Board Presentation Board Presentation Mobile Work Mobile Work Management Management Pilot Project Pilot Project Mike Beardslee, PMP, GISP Mike Beardslee, PMP, GISP October 14, 2010

Board Presentation Mobile Work Management Pilot Project Mike Beardslee, PMP, GISP October 14, 2010

Embed Size (px)

Citation preview

Page 1: Board Presentation Mobile Work Management Pilot Project Mike Beardslee, PMP, GISP October 14, 2010

Board PresentationBoard Presentation

Mobile Work Mobile Work ManagementManagementPilot ProjectPilot Project

Mike Beardslee, PMP, GISPMike Beardslee, PMP, GISPOctober 14, 2010

Page 2: Board Presentation Mobile Work Management Pilot Project Mike Beardslee, PMP, GISP October 14, 2010

22

Agenda

Strategic Plan/CIP Background Scope and Architecture Spending Plan/Procurement ROI Future Steps Recommended Board Action

Page 3: Board Presentation Mobile Work Management Pilot Project Mike Beardslee, PMP, GISP October 14, 2010

33

Mobile Work Management Program

Loudoun Water Strategic Plan Goal– Leverage technology to optimize business Leverage technology to optimize business

practicespractices Part of 2010 CIP

Page 4: Board Presentation Mobile Work Management Pilot Project Mike Beardslee, PMP, GISP October 14, 2010

44

Background

Current use of laptops in field– Clumsy, slow, require connectivityClumsy, slow, require connectivity

Need for more efficient mobile platform– Automate data entry/managementAutomate data entry/management– Boost data integrityBoost data integrity– Mapping and routing functionsMapping and routing functions– Decrease windshield time, increase time on Decrease windshield time, increase time on

tasktask– Improve customer serviceImprove customer service

Page 5: Board Presentation Mobile Work Management Pilot Project Mike Beardslee, PMP, GISP October 14, 2010

55

Background

Initial task order $48,036 to Gannett Fleming for Implementation Plan– Define phased approachDefine phased approach– Recommend technical solutionsRecommend technical solutions– Foundation for new task orderFoundation for new task order

Page 6: Board Presentation Mobile Work Management Pilot Project Mike Beardslee, PMP, GISP October 14, 2010

66

Task Order #3

Pilot Project, $186,600 Establish framework for mobile work

management platform– Back office ‘middle-ware’Back office ‘middle-ware’

Two mobile applications on iPhones/iPads– Hydrant FlushingHydrant Flushing– Meter Service WorkMeter Service Work

Completion in Q2, 2011

Page 8: Board Presentation Mobile Work Management Pilot Project Mike Beardslee, PMP, GISP October 14, 2010

88

Mobile – CIP

2010 2011 2012 Total

2010 CIP $500,000 $400,000 $200,000 $1,100,000

Revised 2011 CIP Projection

$150,000 $500,000 $450,000 $1,100,000

Page 9: Board Presentation Mobile Work Management Pilot Project Mike Beardslee, PMP, GISP October 14, 2010

99

Procurement Actions

Task Order #1Implementation

Plan(Complete)

2010 2011 2012

Task Order #3Pilot Project

Possible Future Mobile Implementation

Phases - Separate Procurement(s)

Today

Timeline

$48k

$186k

$866k

Page 10: Board Presentation Mobile Work Management Pilot Project Mike Beardslee, PMP, GISP October 14, 2010

1010

ROI

20% gain in efficiency through reduced mileage and associated costs

Hydrant flushing– $20k - $40k in labor savings$20k - $40k in labor savings– Intangible benefits (data integrity, etc.)Intangible benefits (data integrity, etc.)

Page 11: Board Presentation Mobile Work Management Pilot Project Mike Beardslee, PMP, GISP October 14, 2010

1111

Future

ROI Analysis Procurement for additional mobile

apps– Cross connection/backflowCross connection/backflow– Manhole checksManhole checks– Easement maintenanceEasement maintenance

Page 12: Board Presentation Mobile Work Management Pilot Project Mike Beardslee, PMP, GISP October 14, 2010

1212

Recommended Board Action

I move the Board approve Task Order No. 3 with Gannett Fleming for an estimated not to exceed cost of $186,600 and authorize an approximate 10 percent contingency to be controlled by the General Manager, for an authorized budget ceiling not to exceed $205,000 without further Board approval.

Page 13: Board Presentation Mobile Work Management Pilot Project Mike Beardslee, PMP, GISP October 14, 2010

1313

Questions?