62
Brian Perry Civil Diaphragm &Secant Pile Walls by Nick Wharmby

Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Brian Perry Civil

Diaphragm &Secant Pile Walls

by

Nick Wharmby

Page 2: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Focus of the Presentation

• Diaphragm Walls

• Secant Piles

PonsonbyBusway

Page 3: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Wall Options / SelectionWall Type Sheetpile Wall Secant Piles Wall

(Hard / Firm)

Cutter SoilMix Wall

(Steel beams)

Slurry Wall

(steel beams or precast panels)

Diaphragm Wall

(In-situ or Precast Concrete)

Aspect

Technology Proven in NZ Proven in NZ Site trial required in NZ Proven in NZ Proven

Specialist plant Widely available in NZ Available in NZ Available offshore Readily available Readily available

Environment - Noise Yes, unless Giken or similar Machine only Machine only Machine only Machine only

- Vibration Yes, unless Giken or similar No No No No

- Spoil No 100% 30 - 40% 100% 100%

Construction - Establishment Cranes, vibros and hammers and / or pile jacking plant (Giken)

50-60T self erecting hydraulic drilling rigs and handling crane.

90T CSM machine, handling crane, 15m

3/hr grout plant with screw feed

silos, compressor, high pressure pumps

60T crane + grab, handling crane, long-reach excavator. 15m

3/hr grout

plant with screw feed silos

60T crane + grab, handling crane, mud conditioning plant, mud storage

- Material to site Sheet piles Concrete, reinforcement cages Cement, bentonite, steel Cement, bentonite, steel or precast concrete panels

Bentonite, reinforcement cages or precast concrete panels

- Work face access Plant & Materials delivery Plant & Materials delivery Plant, materials and pipeline delivery of grout

Plant, materials and pipeline delivery of slurry

Plant, materials and pipelines for bentonite mud circulation

- Programme flexibility Can easily increase the number of rigs to accelerate Significant further mobilisation Can easily increase the number of rigs to accelerate

Product - Wall movement Flexible Very stiff Stiff (depends on steel section) Stiff (depends on steel section)

Very stiff (PC Panels)

Very stiff

- Watertightness Good with joint treatment Satisfactory but some seepage Satisfactory but some seepage Good due to total replacement with low permeability CB slurry

Excellent with waterbar across panel joints

- Connections Welded below capping beam level Drilled & grouted bars + waterstop Welded below capping beam level, bending moment possible

Welded below capping beam level, bending moment possible

Full moment & shear connection via box-out and pull-out bars

- Durability Internal painting and sacrificial thickness of steel

Conventional concrete in the ground design. Internal lining for long-term seepage

sacrificial thickness of steel and internal lining wall for ground water

PC panels would negate sacrificial thickness of steel and internal lining wall

Conventional concrete in the ground design. No internal lining necessary

- Load capacity Low end bearing capacity Capacity can be enhanced by rock socket formation

Capacity limited by penetration of steel beams

Capacity limited by penetration of steel beams

Wall can be formed with nominal rock socket over large area

Sheetpile Wall Secant Piles Wall

(Hard / Firm)

Cutter SoilMix Wall

(Steel beams)

Slurry Wall

(steel beams or precast panels)

Diaphragm Wall

(In-situ or Precast Concrete)

Proven in NZ Proven in NZ Site specific trial required Proven in NZ Proven in NZ

Widely available in NZ Available in NZ Available offshore Readily available Readily available

Yes, unless Giken or similar Machine only Machine only Machine only Machine only

Yes, unless Giken or similar No No No No

No 100% 30 - 40% 100% 100%

Cranes, vibros and hammers and / or pile jacking plant (Giken)

50-60T self erecting hydraulic drilling rigs and handling crane.

90T CSM machine, handling crane, 15m

3/hr grout plant with screw feed

silos, compressor, high pressure pumps

50T crane + grab, handling crane, long-reach excavator. 15m

3/hr grout

plant with screw feed silos

50T crane + grab, handling crane, mud conditioning plant, mud storage

Sheet piles Concrete, reinforcement cages Cement, bentonite, steel Cement, bentonite, steel or precast concrete panels

Bentonite, reinforcement cages or precast concrete panels

Plant & Materials delivery Plant & Materials delivery Plant, materials and pipeline delivery of grout

Plant, materials and pipeline delivery of slurry

Plant, materials and pipelines for bentonite mud circulation

Can easily increase the number of rigs to accelerate Significant further mobilisation Can easily increase the number of rigs to accelerate

Flexible Very stiff Stiff (depends on steel section) Stiff (depends on steel section)

Very stiff (PC Panels)

Very stiff

Good with joint treatment Satisfactory but some seepage Satisfactory but some seepage Good due to total replacement with low permeability CB slurry

Excellent with waterbar across panel joints

Welded below capping beam level Drilled & grouted bars + waterstop Welded below capping beam level, bending moment possible

Welded below capping beam level, bending moment possible

Full moment & shear connection via box-out and pull-out bars

Internal painting and sacrificial thickness of steel

Conventional concrete in the ground design. Internal lining for long-term seepage

sacrificial thickness of steel and internal lining wall for ground water

PC panels would negate sacrificial thickness of steel and internal lining wall

Conventional concrete in the ground design. No internal lining necessary

Low end bearing capacity Capacity can be enhanced by rock socket formation

Capacity limited by penetration of steel beams

Capacity limited by penetration of steel beams

Wall can be formed with nominal rock socket over large area

Page 4: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls – Layout & Joint

• Panels excavated under

support fluid (bentonite)

• Reinforced concrete

panels cast using tremie

• Waterstop included

across panel joints

Page 5: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls - Panel Joints

Page 6: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

• Wall joint waterbar

• Slab connection

– Waterbar / waterstop

– Breakback cracking

– Waterbar / slab

pathway

Diaphragm Wall - Joints

Page 7: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls - Trench Stability

Page 8: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls – Trench Stability

SPT “N” value Su – Vane tests Su Remoulded

Page 9: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Panel / Bore Stability Assessment : Huder Madrid 1972 approach Huder(H)

Schneebeli(S)

Locaton : Trench Stability - General 7.0m wide panel

Panel length / Bore diameter, B (m) = 7.000

Depth to Groundwater level (m) = 1.500

Depth to Bentonite [-'ve above G.L.] (m) = 0.500 Soil arching around a slurry trench

Surcharge at ground level (KN/m2) = 0.000

Stratigraphy / Soil Parameters

Strata Depth to Density Effective Total

Description strata (m) ' c' Cu Cu/ z

(KN/m3) (degs) (KPa) (KPa) (KPa)

Guidewalls 0.0 17 30 0.0 0 0

Alluvial Clay (TG) 1.2 17 0 0.0 15 -2

Alluvial Clay (TG) 3.0 17 0 0.0 10 0

Alluvial Clay (TG) 6.0 17 0 0.0 10 2

All Silt/Sand (TG) 10.0 17 30 10.0

All Silt/Sand (TG) 14.0 17 30 15.0

Diaphragm Walls - Trench Stability

Page 10: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

0.00

2.00

4.00

6.00

8.00

10.00

12.00

14.00

16.00

18.00

20.00

0.00 5.00 10.00 15.00 20.00 25.00 30.00

De

pth

(m

)

Pressure (KPa)

Stability Assessment Graph

Active Pressure Bentonite Pressure

Diaphragm Walls - Trench Stability

Page 11: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

0.00

2.00

4.00

6.00

8.00

10.00

12.00

14.00

16.00

18.00

20.00

0.00 5.00 10.00 15.00 20.00 25.00 30.00

De

pth

(m

)

Pressure (KPa)

Stability Assessment Graph

Active Pressure Bentonite Pressure

0.00

2.00

4.00

6.00

8.00

10.00

12.00

14.00

16.00

18.00

20.00

0.00 5.00 10.00 15.00 20.00 25.00 30.00

De

pth

(m

)

Pressure (KPa)

Stability Assessment Graph

Active Pressure Bentonite PressureAdd 10KPa surcharge I.0m drop in Bentonite level

Minimum

Guidewall

depth Potentially

Unstable

Diaphragm Walls - Trench Stability

Page 12: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

• Maintaining a positive

fluid pressure

– Minimise fluid loss into

soil

– Formation of “Filter

cake” or effective

“Membrane”

• Maintaining support

fluid quality

Water PressureFluid Pressure

Support fluid pressure <= water pressure

>> INSTABILITY

Diaphragm Walls - Trench Stability

Page 13: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Assessment of Ground Bearing Pressures

2.75 m 1.00 m

5.49 m 3.92 m

Crane Weight 106800 kg

Boom Length 20 m

Load (Incl hook) 25.0 t Nearest Chart Radius with this load = 12 m

Max. Radius 13 m Chart Load at this Radius = 29.7 t

Total / Gross Load 131800.0 kg Tipping Load at this Radius = 39.6 t

Effective Eccentricity under Load at Max. Radius = 1.04 m

Front Rear Front Rear ecc Length Length Pressure

(Degrees) (KPa) (KPa) (KPa) (KPa) (m) (m) (m) (KPa)

0 252 0 252 0 1.038 5.122 3.415 189

5 263 0 240 0 1.034 5.134 3.423 198

10 273 0 227 0 1.022 5.170 3.447 205

15 281 0 213 0 1.002 5.229 3.486 211

20 288 0 199 0 0.975 5.310 3.540 216

25 292 0 185 0 0.940 5.414 3.609 219

30 295 3 172 2 0.899 5.490 3.693 221

35 296 11 158 6 0.850 5.490 3.790 222

40 295 21 145 10 0.795 5.490 3.900 222

45 292 32 133 15 0.734 5.490 4.023 221

50 286 45 121 19 0.667 5.490 4.156 219

55 279 59 110 23 0.595 5.490 4.300 216

60 269 74 100 28 0.519 5.490 4.452 212

65 258 91 91 32 0.438 5.490 4.613 207

70 245 108 82 36 0.355 5.490 4.780 203

75 230 126 74 41 0.269 5.490 4.953 197

80 214 144 67 45 0.180 5.490 5.130 192

85 198 162 61 50 0.090 5.490 5.309 186

90 180 180 55 55 0.000 5.490 5.490 180

Track /

Body

Slew

Bearing Pressures (KPa) RH Track Loading

Equiv.RectangularDimensions (m)LH TrackRH Track

0

10

20

30

40

50

60

70

80

90

0 100 200 300 400

Pressure (KPa)

Equiv Front Rear

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0

5.5

6.0

0 10 20 30 40 50 60 70

Stress (KPa)

sz

sx

Diaphragm Walls - Trench Stability

Page 14: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls - Site Layout

Mayfair, London

Page 15: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls – Conditioning Plant

New Lynn Rail Trench

Page 16: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls – Conditioning Plant

New Lynn Rail TrenchNew Lynn Rail Trench

Page 17: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls

- Guide walls

New Lynn Rail Trench Lancashire

Page 18: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls – Rope Grab

New Lynn Rail Trench

Page 19: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls – Hydraulic Grab

New Lynn Rail Trench

Page 20: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

• Detailing

• Fabrication

• Transportation

• Lifting

• Connections

Diaphragm Wall - Reinforcement

New Lynn Rail Trench

Page 21: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls - Reinforcement

New Lynn Rail Trench

Page 22: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls - Reinforcement

New Lynn Rail Trench

Page 23: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls

- Reinforcement

800 mmCorbel

1500 mm Diaphragm Wall

CouplersMesh where

cover exceeds 75 mm

130 mmtolerance for

couplers

1500 mm

Bearing zone

Blackpool

• Tolerances for built

in connections

• Boxouts

• Cracking during

breakout

• Waterstop /

waterbar

Page 24: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Marchwood

Diaphragm Walls - Reinforcement

Page 25: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls - Exposed Wall

Iwade

Page 26: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls - Exposed Wall

Haverigg

Page 27: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls - Exposed Wall

Mayfair Car Park

Page 28: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls - Exposed Wall

New Lynn Rail Trench

Page 29: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls - Exposed Wall

New Lynn Rail Trench

Page 30: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Diaphragm Walls - Exposed Wall

MarchwoodNew Lynn Rail Trench

Page 31: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

• Low Strength Concrete Firm piles

• Reinforced concrete Hard piles

• Flexible wall layout

• Use of CFA methods is possible

Secant Pile Walls

Page 32: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Secant Pile Walls

BNZ Auckland

Maintaining overlap

• Plan position

– guide wall

• Verticality

– Strength of “soft” mix

– Sequence of pile

construction

– effect of obstructions

Page 33: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Secant Pile Walls

• SPERW (2nd Edition 2007) Pile Overlap

Page 34: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Secant Pile Wall – Guide walls

Tauranga Manukau

Page 35: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Secant Pile Walls - Concrete Mix

• Constructional

– placement

– drillability

– seepage control

• Structural

– Strength

– durability

650mm

100mm

Page 36: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Secant Pile Walls - Concrete Mix

• Soft / Firm

Mix Trials

200KPa

Page 37: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Secant Pile Walls – Soft mix

BNZ Auckland

• Strength of “soft” mix

– Fit for purpose

• Infill between piles

• Unreinforced

• Strength &

Batching variance

of small quantities

0

2

4

6

8

10

12

0 7 14 21 28 35 42 49 56 63

Str

en

gth

(M

Pa

)

.

Age (days)

Page 38: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Rig Weight

(T)

Power

(KW)

Torque

(KNm)

Max. Pile

Diameter

(m)

Max.Pile

Depth

(m)

LoDril 40 209 68 1.2 24

SR30 37 205 130 1.5 48

R516 54 230 180 2.0 44

SR50 54 230 180 2.0 61

R625 70 300 240 2.5+ 77+

Secant Pile Walls - Hydraulic Rigs

Page 39: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Secant Pile Walls - Hydraulic Rigs

Newmont Gold, Waihi BNZ, Auckland

Page 40: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Site

BNZ Auckland

Page 41: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Secant Pile Walls

BNZ Auckland

Page 42: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Secant Pile

Walls

BNZ Auckland

Page 43: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Hobson

Secant Pile

Walls

Page 44: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Secant Pile Walls

Manukau

Page 45: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Secant Pile Walls

• Time to watch a short video clip

Page 46: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

BNZ Auckland

Secant Pile Walls

SPERW 2nd Edition 2007 Cl. C9.4.4

Page 47: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Secant Pile

Walls

BNZ Auckland

Page 48: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Secant Pile Walls – Waterproof lining

BNZ Auckland

• Fixing membrane

• Swelling constraint

Page 49: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

• Boring

– Flighting

– Polishing

– Loosening

• Concreting

– Poor base

– Necking

– Blockages

• Cage insertion

CFA Secant Pile Walls

Page 50: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Ground Conditions Drill Conc. Cage Comments

1. Very Soft Clays Concrete instability / integrity

2. Soft to Stiff Silts / Clays

3. Very Loose / Loose Sands High permeability can make cage

insertion problematic4. Dry Sands / Sandstones

5. Dense Wet Sands

6. Gravels & Cobbles <150mm OK provided material will flight

7. Boulders Obstruct or deflect auger

8. Weak Rocks <5MPa Rock head and pull down required

9. Moderately Strong Rocks >5MPa Refusal and reduced friction

10. Voided Ground Integrity, loss of concrete

11. Soft / Loose over hard Flighting, settlement & void potential

= No real Issues to = particular care required,

- = potentially significant issues, refer to Manager Engineering for mitigation measures / alternatives

“If in doubt ASK”

CFA Bored Piles

Page 51: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

CFA Bored Piles

Rig Weight

(T)

Torque

(KNm)

Max.Pile

Diameter

(m)

Max.

Depth

(m)

SR30 36 121 0.75 18.5

SR50 53 180 0.60

0.90

21.0

18.0

Page 52: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

• Real time monitoring during construction

• Operators guide

• Quality records

CFA Bored Piles

Page 53: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

CFA Secant Pile Walls

Ellerslie & Shaddock (173K)

Page 54: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

CFA Secant Pile Walls

• Key Factors

– Soft pile mix

– Auger string

– Pile layout

– Boring head

Page 55: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Maleme St, Tauranga

CFA Secant Pile Walls

Page 56: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Maleme St, Tauranga

CFA Secant Pile Walls

Page 57: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Maleme St, Tauranga

CFA Secant Pile Walls

Page 58: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

CFA Secant Pile Wall - Arched

• Soil Load applied to

wall piles

• Arched “Firm” piles

distribute the load to

the “Hard” piles

• Stability provided by

embedment and

structural capacity

Flowable Fill

Soft Pile

Soft Pile

Soft Pile

Soft Pile

Soft Pile

Soft Pile

Typical section through wall

Page 59: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

CFA Secant Pile Wall - Arched

Page 60: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

SPERW

2nd Edition 2007

• Client, Consultant &

Contractor developed

• Specifications

• Construction

guidelines

“If in doubt ASK”

Page 61: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles

Key Points

• Diaphragm and secant pile walls are

proven methodologies in NZ

• CFA methods have been developed to

enable secant pile wall construction

• ICE Specification advocated

“THANK YOU”

Page 62: Brian Perry Civil Diaphragm &Secant Pile Walls · 2013. 5. 13. · Secant Pile Walls –Soft mix BNZ Auckland •Strength of “soft” mix –Fit for purpose •Infill between piles