Bond Construction Update Citizen’s Oversight Committee. Long Beach Community College District October 19, 2009. EDUCATE ENGAGE EMPOWER. Agenda. Completed Construction Projects LAC Carson Street Median Fence Replacement LAC Pool boiler upgrade - PowerPoint PPT Presentation
Citation preview
Bond Construction Bond Construction UpdateUpdate
Citizen’s Oversight Citizen’s Oversight CommitteeCommittee
Bond Construction Bond Construction UpdateUpdate
Citizen’s Oversight Citizen’s Oversight CommitteeCommittee
Long Beach Community College District October 19, 2009
EDUCATE ENGAGE EMPOWER 1
Agenda Completed Construction Projects
LAC Carson Street Median Fence Replacement LAC Pool boiler upgrade LAC CDC installation of new roof and playground equipment PCC MM Exterior renovation and ADA upgrades PCC added additional parking at corner of PCH and Walnut
Current & Upcoming Construction Projects LAC South Quad Complex LAC Building A, Student Services Retrofit LAC Math Technology Building LAC Parking Structure LAC Building O Complex LAC Infrastructure Improvements LAC Q & R ADA/HVAC UpgradesLAC Q & R ADA/HVAC Upgrades PCC Industrial Tech Phase 1 PCC MDAB (Multi-Disciplinary Academic Building) PCC Building CC Retrofit District Wide – Electronic Signage Plan District Wide - Energy RetrofitsDistrict Wide - Energy Retrofits Los Coyotes Property Upcoming Projects Planned Phasing of Future Projects
Q & A2
Current and UpcomingConstruction Projects
Construction approx. 99% Complete
Space includes Approx. 68,000 ASF 32 modern classrooms and labs 38 faculty offices Executive offices Multipurpose room State of the art Board Room
Substantial completion anticipated Fall 2009
South Quad Complex – Measure E 2002South Quad Complex – Measure E 2002
3
Current and UpcomingConstruction Projects
LAC Building A – Student Services RetrofitLAC Building A – Student Services Retrofit
Measure E 2008Measure E 2008
4
Plans submitted to DSA September 2009 Adds 6,500 Sq. Ft. to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction end of Spring 2010
Current and UpcomingConstruction Projects
Completed Schematic Design Will house Math and Culinary Arts instructional
program as well as Reprographics Estimated start of construction Winter 2013
LAC Math Technology Building – Measure E 2008LAC Math Technology Building – Measure E 2008
5
Current and UpcomingConstruction Projects
LAC Parking Structure – Measure E 2008LAC Parking Structure – Measure E 2008
6
Spaces for 900 Vehicles Photovoltaic Electrical Generation Array on top level To be located Southeast corner of Lot J adjacent to the Verizon building Outfitted with single-axis tracking system Minimum 450 KW+ output Curriculum building opportunity Exhibit classroom Groundbreaking January 22nd, 2010
Current and UpcomingConstruction Projects
LAC Building O Complex – Measure E 2008LAC Building O Complex – Measure E 2008
7
Property acquired December 2008
Two structures totaling 87,000 square feet
Occupants shall be: IITS, BMT, Warehouse Facility (operational), ERD, and Foundation Office (Relocated July 6th , 2009)
Tenant improvements underway on: ERD offices, elevator installation for bldg. 1
Potential rental spaces being assessed
8
LAC Infrastructure Improvement ProjectsLAC Infrastructure Improvement Projects
Measure E 2008Measure E 2008
Current and UpcomingConstruction Projects
Landscaping upgrades to be implemented in conjunction with infrastructure project phasing
Project to be completed in a phased construction schedule
Total annual estimated savings of 1.5 million Kwh
Project started Fall 2009. Anticipated completion Summer 2011
Upgrades include; Reclaimed Water, Domestic Water, Data, etc.
Majority of existing building HVAC systems to be connected to new infrastructure
Current and UpcomingConstruction Projects
9
Complete building ADA upgrade: includes restrooms, stair lift, etc. (Bldg. R)
All new infrastructure: new piping, fixtures, etc. (Bldg. R) Minor renovations to offices (Bldg. R) Total renovation of locker/training rooms (Bldg. R) HVAC upgrade: includes new air handlers, ductwork, etc.
(Bldg. Q & R) Update fire alarm system (Bldg. Q & R) Construction will be done in phases so as to minimize
disruption of classes Final construction documents to be submitted to DSA Fall
2009 Estimated start of construction Summer 2010
LAC Q & R ADA/HVAC - Measure E 2008LAC Q & R ADA/HVAC - Measure E 2008
Current and UpcomingConstruction Projects
Modern facility houses Welding Department and other trade programs
Construction is 98% complete Replaces existing antiquated
structures New Northern face of the campus Completion anticipated late Fall 2009
PCC Industrial Technology Center Phase 1PCC Industrial Technology Center Phase 1
Measure E 2002Measure E 2002
10
Current and UpcomingConstruction Projects
PCC MDAB PCC MDAB (Multi-Disciplinary Academic Building) - Measure E 2002(Multi-Disciplinary Academic Building) - Measure E 2002
11
Received reviewed plans from DSA. Currently in construction drawing technical review phase Install portables for swing space at PCC Fall 2009 Anticipated start of MDAB construction Spring 2010 Project to be completed in two phases
Current and UpcomingConstruction Projects
PCC Building CC Retrofit - Measure E 2008PCC Building CC Retrofit - Measure E 2008
12
To be designed by Hill Partnership Architects Houses the Fitness Center, Gymnasium, Weight Room, and
Faculty and Staff Offices Swing space to be located on PCC Campus (Bldg. GG) To be completed concurrently with MDAB project phase 2 Anticipated start of construction Summer 2011
Current and UpcomingConstruction Projects
District Wide – Electronic Signage PlanDistrict Wide – Electronic Signage Plan Measure E 2008Measure E 2008
13
District Wide Signage Plan complete Final site locations determined Awaiting construction bids Construction completion of Marquee Signs
Spring 2010
Current and UpcomingConstruction Projects
14
Phase 2B (Design Phase)
HVAC upgrades (Air Handlers, Zone upgrades, tie to Central plant, etc.)
Controls upgrades Lighting upgrades (Interior/Exterior/Lighting controls)
Hot water system upgrades Irrigation controls Window film addition
HVAC Controls and Scheduling Parameters on temperature controls for better energy
efficiency Summer cooling 75° and winter heating 70° (FAC approved)
Working with Academic Services to create HVAC schedules for all classrooms on campus
District Wide Energy Retrofits - Measure E 2008District Wide Energy Retrofits - Measure E 2008
Current and UpcomingConstruction Projects
15
Financial Benefit of Energy Retrofit ProgramFinancial Benefit of Energy Retrofit Program
Current and UpcomingConstruction Projects
16
Re-design current dirt lot to have 80 parking stalls with new lighting and drainage. (Awaiting City feedback)
Re-slurry and re-stripe existing asphalt parking lot. (Done)
Replace elevator controls to bring them up to new current standards. (In process)
Installation of new automated front door. (In process)
Building perimeter landscape upgrade. (In process)
Los Coyotes Property - Measure E 2008Los Coyotes Property - Measure E 2008
LAC Facility Site Plan
l i b
e r
a l
a r
t s
Liberal Arts CampusSite Plan
PCC Facility Site Plan
p a
c i f
i c
c
o a
s t
Pacific Coast CampusSite Plan
Current and UpcomingConstruction Projects
19
LAC Bldg. F - Conversions of rooms F104 and F106 to new classroom space. Bldg. G and H - Repainting Expansion of Building I (Awaiting DSA approval)
Bookstore swing space to be located West of J building. Relocate Bond Management Team Offices to O Building (Community Outreach and
Services Facility) and removal of W trailers (December 2009)
Increase parking at Faculty and Lew Davis St. IITS relocation to O building Bldg. K – Roof extension over Kiln area Bldg. J – Theater lighting control panel replacement CDC – new carpet installation
PCC Bldg. JJ – Add new landscaping around perimeter MDAB swing space preparation Install exterior lighting at Tech1 Demolition of UU and VV
Upcoming ProjectsUpcoming Projects
Planned Phasing of Future Projects
20
2009-10 Parking Structure – groundbreaking Spring 2010 South Quad Complex complete - Fall 2009
Tech 1 at PCC complete – Fall 2009
Building O occupancy scheduled Foundation – July 2009
ERD, Warehouse, BMT and IITS – January 2010 Begin infrastructure construction – Fall 2009
Master landscaping implementation will follow this project
Submit FPP for M/N Project at LAC and MM Project at PCC and submit IPP for P Building at LAC and MM Project at PCC – July 1, 2009
Install portables for swing space at PCC – Fall 2009
Planned Phasing of Future Projects
21
2009-10 (continued) Submit plans to DSA for Building A renovation – August 2009 Submit plans to DSA for Building I (Bookstore) renovation –
September 2009 Submit plans to DSA for Building R (Gym) renovations – Fall
2009
Begin retrofit of Z Building – Fall 2009
Begin construction of Buildings DD and EE at PCC Anticipating December 2009 start
Schematic design begins for Outdoor PE Labs at LAC – Spring 2010
Anticipating swing space move for Building A at LAC – June 2010
Marquees complete – Spring 2010
Planned Phasing of Future Projects
22
2010-11 Begin Building R (Gym) HVAC and ADA upgrades –
Summer 2010 Anticipating Spring 2011 completion
Begin construction of Building I (Bookstore) and move to portable swing space – Summer 2010
Retrofit completion of Building Z – Summer 2010 Submit plans to DSA for Outdoor PE Labs – Fall 2010 Begin construction of Building A at LAC – Fall 2010
Begin Schematic Design for Buildings C and F at LAC
Submit plans to DSA no later than Summer 2011
Planned Phasing of Future Projects
23
2011-12 Infrastructure project complete at LAC – Summer 2011 Submit plans to DSA for Math/Technology Building at LAC –
Summer 2011
Begin construction of Buildings AA, BB and CC at PCC – Summer 2011
Construction completion of Buildings DD and EE at PCC – Summer 2011
Begin construction of Outdoor PE Labs at LAC – Summer 2011 Anticipating Spring 2012 completion
Anticipated construction completion of Building I (Bookstore) at LAC – Fall 2011
Anticipated construction completion of Parking Structure at LAC – Fall 2011
Planned Phasing of Future Projects
24
2012-13 Move Buildings C and F programs into Swing Space (M/N
Building) and begin construction – Summer 2012
Anticipated Construction completion of Building A at LAC – Summer 2012
Submit plans to DSA for M/N Building at LAC and Building MM (Phase 1) at PCC – Summer 2012
Begin Schematic Design for Building P at LAC and Building MM (Phase 2) at PCC – Summer 2012 Submit to DSA – Spring 2013
Begin construction of Math/Technology Building at LAC – Winter 2013
Planned Phasing of Future Projects
25
2012-13 (continued)
Begin Schematic Design for Building D and E renovations – Fall 2013
Anticipated Construction completion of Buildings AA, BB and CC at PCC – Spring 2013
Submit plans to DSA for Building GG at PCC – Summer 2012
Planned Phasing of Future Projects
26
2013-14 Begin construction on Building GG at PCC – Summer 2013
Anticipated Construction completion of Buildings C and F at LAC – Fall 2013
Begin construction of Buildings M/N at LAC and MM (Phase 1) at PCC – Fall 2013
Submit plans to DSA for Buildings D and E renovations at LAC – Fall 2013
Schematic design for Performing Arts Building (G&H) and Building R at LAC – Spring 2014
Planned Phasing of Future Projects
27
2014-15 Anticipated Construction completion of Math/Technology
Building at LAC – Summer 2014
Begin construction on Buildings D and E at LAC – Fall 2014
Submit plans to DSA for Performing Arts Building and Building R (Gym) at LAC – Spring 2015 Anticipate construction start – Spring 2016
Anticipated construction completion of Buildings M/N at LAC and MM at PCC – late Spring 2015
Begin construction on Buildings P at LAC and MM (Phase 2) at PCC – Spring 2015
QUESTIONS&
ANSWERS