BOND PROGRAM UPDATE Building Tomorrow Today. Long Beach Community College District Citizens’ Oversight Committee. April 9, 2007. AGENDA. Completed Construction Projects Current & Upcoming Construction Projects South Quad Complex – Bid #2 LAC Central Plant Structure - PowerPoint PPT Presentation
Citation preview
BOND PROGRAM UPDATEBuilding Tomorrow Today
Long Beach Community College DistrictCitizens’ Oversight Committee
April 9, 2007April 9, 2007
AGENDAAGENDAAGENDAAGENDA
Completed Construction ProjectsCompleted Construction ProjectsCurrent & Upcoming Construction Current & Upcoming Construction
ProjectsProjects South Quad Complex – Bid #2South Quad Complex – Bid #2
LAC Central Plant StructureLAC Central Plant Structure
LAC Learning Resources Center – InterimLAC Learning Resources Center – Interim
LAC Learning Resources Center - StructureLAC Learning Resources Center - Structure
South Quad Complex StructureSouth Quad Complex Structure
PCC Central Plant & UtilitiesPCC Central Plant & Utilities
PCC Learning Resources CenterPCC Learning Resources Center
PCC Industrial Tech Phase 1PCC Industrial Tech Phase 1
PCC Industrial Tech Phase 2PCC Industrial Tech Phase 2What’s Next?What’s Next?Q & AQ & A
PCC CDC – 4/06 District Facilities &
Warehouse Complex – Opened 1/17/06
Men’s Gym Boiler Replacement – 4/06
PCC MM/NN Lighting Upgrade – 4/05
LAC Athletic Field – 3/06 South Quad Complex
Bid Pkg. #1 – 12/05 LAC/LRC Utilities–6/06 LAC Men’s Gym Façade
Replacement (FEMA & Insurance Funded)
East Campus Demolition
Various ProjectsVarious Projects
COMPLETED CONSTRUCTION PROJECTSCOMPLETED CONSTRUCTION PROJECTS
Construction 98.5% Complete
Relocation of Water Main and Reclaimed Water Lines
Coordinated with Central Plant
Relocates Major Utilities Out of
Golf Mall Clears Way for
Structures
South Quad Complex – Bid Package #2South Quad Complex – Bid Package #2
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
Part of Infrastructure Master Plan Improvements
Early Utility Package Under Construction
Awarded to Siemens on DBOM Contract
Construction Starts April; Contractor Mobilizing
Completion Anticipated Summer 2008
LAC Central Plant – StructureLAC Central Plant – Structure
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
Construction 50% Complete
Anticipate Completion June 2007
Modular Buildings to be Installed Saturday 3/31/07
Utility Installation Complete Under Previous Phase (Bid Pkg. #1)
Includes Retrofit of Building E Basement
LAC/Learning Resources Center – Interim FacilitiesLAC/Learning Resources Center – Interim Facilities
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
Re-Bid Opening 3/29/07 First Bids Rejected Move
Planning Underway Utility Installation
Complete Under Previous Phase (Bid Pkg. #1)
Anticipate Start in June 2007; Completion in December 2008
LAC/Learning Resources Center – StructureLAC/Learning Resources Center – Structure
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
Construction Begun; Approx. 35% Complete
Overlaps Central Plant Early Piping Due to Utility Conflicts
Additional Modern Classrooms, Multi-purpose Rm., Offices, etc.
Shifts Campus Center South of Carson off Lew Davis
South Quad Complex Structure (Bid Pkg. #3)South Quad Complex Structure (Bid Pkg. #3)
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
Part of Infrastructure Master Plan Improvements
Early Utility Package Under Construction; Approx. 98.5% Complete.
Allows Utility Installation while Structure is in Plan Check
Clears Way for Structure Structure in Plan Check DBOM Contract Awarded
to Siemens; Anticipate NTP April (NOI Issued)
PCC Central Plant & UtilitiesPCC Central Plant & Utilities
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
Awarded to Soltek Pacific Construction Start in April
Pending State Authorization
Modern Facility with Computer Lab and Multimedia
Expanded Facility Bridge to Bldg. EE Art Deco Style
PCC Learning Resources CenterPCC Learning Resources Center
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
Replaces Existing Antiquated Structures
DSA Reviewing Changes; Out to Bid; Start in July 2007
Modern Facility Houses Machine Tools and Welding Depts.
New Campus “Bookend” S.E. Interim Bungalow
Construction In Close Out Phase to Clear Tech 1 Site
PCC Industrial Technology Center Phase 1PCC Industrial Technology Center Phase 1
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
Replaces Existing Antiquated Structures
Construction Underway; Approx. 53% Complete
PCC Industrial Technology Center Phase 2PCC Industrial Technology Center Phase 2
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
CURRENT & UPCOMINGCONSTRUCTION PROJECTS
Modern Facility Houses Aviation and Automotive Depts.
Impacted by DF&WC
Completion in Summer 2007
Student Services Centers – LAC Planning Underway;
Construction to Start at End of South Quad Complex
– PCC Awaiting State Funding; Will Start Construction in 2009/2010
– Centralizes Student Support Services (Admissions, Financial Aid, Cashier, Counseling, Job Placement, etc.)
Secondary Projects LAC & PCCSecondary Projects LAC & PCC
WHAT’S NEXT?WHAT’S NEXT?
Multi-Disciplinary Academic Buildings (AA, BB, DD, EE)
– Awaiting State Approval to Start Design; Antic. August 2007
– Construction 2009– Retrofits Most of Existing
Occupants in More Efficient Facility
– Classrooms and Offices– Labs Including Computer, Art,
Foreign Language, English, and Science Labs
– Absorbs Some Portable Occupants
New Building M Gym (Q & R) Projects Building E & F