bobrn calculation

Embed Size (px)

Citation preview

  • 7/30/2019 bobrn calculation

    1/2

    ABSTRACT

    As leading companies continue to look for innovative ways to reduce costs and increase

    in production, and labour is one of the main constrain of present time, rail wagonunloading systems are generating more attention. Our project gives a brief overview of

    unloading coal by BOBRN (Bottom open broad gauge rail) type wagon using track

    hoppers instead of manual unloading.INTRODUCTION

    1.1 An overview of the company

    Malabar Cements Ltd is the only Portland cement manufacturer in Kerala. The companywas incorporated in April 1978 commenced commercial production in 1984, with a

    capital outlay of Rs.680 Million and paid-up equity capital of 260 Million is owned fully

    by the Govt. of Kerala.

    The 1200 Tonnes per day plant at Walayar is continuously running in profit. Geologicalsurvey of India has identified a cement limestone in Walayar Reserve Forest way back in

    1961-62.The Mineral Exploration Corporation Ltd confirmed its efficiency.

    Despite its difficult terrain and perilous conditions at the deposit, Kerala State Industrial

    Development Corporation (KSIDC) obtained the Industrial License for setting up a unitin November 1976. The Malabar Cements Ltd thus comes into existence at Walayar,

    Palakkad District.The company is well equipped to set precedence among public sector unit in the State. A

    2.5MW multifold power plant was commissioned in June 1998 to complement 25% of

    the total power requirement for the Walayar plant operation. The company was updatedby the plant with State Art Technology in time.

    Belt bucket elevators, Kiln automation, modification to cement mill internals etc are few

    to mention. The 0.42 Million capacities less than 10% of the cement consumption in

    Kerala, the company harness the market beyond care segments.

    CALCULATION FOR MANUAL COAL UNLOADING

    3.1 Time study

    Time of arrival of wagons = 5.30 am Time of unloading start = 7.00 am

    Time of unloading finish = 2.40 am

    Time taken for unloading 5 wagons = 50 min

    Dozing time for 5 wagons = 30 min Time taken for shifting 5 wagons = 15 min

    Rest time for 5 wagons = 5 min

    Total time for 5 wagons =50+30+15+5= 100 min

    Total time for 1 wagon = 100/5

    = 20 min Effective time for unloading 1 wagon of coal

    carrying 65T = 20 min

    Time for unloading 59 wagons = 20*59

    = 1180 min

  • 7/30/2019 bobrn calculation

    2/2

    Routine idle time for shunting of rake to

    a safe track and detaching of railway

    engine (5.30am to 7.00 am ) = 90 min Total time for unloading 59 wagons including

    routine idle time = 1270 min

    = 21 hrs 10 min Time allowed by railway without demurrage

    for unloading = 9 hrs

    Demurrage time = 12 hrs 10 min3.2 Cost study

    Rate of unloading charge = Rs 36 /TONNE

    Cost for unloading 1 wagon = 36*65

    = Rs 2340 Cost for unloading 59 wagons = 2340*59

    = Rs 138060

    Time allowed without demurrage by railway= 9 hrs

    Extra time taken = 12 hrs Rate of demurrage charge = Rs 100 / wagon/hr

    Demurrage charge for 59 wagons for 12 hrs = 100* 59*12= Rs 70800

    Total cost per rake = 70800+138060

    = Rs 208860 Cost of indigenous coal = Rs 3000/T

    Cost of imported coal = Rs 6300/T

    Yearly consumption of indigenous coal = 60000T/year

    Yearly consumption of imported coal = 40000T/year Total consumption of coal = 100000T/year

    Labour cost per Tonne for manual unloading= Rs 36/Tonne

    Labour cost per year for manual unloading(Excluding demurrage charge) = Rs 36lakhs

    Cost of coal in one year (coal value per year) = Rs 4320lakhs

    Ratio of labour cost to coal value inmanual unloading = 0.83%