Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Boggabri Coal Operations Pty Ltd
Boggabri Coal Mine
2017 Annual Review 31 March 2018
Annual Review 2017
BCOPL Page i
Revision Control Chart
Rev No Original 1 2 3 4
Revision Date 31 March 2018
Prepared by J McDonough
Reviewed by D Martin / H Russell
Approved by R Balks
Signature
Distribution Control
Company Position
BCOPL Environment Superintendent
Division of Resources and Geoscience Regional Environment Officer
Department of Planning and Environment Senior Planning Officer
Department of Primary Industry – Land and Natural Resources Area Manager North West
Department of Planning Infrastructure – Water Water Regulation Officer
Environment Protection Authority Regional Operations Officer Armidale
NSW Forests Forestry Occupancy Supervisor
Community Consultative Committee Chairman
BGC Contracting Project Manager
Annual Review Title Block
Name of Operation Boggabri Coal Mine
Name of Operator Boggabri Coal Operations Pty Ltd
Development Consent / Project Approval # 09_0182
Name of Holder of Project Approval Boggabri Coal Pty Limited (now trading as Boggabri Coal Operations Pty Limited)
Mining Lease # CL 368
Name of holder of mining lease Boggabri Coal Pty Limited (now trading as Boggabri Coal Operations Pty Limited)
Water Licence # see page 3 below for details
Name of holder of water access licences Boggabri Coal Pty Limited (now trading as Boggabri Coal Operations Pty Limited)
MOP Commencement Date 19 December 2017
MOP Completion Date 31 December 2021
Annual Review Commencement Date 1 January 2017
Annual Review Completion Date 31 December 2017
I, Ray Balks, certify that this audit report is a true and accurate record of the compliance status of Boggabri Coal Mine for the period 1 January 2017 to 31 December 2017 and that I am authorised to make this statement on behalf of Boggabri Coal Operations Pty Limited.
Name of authorized reporting officer Ray Balks
Title of authorized reporting officer General Manager Operations
Signature of authorized reporting officer
Date 31/03/2018 (Rev O)
Annual Review 2017
BCOPL Page ii
Contents Page Number
1. STATEMENT OF COMPLIANCE 1
2. INTRODUCTION 9
2.1 Mine Contacts 9
2.2 Approvals, Licences and Mining Leases 9
2.3 Mine Operation Introduction and History 11
2.4 Purpose and Scope of Report 12
2.5 Actions from 2016 Annual Review 14
3. SUMMARY OF OPERATIONS 17
3.1 Mining Preparation 17
Saline or Potentially Acid Forming Materials 17
3.2 Mining Operations 17
Equipment 17
Activities 18
Pit Progression 18
Production Waste 18
3.3 Production Statistics 19
3.4 Exploration 20
3.5 Construction Activities during 2017 23
3.6 Construction Activities Proposed for 2018 23
4. ENVIRONMENTAL MANAGEMENT AND PERFORMANCE 24
4.1 Meteorology 25
Environmental Management 25
Environmental Performance 26
Improvements and Initiatives 30
4.2 Air Quality 30
Environmental Management 30
Environmental Performance 31
Improvements and Initiatives 35
4.3 Operational Noise 35
Environmental Management 35
Environmental Performance 36
Improvements and Initiatives 42
4.4 Blasting 43
Annual Review 2017
BCOPL Page iii
Environmental Management 43
Environmental Performance 43
Improvements and Initiatives 45
4.5 Surface Water 46
Environmental Management 46
Environmental Performance 49
Improvements and Initiatives 54
4.6 Groundwater 54
Environmental Management 54
Environmental Performance 56
Improvements and Initiatives 69
4.7 Biodiversity 70
Environmental Management 70
Environmental Performance 71
Improvements and Initiatives 79
4.8 Hazardous Materials 80
Environmental Management 80
Environmental Performance 80
4.9 Waste Management 82
Environmental Management 82
Environmental Performance 83
4.10 Spontaneous Combustion 86
Environmental Management 86
Environmental Performance 86
4.11 Heritage 86
Environmental Management 86
Environmental Performance 87
Improvements and Initiatives 88
4.12 Greenhouse Gases 89
Environmental Management 89
Environmental Performance 89
Improvements and Initiatives 90
4.13 Public Safety 90
Environmental Management 90
Environmental Performance 90
4.14 Traffic 92
Environmental Management 92
Annual Review 2017
BCOPL Page iv
Environmental Performance 92
4.15 Socio-economic 93
Socio-economic Management 93
Environmental Performance 93
5. INCIDENTS AND NON-COMPLIANCES 101
5.1 Notices, Warnings and Other Compliance-Related Correspondence 104
6. AUDITS 107
6.1 Independent Environmental Compliance Audit 107
Scope of audit 107
Audit Outcomes 107
DPE Review 107
Status of Audit Recommendations 107
7. COMMUNITY 108
7.1 Community Programs and Investment 108
7.2 Community Consultative Committee 109
7.3 Complaints 110
Management of Complaints 110
Registered Environmental Complaints 110
7.4 Workforce Profile 112
BCOPL Employees 112
Mining Contractor 112
8. REHABILITATION 113
8.1 Rehabilitation Methodology 113
8.2 Rehabilitation Progress 113
Summary of Land Rehabilitation 113
2017 Plantings 114
Rehabilitation Status 114
8.3 Rehabilitation Biodiversity Monitoring 116
Photographic Monitoring 116
Summary of Findings 118
8.4 Growth Performance 119
Growth Medium Suitability 119
8.5 Rehabilitation in 2018 120
9. ACTIVITIES PROPOSED FOR NEXT ANNUAL REVIEW PERIOD 121
Annual Review 2017
BCOPL Page v
10. REFERENCES 122
Annual Review 2017
BCOPL Page vi
List of tables Table 1-1 Statement of compliance 1 Table 1-2 Non-compliances during the reporting period 2 Table 2-1 BCM Mine Contacts 9 Table 2-2 Key Approvals, Consents, Mining Leases and Licences 9 Table 2-3 Annual Review requirements 13 Table 2-4 Issues from 2016 AEMR to be addressed in 2017 Annual Review 14 Table 3-1 Equipment fleet as at December 2017 18 Table 3-2 Production and Waste Rock Summary 19 Table 3-3 Compliance with Project Approval Conditions 19 Table 3-4 BCM Exploration Drilling 20 Table 3-5 Summary of Construction Activities during the Reporting Period 23 Table 4-1 Key EMPs 24 Table 4-2 MET Monitoring Parameters 25 Table 4-3 Air Quality Monitoring Sites 31 Table 4-4 Depositional Dust – Annual Average Results 32 Table 4-5 Current Noise Monitoring Locations 36 Table 4-6 Noise Limits 36 Table 4-7 Summary of Attended Noise Monitoring Results - dB(A) LAeq (15 minutes) & L1 (1 min) 38 Table 4-8 Summary of 2017 sound power screening results 40 Table 4-9 Surface Water Quality Monitoring Regime 48 Table 4-10 Surface Water Quality Testing Parameters 49 Table 4-11 Summary of Frequency Based Monitoring Results 50 Table 4-12 Water Take 51 Table 4-13 Predicted Water Demand 51 Table 4-14 Water Storage Summary 53 Table 4-15 Construction Details of Monitoring Bores 55 Table 4-16 Groundwater Quality Testing Parameters 56 Table 4-17 Minimum Measured Water Levels 57 Table 4-18 Groundwater Quality Trigger Values 61 Table 4-19 Results Summary for In Situ Water Quality Measurements 64 Table 4-20 Results Summary for Analysis of Major Ions 65 Table 4-21 Results Summary for Analysis of Metals 66 Table 4-22 Results Summary for Analysis of Nutrients 67 Table 4-23 Animal Groups Encountered during Clearing Operations 72 Table 4-24 Threatened Species Encountered during Clearing Operations 73 Table 4-25 Explosives and Hazardous Materials Licence / Notification Holders 81 Table 4-26 Diesel Fuel Consumption 81 Table 4-27 Summary of Mining Operation Waste Disposal 83 Table 4-28 Summary of Bioremediation Areas 85 Table 4-29 BCOPL GHG and Energy Statistics 89 Table 4-30 Social Impact Monitoring Summary 93 Table 4-31 Approval Rates for New Dwellings in Gunnedah and Narrabri 2010 - 2013 96 Table 4-32 Local School Enrolments 2011 - 2016 98 Table 4-33 Key Crime Statistics 2011 - 2017 99 Table 5-1 Non-compliances during the reporting period 101 Table 5-1 Notices and warnings received during the reporting period 105 Table 7-1 BCOPL Community Funding 2017 108 Table 7-2 Complaint Summary 111 Table 7-3 Residential Locality of BCOPL Employees 112 Table 8-1 Rehabilitation Status 114 Table 8-2 Survey Locations for Rehabilitation Sites at BCM 116 Table 9-1 Activities Proposed for next Annual Review Period 121
Annual Review 2017
BCOPL Page vii
List of figures Figure 2-1 Locality Map 16 Figure 3-1 Extent of 2017 Exploration Drilling 22 Figure 4-1 Monthly Temperature Records 26 Figure 4-2 Monthly Rainfall 27 Figure 4-3 Comparison of 2016 and 2017 Rainfall 27 Figure 4-4 Monthly Wind Rose Summary January – April 2017 28 Figure 4-5 Monthly Wind Rose Summary May – August 2017 29 Figure 4-6 Monthly Wind Rose Summary September – December 2017 30 Figure 4-7 Merriown PM10 Monitoring Results 33 Figure 4-8 Roma PM10 Monitoring Results 34 Figure 4-9 Summary of Peak Vibration Monitoring Results 44 Figure 4-10 Blast Overpressure Results 45 Figure 4-11 Monthly Dust Suppression Water Usage 52 Figure 4-12 Long Term Groundwater Levels for all Bores 57 Figure 4-13 Alluvium and Boggabri Volcanics Hydrograph and CDFM Curve 59 Figure 4-14 Maules Creek Formation Hydrographs 60 Figure 4-15 Groundwater Trends in Temperature 62 Figure 4-16 Groundwater Trends in pH 63 Figure 4-17 Groundwater Trends in Electrical Conductivity 63 Figure 4-18 Artefact located in the Tree Clearing Area 2017 87 Figure 4-19 Sources of BCM Scope 1 and Scope 2 Emissions 90 Figure 4-20 New Dwelling Commencements in Gunnedah and Narrabri 2011 – 2013 97 Figure 4-21 Employment Land Availability Gunnedah LGA 2011 - 2013 97 Figure 4-22 Employment Land Availability Narrabri LGA 2011 - 2013 98 Figure 7-1 Complaints Received 111 Figure 8-1 Extent of Mining and Rehabilitation at the end of the 2017 Reporting Period 115 Figure 8-2 2008 Rehabilitation (nine years old) 117 Figure 8-3 2010 Rehabilitation (seven years old) 117 Figure 8-4 2011 Rehabilitation (six years old) 118
List of appendices Appendix A Environmental Monitoring Location Plan Appendix B Biodiversity Monitoring Maps Appendix C Independent Environmental Audit Action Plan
Annual Review 2017
BCOPL Page 1
Glossary
Abbreviations Terms
AR Annual Review
AEMR Annual Environmental Management Report
AHCS Aboriginal Heritage Conservation Strategy
AQMS Air Quality Management Strategy
AQGHGMP Air Quality and Greenhouse Gas Management Plan
ARI Average Recurrence Interval
ASCF Aboriginal Stakeholder Consultative Forum
BCOPL Boggabri Coal Operations Pty Limited
BCM Boggabri Coal Mine
BCT Boggabri Coal Terminal
BFMP Blast Fume Management Protocol
BIA Biodiversity Impact Assessment
BLMP Blast Management Plan
BLMS Blast Management Strategy
BMP Biodiversity Management Plan
BOA Biodiversity Offset Area
BOS Biodiversity Offset Strategy
BTM Complex Boggabri-Tarrawonga-Maules Creek Complex
CCC Community Consultative Committee
CDFM Cumulative Deviation From Mean Rainfall
CHMP Cultural Heritage Management Plan
CHPP Coal Handling and Preparation Plant
DoEE Department of Environment and Energy (Cth)
DPE Department of Planning and Environment
DPI Department of Primary Industries
DRE NSW Division of Resources and Energy
EA Environmental Assessment
EMP Environmental Management Plan
EMS Environmental Management System
EPA Environment Protection Authority
EP&A Act Environmental Planning and Assessment Act 1979 (NSW)
EPBC Act Environment Protection and Biodiversity Conservation Act 1999 (Cth)
EPL Environment Protection Licence
GHG Greenhouse Gas
GWMP Groundwater Management Plan
HVAS High Volume Air Sampler
IAR Idemitsu Australia Resources Group
MIA Mine Infrastructure Area
MET Station Meteorological Monitoring Station
MOP Mining Operations Plan
Mtpa Million Tonnes Per Annum
Annual Review 2017
BCOPL Page 2
Abbreviations Terms
MWD Mine Water Dam
NGER National Greenhouse and Energy Reporting
NGER Act National Greenhouse and Energy Reporting Act 2007(Cth)
NPI National Pollutant Inventory
NSC Narrabri Shire Council
OEH NSW Office of Environment and Heritage
PA Project Approval 09_0182
PAC NSW Planning and Assessment Commission
PAF Potential Acid Forming
PIRMP Pollution Incident Response Management Plan
PM2.5 Particulate matter < 2.5 µm
PM10 Particulate matter < 10 µm
POEO Act Protection of the Environment Operations Act 1997(NSW)
RAP Registered Aboriginal Parties
ROM Run of Mine
SCMP Spontaneous Combustion Management Plan
SEWPaC Commonwealth Department of Sustainability, Environment, Water, Populations and Communities (now Commonwealth Department of the Environment and Energy)
SIMP Social Impact Management Plan
SMP Soil Management Protocol
SWB Site Water Balance
SWMP Surface Water Management Plan
TARP Trigger Action Response Plan
TEOM Tapered Element Oscillating Microbalance
TLO Train Load-out Facility
TMP Traffic Management Plan
TSC Act Threatened Species Conservation Act 1995 (NSW)
WAL Water Access Licence
WMP Water Management Plan
WMS BTM Complex Water Management Strategy
http://www.comlaw.gov.au/Series/C2007A00175http://www.comlaw.gov.au/Series/C2007A00175
Annual Review 2017
BCOPL Page 1
1. STATEMENT OF COMPLIANCE
In accordance with the requirements of the Post-approval requirements for State significant mining
developments – Annual Review Guideline (NSW Government, 2015), a statement of compliance has
been prepared to document the status of compliance with BCM's Project Approval 09_0182 (including
Statement of Commitments), mining leases and other relevant approvals as at the end of the 2017
reporting period. Table 1-1 identifies whether or not non-compliances occurred during the reporting period
for each statutory approval. Where non-compliances are identified, further details are provided in
Table 1-2. Non-compliances have been colour-coded in that table, in accordance with the descriptions
provided in the Annual Review Guideline.
Table 1-1 Statement of compliance
Approval Were all conditions of the relevant approval(s) complied with during the reporting period?
Project Approval 09_0182 (incl. Statement of Commitments) No
Coal Lease 368 Yes
Mining Lease 1755 Yes
Authorisation 355 Yes
Authorisation 339 Yes
EPL 12407 No
EPL 20404 Yes
WAL 12691 Yes
WAL12767 Yes
WAL14483 Yes
WAL15037 Yes
WAL24103 Yes
WAL29473 Yes
WAL29562 Yes
WAL2571 Yes
WAL2572 Yes
WAL2595 Yes
WAL2596 Yes
WAL31084 Yes
WAL14495 Yes
WAL36547 Yes
WAL31096 Yes
http://www.planning.nsw.gov.au/~/media/3AA21D35168042FE813DD0FB92E00E58.ashxhttp://www.planning.nsw.gov.au/~/media/3AA21D35168042FE813DD0FB92E00E58.ashx
Annual Review 2017
BCOPL Page 2
Table 1-2 Non-compliances during the reporting period
Relevant approval
Ref. Condition description Compliance status*
Comment BCOPL response Where addressed in the Annual Review
PA 09_0182 (incl. Statement of Commitments)
Sch 3, C12(b)
The Proponent shall: operate a comprehensive noise management system on site that uses a combination of predictive meteorological forecasting and real-time noise monitoring data to guide the day to day planning of mining operations and the implementation of both proactive and reactive noise mitigation measures to ensure compliance with the relevant conditions of this approval…
Non-compliance (low risk)
The non-compliance was identified during the Independent Environmental Audit. The auditor’s comments were: Sentinex-real-time monitoring-daily monitoring data provided to key BCOPL staff and contractors via email. Evidence of triggers for real time noise monitoring outlined in the Noise MP. Minimal evidence provided for reviewing/changing operations based on real-time noise monitoring results (implementation of triggers). The auditors recommendations were: 1. Further liaison with the DPE
regarding approval of the June 2017 version of the Noise Management Plan.
2. Implementation of the real time monitoring program and recording of reviewing/changing operations in site documentation (including OCE reports).
3. Additional information should be provided in the AEMR relating to activities for reviewing/changing operations based on real time noise monitoring.
BCOPL will continue to proactively manage noise impacts in line with the approved Noise Management Plan. BCOPL has implemented recommendations 1 and 2. For recommendation no. 3, BCOPL will continue to prepare AEMRs/Annual Reviews in accordance with the Annual Review Guideline (DPE, 2015) and to the satisfaction of DPE.
Section 4.3 and Section 5
Sch 3, C13(f)
The Proponent shall prepare and implement a Noise Management Plan for the project to the satisfaction of the Secretary. This plan must: include a monitoring program that: - uses a combination of real time and supplementary attended monitoring to evaluate the performance of the project;
Non-compliance (low risk)
The non-compliance was identified during the Independent Environmental Audit. The auditor’s comments were: Noise monitoring - non compliant relating to the implementation of the real-time noise monitoring program (sub condition f). Minimal evidence provided for reviewing/changing operations based on real-time noise monitoring results (implementation of triggers).
As above Section 4.3 and Section 5
Annual Review 2017
BCOPL Page 3
Relevant approval
Ref. Condition description Compliance status*
Comment BCOPL response Where addressed in the Annual Review
- evaluates and reports on the effectiveness of the noise management system on site…
The auditor’s recommendations were as per those outlined above for Sch3, cl12(b).
Sch 3, C38(b)
The Proponent shall prepare and implement a Surface Water Management Plan, which includes: …
a detailed description of the water management system on site, including the:
clean water diversion systems;
erosion and sediment controls (dirty water system);
mine water management systems including irrigation areas;
discharge limits in accordance with EPL requirements;
water storages;
haul road and Boggabri Rail Spur Line and bridge flood and water diversions;
performance criteria for the following, including trigger levels for investigating any potentially adverse impacts associated with the project:
the water management system;
soils within the irrigation area;
downstream surface water quality;
Non-compliance (low risk)
The non-compliance was identified during Independent Environmental Audit. The auditor’s comments were: Currently clean water is being captured in a dam (road built across) and clean water from a large section of the catchment does not leave site. This is not as per the Water Management Plan (July 2017 - unapproved) and the MOP. SLR understands this dam was only built recently in the month prior to the site visit however the site is not licenced to collect water from this dam, with the original design to divert the clean water around the site. Field inspection noted the incorrect clean/dirty water management in the area around the ‘clean water diversion drain’. Currently clean water is being captured in a dam (road built across) and clean water from a large section of the catchment does not leave site. The auditor’s recommendations were: 1. Improvements required for
clean/dirty water management in the area around the ‘clean water diversion drain’. Pursue options for ensuring that clean water diversions shown on MOP, in Water Management Plan, align with what is constructed on site and all necessary licences are in place for the solution. Undertake consultation with government agencies as required.
2. SD11 – adjacent to rail load out. Rilling across dam. Pipeline has
BCOPL will implement recommendations 1, 2 and 3 by 16 April 2018. For recommendation 4, BCOPL will continue to manage the capacity of SD6 in accordance with the approved Surface Water Management Plan.
Section 5 and Appendix C
Annual Review 2017
BCOPL Page 4
Relevant approval
Ref. Condition description Compliance status*
Comment BCOPL response Where addressed in the Annual Review
downstream flooding impacts, including flood impacts due to the construction and operation of the Boggabri Rail Spur Line and rail bridge; and
stream and riparian vegetation health, including the Namoi River;
a program to monitor:
the effectiveness of the water management system;
soils within the irrigation area; and
surface water flows and quality in the watercourses that could be affected by the project;
downstream flooding impacts; and
a plan to respond to any exceedances of the performance criteria, and mitigate and/or offset any adverse surface water impacts of the project;…
caused erosion and if not treated could affect dam integrity. Recommend moving pipeline location closer to the water or additional rocks placed around the eroded area to reduce erosion.
3. Completion of monitoring for stream and riparian monitoring for Nagero Creek and the Namoi River as per the Water Management Plan.
4. Tarrawonga Drainage Area - protocol. Develop a protocol to review the capacity of SD6 if the Tarrawonga drain is close to discharging (Tarrawonga drain flows to SD6). BCOPL should obtain samples of surface water when water enters the Boggabri site from the Tarrawonga Drainage Area.
Sch3, C38(c)
The Proponent shall prepare and implement a Groundwater Management Plan, which includes:
the monitoring and testing requirements specified in the PAC recommendations for groundwater
Non-compliance (low risk)
The non-compliance was identified during the Independent Environmental Audit. The auditor’s comments were: There were occasions during the audit period where monitoring was unable to be undertaken at some groundwater locations. These were outlined in the EPL Annual Returns. The reason for these bores not being
BCOPL will continue to liaise with DPI Water for relevant licensing matters on an ‘as required’ basis. Redundant groundwater monitoring bores have been removed from the revised Groundwater
Section 4.6 and Section 5
Annual Review 2017
BCOPL Page 5
Relevant approval
Ref. Condition description Compliance status*
Comment BCOPL response Where addressed in the Annual Review
management as set out in Appendix 6;
a program to monitor and assess:
groundwater inflows to the open cut mining operations;
the seepage/leachate from water storages, backfilled voids and the final void;
interconnectivity between the alluvial and bedrock aquifers;
background changes in groundwater yield/quality against mine-induced changes;
the impacts of the project on: o regional and local
(including alluvial) aquifers;
o groundwater supply of potentially affected landowners;
o aquifers potentially affected by the mine irrigation area;
o groundwater dependent ecosystems (including potential impacts on stygo-fauna)
monitored include 'monitoring bore casing damaged due to ground movement, preventing a pump or bailer from being placed in the bore to obtain a groundwater sample. SLR understands additional bores will be installed (following approval from the DPI Water) to offset the loss of bores. The auditor’s recommendations were:
1. Further liaison with DPI Water regarding licencing of bores.
2. Updates to the Water Management Plan if required for most up to date monitoring locations.
Management Plan, which was approved by the DPE in May 2017. An application to remove these redundant monitoring points from EPL 12407 was lodged with NSW EPA during the reporting period. The application is currently being processed.
Annual Review 2017
BCOPL Page 6
Relevant approval
Ref. Condition description Compliance status*
Comment BCOPL response Where addressed in the Annual Review
and riparian vegetation…
Sch3, C49(e)(v)
The Proponent shall prepare and implement a Biodiversity Management Plan for the project to the satisfaction of the Secretary. This plan must: …(e) include a detailed description of the measures that would be implemented including the procedures to be implemented for: …(v) minimising the impacts on fauna on site, including undertaking pre-clearance surveys;…
Non-compliance (low risk)
According to BCOPL’s tree clearing procedure, which is an appendix to the BMP, vegetation clearing is to cease if ambient temperatures exceed 35oC. On 18 February 2017, BCOPL continued clearing vegetation for a period of approximately 10 minutes after temperatures had exceeded 35oC. The failure to cease clearing activities was attributed to BCOPL’s third-party-provided automatic SMS temperature alert system failing and BCOPL’s clearing supervisor subsequently not being advised that temperatures had exceeded 35oC. BCOPL received an Official Caution from DPE for the incident. DPE asserted that the clearing activities during temperatures in excess of 35oC contravened Schedule 3, Condition 49 as BCOPL had failed to implement the BMP.
BCOPL has installed a secondary temperature monitoring unit as a back-up system should the primary automated SMS temperature alert system fail. Temperature SMS updates are also now issued to relevant personnel every 15 minutes during tree clearing activities. These actions were completed in 2017.
Section 5
Sch3, C57(c)
The Proponent shall prepare and implement an Archaeological Salvage Program that must: (c) incorporate methodology including:
sub-surface testing;
staged salvage, based on anticipated mine planning;
pre-disturbance monitoring;
site assessment and reporting protocols;
Non-compliance (low risk)
The non-compliance was identified during the Independent Environmental Audit. The auditor made a number of comments regarding content that they believed should be included within the CHMP. They asserted that the absence of this content constituted a non-compliance with this condition. The auditor made six recommendations for improvements. Further details regarding the auditors comments and recommendations are
BCOPL has committed to implement five of the six recommendations. The sixth recommendation was to include within the CHMP, an outline of the progress made toward the establishment of a long-term Keeping Place in consultation with registered Aboriginal parties. BCOPL has
Section 5 and Appendix C
Annual Review 2017
BCOPL Page 7
Relevant approval
Ref. Condition description Compliance status*
Comment BCOPL response Where addressed in the Annual Review
research objectives to inform knowledge of Aboriginal occupation;
protection, storage and management of salvaged Aboriginal objects;
addressing relevant statutory requirements under the National Parks and Wildlife Act 1974; and
proposed long-term plan for protection of salvaged
Aboriginal objects.
contained in the Audit Action Plan contained in Appendix C.
elected to keep such records on site EMS rather than including them in the CHMP. This is due to the document requiring continual review at each update and the fact that it would not improve the management system in any way. Further details are contained in the Audit Action Plan in Appendix C.
Sch5, C13
The Proponent shall ensure that the noise and air quality risk/response matrices required to be developed in the Noise and Air Quality Management Plans and validated real time monitoring data are available online and includes: (a) timely publication of validated monitoring data in a clearly understandable form; (b) identification of mine operational responses to monitoring data and weather forecasts;
Non-compliance (low risk)
The non-compliance was identified during the Independent Environmental Audit. The auditor’s comments were:
1. Evidence sighted of real-time air quality monitoring - PM10. No evidence of real-time noise monitoring available online.
2. No evidence online of mine responses.
The auditor’s recommendations were: 1. Ensure real-time noise monitoring
is available on the website as real-time air is available.
2. Additional information should be provided in the AEMR regarding real time noise and air monitoring including responses to triggers.
BCOPL provided the following responses to the auditor’s recommendations: 1. The condition does
not require the real-time noise monitoring data to be available online in real-time. It requires validated real-time monitoring data to be available online. Validated real-time monitoring data is currently available online. No action is proposed.
2. All previous AEMRs/Annual Reviews have been prepared to the satisfaction of DPE. BCOPL will continue to prepare AEMRs/Annual Reviews in
Section 5
Annual Review 2017
BCOPL Page 8
Relevant approval
Ref. Condition description Compliance status*
Comment BCOPL response Where addressed in the Annual Review
accordance with the Annual Review Guideline (DPE, 2015) and to the satisfaction of DPE. No action is proposed.
EPL 12407 P 1.3 Surface water monitoring & groundwater monitoring
Non-compliance (low risk)
A monitoring point was not monitored in all instances due to accessibility restrictions
BCOPL is seeking a variation to the EPL to remove redundant or unsafe monitoring locations.
Section 5
Monitoring points were not monitored in all instances as some have been mined through, collapsed or are inaccessible
BCOPL is seeking a variation to the EPL to remove redundant or unsafe monitoring locations.
Section 5
M 2.3 Surface water monitoring & groundwater monitoring
Non-compliance (low risk)
A monitoring point was not monitored in all instances due to accessibility restrictions
BCOPL is seeking a variation to the EPL to remove redundant or unsafe monitoring locations.
Section 5
Monitoring points were not monitored in all instances as some have been mined through, collapsed or are inaccessible
BCOPL is seeking a variation to the EPL to remove redundant or unsafe monitoring locations.
Section 5
*non-compliances listed in the table relate to those deemed to have occurred during the reporting period. Refer to Appendix C for a complete list of non-compliances identified
during the Independent Environmental Audit, which covered the period from July 2014 to July 2017.
Annual Review 2017
BCOPL Page 9
2. INTRODUCTION
2.1 Mine Contacts
Table 2-1 BCM Mine Contacts
General Manager Operations:
Company:
Address:
Phone:
Fax:
Ray Balks
Boggabri Coal Operations Pty Limited
386 Leard Forest Rd, Boggabri, NSW, 2382
02 6749 6013
02 6743 4496
Health Safety and Environment Manager:
Company:
Address:
Phone:
Fax:
Peter Forbes
Boggabri Coal Operations Pty Limited
386 Leard Forest Rd, Boggabri, NSW, 2382
02 6749 6038
02 6743 4496
Environmental Superintendent:
Company:
Address:
Phone:
Fax:
Daniel Martin
Boggabri Coal Operations Pty Limited
386 Leard Forest Rd, Boggabri, NSW, 2382
02 6749 6013
02 6743 4496
2.2 Approvals, Licences and Mining Leases
Table 2-2 summarises the key mining leases and approvals currently held by BCOPL which are relevant
to the operations at BCM.
Table 2-2 Key Approvals, Consents, Mining Leases and Licences
Description Date granted/ commencement date
Expiry/duration
Project Approvals
Project Approval 09_0182 18 July 2012 31 December 2033
09_0182 Mod 2 17 February 2015 31 December 2033
09_0182 Mod 3 17 March 2014 31 December 2033
09_0182 Mod 4 23 March 2015 31 December 2033
09_0182 Mod 5 30 August 2016 31 December 2033
09_0182 Mod 6 7 July 2017 31 December 2033
EPBC Act Approval 11 February 2013 31 December 2053
Coal Leases
Coal Lease CL 368 15 November 1990 14 November 2032
Annual Review 2017
BCOPL Page 10
Description Date granted/ commencement date
Expiry/duration
Mining Leases / Authorisations
Authorisation A 355 19 July 1984 11 April 2018
Authorisation A 339 11 April 1984 11 April 2022
Mining Lease ML 1755 30 June 2017 30 June 2038
Environmental Protection Licences
EPL 12407 11 January 2006 In perpetuity (Anniversary 11 January) until surrendered
EPL 20404 19 May 2014 In perpetuity (Anniversary 19 May) until surrendered
Water Licences
WAL 12691 27 July 2012 In perpetuity
WAL12767 8 April 2014 In perpetuity
WAL14483 27 July 2012 In perpetuity
WAL15037 12 December 2013 In perpetuity
WAL24103 1 September 2011 In perpetuity
WAL29473 26 July 2012 In perpetuity
WAL29562 26 July 2012 In perpetuity
WAL2571 12 December 2013 In perpetuity
WAL2572 25 December 2013 In perpetuity
WAL2595 12 December 2013 In perpetuity
WAL2596 25 September 2013 In perpetuity
WAL31084 22 August 2013 In perpetuity
WAL14495 3 February 2014 In perpetuity
WAL36547 6 February 2014 In perpetuity
WAL31096 25 November 2014 In perpetuity
90FW833717 21 September 2015 4 April 2020
90FW834023 21 September 2015 4 June 2020
90FW834016 21 September 2015 28 October 2018
Mining Operations Plans
Current MOP 19 December 2017 31 December 2021
Radiation Licences
Licence No. 5083602 14 June 2017 14 June 2018
Annual Review 2017
BCOPL Page 11
Description Date granted/ commencement date
Expiry/duration
Council Approvals
CC 04-04-2012 Mod1 22 October 2012 In perpetuity
CC 02-03-2012 6 June 2012 In perpetuity
CC 10-01-2012 Mod1 1 June 2012 In perpetuity
OC 09-10-2013 19 November 2013 In perpetuity
OC 02-04-2013 9 April 2013 In perpetuity
OC 01-03-2013 28 March 2013 In perpetuity
C6 – Approval to Operate a System of Sewage Management
20 February 2012 13 May 2024
Part 5 Determination –Goonbri Road Upgrade 28 March 2014 In perpetuity
Forestry Corporation Permits
Authorisation to Undertake Environmental Monitoring Activities
15 February 2016 30 June 2017
Forestry Compensation Agreement 23 January 2006 14 November 2032
Crown Lands Licences
RI 507102 12 November 2012 14 November 2032
RI 533986 5 June 2014 14 November 2032
2.3 Mine Operation Introduction and History
Boggabri Coal Mine (BCM) is an open cut coal mine located 15 km north-east of the township of Boggabri
in north-western New South Wales (NSW). BCM is managed by Boggabri Coal Operations Pty Ltd
(BCOPL) which is majority owned by Idemitsu Australia Resources Group (IAR), a subsidiary of
Japanese company Idemitsu Kosan Pty Ltd.
Environmental assessments first commenced at BCM in 1976 followed by grant of approval for the project
in 1989, and the commencement of operations in 2006. Truck and excavator operations produce a
crushed and screened export quality thermal coal and pulverised coal injection product, which is
transported from the mine via rail to the Port of Newcastle, for export to overseas markets. In the 2017
calendar year BCM produced 6.9 million tonnes (Mt) of product coal.
In 2009, BCOPL lodged a major project application under the now-repealed Part 3A of the Environmental
Planning and Assessment Act 1979 (EP&A Act). This project approval (Project Approval 09_0182) (PA),
was granted by the NSW Planning Assessment Commission (PAC) in June 2012, allowing for extraction
of up to 8.6 Mtpa of run of mine (ROM) coal from BCM until the end of year 2033 (the Project).
Under the PA, a new rail load-out facility and rail spur was constructed. Operation of this infrastructure
commenced in December 2014. This has eliminated routine road transport of product coal between the
mine infrastructure area (MIA) and the Boggabri Coal Terminal (BCT). All product coal is currently
transported from site via rail. A new Coal Handling and Preparation Plant (CHPP) was commissioned in
mid-2015, enabling further processing of ROM coal required for the mine to reach the full production rate.
Annual Review 2017
BCOPL Page 12
The PA also provides for the upgrade of the overburden and coal haulage fleet and other ancillary
infrastructure, as well as the option of a dragline.
Six modifications to the PA have been lodged since granting of the original PA. One of these
modifications (Mod 1) was subsequently withdrawn. The latest modification (Mod 6) was lodged for
assessment under the EP&A Act in June 2017 and approved in July 2017. The modification involved a
minor administrative amendment to Schedule 2, Condition 12 of the PA to address the underutilisation of
the Boggabri Rail Spur Line. The modification made provision for BCOPL to transport up to 10 million
tonnes of product coal via the Boggabri Rail Spur Line in any calendar year. The modification did not
relate to any corresponding change in the approved maximum rate of production for the BCM, which
remained at 8.6 Mtpa ROM.
In NSW, mining operations and certain mining purposes must be carried out in accordance with a Mining
Operations Plan (MOP) that has been approved by the NSW Department of Planning and Environment –
Division of Resources and Energy (DRE). This obligation derives from a condition of authorisation issued
under the Mining Act 1992. BCOPL is currently operating under an approved MOP that applies to
activities at the BCM between 2015 and 2019. The latest amendment to the MOP (Amendment C) was
approved in February 2017.
2.4 Purpose and Scope of Report
This Annual Review discusses the environmental performance of BCOPL and its contractors, in relation
to compliance with the conditions of the PA, and other relevant leases, licences and approvals. It provides
a summary of actual operational and environmental management activities undertaken at the BCM during
the reporting period (1 January to 31 December 2017) and provides a review against planned works, as
described in the MOP, and predicted impacts documented in the Continuation of Boggabri Coal Mine
Environmental Assessment (EA) (Hansen Bailey, 2010). The Annual Review also covers community
relations and addresses mine development and rehabilitation undertaken during the reporting period.
The Annual Review has been prepared to satisfy the conditions of the PA (in particular Condition 4 of
Schedule 5) and CL 368. Key requirements of these approvals are described in Table 2-3. A map
illustrating the mine locality and project boundary is provided in Figure 2-1 while relevant monitoring
points and land ownership are shown in Appendix A. Offset properties for BCM are identified on the
figures provided in Appendix B.
This document has been prepared generally in accordance with the Post-approval requirements for State
significant mining developments – Annual Review Guideline (NSW Government, 2015), where
practicable, as well as the relevant BCOPL reporting framework.
http://www.planning.nsw.gov.au/~/media/3AA21D35168042FE813DD0FB92E00E58.ashxhttp://www.planning.nsw.gov.au/~/media/3AA21D35168042FE813DD0FB92E00E58.ashx
Annual Review 2017
BCOPL Page 13
Table 2-3 Annual Review requirements
Licence, Approval or Guideline
Section Reference
Requirement Reference in this report
CL 368 Condition 4 (a) The lease holder must lodge Environmental Management Reports (EMR) with the Director-General annually or at dates otherwise directed by the Director-General.
(b) The EMR must:
i. Report against compliance with the MOP
ii. Report on progress in respect of rehabilitation completion criteria
iii. Report on the extent of compliance with regulatory requirements; and
iv. Have regard to any relevant guidelines adopted by the Director-General
Whole document
Project Approval 09_0182
Schedule 5, Condition 4
Annual Review
By the end of March each year, the Proponent shall review the environmental performance of the project for the previous calendar year to the satisfaction of the Secretary. This review must:
(a) describe the development (including any rehabilitation) that was carried out in the past calendar year, and the development that is proposed to be carried out over the current calendar year;
Section 8
(b) include a comprehensive review of the monitoring results and complaints records of the project over the past year, which includes a comparison of these results against the:
relevant statutory requirements, limits or performance measures / criteria;
monitoring results of previous years; and
relevant predictions in the EA
Section 4, Section 7.3
(c) identify any non-compliance over the last year, and describe what actions were (or are being) taken to ensure compliance;
Section 4, Section 4.15.2.1
(d) identify any trends in the monitoring data over the life of the project;
Section 4
(e) identify any discrepancies between the predicted and actual impacts of the project, and analyse the potential cause of any significant discrepancies; and
Section 4
(f) describe what measures will be implemented over the next year to improve the environmental performance of the project.
Section 9
Schedule 3, Condition 10
The Proponent shall:
(a) conduct an annual testing program of the attenuated plant on site to ensure that the attenuation remains effective;
(b) restore the effectiveness of any attenuation if it is found to be defective; and
(c) report on the results of any testing and/or attenuation work within the Annual Review.
Section 4.3.2.2
Annual Review 2017
BCOPL Page 14
Licence, Approval or Guideline
Section Reference
Requirement Reference in this report
Schedule 3, Condition
12
The proponent shall …
(i) use its best endeavours to achieve the long term intrusive noise goals for the project in Table 5, where this is reasonable and feasible, and report on the progress towards achieving these
goals in the annual review; and
Section 0
Schedule 3, Condition
68
The Proponent shall:
(a) implement all reasonable and feasible measures to minimise the waste (including coal reject) generated by the project;
(b) ensure that the waste generated by the project is appropriately stored, handled and disposed of;
(c) monitor and report on the effectiveness of the waste minimisation and management measures in the Annual Review.
Section 4.9
Schedule 3, Condition 77
The proponent shall prepare and implement a Social Impact Management Plan (which will)…
(h) include a monitoring program, incorporating key performance indicators and a review and reporting protocol, including
reporting in the annual review.
Section 7
Boggabri Coal Project EA
Section 8 BCOPL will prepare an Annual Review (which summarises monitoring results and reviews performance) and distribute it to the relevant regulatory authorities and the Boggabri CCC.
Whole document
2.5 Actions from 2016 Annual Review
The 2016 Annual Review (previously termed Annual Environmental Management Report (AEMR)) was
provided to DRE, NSW Department of Primary Industries (DPI) – Agriculture, NSW Environment
Protection Authority (EPA) and Department of Planning and Environment (DPE) in March 2017.
BCOPL received confirmation on 5 May 2017 that the 2016 AEMR generally satisfied DPE’s Annual
Review requirements. No written feedback was received from any other regulatory agencies.
A total of five comments were received from DPE regarding actions to be addressed in the 2017 Annual
Review. These comments and a reference to where each one is addressed in this document are
presented in Table 2-4.
Table 2-4 Issues from 2016 AEMR to be addressed in 2017 Annual Review
Action required from previous AEMR Action taken by the Operator Section Addressed
a) Section 2 Introduction – please
include the operational disturbance
footprint, mining lease boundaries
and offset areas on Figure 2-1
Figure 2-1 has been updated to include the elements requested by DPE.
Figure 2-1
Annual Review 2017
BCOPL Page 15
Action required from previous AEMR Action taken by the Operator Section Addressed
b) Section 2.5 Actions Required from
previous AR review – please include
comments from other regulatory
agencies. If no feedback provided,
please state in this section
Section 2.5 has been updated to state that no feedback on the 2016 Annual Review was received from any other agencies.
Section 2.5
c) Section 4.3 – Operational Noise –
please provide details of the joint rail
noise assessment and evidence of
compliance with Schedule 3
Condition 11
Details of the joint rail noise assessment and evidence of compliance with Schedule 3, Condition 11 has been provided in Section 4.3.2.4.
Section 4.3.2.4
d) Section 5 Incidents and Non-
Compliance – please include a
summary of any warning letters,
official cautions, penalty notices or
prosecution proceedings by any
regulatory agency, and a summary
of the operator’s response to any
official cautions or warning letters,
penalty notices or prosecution
proceedings, as per Section 11 of
the Annual Review Guideline
(October 2015).
A summary of any warning letters, official cautions, penalty notices or prosecution proceedings by any regulatory agency, and a summary of BCOPL’s responses has been provided in Section 5.
Section 5
e) Section 9 Activities proposed for
next reporting period – please
include a timeline for implementation
of measures to be completed in the
next reporting period, as per Section
12 of the Annual Review Guideline
(October 2015)
A timeline for implementation of measures to be completed in the next reporting period has been provided in Section 9.
Section 9
Projection: Transverse MercatorCoordinate System: GDA 1994 MGA Zone 56
© WSP Australia Pty Ltd ("WSP") Copyright in the drawings, information and data recorded ("the information") is the property of WSP. This document and the information are solely for the use of the authorised recipient and this document may not be used, copied or reproduced in whole or part for any purpose other than that which it was supplied by WSP. WSP makes no representation, undertakes no duty and accepts no responsibility to any third party who may use or rely upon this document or the information.NCSI Certified Quality System to ISO 9001. © APPROVED FOR AND ON BEHALF OF WSP Australia Pty LtdIdemitsu Australia Resources Pty Ltd DRAWING. \\APNTLFPS01\proj\B\Boggabri_Coal\2171706A_Boggabri_Coal_GIS_services\10_GIS\Projects\_Drawings_Figures_Sketches\Environment\AEMR\2267037B_GIS_AEMR002_A1.mxd
!
!!
!!
!!
!
! !! ! !
!
!!
!!
!
!!
!
!
!
! !
! !
!!
!!
!
!!
!!
!!
!
!!!
!
!
!
!
!
!!
!!
!!
!
!!
!
!
AUTH339AUTH355
ML1755
CL368
MyallPlainsMerriendi
Mallee
Braefield
Jerralong
NiokaNorth
Sunshine
Namoi
Wirrilah
Goonbri
Legend
!
! !
! Mine tenementBoggabri Coal MineProject Approval AreaOperational disturbance footprintBiodiversity offset area
Scale correct when printed at A3 Landscape
0 3 6 kmµScale 1:200,000
DOCUMENT 2267037B_GIS_AEMR002_A1
DATE. 2/03/2018EDITED BY. MitchellEm
2-1FIGURETITLE. LOCALITY PLAN
AUTHOR. suansrirImagery:Sources: Esri, HERE, DeLorme, Intermap, increment P Corp., GEBCO, USGS, FAO, NPS,
Annual Review 2017
BCOPL Page 17
3. SUMMARY OF OPERATIONS
3.1 Mining Preparation
Vegetation is cleared in advance of mining activities in accordance with the following documents:
Clearing and Fauna Management Protocol, which forms Appendix B of the approved Biodiversity
Management Plan (BMP)
Cultural Heritage Management Plan (CHMP).
The adopted clearing protocol follows a two-stage clearing process to minimise impacts on native
biodiversity. Prior to removal of vegetation, trained ecologists survey the areas proposed for clearing
(refer to Section 4.7.2.2). Archaeological salvage is also undertaken as part of the clearing process to
identify and potentially recover artefacts (refer to Section 4.11.2.1).
Sampling is undertaken prior to stripping of topsoils and subsoils to identify the soil resource, inform the
preparation of a soil inventory to assist with rehabilitation planning, and to determine soil amelioration
requirements.
Topsoil is then stripped in accordance with the approved Soil Management Protocol (SMP) and BMP, and
where possible, hauled directly to re-profiled rehabilitation areas. Where re-profiled areas are not ready to
receive topsoil, the topsoil is hauled to a temporary stockpile location where it is stored for future transport
to rehabilitation locations.
126,540 m3 of topsoil recovery was undertaken during the 2017 reporting period. Of this, 37,310 m3 was
spread over a 42 ha rehabilitation area in readiness for revegetation. At the end of December 2017, there
was a total of 1,812,900 m3 of topsoil material stockpiled across the BCM.
Saline or Potentially Acid Forming Materials
Most of the strata are devoid of acid producing pyrite. A small proportion of the potential coal reject
materials located near the Braymont Seam have a relatively high total sulphur content and negligible
buffering capacity and are classified as Potentially Acid Forming – High Capacity (PAF). However, most
overburden materials are likely to be non-acid forming and have a high factor of safety with respect to
potential acid generation. The overburden is therefore regarded as a non-acid forming unit.
Based on these outcomes, the risk of acid mine drainage at BCM is considered low. During the reporting
period, BCOPL implemented an established process to manage PAF materials. The process involves
annual sampling of reject material to identify any material that could be classified as PAF. If, following
completion of sampling, material is identified as PAF, it is subject to deep in-pit burial. Sampling and
analysis undertaken during the reporting period did not identify any PAF material.
No PAF material has been identified at the BCM to date.
3.2 Mining Operations
Equipment
Truck and excavator operations will continue to be undertaken as approved through the MOP term (2017-2021). The mining equipment fleet as at December 2017 is listed in Table 3-1.
Annual Review 2017
BCOPL Page 18
Table 3-1 Equipment fleet as at December 2017
Equipment Number in fleet
Haul trucks 45
Excavators 10
Front end loaders 7
Dozers 13
Graders 4
Water carts 8
Service trucks 4
Drills 5
Total 96
Activities
A summary of mining activities undertaken at BCM during the reporting period is as follows:
Drilling and blasting of overburden
Overburden removal by large hydraulic excavators, front-end loaders, shovels and dozers
Haulage of waste to in-pit and out-of-pit emplacement areas
Extraction of coal using large hydraulic excavators, front-end loaders, dozers and various Komatsu,
Caterpillar and Hitachi rear dump trucks
Movement of coal directly to a bypass crusher as product coal or stockpiled on ROM pads for further
blending and crushing
Coal Processing through the CHPP.
Mining activities were compliant with the requirements of the PA including not clearing within 250 m of
Maules Creek Mine mining lease boundary.
Pit Progression
Coal is mined from eight coal seams including the Herndale, Onavale, Teston, Thornfield, Braymont,
Bollol Creek, Jeralong and basal Merriown seams.
During the reporting period, pit development progressed in two directions. These were to the north-west
and the east (refer to Figure 8-1).
Production Waste
Waste emplacement areas have been created through the clearing of designated out-of-pit areas and by
in–pit emplacement in mined-out sections of the mine. The main emplacement areas are immediately to
the west and south of the active mining area (refer to Figure 8-1).
During the reporting period, out-of-pit dumping continued on the western overburden emplacement area
in accordance with the MOP, to a maximum RL of 395 m. The pit void was also progressively backfilled
with overburden.
Annual Review 2017
BCOPL Page 19
3.3 Production Statistics
From January to November 2017, mine production at BCM was carried out by mining contractor Downer Mining. From December onwards, mine production was carried out by Boggabri Coal Operations and
BGC Contracting. Mining was undertaken in accordance with the approved MOP and site work standards
and procedures, which have been developed to ensure ongoing compliance with the approved
management plans and MOP.
A summary of production figures for the 2016 and 2017 calendar years is provided in Table 3-2 below.
Also shown are the predicted production figures for the 2018 calendar year.
Table 3-2 Production and Waste Rock Summary
Material Project
Approval Limit
Reporting Period (Calendar Year)
2016 (actual) 2017 (actual) 2018 (predicted)
Waste Rock / Overburden (Mbcm3)
N/A 50.0 52.0 54.1
ROM Coal (Mt) 8.6 7.8 8.0 8.0
Reject Material (Mt) N/A 1.5 1.5 1.3
Stripped Topsoil (kbcm3)
N/A 208.3 126.5 144.2
Saleable Product (Mt)
8.6 (by rail) 6.9 6.9 7.1
Mining operations within the 2017 calendar year remained below the limits specified in the PA. Specific
conditions from Schedule 2 of the PA are presented in Table 3-3 with responses on the compliance of
each also provided.
Table 3-3 Compliance with Project Approval Conditions
Project Approval Condition No. and Description Compliance Response
8. The Proponent shall not extract more than 3.5 million tonnes of ROM coalfrom the site in any calendar year (on a pro rata monthly basis) while ever coalis being transported along the private haul road to the coal loader, unless aroad safety audit at the intersections of Leard Forest Road and Therribri Roadhas been completed in consultation with Council and RMS, and anyrecommended actions implemented to the satisfaction of the Secretary.
Compliant – coal was transported via the rail spur during 2017
9. The Proponent shall not extract more than 4.5 million tonnes of ROM coalfrom the site in any calendar year (on a pro rata monthly basis) or undertakemining operations outside the disturbance area approved under DA36/88MOD 2, unless the Biodiversity Management Plan required under condition 49of Schedule 3 has been approved by the Secretary.
Compliant –The BMP has been approved.
10. The Proponent shall not extract more than 8.6 million tonnes of ROM coalfrom the site in any calendar year.
Compliant – 8.0 Mt of ROM Coal was extracted in 2017
11. The Proponent may process up to 4.2 million tonnes of ROM coal in theCHPP in any calendar year.
Compliant – 4.0 Mt of ROM coal was processed in the Coal Processing Plant during 2017
Annual Review 2017
BCOPL Page 20
Project Approval Condition No. and Description Compliance Response
11A. The Proponent shall not process any coal from the Tarrawonga coal mine unless it has demonstrated that adequate water license are held to account for the required water use associated with processing this coal, to the satisfaction of the Secretary.
Compliant – no coal was processed for Tarrawonga Coal
Mine in 2017
12. The Proponent may transport up to 10 million tonnes of product coal viathe Boggabri Rail Spur Line in any calendar year; comprising:
(a) 8.6 million tonnes of product coal from the Boggabri coal mine in anycalendar year; and
(b) 3 million tonnes of product coal from the Tarrawonga coal mine in anycalendar year.
Compliant – 6.9 Mt of product coal from the Boggabri coal mine was transported in 2017. No coal from the Tarrawonga coal mine was transported in 2017.
13. The Proponent may only transport coal from the site by road for 22 monthsfollowing the date of this approval, or for such additional period as may resultfrom delays in construction of the Boggabri Rail Spur Line as agreed by theSecretary. Following expiry of this period, all coal is to be transported from thesite via the Boggabri Rail Spur Line unless in exceptional circumstances asagreed with RMS, the Council and approved by the Secretary.
Compliant – transport of coal by road was ceased following completion of the Boggabri Rail Spur Line. The Boggabri Rail Spur Line was operational throughout 2017.
3.4 Exploration
Exploration drilling was undertaken in 2017 by BCOPL, for the purpose of determining coal quality and
structure for modelling through the installation of infill drill holes.
A total of 47 exploration holes were drilled by BCOPL during the reporting period, as detailed in
Table 3-4. All holes were completed for the purpose of structure and coal quality testing and greenhouse
gas emission estimates. Figure 3-1 indicates the location of the boreholes drilled during the 2017
calendar year.
Nineteen boreholes have been sealed and the balance have been left open to be used for geophysical
testing in advance of mining.
Table 3-4 BCM Exploration Drilling
Hole MGA
Easting
MGA
Northing
RL (m) Total
Depth (m)
Drill
Start
Drill
Finish
Purpose
BC2288 229849.81 6610961.97 351.78 175 5/06/2017 6/06/2017 Structure
BC2289 229777.95 6611754.51 358.6 211 7/06/2017 8/06/2017 Structure
BC2290 229768.33 6611709.51 353.46 205 8/06/2017 9/06/2017 Structure
BC2291 228825.44 6612394.15 338.69 169 9/06/2017 10/06/2017 Structure
BC2292 228630.42 6612290.52 330.91 163 10/06/2017 11/06/2017 Structure
BC2293 228502.95 6612196.93 326.44 151 11/06/2017 11/06/2017 Structure
BC2294 228329.31 6612108.5 325.49 151 11/06/2017 12/06/2017 Structure
BC2295 228575.67 6612064.77 324.1 140 12/06/2017 13/06/2017 Structure
BC2296 228620.76 6612199.26 329.15 151 12/06/2017 13/06/2017 Structure
BC2297 229645.68 6611732.12 354.24 205 20/06/2017 20/06/2017 Structure
BC2298 229690.87 6611713.69 350.7 199 21/06/2017 21/06/2017 Structure
BC2299 229746.7 6610865.67 341.62 163 22/06/2017 22/06/2017 Structure
BC2300 229905.32 6610892.74 349.2 169 22/06/2017 23/06/2017 Structure
Annual Review 2017
BCOPL Page 21
Hole MGA
Easting
MGA
Northing
RL (m) Total
Depth (m)
Drill
Start
Drill
Finish
Purpose
BC2301 229650.46 6611779.08 360.73 217 23/06/2017 24/06/2017 Structure
BC2302 228757.47 6612161.9 339.79 163 25/06/2017 25/06/2017 Structure
BC2303 229058.27 6612228.41 364.55 187 26/06/2017 27/06/2017 Structure
BC2304 228963.16 6612397.57 344.16 169 27/06/2017 4/07/2017 Structure
BC2305 229219.3 6612313.58 367.93 199 4/07/2017 5/07/2017 Structure
BC2306 229133.89 6612481.77 352.99 181 5/07/2017 6/07/2017 Structure
BC2307 229096.4 6612358.89 352.75 181 6/07/2017 7/07/2017 Structure
BC2308 228891.22 6612129.78 345.11 163 7/07/2017 7/07/2017 Structure
BC2309 228929.95 6612264.88 345.74 169 8/07/2017 8/07/2017 Structure
BC2310 228719.3 6612023.77 328.18 148 9/07/2017 9/07/2017 Structure
BC2311 228793.89 6612296.24 337.07 163 10/07/2017 10/07/2017 Structure
BC2312 226092.27 6611910.63 340.57 256 11/07/2017 12/07/2017 Coal Quality
BC2313 229749.3 6610962.1 344.71 165.22 21/07/2017 26/07/2017 Coal Quality
BC2314 229751.9 6611361.15 343.15 183.1 27/07/2017 5/08/2017 Coal Quality
BC2315 229759.16 6611663.03 353.91 201.1 5/08/2017 10/08/2017 Coal Quality
BC2316 226447.12 6611408.11 318.66 132.16 10/08/2017 19/08/2017 Gas
BC2317 228630.47 6611978.06 322.48 135.16 20/08/2017 24/08/2017 Coal Quality
BC2318 228073 6611968.37 315.39 171.42 25/08/2017 27/08/2017 Gas
BC2319 229847.19 6610859.98 344.21 162.11 6/09/2017 11/09/2017 Coal Quality
BC2320 228781.94 6612375.29 336.62 246 3/08/2017 6/08/2017 Coal Quality
BC2321 227091.49 6611286.92 306.78 337 16/08/2017 18/08/2017 Coal Quality
BC2322 227721.43 6611768.78 310.49 313 14/07/2017 11/08/2017 Coal Quality
BC2323 229833.2 6611070.53 355.78 183.11 11/09/2017 22/09/2017 Coal Quality
BC2324 229749.6 6611160.99 344.33 171.16 23/09/2017 2/10/2017 Coal Quality
BC2325 229766.8 6611542.59 347.89 195.01 3/10/2017 8/10/2017 Coal Quality
BC2326 228232.23 6611932.98 317.89 129.12 9/10/2017 17/10/2017 Coal Quality
BC2327 228803 6612074 337.1 153.28 17/10/2017 23/10/2017 Coal Quality
BC2328 228100.68 6611847.86 312.91 112.67 24/10/2017 26/10/2017 Coal Quality
BC2329 227936.52 6611891.72 313.72 114.06 1/11/2017 3/11/2017 Coal Quality
BC2330 229851.2 6611261.12 351.7 180.33 4/11/2017 9/11/2017 Coal Quality
BC2331 229853.41 6611461.3 352.64 192.11 9/11/2017 24/11/2017 Coal Quality
BC2332 229155.48 6612269.5 367.02 189.16 26/11/2017 29/11/2017 Coal Quality
BC2333 228406.88 6612158.81 326.39 155.93 5/12/2017 9/12/2017 Coal Quality
BC2334 228973.53 6612182.01 351.57 168.17 9/12/2017 15/12/2017 Coal Quality
Annual Review 2017
BCOPL Page 22
Figure 3-1 Extent of 2017 Exploration Drilling
Annual Review 2017
BCOPL Page 23
3.5 Construction Activities during 2017
A summary of construction activities undertaken during the reporting period and their completion status is
provided in Table 3-5.
Table 3-5 Summary of Construction Activities during the Reporting Period
Infrastructure Commencement Date Completion Date
Mine Infrastructure Area (MIA)
Eight drive-in concrete sumps January 2017 September 2017
New main administration building and changes to location of CHPP offices
September 2017 December 2017
Access road from Train Load Out (TLO) to carpark
October 2017 January 2018
Other
New ROM Haul Road January 2016 March 2017
Internal Water Reticulation Upgrade July 2016 Ongoing
ROM 6 (in-pit ROM) October 2016 February 2017
Access Road 2 rectification works January 2017 March 2017
Modifications to the rejects loop within the MIA
January 2017 July 2017
Installation of two productions bores and ancillary infrastructure (power lines, access tracks and water transfer pipelines)
January 2017 December 2017
Spur Line Rectification Works January 2016 June 2017
New rail crossing infrastructure on mine access road from Kamilaroi Highway
March 2017 November 2017
3.6 Construction Activities Proposed for 2018
Activities during the 2018 reporting period will involve construction of a new 2 GL capacity mine water
dam (MW5) and the extension of the awning over the tyre bay in the maintenance area.
Annual Review 2017
BCOPL Page 24
4. ENVIRONMENTAL MANAGEMENT AND PERFORMANCE
The Environment Management Strategy (EMS) provides the strategic framework for environmental
management at BCM. The EMS:
Outlines all relevant statutory leases, licences and approvals that apply to BCM
Details key plans, procedures, management plans and other documents that will be implemented to
ensure compliance with all relevant leases, licences and approvals
Describes the key processes that will be implemented to:
o Communicate with community and government stakeholders
o Manage community complaints
o Resolve disputes
o Respond to non-compliance incidents and emergencies
Outlines BCM’s monitoring, reporting and auditing requirements
Outlines relevant roles, responsibilities and accountabilities relevant to environment management for
all BCOPL employees and contractors.
A suite of environmental management plans (EMPs) have been developed to guide environmental
management at BCM. They have been developed in accordance with the EMS, the PA and other
statutory requirements. The revision status of approved key EMPs, as required by the PA, is summarised
in Table 4-1.
Table 4-1 Key EMPs
Management Plan Status
BMP Rev 9 October 2015 – revised currently awaiting approval
Blast Management Plan (BLMP) Rev 1 June 2013 - revised currently awaiting approval
Air Quality and Greenhouse Gas Management Plan (AQGHGMP)
Rev 3 January 2015 – revised currently awaiting approval
Traffic Management Plan (TMP) Rev 3 October 2013 – revised currently awaiting approval
Cultural Heritage Management Plan (CHMP) Revision 7 Approved February 2017
Environment Management Strategy Rev Original November 2012 – revised currently awaiting approval
Noise Management Plan (NMP) Rev 9 Approved March 2016 – revised currently awaiting approval
Water Management Plan (WMP)
Surface Water Management Plan (SWMP)
Groundwater Management Plan (GWMP)
Site Water Balance (SWB)
Rev 6 May 2017
Social Impact Management Plan (SIMP) Rev 4 November 2013 – revised currently awaiting approval
Rehabilitation Management Plan (RMP) Incorporated into the 2017-21 Mining Operations Plan (MOP) for the project, at the request of the Department. The MOP was approved 19 December 2017.
Annual Review 2017
BCOPL Page 25
Management Plan Status
Pollution Incident Response Management Plan (PIRMP)
Rev R - revised February 2017
The PIRMP listed in Table 4-1 applies to all activities that have the potential to generate pollution
incidents at BCM. These include, but are not limited to, water discharge events, hazardous spills resulting
in land or water pollution, and fire hazards.
The PIRMP provides an overarching procedure to respond to pollution incidents at BCM including:
outlining the response and notification requirements in the event of a pollution incident at BCM
providing clear definition of the roles and responsibilities for pollution incident responses at BCM
facilitating compliance with the requirements of the POEO Act and associated regulations
4.1 Meteorology
Environmental Management
The PA (Schedule 3, Condition 32) requires a permanent meteorological station to be installed and
maintained for the life of the BCM. The station must comply with the requirements of the Approved
Methods for Sampling of Air Pollutants in New South Wales Guideline and be capable of determining the
temperature lapse rate.
As such, a meteorological monitoring station (MET) has been established to continuously measure and
record wind speed, wind direction, temperature, solar radiation and rainfall at BCM. The location of the
BCM MET station is shown on the Environmental Monitoring Location Plan in Appendix A.
The MET station provides real-time data to BCOPL employees and contractors. Meteorological data is
used for assessing compliance, proactive dust and noise management, and for investigative and
reporting requirements.
The parameters recorded by the BCM MET monitoring station and the method are outlined in Table 4-2.
Table 4-2 MET Monitoring Parameters
Parameter Units Frequency Averaging period
Temperature at 2m ºC Continuous 15 minute
Temperature at 10m ºC Continuous 15 minute
Wind direction at 10m º Continuous 15 minute
Sigma theta at 10m º Continuous 15 minute
Rainfall mm/hr. Continuous 1 hour
Solar radiation W/m2 Continuous 15 minute
Additional requirements: – Siting & Measurement
n/a n/a n/a
Annual Review 2017
BCOPL Page 26
Environmental Performance
4.1.2.1 Temperature
Maximum, minimum and average temperatures are calculated daily from the 15min recordings. Figure
4-1 shows average monthly temperature records for the reporting period (10m MET recordings).
Compared to the previous reporting period, the average minimum and maximum temperatures are
notably higher in summer.
Figure 4-1 Monthly Temperature Records
4.1.2.2 Rainfall
Rainfall is measured using an RG5 type flow-through monitor, with a 15-minute recording interval.
Monthly rainfall totals for the reporting period are presented in Figure 4-2.
A comparison of 2016 and 2017 rainfall is shown in Figure 4-3.
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17
Deg
rees
Cel
siu
s
minimum maximum average
Annual Review 2017
BCOPL Page 27
Figure 4-2 Monthly Rainfall
Figure 4-3 Comparison of 2016 and 2017 Rainfall
4.1.2.3 Wind
Wind speed and direction are important parameters for preparation of blasting activities, investigating
noise and dust complaints, and assessing cumulative impacts as a result of other coal mines operating in
the region. Wind data for 2017 are presented in the wind roses provided in Figure 4-4, Figure 4-5 and
Figure 4-6. Wind speed values are displayed as metres per second.
84
16.6
53.2
14.6
74
45.6
17 17
8.4
78.2
59.2
38
0
100
200
300
400
500
600
0
10
20
30
40
50
60
70
80
90
Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17
Cu
mu
lati
ve R
ain
fall
(mm
)
Mo
nth
yl R
ain
fall
(mm
)
Monthly Total Cumulative Rainfall
0
100
200
300
400
500
600
700
0
20
40
60
80
100
120
140
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Cu
mu
ltai
ve R
ain
fall
(mm
)
Mo
nth
ly R
ain
fall
(mm
)
2016 2017 Cumulative Total 2016 Cumulative Total 2017
Annual Review 2017
BCOPL Page 28
Analysis of data reveals that prevailing winds during the 2017 reporting period were predominantly from
the south-east from January through April and from the north-west and east from May through December.
The prevailing wind conditions during this reporting period were relatively consistent with the historical
data as presented in the 2010 EA. Average wind speeds were notably higher in January, March, October
and November and were notably lower in February, June, July and September than the previous
reporting period.
The MET data identified that average monthly wind speed did not exceed 3 m/s in 2016.
January 2017
February 2017
March 2017
April 2017
Figure 4-4 Monthly Wind Rose Summary January – April 2017
Annual Review 2017
BCOPL Page 29
May 2017
June 2017
July 2017
August 2017
Figure 4-5 Monthly Wind Rose Summary May – August 2017
September 2017
October 2017
Annual Review 2017
BCOPL Page 30
November 2017
December 2017
Figure 4-6 Monthly Wind Rose Summary September – December 2017
Improvements and Initiatives
Building on the work completed during the 2016 reporting period, BCOPL continued to implement and
refine the real-time air quality management system at the BCM. This included ongoing utilisation of real-
time meteorological data and weather forecasting software to guide the day-to-day implementation of
reactive and proactive mitigation measures.
4.2 Air Quality
Environmental Management
Air quality management at BCM is undertaken in accordance with the AQGHGMP. Through
implementation of the AQGHGMP, BCOPL execute a range of mitigation measures for air quality that
have proved to be effective at managing dust impacts, demonstrated by maintaining compliance with
criteria specified in the PA. During the reporting period, mitigation measures included the following:
Dust suppression with bulk water trucks using dust suppression additives ’Avenger Coal’ and ‘Boost X’
in mining areas, construction areas and haul roads
Visual assessments of mining and coal transport areas to identify dust sources and modify operations
as required
Progressive rehabilitation of waste emplacements
Revegetating disturbed areas of the rail corridor
Implementation of product coal handling controls to minimise dust generation
Maintaining unsealed surfaces and trafficable areas in good condition
Installation and maintenance of dust suppression equipment on drill rigs
Implementing good practice blast design to minimise dust and plan blasting to suit meteorological
conditions
Monitoring meteorological conditions to plan and modify operations as required
These mitigation measures will continue to be employed throughout 2018.
Annual Review 2017
BCOPL Page 31
BCOPL implements a dust monitoring program to measure concentrations of depositional dust, PM10 and
PM2.5 in the vicinity of the BCM. Depositional dust monitoring provides an indication of levels of dust in the
atmosphere measured in g/m²/month of insoluble matter. PM10 measures the concentration of particulate
matter less than 10 microns in diameter, whilst PM2.5 monitoring measures the concentration of
particulate matter less than 2.5 microns in diameter. PM10 monitoring utilises a High Volume Air Sampler
(HVAS) and tapered element oscillating microbalance (TEOM), whilst PM2.5 is measured only use a
TEOM.
The current dust monitoring program includes 3 depositional dust gauges, two HVAS and one TEOM,
details of which are provided in Table 4-3. A figure showing the location of each air quality monitoring site
is provided in Appendix A.
Table 4-3 Air Quality Monitoring Sites
Site ID To be used for compliance monitoring?
Type Units Frequency
D4 Yes Deposited dust gauge g/m2/month Monthly
D5 Yes Deposited dust gauge g/m2/month Monthly
D6 Yes Deposited dust gauge g/m2/month Monthly
Roma
Merriown
Yes
Yes
HVAS (PM10)
HVAS (PM10)
µg/m3
µg/m3 Every 6 days
Every 6 days
Tarrawonga No TEOM (PM10 & PM2.5) µg/m3 Continuous
Environmental Performance
4.2.2.1 Depositional Dust
BCM’s depositional dust monitoring is undertaken on a monthly basis at three monitoring sites: D4, D5
and D6 (refer to Appendix A). D5 is located on land owned by BCOPL, while D4 and D6 are located on
land owned by Whitehaven Coal Pty Limited.
In accordance with the PA (Schedule 3, Condition 27), the annual average depositional dust must not
exceed the limit of 4 g/m2/month at any residence on privately owned land, or on more than 25 percent of
any privately-owned land. Given that there are no criteria specified for non-privately owned land, the
results have been assessed against these criteria for consistency, despite land being mine-owned.
Sampling and analysis is undertaken in accordance with AS/NZS 3580.10.1:2003: Methods for Sampling
and Analysis of Ambient Air – Determination of Particulate Matter – Deposited Matter – Gravimetric
Method.
Results
Depositional dust samples were subject to visual analysis by a NATA accredited laboratory to determine
sample contamination by naturally occurring impurities. Table 4-4 presents the corrected results following
visual analysis of the three dust monitors.
The results indicate that all depositional dust gauges remained below the criterion for the annual average
during 2017.
Annual Review 2017
BCOPL Page 32
Table 4-4 Depositional Dust – Annual Average Results
Monitoring Point Limit
(g/m2/month)
Corrected annual average* (g/m2/month)
D4 4 2.6
D5 4 1.6
D6 4 1.5
* Total adjusted after visual analysis. Annual average applies to 2017 calendar year.
Depositional dust systems are often subject to contamination by naturally occurring impurities such as
bird droppings, insects and vegetation. On eighteen occasions over the reporting period, samples were
observed to be contaminated and were therefore not analysed by the laboratory. This included samples
from January (D4 and D6), February (D4 and D6), March (D4), April (D4 and D5), May (D4), June (D4
and D6), July (D6), August (D5 and D6), September (D6), October (D5 and D6), November (D6), and
December (D4).
The result for D4 and D5 are above the predicted levels documented in the EA (1.1 and 0.6 g/m2/month)
for the closest corresponding year of operations (Year 5). D6 is located outside the area assessed in the
EA and no predictions were provided. All dust gauge results remain below the criteria specified in the PA.
Depositional dust levels within gauge D4
Between 2014 and 2015, the rolling annual average of all gauges was on a downward trend. During
2015, the trend stabilised and then began trending upwards in 2016, before stabilising in 2017.
Depositional dust levels recorded during the 2017 reporting period remain within the range of historical
results.
4.2.2.2 PM10
BCM monitors PM10 dust through two HVAS units. The BCM HVAS is located on the Merriown property
approximately 1 km west of the BCM. The second HVAS, Roma PM10 is located on the Roma property
and commenced operation on the 1 July 2015. Sampling is undertaken for a period of 24 hours every 6
days. PM10 monitoring is ongoing from previous reporting periods. Results for both samplers have been
provided in this report and will continue to be monitored throughout 2018.
Results
The PM10 monitoring results for Merriown HVAS and Roma HVAS over the 12 month period are provided
in Figure 4-7 and Figure 4-8, respectively. Both figures also include BCM’s rolling average over the
reporting period.
In accordance with the PA, the short-term concentration limit for PM10 over each 24-hour period is 50
µg/m3 while the long-term concentration limit for the annual average is 30 µg/m3.
The average PM10 concentrations at the Merriown HVAS and Roma HVAS monitors over the reporting
period were 12.0 µg/m3 and 12.5 µg/m3 per month, respectively. In comparison, the average
concentrations at the Merriown HVAS and Roma HVAS monitors during the 2016 reporting period were
10.4 µg/m3 and 9.9 µg/m3 per month respectively. The annual average PM10 levels are below the PM10
levels (14µg/m3) predicted in the EA.
Annual Review 2017
BCOPL Page 33
One exceedance of the short-term PM10 criterion was recorded at the Merriown HVAS monitor during the
reporting period. The Roma HVAS monitor also recorded two results that were higher than the short-term
criterion, however these are not considered exceedances as the monitoring location is not used as a
compliance measurement tool. Neither monitors recorded results that exceeded the long-term PM10
criterion.
The short-term PM10 results for the 2017 reporting period are generally consistent with the 2015 and 2016
reporting periods with the exception of the individual exceedance of the short-term criterion recorded at
the Merriown HVAS monitor and the two elevated results at the Roma HVAS monitor. Disc ploughing was
observed in nearby paddocks at the time the single exceedance of the short-term criterion was recorded
at the Merriown HVAS monitor. While Merriown HVAS was not included in the EA as a receiver in the air
quality model due to it being owned by BCOPL, interpolation of the PM10 air quality contours in the EA
indicate PM10 concentrations of between 20 to 30 µg/m3 were predicted to occur at the property during the
reporting period. The short-term PM10 levels recorded at Merriown HVAS were generally below the levels
predicted in the EA. The 2017 PM10 levels indicated the trend is generally stable.
Figure 4-7 Merriown PM10 Monitoring Results
0
10
20
30
40
50
60
70
Jan
/17
Fe
b/1
7
Ma
r/1
7
Ap
r/17
Ma
y/1
7
Jun
/17
Jul/17
Au
g/1
7
Se
p/1
7
Oct/
17
Nov/1
7
Dec/1
7
PM
10
(ug
/m3)
Merriown - PM10
Merriown - PM10 Current annual average PM10 24hr Criterion PM10 Annual Criterion
Annual Review 2017
BCOPL Page 34
Figure 4-8 Roma PM10 Monitoring Results
4.2.2.3 Total Suspended Particulates
The ambient air quality criterion for TSP quoted in Table 9 of the PA (annual average 90µg/m3) is based on
a value derived by the National Health and Medical Research Council (NHMRC) in 1996. There is an
established relationship between TSP concentration and the concentration of PM10. In areas where coal
mining is a significant component of the local particulate emission inventory, PM10 typically comprises ~40%
of the TSP (SPCC, 1986 and others).
As prior studies have confirmed that the long-term average PM10 to TSP ratio is close to 0.4:1, that is, 40%
of TSP is comprised of PM10, inversely, the relationship between TSP and PM10 can be written as:
TSP = PM10 x 2.5. Due to the nature of the relationship between TSP and PM10 levels, the TSP criterion of
90 µg/m3 (annual average) will always be satisfied when the long-term PM10 criterion of 30 µg/m3 is satisfied.
As discussed above in Section 4.2.2.2, Boggabri Coal currently monitor PM10 at two locations within the
vicinity of the operation; the ‘Merriown HVAS’ and ‘Roma HVAS’ monitors.
In consideration of the historical PM10 monitoring undertaken for the BCM (i.e. results have historically been
significantly below the PM10 annual average criteria) and the above relationship between PM10 and TSP,
BCOPL consider that compliance with the long-term TSP criteria can be demonstrated via the application
of the known relationship between PM10 and TSP. This can be achieved by calculating annual average TSP
results from the PM10 monitoring using the above calculation for the locations in the vicinity of the operation.
The calculation of TSP is based on the available data at the Merriown HVAS and Roma HVAS monitoring
locations.
0
10
20
30
40
50
60
70Jan
/17
Fe
b/1
7
Ma
r/1
7
Ap
r/17
Ma
y/1
7
Jun
/17
Jul/17
Au
g/1
7
Se
p/1
7
Oct/
17
No
v/1
7
De
c/1
7
PM
10
(ug
/m3)
Roma - PM10
Roma- PM10 Current annual average PM10 24hr Criterion PM10 Annual Criterion
Annual Review 2017
BCOPL Page 35
The results indicate the annual average TSP at Merriown (30.1 ug/m3) and Roma (31.1 µg/m3) are below
the air quality criterion in the PA. Similarly, the results indicate the level of TSP at Roma is below the TSP
levels predicted in the EA (35µg/m3) for the reporting period.
Improvements and Initiatives
BCOPL installed an additional TEOM at the mine-owned ‘Wilberoi East’ property during the reporting
period. The Wilberoi TEOM will be linked up with the ‘Sentinex’ real-time air quality management system
and be utilised as an additional tool to guide the day-to-day management of air quality at the BCM.
4.3 Operational Noise
Environmental Management
Operational noise is managed by BCOPL in accordance with the approved NMP. The NMP covers all
operational activities with the potential to ge