156
Boggabri Coal Operations Pty Ltd Boggabri Coal Mine 2017 Annual Review 31 March 2018

Boggabri Coal Operations Pty Ltd Boggabri Coal Mine 2017 ... · 7.4 Workforce Profile 112 BCOPL Employees 112 Mining Contractor 112 8. REHABILITATION 113 ... BTM Complex Boggabri

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

  • Boggabri Coal Operations Pty Ltd

    Boggabri Coal Mine

    2017 Annual Review 31 March 2018

  • Annual Review 2017

    BCOPL Page i

    Revision Control Chart

    Rev No Original 1 2 3 4

    Revision Date 31 March 2018

    Prepared by J McDonough

    Reviewed by D Martin / H Russell

    Approved by R Balks

    Signature

    Distribution Control

    Company Position

    BCOPL Environment Superintendent

    Division of Resources and Geoscience Regional Environment Officer

    Department of Planning and Environment Senior Planning Officer

    Department of Primary Industry – Land and Natural Resources Area Manager North West

    Department of Planning Infrastructure – Water Water Regulation Officer

    Environment Protection Authority Regional Operations Officer Armidale

    NSW Forests Forestry Occupancy Supervisor

    Community Consultative Committee Chairman

    BGC Contracting Project Manager

    Annual Review Title Block

    Name of Operation Boggabri Coal Mine

    Name of Operator Boggabri Coal Operations Pty Ltd

    Development Consent / Project Approval # 09_0182

    Name of Holder of Project Approval Boggabri Coal Pty Limited (now trading as Boggabri Coal Operations Pty Limited)

    Mining Lease # CL 368

    Name of holder of mining lease Boggabri Coal Pty Limited (now trading as Boggabri Coal Operations Pty Limited)

    Water Licence # see page 3 below for details

    Name of holder of water access licences Boggabri Coal Pty Limited (now trading as Boggabri Coal Operations Pty Limited)

    MOP Commencement Date 19 December 2017

    MOP Completion Date 31 December 2021

    Annual Review Commencement Date 1 January 2017

    Annual Review Completion Date 31 December 2017

    I, Ray Balks, certify that this audit report is a true and accurate record of the compliance status of Boggabri Coal Mine for the period 1 January 2017 to 31 December 2017 and that I am authorised to make this statement on behalf of Boggabri Coal Operations Pty Limited.

    Name of authorized reporting officer Ray Balks

    Title of authorized reporting officer General Manager Operations

    Signature of authorized reporting officer

    Date 31/03/2018 (Rev O)

  • Annual Review 2017

    BCOPL Page ii

    Contents Page Number

    1. STATEMENT OF COMPLIANCE 1

    2. INTRODUCTION 9

    2.1 Mine Contacts 9

    2.2 Approvals, Licences and Mining Leases 9

    2.3 Mine Operation Introduction and History 11

    2.4 Purpose and Scope of Report 12

    2.5 Actions from 2016 Annual Review 14

    3. SUMMARY OF OPERATIONS 17

    3.1 Mining Preparation 17

    Saline or Potentially Acid Forming Materials 17

    3.2 Mining Operations 17

    Equipment 17

    Activities 18

    Pit Progression 18

    Production Waste 18

    3.3 Production Statistics 19

    3.4 Exploration 20

    3.5 Construction Activities during 2017 23

    3.6 Construction Activities Proposed for 2018 23

    4. ENVIRONMENTAL MANAGEMENT AND PERFORMANCE 24

    4.1 Meteorology 25

    Environmental Management 25

    Environmental Performance 26

    Improvements and Initiatives 30

    4.2 Air Quality 30

    Environmental Management 30

    Environmental Performance 31

    Improvements and Initiatives 35

    4.3 Operational Noise 35

    Environmental Management 35

    Environmental Performance 36

    Improvements and Initiatives 42

    4.4 Blasting 43

  • Annual Review 2017

    BCOPL Page iii

    Environmental Management 43

    Environmental Performance 43

    Improvements and Initiatives 45

    4.5 Surface Water 46

    Environmental Management 46

    Environmental Performance 49

    Improvements and Initiatives 54

    4.6 Groundwater 54

    Environmental Management 54

    Environmental Performance 56

    Improvements and Initiatives 69

    4.7 Biodiversity 70

    Environmental Management 70

    Environmental Performance 71

    Improvements and Initiatives 79

    4.8 Hazardous Materials 80

    Environmental Management 80

    Environmental Performance 80

    4.9 Waste Management 82

    Environmental Management 82

    Environmental Performance 83

    4.10 Spontaneous Combustion 86

    Environmental Management 86

    Environmental Performance 86

    4.11 Heritage 86

    Environmental Management 86

    Environmental Performance 87

    Improvements and Initiatives 88

    4.12 Greenhouse Gases 89

    Environmental Management 89

    Environmental Performance 89

    Improvements and Initiatives 90

    4.13 Public Safety 90

    Environmental Management 90

    Environmental Performance 90

    4.14 Traffic 92

    Environmental Management 92

  • Annual Review 2017

    BCOPL Page iv

    Environmental Performance 92

    4.15 Socio-economic 93

    Socio-economic Management 93

    Environmental Performance 93

    5. INCIDENTS AND NON-COMPLIANCES 101

    5.1 Notices, Warnings and Other Compliance-Related Correspondence 104

    6. AUDITS 107

    6.1 Independent Environmental Compliance Audit 107

    Scope of audit 107

    Audit Outcomes 107

    DPE Review 107

    Status of Audit Recommendations 107

    7. COMMUNITY 108

    7.1 Community Programs and Investment 108

    7.2 Community Consultative Committee 109

    7.3 Complaints 110

    Management of Complaints 110

    Registered Environmental Complaints 110

    7.4 Workforce Profile 112

    BCOPL Employees 112

    Mining Contractor 112

    8. REHABILITATION 113

    8.1 Rehabilitation Methodology 113

    8.2 Rehabilitation Progress 113

    Summary of Land Rehabilitation 113

    2017 Plantings 114

    Rehabilitation Status 114

    8.3 Rehabilitation Biodiversity Monitoring 116

    Photographic Monitoring 116

    Summary of Findings 118

    8.4 Growth Performance 119

    Growth Medium Suitability 119

    8.5 Rehabilitation in 2018 120

    9. ACTIVITIES PROPOSED FOR NEXT ANNUAL REVIEW PERIOD 121

  • Annual Review 2017

    BCOPL Page v

    10. REFERENCES 122

  • Annual Review 2017

    BCOPL Page vi

    List of tables Table 1-1 Statement of compliance 1 Table 1-2 Non-compliances during the reporting period 2 Table 2-1 BCM Mine Contacts 9 Table 2-2 Key Approvals, Consents, Mining Leases and Licences 9 Table 2-3 Annual Review requirements 13 Table 2-4 Issues from 2016 AEMR to be addressed in 2017 Annual Review 14 Table 3-1 Equipment fleet as at December 2017 18 Table 3-2 Production and Waste Rock Summary 19 Table 3-3 Compliance with Project Approval Conditions 19 Table 3-4 BCM Exploration Drilling 20 Table 3-5 Summary of Construction Activities during the Reporting Period 23 Table 4-1 Key EMPs 24 Table 4-2 MET Monitoring Parameters 25 Table 4-3 Air Quality Monitoring Sites 31 Table 4-4 Depositional Dust – Annual Average Results 32 Table 4-5 Current Noise Monitoring Locations 36 Table 4-6 Noise Limits 36 Table 4-7 Summary of Attended Noise Monitoring Results - dB(A) LAeq (15 minutes) & L1 (1 min) 38 Table 4-8 Summary of 2017 sound power screening results 40 Table 4-9 Surface Water Quality Monitoring Regime 48 Table 4-10 Surface Water Quality Testing Parameters 49 Table 4-11 Summary of Frequency Based Monitoring Results 50 Table 4-12 Water Take 51 Table 4-13 Predicted Water Demand 51 Table 4-14 Water Storage Summary 53 Table 4-15 Construction Details of Monitoring Bores 55 Table 4-16 Groundwater Quality Testing Parameters 56 Table 4-17 Minimum Measured Water Levels 57 Table 4-18 Groundwater Quality Trigger Values 61 Table 4-19 Results Summary for In Situ Water Quality Measurements 64 Table 4-20 Results Summary for Analysis of Major Ions 65 Table 4-21 Results Summary for Analysis of Metals 66 Table 4-22 Results Summary for Analysis of Nutrients 67 Table 4-23 Animal Groups Encountered during Clearing Operations 72 Table 4-24 Threatened Species Encountered during Clearing Operations 73 Table 4-25 Explosives and Hazardous Materials Licence / Notification Holders 81 Table 4-26 Diesel Fuel Consumption 81 Table 4-27 Summary of Mining Operation Waste Disposal 83 Table 4-28 Summary of Bioremediation Areas 85 Table 4-29 BCOPL GHG and Energy Statistics 89 Table 4-30 Social Impact Monitoring Summary 93 Table 4-31 Approval Rates for New Dwellings in Gunnedah and Narrabri 2010 - 2013 96 Table 4-32 Local School Enrolments 2011 - 2016 98 Table 4-33 Key Crime Statistics 2011 - 2017 99 Table 5-1 Non-compliances during the reporting period 101 Table 5-1 Notices and warnings received during the reporting period 105 Table 7-1 BCOPL Community Funding 2017 108 Table 7-2 Complaint Summary 111 Table 7-3 Residential Locality of BCOPL Employees 112 Table 8-1 Rehabilitation Status 114 Table 8-2 Survey Locations for Rehabilitation Sites at BCM 116 Table 9-1 Activities Proposed for next Annual Review Period 121

  • Annual Review 2017

    BCOPL Page vii

    List of figures Figure 2-1 Locality Map 16 Figure 3-1 Extent of 2017 Exploration Drilling 22 Figure 4-1 Monthly Temperature Records 26 Figure 4-2 Monthly Rainfall 27 Figure 4-3 Comparison of 2016 and 2017 Rainfall 27 Figure 4-4 Monthly Wind Rose Summary January – April 2017 28 Figure 4-5 Monthly Wind Rose Summary May – August 2017 29 Figure 4-6 Monthly Wind Rose Summary September – December 2017 30 Figure 4-7 Merriown PM10 Monitoring Results 33 Figure 4-8 Roma PM10 Monitoring Results 34 Figure 4-9 Summary of Peak Vibration Monitoring Results 44 Figure 4-10 Blast Overpressure Results 45 Figure 4-11 Monthly Dust Suppression Water Usage 52 Figure 4-12 Long Term Groundwater Levels for all Bores 57 Figure 4-13 Alluvium and Boggabri Volcanics Hydrograph and CDFM Curve 59 Figure 4-14 Maules Creek Formation Hydrographs 60 Figure 4-15 Groundwater Trends in Temperature 62 Figure 4-16 Groundwater Trends in pH 63 Figure 4-17 Groundwater Trends in Electrical Conductivity 63 Figure 4-18 Artefact located in the Tree Clearing Area 2017 87 Figure 4-19 Sources of BCM Scope 1 and Scope 2 Emissions 90 Figure 4-20 New Dwelling Commencements in Gunnedah and Narrabri 2011 – 2013 97 Figure 4-21 Employment Land Availability Gunnedah LGA 2011 - 2013 97 Figure 4-22 Employment Land Availability Narrabri LGA 2011 - 2013 98 Figure 7-1 Complaints Received 111 Figure 8-1 Extent of Mining and Rehabilitation at the end of the 2017 Reporting Period 115 Figure 8-2 2008 Rehabilitation (nine years old) 117 Figure 8-3 2010 Rehabilitation (seven years old) 117 Figure 8-4 2011 Rehabilitation (six years old) 118

    List of appendices Appendix A Environmental Monitoring Location Plan Appendix B Biodiversity Monitoring Maps Appendix C Independent Environmental Audit Action Plan

  • Annual Review 2017

    BCOPL Page 1

    Glossary

    Abbreviations Terms

    AR Annual Review

    AEMR Annual Environmental Management Report

    AHCS Aboriginal Heritage Conservation Strategy

    AQMS Air Quality Management Strategy

    AQGHGMP Air Quality and Greenhouse Gas Management Plan

    ARI Average Recurrence Interval

    ASCF Aboriginal Stakeholder Consultative Forum

    BCOPL Boggabri Coal Operations Pty Limited

    BCM Boggabri Coal Mine

    BCT Boggabri Coal Terminal

    BFMP Blast Fume Management Protocol

    BIA Biodiversity Impact Assessment

    BLMP Blast Management Plan

    BLMS Blast Management Strategy

    BMP Biodiversity Management Plan

    BOA Biodiversity Offset Area

    BOS Biodiversity Offset Strategy

    BTM Complex Boggabri-Tarrawonga-Maules Creek Complex

    CCC Community Consultative Committee

    CDFM Cumulative Deviation From Mean Rainfall

    CHMP Cultural Heritage Management Plan

    CHPP Coal Handling and Preparation Plant

    DoEE Department of Environment and Energy (Cth)

    DPE Department of Planning and Environment

    DPI Department of Primary Industries

    DRE NSW Division of Resources and Energy

    EA Environmental Assessment

    EMP Environmental Management Plan

    EMS Environmental Management System

    EPA Environment Protection Authority

    EP&A Act Environmental Planning and Assessment Act 1979 (NSW)

    EPBC Act Environment Protection and Biodiversity Conservation Act 1999 (Cth)

    EPL Environment Protection Licence

    GHG Greenhouse Gas

    GWMP Groundwater Management Plan

    HVAS High Volume Air Sampler

    IAR Idemitsu Australia Resources Group

    MIA Mine Infrastructure Area

    MET Station Meteorological Monitoring Station

    MOP Mining Operations Plan

    Mtpa Million Tonnes Per Annum

  • Annual Review 2017

    BCOPL Page 2

    Abbreviations Terms

    MWD Mine Water Dam

    NGER National Greenhouse and Energy Reporting

    NGER Act National Greenhouse and Energy Reporting Act 2007(Cth)

    NPI National Pollutant Inventory

    NSC Narrabri Shire Council

    OEH NSW Office of Environment and Heritage

    PA Project Approval 09_0182

    PAC NSW Planning and Assessment Commission

    PAF Potential Acid Forming

    PIRMP Pollution Incident Response Management Plan

    PM2.5 Particulate matter < 2.5 µm

    PM10 Particulate matter < 10 µm

    POEO Act Protection of the Environment Operations Act 1997(NSW)

    RAP Registered Aboriginal Parties

    ROM Run of Mine

    SCMP Spontaneous Combustion Management Plan

    SEWPaC Commonwealth Department of Sustainability, Environment, Water, Populations and Communities (now Commonwealth Department of the Environment and Energy)

    SIMP Social Impact Management Plan

    SMP Soil Management Protocol

    SWB Site Water Balance

    SWMP Surface Water Management Plan

    TARP Trigger Action Response Plan

    TEOM Tapered Element Oscillating Microbalance

    TLO Train Load-out Facility

    TMP Traffic Management Plan

    TSC Act Threatened Species Conservation Act 1995 (NSW)

    WAL Water Access Licence

    WMP Water Management Plan

    WMS BTM Complex Water Management Strategy

    http://www.comlaw.gov.au/Series/C2007A00175http://www.comlaw.gov.au/Series/C2007A00175

  • Annual Review 2017

    BCOPL Page 1

    1. STATEMENT OF COMPLIANCE

    In accordance with the requirements of the Post-approval requirements for State significant mining

    developments – Annual Review Guideline (NSW Government, 2015), a statement of compliance has

    been prepared to document the status of compliance with BCM's Project Approval 09_0182 (including

    Statement of Commitments), mining leases and other relevant approvals as at the end of the 2017

    reporting period. Table 1-1 identifies whether or not non-compliances occurred during the reporting period

    for each statutory approval. Where non-compliances are identified, further details are provided in

    Table 1-2. Non-compliances have been colour-coded in that table, in accordance with the descriptions

    provided in the Annual Review Guideline.

    Table 1-1 Statement of compliance

    Approval Were all conditions of the relevant approval(s) complied with during the reporting period?

    Project Approval 09_0182 (incl. Statement of Commitments) No

    Coal Lease 368 Yes

    Mining Lease 1755 Yes

    Authorisation 355 Yes

    Authorisation 339 Yes

    EPL 12407 No

    EPL 20404 Yes

    WAL 12691 Yes

    WAL12767 Yes

    WAL14483 Yes

    WAL15037 Yes

    WAL24103 Yes

    WAL29473 Yes

    WAL29562 Yes

    WAL2571 Yes

    WAL2572 Yes

    WAL2595 Yes

    WAL2596 Yes

    WAL31084 Yes

    WAL14495 Yes

    WAL36547 Yes

    WAL31096 Yes

    http://www.planning.nsw.gov.au/~/media/3AA21D35168042FE813DD0FB92E00E58.ashxhttp://www.planning.nsw.gov.au/~/media/3AA21D35168042FE813DD0FB92E00E58.ashx

  • Annual Review 2017

    BCOPL Page 2

    Table 1-2 Non-compliances during the reporting period

    Relevant approval

    Ref. Condition description Compliance status*

    Comment BCOPL response Where addressed in the Annual Review

    PA 09_0182 (incl. Statement of Commitments)

    Sch 3, C12(b)

    The Proponent shall: operate a comprehensive noise management system on site that uses a combination of predictive meteorological forecasting and real-time noise monitoring data to guide the day to day planning of mining operations and the implementation of both proactive and reactive noise mitigation measures to ensure compliance with the relevant conditions of this approval…

    Non-compliance (low risk)

    The non-compliance was identified during the Independent Environmental Audit. The auditor’s comments were: Sentinex-real-time monitoring-daily monitoring data provided to key BCOPL staff and contractors via email. Evidence of triggers for real time noise monitoring outlined in the Noise MP. Minimal evidence provided for reviewing/changing operations based on real-time noise monitoring results (implementation of triggers). The auditors recommendations were: 1. Further liaison with the DPE

    regarding approval of the June 2017 version of the Noise Management Plan.

    2. Implementation of the real time monitoring program and recording of reviewing/changing operations in site documentation (including OCE reports).

    3. Additional information should be provided in the AEMR relating to activities for reviewing/changing operations based on real time noise monitoring.

    BCOPL will continue to proactively manage noise impacts in line with the approved Noise Management Plan. BCOPL has implemented recommendations 1 and 2. For recommendation no. 3, BCOPL will continue to prepare AEMRs/Annual Reviews in accordance with the Annual Review Guideline (DPE, 2015) and to the satisfaction of DPE.

    Section 4.3 and Section 5

    Sch 3, C13(f)

    The Proponent shall prepare and implement a Noise Management Plan for the project to the satisfaction of the Secretary. This plan must: include a monitoring program that: - uses a combination of real time and supplementary attended monitoring to evaluate the performance of the project;

    Non-compliance (low risk)

    The non-compliance was identified during the Independent Environmental Audit. The auditor’s comments were: Noise monitoring - non compliant relating to the implementation of the real-time noise monitoring program (sub condition f). Minimal evidence provided for reviewing/changing operations based on real-time noise monitoring results (implementation of triggers).

    As above Section 4.3 and Section 5

  • Annual Review 2017

    BCOPL Page 3

    Relevant approval

    Ref. Condition description Compliance status*

    Comment BCOPL response Where addressed in the Annual Review

    - evaluates and reports on the effectiveness of the noise management system on site…

    The auditor’s recommendations were as per those outlined above for Sch3, cl12(b).

    Sch 3, C38(b)

    The Proponent shall prepare and implement a Surface Water Management Plan, which includes: …

    a detailed description of the water management system on site, including the:

    clean water diversion systems;

    erosion and sediment controls (dirty water system);

    mine water management systems including irrigation areas;

    discharge limits in accordance with EPL requirements;

    water storages;

    haul road and Boggabri Rail Spur Line and bridge flood and water diversions;

    performance criteria for the following, including trigger levels for investigating any potentially adverse impacts associated with the project:

    the water management system;

    soils within the irrigation area;

    downstream surface water quality;

    Non-compliance (low risk)

    The non-compliance was identified during Independent Environmental Audit. The auditor’s comments were: Currently clean water is being captured in a dam (road built across) and clean water from a large section of the catchment does not leave site. This is not as per the Water Management Plan (July 2017 - unapproved) and the MOP. SLR understands this dam was only built recently in the month prior to the site visit however the site is not licenced to collect water from this dam, with the original design to divert the clean water around the site. Field inspection noted the incorrect clean/dirty water management in the area around the ‘clean water diversion drain’. Currently clean water is being captured in a dam (road built across) and clean water from a large section of the catchment does not leave site. The auditor’s recommendations were: 1. Improvements required for

    clean/dirty water management in the area around the ‘clean water diversion drain’. Pursue options for ensuring that clean water diversions shown on MOP, in Water Management Plan, align with what is constructed on site and all necessary licences are in place for the solution. Undertake consultation with government agencies as required.

    2. SD11 – adjacent to rail load out. Rilling across dam. Pipeline has

    BCOPL will implement recommendations 1, 2 and 3 by 16 April 2018. For recommendation 4, BCOPL will continue to manage the capacity of SD6 in accordance with the approved Surface Water Management Plan.

    Section 5 and Appendix C

  • Annual Review 2017

    BCOPL Page 4

    Relevant approval

    Ref. Condition description Compliance status*

    Comment BCOPL response Where addressed in the Annual Review

    downstream flooding impacts, including flood impacts due to the construction and operation of the Boggabri Rail Spur Line and rail bridge; and

    stream and riparian vegetation health, including the Namoi River;

    a program to monitor:

    the effectiveness of the water management system;

    soils within the irrigation area; and

    surface water flows and quality in the watercourses that could be affected by the project;

    downstream flooding impacts; and

    a plan to respond to any exceedances of the performance criteria, and mitigate and/or offset any adverse surface water impacts of the project;…

    caused erosion and if not treated could affect dam integrity. Recommend moving pipeline location closer to the water or additional rocks placed around the eroded area to reduce erosion.

    3. Completion of monitoring for stream and riparian monitoring for Nagero Creek and the Namoi River as per the Water Management Plan.

    4. Tarrawonga Drainage Area - protocol. Develop a protocol to review the capacity of SD6 if the Tarrawonga drain is close to discharging (Tarrawonga drain flows to SD6). BCOPL should obtain samples of surface water when water enters the Boggabri site from the Tarrawonga Drainage Area.

    Sch3, C38(c)

    The Proponent shall prepare and implement a Groundwater Management Plan, which includes:

    the monitoring and testing requirements specified in the PAC recommendations for groundwater

    Non-compliance (low risk)

    The non-compliance was identified during the Independent Environmental Audit. The auditor’s comments were: There were occasions during the audit period where monitoring was unable to be undertaken at some groundwater locations. These were outlined in the EPL Annual Returns. The reason for these bores not being

    BCOPL will continue to liaise with DPI Water for relevant licensing matters on an ‘as required’ basis. Redundant groundwater monitoring bores have been removed from the revised Groundwater

    Section 4.6 and Section 5

  • Annual Review 2017

    BCOPL Page 5

    Relevant approval

    Ref. Condition description Compliance status*

    Comment BCOPL response Where addressed in the Annual Review

    management as set out in Appendix 6;

    a program to monitor and assess:

    groundwater inflows to the open cut mining operations;

    the seepage/leachate from water storages, backfilled voids and the final void;

    interconnectivity between the alluvial and bedrock aquifers;

    background changes in groundwater yield/quality against mine-induced changes;

    the impacts of the project on: o regional and local

    (including alluvial) aquifers;

    o groundwater supply of potentially affected landowners;

    o aquifers potentially affected by the mine irrigation area;

    o groundwater dependent ecosystems (including potential impacts on stygo-fauna)

    monitored include 'monitoring bore casing damaged due to ground movement, preventing a pump or bailer from being placed in the bore to obtain a groundwater sample. SLR understands additional bores will be installed (following approval from the DPI Water) to offset the loss of bores. The auditor’s recommendations were:

    1. Further liaison with DPI Water regarding licencing of bores.

    2. Updates to the Water Management Plan if required for most up to date monitoring locations.

    Management Plan, which was approved by the DPE in May 2017. An application to remove these redundant monitoring points from EPL 12407 was lodged with NSW EPA during the reporting period. The application is currently being processed.

  • Annual Review 2017

    BCOPL Page 6

    Relevant approval

    Ref. Condition description Compliance status*

    Comment BCOPL response Where addressed in the Annual Review

    and riparian vegetation…

    Sch3, C49(e)(v)

    The Proponent shall prepare and implement a Biodiversity Management Plan for the project to the satisfaction of the Secretary. This plan must: …(e) include a detailed description of the measures that would be implemented including the procedures to be implemented for: …(v) minimising the impacts on fauna on site, including undertaking pre-clearance surveys;…

    Non-compliance (low risk)

    According to BCOPL’s tree clearing procedure, which is an appendix to the BMP, vegetation clearing is to cease if ambient temperatures exceed 35oC. On 18 February 2017, BCOPL continued clearing vegetation for a period of approximately 10 minutes after temperatures had exceeded 35oC. The failure to cease clearing activities was attributed to BCOPL’s third-party-provided automatic SMS temperature alert system failing and BCOPL’s clearing supervisor subsequently not being advised that temperatures had exceeded 35oC. BCOPL received an Official Caution from DPE for the incident. DPE asserted that the clearing activities during temperatures in excess of 35oC contravened Schedule 3, Condition 49 as BCOPL had failed to implement the BMP.

    BCOPL has installed a secondary temperature monitoring unit as a back-up system should the primary automated SMS temperature alert system fail. Temperature SMS updates are also now issued to relevant personnel every 15 minutes during tree clearing activities. These actions were completed in 2017.

    Section 5

    Sch3, C57(c)

    The Proponent shall prepare and implement an Archaeological Salvage Program that must: (c) incorporate methodology including:

    sub-surface testing;

    staged salvage, based on anticipated mine planning;

    pre-disturbance monitoring;

    site assessment and reporting protocols;

    Non-compliance (low risk)

    The non-compliance was identified during the Independent Environmental Audit. The auditor made a number of comments regarding content that they believed should be included within the CHMP. They asserted that the absence of this content constituted a non-compliance with this condition. The auditor made six recommendations for improvements. Further details regarding the auditors comments and recommendations are

    BCOPL has committed to implement five of the six recommendations. The sixth recommendation was to include within the CHMP, an outline of the progress made toward the establishment of a long-term Keeping Place in consultation with registered Aboriginal parties. BCOPL has

    Section 5 and Appendix C

  • Annual Review 2017

    BCOPL Page 7

    Relevant approval

    Ref. Condition description Compliance status*

    Comment BCOPL response Where addressed in the Annual Review

    research objectives to inform knowledge of Aboriginal occupation;

    protection, storage and management of salvaged Aboriginal objects;

    addressing relevant statutory requirements under the National Parks and Wildlife Act 1974; and

    proposed long-term plan for protection of salvaged

    Aboriginal objects.

    contained in the Audit Action Plan contained in Appendix C.

    elected to keep such records on site EMS rather than including them in the CHMP. This is due to the document requiring continual review at each update and the fact that it would not improve the management system in any way. Further details are contained in the Audit Action Plan in Appendix C.

    Sch5, C13

    The Proponent shall ensure that the noise and air quality risk/response matrices required to be developed in the Noise and Air Quality Management Plans and validated real time monitoring data are available online and includes: (a) timely publication of validated monitoring data in a clearly understandable form; (b) identification of mine operational responses to monitoring data and weather forecasts;

    Non-compliance (low risk)

    The non-compliance was identified during the Independent Environmental Audit. The auditor’s comments were:

    1. Evidence sighted of real-time air quality monitoring - PM10. No evidence of real-time noise monitoring available online.

    2. No evidence online of mine responses.

    The auditor’s recommendations were: 1. Ensure real-time noise monitoring

    is available on the website as real-time air is available.

    2. Additional information should be provided in the AEMR regarding real time noise and air monitoring including responses to triggers.

    BCOPL provided the following responses to the auditor’s recommendations: 1. The condition does

    not require the real-time noise monitoring data to be available online in real-time. It requires validated real-time monitoring data to be available online. Validated real-time monitoring data is currently available online. No action is proposed.

    2. All previous AEMRs/Annual Reviews have been prepared to the satisfaction of DPE. BCOPL will continue to prepare AEMRs/Annual Reviews in

    Section 5

  • Annual Review 2017

    BCOPL Page 8

    Relevant approval

    Ref. Condition description Compliance status*

    Comment BCOPL response Where addressed in the Annual Review

    accordance with the Annual Review Guideline (DPE, 2015) and to the satisfaction of DPE. No action is proposed.

    EPL 12407 P 1.3 Surface water monitoring & groundwater monitoring

    Non-compliance (low risk)

    A monitoring point was not monitored in all instances due to accessibility restrictions

    BCOPL is seeking a variation to the EPL to remove redundant or unsafe monitoring locations.

    Section 5

    Monitoring points were not monitored in all instances as some have been mined through, collapsed or are inaccessible

    BCOPL is seeking a variation to the EPL to remove redundant or unsafe monitoring locations.

    Section 5

    M 2.3 Surface water monitoring & groundwater monitoring

    Non-compliance (low risk)

    A monitoring point was not monitored in all instances due to accessibility restrictions

    BCOPL is seeking a variation to the EPL to remove redundant or unsafe monitoring locations.

    Section 5

    Monitoring points were not monitored in all instances as some have been mined through, collapsed or are inaccessible

    BCOPL is seeking a variation to the EPL to remove redundant or unsafe monitoring locations.

    Section 5

    *non-compliances listed in the table relate to those deemed to have occurred during the reporting period. Refer to Appendix C for a complete list of non-compliances identified

    during the Independent Environmental Audit, which covered the period from July 2014 to July 2017.

  • Annual Review 2017

    BCOPL Page 9

    2. INTRODUCTION

    2.1 Mine Contacts

    Table 2-1 BCM Mine Contacts

    General Manager Operations:

    Company:

    Address:

    Phone:

    Fax:

    Ray Balks

    Boggabri Coal Operations Pty Limited

    386 Leard Forest Rd, Boggabri, NSW, 2382

    02 6749 6013

    02 6743 4496

    Health Safety and Environment Manager:

    Company:

    Address:

    Phone:

    Fax:

    Peter Forbes

    Boggabri Coal Operations Pty Limited

    386 Leard Forest Rd, Boggabri, NSW, 2382

    02 6749 6038

    02 6743 4496

    Environmental Superintendent:

    Company:

    Address:

    Phone:

    Fax:

    Daniel Martin

    Boggabri Coal Operations Pty Limited

    386 Leard Forest Rd, Boggabri, NSW, 2382

    02 6749 6013

    02 6743 4496

    2.2 Approvals, Licences and Mining Leases

    Table 2-2 summarises the key mining leases and approvals currently held by BCOPL which are relevant

    to the operations at BCM.

    Table 2-2 Key Approvals, Consents, Mining Leases and Licences

    Description Date granted/ commencement date

    Expiry/duration

    Project Approvals

    Project Approval 09_0182 18 July 2012 31 December 2033

    09_0182 Mod 2 17 February 2015 31 December 2033

    09_0182 Mod 3 17 March 2014 31 December 2033

    09_0182 Mod 4 23 March 2015 31 December 2033

    09_0182 Mod 5 30 August 2016 31 December 2033

    09_0182 Mod 6 7 July 2017 31 December 2033

    EPBC Act Approval 11 February 2013 31 December 2053

    Coal Leases

    Coal Lease CL 368 15 November 1990 14 November 2032

  • Annual Review 2017

    BCOPL Page 10

    Description Date granted/ commencement date

    Expiry/duration

    Mining Leases / Authorisations

    Authorisation A 355 19 July 1984 11 April 2018

    Authorisation A 339 11 April 1984 11 April 2022

    Mining Lease ML 1755 30 June 2017 30 June 2038

    Environmental Protection Licences

    EPL 12407 11 January 2006 In perpetuity (Anniversary 11 January) until surrendered

    EPL 20404 19 May 2014 In perpetuity (Anniversary 19 May) until surrendered

    Water Licences

    WAL 12691 27 July 2012 In perpetuity

    WAL12767 8 April 2014 In perpetuity

    WAL14483 27 July 2012 In perpetuity

    WAL15037 12 December 2013 In perpetuity

    WAL24103 1 September 2011 In perpetuity

    WAL29473 26 July 2012 In perpetuity

    WAL29562 26 July 2012 In perpetuity

    WAL2571 12 December 2013 In perpetuity

    WAL2572 25 December 2013 In perpetuity

    WAL2595 12 December 2013 In perpetuity

    WAL2596 25 September 2013 In perpetuity

    WAL31084 22 August 2013 In perpetuity

    WAL14495 3 February 2014 In perpetuity

    WAL36547 6 February 2014 In perpetuity

    WAL31096 25 November 2014 In perpetuity

    90FW833717 21 September 2015 4 April 2020

    90FW834023 21 September 2015 4 June 2020

    90FW834016 21 September 2015 28 October 2018

    Mining Operations Plans

    Current MOP 19 December 2017 31 December 2021

    Radiation Licences

    Licence No. 5083602 14 June 2017 14 June 2018

  • Annual Review 2017

    BCOPL Page 11

    Description Date granted/ commencement date

    Expiry/duration

    Council Approvals

    CC 04-04-2012 Mod1 22 October 2012 In perpetuity

    CC 02-03-2012 6 June 2012 In perpetuity

    CC 10-01-2012 Mod1 1 June 2012 In perpetuity

    OC 09-10-2013 19 November 2013 In perpetuity

    OC 02-04-2013 9 April 2013 In perpetuity

    OC 01-03-2013 28 March 2013 In perpetuity

    C6 – Approval to Operate a System of Sewage Management

    20 February 2012 13 May 2024

    Part 5 Determination –Goonbri Road Upgrade 28 March 2014 In perpetuity

    Forestry Corporation Permits

    Authorisation to Undertake Environmental Monitoring Activities

    15 February 2016 30 June 2017

    Forestry Compensation Agreement 23 January 2006 14 November 2032

    Crown Lands Licences

    RI 507102 12 November 2012 14 November 2032

    RI 533986 5 June 2014 14 November 2032

    2.3 Mine Operation Introduction and History

    Boggabri Coal Mine (BCM) is an open cut coal mine located 15 km north-east of the township of Boggabri

    in north-western New South Wales (NSW). BCM is managed by Boggabri Coal Operations Pty Ltd

    (BCOPL) which is majority owned by Idemitsu Australia Resources Group (IAR), a subsidiary of

    Japanese company Idemitsu Kosan Pty Ltd.

    Environmental assessments first commenced at BCM in 1976 followed by grant of approval for the project

    in 1989, and the commencement of operations in 2006. Truck and excavator operations produce a

    crushed and screened export quality thermal coal and pulverised coal injection product, which is

    transported from the mine via rail to the Port of Newcastle, for export to overseas markets. In the 2017

    calendar year BCM produced 6.9 million tonnes (Mt) of product coal.

    In 2009, BCOPL lodged a major project application under the now-repealed Part 3A of the Environmental

    Planning and Assessment Act 1979 (EP&A Act). This project approval (Project Approval 09_0182) (PA),

    was granted by the NSW Planning Assessment Commission (PAC) in June 2012, allowing for extraction

    of up to 8.6 Mtpa of run of mine (ROM) coal from BCM until the end of year 2033 (the Project).

    Under the PA, a new rail load-out facility and rail spur was constructed. Operation of this infrastructure

    commenced in December 2014. This has eliminated routine road transport of product coal between the

    mine infrastructure area (MIA) and the Boggabri Coal Terminal (BCT). All product coal is currently

    transported from site via rail. A new Coal Handling and Preparation Plant (CHPP) was commissioned in

    mid-2015, enabling further processing of ROM coal required for the mine to reach the full production rate.

  • Annual Review 2017

    BCOPL Page 12

    The PA also provides for the upgrade of the overburden and coal haulage fleet and other ancillary

    infrastructure, as well as the option of a dragline.

    Six modifications to the PA have been lodged since granting of the original PA. One of these

    modifications (Mod 1) was subsequently withdrawn. The latest modification (Mod 6) was lodged for

    assessment under the EP&A Act in June 2017 and approved in July 2017. The modification involved a

    minor administrative amendment to Schedule 2, Condition 12 of the PA to address the underutilisation of

    the Boggabri Rail Spur Line. The modification made provision for BCOPL to transport up to 10 million

    tonnes of product coal via the Boggabri Rail Spur Line in any calendar year. The modification did not

    relate to any corresponding change in the approved maximum rate of production for the BCM, which

    remained at 8.6 Mtpa ROM.

    In NSW, mining operations and certain mining purposes must be carried out in accordance with a Mining

    Operations Plan (MOP) that has been approved by the NSW Department of Planning and Environment –

    Division of Resources and Energy (DRE). This obligation derives from a condition of authorisation issued

    under the Mining Act 1992. BCOPL is currently operating under an approved MOP that applies to

    activities at the BCM between 2015 and 2019. The latest amendment to the MOP (Amendment C) was

    approved in February 2017.

    2.4 Purpose and Scope of Report

    This Annual Review discusses the environmental performance of BCOPL and its contractors, in relation

    to compliance with the conditions of the PA, and other relevant leases, licences and approvals. It provides

    a summary of actual operational and environmental management activities undertaken at the BCM during

    the reporting period (1 January to 31 December 2017) and provides a review against planned works, as

    described in the MOP, and predicted impacts documented in the Continuation of Boggabri Coal Mine

    Environmental Assessment (EA) (Hansen Bailey, 2010). The Annual Review also covers community

    relations and addresses mine development and rehabilitation undertaken during the reporting period.

    The Annual Review has been prepared to satisfy the conditions of the PA (in particular Condition 4 of

    Schedule 5) and CL 368. Key requirements of these approvals are described in Table 2-3. A map

    illustrating the mine locality and project boundary is provided in Figure 2-1 while relevant monitoring

    points and land ownership are shown in Appendix A. Offset properties for BCM are identified on the

    figures provided in Appendix B.

    This document has been prepared generally in accordance with the Post-approval requirements for State

    significant mining developments – Annual Review Guideline (NSW Government, 2015), where

    practicable, as well as the relevant BCOPL reporting framework.

    http://www.planning.nsw.gov.au/~/media/3AA21D35168042FE813DD0FB92E00E58.ashxhttp://www.planning.nsw.gov.au/~/media/3AA21D35168042FE813DD0FB92E00E58.ashx

  • Annual Review 2017

    BCOPL Page 13

    Table 2-3 Annual Review requirements

    Licence, Approval or Guideline

    Section Reference

    Requirement Reference in this report

    CL 368 Condition 4 (a) The lease holder must lodge Environmental Management Reports (EMR) with the Director-General annually or at dates otherwise directed by the Director-General.

    (b) The EMR must:

    i. Report against compliance with the MOP

    ii. Report on progress in respect of rehabilitation completion criteria

    iii. Report on the extent of compliance with regulatory requirements; and

    iv. Have regard to any relevant guidelines adopted by the Director-General

    Whole document

    Project Approval 09_0182

    Schedule 5, Condition 4

    Annual Review

    By the end of March each year, the Proponent shall review the environmental performance of the project for the previous calendar year to the satisfaction of the Secretary. This review must:

    (a) describe the development (including any rehabilitation) that was carried out in the past calendar year, and the development that is proposed to be carried out over the current calendar year;

    Section 8

    (b) include a comprehensive review of the monitoring results and complaints records of the project over the past year, which includes a comparison of these results against the:

    relevant statutory requirements, limits or performance measures / criteria;

    monitoring results of previous years; and

    relevant predictions in the EA

    Section 4, Section 7.3

    (c) identify any non-compliance over the last year, and describe what actions were (or are being) taken to ensure compliance;

    Section 4, Section 4.15.2.1

    (d) identify any trends in the monitoring data over the life of the project;

    Section 4

    (e) identify any discrepancies between the predicted and actual impacts of the project, and analyse the potential cause of any significant discrepancies; and

    Section 4

    (f) describe what measures will be implemented over the next year to improve the environmental performance of the project.

    Section 9

    Schedule 3, Condition 10

    The Proponent shall:

    (a) conduct an annual testing program of the attenuated plant on site to ensure that the attenuation remains effective;

    (b) restore the effectiveness of any attenuation if it is found to be defective; and

    (c) report on the results of any testing and/or attenuation work within the Annual Review.

    Section 4.3.2.2

  • Annual Review 2017

    BCOPL Page 14

    Licence, Approval or Guideline

    Section Reference

    Requirement Reference in this report

    Schedule 3, Condition

    12

    The proponent shall …

    (i) use its best endeavours to achieve the long term intrusive noise goals for the project in Table 5, where this is reasonable and feasible, and report on the progress towards achieving these

    goals in the annual review; and

    Section 0

    Schedule 3, Condition

    68

    The Proponent shall:

    (a) implement all reasonable and feasible measures to minimise the waste (including coal reject) generated by the project;

    (b) ensure that the waste generated by the project is appropriately stored, handled and disposed of;

    (c) monitor and report on the effectiveness of the waste minimisation and management measures in the Annual Review.

    Section 4.9

    Schedule 3, Condition 77

    The proponent shall prepare and implement a Social Impact Management Plan (which will)…

    (h) include a monitoring program, incorporating key performance indicators and a review and reporting protocol, including

    reporting in the annual review.

    Section 7

    Boggabri Coal Project EA

    Section 8 BCOPL will prepare an Annual Review (which summarises monitoring results and reviews performance) and distribute it to the relevant regulatory authorities and the Boggabri CCC.

    Whole document

    2.5 Actions from 2016 Annual Review

    The 2016 Annual Review (previously termed Annual Environmental Management Report (AEMR)) was

    provided to DRE, NSW Department of Primary Industries (DPI) – Agriculture, NSW Environment

    Protection Authority (EPA) and Department of Planning and Environment (DPE) in March 2017.

    BCOPL received confirmation on 5 May 2017 that the 2016 AEMR generally satisfied DPE’s Annual

    Review requirements. No written feedback was received from any other regulatory agencies.

    A total of five comments were received from DPE regarding actions to be addressed in the 2017 Annual

    Review. These comments and a reference to where each one is addressed in this document are

    presented in Table 2-4.

    Table 2-4 Issues from 2016 AEMR to be addressed in 2017 Annual Review

    Action required from previous AEMR Action taken by the Operator Section Addressed

    a) Section 2 Introduction – please

    include the operational disturbance

    footprint, mining lease boundaries

    and offset areas on Figure 2-1

    Figure 2-1 has been updated to include the elements requested by DPE.

    Figure 2-1

  • Annual Review 2017

    BCOPL Page 15

    Action required from previous AEMR Action taken by the Operator Section Addressed

    b) Section 2.5 Actions Required from

    previous AR review – please include

    comments from other regulatory

    agencies. If no feedback provided,

    please state in this section

    Section 2.5 has been updated to state that no feedback on the 2016 Annual Review was received from any other agencies.

    Section 2.5

    c) Section 4.3 – Operational Noise –

    please provide details of the joint rail

    noise assessment and evidence of

    compliance with Schedule 3

    Condition 11

    Details of the joint rail noise assessment and evidence of compliance with Schedule 3, Condition 11 has been provided in Section 4.3.2.4.

    Section 4.3.2.4

    d) Section 5 Incidents and Non-

    Compliance – please include a

    summary of any warning letters,

    official cautions, penalty notices or

    prosecution proceedings by any

    regulatory agency, and a summary

    of the operator’s response to any

    official cautions or warning letters,

    penalty notices or prosecution

    proceedings, as per Section 11 of

    the Annual Review Guideline

    (October 2015).

    A summary of any warning letters, official cautions, penalty notices or prosecution proceedings by any regulatory agency, and a summary of BCOPL’s responses has been provided in Section 5.

    Section 5

    e) Section 9 Activities proposed for

    next reporting period – please

    include a timeline for implementation

    of measures to be completed in the

    next reporting period, as per Section

    12 of the Annual Review Guideline

    (October 2015)

    A timeline for implementation of measures to be completed in the next reporting period has been provided in Section 9.

    Section 9

  • Projection: Transverse MercatorCoordinate System: GDA 1994 MGA Zone 56

    © WSP Australia Pty Ltd ("WSP") Copyright in the drawings, information and data recorded ("the information") is the property of WSP. This document and the information are solely for the use of the authorised recipient and this document may not be used, copied or reproduced in whole or part for any purpose other than that which it was supplied by WSP. WSP makes no representation, undertakes no duty and accepts no responsibility to any third party who may use or rely upon this document or the information.NCSI Certified Quality System to ISO 9001. © APPROVED FOR AND ON BEHALF OF WSP Australia Pty LtdIdemitsu Australia Resources Pty Ltd DRAWING. \\APNTLFPS01\proj\B\Boggabri_Coal\2171706A_Boggabri_Coal_GIS_services\10_GIS\Projects\_Drawings_Figures_Sketches\Environment\AEMR\2267037B_GIS_AEMR002_A1.mxd

    !

    !!

    !!

    !!

    !

    ! !! ! !

    !

    !!

    !!

    !

    !!

    !

    !

    !

    ! !

    ! !

    !!

    !!

    !

    !!

    !!

    !!

    !

    !!!

    !

    !

    !

    !

    !

    !!

    !!

    !!

    !

    !!

    !

    !

    AUTH339AUTH355

    ML1755

    CL368

    MyallPlainsMerriendi

    Mallee

    Braefield

    Jerralong

    NiokaNorth

    Sunshine

    Namoi

    Wirrilah

    Goonbri

    Legend

    !

    ! !

    ! Mine tenementBoggabri Coal MineProject Approval AreaOperational disturbance footprintBiodiversity offset area

    Scale correct when printed at A3 Landscape

    0 3 6 kmµScale 1:200,000

    DOCUMENT 2267037B_GIS_AEMR002_A1

    DATE. 2/03/2018EDITED BY. MitchellEm

    2-1FIGURETITLE. LOCALITY PLAN

    AUTHOR. suansrirImagery:Sources: Esri, HERE, DeLorme, Intermap, increment P Corp., GEBCO, USGS, FAO, NPS,

  • Annual Review 2017

    BCOPL Page 17

    3. SUMMARY OF OPERATIONS

    3.1 Mining Preparation

    Vegetation is cleared in advance of mining activities in accordance with the following documents:

    Clearing and Fauna Management Protocol, which forms Appendix B of the approved Biodiversity

    Management Plan (BMP)

    Cultural Heritage Management Plan (CHMP).

    The adopted clearing protocol follows a two-stage clearing process to minimise impacts on native

    biodiversity. Prior to removal of vegetation, trained ecologists survey the areas proposed for clearing

    (refer to Section 4.7.2.2). Archaeological salvage is also undertaken as part of the clearing process to

    identify and potentially recover artefacts (refer to Section 4.11.2.1).

    Sampling is undertaken prior to stripping of topsoils and subsoils to identify the soil resource, inform the

    preparation of a soil inventory to assist with rehabilitation planning, and to determine soil amelioration

    requirements.

    Topsoil is then stripped in accordance with the approved Soil Management Protocol (SMP) and BMP, and

    where possible, hauled directly to re-profiled rehabilitation areas. Where re-profiled areas are not ready to

    receive topsoil, the topsoil is hauled to a temporary stockpile location where it is stored for future transport

    to rehabilitation locations.

    126,540 m3 of topsoil recovery was undertaken during the 2017 reporting period. Of this, 37,310 m3 was

    spread over a 42 ha rehabilitation area in readiness for revegetation. At the end of December 2017, there

    was a total of 1,812,900 m3 of topsoil material stockpiled across the BCM.

    Saline or Potentially Acid Forming Materials

    Most of the strata are devoid of acid producing pyrite. A small proportion of the potential coal reject

    materials located near the Braymont Seam have a relatively high total sulphur content and negligible

    buffering capacity and are classified as Potentially Acid Forming – High Capacity (PAF). However, most

    overburden materials are likely to be non-acid forming and have a high factor of safety with respect to

    potential acid generation. The overburden is therefore regarded as a non-acid forming unit.

    Based on these outcomes, the risk of acid mine drainage at BCM is considered low. During the reporting

    period, BCOPL implemented an established process to manage PAF materials. The process involves

    annual sampling of reject material to identify any material that could be classified as PAF. If, following

    completion of sampling, material is identified as PAF, it is subject to deep in-pit burial. Sampling and

    analysis undertaken during the reporting period did not identify any PAF material.

    No PAF material has been identified at the BCM to date.

    3.2 Mining Operations

    Equipment

    Truck and excavator operations will continue to be undertaken as approved through the MOP term (2017-2021). The mining equipment fleet as at December 2017 is listed in Table 3-1.

  • Annual Review 2017

    BCOPL Page 18

    Table 3-1 Equipment fleet as at December 2017

    Equipment Number in fleet

    Haul trucks 45

    Excavators 10

    Front end loaders 7

    Dozers 13

    Graders 4

    Water carts 8

    Service trucks 4

    Drills 5

    Total 96

    Activities

    A summary of mining activities undertaken at BCM during the reporting period is as follows:

    Drilling and blasting of overburden

    Overburden removal by large hydraulic excavators, front-end loaders, shovels and dozers

    Haulage of waste to in-pit and out-of-pit emplacement areas

    Extraction of coal using large hydraulic excavators, front-end loaders, dozers and various Komatsu,

    Caterpillar and Hitachi rear dump trucks

    Movement of coal directly to a bypass crusher as product coal or stockpiled on ROM pads for further

    blending and crushing

    Coal Processing through the CHPP.

    Mining activities were compliant with the requirements of the PA including not clearing within 250 m of

    Maules Creek Mine mining lease boundary.

    Pit Progression

    Coal is mined from eight coal seams including the Herndale, Onavale, Teston, Thornfield, Braymont,

    Bollol Creek, Jeralong and basal Merriown seams.

    During the reporting period, pit development progressed in two directions. These were to the north-west

    and the east (refer to Figure 8-1).

    Production Waste

    Waste emplacement areas have been created through the clearing of designated out-of-pit areas and by

    in–pit emplacement in mined-out sections of the mine. The main emplacement areas are immediately to

    the west and south of the active mining area (refer to Figure 8-1).

    During the reporting period, out-of-pit dumping continued on the western overburden emplacement area

    in accordance with the MOP, to a maximum RL of 395 m. The pit void was also progressively backfilled

    with overburden.

  • Annual Review 2017

    BCOPL Page 19

    3.3 Production Statistics

    From January to November 2017, mine production at BCM was carried out by mining contractor Downer Mining. From December onwards, mine production was carried out by Boggabri Coal Operations and

    BGC Contracting. Mining was undertaken in accordance with the approved MOP and site work standards

    and procedures, which have been developed to ensure ongoing compliance with the approved

    management plans and MOP.

    A summary of production figures for the 2016 and 2017 calendar years is provided in Table 3-2 below.

    Also shown are the predicted production figures for the 2018 calendar year.

    Table 3-2 Production and Waste Rock Summary

    Material Project

    Approval Limit

    Reporting Period (Calendar Year)

    2016 (actual) 2017 (actual) 2018 (predicted)

    Waste Rock / Overburden (Mbcm3)

    N/A 50.0 52.0 54.1

    ROM Coal (Mt) 8.6 7.8 8.0 8.0

    Reject Material (Mt) N/A 1.5 1.5 1.3

    Stripped Topsoil (kbcm3)

    N/A 208.3 126.5 144.2

    Saleable Product (Mt)

    8.6 (by rail) 6.9 6.9 7.1

    Mining operations within the 2017 calendar year remained below the limits specified in the PA. Specific

    conditions from Schedule 2 of the PA are presented in Table 3-3 with responses on the compliance of

    each also provided.

    Table 3-3 Compliance with Project Approval Conditions

    Project Approval Condition No. and Description Compliance Response

    8. The Proponent shall not extract more than 3.5 million tonnes of ROM coalfrom the site in any calendar year (on a pro rata monthly basis) while ever coalis being transported along the private haul road to the coal loader, unless aroad safety audit at the intersections of Leard Forest Road and Therribri Roadhas been completed in consultation with Council and RMS, and anyrecommended actions implemented to the satisfaction of the Secretary.

    Compliant – coal was transported via the rail spur during 2017

    9. The Proponent shall not extract more than 4.5 million tonnes of ROM coalfrom the site in any calendar year (on a pro rata monthly basis) or undertakemining operations outside the disturbance area approved under DA36/88MOD 2, unless the Biodiversity Management Plan required under condition 49of Schedule 3 has been approved by the Secretary.

    Compliant –The BMP has been approved.

    10. The Proponent shall not extract more than 8.6 million tonnes of ROM coalfrom the site in any calendar year.

    Compliant – 8.0 Mt of ROM Coal was extracted in 2017

    11. The Proponent may process up to 4.2 million tonnes of ROM coal in theCHPP in any calendar year.

    Compliant – 4.0 Mt of ROM coal was processed in the Coal Processing Plant during 2017

  • Annual Review 2017

    BCOPL Page 20

    Project Approval Condition No. and Description Compliance Response

    11A. The Proponent shall not process any coal from the Tarrawonga coal mine unless it has demonstrated that adequate water license are held to account for the required water use associated with processing this coal, to the satisfaction of the Secretary.

    Compliant – no coal was processed for Tarrawonga Coal

    Mine in 2017

    12. The Proponent may transport up to 10 million tonnes of product coal viathe Boggabri Rail Spur Line in any calendar year; comprising:

    (a) 8.6 million tonnes of product coal from the Boggabri coal mine in anycalendar year; and

    (b) 3 million tonnes of product coal from the Tarrawonga coal mine in anycalendar year.

    Compliant – 6.9 Mt of product coal from the Boggabri coal mine was transported in 2017. No coal from the Tarrawonga coal mine was transported in 2017.

    13. The Proponent may only transport coal from the site by road for 22 monthsfollowing the date of this approval, or for such additional period as may resultfrom delays in construction of the Boggabri Rail Spur Line as agreed by theSecretary. Following expiry of this period, all coal is to be transported from thesite via the Boggabri Rail Spur Line unless in exceptional circumstances asagreed with RMS, the Council and approved by the Secretary.

    Compliant – transport of coal by road was ceased following completion of the Boggabri Rail Spur Line. The Boggabri Rail Spur Line was operational throughout 2017.

    3.4 Exploration

    Exploration drilling was undertaken in 2017 by BCOPL, for the purpose of determining coal quality and

    structure for modelling through the installation of infill drill holes.

    A total of 47 exploration holes were drilled by BCOPL during the reporting period, as detailed in

    Table 3-4. All holes were completed for the purpose of structure and coal quality testing and greenhouse

    gas emission estimates. Figure 3-1 indicates the location of the boreholes drilled during the 2017

    calendar year.

    Nineteen boreholes have been sealed and the balance have been left open to be used for geophysical

    testing in advance of mining.

    Table 3-4 BCM Exploration Drilling

    Hole MGA

    Easting

    MGA

    Northing

    RL (m) Total

    Depth (m)

    Drill

    Start

    Drill

    Finish

    Purpose

    BC2288 229849.81 6610961.97 351.78 175 5/06/2017 6/06/2017 Structure

    BC2289 229777.95 6611754.51 358.6 211 7/06/2017 8/06/2017 Structure

    BC2290 229768.33 6611709.51 353.46 205 8/06/2017 9/06/2017 Structure

    BC2291 228825.44 6612394.15 338.69 169 9/06/2017 10/06/2017 Structure

    BC2292 228630.42 6612290.52 330.91 163 10/06/2017 11/06/2017 Structure

    BC2293 228502.95 6612196.93 326.44 151 11/06/2017 11/06/2017 Structure

    BC2294 228329.31 6612108.5 325.49 151 11/06/2017 12/06/2017 Structure

    BC2295 228575.67 6612064.77 324.1 140 12/06/2017 13/06/2017 Structure

    BC2296 228620.76 6612199.26 329.15 151 12/06/2017 13/06/2017 Structure

    BC2297 229645.68 6611732.12 354.24 205 20/06/2017 20/06/2017 Structure

    BC2298 229690.87 6611713.69 350.7 199 21/06/2017 21/06/2017 Structure

    BC2299 229746.7 6610865.67 341.62 163 22/06/2017 22/06/2017 Structure

    BC2300 229905.32 6610892.74 349.2 169 22/06/2017 23/06/2017 Structure

  • Annual Review 2017

    BCOPL Page 21

    Hole MGA

    Easting

    MGA

    Northing

    RL (m) Total

    Depth (m)

    Drill

    Start

    Drill

    Finish

    Purpose

    BC2301 229650.46 6611779.08 360.73 217 23/06/2017 24/06/2017 Structure

    BC2302 228757.47 6612161.9 339.79 163 25/06/2017 25/06/2017 Structure

    BC2303 229058.27 6612228.41 364.55 187 26/06/2017 27/06/2017 Structure

    BC2304 228963.16 6612397.57 344.16 169 27/06/2017 4/07/2017 Structure

    BC2305 229219.3 6612313.58 367.93 199 4/07/2017 5/07/2017 Structure

    BC2306 229133.89 6612481.77 352.99 181 5/07/2017 6/07/2017 Structure

    BC2307 229096.4 6612358.89 352.75 181 6/07/2017 7/07/2017 Structure

    BC2308 228891.22 6612129.78 345.11 163 7/07/2017 7/07/2017 Structure

    BC2309 228929.95 6612264.88 345.74 169 8/07/2017 8/07/2017 Structure

    BC2310 228719.3 6612023.77 328.18 148 9/07/2017 9/07/2017 Structure

    BC2311 228793.89 6612296.24 337.07 163 10/07/2017 10/07/2017 Structure

    BC2312 226092.27 6611910.63 340.57 256 11/07/2017 12/07/2017 Coal Quality

    BC2313 229749.3 6610962.1 344.71 165.22 21/07/2017 26/07/2017 Coal Quality

    BC2314 229751.9 6611361.15 343.15 183.1 27/07/2017 5/08/2017 Coal Quality

    BC2315 229759.16 6611663.03 353.91 201.1 5/08/2017 10/08/2017 Coal Quality

    BC2316 226447.12 6611408.11 318.66 132.16 10/08/2017 19/08/2017 Gas

    BC2317 228630.47 6611978.06 322.48 135.16 20/08/2017 24/08/2017 Coal Quality

    BC2318 228073 6611968.37 315.39 171.42 25/08/2017 27/08/2017 Gas

    BC2319 229847.19 6610859.98 344.21 162.11 6/09/2017 11/09/2017 Coal Quality

    BC2320 228781.94 6612375.29 336.62 246 3/08/2017 6/08/2017 Coal Quality

    BC2321 227091.49 6611286.92 306.78 337 16/08/2017 18/08/2017 Coal Quality

    BC2322 227721.43 6611768.78 310.49 313 14/07/2017 11/08/2017 Coal Quality

    BC2323 229833.2 6611070.53 355.78 183.11 11/09/2017 22/09/2017 Coal Quality

    BC2324 229749.6 6611160.99 344.33 171.16 23/09/2017 2/10/2017 Coal Quality

    BC2325 229766.8 6611542.59 347.89 195.01 3/10/2017 8/10/2017 Coal Quality

    BC2326 228232.23 6611932.98 317.89 129.12 9/10/2017 17/10/2017 Coal Quality

    BC2327 228803 6612074 337.1 153.28 17/10/2017 23/10/2017 Coal Quality

    BC2328 228100.68 6611847.86 312.91 112.67 24/10/2017 26/10/2017 Coal Quality

    BC2329 227936.52 6611891.72 313.72 114.06 1/11/2017 3/11/2017 Coal Quality

    BC2330 229851.2 6611261.12 351.7 180.33 4/11/2017 9/11/2017 Coal Quality

    BC2331 229853.41 6611461.3 352.64 192.11 9/11/2017 24/11/2017 Coal Quality

    BC2332 229155.48 6612269.5 367.02 189.16 26/11/2017 29/11/2017 Coal Quality

    BC2333 228406.88 6612158.81 326.39 155.93 5/12/2017 9/12/2017 Coal Quality

    BC2334 228973.53 6612182.01 351.57 168.17 9/12/2017 15/12/2017 Coal Quality

  • Annual Review 2017

    BCOPL Page 22

    Figure 3-1 Extent of 2017 Exploration Drilling

  • Annual Review 2017

    BCOPL Page 23

    3.5 Construction Activities during 2017

    A summary of construction activities undertaken during the reporting period and their completion status is

    provided in Table 3-5.

    Table 3-5 Summary of Construction Activities during the Reporting Period

    Infrastructure Commencement Date Completion Date

    Mine Infrastructure Area (MIA)

    Eight drive-in concrete sumps January 2017 September 2017

    New main administration building and changes to location of CHPP offices

    September 2017 December 2017

    Access road from Train Load Out (TLO) to carpark

    October 2017 January 2018

    Other

    New ROM Haul Road January 2016 March 2017

    Internal Water Reticulation Upgrade July 2016 Ongoing

    ROM 6 (in-pit ROM) October 2016 February 2017

    Access Road 2 rectification works January 2017 March 2017

    Modifications to the rejects loop within the MIA

    January 2017 July 2017

    Installation of two productions bores and ancillary infrastructure (power lines, access tracks and water transfer pipelines)

    January 2017 December 2017

    Spur Line Rectification Works January 2016 June 2017

    New rail crossing infrastructure on mine access road from Kamilaroi Highway

    March 2017 November 2017

    3.6 Construction Activities Proposed for 2018

    Activities during the 2018 reporting period will involve construction of a new 2 GL capacity mine water

    dam (MW5) and the extension of the awning over the tyre bay in the maintenance area.

  • Annual Review 2017

    BCOPL Page 24

    4. ENVIRONMENTAL MANAGEMENT AND PERFORMANCE

    The Environment Management Strategy (EMS) provides the strategic framework for environmental

    management at BCM. The EMS:

    Outlines all relevant statutory leases, licences and approvals that apply to BCM

    Details key plans, procedures, management plans and other documents that will be implemented to

    ensure compliance with all relevant leases, licences and approvals

    Describes the key processes that will be implemented to:

    o Communicate with community and government stakeholders

    o Manage community complaints

    o Resolve disputes

    o Respond to non-compliance incidents and emergencies

    Outlines BCM’s monitoring, reporting and auditing requirements

    Outlines relevant roles, responsibilities and accountabilities relevant to environment management for

    all BCOPL employees and contractors.

    A suite of environmental management plans (EMPs) have been developed to guide environmental

    management at BCM. They have been developed in accordance with the EMS, the PA and other

    statutory requirements. The revision status of approved key EMPs, as required by the PA, is summarised

    in Table 4-1.

    Table 4-1 Key EMPs

    Management Plan Status

    BMP Rev 9 October 2015 – revised currently awaiting approval

    Blast Management Plan (BLMP) Rev 1 June 2013 - revised currently awaiting approval

    Air Quality and Greenhouse Gas Management Plan (AQGHGMP)

    Rev 3 January 2015 – revised currently awaiting approval

    Traffic Management Plan (TMP) Rev 3 October 2013 – revised currently awaiting approval

    Cultural Heritage Management Plan (CHMP) Revision 7 Approved February 2017

    Environment Management Strategy Rev Original November 2012 – revised currently awaiting approval

    Noise Management Plan (NMP) Rev 9 Approved March 2016 – revised currently awaiting approval

    Water Management Plan (WMP)

    Surface Water Management Plan (SWMP)

    Groundwater Management Plan (GWMP)

    Site Water Balance (SWB)

    Rev 6 May 2017

    Social Impact Management Plan (SIMP) Rev 4 November 2013 – revised currently awaiting approval

    Rehabilitation Management Plan (RMP) Incorporated into the 2017-21 Mining Operations Plan (MOP) for the project, at the request of the Department. The MOP was approved 19 December 2017.

  • Annual Review 2017

    BCOPL Page 25

    Management Plan Status

    Pollution Incident Response Management Plan (PIRMP)

    Rev R - revised February 2017

    The PIRMP listed in Table 4-1 applies to all activities that have the potential to generate pollution

    incidents at BCM. These include, but are not limited to, water discharge events, hazardous spills resulting

    in land or water pollution, and fire hazards.

    The PIRMP provides an overarching procedure to respond to pollution incidents at BCM including:

    outlining the response and notification requirements in the event of a pollution incident at BCM

    providing clear definition of the roles and responsibilities for pollution incident responses at BCM

    facilitating compliance with the requirements of the POEO Act and associated regulations

    4.1 Meteorology

    Environmental Management

    The PA (Schedule 3, Condition 32) requires a permanent meteorological station to be installed and

    maintained for the life of the BCM. The station must comply with the requirements of the Approved

    Methods for Sampling of Air Pollutants in New South Wales Guideline and be capable of determining the

    temperature lapse rate.

    As such, a meteorological monitoring station (MET) has been established to continuously measure and

    record wind speed, wind direction, temperature, solar radiation and rainfall at BCM. The location of the

    BCM MET station is shown on the Environmental Monitoring Location Plan in Appendix A.

    The MET station provides real-time data to BCOPL employees and contractors. Meteorological data is

    used for assessing compliance, proactive dust and noise management, and for investigative and

    reporting requirements.

    The parameters recorded by the BCM MET monitoring station and the method are outlined in Table 4-2.

    Table 4-2 MET Monitoring Parameters

    Parameter Units Frequency Averaging period

    Temperature at 2m ºC Continuous 15 minute

    Temperature at 10m ºC Continuous 15 minute

    Wind direction at 10m º Continuous 15 minute

    Sigma theta at 10m º Continuous 15 minute

    Rainfall mm/hr. Continuous 1 hour

    Solar radiation W/m2 Continuous 15 minute

    Additional requirements: – Siting & Measurement

    n/a n/a n/a

  • Annual Review 2017

    BCOPL Page 26

    Environmental Performance

    4.1.2.1 Temperature

    Maximum, minimum and average temperatures are calculated daily from the 15min recordings. Figure

    4-1 shows average monthly temperature records for the reporting period (10m MET recordings).

    Compared to the previous reporting period, the average minimum and maximum temperatures are

    notably higher in summer.

    Figure 4-1 Monthly Temperature Records

    4.1.2.2 Rainfall

    Rainfall is measured using an RG5 type flow-through monitor, with a 15-minute recording interval.

    Monthly rainfall totals for the reporting period are presented in Figure 4-2.

    A comparison of 2016 and 2017 rainfall is shown in Figure 4-3.

    0.0

    5.0

    10.0

    15.0

    20.0

    25.0

    30.0

    35.0

    40.0

    Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17

    Deg

    rees

    Cel

    siu

    s

    minimum maximum average

  • Annual Review 2017

    BCOPL Page 27

    Figure 4-2 Monthly Rainfall

    Figure 4-3 Comparison of 2016 and 2017 Rainfall

    4.1.2.3 Wind

    Wind speed and direction are important parameters for preparation of blasting activities, investigating

    noise and dust complaints, and assessing cumulative impacts as a result of other coal mines operating in

    the region. Wind data for 2017 are presented in the wind roses provided in Figure 4-4, Figure 4-5 and

    Figure 4-6. Wind speed values are displayed as metres per second.

    84

    16.6

    53.2

    14.6

    74

    45.6

    17 17

    8.4

    78.2

    59.2

    38

    0

    100

    200

    300

    400

    500

    600

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17

    Cu

    mu

    lati

    ve R

    ain

    fall

    (mm

    )

    Mo

    nth

    yl R

    ain

    fall

    (mm

    )

    Monthly Total Cumulative Rainfall

    0

    100

    200

    300

    400

    500

    600

    700

    0

    20

    40

    60

    80

    100

    120

    140

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    Cu

    mu

    ltai

    ve R

    ain

    fall

    (mm

    )

    Mo

    nth

    ly R

    ain

    fall

    (mm

    )

    2016 2017 Cumulative Total 2016 Cumulative Total 2017

  • Annual Review 2017

    BCOPL Page 28

    Analysis of data reveals that prevailing winds during the 2017 reporting period were predominantly from

    the south-east from January through April and from the north-west and east from May through December.

    The prevailing wind conditions during this reporting period were relatively consistent with the historical

    data as presented in the 2010 EA. Average wind speeds were notably higher in January, March, October

    and November and were notably lower in February, June, July and September than the previous

    reporting period.

    The MET data identified that average monthly wind speed did not exceed 3 m/s in 2016.

    January 2017

    February 2017

    March 2017

    April 2017

    Figure 4-4 Monthly Wind Rose Summary January – April 2017

  • Annual Review 2017

    BCOPL Page 29

    May 2017

    June 2017

    July 2017

    August 2017

    Figure 4-5 Monthly Wind Rose Summary May – August 2017

    September 2017

    October 2017

  • Annual Review 2017

    BCOPL Page 30

    November 2017

    December 2017

    Figure 4-6 Monthly Wind Rose Summary September – December 2017

    Improvements and Initiatives

    Building on the work completed during the 2016 reporting period, BCOPL continued to implement and

    refine the real-time air quality management system at the BCM. This included ongoing utilisation of real-

    time meteorological data and weather forecasting software to guide the day-to-day implementation of

    reactive and proactive mitigation measures.

    4.2 Air Quality

    Environmental Management

    Air quality management at BCM is undertaken in accordance with the AQGHGMP. Through

    implementation of the AQGHGMP, BCOPL execute a range of mitigation measures for air quality that

    have proved to be effective at managing dust impacts, demonstrated by maintaining compliance with

    criteria specified in the PA. During the reporting period, mitigation measures included the following:

    Dust suppression with bulk water trucks using dust suppression additives ’Avenger Coal’ and ‘Boost X’

    in mining areas, construction areas and haul roads

    Visual assessments of mining and coal transport areas to identify dust sources and modify operations

    as required

    Progressive rehabilitation of waste emplacements

    Revegetating disturbed areas of the rail corridor

    Implementation of product coal handling controls to minimise dust generation

    Maintaining unsealed surfaces and trafficable areas in good condition

    Installation and maintenance of dust suppression equipment on drill rigs

    Implementing good practice blast design to minimise dust and plan blasting to suit meteorological

    conditions

    Monitoring meteorological conditions to plan and modify operations as required

    These mitigation measures will continue to be employed throughout 2018.

  • Annual Review 2017

    BCOPL Page 31

    BCOPL implements a dust monitoring program to measure concentrations of depositional dust, PM10 and

    PM2.5 in the vicinity of the BCM. Depositional dust monitoring provides an indication of levels of dust in the

    atmosphere measured in g/m²/month of insoluble matter. PM10 measures the concentration of particulate

    matter less than 10 microns in diameter, whilst PM2.5 monitoring measures the concentration of

    particulate matter less than 2.5 microns in diameter. PM10 monitoring utilises a High Volume Air Sampler

    (HVAS) and tapered element oscillating microbalance (TEOM), whilst PM2.5 is measured only use a

    TEOM.

    The current dust monitoring program includes 3 depositional dust gauges, two HVAS and one TEOM,

    details of which are provided in Table 4-3. A figure showing the location of each air quality monitoring site

    is provided in Appendix A.

    Table 4-3 Air Quality Monitoring Sites

    Site ID To be used for compliance monitoring?

    Type Units Frequency

    D4 Yes Deposited dust gauge g/m2/month Monthly

    D5 Yes Deposited dust gauge g/m2/month Monthly

    D6 Yes Deposited dust gauge g/m2/month Monthly

    Roma

    Merriown

    Yes

    Yes

    HVAS (PM10)

    HVAS (PM10)

    µg/m3

    µg/m3 Every 6 days

    Every 6 days

    Tarrawonga No TEOM (PM10 & PM2.5) µg/m3 Continuous

    Environmental Performance

    4.2.2.1 Depositional Dust

    BCM’s depositional dust monitoring is undertaken on a monthly basis at three monitoring sites: D4, D5

    and D6 (refer to Appendix A). D5 is located on land owned by BCOPL, while D4 and D6 are located on

    land owned by Whitehaven Coal Pty Limited.

    In accordance with the PA (Schedule 3, Condition 27), the annual average depositional dust must not

    exceed the limit of 4 g/m2/month at any residence on privately owned land, or on more than 25 percent of

    any privately-owned land. Given that there are no criteria specified for non-privately owned land, the

    results have been assessed against these criteria for consistency, despite land being mine-owned.

    Sampling and analysis is undertaken in accordance with AS/NZS 3580.10.1:2003: Methods for Sampling

    and Analysis of Ambient Air – Determination of Particulate Matter – Deposited Matter – Gravimetric

    Method.

    Results

    Depositional dust samples were subject to visual analysis by a NATA accredited laboratory to determine

    sample contamination by naturally occurring impurities. Table 4-4 presents the corrected results following

    visual analysis of the three dust monitors.

    The results indicate that all depositional dust gauges remained below the criterion for the annual average

    during 2017.

  • Annual Review 2017

    BCOPL Page 32

    Table 4-4 Depositional Dust – Annual Average Results

    Monitoring Point Limit

    (g/m2/month)

    Corrected annual average* (g/m2/month)

    D4 4 2.6

    D5 4 1.6

    D6 4 1.5

    * Total adjusted after visual analysis. Annual average applies to 2017 calendar year.

    Depositional dust systems are often subject to contamination by naturally occurring impurities such as

    bird droppings, insects and vegetation. On eighteen occasions over the reporting period, samples were

    observed to be contaminated and were therefore not analysed by the laboratory. This included samples

    from January (D4 and D6), February (D4 and D6), March (D4), April (D4 and D5), May (D4), June (D4

    and D6), July (D6), August (D5 and D6), September (D6), October (D5 and D6), November (D6), and

    December (D4).

    The result for D4 and D5 are above the predicted levels documented in the EA (1.1 and 0.6 g/m2/month)

    for the closest corresponding year of operations (Year 5). D6 is located outside the area assessed in the

    EA and no predictions were provided. All dust gauge results remain below the criteria specified in the PA.

    Depositional dust levels within gauge D4

    Between 2014 and 2015, the rolling annual average of all gauges was on a downward trend. During

    2015, the trend stabilised and then began trending upwards in 2016, before stabilising in 2017.

    Depositional dust levels recorded during the 2017 reporting period remain within the range of historical

    results.

    4.2.2.2 PM10

    BCM monitors PM10 dust through two HVAS units. The BCM HVAS is located on the Merriown property

    approximately 1 km west of the BCM. The second HVAS, Roma PM10 is located on the Roma property

    and commenced operation on the 1 July 2015. Sampling is undertaken for a period of 24 hours every 6

    days. PM10 monitoring is ongoing from previous reporting periods. Results for both samplers have been

    provided in this report and will continue to be monitored throughout 2018.

    Results

    The PM10 monitoring results for Merriown HVAS and Roma HVAS over the 12 month period are provided

    in Figure 4-7 and Figure 4-8, respectively. Both figures also include BCM’s rolling average over the

    reporting period.

    In accordance with the PA, the short-term concentration limit for PM10 over each 24-hour period is 50

    µg/m3 while the long-term concentration limit for the annual average is 30 µg/m3.

    The average PM10 concentrations at the Merriown HVAS and Roma HVAS monitors over the reporting

    period were 12.0 µg/m3 and 12.5 µg/m3 per month, respectively. In comparison, the average

    concentrations at the Merriown HVAS and Roma HVAS monitors during the 2016 reporting period were

    10.4 µg/m3 and 9.9 µg/m3 per month respectively. The annual average PM10 levels are below the PM10

    levels (14µg/m3) predicted in the EA.

  • Annual Review 2017

    BCOPL Page 33

    One exceedance of the short-term PM10 criterion was recorded at the Merriown HVAS monitor during the

    reporting period. The Roma HVAS monitor also recorded two results that were higher than the short-term

    criterion, however these are not considered exceedances as the monitoring location is not used as a

    compliance measurement tool. Neither monitors recorded results that exceeded the long-term PM10

    criterion.

    The short-term PM10 results for the 2017 reporting period are generally consistent with the 2015 and 2016

    reporting periods with the exception of the individual exceedance of the short-term criterion recorded at

    the Merriown HVAS monitor and the two elevated results at the Roma HVAS monitor. Disc ploughing was

    observed in nearby paddocks at the time the single exceedance of the short-term criterion was recorded

    at the Merriown HVAS monitor. While Merriown HVAS was not included in the EA as a receiver in the air

    quality model due to it being owned by BCOPL, interpolation of the PM10 air quality contours in the EA

    indicate PM10 concentrations of between 20 to 30 µg/m3 were predicted to occur at the property during the

    reporting period. The short-term PM10 levels recorded at Merriown HVAS were generally below the levels

    predicted in the EA. The 2017 PM10 levels indicated the trend is generally stable.

    Figure 4-7 Merriown PM10 Monitoring Results

    0

    10

    20

    30

    40

    50

    60

    70

    Jan

    /17

    Fe

    b/1

    7

    Ma

    r/1

    7

    Ap

    r/17

    Ma

    y/1

    7

    Jun

    /17

    Jul/17

    Au

    g/1

    7

    Se

    p/1

    7

    Oct/

    17

    Nov/1

    7

    Dec/1

    7

    PM

    10

    (ug

    /m3)

    Merriown - PM10

    Merriown - PM10 Current annual average PM10 24hr Criterion PM10 Annual Criterion

  • Annual Review 2017

    BCOPL Page 34

    Figure 4-8 Roma PM10 Monitoring Results

    4.2.2.3 Total Suspended Particulates

    The ambient air quality criterion for TSP quoted in Table 9 of the PA (annual average 90µg/m3) is based on

    a value derived by the National Health and Medical Research Council (NHMRC) in 1996. There is an

    established relationship between TSP concentration and the concentration of PM10. In areas where coal

    mining is a significant component of the local particulate emission inventory, PM10 typically comprises ~40%

    of the TSP (SPCC, 1986 and others).

    As prior studies have confirmed that the long-term average PM10 to TSP ratio is close to 0.4:1, that is, 40%

    of TSP is comprised of PM10, inversely, the relationship between TSP and PM10 can be written as:

    TSP = PM10 x 2.5. Due to the nature of the relationship between TSP and PM10 levels, the TSP criterion of

    90 µg/m3 (annual average) will always be satisfied when the long-term PM10 criterion of 30 µg/m3 is satisfied.

    As discussed above in Section 4.2.2.2, Boggabri Coal currently monitor PM10 at two locations within the

    vicinity of the operation; the ‘Merriown HVAS’ and ‘Roma HVAS’ monitors.

    In consideration of the historical PM10 monitoring undertaken for the BCM (i.e. results have historically been

    significantly below the PM10 annual average criteria) and the above relationship between PM10 and TSP,

    BCOPL consider that compliance with the long-term TSP criteria can be demonstrated via the application

    of the known relationship between PM10 and TSP. This can be achieved by calculating annual average TSP

    results from the PM10 monitoring using the above calculation for the locations in the vicinity of the operation.

    The calculation of TSP is based on the available data at the Merriown HVAS and Roma HVAS monitoring

    locations.

    0

    10

    20

    30

    40

    50

    60

    70Jan

    /17

    Fe

    b/1

    7

    Ma

    r/1

    7

    Ap

    r/17

    Ma

    y/1

    7

    Jun

    /17

    Jul/17

    Au

    g/1

    7

    Se

    p/1

    7

    Oct/

    17

    No

    v/1

    7

    De

    c/1

    7

    PM

    10

    (ug

    /m3)

    Roma - PM10

    Roma- PM10 Current annual average PM10 24hr Criterion PM10 Annual Criterion

  • Annual Review 2017

    BCOPL Page 35

    The results indicate the annual average TSP at Merriown (30.1 ug/m3) and Roma (31.1 µg/m3) are below

    the air quality criterion in the PA. Similarly, the results indicate the level of TSP at Roma is below the TSP

    levels predicted in the EA (35µg/m3) for the reporting period.

    Improvements and Initiatives

    BCOPL installed an additional TEOM at the mine-owned ‘Wilberoi East’ property during the reporting

    period. The Wilberoi TEOM will be linked up with the ‘Sentinex’ real-time air quality management system

    and be utilised as an additional tool to guide the day-to-day management of air quality at the BCM.

    4.3 Operational Noise

    Environmental Management

    Operational noise is managed by BCOPL in accordance with the approved NMP. The NMP covers all

    operational activities with the potential to ge