BOQ_for_Line[1].xlsx

Embed Size (px)

Citation preview

  • 8/14/2019 BOQ_for_Line[1].xlsx

    1/4

    Best of t

    Rate Amount

    Line Material1 GI Tower parts (Line) 528 MT 0

    2 GI Bolts & Nuts (SS & Line) 17 MT 0

    3 ACSR Panther Conductor 135 kM 0

    4 70 KN Suspension Composite insulators 325 Nos 0

    5 120 KN Tension Composite insulators 508 Nos 0

    6 7/3.15 HTGS Earth Wire 23 KM 0

    7 Single tension hardware for panther ( line) 374 Sets 0

    8 Double TensionHard ware for ACSR Panther 80 Sets 0

    9 Vibration Dampers for ACSR Panther conductor. 1,053 Sets 0

    10 Mid span Compression joints for ACSR Panther 100 Sets 0

    11 Repair sleeves for ACSR Panther 40 Sets 0

    13 Earth wire tension Hardware with earth bond 72 Nos 0

    14 Earth wire Suspension Hardware with earth bonds 49 Nos 0

    15 Single suspension hardware for ACSR Panther wih FAH 264 Sets0

    16 Single tension hardware for ACSR Panther wih FAH 7 Sets 0

    17 Mid span Compression joints for earth wire 30 Nos 0

    18 P.A rod for Panther Conductor 252 Mtr 0

    19 Earthing system/ACD 80 Nos 0

    20 Number plates 80 Nos 0

    21 Caution plates 80 Nos 0

    22 Danger Boards 80 Nos 023 Earth bond size 450 mm long 36 Mtr 0

    24 Earth bond size 300 mm long 42 Mtr 0

    25 Phase plate (RYB each) 160 Nos 0

    26 Circuit plates (I & II each) 80 Nos 0

    0

    Description Line Unit

    Electrical Material BOQ for erection of 132 kV Transmission line from Tirumalayapalli to Kondapuram(21.693 KM)

    HWPLSl.No.

  • 8/14/2019 BOQ_for_Line[1].xlsx

    2/4

    Best of three

    Rate Amount

    1 Erection of towers including tackweilding upto Bottom cross arms 528 MT 0

    2Stringing of conductor including jumpers,insulator hoisting,vibratingdampers fixing,armour rod fixing,earthbond fixing and midspan jointsand other related necessary accessories.

    22 KM

    0

    3

    accessories 23 KM 0

    4 Tower accessories fixing(Number,danger,caution,phase plates & ACD 80 Locations 0

    0

    0

    Erection of 132 KV Transmission line (21.693 KM) from Tirumalayapalli to KondapuramHWPL

    S.No Description of work Qty Unit

    Page 2 of 4

  • 8/14/2019 BOQ_for_Line[1].xlsx

    3/4

    Best of three

    Unit Rate AmountP type WET 7 - P type BC 31 - P type HR 4 - P type PS 0 - P type DRY 0 - R type WET 2 - R type BC 6 - R type HR 0 - R type PS 0 - R type DRY 0 - S type WET 8 - S type BC 6 - S type HR 5 - S type PS 1 - S type DRY 0 - D type PS 0 -

    TND/TNS WET 2 - JC PS 4 -

    -

    Unit Rate Amount1 04 00 01 00 05 00 01 00 00 00 0

    0

    Civil FOUNDATION BOQ for execution of 132 kV Tr. Line including stub setting & BackfillingDetails of 132 KV Transmission line

    Revetment BOQ for execution of 132 kV Tr. Line

    HWPL

    HWPL

    P +6

    Type of Towers Classification WET

    Type of Tower Qty

    R NTR +3S NTS +3S +6S +9

    220 kV DJC

    P NTP +3

    Page 3 of 4

  • 8/14/2019 BOQ_for_Line[1].xlsx

    4/4

    Best of three

    Unit Rate Amount

    30

    80 00 0

    80 0

    10

    1 0

    0 00

    Particulars HWPL1 Electrical Material for 132 kva 02 Erection of 132 KV Transmission line 03 Civil foundation - 4 Revetment 05 Other Civil works 0

    0

    MINMAXAVG

    Other Civil Works

    Counter Poise Earthing if required in mtr

    Formation of temparary access road (Hilly area)for locations 67- 78 in KM'sTower Earthing

    HWPL

    ROW per Location

    Liasoning Charges includingCEIG,PTCC,R&B,APTRANSCO (TLC, TL&SS)including commissioning of Tr.Line and HOTO.

    Crop compensation per KM.

    ROW for 220 KV line crossing with (TNS/TNDtower)

    Description of work Qty

    Page 4 of 4