1 Bond Measures Transform Peralta Facilities Capital Projects & Maintenance Status Report Presented by Dr. Sadiq B. Ikharo Vice Chancellor General Services April 12, 2011

Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

1

Bond Measures Transform PeraltaFacilities Capital Projects & Maintenance

Status Report

Presented by Dr. Sadiq B. IkharoVice Chancellor General ServicesApril 12, 2011

Page 2: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

2

Contents

Overview……………………………….…. 3Program Operation…………………….…13Data Support…………….................…....23Sustainability…………….................…....30Small & Local Business Participation…..37The Dollars………………………………..47The Projects………………………………56

Page 3: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

3

Overview

Page 4: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

4

Background

$390 million Measure A bond passed on June 6, 200674.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont and AlbanyProceeds to construct and rehabilitate educational and administrative buildings, grounds and infrastructure; acquire furnishings and equipment; and purchase or lease real property Trustees directed that majority of expenditures be maximized through a planned approachBottom-up, shared-governance-directed Educational and Facilities Master Plans craftedSmall portion of funds spent immediately on health and safety situations and acquisition of badly needed technology equipment as identified by each college

$153.2 million Measure E Bond passed in November 2000Portion of proceeds combined with Measure A funds to realize specific projects

State of California Matching FundsIncluded in budgeting for new Laney Library and Merritt Child Care CenterProjects on hold pending receipt of state funds

Page 5: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

5

Citizens Oversight Committee

California Proposition 39 passed in 2000 directs certain Measure A requirements

Mandates District-appointed Citizens' Oversight CommitteeDesignates membership to represent specific groupsMeets several times a year to review projects and expenditures

Current MembersHelene LeCar, President, Community at LargePolly Amrein, Senior Citizens’ OrganizationBill Patterson, Peralta FoundationKaren Friedman, Peralta FoundationJim Stonehouse, Taxpayer’s OrganizationKate Quick, Community at LargeOdell Johnson, Senior Citizens’ OrganizationJurena Storm, Student Representative

Page 6: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

6

Bond Rating

Standard & Poor’s affirmed its “AA-” rating on District’s General Obligation bonds

Rating indicates ability to pay off debt

AA- is considered a strong rating

Findings cited District adoption of FY 2009-10 budget and improved accounting systems

Page 7: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

7

Measure A Bond Sales & Expenditures

A total of $275 million has been sold to date$ 75 million on 08/01/2006

$ 100 million on 11/12/2007

$ 100 million on 09/14/2009

Balance remaining is $115 million

Soon to be released FCMAT analysis will report on interest earned

Overview

Page 8: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

8

Fiscal and Performance AccountabilityMeasure A spending is subject to two audits

Financial StatementsReviews fiscal management and reporting done by PCCD’s Finance Department

PerformanceDetermines whether District expenditures are in accordance with bond, State law, and District legal dictates and policies

Audits conducted by Vavrinek, Trine, Day & Co. LLP, CPA’sAudit reviews cover entire program: colleges, District-wide & DAC“Unqualified” opinion earned on FY 2008-09 and FY2009-10 audits

“Unqualified” indicates the auditor did not detect any significant internal control breakdownsPerformed according to generally accepted auditing standards (GAAS) to ensure that internal controls are adequate, functional and established in conformity to laws and regulations

Findings from FY 2008-09 audit:Performance Audit passed with no significant issues identifiedThree process issues identified in the Financial Statements Audit have been corrected:

Inter-fund borrowing allowance documentation; accounts payable fiscal year-end cut-out procedures; and prior year audit adjustments posting

Findings from FY 2009-10 auditPerformance Audit passed with no significant issues identifiedFive process issues identified in the Financial Statements Audit have been corrected:

Inter-fund borrowing allowance documentation; accounts payable fiscal year-end cut-off procedures; audit adjustments postings; payroll expense allocations; and Oversight Committee meeting quorums

Page 9: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

9

Litigation

No litigation related to the District’s implementation and management of the Measure A Bond.

District successfully negotiated a settlement agreement in Berkeley City College construction litigation

Prime contract approx. $43 millionDistrict is legally mandated to withhold 10% ($4.3 million) of total contract until project is fully complete and passes all inspections and close outSubcontractors sued prime contractor and District for non-payment of fees (prime contractor responsibility)Prime contractor sought additional fee payment from District of $12 millionSettlement negotiated down to $1 million dollars

Page 10: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

10

Accreditation

District awarded a commendation from the Accrediting Commission for Community and Junior Colleges (ACCJC)

2009 recognitionRelated to Educational Master PlanningHonored for shared governance related to facility planningAcknowledged colleges’ participation in planning and deployment

Page 11: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

11

Shared Governance

Important component of capital projects decision-makingImplemented through Planning and Budgeting Integration Model (PBIM)

Core response to Accreditation recommendation regarding collective establishment of coordinated planning and budgeting systemDistrict-wide structure for decision-making recommendationsIntegrates planning and budgeting across all colleges and district officesProvides transparent processSystem of four committees to receive planning inputs from colleges and make recommendations to Chancellor

Facilities Committee addresses capital program

Page 12: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

12

Shared Governance: PBIM StructureBoard of Trustees

Chancellor/SMT

District Planning & Budgeting Council

District Facilities Committee

BCC COA Laney Merritt

Draft Initiatives

Draft Initiatives

Integrated Planning & Budgeting Priorities

Page 13: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

13

Program Operation

Page 14: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

14

Program Planning

Integrated Facilities Master Plan with Educational Master Plans from each college to direct campus retooling

Balances forward movement, immediate needs such as protecting heath, safety and accessibility, and responds to unforeseen emergencies demanding quick actionSupports District’s educational direction by guiding repair, upgrade and replace decisions for buildings, infrastructure and equipment

Documented structural, mechanical, plumbing, electrical, technology, landscaping, and civil engineering components of every building on every campus, except those either in-design for substantial modernization or under construction

Delivers guidelines and standards in numerous areas including: sustainability; energy efficiency; landscaping; information technology, communications; infrastructure; utility and mechanical systems; graphics and signage; security; circulation, parking and more

Conducted district-wide energy audits to better determine energy usage by equipment

Combines five-year-view of project priorities with ten-year projection of project needs

Page 15: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

15

Program Budgeting

Trustees approved Budget and Spending Plan in June 2009

Contains spending parameters and expenditure detail Helps guide bond sales by projecting timing and amountsSpecifies general overhead, including management and communications, and contingency reserveIncludes five-year cash flow projections for each college, the District Administrative Center and District-wide projects Prescribes process to redirect funds within respective allocations; inform interested and involved parties of requested and approved changes; and provide approval documentation

Page 16: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

16

Program Management

Strategic decision to internally manage the Measure A programProjected to save the District over $15 millionMaximizes dollars available for projectsReduces overhead outlay

Instead of contracting with an outside construction program management company

Develops internal capacity that can be applied to ongoing and future facilities projects

Staff positions include: Director of Capital Outlay; Project Managers (2); Facilities Planning and Development Manager; Move Manager; Design Manager; Buyer; Senior Secretary; and Clerical Assistant

Provides more direct and immediate accountability Delivers greater transparency for stakeholders and others

Page 17: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

17

Project Delivery Methods

District primarily using following delivery methodsDesign-bid-build

Traditional approach/standard delivery methodologyAdvantages: Widely used; institutionalized; linear progression; allows funding in phases; hands-onDisadvantages: Adversarial; no incentive for low bidder to provide right price; builder’s expertise missing; often leads to litigation

Design-buildRecently approved for use by community collegesUsed for Laney Athletic Complex project, COA boiler house and Merritt solar installation.Advantages: Accelerated project delivery time; most opportunity for innovation; high valueDisadvantages: Significant upfront time; difficult to review proposals; required approvals and approval agencies; institutional capabilities; different insurance requirements

Multiple PrimesConstruction manager (CM) hired in lieu of general contractor (GC)Advantages: Closer relationship to each trade/contract; no mark-ups on trade contracts; Hands-on all project aspectsDisadvantages: Owner/CM acts as GC; directly responsible for trades coordination; increased paperwork/processing

Page 18: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

18

Vendor Performance Evaluation

Process and supportive documentation created to monitor and evaluate contractor performance

Separate forms for professional services and capital projectsCreates record of excellent, adequate or poor performance with issues detailProvides documentation in event of debarment

Penalty levied on vendor for egregious and/or illegal behavior or performanceVendor precluded from doing business with District for one (1) year

Page 19: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

19

Vendor Performance Evaluation

Professional Services

PROFESSIONAL SERVICES PERFORMANCE EVALUATION FORM To be completed by College President and Business Manager for consideration of contract renewal. Location District BCC COA Laney Merritt Vendor ICC # Vendor Number Date: CONTRACT INFORMATION Contract Title Funding Term of Performance Vendor’s key personnel

Original contract amount Amendments Change Orders and Percentages (%) Final contract amount

SCHEDULE & BUDGET – Did vendor meet realistic schedules and was deliverables within budget? Yes No (Explain)

PERFORMANCE RATING SCORE Provide a score for each criteria with 5 being the highest and 1 the lowest. 1 = Outstanding 2 = Great 3 = Good 4 = Improvement Needed 5 = Unacceptable Work performed in compliance with contract terms, scope of work and Peralta’s expectations

Deliverables provided, as required Staff availability and accessibility Staff professionalism Customer service Verbal Communication – understood directions and instructions clearly Prompt and effective correction of situations and conditions Documentation records, receipts, invoices and computer generated reports received in a timely manner and in compliance with contract specifications

TOTAL SCORE: OVERALL PERFORMANCE: Outstanding Great Good Improvement Needed Unacceptable

CAPITAL PROJECTS

DEPARTMENT OF GENERAL SERVICES—PROJECT EVALUATION FORM Vendor: Vendor No.: Date: This evaluation from is to be used by the Department of General Services and external Project Managers and Construction Managers to evaluate all projects including Consultants contracts. The Department of General Services recognizes that Consultant cannot improve or sustain good performance without project-specific constructive feedback. This evaluation is to provide constructive feedback and will be kept on file for review for future consultant selection. Interim evaluations are used to give timely performance feedback, and allows opportunity for performance modification to ensure the project’s success. Final evaluation is used for future Consultant selection, and helps the District’s General Services Department develop and hire the best possible firms. PROJECT INFORMATION Project No: Project Name:

Project Start Date:

Location of Project: % Complete:

Scope of Work:

Type of Work:

Facilities Project Manager:

Firm Name: Consultant Project Manager:

Evaluation Date: Evaluation Type: (Check one) Interim or Final

RATING SYSTEM DEFINITIONS

Scale Rating Name Rating Description

5 Outstanding Deliverables exceed standards with minimal District General Service’s direction; seeks opportunities for self-improvement; models, coaches and inspires excellent service; owns project problems and offers analysis of resolution options.

4 Great Deliverables exceed standards with some District General Service’s direction; frequently checks in on status of service and provides consistent quality service; identifies project problems in advance and offers timely alternative options.

3 Good Deliverables meet standards with some District General Service’s direction; provides expected service and quality checks required by the contract; helps to analyze and resolve problems as they occur.

2 Improvement Needed

A comment is required. Deliverables eventually meet minimum standards with frequent District General Service’s coaching required; provides mediocre service, rarely checking for feedback; unaware of problems until discovery by others, then provides weak solution analysis.

1 Unacceptable A comment is required. Deliverables are substandard even with frequent District General Service’s coaching; rarely provides expected service and no quality service checks are evident; unaware of problems until discovery by others, then unable to provide analysis or resolution options.

Report Examples (first pages)

Page 20: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

20

Project Labor Agreement

Formal agreement between PCCD and Alameda County Building and Trades

Approved by TrusteesLabor unions agree to settle disputes without strikes, lockouts, work slow downs or stoppagesDistrict contractors must abide by union rules on membership, work rules and employee compensationSLEB/SELBE participation Impacts

Decreased project participation by small businesses unable to meet union workforce requirements

Page 21: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

21

Maintenance and Operations Impacts

Measure A Implementation directly impacts maintenance and operations responsibilities of the Facilities and Operations Division

Division presently composed of a Director, sixteen Engineers, ten Grounds personnel, two Custodians, and one Administrative Clerk Seven positions remain unfilled this and the previous FY 2009-2010 fiscal year Present year staffing is 23% less than two years ago, yet increased productivity has occurred Additional training may be required when new equipment brought on line through building remodel or new building commissioningUpcoming, highly-complex buildings may require that engineering crew be augmented with additional trained personnelGrounds personnel can stay as presently configured since new buildings decrease groomed area by each new building’s footprint Custodial must fill one of its two vacant swing shift positions

Total Cost of Ownership (TCO) of future buildingsDeferring future repair through extended warranties has proven cost effective at BCC Annual recurring expenses associated with day-to-day maintenance and operationsRecapitalization costs including periodic recurring expenses i.e. retrofits and modernizations

Leave building shell but replace worn equipment while upgrading habitability and functionality

Page 22: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

22

Public Education

Education and outreach initiatives to inform PCCD internal and public external audiences about Measure A progress and successes

NewslettersCommunity reportOversight Committee toursSpecial events and ribbon-cuttingsBus tour for publicInformation on websiteSocial networking sitesPublic reports

Page 23: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

23

Data Support

Page 24: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

24

Primavera Data Management

In-house program management data supportRobust project scheduling and tracking Web interface allows stakeholders to track projectsConsolidated all-on-one reportingEasy viewing of project status, the dollars, contractors, funding sources, and start and end datesHelps determine realistic plans and proposalsStrengthens ability to analyze and manage construction schedules and control change ordersSupports audit reconciliationsSupports documentation requirements

Page 25: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

25

Completed Projects Report Example

Page 26: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

26

Projects in Progress Report Example

Page 27: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

27

Future Projects Report Example

Page 28: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

28

College Construction Schedule Report Example

Page 29: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

29

Projects Summary Report

Page 30: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

30

Sustainability

Page 31: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

31

Sustainability: Board Policy 2.40Board Commitments

Pursue responsible environmental sustainability as a policy consistent with the District’s primary educational missionIntegrate values of sustainability, stewardship, and resource conservation in physical environment interactionsEngage in pollution prevention activities and develop and promote practices that maximize beneficial effects and minimize harmful effects of operations and activities on surrounding environment Carry out efforts in ways that save significant financial resources through energy and other resource conservationMaximize energy efficiency particularly in heating, cooling, lighting, information technology, mechanical, and water systems Exceed State of California Building Code Title 24 energy efficiency requirements by no less than 35%Create a plan to reduce greenhouse gas emissions caused by energy consumption by 50% within five years of Dec. 2007Become “carbon neutral” within ten years from Dec. 2007Employ sustainable landscaping and grounds design, construction and maintenance practices promoting integrated pest management and use of drought tolerant, fire safe, and native vegetation typesUse LEED (Leadership in Energy and Environmental Design) or equivalent certification criteria in renovations over 10,000 square feet and all new-building construction Use low and no VOC paints and low-toxicity cleaning supplies, establishing clear construction protocols with contractors, etc.

Page 32: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

32

Sustainability: Implementation

Progress being made in meeting Board policy goalsSpecific conservation focus is moving PCCD to be more environmentally responsible

New and retrofitted buildings includedLEED experienced architects and construction firms being hiredSustainability-minded design parameters for new buildings

Page 33: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

33

Sustainability Benefits to District

Measure A sustainability projects have reduced use of natural resources and shifted operations towards resource efficienciesProjects have also financially benefited District

T-12 to T-5 lighting conversion$133,000 rebate from PG&E$90,000/year utility reduction

Chevron ES Early Action Program Efficiency Projects$131,000 rebate from PG&E$300,000/year utility reduction (est.)

Laney College & District Office Recycled Water tie-in$7,500/year water reduction

Merritt College Solar PV$275,000/year rebate from PG&E (5yr) $210,000/year utility reduction

Weather-Based Irrigation Controls$40,000 rebate from EBMUD

COA Bay Friendly Entryway$20,000 grant from StopWaste.org

Laney College Culinary Arts to Garden Closed-Loop Composting$25,000 grant from StopWaste.org

Page 34: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

34

Sustainability: Achievements

BCC awarded new building LEED Silver certification1st in Berkeley

Energy efficient lighting installed district-wideNew air conditioning for Laney F&G buildingsHVAC run-time schedules adjusted and equipment programmed district-wideOld boiler systems replaced at COADistrict offices air handling system retrofittedNew recycled water irrigation installedMerritt 1.2Mw solar farm installed

Offset college’s electricity use by 40%Results in annual savings of $240,000Annual $312,000 savings for 5 years from rebates and net metering

Page 35: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

35

Sustainability: Current Projects

LaneySolar PV

Panels installed as new parking lot canopies and on rooftopsMonthly generation between 4K and 13K KWh Projected annual energy savings of $161,700$1,133,500 in rebates over 5 years

CogenerationRFP being developed to heat pool and produce electricity

Induction lighting replacementRecent partnership with City-operated Oakland Shines to replace outside lighting

BCCSolar PV

Panels installed over parking areasMonthly generation between 46K and 150K KWhProjected annual electricity use off-set of 10%

Page 36: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

36

Sustainability: Future

Another round of energy conservation projects being plannedAll projects qualify for PG&E incentive funds

Monitoring-based CommissioningUtilizes existing meters to find mechanical system trouble spots.

PC workstation power monitoringSoftware powers-down computers and servers at scheduled intervals

Plug load occupancy sensorsPowers down devices when no humans are nearby

Pool coversMinimize evaporation of water

District desire to be completely powered by renewable energy by 2017 could be impacted by funding situation

Page 37: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

37

Small and Local Business Participation

Page 38: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

38

Local Business: Board Policy 6.90

Board CommitmentEnsure equal opportunity and equitable treatment in awarding and managing public contractsEncourage and facilitate full and equitable opportunities for small local business enterprises (SLBE) and small emerging local business enterprises (SELBE) in prime and subcontractingAnnual overall SLBE program goal of twenty-five percent (25%)Chancellor issues Implementing Procedures

Page 39: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

39

Local Business: Implementation

OutreachOpportunities posted on District websiteParticipation in local vendor outreach eventsSpecifically-targeted efforts conducted on Laney Athletic project; included phone, email, public meeting & advertising

StrategiesUnbundling work scopes

Break work scopes up into smaller pieces to allow for greater participation by small businesses

Page 40: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

40

Small Local Business Definitions

Local business must be located at a fixed, established commercial address located in the District’s market area of Albany, Alameda, Berkeley, Emeryville, Oakland, or Piedmont, and not a temporary or movable office, post office box, or telephone answering serviceSmall business enterprises defined as:

Small Local Business Enterprise (SLEB)Over the past 3 years revenue of less than $8.5 million annually for a construction firm, $6 million for goods and non-professional services or $3 million for architecture, engineering and professional services

Small Emerging Local Business Enterprises (SELBE)Over the past 3 years revenue of less than $1.5 million annually

Both must meet geographic location requirements

Page 41: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

41

Small and Local Business Participation

10.9%51.6%312009-10**44.5%77.4%312008-0914.1%39.4%332007-08

23.4%64.0%502006-07

% of DollarsSLBE Participation# Bids AwardedFiscal Year

SLEB Participation for 2006 - 2010

25.5%$ 15,953,010$ 62,450,1252009-10**33.1%$ 25,610,231$ 77,320,5202008-0925.5%$ 19,912,333$ 78,003,211 2007-0816.6%$ 13,504,230$ 81,297,769 2006-07

Total % to LocalTotal Local & SLEBTotal SpendingFiscal Year

Total Spending – SLEB & Local Firms for 2006 - 2010

** PLA enacted

Page 42: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

42

Local Business Participation Project Management & Construction Management

Project Management (PM) and Construction Management (CM) Contracts overwhelmingly awarded to local businesses

Measure E– 75% to local businesses from 2004 -2011Measure A– 77% to local businesses from 2006 -2011

Page 43: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

43

Local Business Participation Project Management & Construction Management

Measure A Expenditures for Project Management & Construction Management Services 2006-20011

77%

23%

PM/CM Local Participation PM/CM Outside Local Area

Measure E Expenditures for Project Mananagement & Construction Management 2004-

2011

75%

25%

PM/CM Local Participation

PM/CM Outside Marke Area

Page 44: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

44

Local PM CM Measure A

Page 45: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

45

Local PM CM Measure E

Page 46: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

46

Small & Local Business Future Opportunities

Remaining projects are very largeMost small projects are completedDesign-build and/or multiple primes methodology will be usedDistrict will continue outreachDistrict will work with primes to package work small enough for SLEB/SELEB participation (unbundling)District will work with/require primes to do active outreach to SLEB/SELEB companies

Especially for under represented firms

Page 47: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

47

The Dollars

Page 48: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

48

Measure A Total Program Overview

Completed Projects: $ 102,763,861

Projects In Progress: $ 196,290,706

FF&E & Computers $ 35,632,719

Future Projects: $ 55,312,714

GRAND TOTAL: $ 390,000,000

Page 49: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

49

Measure A Program Status Overview

$196,290,706

$102,763,861$55,312,714

$35,632,719 CompletedIn ProgressFF&E + IT*Future

*Furniture, Fixtures & Equipment + Computers

Page 50: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

50

Measure A Budget Summary

GRAND TOTAL $ 390,000,000

BCCCapital Projects: $ 19,100,000Bldg. Improvements: $ 1,660,000 FF&E: $ 3,894,827TOTAL: $ 24,654,827

COACapital Projects: $ 54,507,829Bldg. Improvements : $ 9,681,726FF&E: $ 6,885,288Other: $ 2,000,000TOTAL: $ 73,074,843

MerrittCapital Projects: $ 71,205,390Bldg. Improvements: $ 12,429,000FF&E: $ 7,393,526 Other: $ 2,200,000TOTAL: $ 93,227,916

LaneyCapital Projects: $ 108,486,885Bldg. Improvements:$ 23,294,280FF&E: $ 12,504,868Other: $ 604,045TOTAL: $ 144,890,098

District-wideCapital Projects $ 18,522,816FF&E $ 5,649,652Other: $ 19,926,007TOTAL $ 44,098,475

DACCapital Projects : $ 6,854,455FF&E: $ 3,199,386TOTAL: $ 10,053,841

Page 51: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

51

Measure A Allocations Dollars

$10,053,841$44,098,475

$73,074,843

$24,654,827

$93,227,916

$144,890,098

BCCCOALaneyMerrittDACDist-wide

Page 52: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

52

Measure A Allocation Percentages

6%19%

37%

24%

3%11%

BCCCOALaneyMerrittDACD-W

Page 53: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

53

Measure A Budget – Expended - Balance

$ 16,753,150$ 27,345,325$ 44,098,475Dist-wide$ 265,184,453$ 124,815,547$ 390,000,000 TOTAL

$ 2,835,918$ 7,217,923$ 10,053,841DAC$ 74,349,002$ 18,878,914$ 93,227,916Merritt

$ 101,626,367$ 43,263,731 $ 144,890,098Laney$ 51,237,421 $ 21,837,422$ 73,074,843COA

$ 18,382,595$ 6,272,232$ 24,654,827BCCBalanceExpendedTotal BudgetSite

Page 54: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

54

Furniture, Fixtures, Equipment & Computers

$ 21,452,136$ 25,072,410$ 46,524,546TOTAL

$ 2,796,330$ 9,850,322$ 12,649,652District-wide IT*$ 1,237,533 $ 1,961,853$ 3,199,386Dist. Admin, Ctrs.$ 3,608,657$ 3,784,869$ 7,393,526 Merritt College$ 6,951,686$ 5,553,182 $ 12,504,868 Laney College$ 4,743,317 $ 2,141,970 $ 6,885,287 College of Alameda$ 2,114,413 $ 1,780,414$ 3,894,827Berkeley City College

RemainingExpendedBudgetedSite

Measure A Expenditures thru 2/28/2011

*Budget transfer pending

Page 55: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

55

Management & Operations Expenditures

$ 13,789,906TOTAL

$ 1,464,966In-house Program Management & Operations

$ 1,836,772Department of General Services

$ 292,526Financial Services – Budget

$ 732,096Admissions & Records

$ 490,442Educational Services

$ 515,864Marketing - PCTV

$ 8,012,457Information Technology

$ 164,962General Counsel

$ 57,058Chancellor’s Office

$ 222,763Board of Trustees

TOTAL EXPENDITUREDEPARTMENT

In-house Program Management & Operations From 7/1/06 thru 6/30/10

Page 56: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

56

The Projects

Page 57: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

57

Awards

Measure A projects have earned multiple awards and honors

Laney Student Center: CCFC Award of Excellence for Master PlanningLaney Culinary Academy: CCFC Award of Merit for Merritt : Award of Merit for Student CenterBCC: US Green Building Council LEED Silver CertificationBCC: CCFC Award of Merit for Campus CompletionMerritt Student Center: American Schools and Universities Award of Excellence

Page 58: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

58

Berkeley City College

Page 59: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

59

Berkeley City College Completed Projects

Short-term renovations, including campus wide ADA upgrades

Existing Building Build-outInterior finishing of new buildingBuild-out 3rd & 4th floorsNew, large tiered classroomFlexible configuration classroomStudent services & administration offices

Page 60: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

60

Berkeley City College Current Projects

Campus Expansion (additional facility acquisition)Existing Building Build-out

Build-out 5th floorsWet & dry science labsArt spaceStudent club room Bookstore space

New Parking Facility (additional facility acquisition)Photo voltaics (solar panels)

Page 61: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

61

College of Alameda

Page 62: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

62

College of Alameda Completed Projects

Campus-wide sidewalk replacement Campus building renovations/short-term projects:

Ductwork cleaning & equipment renovationBathroomsGym; flooring, painting & lighting throughoutLocker roomsADA showers Dance floorRestroom upgradesWeight room renovationsDecking repairs

One-stop Student CenterDental Clinic renovation & Community Clinic build-out Tennis Courts

Page 63: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

63

College of Alameda Current Projects

C&D Science BuildingDesign-build methodologyProgramming completedCurrently creating schematics of architectural bridging documents

860 AtlanticScience and laboratories swing spaceGenomics program (Merritt)

Cougar Village ExpansionClassroom swing space

New, reconfigured access road including drought-resistant landscaping

Page 64: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

64

Laney College

Page 65: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

65

Laney College Completed ProjectsCulinary Kitchen & Bistro total build-outCampus-wide improvements

Gateway to college program renovations inc. class & office flooring, painting & electricalDisabled Students Programs & Services (DSPS) renovationsRefurbish restrooms & showersWelding labs upgradesCarpentry & wood tech classrooms upgradesChemistry classrooms upgradesCosmetology classrooms repairsDSPS swing spaceTunnel lighting upgradeInterim relocationTheater modificationsStudent welcome centerFitness renovationsComputer lab renovationsSecurity system installationComputer Lab & HVAC ImprovementsNew, expanded cooling for computer labAll rooftop mechanical equipment replaced

Page 66: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

66

Laney College Current Projects

Student Center Design-bid-buildComplete Building RenovationDSA approval grantedCurrently planing swing space

Athletic Complex & Parking LotParking lot completedBaseball field completedField house under constructionPhoto voltaic coming

Tower Building RefurbishmentDSA approval grantedPlanning swing space

Tower Swing SpaceTower 2nd Fl Relocation

Permanently moving financial aid & cashiers officeNew electrical, flooring & painting

Campus-wide ADA improvements & barrier removal

Page 67: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

67

Merritt College

Page 68: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

68

Merritt College Completed Projects

Photo Voltaic (solar panels)Installation on 2 sites

Tennis court upgradesImproved lighting & parking lot repairs & resurfacing

Page 69: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

69

Merritt College Current Projects

New, state-of-the art Allied Health BuildingDesign-buildArchitectural bridging documents completedDesign-build team advertising and prequalification pending

Genomics Program spaceLibrary & Learning Center renovationsLibrary swing spaceCampus-wide Modernizations

LightingSidewalks and handrails replacement

Building Q improvements w/ reconfigured and refurbished officesWaterproof Buildings D, Q & PGym UpgradeBldg. D ductwork cleaning & repair, including ultrasonic germ killerHorticulture Dept. Improvements with replaced lighting, new greenhouse water controls, pull-down power outlets, beams and roof dry rot repairsChild Care Center Improvements (pending state matching funds)

Page 70: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

70

District-wide

Page 71: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

71

District-wide Completed Projects

PavingLightingBoilers and Energy Usage Monitoring & ControlsLandscapingElevator Upgrades

Page 72: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

72

District-wide Current Projects

Smart ClassroomsPublic Safety & Security Improvements

Security camerasIT infrastructure

Police Control Services renovationLibrary TechnologySignage

Site IdentificationRoomsWay-finding

Peralta TV FacilityNew portablesLandscapingFurnishingsControl room equipment

Page 73: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

73

District Administrative Center

Page 74: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

74

District Administrative Center Current Projects

None

Page 75: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

75

District Administrative Center Completed Projects

Office RenovationsNew Rooftop HVAC mechanicalsInternational Student Program Facilities

New modular buildingUpgrade of existing buildingPaintingLandscapingNew tension structure

Emergency Generator Replacement & Power Upgrade

Page 76: Bond Measures Transform Peralta · 4 Background $390 million Measure A bond passed on June 6, 2006 74.7% approval by the voters of Oakland, Alameda, Berkeley, Emeryville, Piedmont

76

Department of General Services Measure A Staff