13
Carbon calculator design tool for bridges & 1 David A. Smith BEng, CEng, FICE Structures Service Director, Atkins, Epsom, UK & 2 Phillippa Spencer MSc, CEng, MICE Bridge engineer, formerly Atkins, Epsom, UK & 3 Chris Dolling BSc, CEng, MICE Manager, Technical Development, British Constructional Steelwork Association Ltd, Doncaster, UK & 4 Chris Hendy MA (Cantab), CEng, FICE, FREng Head of Bridge Design and Technology, Atkins, Epsom, UK 1 2 3 4 BCSA and Corus engaged Atkins to develop a simplified carbon calculator design tool, which could be used to evaluate the carbon footprint of typical steel–concrete composite bridges. A key requirement was to allow rapid evaluation of a range of preliminary design options based on minimal calculated quantities for each option, using typical default assumptions. In addition, the tool needed to be flexible enough to allow the designer to enter more detailed data to override default assumptions and quantities should they become known more accurately. This paper describes the development of the design tool, assumptions used in setting the default parameters and commentary on the sources of information used for the carbon data. An illustration of its use in comparing a typical steel–concrete composite bridge with an equivalent concrete bridge is also provided. It is intended that the design tool will be used by bridge designers to help quantify the embodied and operational carbon dioxide of steel–concrete composite bridges at all stages in their life-cycle, facilitate reductions in the carbon dioxide footprint during construction and maintenance by allowing alternatives to be rapidly assessed, and benchmark projects to facilitate continuous improvement with respect to carbon dioxide. 1. Introduction and project background With the introduction of climate change legislation and greenhouse gas reduction targets, carbon dioxide emission reduction has become a dominant aspect of sustainable design. To reduce car- bon in designs engineers need to be able to measure it. While quantifying embodied carbon in designs is possible through the numerous carbon calculators that have been developed, such as the UK Environment Agency calculator (EA, 2010), they do not lead to a consistent assessment of carbon on their own. This is mostly because of what they do not cover rather than what they do. Within the authors’ own organisations it was noted that when the same bridge was given to different engineers for determin- ing its ‘carbon footprint’, vastly different answers were returned. This was not because of incompetence or error but simply because different engineers made different assumptions about unknowns or, indeed, the boundaries defining the carbon assessment itself. Partially as a result of this observa- tion, Atkins was appointed by the British Constructional Steelwork Association Ltd (BCSA) and Corus (now Tata Steel), to develop a simplified carbon calculator design tool that could be used to evaluate the carbon footprint of typical steel–concrete composite bridges, based on the inventory of carbon and energy database (Hammond and Jones, 2008) for unit rates among other widely available carbon data values. A key requirement for the design tool was to allow rapid evaluation of a range of preliminary design options based on minimal calculated quantities for each option. This was to be achieved by including realistic default assumptions for aspects of the project that may have very limited information available at the design stage but that may have a significant impact on overall carbon dioxide. In addition, the design tool needed to be flexible enough to allow the designer to enter more detailed data to override these default assumptions and quantities should they become known more accurately. This paper describes the development of the design tool, the assumptions used in setting the default parameters and Bridge Engineering Carbon calculator design tool for bridges Smith, Spencer, Dolling and Hendy Proceedings of the Institution of Civil Engineers http://dx.doi.org/10.1680/bren.13.00025 Paper 1300025 Received 16/10/2013 Accepted 06/06/2014 Keywords: bridges/design methods & aids/sustainability ice | proceedings ICE Publishing: All rights reserved 1

Bren 1300025 h

Embed Size (px)

DESCRIPTION

Carbon footprint of composite bridges. Institution of Civil Engineers

Citation preview

  • Carbon calculator design toolfor bridges

    &1 David A. Smith BEng, CEng, FICEStructures Service Director, Atkins, Epsom, UK

    &2 Phillippa Spencer MSc, CEng, MICEBridge engineer, formerly Atkins, Epsom, UK

    &3 Chris Dolling BSc, CEng, MICEManager, Technical Development, British Constructional SteelworkAssociation Ltd, Doncaster, UK

    &4 Chris Hendy MA (Cantab), CEng, FICE, FREngHead of Bridge Design and Technology, Atkins, Epsom, UK

    1 2 3 4

    BCSA and Corus engaged Atkins to develop a simplified carbon calculator design tool, which could be used to

    evaluate the carbon footprint of typical steelconcrete composite bridges. A key requirement was to allow rapid

    evaluation of a range of preliminary design options based on minimal calculated quantities for each option, using

    typical default assumptions. In addition, the tool needed to be flexible enough to allow the designer to enter more

    detailed data to override default assumptions and quantities should they become known more accurately. This paper

    describes the development of the design tool, assumptions used in setting the default parameters and commentary

    on the sources of information used for the carbon data. An illustration of its use in comparing a typical steelconcrete

    composite bridge with an equivalent concrete bridge is also provided. It is intended that the design tool will be used

    by bridge designers to help quantify the embodied and operational carbon dioxide of steelconcrete composite

    bridges at all stages in their life-cycle, facilitate reductions in the carbon dioxide footprint during construction and

    maintenance by allowing alternatives to be rapidly assessed, and benchmark projects to facilitate continuous

    improvement with respect to carbon dioxide.

    1. Introduction and project background

    With the introduction of climate change legislation and greenhouse

    gas reduction targets, carbon dioxide emission reduction has

    become a dominant aspect of sustainable design. To reduce car-

    bon in designs engineers need to be able to measure it. While

    quantifying embodied carbon in designs is possible through the

    numerous carbon calculators that have been developed, such as the

    UK Environment Agency calculator (EA, 2010), they do not lead

    to a consistent assessment of carbon on their own. This is mostly

    because of what they do not cover rather than what they do.

    Within the authors own organisations it was noted that when

    the same bridge was given to different engineers for determin-

    ing its carbon footprint, vastly different answers were

    returned. This was not because of incompetence or error but

    simply because different engineers made different assumptions

    about unknowns or, indeed, the boundaries defining the

    carbon assessment itself. Partially as a result of this observa-

    tion, Atkins was appointed by the British Constructional

    Steelwork Association Ltd (BCSA) and Corus (now Tata

    Steel), to develop a simplified carbon calculator design tool

    that could be used to evaluate the carbon footprint of typical

    steelconcrete composite bridges, based on the inventory of

    carbon and energy database (Hammond and Jones, 2008) for

    unit rates among other widely available carbon data values. A

    key requirement for the design tool was to allow rapid

    evaluation of a range of preliminary design options based on

    minimal calculated quantities for each option. This was to be

    achieved by including realistic default assumptions for aspects

    of the project that may have very limited information available

    at the design stage but that may have a significant impact on

    overall carbon dioxide. In addition, the design tool needed to

    be flexible enough to allow the designer to enter more detailed

    data to override these default assumptions and quantities

    should they become known more accurately.

    This paper describes the development of the design tool, the

    assumptions used in setting the default parameters and

    Bridge Engineering

    Carbon calculator design tool for bridgesSmith, Spencer, Dolling and Hendy

    Proceedings of the Institution of Civil Engineers

    http://dx.doi.org/10.1680/bren.13.00025

    Paper 1300025

    Received 16/10/2013 Accepted 06/06/2014

    Keywords: bridges/design methods & aids/sustainability

    ice | proceedings ICE Publishing: All rights reserved

    1

  • commentary on the sources of information used for the carbon

    data. An illustration of its use in comparing a typical steel

    concrete composite bridge with an equivalent concrete bridge is

    also provided.

    It is intended that the design tool will be used by bridge

    designers to help

    & quantify the embodied and operational carbon dioxide ofsteelconcrete composite bridges at all stages in their

    lifetime

    & facilitate reductions in the carbon dioxide footprint duringconstruction and maintenance by allowing alternatives to be

    rapidly assessed

    & benchmark projects to facilitate continuous improvementwith respect to carbon dioxide.

    2. Scope of carbon calculationsThe calculator covers all aspects of a highway bridge project,

    including detailed consideration of

    & site set up and shut down& materials used& construction activities& maintenance and inspection& demolition& highway traffic data& delay during construction& delay during maintenance.

    The calculator covers rail bridges and any impact their con-

    struction has on highway traffic, but the impact of any delay to

    rail traffic itself is not covered.

    During design, the bridge designer has little information on

    many important aspects influencing carbon considerations,

    such as

    & site establishment how long will the project be on site, forexample, and what overheads are involved

    & sourcing of materials where do the materials come from,for example

    & construction equipment how will the bridge be built, forexample, and what do we use to build it

    & traffic impacts during construction and maintenance willthe existing traffic be delayed, for example, and if it is

    diverted where does it go

    & maintenance and inspection how will the asset bemaintained during its life and what resources will we use

    to maintain it.

    The above unknowns may have far more impact on total carbon

    dioxide than the embodied carbon dioxide in the materials

    themselves and this is the reason why carbon predictions

    can be so variable; different designers make different decisions,

    inclusions and omissions.

    The minimum required inputs to the calculator are kept

    intentionally few in number and are initially limited to the few

    drop-down options and numerical or text input cells illustrated

    in Figure 1. This is achieved by providing over 50 default

    assumptions within the remainder of the spreadsheet. How-

    ever, when more detailed information becomes known, some

    or all of these assumptions may be refined by the user to

    improve accuracy.

    3. Development and functionality of thedesign tool

    3.1 Format and presentation

    The design tool was designed such that it allows for a

    comprehensive estimation of carbon dioxide with only minimal

    high level information such as the type of bridge, dimensions,

    concrete and steel quantities and the number of bearings. It

    also mirrors the structure of a bridge project by having discrete

    elements of the project life-cycle where information is inserted

    for each project element design/construction, maintenance

    and traffic delay. For each life-cycle phase this was further

    divided into the key sections of the specific phase. For example,

    the design/construction element was further split into founda-

    tions, substructure and superstructure. This approach was

    taken to allow users easily to adjust elements of a bridge

    project within their control. Examples of this might include

    proposals to change from driven piles to bored piles or from

    steel parapets to concrete parapets. Does a ladder deck bridge

    have a lower carbon footprint than a multigirder bridge deck,

    or is a pair of column piers better than a leaf pier, for example?

    The design tool is laid out using seven separate worksheets

    & user guide& summary& user locked default assumptions& user values editable assumptions& traffic data& construction materials& information.

    3.2 Basic initial input

    To gain a rapid approximation of the carbon dioxide for a

    bridge the user enters information into the simple front

    summary sheet where preliminary material quantities are input

    (see Figure 1). The number of cells where input is required is

    limited to 16. Nine of these are global details of the bridge and

    project and cover

    Bridge Engineering Carbon calculator design toolfor bridgesSmith, Spencer, Dolling and Hendy

    2

  • & bridge name& structure/project number& type of bridge (road (plus road classification), rail or

    footbridge)

    & type of obstacle crossed (plus classification if a road)& estimated construction duration& bridge length& bridge width.

    The remaining seven required inputs relate to basic material

    quantities from a preliminary design including reinforced

    concrete, structural steel (painted and weathering) and the

    number of bearings for each of the foundations, substructure

    and superstructure bridge elements.

    Having input this limited information, the design tool

    automatically calculates the carbon footprint of the bridge

    with a graphical breakdown showing the relative proportions

    due to construction, maintenance and traffic delays. The con-

    struction element is further subdivided to show the pro-

    portions for the deck, substructures and foundations. Such a

    presentation allows the bridge designer to see where the major

    carbon dioxide burdens are, allowing the focus of design

    development to be on the big issues in terms of reducing overall

    emissions.

    3.3 Default values and user-defined values

    Behind this simple summary sheet is a huge amount of data

    and considered assumptions. If the user wishes, they can delve

    into all of the data and assumptions, amending them to suit

    any better information that they may have, or testing the effect

    of different design details. As a bridge design develops, the

    amount of available project-specific information increases, so

    Figure 1. Summary sheet showing minimal initial input

    requirements

    Bridge Engineering Carbon calculator design toolfor bridgesSmith, Spencer, Dolling and Hendy

    3

  • the carbon footprint calculation can be updated, becoming

    more and more accurate with each iteration.

    The user locked and user values worksheets expand each of

    the project elements and provide significantly more detail on

    each of the materials or plant used for each item that makes up

    the bridge project. Both worksheets are identically laid out,

    with the user-defined value functionality being the only

    difference between them.

    The user locked worksheet sets out default values that the

    user cannot edit but can view to see what has been used for the

    quantities, proportion of materials attributed to the bridge

    element (e.g. the assumed split of concrete between piles and

    pile caps), plant used and durations on site, transportation

    distances, inspection regimes, maintenance intervals and the

    associated traffic management arrangements during construc-

    tion and maintenance of the structure. These default values are

    underpinned by a series of assumptions discussed further in

    Section 4.

    The user values worksheet allows adjustment of some or all

    the default values to refine the calculation as more information

    becomes available. The type of plant, transportation method

    and distances travelled can also be adjusted. The editable cells

    are coloured green and blue to aid ease of finding and ad-

    justing. An option to return all values to their default settings is

    also included.

    3.4 Construction materials carbon dioxide data

    To support further the functionality and usefulness for users of

    the tool, additional worksheets are provided that can override

    the base carbon dioxide data assumed. This functionality was

    included as it is believed that over time further research into

    the carbon dioxide emissions will be carried out and the values

    for each construction material will be refined. In addition, this

    facility enables the user to cater for non-standard materials

    such as bespoke concrete mix designs.

    3.5 Traffic carbon dioxide data

    Implementation of considerations of the impact of traffic delay

    and diversion into the design tool is part of its core func-

    tionality. This functionality also necessitated an additional

    sheet on which the default parameters can be altered by the

    user. The override sheet provides the user with options to

    change the speed limit of the traffic if a contraflow is adopted

    and to amend route diversion lengths if a full road closure is

    required.

    An option to return to the default settings is provided in this

    worksheet.

    4. Key assumptionsKey assumptions made in defining the default values in the

    bridge carbon calculator design tool are discussed below.

    4.1 Assumptions for materials

    Over many years there has been a significant amount of

    research and development undertaken in the area of quantify-

    ing carbon dioxide emissions so the use of freely available

    carbon dioxide data were integrated into the carbon calculator.

    Carbon dioxide values were primarily sourced from the Bath

    University inventory of carbon and energy (Hammond and

    Jones, 2008) and the Department for Environment, Food and

    Rural Affairs (Defra, 2009) for plant and vehicle emissions.

    Carbon dioxide values for steelwork were provided by the

    BCSA during several discussions as the commission pro-

    gressed. Each of these sources has defined carbon boundaries

    and it was vital to understand these boundaries so that the

    carbon calculator consistently provided full life-cycle carbon

    dioxide values for the life of a bridge.

    The Bath University inventory of carbon and energy

    (Hammond and Jones, 2008) has a default carbon boundary

    of cradle to gate. This is a partial product life-cycle from

    resource extraction (cradle) to the factory gate. This means

    that transportation of the product from the manufacturers

    factory to the site had to be added in separately to the carbon

    calculator to provide a whole life value.

    The Defra carbon dioxide data concentrate on carbon dioxide

    emissions for engines, fossil fuels, electricity and emissions

    resulting from different modes of transport and vehicles. From

    these data carbon dioxide values per hour or per vehicle

    kilometre were used to quantify the transportation of materials

    and the duration and use of specific construction plant

    throughout the construction and maintenance periods of the

    bridge. Incorporation of these data values enabled a full

    carbon dioxide life-cycle to be calculated, overcoming the

    shortfalls of cradle to gate data values obtained separately.

    Key for the BSCA in the development of the carbon calculator

    was the use of accurate carbon dioxide figures for steel. The

    figures promoted by the BCSA (Anon, 2010) are used in the

    bridges carbon calculator and are based on the system

    expansion method used by the World Steel Association. The

    system expansion method is the most comprehensive assess-

    ment method currently available and is the preferred approach

    of the BS EN ISO 14040 (BSI, 2006) series of environmental

    standards. The method credits the manufacturing processes for

    co-products that save energy and emissions, such as process

    gases being used to generate electricity. Credit is also given for

    the net carbon dioxide that is saved when a product is reused or

    recycled. In particular, the method credits the manufacturing

    process for the creation of by-products, such as ground

    Bridge Engineering Carbon calculator design toolfor bridgesSmith, Spencer, Dolling and Hendy

    4

  • granulated blast-furnace slag (GGBS), which can be used as

    cement replacement.

    The system expansion method is used in the design tool by

    default. However, an option is given to use the 50 : 50

    approach, which is an average of the system expansion

    method and the recycled content method from the Bath

    database. For concrete, the use of 100% ordinary Portland

    cement (OPC) is taken as the default to avoid double-counting

    the benefit of cement replacements, which are already taken

    into account in the system expansion method. A warning is

    provided to users that reducing the OPC content by includ-

    ing GGBS, for example, or other cement replacements will

    introduce double-counting unless the steel value is also adjusted

    accordingly.

    Default assumptions are also made for the transportation and

    delivery of construction materials. For example, 200 km is

    taken as the default distance for transporting structural steel,

    bearings and parapets, and 50 km is taken as the default for

    concrete, formwork and surfacing.

    There is currently very limited information available for most

    proprietary bridge products such as bearings, parapets and joints.

    Hence carbon dioxide estimates for these are based on constituent

    materials together with simple bridge dimensions such as the

    bridge width for joints, bridge length for parapets and deck area

    for bearings. Other materials used to construct the bridge, such as

    formwork, also need not be explicitly calculated, as default

    quantities are generated based on approximate relationships

    between the volume of concrete and volume of formwork.

    Greater accuracy is seldom warranted because they typically

    represent only a small proportion of the total carbon footprint.

    4.2 Assumptions for construction plant and traffic

    delays

    Default assumptions are made for the plant used to construct

    the bridge based on the input estimated duration on site. Any

    traffic management requirements, commensurate with the type

    of road being crossed, have a choice of two defaults

    & full closure with night-time working and a diversion for thetraffic (the default diversion length is a function of the road

    type selected).

    & contraflow incorporating slowing speeds down by 10 mile/hfor a specified distance to account for the lengths of traffic

    management required.

    The impact of the traffic disruption in terms of carbon

    footprint is calculated within the design tool using national

    traffic statistics (Defra, 2009) for different types of vehicles and

    traffic speeds. Traffic diversions can have a significant impact

    on increasing carbon dioxide, which highlights the need to

    design for bridge erection and construction with the minimum

    of delay to traffic.

    4.3 Assumptions for maintenance and inspection

    The following default assumptions are made for maintenance.

    & There will be four maintenance closures (with defaultduration of five nights) over the lifetime of the bridge with

    replacement of bearings every 30 years.

    & All major maintenance is undertaken during these closures.& No strengthening to the deck is required for bearing

    replacement.

    & All ancillary items are replaced like for like.& Concrete repairs are minimal.& One full replacement of the parapets is undertaken in the

    bridges life together with one panel replacement each

    year to account for accidental impacts during the lifetime of

    the bridge.

    & All painted steelwork is repainted at each maintenanceclosure.

    While the assumption of being able to conduct all major

    maintenance conveniently at the same time is optimistic, the

    amount of maintenance to be performed is arguably con-

    servative to offset some of this.

    The following default assumptions are made for inspection.

    & Inspections are based on current UK requirements specifiedin the UK design manual for roads and bridges.

    & General inspections each of 1 d duration are undertakenevery 2 years.

    & Principal inspections each of 2 d duration are undertakenevery 6 years.

    It is also assumed that no remote monitoring of the structure is

    necessary or provided.

    5. Typical steelconcrete composite bridgeexample and comparison

    To test the bridge carbon calculator design tool, a comparative

    assessment of two bridge designs was carried out between a

    steelconcrete composite bridge and a pre-tensioned precast

    concrete beam bridge equivalent. This assessment was based on

    preliminary design quantities for a typical three-span over-

    bridge with open side spans carrying a single carriageway. Both

    bridges were designed to the Eurocodes. Details of the two

    bridges are discussed below, with commentary on the results

    and conclusions arising.

    5.1 Common bridge details

    The following details were assumed for both bridge options

    considered

    Bridge Engineering Carbon calculator design toolfor bridgesSmith, Spencer, Dolling and Hendy

    5

  • & road overbridge (urban A road classification)& crossing an existing road (urban A road classification)& construction duration of 24 weeks& bridge length of 84 m& bridge width of 17?5 m.

    5.2 Steelconcrete composite bridge example

    The example steelconcrete composite option considered was of

    ladder deck construction with substructures and foundations

    representative of current UK best economic practice. This

    included adopting single columns under each main girder and

    bankseat abutments. Figures 2, 3 and 4 show the general

    arrangement of the steelconcrete composite ladder deck bridge.

    The steelconcrete composite ladder deck bridge was designed

    using the BCSA/Tata Steel preliminary steel composite bridge

    design charts (BCSA, 2010; Mitchell et al., 2011), which gave

    preliminary but optimised material quantities directly.

    5.3 Pre-tensioned precast concrete beam bridge

    In order to obtain a like-for-like comparison with the steel

    concrete composite design, a pre-tensioned precast concrete

    beam bridge of similar dimensions was also considered. Stru-

    ctural general arrangements are shown in Figures 58. The

    particular form of the pre-tensioned precast concrete beam

    bridge chosen represented a bridge recently designed by Atkins

    to BS 5400 (BSI, 1990) for another scheme. It was not expected

    that the concrete outline or reinforcement quantities would

    change significantly when reworked to the Eurocodes.

    5.4 Preliminary design quantities and carboncalculations

    Table 1 summarises the key preliminary design quantities for

    each bridge option considered.

    The results obtained from the bridge carbon calculator design

    tool are shown in Figures 9 and 10 and are discussed in the

    following sections.

    5.5 Carbon dioxide emissions for design and

    construction material quantities

    The preliminary bridge details and the materials quantities

    listed in Table 1 were inserted into the summary sheet of the

    bridge carbon calculator for each bridge option. The default

    values were then overridden with user-defined values to adjust

    the details of the reinforcement content percentages and the

    number and type of bearings used. These adjustments were

    Steelconcrete composite ladder deck solution

    B

    B

    End span

    0 1 1 1 1 1 1 11 1 00* 0* 0 0* 0* 0* 0* 0*0 01

    24 m

    End span

    24 m

    Internal span

    Elevation

    *Spread footing asrequired in brief??

    36 m

    A

    A

    Figure 2. Steelconcrete composite ladder deck example general

    arrangement: elevation

    500 5002000

    1500 1500

    1600 1600

    2000

    Section AA (NTS)With intermediate

    cross-girder

    Section BB (NTS)With main

    cross-girder

    17 464

    12 464

    14 264

    Figure 3. Steelconcrete composite ladder deck example general

    arrangement: sections

    Bridge Engineering Carbon calculator design toolfor bridgesSmith, Spencer, Dolling and Hendy

    6

  • made in the user values worksheet. The total carbon dioxide

    emissions (for material quantities only) for both bridges are

    shown in Table 2, illustrating both the default and user-defined

    value results for both bridge options.

    The comparative assessment for material quantities only, using

    the default assumptions and values, suggested that the steel

    concrete composite bridge had a 13% lower carbon footprint

    than the equivalent precast pre-tensioned concrete bridge.

    500 1600 1600

    5800 4000

    Foundation arrangement

    1200

    1500 Pier1500 Pier

    1

    1

    Section 111600 1600 500

    500 5001500 1500

    Figure 4. Steelconcrete composite ladder deck example general

    arrangement: piers

    * Bridge square in plan

    B

    B Five beams Nine beams Five beams

    A

    End span

    24.22 m

    Internal span

    36.079 m

    End span

    24.22 m

    Figure 5. Pre-tensioned precast concrete beam bridge example

    general arrangement: elevation

    Bridge Engineering Carbon calculator design toolfor bridgesSmith, Spencer, Dolling and Hendy

    7

  • The key items that differ between the two bridges are the

    bearings and the reinforcement percentages. Within the design

    tool the default assumption for the reinforcement percentage in

    reinforced concrete is 2?5%. For the concrete bridge option the

    reinforcement percentage value used for the total concrete

    volume of the deck and the beams combined was 3?5%. This

    takes into account an average between a higher density (5% in

    the deck) and lower density (1?9% in the beams) as noted in

    Table 1, because the reinforced concrete volumes for deck and

    beams are not separate entries in the tool. The equivalent value

    of reinforcement for the concrete beam includes links and an

    allowance for prestressing strand (using an effective increased

    Summary of quantities

    Steelconcrete composite bridge Pre-tensioned precast concrete beam bridge

    Quantities Reinforcement content: % Quantities Reinforcement content: %

    Foundations: m3

    Pile cap 261 1 319 1

    Precast piles 301 1 315 1

    Total 562 634

    Substructure: m3

    Abutments 212 2 212 2

    Piers (incl. diaphragms) 49 2 250 2

    Wingwalls 22 2 22 2

    Total 283 483

    Superstructure

    Articulation: number of

    bearings

    Mechanical 8 0

    Elastomeric 0 10

    Total 8 10

    Structural steel: t

    Painted steel 222 0

    Weathering steel 0 0

    Total 222 0

    Reinforced concrete: m3

    Deck 346 5 346 5

    Beams 0 0 362 1?9a

    Total 346 708

    aEquivalent value of reinforcement includes links and allowance for prestressing strand (using increased weight of strand toaccount for increased carbon dioxide unit rate of steel coil)

    Table 1. Quantities from preliminary design

    Carbon dioxide emissions for steelconcrete

    composite bridge: tCO2

    Carbon dioxide emissions for pre-tensioned precast

    concrete beam bridge: tCO2

    Default values User-defined values Default values User-defined values

    Foundation 313?6 234?6 352?4 263?2

    Substructure 221?8 208?6 400?9 378?4

    Superstructure 673?6 753?5 636?6 633?5

    Total 1209?0 1196?7 1389?9 1275?1

    Table 2. Total tonnes of carbon dioxide emissions for design and

    construction (materials only)

    Bridge Engineering Carbon calculator design toolfor bridgesSmith, Spencer, Dolling and Hendy

    8

  • weight of strand to account for the increased carbon dioxide unit

    rate of steel coil). Adjusting the user-defined values for rein-

    forcement content and bearing type (elastomeric for the concrete

    option and mechanical for the steel, as noted in Tables 1 and 2)

    further refines the carbon footprint for both designs.

    When the default values were altered to more accurately

    known values, the totals showed that the carbon dioxide

    difference between the two bridges reduced from 13% to

    around 6%. There was a negligible difference between the

    default and user-defined values for the steelconcrete compo-

    site bridge; differences for the precast concrete bridge arose

    mainly from adjusting the default reinforcement quantities

    where they are less appropriate for precast beams.

    It should also be noted that mechanical bearings (used for the

    steelconcrete composite bridge) have higher embodied carbon

    dioxide than elastomeric bearings (used in the pre-tensioned

    concrete bridge). In this particular example, the elastomeric

    bearings had only 37% the emissions of the mechanical bearing

    even though a greater number had been assumed to be required

    (ten compared to eight).

    5.6 Carbon dioxide emissions for inspection and

    maintenance

    The total carbon dioxide emissions for the inspection and

    maintenance phases of each option are shown in Table 3, again

    illustrating both the default and user-defined value results for

    both bridge options.

    For inspections, both bridges have the same total carbon

    dioxide emissions due to the general requirements used for the

    assumptions, as set out in BD 63/07 (HA, 2007).

    For the maintenance of each bridge option, considering just the

    default assumptions and values, the total carbon dioxide

    Carbon dioxide emissions for steel concrete

    composite bridge: tCO2

    Carbon dioxide emissions for pre-tensioned precast

    concrete beam bridge: tCO2

    Default values User-defined values Default values User-defined values

    Inspection 17?4 17?4 17?4 17?4

    Maintenance 288?7 268?5 351?3 144?6

    Total 306?1 285?9 368?7 162?0

    Table 3. Total tonnes of carbon dioxide emissions for inspection

    and maintenance

    500 2000

    Footway

    Precastpre-tensionedU-beamusing existingbeamdimensions

    Detail A

    1600 1783 1783 1783 1783 1783

    Section AA (NTS)

    500

    500

    250

    Parapet

    Edge beam

    Detail A (NTS)

    1783 1783 1783 1600

    Footway

    2000 500

    17 464

    12 464

    Carriageway

    Figure 6. Pre-tensioned precast concrete beam bridge example

    general arrangement: main span section

    Bridge Engineering Carbon calculator design toolfor bridgesSmith, Spencer, Dolling and Hendy

    9

  • burden is greater (by 20%) in the concrete design in com-

    parison to the steel. This is mainly due to the input of extra

    bearing numbers being specified (ten compared to eight) and

    thus being assumed to require replacement. By default, the

    bearings are assumed to be mechanical types for both options

    and there is an assumed allowance for concrete removal and

    repair associated with each bearing replacement. In addition,

    due to the higher total concrete quantities required for the

    concrete bridge option, there is a higher carbon dioxide burden

    for concrete repairs over the design life of the structure. When

    using the user-defined values to specify elastomeric bearings,

    however, for the concrete bridge option, the carbon dioxide

    burden of maintaining the bridge is reduced significantly below

    that for the steel option (46% lower).

    5.7 Carbon dioxide emissions for site set up

    For both bridge options the site set-up assumptions are the

    same and have a minimal effect on the total carbon footprint

    for a project. At the preliminary design stage, very little, if any,

    information would be known for making major adjustments to

    the default assumptions built into the design tool, but the

    influence is not large enough to warrant further effort until

    much later in the project.

    5.8 Carbon dioxide emissions for traffic delay

    For both bridge options the traffic delay is similar due to the

    classification of roads being crossed and a new road being built

    on the bridge. This aspect of the total carbon footprint is the

    most significant, accounting for around 75% of the total

    carbon dioxide emissions for these particular examples. It

    should be noted that the road classification adopted for this

    comparison study is urban A roads only. Altering these road

    1600

    Precastpre-tensioned

    U-beam 1600

    500

    3566

    Section BB (NTS)

    Carriageway20002000500

    Footway Footway

    17 464

    12 464

    3566 3566 3566

    Figure 7. Pre-tensioned precast concrete beam bridge example

    general arrangement: back span section

    Use diaphragmand beam depthfrom existingdesign

    1200 mmdiameterpier

    Pier

    5955

    732

    1600Typical Typical

    1600

    1200

    500 1500 1500

    4000

    12.0 mto foundinglevel

    500

    18.468 m

    732

    5955

    17 464

    Pier Deck

    Pre-tensioned beamDeck/pier

    Pierpilecap

    Diaphragm

    Figure 8. Pre-tensioned precast concrete beam bridge example

    general arrangement: piers

    Bridge Engineering Carbon calculator design toolfor bridgesSmith, Spencer, Dolling and Hendy

    10

  • classifications to higher trafficked roads will have an even more

    significant effect on a total project and in some cases may

    render the total carbon dioxide embodied in the construction

    materials insignificant by comparison, particularly for motor-

    way construction. This highlights that choosing erection and

    construction methods to minimise traffic disruption can be key

    to minimising the burden of carbon dioxide emissions on

    bridge projects. The same logic and conclusions apply to

    eliminating the need for significant traffic management during

    operation and maintenance.

    5.9 Conclusions from the comparative assessment

    The embodied carbon dioxide in the steelconcrete composite

    bridge was shown to be marginally lower than that in the

    similar pre-tensioned precast concrete beam bridge. The

    difference was, however, very small and cannot necessarily be

    regarded as a general conclusion for all such bridges for a

    number of reasons, including the following.

    & The preliminary steelconcrete composite bridge design chartsoptimise the design of the steel sections for the steelconcrete

    composite bridge option, but the same level of optimisation

    could not be achieved for the pre-tensioned precast concrete

    beam design in the limited time available for this study.

    & An independent design team undertook the concrete bridgedesign, which may have led to minor variations in design

    assumptions.

    & Good design and detailing to provide an efficient use ofmaterials and ease of construction and maintainablity is key

    to minimising carbon emissions and is much more

    important than the actual choice of materials.

    Notwithstanding the material quantities, the comparative

    assessment illustrated that traffic delay was the main con-

    tributor to carbon dioxide emissions for the construction and

    maintenance of the bridge, accounting for around 75% of the

    total emissions. Investigating options for managing the traffic

    and keeping it free flowing is therefore fundamental to

    reducing the overall emission burden. Such options might

    include night working, alternative diversion route planning

    (both of which are provided as options to change to from

    the default assumptions in the design tool), or looking at

    Figure 9. Results for steelconcrete composite bridge example

    Bridge Engineering Carbon calculator design toolfor bridgesSmith, Spencer, Dolling and Hendy

    11

  • high-performance materials and low-maintenance designs to

    reduce the maintenance intervention requirements and sub-

    sequent impact on traffic.

    6. ConclusionThe development of a bridge-specific carbon calculator design

    tool has enabled a consistent approach to be taken in assessing

    the carbon footprint of various bridge options at the preliminary

    design stage of a project. The tool has been written to enable

    rapid calculation of the carbon dioxide burden for bridge

    schemes with minimal, basic input required, yet also be flexible

    enough to incorporate new data and adjust the default as-

    sumptions as the project develops and more detailed informa-

    tion becomes available. It is intended that the design tool will be

    used by bridge designers to help

    & quantify the embodied and operational carbon dioxide ofsteelconcrete composite bridges at all stages in their life-cycle

    & facilitate reductions in the carbon dioxide footprint duringconstruction and maintenance by allowing alternatives to be

    rapidly assessed

    & benchmark projects to facilitate continuous improvementwith respect to carbon dioxide.

    While the design tool was initially developed for typical

    highway bridges in the UK, it was written to be flexible enough

    for use with rail bridges, footbridges and smaller highway

    bridges. The flexibility of the tool also allows international use,

    with careful adjustment and consideration of some of the

    default assumptions, including default distances for travel. The

    design tool is principally intended for concept and preliminary

    design to assist with evaluating the benefits and disbenefits of a

    range of possible bridge options.

    Some of the key findings from assessing the carbon foot-

    prints of a number of bridges with the design tool include the

    following.

    & Carbon dioxide per square metre of deck area forconstruction of a typical bridge is somewhere between 1 and

    3 t if traffic impacts are ignored; typically 2 t/m2 for routine

    construction.

    Figure 10. Results for pre-tensioned precast concrete beam bridge

    example

    Bridge Engineering Carbon calculator design toolfor bridgesSmith, Spencer, Dolling and Hendy

    12

  • & Typically one-third to half the carbon dioxide emissionsfor a bridge is produced during maintenance, so

    consideration of good design for maintenance is

    important.

    & Minimising traffic delay is key for the construction phaseand maintenance in terms of limiting the effects of traffic

    delay on carbon dioxide. This is usually much more

    significant in terms of carbon dioxide than the embodied

    carbon in the materials themselves, so good design with

    respect to ease of construction and maintenance is therefore

    important.

    & Comparisons between steel, concrete and steelconcretecomposite indicate that their embodied carbon contents are

    similar and that the benefits of an efficient design are much

    more significant than the choice of material.

    & Embodied carbon dioxide in the design itself is roughlyproportional to total bridge cost, so advances in analysis

    techniques and codes lead to more efficient designs in terms

    of both carbon and cost.

    A freely downloadable version of the design tool is available

    from http://www.steelconstruction.org/resources/sustainability/

    bridges-carbon-calculator.html.

    AcknowledgementsThis paper is published with the permission of the BCSA and

    Tata Steel. The authors acknowledge John Dowling (BCSA)

    for his valuable input during the development phase and in

    checking and testing, and Louisa Man (Atkins) for providing

    subsequent thorough reviews of the completed tool.

    REFERENCES

    Anon (2010) The Carbon footprint of steel. New Steel

    Construction Magazine, January: 3233.

    BCSA (British Constructional Steel Association) (2010)

    Preliminary Steel Composite Bridge Design Charts. see

    http://www.steelconstruction.org/resources/technical/

    bridges-preliminary-design.html (accessed 13/01/2013).

    BSI (1990) BS 5400-4:1990: Steel, concrete and composite

    bridges, Part 4 Code of practice for design of concrete

    bridges. BSI, London, UK.

    BSI (2006) BS EN ISO 14040:2006: Environmental

    management Life cycle assessment: Principles and

    framework. BSI, London, UK.

    Defra (Department for Environment, Food and Rural Affairs)

    (2009) Guidelines to Green House Gases Conversion Factors.

    Sourced from revised factors developed by AEA and

    agreed with Department for Transport, see http://archive.

    defra.gov.uk/environment/business/reporting/pdf/

    20090928-guidelines-ghg-conversion-factors.pdf (accessed

    15/08/2012).

    EA (Environment Agency) (2010) Carbon Calculator for

    Construction Activities. EA, UK, see https://publications.

    environment-agency.gov.uk/skeleton/publications/

    SearchResults.aspx?name5GEHO0712BWTW-E-X

    (accessed 12/02/2013).

    HA (Highways Agency) (2007) DMRB (Design Manual for

    Roads and Bridges) BD 63/07 Volume, Section 2.

    Highway Structures: Inspection and Maintenance

    Inspection of Highway Structures. Highways Agency,

    London, UK.

    Hammond G and Jones C (2008) Inventory of Carbon & Energy

    (ICE). University of Bath, UK, see www.bath.ac.uk/mech-

    eng/sert/embodied/ (accessed 12/02/2013).

    Mitchell RP, Smith DA and Dolling C (2011) Updating preliminary

    steel concrete composite bridge design charts for Eurocodes.

    Proceedings of the ICE Bridge Engineering 164(4):

    185194.

    WHAT DO YOU THINK?

    To discuss this paper, please email up to 500 words to the

    editor at [email protected]. Your contribution will be

    forwarded to the author(s) for a reply and, if considered

    appropriate by the editorial panel, will be published as

    discussion in a future issue of the journal.

    Proceedings journals rely entirely on contributions sent in

    by civil engineering professionals, academics and stu-

    dents. Papers should be 20005000 words long (briefing

    papers should be 10002000 words long), with adequate

    illustrations and references. You can submit your paper

    online via www.icevirtuallibrary.com/content/journals,

    where you will also find detailed author guidelines.

    Bridge Engineering Carbon calculator design toolfor bridgesSmith, Spencer, Dolling and Hendy

    13

    Figure 1Figure 2Figure 3Figure 4Figure 5Table 1Table 2Table 3Figure 6Figure 7Figure 8Figure 9Figure 10Reference 1Reference 2Reference 3Reference 4Reference 5Reference 6Reference 7Reference 8Reference 9