PT. TRUBA JURONG ENGINEERING
LABUAN 2 BANTEN 2 X 300 MW CFSPP PROJECT
DOC. NO
BOILER DRUM ERECTION PROCEDURE
ISSUANCE DATE:
Unit Issuing : Construction Approved By : Site Manager Page 2 of 6 REVISION 0
1. General
The Boiler Drum (166 Tones ) with Hanger (10 Tones) and also rigging
tools (6.5 Tones) is erected to its final location (EL 66800) by using 2 unit
PSC heavy lift jack type L 300 lifting jack with Capacity each unit are
( 110 tones SWL ) in the cases proposed 7 parts 18 mm diameter
Dyform strand cables @ 70 meter long. The detailed preparation work,
erection and final alignment are as follow.
2. Equipment Specification
L 300 Lifting (2 Numbers)
Capacity : each @ SWL 110 MT based upon 7 – parts (from
total of 19 strands) Dyform Strand @ safety factor
2.5.
Stroke : 450 mm.
Câble : 7 Nos .18 mm Strand @ 70 meter long.
Skate Roller : 8 Nos each @ 100 ton mechanical skate rollers.
Hydraulic Control hoses: 2 units of hydraulic control hoses, sufficient for
carrying out above work.
Power Pack : L4/12 E
Capacity : 2 Nos liner at 15 liter
Supply : 415 V 3 phase 50 Hz
System
PT. TRUBA JURONG ENGINEERING
LABUAN 2 BANTEN 2 X 300 MW CFSPP PROJECT
DOC. NO
BOILER DRUM ERECTION PROCEDURE
ISSUANCE DATE:
Unit Issuing : Construction Approved By : Site Manager Page 3 of 6 REVISION 0
Capacity : 220 tones
Lifting rate : 12 M / hours.
Chain Blocks.
Capacity : 5 ton 2 units
: 10 ton 2 units
All necessary spare parts and specialist hand tool to support of lifting.
4. Installation of Equipment.
The actual equipment installation method at site is by 450 tonnes crane
available at site.
The following is proposed:
a) The lifting strands will be delivered to site in coils (approximately 2
tones each) and will be cut to length using disc cutter .The end of
strands will be prepared for threading.
b) The jack base will be tack welded to the jack supports beams
together with the moving skates and the fixed anchor blocks
installed inside their fabrications.
c) The jacks and fixed anchor will now be threaded with their strands
comprising the lifting cables.
d) The complete assemblies of jacks, beams, cables, anchors and
fabrications will now be lifted in to place and secured.
e) The power pack now be positioned at high level and the hydraulic
connections made.
f) The system is now ready for testing and connection to the drums.
PT. TRUBA JURONG ENGINEERING
LABUAN 2 BANTEN 2 X 300 MW CFSPP PROJECT
DOC. NO
BOILER DRUM ERECTION PROCEDURE
ISSUANCE DATE:
Unit Issuing : Construction Approved By : Site Manager Page 4 of 6 REVISION 0
5. Strap Hanger setting of Boiler Drum
Prior to the lifting the Drum, the Boiler Drum strap hangers are set to
facilitate the setting of Drum in its final location. After marking the center
line on roof girder, the strap hanger is set in position and goes along with
the steam drum. The detail is as per Drawing RED-004-CM2-SD-2004.
6. Drum Lifting Details
The length of steam drum is 22150 mm and the span between grid G3
and G5 is 21000 mm. Hence the drum is required to be tilted and lifted to
avoid clashing with steel. On this case, the drum will be tilted at an
inclination of 35 degrees.
The jacks will be mounted on jack support beams which will be mounted
on roller type’s skates. The movement and restrain of beam will be by
chain block. The jacks will be operated from a single electric hydraulic
power pack.
The actual loads on jacks as the drum is hoisted up at 35o is considered
(Lifting load of drum with internals 166t + hangers 10t + rigging tools
6.5t) at jack near grid G5 is 1343.49 KN and jack near grid G3 is 937.76
KN including safety factor 25%.
The following sequence is proposed to clear the steel work on gridlines.
a) Preparatory works such as temporary scaffold access platforms at top
deck steel for jack operators and erectors and other levels’ access for
watchmen at various elevations must be prepared in advance.
b) The lifting equipment will be tensioned up to 25 % increment unit 1
the drum lifts clear its supports.
PT. TRUBA JURONG ENGINEERING
LABUAN 2 BANTEN 2 X 300 MW CFSPP PROJECT
DOC. NO
BOILER DRUM ERECTION PROCEDURE
ISSUANCE DATE:
Unit Issuing : Construction Approved By : Site Manager Page 5 of 6 REVISION 0
c) Drum is lifted up by approximately 100 mm from the present position
and held for approximately 15 minutes while all direct load bearing
temporary and permanent girders and beams, jacking system are
checked for any undue deflections or connections (steel/hoses) non
conformities.
d) Once the system has been cleared for safe lifting, the
wood/steel/concrete block that were supporting the drum at ground
floor are removed using mobile crane, forklift, and chain blocks.
e) The lifting equipment will be tensioned up to 25 % increment unit 1
the drum lifts clear its supports as details attached (3). After removal
of Drum’s support, the drum’s permanent U rod hangers are
positioned on either side of the drum near actual locations secured by
temporary clamping and slings in such a way as to remain vertical
even when the drum is lifted in an inclined position.
f) Continue lifting until there is 1.5 meter clearance beneath the drum.
The Drum shall be raised up in a gradually speed to minimize the jack
effect of the load. It shall be lifted in a horizontal position if possible
and If not it shall be in the position where both hooks of the lifting
device is carrying the load. The angle of inclination shall be on position
where the lifting cable is not its vertical position.
g) Lifting one end (the end with the jack nearest the drum final position
center line) unit 1 the drum reaches an inclination of 35 degrees to the
horizontal. At this inclination, the drum should clear the steel on both
sides. A continuous monitoring on the condition of the lifting system
shall be done. The spotter will continuously following the drum while
on its way up to check for any obstruction along the way of the drum.
If there any obstruction, the spotter should be inform the lifting
engineer to hold the lifting until the obstruction is cleared, then
resume the lifting.
PT. TRUBA JURONG ENGINEERING
LABUAN 2 BANTEN 2 X 300 MW CFSPP PROJECT
DOC. NO
BOILER DRUM ERECTION PROCEDURE
ISSUANCE DATE:
Unit Issuing : Construction Approved By : Site Manager Page 6 of 6 REVISION 0
h) Lift both ends together until 1 the highest end is clear above the + 60.
M level steel.
i) Lift on the lowest end only until the drum is returned to horizontal. At
the same time pull the movable jack support beam away from the
center line to maintain the plumb of the lifting cables.
j) Once drum is horizontal is horizontal continue lifting both end together
until the U – Bolt connection can be made.
k) After U – Bolt installation is complete, transfer the load from the lifting
cables to the bolts by gently bleeding the system down.
l) The lifting device shall dismantled together with the temporary
support to clear the way for the erection work to progress,
Note during the lifting the power pack operator will monitor the individual
jack loads .In addition; the operator will need to be in contact with the
lift co-coordinators and spotters watching the drum clearance as it
passes each level.
7. Final Alignment of Steam Drum
After the drum is set in position, the below mentioned alignment is carried
out to confirm the centering of drum along X and Y axis .Details in
attachment (4).
a. Rolling.
b. Elevation of Drum.
c. Level of Drum.
d. Drum Centering.
The steam Drum shall finally alignment first before the connection of any
pipe on to it. Alignment shall be checked and confirmed in the following
manner.
PT. TRUBA JURONG ENGINEERING
LABUAN 2 BANTEN 2 X 300 MW CFSPP PROJECT
DOC. NO
BOILER DRUM ERECTION PROCEDURE
ISSUANCE DATE:
Unit Issuing : Construction Approved By : Site Manager Page 7 of 6 REVISION 0
1. Check the X and Y axis of the drum centre line if it coincides with the
line previously established. If not adjustment shall be made to the
position of the drum by pulling to the direction where there is a
negative variance, until be come zero variance. This shall be done on
all direction where there is a difference with the lay – out
2. Check the final elevation of the drum horizontal axis.
3. Check the leveling of the drum .This shall be done by checking the left
and right end of the drum along the horizontal axis of the drum and
also on both end, front and rear side of the drum respectively. Make
sure that the position of the drum is as per lay out and accrue level.
8. General Notes:
1. Manning scheme for lifting of Drum shall prepared after reviewing
thoroughly by personnel relevant to the works, and the procedure shall
be carried out under careful verification in safety at every step.
2. Area within the lifting works shall be roped off with safety marks rope
and notice board denoted “KEEP OFF EXCEPT PERSONEL CONCERNED”
shall be putt there.
3. Lifting tools such as wire rope /strand, chain block etc shall be checked
firmly in advance and confirmed thoroughly that no any defective point
exist.
4. Sign to Jack operator shall be given only nominated person shall be
handling winch only by sign his sign.