b) Must be closely checked for specified lap splice lengths, support and wire tie accuracy.

c) Must be closely checked for size, shape, length, spacing and quantity used.

d) All of the above.

Reinforcing steel in piers and abutments

Page 27: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

9. Reinforcing steel in piers and abutments

CORRECT!CORRECT!

Next

Page 28: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

9. Reinforcing steel in piers and abutments

INCORRECT! The correct answer is “D,” all of the above.

Next

Page 29: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

10. When placing concrete as part of a bridge’s superstructure, the concrete should not be allowed to drop more than 4 feet.

a) Trueb) False

Page 30: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

10. When placing concrete as part of a bridge’s superstructure, the concrete should not be allowed to drop more than 4 feet.

CORRECT!CORRECT!

Next

Page 31: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

10. When placing concrete as part of a bridge’s superstructure, the concrete should not be allowed to drop more than 4 feet.

INCORRECT! The correct answer is “False.”

Next

Page 32: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

11.

a) 1/3 turnb) 1/2 turnc) 2/3 turnd) 1 full turn

A ½ inch High Strength Bolt that is 4 inches long and installed perpendicular to the connection has a turn requirement in the Rotational Capacity Test of

Page 33: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

11. A ½ inch High Strength Bolt that is 4 inches long and installed perpendicular to the connection has a turn requirement in the Rotational Capacity Test of

CORRECT!CORRECT!

Next

Page 34: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

11. A ½ inch High Strength Bolt that is 4 inches long and installed perpendicular to the connection has a turn requirement in the Rotational Capacity Test of

INCORRECT! The correct answer is “B,” 1/2 turn.

Next

Page 35: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

12.

a) 6”b) 12”c) 18”d) None of the above

The granular wall backfill under an impact panel should be placed in ______ lifts.

Page 36: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

12. The granular wall backfill under an impact panel should be placed in ______ lifts.

CORRECT!CORRECT!

Next

Page 37: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

12. The granular wall backfill under an impact panel should be placed in ______ lifts.

INCORRECT! The correct answer is “D,” none of the above.

Next

Page 38: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

13.

a) 2”b) 2½”c) 3½”d) 4½”

Your bridge has precast bulb-I girders with a camber of 2½” and the deck and rail deadload together has a deflection of 2”. The top flange of the bulb-I girders is a total of 2 feet wide and your superelvation is 0.04 ft/ft. With a minimum buildup required across the entire girder of 1”, then the total buildup at the ends of the beams at the girder centerline will be ______.

Page 39: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

13. Your bridge has precast bulb-I girders with a camber of 2½” and the deck and rail deadload together has a deflection of 2”. The top flange of the bulb-I girders is a total of 2 feet wide and your superelvation is 0.04 ft/ft. With a minimum buildup required across the entire girder of 1”, then the total buildup at the ends of the beams at the girder centerline will be ______.

CORRECT!CORRECT!

2”

Next

Page 40: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

13. Your bridge has precast bulb-I girders with a camber of 2½” and the deck and rail deadload together has a deflection of 2”. The top flange of the bulb-I girders is a total of 2 feet wide and your superelvation is 0.04 ft/ft. With a minimum buildup required across the entire girder of 1”, then the total buildup at the ends of the beams at the girder centerline will be ______.

INCORRECT! The correct answer is “A,” 2 inches.

Next

Page 41: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

14.

a) 5b) 6c) 7d) 9

You have a 6 ft. diameter drilled shaft with a clearance of 3” from the reinforcement cage to the side of the shaft. How many spacers are required at each interval around the drilled shaft reinforcement cage?

Page 42: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

14. You have a 6 ft. diameter drilled shaft with a clearance of 3” from the reinforcement cage to the side of the shaft. How many spacers are required at each interval around the drilled shaft reinforcement cage?

CORRECT!CORRECT!

Next

Page 43: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

14. You have a 6 ft. diameter drilled shaft with a clearance of 3” from the reinforcement cage to the side of the shaft. How many spacers are required at each interval around the drilled shaft reinforcement cage?

INCORRECT! The correct answer is “C,” 7.

Next

Page 44: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

c) 109.4%d) 121.5%

15.

a) 103.4%b) 107.3%

You have a post-tensioned box girder bridge that will have the tendons tensioned from both ends. Given the following elongation amounts, what is the % of elongation per tendon?

20% Actual Elongation

100% Actual Elongation

Calculated 80% Elongation

Bent 1

7 ¼ 65 ¾ 54 ½

Bent 4

0 6 7/8 5 ¼

Page 45: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

15. You have a post-tensioned box girder bridge that will have the tendons tensioned from both ends. Given the following elongation amounts, what is the % of elongation per tendon?

20% Actual Elongation

100% Actual Elongation

Calculated 80% Elongation

Bent 1

7 ¼ 65 ¾ 54 ½

Bent 4

0 6 7/8 5 ¼

CORRECT!CORRECT!

Next

Page 46: BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next

Bridge InspectorPractice Questions

15. You have a post-tensioned box girder bridge that will have the tendons tensioned from both ends. Given the following elongation amounts, what is the % of elongation per tendon?

20% Actual Elongation

100% Actual Elongation

Calculated 80% Elongation

Bent 1

7 ¼ 65 ¾ 54 ½

Bent 4

0 6 7/8 5 ¼

INCORRECT! The correct answer is “C,” 109.4%.

Next