7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
1/55
Sl. Item Name Unit L B H
1 Excavation Mtr. 2.35 2.65 1.5
2 PCC (1:4:8) Mtr. 2.05 2.35 0.1000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
3 RCC-Raft (1:1.5:3) Mtr. 1.9000 2.2000 0.3500
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
4 RF steel- Raft-short side Mtr. 2.2200 --- ---
5 RF steel- Raft-long side Mtr. 2.5200 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
2/55
Unit Qty.
cum. 9.3413
cum. 0.4818 Bags
cum. 0.0371 2.0
cum. 0.1482
cum. 0.2965
cum. 1.4630 Bags
cum. 0.2660 11.7
cum. 0.3990
cum. 0.7980
Mtr. 34.7800 Kg
Mtr. 34.4400 45.5 10 MM.
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
3/55
Sl. Item Name Unit L B H
1 Excavation Mtr. 2.45 2.65 1.5
2 PCC (1:4:8) Mtr. 2.15 2.35 0.1000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
3 RCC-Raft (1:1.5:3) Mtr. 2.0000 2.2000 0.3500
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
4 RF steel- Raft-short side Mtr. 2.3200 --- ---
5 RF steel- Raft-long side Mtr. 2.5200 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
4/55
Unit Qty.
cum. 9.7388
cum. 0.5053 Bags
cum. 0.0389 2.1
cum. 0.1555
cum. 0.3109
cum. 1.5400 Bags
cum. 0.2800 12.3
cum. 0.4200
cum. 0.8400
Mtr. 36.3467 Kg
Mtr. 36.1200 47.7 10 MM
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
5/55
Sl. Item Name Unit L B H
1 Excavation Mtr. 3.35 3.65 1.5
2 PCC (1:4:8) Mtr. 3.05 3.35 0.1000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
3 RCC-Raft (1:1.5:3) Mtr. 2.9000 3.2000 0.4000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
4 RF steel- Raft-short side Mtr. 3.3200 --- ---
5 RF steel- Raft-long side Mtr. 3.6200 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
6/55
Unit Qty.
cum. 18.3413
cum. 1.0218 Bags
cum. 0.0786 4.3
cum. 0.3144
cum. 0.6288
cum. 3.7120 Bags
cum. 0.6749 29.7
cum. 1.0124
cum. 2.0247
Mtr. 74.1467 Kg
Mtr. 73.6067 140.0 12 MM
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
7/55
Sl. Item Name Unit L B H
1 Excavation Mtr. 3.45 3.95 1.5
2 PCC (1:4:8) Mtr. 3.15 3.65 0.1000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
3 RCC-Raft (1:1.5:3) Mtr. 3.0000 3.5000 0.4500
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
4 RF steel- Raft-short side Mtr. 3.4200 --- ---
5 RF steel- Raft-long side Mtr. 3.9200 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
8/55
Unit Qty.
cum. 20.4413
cum. 1.1498 Bags
cum. 0.0884 4.8
cum. 0.3538
cum. 0.7075
cum. 4.7250 Bags
cum. 0.8591 37.8
cum. 1.2886
cum. 2.5773
Mtr. 83.2200 Kg
Mtr. 82.3200 156.8 12 MM
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
9/55
Sl. Item Name Unit L B H
1 Excavation Mtr. 2.65 3.95 1.5
2 PCC (1:4:8) Mtr. 2.35 3.65 0.1000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
3 RCC-Raft (1:1.5:3) Mtr. 2.2000 3.5000 0.5000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
4 RF steel- Raft-short side-Bottom Mtr. 2.7200 --- ---
5 RF steel- Raft-long side-Bottom Mtr. 4.0200 --- ---
6 RF steel- Raft-short side-Top Mtr. 2.7200 --- ---
7 RF steel- Raft-long side-Top Mtr. 4.0200 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
10/55
Unit Qty.
cum. 15.7013
cum. 0.8578 Bags
cum. 0.0660 3.6
cum. 0.2639
cum. 0.5278
cum. 3.8500 Bags
cum. 0.7000 30.8
cum. 1.0500
cum. 2.1000
Mtr. 66.1867
Mtr. 62.9800
Mtr. 50.3200 Kg
Mtr. 48.2400 215.7
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
11/55
Sl. Item Name Unit L B H
1 Excavation Mtr. 3.15 4.45 1.5
2 PCC (1:4:8) Mtr. 2.85 4.15 0.1000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
3 RCC-Raft (1:1.5:3) Mtr. 2.7000 4.0000 0.5000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
4 RF steel- Raft-short side-Bottom Mtr. 3.2200 --- ---
5 RF steel- Raft-long side-Bottom Mtr. 4.5200 --- ---
6 RF steel- Raft-short side-Top Mtr. 3.2200 --- ---
7 RF steel- Raft-long side-Top Mtr. 4.5200 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
12/55
Unit Qty.
cum. 21.0263
cum. 1.1828 Bags
cum. 0.0910 5.0
cum. 0.3639
cum. 0.7278
cum. 5.4000 Bags
cum. 0.9818 43.2
cum. 1.4727
cum. 2.9455
Mtr. 89.0867
Mtr. 85.8800
Mtr. 67.6200 Kg
Mtr. 65.5400 291.9
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
13/55
Sl. Item Name Unit L B H
1 Excavation Mtr. 3.65 4.65 1.5
Mtr. 2.9 2.25 1.5
2 PCC (1:4:8) - 3.35 X 4.35 Mtr. 3.35 4.35 0.1000
2 PCC (1:4:8) - 2.6 X 1.95 Mtr. 2.6 1.95 0.1000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
3 RCC-Raft (1:1.5:3)- 3.2 X 4.2 Mtr. 3.2000 4.2000 0.5000
3 RCC-Raft (1:1.5:3)- 2.45 X 1.8 Mtr. 2.4500 1.8000 0.5000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
4 RF steel- Raft-short side-Bottom Mtr. 3.7200 --- ---
5 RF steel- Raft-long side-Bottom Mtr. 4.7200 --- ---
4 RF steel- Raft-short side-Bottom Mtr. 5.5200 --- ---
5 RF steel- Raft-long side-Bottom Mtr. 2.9700 --- ---
6 RF steel- Raft-short side-Top Mtr. 3.7200 --- ---
7 RF steel- Raft-long side-Top Mtr. 4.7200 --- ---6 RF steel- Raft-short side-Top Mtr. 5.5200 --- ---
7 RF steel- Raft-long side-Top Mtr. 2.9700 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
14/55
Unit Qty.
cum. 25.4588 Cum
cum. 9.7875 35.2
cum. 1.4573
cum. 0.5070 Bags
cum. 0.1511 8.2
cum. 0.6044
cum. 1.2088
cum. 6.7200
cum. 2.2050 Bags
cum. 1.6227 71.4
cum. 2.4341
cum. 4.8682
Mtr. 55.8000
Mtr. 125.5520
Mtr. 113.7120
Mtr. 45.7380
Mtr. 47.1200
Mtr. 105.4133Mtr. 95.6800 Kg
Mtr. 38.6100 594.6
4200
2450
1800
5000
3200
A
B C
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
15/55
Sl. Foundation type Excavation (cum) Cement (bag) Sand (cum.) Stone (cum.)
1 F1-Excavation 9.34
2 F1-PCC 2 0.15 0.30
3 F1-RCC 12 0.40 0.80
4 F1-steel
5 F2-Excavation 9.74
6 F2-PCC 2 0.16 0.31
7 F2-RCC 12 0.42 0.84
8 F2-steel
9 F3-Excavation 18.34
10 F3-PCC 4 0.31 0.63
11 F3-RCC 30 1.01 2.02
12 F3-steel
13 F4-Excavation 20.44
14 F4-PCC 5 0.35 0.71
15 F4-RCC 38 1.29 2.58
16 F4-steel
17 CF1-Excavation 15.7018 CF1-PCC 4 0.26 0.53
19 CF1-RCC 31 1.05 2.10
20 CF1-steel
21 CF2-Excavation 21.03
22 CF2-PCC 5 0.36 0.73
23 CF2-RCC 43 1.47 2.95
24 CF2-steel
21 CF3-Excavation 35.25
22 CF3-PCC 8 0.60 1.21
23 CF3-RCC 71 2.43 4.87
24 CF3-steel
Gross Total 129.84 267 10.28 20.56
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
16/55
Steel (Kg.)
45.54
47.68
139.98
156.83
215.74
291.91
594.59
1492.26
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
17/55
Sl. Item Name Unit b1 b2 H
1 RCC-Column (1:2:4)-300 X 450 Mtr. 0.3000 0.4500 6.6000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Column-main Mtr. 1.0000 --- ---
3 RF steel- Column-tie-a Mtr. 1.4000 --- ---
4 RF steel- Column-tie-b Mtr. 0.9000 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
18/55
Unit Qty.
cum. 3.5640 Bags
cum. 0.6480 28.5
cum. 0.9720
cum. 1.9440
Mtr. 8.0000 3.7895 6.736842
Mtr. 8.4000 3.5368 Kg.
Mtr. 5.4000 2.2737 16.3
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
19/55
Sl. Item Name Unit b1 b2 H
1 RCC-Column (1:2:4)-300 X 450 Mtr. 0.3000 0.4500 6.6000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Column-main Mtr. 1.0000 --- ---
3 RF steel- Column-tie-a Mtr. 1.4000 --- ---
4 RF steel- Column-tie-b Mtr. 0.9000 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
20/55
Unit Qty.
cum. 3.5640 Bags
cum. 0.6480 28.5
cum. 0.9720
cum. 1.9440
Mtr. 8.0000 13.4737
Mtr. 8.4000 3.5368 Kg.
Mtr. 5.4000 2.2737 19.3
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
21/55
Sl. Item Name Unit b1 b2 H
1 RCC-Column (1:2:4)-400 X600 Mtr. 0.4000 0.6000 6.6000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Column-main Mtr. 1.0000 --- ---
3 RF steel- Column-tie-a Mtr. 1.7800 --- ---
4 RF steel- Column-tie-b Mtr. 1.0200 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
22/55
Unit Qty.
cum. 6.3360 Bags
cum. 1.1520 50.7
cum. 1.7280
cum. 3.4560
Mtr. 8.0000 21.0526
Mtr. 10.6800 4.4968 Kg.
Mtr. 6.1200 2.5768 28.1
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
23/55
Sl. Item Name Unit b1 b2 H
1 RCC-Column (1:2:4)-400 X600 Mtr. 0.4000 0.6000 6.6000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Column-main Mtr. 1.0000 --- ---
3 RF steel- Column-tie-a Mtr. 1.7800 --- ---
3 RF steel- Column-tie-b Mtr. 1.0200 --- ---
4 RF steel- Column-tie-c Mtr. 1.4800 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
24/55
Unit Qty.
cum. 6.3360 Bags
cum. 1.1520 50.7
cum. 1.7280
cum. 3.4560
Mtr. 8.0000 3.7895 21.052632
Mtr. 10.6800 4.4968
Mtr. 6.1200 2.5768 Kg.
Mtr. 8.8800 3.7389 35.7
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
25/55
Sl. Item Name Unit b1 b2 H
1 RCC-Column (1:2:4)-400 X600 Mtr. 0.4000 0.6000 6.6000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Column-main Mtr. 1.0000 --- ---
3 RF steel- Column-tie-a Mtr. 1.7800 --- ---
3 RF steel- Column-tie-b Mtr. 1.0200 --- ---
4 RF steel- Column-tie-c Mtr. 1.4800 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
26/55
Unit Qty.
cum. 6.3360 Bags
cum. 1.1520 50.7
cum. 1.7280
cum. 3.4560
Mtr. 8.0000 31.5789
Mtr. 10.6800 4.4968
Mtr. 6.1200 2.5768 Kg.
Mtr. 8.8800 3.7389 42.4
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
27/55
Sl. Item Name Unit b1 b2 H
1 RCC-Column (1:2:4)-400 X600 Mtr. 0.4000 0.6000 6.6000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Column-main Mtr. 1.0000 --- ---
3 RF steel- Column-tie-a Mtr. 1.7800 --- ---
3 RF steel- Column-tie-b Mtr. 1.0200 --- ---
4 RF steel- Column-tie-c Mtr. 1.0200 --- ---
4 RF steel- Column-tie-c Mtr. 1.4800 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
28/55
Unit Qty.
cum. 6.3360 Bags
cum. 1.1520 50.7
cum. 1.7280
cum. 3.4560
Mtr. 8.0000 31.5789
Mtr. 10.6800 4.4968
Mtr. 6.1200 2.5768
Mtr. 6.1200 2.5768 Kg.
Mtr. 8.8800 3.7389 45.0
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
29/55
Sl. Item Name Unit b1 b2 H
1 RCC-Column (1:2:4)-400 X600 Mtr. 0.4000 0.6000 6.6000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Column-main Mtr. 1.0000 --- ---
3 RF steel- Column-tie-a Mtr. 1.7800 --- ---
3 RF steel- Column-tie-b Mtr. 1.0200 --- ---
4 RF steel- Column-tie-c Mtr. 1.4800 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
30/55
Unit Qty.
cum. 6.3360 Bags
cum. 1.1520 50.7
cum. 1.7280
cum. 3.4560
Mtr. 8.0000 49.3421
Mtr. 10.6800 4.4968
Mtr. 6.1200 2.5768 Kg.
Mtr. 8.8800 3.7389 60.2
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
31/55
Sl. Foundation type Cement (bag) Sand (cum.) Stone (cum.) Steel (Kg.)
1 C1-RCC 29 0.97 1.94
2 C1-steel 16.34
3 C2-RCC 29 0.97
4 C2-steel 1.94 19.28
5 C3-RCC 51 1.73 3.46
6 C3-steel 28.13
7 C4-RCC 51 1.73 3.46
8 C4-steel 35.65
9 C5-RCC 51 1.73 3.46
10 C5-steel 42.39
11 C6-RCC 51 1.73 3.46
12 C6-steel 44.97
13 C7-RCC 51 1.73 3.46
14 C7-steel 60.15
Gross Total : 310 10.58 21.17 246.92
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
32/55
Sl. Item Name Unit B D L
2 PCC (1:4:8) Mtr. 0.3 0.225 136.9019
0.3 0.225 14.1603
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
33/55
Unit Qty.
cum. 9.2409 Bags
0.9558
cum. 0.7108 38.8
cum. 2.8433
cum. 5.6867
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
34/55
Sl. Item Name Unit B D L
1 RCC-Beam (1:1.5:3)-500 X300-PB1 Mtr. 0.3000 0.5000 136.9019
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
1 RCC-Beam (1:1.5:3)-500 X300-PB2 Mtr. 0.3000 0.5000 14.1603
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Beam-main-PB1 Mtr. 136.9019 --- ---
2 RF steel- Beam-main-PB2 Mtr. 14.1603 --- ---
3 RF steel- Beam-PB1-tie Mtr. 1.3800 --- ---
4 RF steel- Beam-PB2-tie Mtr. 1.3800 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
35/55
Unit Qty.
cum. 20.5353 Bags
cum. 3.7337 164.3
cum. 5.6005
cum. 11.2011
cum. 2.1240 Bags
cum. 0.3862 17.0
cum. 0.5793
cum. 1.1586
Mtr. 821.4114 1,383.43
Mtr. 99.1221 166.94
Mtr. 1,260.8775 530.90 Kg.
Mtr. 131.6548 55.43 2,136.7
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
36/55
Sl. Item Name Unit B D L
1 RCC-Beam (1:1.5:3)-300 X700-PB1 Mtr. 0.3000 0.7000 36.9930
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Beam-main-PB1 Mtr. 36.9930 --- ---
3 RF steel- Beam-PB1-tie Mtr. 1.7800 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
37/55
Unit Qty.
cum. 7.7685 Bags
cum. 1.4125 62.1
cum. 2.1187
cum. 4.2374
Mtr. 221.9580 373.8240 Kg.
Mtr. 440.7636 185.5847 559.4
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
38/55
Sl. Item Name Unit B D L
1 RCC-Beam (1:1.5:3)-300 X700-PB1A Mtr. 0.3000 0.7000 15.9230
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Beam-main-PB1 Mtr. 15.9230 --- ---
3 RF steel- Beam-PB1-tie Mtr. 1.7800 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
39/55
Unit Qty.
cum. 3.3438 Bags
cum. 0.6080 26.8
cum. 0.9120
cum. 1.8239
Mtr. 95.5380 160.9061 Kg.
Mtr. 190.7329 80.3086 241.2
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
40/55
Sl. Item Name Unit B D L
1 RCC-Beam (1:1.5:3)-300 X600-PB2 Mtr. 0.3000 0.6000 87.2094
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Beam-main-PB1 Mtr. 87.2094 --- ---
3 RF steel- Beam-PB1-tie Mtr. 1.5800 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
41/55
Unit Qty.
cum. 15.6977 Bags
cum. 2.8541 125.6
cum. 4.2812
cum. 8.5624
Mtr. 523.2564 881.2739 Kg.
Mtr. 920.1857 387.4466 1,268.7
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
42/55
Sl. Item Name Unit B D L
1 RCC-Beam (1:1.5:3)-300 X600-PB2A Mtr. 0.3000 0.6000 64.7681
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Beam-main-PB1 Mtr. 64.7681 --- ---
3 RF steel- Beam-PB1-tie Mtr. 1.5800 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
43/55
Unit Qty.
cum. 11.6583 Bags
cum. 2.1197 93.3
cum. 3.1795
cum. 6.3590
Mtr. 388.6086 654.4987 Kg.
Mtr. 683.8040 287.9175 942.4
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
44/55
DesriptionF-1 F-2 F-3 F-4 CF-1 CF-2 CF-3 C-1 C-2 C-3 C-4 C-5
1 Excavation Cu-M 9.34 9.74 18.34 20.44 15.70 21.03 25.46
2 Back filling Cu-M
3 Disposal of surplus earth Cu-M
4 PCC 1:4:8 Cu-M 0.48 0.51 1.02 1.15 0.86 1.18 1.96 5 RCC-Raft (1:1.5:3) Cu-M 1.46 1.54 3.71 4.73 3.85 5.40 8.93 3.56 3.56 6.34 6.34 6.34
6 RCC-Column (1:1.5:3) Cu-M
7 Reinforcement steel
a) 8 mm dia Kgs. 5.81 5.81 7.07 10.81 10.81
b) 10 mm dia Kgs. 45.54 47.68
c) 12 mm dia Kgs. 139.98 156.83 215.74 291.91 594.59 3.79 3.79
d) 16 mm dia Kgs. 6.74 13.47
e) 20 mm dia Kgs. 21.05 21.05 31.58
f) 25 mm dia Kgs.
No. of Foundation 5 6 8 5 1 1 1 13 2 3 3 4
1 Excavation Cum 46.706 58.4325 146.73 102.21 15.701 21.0263 25.459 0 0 0 0 0
2 Back filling Cum 0 0 0 0 0 0 0 0 0 0 0 0
3 Disposal of surplus earth Cum 0 0 0 0 0 0 0 0 0 0 0 0
4 PCC 1:4:8 Cum 2.4088 3.0315 8.174 5.7488 0.8578 1.18275 1.9643 0 0 0 0 0
5 RCC-Raft (1:1.5:3) Cum 7.315 9.24 29.696 23.625 3.85 5.4 8.925 46.332 7.128 19.008 19.008 25.344
6 RCC-Column (1:1.5:3) Cum 0 0 0 0 0 0 0 0 0 0 0 0
7 Reinforcement steel
8 mm dia Kgs. 0 0 0 0 0 0 0 75.537 11.6211 21.221 32.438 43.251
10 mm dia Kgs. 227.7 286.053 0 0 0 0 0 0 0 0 0 0
12 mm dia Kgs. 0 0 1119.8 784.14 215.74 291.909 594.59 49.263 26.9474 0 11.368 0
16 mm dia Kgs. 0 0 0 0 0 0 0 87.579 26.9474 0 0 0
20 mm dia Kgs. 0 0 0 0 0 0 0 0 0 63.158 63.158 126.32 3
25 mm dia Kgs. 0 0 0 0 0 0 0 0 0 0 0 0
HVPNL KUNDLI 132 kV SWITCH
Control
Foundation
Please note that Excavation quantities are worked out with considering the working space 600mm for tower fdn and 300mm for equipme
Column
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
45/55
-0.147
0
Cement Ba
Cement Ba
Cement Ba
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
46/55
Sl. Item Name Unit B D L
1 RCC-Beam (1:1.5:3)-300 X600-PB2 Mtr. 0.3000 0.6000 10.5350
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Beam-main-PB1 Mtr. 10.5350 --- ---
3 RF steel- Beam-PB1-tie Mtr. 1.5800 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
47/55
Unit Qty.
cum. 1.8963 Bags
cum. 0.3448 15.2
cum. 0.5172
cum. 1.0343
Mtr. 63.2100 106.4589 Kg.
Mtr. 112.5487 47.3889 153.8
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
48/55
Sl. Item Name Unit B D L
1 RCC-Beam (1:1.5:3)-300 X600-PB2 Mtr. 0.3000 0.6000 26.8349
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Beam-main-PB1 Mtr. 26.8349 --- ---
3 RF steel- Beam-PB1-tie Mtr. 1.5800 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
49/55
Unit Qty.
cum. 4.8303 Bags
cum. 0.8782 38.6
cum. 1.3173
cum. 2.6347
Mtr. 161.0094 271.1737 Kg.
Mtr. 284.2409 119.6804 390.9
16.2999
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
50/55
Sl. Item Name Unit B D L
1 RCC-Beam (1:1.5:3)-230 X300-L1 Mtr. 0.2300 0.3000 110.1983
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Beam-main-PB1 Mtr. 110.1983 --- ---
3 RF steel- Beam-PB1-tie Mtr. 0.8400 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
51/55
Unit Qty.
cum. 7.6037 Bags
cum. 1.3825 60.8
cum. 2.0737
cum. 4.1475
Mtr. 661.1898 1,113.5828 Kg.
Mtr. 617.9505 260.1897 1,373.8
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
52/55
Sl. Item Name Unit B D L
1 RCC-Beam (1:1.5:3)-230 X300-L2 Mtr. 0.2300 0.3000 3.0000
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Beam-main-PB1 Mtr. 3.0000 --- ---
3 RF steel- Beam-PB1-tie Mtr. 0.8400 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
53/55
Unit Qty.
cum. 0.2070 Bags
cum. 0.0376 1.7
cum. 0.0565
cum. 0.1129
Mtr. 18.0000 30.3158 Kg.
Mtr. 17.6400 7.4274 37.7
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
54/55
Sl. Item Name Unit B D L
RCC-Beam (1:1.5:3) - Slab-P1 Mtr. 32.6920 0.15 10.5350
1 RCC-Beam (1:1.5:3) - Slab-P2 Mtr. 5.3880 0.1500 11.1253
a Cement --- --- ---
b Sand --- --- ---
c Stone --- --- ---
2 RF steel- Beam-Main Mtr. 11.1253 --- ---
3 RF steel- Beam-Distribution Mtr. 0.8400 --- ---
7/31/2019 BOQ Kundli Foundation Column Beam Lintel Slab
55/55
Unit Qty.
cum. 51.6615
cum. 8.9915 Bags
cum. 11.0278 71.9
cum. 2.4522
cum. 4.9044
Mtr. 66.7518 Kg.
Mtr. 63.1417 139.0