Airport Metro ConnectorBoard Staff BriefingFebruary 12, 2015
1
AMC Transit Station Project Area
22/12/2015
AMC Transit Station Components
> LRT station to be served by the Metro Green Line (proposed service extension) and Crenshaw/LAX Line (project under construction)
> Bus plaza for Metro and municipal buses
> Passenger pick-up, drop-off, pedestrian, and bicycle amenities
> Enclosed transit center/terminal building that connects Metro’s AMC transit station with LAWA’s APM Station
Denver Union Station Transit Center Rail Platforms
Phoenix SkyTrain Connection to Metro Light Rail & Bus Plaza
32/12/2015
Airports with Rail to APM Connections
4
San Francisco AirTrain
Phoenix SkyTrain
Oakland Airport Connector
Miami Mover System
Five Phases of Project Development
DetailedEngineering &
Pre-Construction
(2015-Mid 2020)
Construction
(Mid 2020-2023)Open
Station for
Service
(2023)
Future PhasesEarly Planning
(2011-2014)
Initial Public Meetings
Define Alternatives, Analyze and Screen
Alternatives
Preliminary Costs
Foundation for Draft EIR
We Are Here
Environmental Process & Conceptual Engineering
(2015-2016)Public Scoping
Prepare Draft EIR
Release Draft EIR for public comment
Draft EIR public comment period
Prepare Final EIR
Certify Final EIR
Federal Clearance
52/12/2015
Initiating the CEQA Process
> February 6, 2015: NOP released
> February 19, 2015: Elected Officials’ BriefingWestchester Municipal Building Community Room2:00 pm to 4:00 pm
> February 23, 2015: Scoping meetingFlight Path Learning Center6:00 pm to 8:00 pm
> March 9, 2015: Comment due date
> All formal NOP comments will be summarized in:- Scoping Report- Draft EIR
62/12/2015
72/12/2015