44
BPE Case Studies Non-domestic Estover Community College National Composites Centre 15 th February 2016 Kevin Couling Regional Director, AECOM

BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

BPE Case StudiesNon-domestic

Estover Community CollegeNational Composites Centre

15th February 2016

Kevin Couling

Regional Director, AECOM

Page 2: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Building Performance Evaluation

• £8 million Innovate UK funding – four year programme 2010 –2014

Aims

• to help designers & constructors to deliver more efficient, better performing buildings.

• to assemble substantial body of data to draw generic conclusions on performance

Findings

• Specific findings immediate benefit for participants

• Generic findings being widely disseminated across industry & academia

2

Page 3: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Building Performance Evaluation

3

• Projects are a mix of domestic and non-domestic

• 44 domestic, 48 non-domestic projects

• New build or major refurbishment

• Either under construction, or within 3 years post

completion

Page 4: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

AECOM BPE Projects

4

• Non-Domestic Buildings, Phase 1: Buildings In Use:

- Eli Lilly Research Office Building (completed February 2013)- Stevenage Bioscience Catalyst (completed June 2013)

• Non-Domestic Buildings, Phase 2: Buildings In Use:

- National Composites Centre (completed August 2014)- Estover Community College (completed July 2014)

• Domestic Buildings, Phase 2: In-use performance and post occupancy evaluation:

- Seager Distillery Site Housing Development (completed August 2014)

Page 5: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Estover Community College(Tor Bridge High)

National Composites Centre

Page 6: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Overview

• May 2012 – April 2014

• Occupant satisfaction

• Energy performance

• Renewable / low carbon technologies performance

• Internal conditions

• Lessons for industry

6

Page 7: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Tor Bridge High

7

Project Value ~£28m

Completion August 2012

Client Plymouth City Council

Architect Feilden Clegg Bradley Studios

Structural Engineer Jenkins & Potter

M&E Consultant AECOM

Project Manager EC Harris

Contractor Kier Western

Page 8: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

8 8

Phase 2

Phase 3

Phase

1

Phase

1

Page 9: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Tor Bridge High, Plymouth

• Approx 1,600 pupils on site ranging from 4-18 years old

• 11 buildings

• 16,900m2

• 500kW Biomass boiler

• Mini district heat network

• 2x gas boilers (516kW and 452kW)

• Mainly naturally ventilated

9

Page 10: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Occupant satisfaction survey

• Only one survey carried out

• Response rate relatively low - 44%

• Positive

– Design of building

– Effect on behaviour of pupils

• Negative

– Lighting controls

– Noise

– Storage

10

Page 11: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Occupant Satisfaction

11 11

Page 12: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Wind vortex

12

Page 13: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

13

Occupants like natural

ventilation

...but can leave night vents

open in winter

Page 14: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

14

PIRs are not always as

effective as we anticipate

Page 15: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Biomass boiler

• FM and the Finance team lost confidence in the biomass boiler

• Perceived added maintenance burden, disposal of ash, and high moisture content

• Fuel supply contract provided no means of ensuring fuel quality

• Ineligible for RHI as gas boilers are unmetered for heat so distribution losses cannot be determined

• Shape of fuel pit caused problems

15

Page 16: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Heat consumption

16

0

50

100

150

200

250

300

350

0

50,000

100,000

150,000

200,000

250,000

300,000

De

gre

e D

ay

sS

ou

th W

est

Re

gio

n

kW

h

Total heat consumptionkWh (primary axis), Regional Degree Days (secondary axis)

Biomass Heat Gas Boiler Heat Degree Days

Page 17: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Comparison against EPC

17

0

50

100

150

200

250

EPC Actual

kWh

/m2

heat

electricity

Page 18: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Electricity consumption

18

Energy centre4%

Austen5%

Faraday9%

CADE North9%

CADE South5%

Sports Hall13%

Tenzing5%

Graham Brown0%

Kitchen7%

Cann Bridge

6%

Primary school8%

Unknown29%

Energy centre4%

Austen5%

Faraday9%

CADE North9%

CADE South5%

Sports Hall13%

Tenzing5%

Graham Brown0%

Kitchen7%

Cann Bridge

5%

Primary school8%

Sound House11%

CADE Plant room8%

Server6%

External lights1%

Floodlighting1%

Sprinkler house2%

Unknown2%

Page 19: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Comparison to benchmarks

19

0

10

20

30

40

50

60

70

80

Graham Brown

Austen Primary school

Tenzing Faraday CADE North CADE South Cann Bridge Sound House

Sports Hall Typical Good practice

Typical

Blocks Guide F - Secondary

School

TM46

kWh

/m2

Annual electricity benchmark comparison by block

Retained Block

SEN Teaching

New build

Page 20: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Comparison to benchmarks

20

0

10

20

30

40

50

60

70

80

90

Actual Typical Good practice Typical

Guide F TM46

kWh

/m2

TBH total annual electricity benchmark comparison

0

20

40

60

80

100

120

140

160

180

Actual Typical Good practice Typical

Guide F TM46

kWh

/m2

TBH total annual fossil fuel benchmark comparison

Page 21: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Lessons for industry

• Ensure high level sub-meter reconciliation shortly after handover

• If renewable / low carbon generation is utilised, make sure adequate metering is in place otherwise funding opportunities may be missed.

• Natural ventilation strategy is highly dependent on occupants. More effective ways to indicate appropriate use to occupants are required.

• Manual control can lead to high occupant satisfaction, but also to inappropriate use and energy consumption.

• Suitability of biomass for schools needs careful consideration

• Out of term time use for schools can be problematic

• Occupant satisfaction possibly a missed opportunity

21

Page 22: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

National Composites Centre

22

Project Value ~£25m

Completion 2011

Client University of Bristol & South West RDA

Architect Stride Treglown

Structural Engineer Halcrow

M&E Consultant AECOM

Surveyor Cyril Sweett

Contractor Kier Group

Page 23: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

National Composites Centre

23

• 8,500 m2 state-of-the-art industrial research facility

• Rapid build time – 10 months

• Mixture of office, workshop, and specialised lab spaces

• BREEAM Excellent

• Large 138kWp PV array

• Rainwater harvesting

• Heating via 5 gas boilers

Page 24: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

General layout

24

Page 25: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Ventilation

• Displacement ventilation in workshop

– Low level fresh air

– Internal heat gains in winter

• Mixed mode for office areas

– Automatic windows

– Night cooling

– Squirrel infiltration

• Air tightness

– Part L – 6 m3/(h.m2) @ 50 Pa

– Achieved - 4 m3/(h.m2) @ 50 Pa

– BER ~10% better than TER

25

Page 26: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Key findings

• The NCC has proved a commercial successful – second NCC building (NCC2).

• NCC2 designed by largely the same team as NCC, providing a rare opportunity to directly feedback information from the BPE study.

• Occupants largely satisfied with the building. However, indications that on occasion too hot in summer in office areas.

• Dynamic space - alterations made to space and services since completion (particularly within the Main Workshop space) to accommodate different functions.

• Benchmarking shows while energy consumption for fossil fuel is comparable to other (possibly) relevant benchmark datasets, electricity consumption is much greater.

• Significant opportunities for energy savings identified and fed-back

26

Page 27: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Comparison against EPC

27

Page 28: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Benchmarking

• Benchmarking difficult as very unique building

28

0

20

40

60

80

100

120

140

160

180

NCC Actual (FFTM46 adjusted)

Constructed TM46 Raw TM46(Workshop)

kgC

O2/m

2/p

.a.

Total carbon intensity for NCC against raw and constructed benchmarks

Fossil Fuel

Electricity

Page 29: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

PV array

29

Page 30: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

PV performance

30

-

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

18,000

20,000

Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

Tota

l yie

ld (

kWh

)

Annual comparison of PV generation

Actual PV yield Expected PV yield (MWh)

~3% more than predicted

Page 31: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

PV performance

31

-80,000

-60,000

-40,000

-20,000

-

20,000

40,000

60,000

80,000

100,000

120,000

140,000

160,000

Design Actual Design output Actual output

kWh

PV Array Year 1 performance

On-site use Export Total generated

6%47%

Page 32: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Electricity consumption

32

Not connected to BMS10%

MCC PLT Space East21%

Nitrogen Plant11%

Centre BusBar6%

Manufacturing Lighting total

6%

Autoclave 1 6% West

BusBar5%

Clean RM Chiller5% Spec Gases DB

5% Office Power5%

Office lighting4%

Clean Room P&L3%

Ext Lighting2%

Mech PLT West PTRM

2%

East Freezer 1 & 22%

ATL/AFB Rapid depo P&L1%

Robot 1&21%

Autoclave 1 Chiller1%

Liquid resin cell 1%

Ply Cutter P&L1%

UPS total3%

Other9%

Total electricity consumption:2,370,000 kWh p.a.

Page 33: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Metering issues

• Timestamps incorrect

• BMS truncates exported meter data at 1,000,000 units

33

Page 34: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Page 34

0

50

100

150

200

250

300

350El

ect

rici

ty c

on

sum

pti

on

(kw

h/h

alf

ho

ur)

NCC sub meter reconciliation Fri 08/09/13

Clean Room P&L

Ply Cutter P&L

Robot 1&2

Spec Gases DB

Hot Drape Former

Office Power

Office lighting

Ext Lighting 01

East Freezer 1 & 2

Rapid depo

Liquid resin cell

Manufacturing Pwr total

Manufacturing Lighting total

Clean RM Chiller

MCC PLT Space East

DB-02-BR-PL-12

Mech PLT West PTRM

Centre BusBar

West BusBar

Autoclave 1 Chiller

Nitrogen Plant

Autoclave 1

PV

Total incomer

Page 35: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Gas consumption

35

Autoclave6%

HWS5%

Boilers89%

Total gas consumption:1,560,000 kWh p.a.

Page 36: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Workshop AHU temperature Thursday 19/12/13 to Friday

20/12/13

Page 36

0

5

10

15

20

25

30

35

Supply Temperature (°C) Extract Temperature (°C) Setpoint

Page 37: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Occupant satisfaction

• Two surveys carried out using BUS method roughly a year apart.

• Achieved response rates of 78% and 73%

• Fed results back to design of NCC2

• Statistical comparison of qualitative answers conducted

37

Page 38: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Occupant satisfaction

Positive

• Collaborative environment

• Lots of natural light

• Breakout areas

• Being close to manufacturing facility can be very motivational

38

Negative

• Lack of men’s WCs

• Distracting noise from rainwater down pipe in office areas

• Varying temperatures throughout the day from automatic windows opening and closing

• Frustration with automatic lights going on/off while people are still in the office or meeting room.

• Lack of storage space for desk areas, lockers for cyclists, and workshop materials and tools.

Page 39: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

39

Automated windows

frustrating occupants

Page 40: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Occupant satisfaction

40

Page 41: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Influence of the BPE study on the NCC2 design

• PV array electrical design - arrangement caused negative readings on associated meter. Through feedback to NCC2, PV array feeds directly into the main switch panel.

• Rain water pipes through offices. Noise issue highlighted by BUS. For NCC2, rain water collection pipes will not run through office spaces.

• Allocation of male/female toilets. NCC2 will have proportionally more male than female toilets available for staff to better reflect demographic.

• Screens are being provided on high level automated windows to prevent entry of squirrels.

41

Page 42: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Lesson for industry

• High level meter reconciliation during aftercare following commissioning

• Unsuitability of standard BMS for long term energy monitoring

• Ownership of energy data throughout the building life cycle

• Communication of metering strategy between design team and installers

• PV design export assumptions should be made on regulated and unregulated energy consumption

• Fully consider rain noise during design

42

Page 43: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Lessons for industry - Estover

• Excellent feedback from building users

• Users seem to appreciate having control over their environment

• Fulfils the primary function of providing a great place to teach and learn

43

Lessons for industry - NCC

• Significant commercial success

• Development of NCC2 allowed feedback from BPE directly to design team

• Fulfils the primary function of providing first class facilities for ground breaking research

Page 44: BPE Case Studies Non-domestic Estover Community College ...Biomass boiler •FM and the Finance team lost confidence in the biomass boiler •Perceived added maintenance burden, disposal

Thank you!

Questions later…