  • BLOCK : SANKRA DISTRICT : JAISALMER

    AGRO CLIMATIC ZONE :- 1 C

    TOTAL GEOGRAPHICAL AREA :- 11250 Hac.

    TOTAL EFFECTIVE AREA :- 10000 Hac.

    TOTAL COST :- 1500.00 Lacs.

    UNIT COST :- 15000/Hac.

    ----------------&&&&&&&&----------------

    SUBMITTED BY

    PROJECT MANAGER

    DISTRICT WATERSHED DEVELOPMENT UNIT

    JAISALMER (RAJASTHAN)

  • DPR TEMPLATE Index

    S.No Topics Page no.

    1 Chapter

    • Location

    • General Features of watershed (Cost and Area details)

    • Climatic and Hydrological information

    • Other Development Schemes in the project area

    • Details of infrastructure in the project areas

    • Institutional arrangements (,DWDU,PIA,WDT,WC)

    2 Chapter Basic Data ,Analysis and Scope

    2.1 Demography Details

    2.2 Development Indicators 2.3 Land use 2.4 Agriculture status and Productivity Gap Analysis

    2.5 Horticulture/Vegetable/Floriculture status 2.6 Land holding pattern 2.7 Livestock status

    2.8 Fodder status

    2.9 Farm Implements 2.10 NREGS Status 2.11 Migration details

    2.12 Livelihood Details. 2.13 Existing SHG 2.14 Ground Water details

    2.15 Drinking Water Status 2.16 Water use efficiency 2.17 Slope details

    2.18 Water Budgeting

    2.19 Soil Details 2.20 Soil erosion status

    3 Chapter Proposed Development Plan

    4 Chapter Activity wise Total Abstract of cost

    5 Chapter Annual Action Plan

    5.1 Project fund 5.2 Convergence Plan

    6 Chapter Project outcomes

    7 Technical designs and estimates for proposed activities

    8 Enclosures

    8 .1 Maps

    a. Location –District, block, village, watershed location map

    b. Map of Project with Watershed Boundary demarcation in cadastral map

    c. Land Use Land Cover map d. Existing water bodies, DLT e. PRA Map (along with photos & paper drawing)

    f. GIS based intervention map g. Treatment map ie proposed works on revenue map

  • 8.2 Documents of Agreements:

    • Proceedings of gram sabha for EPA approval

    • Proceedings of gram sabha Resolution for committee constitution

    • Documents related to PRA exercise

    • Proceedings of gram sabha for DPR approval

    • Proceedings of Panchayat Samiti General body for DPR approval

    • Watershed Committee Registration certificate

    • MoU – PIA – DWMA, PIA – WC(in case of NGO as PIA)

  • CHAPTER – I

    Location.

    Jaisalmer- IWMP VIII Project is located in jaisalmer Block of jaisalmer district. The Project area is

    between the 26.72 latitudes & 71.95 longitudes it is at a distance of 45 km from its Block & District

    head quarters. There are 5947 no. of habitations in the project area and other details are given below.

    General features of watershed

    S.No. Name of Project(as per GOI) Jaisalmer (IWMP) VIII 2009-10

    (a) Name of Catchment Barath Ka Gaon

    (b) Name of watershed area(local name) Barath Ka Gaon

    © Project Area 11250 ha.

    (d) Net treatable Area 10000ha.

    e) Cost of Project 1500 lac

    f) Cost/hectare 15,000

    g) Year of Sanction 2009-10

    h) Watershed Code

    i) No. of Gram Panchayats in project area 7

    j) No. of villages in project area 9

    k) Type of Project Desert

    l) Elevation (metres) 210

    m) Major streams -

    n) Slope range (%) 0--2%

    Macro/micro Name of Gram

    Panchayat

    Name of Villages

    Covered

    Census code of

    villages Area (Hact)

    Cluster Barath Ka Gaon Bhakhri 2055700 1500

    Barath Ka Gaon Padroda 2055900 1000

    Bhandhewa Bhandhewa 2062700 1000

    Dantal Sanga bera 2061800 500

    Pannasar Shakti Fozdar Nagar 2060600 1000

    Swami ji ki dhani Jetpura 2064500 1000

    Balad Roopsar 2063400 1500

    Balad Bhikhodai nai 2063300 1500

    Dedaniya Kerawa 2052200 1000

  • The watershed falls in Agroclimatic Zone- I-C .The soil texture is sandylomy The average rainfall is

    194mm.The temperatures in the area are in the ranges between 49--32 centigrade during summer and 26—4

    centigrade during winter.

    The major crops in the area are Bajra, Guar, Mung etc The 28.35% land is under cultivation 0.4%

    land fallow,2.86% land is wasteland. The 0.00% area is irrigated through tubewells.

    397 No of households are BPL (38.58% households) 64 are landless households(6.22% households)

    and 206 household are small and marginal farmers( 20 %household). Average land holding in the area

    is 10.93 ha. 100% area is single cropped area.

    The average annual rainfall (10 years) in the area is 194 mm. There is no Major streams in the

    Watershed area. The major festivals in the villages are Holi, Deewali, krishana janamaastmi, Navratra,

    Gangor, Raksha-bandhan, Moharam & Eid. At present this village is having 5947 population with

    Communities like Rajput, Muslim, Kumhar, Suthar, Megwal and Bhil.

    Climatic and Hydrological information

    Sl.No. Year Average Annual Rainfall(mm)

    1 2001 361

    2 2002 31

    3 2003 137

    4 2004 42

    5 2005 176

    6 2006 501

    7 2007 142

    8 2008 112

    9 2009 72

    10 2010 361

    2. Average Monthly rainfall (last ten years)

    Sl.

    No Month 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010

    Average

    Rainfall(

    mm)

    I June 80.50 6.80 0.00 7.30 23.70 49.80 0.70 13.20 33.00 100.90 31.59

    Ii July 216.50 0.00 60.30 2.20 44.60 3.50 21.00 27.50 21.00 77.70 47.43

    Iii August 64.80 0.40 77.00 28.50 2.20 442.80 105.30 71.80 17.80 90.70 90.13

    iv September 0.00 23.80 0.00 4.10 105.70 5.50 15.10 0.00 0.60 92.00 24.68

  • 3 Maximum rainfall intensity (mm)

    Duration rainfall

    intensity(mm)

    i) 15 minute duration 40

    ii) 30 minute duration 58

    iii) 60 minute duration 69

    4 Temperature (Degree C)

    Season Max Min

    i) Summer Season 49 32

    ii) Winter Season 26 4

    iii) Rainy Season 35 24

    5 Potential Evaporation Transpiration (PET) (mm/dd)

    Season PET

    i) Summer 3200

    ii) Winter 2464

    iii) Rainy 2784

    6 Runoff

    i) Peak Rate (cum/hr) 95.25

    ii) Total run off volume of rainy season

    (ha.m.)

    50.76

    iii) Time of return of maximum flood 5

    years

    10

    years

    In-

    Year

    iv)Periodicity of Drought in village

    area

    3 7 -

    Other Development Schemes in the project area

    S.No Scheme Name of the

    department

    Key

    interventions

    under the

    Scheme

    Targeted

    Beneficiaries

    Provisions

    under the

    Scheme

    1 MG NREGA

    RURAL

    DEVELOPMENT &

    PANCHAYAT RAJ

    DEPARTMENT

    Providing

    Employment

    6772

    135 lac

    2 TFC - 18.75 lac

    3 SFC - 11.50 lac

    4 BRGF TSC -

    26.25 lac 5 SGSY/ IAY -

    6 -

    7 -

  • Details of infrastructure in the project areas

    Parameters Status

    (i) No. of villages connected to the main road by an all- weather road 9

    (ii) No. of villages provided with electricity 9

    (iii) No. of households without access to drinking water 0

    (iv)

    No. of educational institutions : (P) (S) (HS) (VI)

    Primary(P)/ Secondary(S)/ Higher Secondary(HS)/vocational

    institution(VI) 9 1 0 -

    (v) No. of villages with access to Primary Health Centre 4

    (vi) No. of villages with access to Veterinary Dispensary -

    (vii) No. of villages with access to Post Office 7

    (viii) No. of villages with access to Banks 0

    (ix) No. of villages with access to Markets/ mandis 0

    (x) No. of villages with access to Agro-industries 0

    (xi) Total quantity of surplus milk 968 Ltr.

    (xii) No. of milk collection centres (U) (S) (PA) (O)

    (e.g. Union(U)/ Society(S)/ Private agency(PA)/others (O)) - - 12 -

    (xiii) No. of villages with access to Anganwadi Centre 9

    (xiv) Any other facilities with no. of villages (please specify) -

    (xv) Nearest KVK Jaisalmer

    (xvi) cooperative society -

    (xvii) NGOs 4

    (xviii) Credit institutions -

    (i) Bank -

    (ii) Cooperative Society -

    (xix) Agro Service Centre's -

    Institutional arrangements (SLNA,DWDU,PIA,WDT,WC, Secretary)

    DWDU Details

    S.No Particulars Details of DWDU

    1 PM ,DWDU Sh. Ramesh Chandra Mathur, Executive

    Engineer

    2 Address with contact no., website PM, DWDU District Jaisalmer, Zila Parishad,

    Jaisalmer

    3 Telephone 02992-250712

    4 Fax 02992-250712

    5 E-mail [email protected]

    PIA particulars

    S.No Particulars Details of PIA

    6 Name of PIA Sh. Sukhvinder Singh

    7 Designation Assist. Engineer

    8 Address with contact no., website AEN. (IWMP) P.S. Sankra

    9 Telephone 9001109240

    10 Fax ---------

    11 E-mail

  • WDT Particulars:

    S.

    No

    Name of WDT

    member M/F Age Qualification

    Experience

    in watersh

    ed(Yrs)

    Description

    of professi

    onal

    training

    Role/ Function

    1 2 3 4 5 6 7 8

    1 Sh Badriprashad M 32 M.Sc. (A.g) - Yes Agriculture

    2 Sh Indar Raj Singh M 28 L.S.A - - Animal Husbandry

    3 Smt Urmila Moyal F 27 BA

    Socology - Yes SHG

    Details of Watershed Committees (WC)

    S.

    N.

    Name of

    WCs

    Date of

    Gram

    Sabha

    for

    WC

    Date of

    Registrati

    on as a

    Society

    (dd/mm/yy

    yy

    Designati on Name M/F

    SC/ST/

    OBC/G

    eneral

    Landless/

    MF/SF/

    BF

    Name of

    UG/SHG

    Educational

    qualification

    1 Bhakhri

    11-0

    8-2

    010

    President Sh. Nendan M OBC UG Sec

    Secretary Sh. Vasudev singh M OBC Up Primary

    Member Sh. Akbar khan M OBC UG Primary

    Sh Heera ram M OBC UG Litrate

    Sh tiku ram M SC UG Litrate

    Sh Hukam singh M Gen LL UG Litrate

    Sh Firoj khan M OBC UG Litrate

    Sh Bibe khan M OBC UG Litrate

    Smt Puspa F OBC SHG Litrate

  • Smt Dhai F SC SHG Litrate

    Smt Gomti F ST SHG Litrate

    2 Padroda

    12-0

    8-2

    010

    President Sh. Alsha ram M SC UG Primary

    Secretary Sh. Ran singh M Gen - Sec

    Member Sh Ashu singh M Gen UG Primary

    Sh Kishna ram M SC - Up primary

    Sh Balwanta ram M OBC UG Primary

    Sh Thakra ram M SC UG Primary

    Sh Amra ram M SC UG Primary

    Smt Rekha F SC LL UG Up primary

    Smt Soni F SC UG Litrare

    Smt Pappu F SC SHG Litrare

    Smt Puspa F SC SHG Litrare

    Smt Ganga devi F SC SHG Primary

    Sh Sakar F SHG Litrare

    3 Bandhewa

    02-0

    7-2

    010

    -

    President Sh Barkat khan M OBC UG Up Primary

    Secretary Sh. Bhomraj M Gen Up primary

    Member Sh Gulam khan M OBC UG Primary

    Sh Sardar Khan M OBC UG Litrate

    Sh Shambhu ram M OBC UG Litrare

    Sh Karim khan M OBC UG Primary

    Sh Janu khan M OBC Primary

    Smt Chandro F OBC SHG Litrare

    Smt Lahro F OBC UG -

    Smt Kasumbi F OBC -

    Smt Aamna F OBC SHG Litrate

    Smt Indro F SC SHG Litrate

    Sh Kheru khan M OBC Litrate

  • 4 Sangabera

    03-0

    2-2

    011

    President Sh Yaru khan M OBC UG Primary

    Secretary Sh

    Member Sh Dadu ram M ST UG Litrate

    Sh Banki dan M OBC UG Litrate

    Sh Nasir khan M OBC UG Litrate

    Sh Aawan dan M OBC LL -

    Smt Sakino F OBC SHG Litrate

    Sh Fuli F OBC SHG -

    Sh Sakur khan F OBC UG Up Primary

    Smt Amna F OBC UG Litrate

    Smt Sarifo F OBC UG Litrate

    5 Saktifozdar

    Nagar

    President Sh Guman singh M Gen UG Primary

    Secretary Sh Ganpat singh M Gen Sec

    Member Sh Saitan singh M Gen UG Sec

    Smt Ugam kanwar F Gen UG -

    Sh Anop Singh M Gen UG Sec

    Sh Bile khan M Gen UG Litrate

    Smt Chagni F SC UG -

    Sh Gulab singh M OBC LL -

    Sh Khangar singh M Gen Sec

    Smt Chandra

    kanwar F Gen SHG -

    Smt Achat Kanwar F Gen SHG Primary

    6 Jetpura

    04-0

    8-2

    010

    President Sh Salam khan M OBC UG Primary

    Secretary Sh Fuse khan M OBC Up Primary

    Member Sh Mode khan M OBC

    UG -

    Sh Gaji kha M OBC

    UG Litrate

    Sh Adre khan M OBC

    UG -

    Smt Jamna F SC

    SHG -

  • Smt Amri F OBC

    SHG Litrate

    Smt Mohni F OBC

    SHG Litrate

    Smt Andu F OBC

    UG -

    Smt Jammi F OBC

    UG -

    Smt Nasibo F OBC

    SHG Litrate

    Sh Lakhe khan M OBC

    Litrate

    Sh Durga ram M OBC

    Litrate

    7 Roopsar iii

    04-0

    2-2

    011

    President Sh Bhinya ram M OBC UG Up Primary

    Secretary Sh Umardeen

    mehar M OBC Hg Sec

    Member Sh Khartha ram M OBC UG Primary

    Sh Roopa ram M OBC UG Primary

    Sh Agar singh M Gen UG Litrate

    Sh Naru ram M OBC UG Litrate

    Smt Kamla F OBC UG Litrate

    Smt Sugni F SC SHG Litrate

    Smt Gumni F OBC UG Litrate

    Smt Ratni F OBC SHG Litrate

    Sh Kheru khan M OBC UG Litrate

    8 Bhikhodai

    17-0

    7-2

    011

    President Sh Alkhe khan M OBC UG Litrate

    Secretary Sh Lune khan M OBC Sen Sec

    Member Sh haneef khan M OBC UG Sec

    Sh Miran khan M OBC LL UG

    Primary

    Sh Chaina ram M SC UG

    -

  • Sh Babu ram M SC UG

    Sec

    Sh Gyan singh M Gen UG

    Graduate

    Sh Surta ram M OBC UG

    -

    Smt Jinnat F OBC SHG -

    Smt Mariyam M OBC SHG -

    Smt Roopa F OBC UG -

    Smt Bhikhi devi F OBC SHG -

    Smt Baliyo F OBC UG -

    9 Kerawa

    President

    Secretary

    Member

  • CHAPTER – II

    DEMOGRAPHICAL DETAILS

    Table 2.1 Population & Household Details:

    Total Population

    Male

    Female

    Total

    SC

    ST

    3639 3133 6772 353 483

    Household Details

    BPL

    household

    L. Less

    Large

    Farmer

    Small

    Farmer

    M.

    Farmer

    Total

    household

    SC

    household

    ST

    household

    397 164 62 82 324 1029 22 80

    Male, 3639,

    54%

    Female, 3133,

    46%

    Male

    Female

    SC, 353, 6%

    ST, 483, 8%

    Others, 5111,

    86%

    SC

    ST

    Others

  • Table 2.2 Development indicators

    S. No. Development Indicators State Project Area

    1 Per capita income (Rs.) 16,260 9265

    2 Poverty ratio 0.22 0.19

    3 Literacy (%) 60.4 55

    4 Sex Ratio 926 829

    5 infant mortality rate 6.2%

    6 maternal mortality ratio 0.05%

    The table indicates poor socio economic conditions.

    Comparistion of Various Date of State and Projected Area

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    1 2 3 4 5 6

    Series1

    Series2

  • Table 2.3Land Use

    Land Use Total area in Ha.

    Private Panchayat Government Community Total

    Agriculture Land 2235 0 0 0 2235

    Temporary fallow 0 0 0 0 0

    Permanent Fallow 50 0 0 0 50

    Cultivated Rainfed 6280 0 1280 0 7560

    Cultivated irrigated 0 0 0 0 0

    Net Sown Area 1190 0 0 0 1190

    Net Area sown more than once 35 0 0 0 35

    Forest Land 0 0 20 0 20

    Waste Land 0 0 50 0 50

    Pastures 0.00 0 110 0 110

    Others 0 0 0 0 0

    Total 9790 0 1460 0 11250

    0

    1000

    2000

    3000

    4000

    5000

    6000

    7000

    8000

    9000

    Agr

    icul

    ture

    Land

    Per

    man

    ent

    Fallo

    w

    Cul

    tivat

    ed

    irrig

    ated

    Net

    Are

    a

    sow

    n m

    ore

    Was

    te

    Land

    Oth

    ers

    Private

    Panchayat

    Government

  • The project area has 950 ha of cultivable wasteland . 450 ha of fallow land (total 1400 ha) can

    be brought under cultivation if some irrigation source can be provided through Construction of

    WHS like Khadin, Tanka, Farm ponds etc. and also through demonstration of rainfed

    varieties of crops. Construction of WHS can also increase in area under irrigation which is only

    2560 ha is under wastelands and can be brought under vegetative cover, with reasonable effort

    .Activities like Earthen check dams, Vegetative filter strip, V- ditches, staggered trenches ,WHS

    (Johad) Afforestation of wastelands and Pasture development will be taken up on these lands

    Pasture development the land use table shows that there is 550 hectare pasture land

    (5.50%)This emphasizes the need for taking up pastureland development works through sowing

    of promising species of grasses and plantation

    Table 2.4 .a Agriculture and Horticulture status and fuel availability.

    Cropping Status S.

    No

    Season Crop

    sown

    Rain fed Irrigated Total

    Varieties Area

    (ha)

    Production

    (Ton)

    Productiv

    ity

    (kg/ha)

    Varietie

    s

    Area

    (ha)

    Produc

    tion

    (Ton)

    Produc

    tivity

    (kg/ha)

    Area

    (ha)

    Product

    ion

    (Ton)

    1 Kharif Bajra HHB 67 3115 1105 355 - - - - 1105 355

    Moong K851 980 509 520 - - - - 509 520

    Guar 2185 1235 565 1235 565

    2 Rabi Mustured - 215 205 955 - - - - 205 955

    Table 2.4.b Abstract of cropped Area(ha)

    Area under Single crop 6280

    Area under Double crop 215

    Area under Multiple crop 0

    **Write for each crop: The farmers are using WCC 75 ,Raj. 171, varieties of Bajra, whereas

    varieties like HHB 67 , RCB2 can increase the production.

  • The table 2.3 shows that only 1135 ha is double cropped area. Also the crop rotation shows

    that fallow lands are there. This indicates that there is scope for change in crop rotation in

    fields where there are fallow lands through Soil and Water conservation measures, crop

    demonstration and diversification in agriculture.

    Soil and Water conservation measures besides putting fallow lands under cultivation

    can change the area under single cropping to double and multiple cropping.

    Table 2.4.c Productivity Gap Analysis (The table can also be given in bar chart form)

    Name of the crop

    Productivity kg/ha

    India

    Highest Average

    in Rajasthan

    Highest Average of

    Agro climatic

    zone

    District Project Area

    Bajara - 339 500 415 355

    Guar - 476 600 550 520

    Moong 886 679 750 625 565

    Mustared 1095 1203 1250 980 955

    Analysis of the above table indicate that besides national gap there is wide gap in

    productivity within state and even within same agro climatic zones.

    The reasons for this variation are

    • The farmers are using local seeds & varieties like WBC-75,Raj.171 of Bajra, and Maru

    Guar for cultivation of Guar Whereas the recommended varieties for Bajara are RHB

    58, RHB-121 HHB 67 for Moong RMG-62 & K-851 for Guar RBC-936 & RBC-986 to

    provide more yield.

    • Lack of Availability of good quality seeds of desired crop and variety in adequate

    quantities and time to the farmers.

    • Availability of water for cultivation

    The productivity gap and reasons of it indicate potential to increase the productivity through

    crop demonstration .Crop demonstrations would be carried out on improved crops/ varieties,

    improved agronomic practices. INM, IPM, Mixed cropping, distribution of fodder seed mini

    kit. Demonstration of improved methods and economics of fodder crops cultivation and also

    distribution foundation seeds of Forage Crops for further multiplication, introduction of fodder

    crops in the existing crop rotations.

  • Table 2.5 Existing area under horticulture/Vegetables/Floriculture (ha)

    Activity Area Species Varieties Recommended varieties

    Production

    Horticulture - - - - -

    Vegetables - - - - -

    Floriculture - - - - -

    Medicinal Plants

    - - - - -

    Table 2.6 Land holding Pattern in project area

    Type of Farmer

    Total House holds

    Land holding (ha) irrigation source wise

    Land holding (ha)Social group wise

    Irrigated (source)

    Rain fed

    Total Gen SC ST OBC BPL

    (i)Large farmer

    62 0 9454 9454 4215 415 535 4285 4

    (ii) Small farmer

    82 0 80 80 28 12 13 22 5

    (iii) Marginal farmer

    324 0 136 136 13 14 24 54 31

    (iv) Landless person

    164 0 0 0 0 0 0 0 0

    (V)No. of BPL households

    397 0 120 120 12 27 32 13 36

    Total 1029 0 9790 9790 4268 468 604 4374 76

  • Table 2.7 Livestock Status - animals/milk production / average yield.

    S.No .

    Description of animals

    Population in No.

    Yield(milk/mutton/ Wool)

    Equ. cow units

    Dry matter requirement per year (7Kg per animal.)

    Total requirement in M.T.

    1 Cows

    Indigenous 2800 3.5 ltr. per day 2800 7154000 7154

    Hybrid 125 - 125 319375 319

    2 Buffaloes 29 6 ltr. per day 29 74095 74

    3 Goat 7350 1 ltr. per day 3675 18779250 18779

    4 Sheep 12000 1 to 1½ Kg per no. 6000 6570000 6570

    5 Camel 285 - 285 728175 728

    6 Poultry 0 750 Grm per bird 0 0 0

    7 Piggery 0 - 0 0 0

    Total 22589 - 12914 33624895 33624

  • In spite of the large number of livestock, production is less hence increase in productivity

    across all species, is a major challenge. To reduce production of unproductive cattle and

    improve the productivity by improving the breeds by breeding management following

    activities will be taken up

    • Castration

    • Artificial insemination

    • Distribution of superior Breeding bulls for use in Cattle,Buffalo, shee & Goat

    • Breeding distribution crossbred rams

    Besides breed improvement other animal husbandry practices like better health, hygiene

    and feeding practices can increase productivity of livestock. Hence Activities like Animal

    health camps ,Urea-Molasses treatment demonstration ,demonstration of improved methods

    of conservation and utilization of Forage crops are proposed.

    Table 2.8 Existing area under fodder (ha)

    S.No Item Unit Area/Quantity

    1 Existing Cultivable area under Fodder Ha 2150/14850

    2 Production of Green fodder

    Tonns/year 0/0

    3 Production of Dry fodder Tonns/ Year 2150/14850

    4 Area under Pastures Ha 550/3150

    5 Production of fodder Tonns/year 2700/18000

    6 Existing area under Fuel wood

    Ha -

    7 Supplementary feed Kgs/ day -

    8 Silage Pits No -

    9 Availability of fodder Ton 18000

    i.Requirement of fodder= 33624 tonns ii. Availability of fodder = 18000 tonns.

    Deficiency of fodder = 33624-18000= 15624 tonns. The table above shows there is fodder deficiency (Requirement is 33624 tonns and

    Availability 18000 tonns) is15624 tonns.

    To minimize the large and expanding gap between feed and fodder resource availability

    and demand there is need for

  • • Increase in area under fodder crops

    • Increase in productivity of fodder crops

    • Development of pastures • And reduction in large number of livestock production through replacement by few but

    productive animals

    Table 2.9 Farm implements

    S. No Implements Nos.

    1 Tractor 44

    2 Sprayers-manual/ power 85

    3 Cultivators/Harrows 44

    4 Seed drill 0

    5 Any Other 24

    Farm mechanization and seed banks: As discussed earlier 36% land holdings belong

    to small and marginal farmers who own only 31% of total cultivated area so owning of big

    farm implements by individual farmers is not economical so SHG would be promoted to

    buy farm implements and rent to farmer

  • Table 2.10 NREGA Status - No. of Card Holder, activities taken so far,

    employment status.

    Sr. no.

    Name of village Total No .of job

    cards Employment

    Status Activity taken up so

    far

    1 Bhakhri 330 4920000

    Nadi,Tanka,Greval road,Bunding

    2 Padroda 224 3300000

    3 Bhandhewa 320 4800000

    4 Sanga bera 73 1095000

    5 Shakti Fozdar Nagar

    72 1070000

    6 Jetpura 350 2230000

    7 Roopsar 250 3650000

    8 Bhikhodai nai 189 2815000

    9 Kerawa 185 2755000

    0

    1000000

    2000000

    3000000

    4000000

    5000000

    6000000

    Bhak

    hri

    Padr

    oda

    Bhan

    dhew

    a

    Sang

    a be

    ra

    Shak

    ti Fo

    zdar

    Nag

    ar

    Jetp

    ura

    Roop

    sar

    Bhikh

    odai

    nai

    Kera

    wa

    Total No .of job cards

    Employment Status

  • Table 2.11 Migration Details

    Name of village

    No. of

    persons

    migrating

    No. of days per

    year of

    migration

    Major reason(s)

    for migrating

    Distance of

    destination of

    migration from

    the village (km)

    Occupation

    during migration

    Income from

    such occupation

    (Rs. in lakh)

    Bhakhri 15 280

    Employment

    & Business 150-2000

    Employment

    & Business

    24

    Padroda 06 280 08

    Bhandhewa 12 280 15

    Sanga bera 00 280 00

    Shakti Fozdar

    Nagar

    00 0 0

    Jetpura 11 280 14

    Roopsar 16 280 19

    Bhikhodai nai 14 280 17

    Kerawa

    The migration can be checked by creation of employment opportunities, enhancing farm level economy, increase in the income of the people engaged in animal husbandry by dairy and marketing and value addition. (As discussed earlier) and diversification in livelihoods .

    Chart of migrate person & person days

    0

    50

    100

    150

    200

    250

    300

    Bha

    khri

    Pad

    roda

    Bha

    ndhe

    wa

    San

    ga b

    era

    Sha

    kti F

    ozda

    r Nag

    ar

    Jetp

    ura

    Roo

    psar

    Bhikh

    odai n

    ai

    Ker

    awa

    No. of persons migrating

    No. of days per year of

    migration

  • Livelihood Details

    Table 2.12 (a)Major activities (On Farm)

    Name of activity No of House holds Average annual income from the

    cultivators 965 835 lac

    Dairying 165 16 lac

    Poultry - -

    Piggery - -

    Landless Agri. Labourers 64 24lac

  • Table 2.12(b)Major activities (Off Farm)

    Name of activity

    Households/individuals Average annual income from

    the

    Artisans - -

    Carpenter 32 3.46 Lac

    Blacksmith 3 0.75

    Leather Craft - - Porter 36 1.40

    Mason 88 4.25

    Others specify (Cycle Repair ,STD,Craft etc)

    - -

    The efforts for increase in income through off farm activities will be made under livelihood component through assistance to SHG or individuals

    Table 2.13( a ) Status of Existing SHG

    S.No Name of SHG

    Members Activity involved

    Monthly income

    Fund avai.

    Assistance available

    Source of assistance

    Training receive

    1 kalam 10 - Bank Loan Z.P.Jaisalmer Yes

    2 Aakash 10 - Bank Loan Z.P.Jaisalmer Yes

    3 Maa Jasol 10 - Bank Loan Z.P.Jaisalmer Yes

    4 Mahatma Gandhi

    10 - Bank Loan Z.P.Jaisalmer Yes

    5 Mohan 10 - Bank Loan Z.P.Jaisalmer Yes

    6 Sugan 10 - Bank Loan Z.P.Jaisalmer Yes

    7 Jetoni 10 - Bank Loan Z.P.Jaisalmer Yes

    8 Kali bai 10 - Bank Loan Z.P.Jaisalmer Yes

    9 Sabri bai 10 - Bank Loan Z.P.Jaisalmer Yes

    10 Gomatiya 10 - Bank Loan Z.P.Jaisalmer Yes

    11 Madni 10 - Bank Loan Z.P.Jaisalmer Yes

    The table indicates existence of number of groups in the area also these need to be strengthened through trainings and financial assistance

    II. Technical Features

    Table 2.14 Ground Water Details

    S.No Source No. Functional depth(meter )

    Dry Area irrigated

    Water availability (days)

    i) Dug wells 0 0 0 - -

    ii) Shallow tube wells - - - - -

    iii) Pumping sets - - - - -

    iv) Deep Tube Wells 24 150-200 - 0 365 days

    Total 24 - - - -

  • Table 2.15 Availability of drinking water Sl No. Name of

    the Village

    Drinking

    water

    requirement

    ltrs/ day

    Present

    availability

    of drinking

    water

    ltrs/day

    No of

    drinking

    water

    sources

    available

    No

    functional

    No

    requires

    repairs

    No

    defunct

    1 Bhakhri

    7500 6000 2 2

    2 Padroda

    6000 5000 1 1

    3 Bhandhewa

    10000 8000 2 2

    4 Sanga bera

    2500 2000 1 1

    5 Shakti Fozdar

    Nagar

    2000 2000 1 1

    6 Jetpura

    3000 3000 1 1

    7 Roopsar

    9000 8000 2 2

    8 Bhikhodai nai

    6000 5000 1 1

    9 Kerawa

    5000 4000 1 1

    Chart of Drinking water requirement and

    present availability of drinkings water

    0

    2000

    4000

    6000

    8000

    10000

    12000

    Bha

    khri

    Pad

    roda

    Bha

    ndhe

    wa

    San

    ga b

    era

    Sha

    kti F

    ozda

    r Nag

    ar

    Jetp

    ura

    Roo

    psar

    Bhikh

    odai n

    ai

    Ker

    awa

    Drinking water

    requirement ltrs/ day

    Present availability of

    drinking water ltrs/day

  • Table 2.16 Water Use efficiency

    Name of major crop

    Area (Hectare)

    through water saving

    devices(Drip/S prinklers)

    through water

    conserving agronomic

    practices#

    Any other (pl. specify)

    Total

    Mustard 60% 20% - -

    Zeera 60% 20% - -

    • The tables above indicate need for judicious use of available Water.

    • Encouraging optimum use of water through installation of sprinklers on every operational wells

  • Table 2.17 Slope details.

    Slope of Watershed

    S.No. Slope percentage Area in hectares

    1 0 to 3% 11250

    2 3 to 8% -

    3 8 to 25% -

    4 > 25% -

    As most of the area has slope less than 3% construction of contour bunds can solve the problem of water erosion in agriculture fields and protect washing of top soil and manures/fertilizers

  • CHAPTER – III

    Proposed Development Plan: The Activities are indicative addition /deletion in activities will be as per local conditions

    A) Preparatory phase activities Capacity Building Trainings and EPA

    The IEC activities like Kalajathas, Group meetings, door to door campaign, slogans and

    wall writings etc. were carried out in all the habitations of Jaisalmer (IWMP) VIII

    Micro Watershed. A series of meetings were conducted with Gram Panchayat members,

    community and discussed about the implementation of IWMP programme. User groups

    were also formed.

    Grama Sabhas were conducted for approval of EPA (Village), for selecting the

    watershed committee and approval of DPR.

    S.no Name of the Gram Panchayat

    Date on which Grama Sabha approved EPA

    1 Bhakhri 15.10.2010

    2 Padroda 02.10.2010

    3 Bhandhewa 07.10.2010

    4 Sanga bera 20.10.2010

    5 Shakti Fozdar Nagar 20.10.2010

    6 Jetpura 29.10.2010

    7 Roopsar 29.10.2010

    8 Bhikhodai nai 15.10.2010

    9 Kerawa 18.10.2010

  • S. No.

    Names of village

    Amount earmarked for EPA

    Entry Point Activities planned

    Estimated cost

    Expenditure incurred Balance

    Expected outcome

    Actual outcome

    1 Bhakhri 9.00 18 9.00 9.00 0 9.00 9.00

    2 Padroda 6.00

    12 6.00 6.00

    0 6.00 6.00

    3 Bhandhewa 6.00

    12 6.00 6.00

    0 6.00 6.00

    4 Sanga bera 3.00

    06 3.00 3.00

    0 3.00 3.00

    5 Shakti Fozdar Nagar

    6.00 12

    6.00 6.00 0

    6.00 6.00

    6 Jetpura 6.00

    12 6.00 6.00

    0 6.00 6.00

    7 Roopsar 9.00

    18 9.00 9.00

    0 9.00 9.00

    8 Bhikhodai nai 9.00

    18 9.00 9.00

    0 9.00 9.00

    9 Kerawa 6.00

    12 6.00 6.00

    0 6.00 6.00

    The PRA exercise was carried out in all the villages on the dates shown below:

    S.no Name of the village/Habitation

    Date on which PRA conducted

    1 Bhakhri 14.06.2011

    2 Padroda 07.06.2011

    3 Bhandhewa 22.05.2011

    4 Sanga bera 15.07.2011

    5 Shakti Fozdar Nagar 10.08.2011

    6 Jetpura 18.07.2011

    7 Roopsar 09.05.2011

    8 Bhikhodai nai 11.05.2011

    9 Kerawa -

  • Transact walk were carried out involving the community for Social mapping, Resource

    mapping. detailed discussions and deliberations with all the primary stakeholders were carried

    out.

    Socio-economic survey was carried out during 28-3-2011 (dates) period covering all the

    households and primary data on demography, Land holdings, Employment status, Community

    activities etc. was collected as mentioned in chapter 2.

    State remote sensing department was assigned the work of preparing various

    thematic layers using Cartosat-1 and LISS-3 imageries for Creation, development and

    management of geo-spatial database depicting present conditions of land (terrain), water and

    vegetation with respect to watershed under different ownerships at village level

    Various thematic layers provided by SRSAC are :

    • Digitised Khasara maps of the villages falling in project area.

    • Network of Drainage lines, existing water bodies, falling in the project area.

    • Base maps (transport network, village/boundaries, and settlements).

    • Land Use / Land cover map.

    • Contours at 1 meter interval, slope map

    Based on GIS thematic layers, Field visits , PRA and analysis of benchmark data (as

    discussed in chapter 2) final Treatment plan on revenue map for implementation has been

    framed. Thus each intervention identified has been marked on revenue map (map enclosed

    in DPR as annexure------).The GIS based intervention map, PRA based intervention map are

    annexed as ------.

    .

  • s

  • (A)

    Quanitiy Total CostCost From Project

    Fund

    Convergen

    ce Fund

    Beneficiary

    Contribution

    Admn. 10% - 0 150.00 150.00 0.00 0.00

    Monitoring 1% - 0 15.00 15.00 0.00 0.00

    Evaluation 1% - 0 15.00 15.00 0.00 0.00

    EPA 4% - 0 60.00 60.00 0.00 0.00

    I & CB 5% - 0 75.00 75.00 0.00 0.00

    DPR 1% - 0 15.00 15.00 0.00 0.00

    Total (A) 330.00 330.00 0 0

    (B)

    Earthen Bund Mtr 139 13570 18.86 18.86 0.00 1.41

    Tanka Num. 50000 376 188.00 188.00 0.00 14.10

    dhora (Small) Num. 200000 93 186.00 186.00 0.00 13.95

    khadeen Num. 300000 101 303.00 303.00 0.00 22.73

    Khet talai Num. 350000 21 73.50 73.50 0.00 5.51

    Bank Stabilisation/

    Peripheral BundsMtr 0 0 0.00 0.00 0.00 0.00

    Pasture Development hact. 50000 98 49.00 49.00 0.00 3.68

    V- ditch Mtr 27.69 52880 14.64 14.64 0.00 1.10

    Water Harvesting Structure Num. 85000 13 11.05 11.05 0.00 0.83

    Afforestation hact. 50000 96 48.00 48.00 0.00 3.60

    MMS Num. 0 0 0.00 0.00 0.00 0.00

    LSCD Num. 15000 53 7.95 7.95 0.00 0.60

    WHS Num. 0 0 0.00 0.00 0.00 0.00

    Gully Plugs (ECD) Num. 0 0 0.00 0.00 0.00 0.00

    Ground water recharge

    StructureNum. 0 0 0.00 0.00 0.00 0.00

    Total (B) 900.00 900.00 0.00 67.50

    (C)

    Horticulture Plantation Num. 250 16490 41.23 24.74 16.49 7.42

    Sprinklers and Drip

    irrigationhact. 20000 197 39.30 39.30 0.00 11.79

    Floriculture Num. 0 0 0.00 0.00 0.00 0.00

    Vegetables Num. 0 0 0.00 0.00 0.00 0.00

    Medicinal Plants hact. 40000 35 14.02 8.41 5.61 2.52

    Vermi compost Num. 5000 97 4.85 4.85 0.00 1.46

    Crop Demonstration Num. 2000 1950 39.00 39.00 0.00 11.70

    Dairy Num. 1000 1980 19.80 19.80 0.00 5.94

    Annual Camp Num. 50000 56 28.00 28.00 0.00 8.40

    Poultry Num. 0 0 0.00 0.00 0.00 0.00

    Local Artisans/ crafts Num. 10000 48 4.80 4.80 0.00 1.44

    Animal Minral/ Mixar Num. 1000 1980 19.80 19.80 0.00 5.94

    SHG Land less/ BPL Num. 50000 22 11.00 11.00 0.00 3.30

    Food Processing Num. 1000 2530 25.30 25.30 0.00 7.59

    Total ( C) 247.10 225.00 22.10 67.50

    (D) Consolidation 45.00 45.00 0.00 0.00

    Total (D) 45.00 45.00 0.00 0.00

    Grand Total 1522.10 1500.00 22.10 135.00

    Conservation measures for arable land (private land)

    Conservation measures For non arable land

    Drainage line treatment

    Production measures for arable land

    Micro Enterprise

    PROPOSED DEVELOPMENT PLAN

    Unit Unit Cost

    Preparatory Phase activities capacity building trainings & EPA

    Activity

    Total

  • (A)

    Quanitiy Total CostCost From Project

    Fund

    Convergen

    ce Fund

    Beneficiary

    Contribution

    Admn. 10% - 0 37.50 37.50 0.00 0.00

    Monitoring 1% - 0 3.75 3.75 0.00 0.00

    Evaluation 1% - 0 3.75 3.75 0.00 0.00

    EPA 4% - 0 15.00 15.00 0.00 0.00

    I & CB 5% - 0 18.75 18.75 0.00 0.00

    DPR 1% - 0 3.75 3.75 0.00 0.00

    Total (A) 82.50 82.50 0 0

    (B)

    Earthen Bund Mtr 139 3600 5.00 5.00 0.00 0.38

    Tanka Num. 50000 100 50.00 50.00 0.00 3.75

    dhora (Small) Num. 200000 22 44.00 44.00 0.00 3.30

    khadeen Num. 300000 25 75.00 75.00 0.00 5.63

    Khet talai Num. 350000 5 17.50 17.50 0.00 1.31

    Bank Stabilisation/

    Peripheral BundsMtr 0 0 0.00 0.00 0.00 0.00

    Pasture Development hact. 50000 25 12.50 12.50 0.00 0.94

    V- ditch Mtr 27.69 12800 3.54 3.54 0.00 0.27

    Water Harvesting Structure Num. 85000 3 2.55 2.55 0.00 0.19

    Afforestation hact. 50000 25 12.50 12.50 0.00 0.94

    MMS Num. 0 0 0.00 0.00 0.00 0.00

    LSCD Num. 15000 16 2.40 2.40 0.00 0.18

    WHS Num. 0 0 0.00 0.00 0.00 0.00

    Gully Plugs (ECD) Num. 0 0 0.00 0.00 0.00 0.00

    Ground water recharge

    StructureNum. 0 0 0.00 0.00 0.00 0.00

    Total (B) 225.00 225.00 0.00 16.87

    (C)

    Horticulture Plantation Num. 250 4165 10.41 6.25 4.17 1.87

    Sprinklers and Drip

    irrigationhact. 20000 50 10.00 10.00 0.00 3.00

    Floriculture Num. 0 0 0.00 0.00 0.00 0.00

    Vegetables Num. 0 0 0.00 0.00 0.00 0.00

    Medicinal Plants hact. 40000 8.35 3.34 2.00 1.34 0.60

    Vermi compost Num. 5000 25 1.25 1.25 0.00 0.38

    Crop Demonstration Num. 2000 465 9.30 9.30 0.00 2.79

    Dairy Num. 1000 500 5.00 5.00 0.00 1.50

    Annual Camp Num. 50000 15 7.50 7.50 0.00 2.25

    Poultry Num. 0 0 0.00 0.00 0.00 0.00

    Local Artisans/ crafts Num. 10000 12 1.20 1.20 0.00 0.36

    Animal Minral/ Mixar Num. 1000 500 5.00 5.00 0.00 1.50

    SHG Land less/ BPL Num. 50000 5 2.50 2.50 0.00 0.75

    Food Processing Num. 1000 625 6.25 6.25 0.00 1.88

    Total ( C) 61.75 56.25 5.50 16.88

    (D) Consolidation 11.25 11.25 0.00 0.00

    Total (D) 11.25 11.25 0.00 0.00

    Grand Total 380.50 375.00 5.50 33.75

    PROPOSED DEVELOPMENT PLAN

    Unit Unit Cost

    Preparatory Phase activities capacity building trainings & EPA

    Activity

    Gram Panchayat Barath Ka Gaon

    Drainage line treatment

    Production measures for arable land

    Micro Enterprise

    Conservation measures for arable land (private land)

    Conservation measures For non arable land

  • (A)

    Quanitiy Total CostCost From Project

    Fund

    Convergen

    ce Fund

    Beneficiary

    Contribution

    Admn. 10% - 0.00 45.00 45.00 0.00 0.00

    Monitoring 1% - 0.00 4.50 4.50 0.00 0.00

    Evaluation 1% - 0.00 4.50 4.50 0.00 0.00

    EPA 4% - 0.00 18.00 18.00 0.00 0.00

    I & CB 5% - 0.00 22.50 22.50 0.00 0.00

    DPR 1% - 0.00 4.50 4.50 0.00 0.00

    Total (A) 99.00 99.00 0 0

    (B)

    Earthen Bund Mtr 139 3440.00 4.78 4.78 0.00 0.36

    Tanka Num. 50000 120.00 60.00 60.00 0.00 4.50

    dhora (Small) Num. 200000 27.00 54.00 54.00 0.00 4.05

    khadeen Num. 300000 30.00 90.00 90.00 0.00 6.75

    Khet talai Num. 350000 6.00 21.00 21.00 0.00 1.58

    Bank Stabilisation/

    Peripheral BundsMtr 0 0.00 0.00 0.00 0.00 0.00

    Pasture Development hact. 50000 30.00 15.00 15.00 0.00 1.13

    V- ditch Mtr 27.69 16500.00 4.57 4.57 0.00 0.34

    Water Harvesting Structure Num. 85000 4.00 3.40 3.40 0.00 0.26

    Afforestation hact. 50000 30.00 15.00 15.00 0.00 1.13

    MMS Num. 0 0.00 0.00 0.00 0.00 0.00

    LSCD Num. 15000 15.00 2.25 2.25 0.00 0.17

    WHS Num. 0 0.00 0.00 0.00 0.00 0.00

    Gully Plugs (ECD) Num. 0 0.00 0.00 0.00 0.00 0.00

    Ground water recharge

    StructureNum. 0 0.00 0.00 0.00 0.00 0.00

    Total (B) 270.00 270.00 0.00 20.25

    (C)

    Horticulture Plantation Num. 250 5000.00 12.50 7.50 5.00 2.25

    Sprinklers and Drip

    irrigationhact. 20000 60.00 12.00 12.00 0.00 3.60

    Floriculture Num. 0 0.00 0.00 0.00 0.00 0.00

    Vegetables Num. 0 0.00 0.00 0.00 0.00 0.00

    Medicinal Plants hact. 40000 10.00 4.00 2.40 1.60 0.72

    Vermi compost Num. 5000 30.00 1.50 1.50 0.00 0.45

    Crop Demonstration Num. 2000 555.00 11.10 11.10 0.00 3.33

    Dairy Num. 1000 600.00 6.00 6.00 0.00 1.80

    Annual Camp Num. 50000 18.00 9.00 9.00 0.00 2.70

    Poultry Num. 0 0.00 0.00 0.00 0.00 0.00

    Local Artisans/ crafts Num. 10000 15.00 1.50 1.50 0.00 0.45

    Animal Minral/ Mixar Num. 1000 600.00 6.00 6.00 0.00 1.80

    SHG Land less/ BPL Num. 50000 6.00 3.00 3.00 0.00 0.90

    Food Processing Num. 1000 750.00 7.50 7.50 0.00 2.25

    Total ( C) 74.10 67.50 6.60 20.25

    (D) Consolidation 13.50 13.50 0.00 0.00

    Total (D) 13.50 13.50 0.00 0.00

    Grand Total 456.60 450.00 6.60 40.50

    Conservation measures for arable land (private land)

    Conservation measures For non arable land

    Drainage line treatment

    Production measures for arable land

    Micro Enterprise

    PROPOSED DEVELOPMENT PLAN

    Unit Unit Cost

    Preparatory Phase activities capacity building trainings & EPA

    Activity

    Gram Panchayat Balar

  • (A)

    Quanitiy Total CostCost From Project

    Fund

    Convergen

    ce Fund

    Beneficiary

    Contribution

    Admn. 10% - 0 7.50 7.50 0.00 0.00

    Monitoring 1% - 0 0.75 0.75 0.00 0.00

    Evaluation 1% - 0 0.75 0.75 0.00 0.00

    EPA 4% - 0 3.00 3.00 0.00 0.00

    I & CB 5% - 0 3.75 3.75 0.00 0.00

    DPR 1% - 0 0.75 0.75 0.00 0.00

    Total (A) 16.50 16.50 0 0

    (B)

    Earthen Bund Mtr 139 260 0.36 0.36 0.00 0.03

    Tanka Num. 50000 20 10.00 10.00 0.00 0.75

    dhora (Small) Num. 200000 5 10.00 10.00 0.00 0.75

    khadeen Num. 300000 5 15.00 15.00 0.00 1.13

    Khet talai Num. 350000 1 3.50 3.50 0.00 0.26

    Bank Stabilisation/

    Peripheral BundsMtr 0 0 0.00 0.00 0.00 0.00

    Pasture Development hact. 50000 5 2.50 2.50 0.00 0.19

    V- ditch Mtr 27.69 2500 0.69 0.69 0.00 0.05

    Water Harvesting Structure Num. 85000 0 0.00 0.00 0.00 0.00

    Afforestation hact. 50000 5 2.50 2.50 0.00 0.19

    MMS Num. 0 0 0.00 0.00 0.00 0.00

    LSCD Num. 15000 3 0.45 0.45 0.00 0.03

    WHS Num. 0 0 0.00 0.00 0.00 0.00

    Gully Plugs (ECD) Num. 0 0 0.00 0.00 0.00 0.00

    Ground water recharge

    StructureNum. 0 0 0.00 0.00 0.00 0.00

    Total (B) 45.00 45.00 0.00 3.38

    (C)

    Horticulture Plantation Num. 250 830 2.08 1.25 0.83 0.37

    Sprinklers and Drip

    irrigationhact. 20000 10 2.00 2.00 0.00 0.60

    Floriculture Num. 0 0 0.00 0.00 0.00 0.00

    Vegetables Num. 0 0 0.00 0.00 0.00 0.00

    Medicinal Plants hact. 40000 1.66 0.66 0.40 0.27 0.12

    Vermi compost Num. 5000 5 0.25 0.25 0.00 0.08

    Crop Demonstration Num. 2000 120 2.40 2.40 0.00 0.72

    Dairy Num. 1000 100 1.00 1.00 0.00 0.30

    Annual Camp Num. 50000 2 1.00 1.00 0.00 0.30

    Poultry Num. 0 0 0.00 0.00 0.00 0.00

    Local Artisans/ crafts Num. 10000 2 0.20 0.20 0.00 0.06

    Animal Minral/ Mixar Num. 1000 50 0.50 0.50 0.00 0.15

    SHG Land less/ BPL Num. 50000 2 1.00 1.00 0.00 0.30

    Food Processing Num. 1000 125 1.25 1.25 0.00 0.38

    Total ( C) 12.34 11.24 1.10 3.37

    (D) Consolidation 2.25 2.25 0.00 0.00

    Total (D) 2.25 2.25 0.00 0.00

    Grand Total 76.09 75.00 1.10 6.75

    Conservation measures for arable land (private land)

    Conservation measures For non arable land

    Drainage line treatment

    Production measures for arable land

    Micro Enterprise

    PROPOSED DEVELOPMENT PLAN

    Unit Unit Cost

    Preparatory Phase activities capacity building trainings & EPA

    Activity

    Gram Panchayat Dantal

  • (A)

    Quanitiy Total CostCost From Project

    Fund

    Convergen

    ce Fund

    Beneficiary

    Contribution

    Admn. 10% - 0 15.00 15.00 0.00 0.00

    Monitoring 1% - 0 1.50 1.50 0.00 0.00

    Evaluation 1% - 0 1.50 1.50 0.00 0.00

    EPA 4% - 0 6.00 6.00 0.00 0.00

    I & CB 5% - 0 7.50 7.50 0.00 0.00

    DPR 1% - 0 1.50 1.50 0.00 0.00

    Total (A) 33.00 33.00 0 0

    (B)

    Earthen Bund Mtr 139 1870 2.60 2.60 0.00 0.19

    Tanka Num. 50000 37 18.50 18.50 0.00 1.39

    dhora (Small) Num. 200000 10 20.00 20.00 0.00 1.50

    khadeen Num. 300000 8 24.00 24.00 0.00 1.80

    Khet talai Num. 350000 3 10.50 10.50 0.00 0.79

    Bank Stabilisation/

    Peripheral BundsMtr 0 0 0.00 0.00 0.00 0.00

    Pasture Development hact. 50000 10 5.00 5.00 0.00 0.38

    V- ditch Mtr 27.69 6500 1.80 1.80 0.00 0.13

    Water Harvesting Structure Num. 85000 2 1.70 1.70 0.00 0.13

    Afforestation hact. 50000 10 5.00 5.00 0.00 0.38

    MMS Num. 0 0 0.00 0.00 0.00 0.00

    LSCD Num. 15000 6 0.90 0.90 0.00 0.07

    WHS Num. 0 0 0.00 0.00 0.00 0.00

    Gully Plugs (ECD) Num. 0 0 0.00 0.00 0.00 0.00

    Ground water recharge

    StructureNum. 0 0 0.00 0.00 0.00 0.00

    Total (B) 90.00 90.00 0.00 6.75

    (C)

    Horticulture Plantation Num. 250 1330 3.33 2.00 1.33 0.60

    Sprinklers and Drip

    irrigationhact. 20000 22.5 4.50 4.50 0.00 1.35

    Floriculture Num. 0 0 0.00 0.00 0.00 0.00

    Vegetables Num. 0 0 0.00 0.00 0.00 0.00

    Medicinal Plants hact. 40000 3.35 1.34 0.80 0.54 0.24

    Vermi compost Num. 5000 8 0.40 0.40 0.00 0.12

    Crop Demonstration Num. 2000 225 4.50 4.50 0.00 1.35

    Dairy Num. 1000 180 1.80 1.80 0.00 0.54

    Annual Camp Num. 50000 5 2.50 2.50 0.00 0.75

    Poultry Num. 0 0 0.00 0.00 0.00 0.00

    Local Artisans/ crafts Num. 10000 5 0.50 0.50 0.00 0.15

    Animal Minral/ Mixar Num. 1000 200 2.00 2.00 0.00 0.60

    SHG Land less/ BPL Num. 50000 2 1.00 1.00 0.00 0.30

    Food Processing Num. 1000 250 2.50 2.50 0.00 0.75

    Total ( C) 24.37 22.50 1.87 6.75

    (D) Consolidation 4.50 4.50 0.00 0.00

    Total (D) 4.50 4.50 0.00 0.00

    Grand Total 151.86 150.00 1.87 13.50

    Conservation measures for arable land (private land)

    Conservation measures For non arable land

    Drainage line treatment

    Production measures for arable land

    Micro Enterprise

    PROPOSED DEVELOPMENT PLAN

    Unit Unit Cost

    Preparatory Phase activities capacity building trainings & EPA

    Activity

    Gram Panchayat Didaniya

  • (A)

    Quanitiy Total CostCost From Project

    Fund

    Convergen

    ce Fund

    Beneficiary

    Contribution

    Admn. 10% - 0 15.00 15.00 0.00 0.00

    Monitoring 1% - 0 1.50 1.50 0.00 0.00

    Evaluation 1% - 0 1.50 1.50 0.00 0.00

    EPA 4% - 0 6.00 6.00 0.00 0.00

    I & CB 5% - 0 7.50 7.50 0.00 0.00

    DPR 1% - 0 1.50 1.50 0.00 0.00

    Total (A) 33.00 33.00 0 0

    (B)

    Earthen Bund Mtr 139 1500 2.09 2.09 0.00 0.16

    Tanka Num. 50000 29 14.50 14.50 0.00 1.09

    dhora (Small) Num. 200000 10 20.00 20.00 0.00 1.50

    khadeen Num. 300000 12 36.00 36.00 0.00 2.70

    Khet talai Num. 350000 2 7.00 7.00 0.00 0.53

    Bank Stabilisation/

    Peripheral BundsMtr 0 0 0.00 0.00 0.00 0.00

    Pasture Development hact. 50000 8 4.00 4.00 0.00 0.30

    V- ditch Mtr 27.69 4580 1.27 1.27 0.00 0.10

    Water Harvesting Structure Num. 85000 2 1.70 1.70 0.00 0.13

    Afforestation hact. 50000 6 3.00 3.00 0.00 0.23

    MMS Num. 0 0 0.00 0.00 0.00 0.00

    LSCD Num. 15000 3 0.45 0.45 0.00 0.03

    WHS Num. 0 0 0.00 0.00 0.00 0.00

    Gully Plugs (ECD) Num. 0 0 0.00 0.00 0.00 0.00

    Ground water recharge

    StructureNum. 0 0 0.00 0.00 0.00 0.00

    Total (B) 90.00 90.00 0.00 6.75

    (C)

    Horticulture Plantation Num. 250 1500 3.75 2.25 1.50 0.68

    Sprinklers and Drip

    irrigationhact. 20000 19 3.80 3.80 0.00 1.14

    Floriculture Num. 0 0 0.00 0.00 0.00 0.00

    Vegetables Num. 0 0 0.00 0.00 0.00 0.00

    Medicinal Plants hact. 40000 3.34 1.34 0.80 0.53 0.24

    Vermi compost Num. 5000 9 0.45 0.45 0.00 0.14

    Crop Demonstration Num. 2000 200 4.00 4.00 0.00 1.20

    Dairy Num. 1000 175 1.75 1.75 0.00 0.53

    Annual Camp Num. 50000 5 2.50 2.50 0.00 0.75

    Poultry Num. 0 0 0.00 0.00 0.00 0.00

    Local Artisans/ crafts Num. 10000 4 0.40 0.40 0.00 0.12

    Animal Minral/ Mixar Num. 1000 250 2.50 2.50 0.00 0.75

    SHG Land less/ BPL Num. 50000 3 1.50 1.50 0.00 0.45

    Food Processing Num. 1000 255 2.55 2.55 0.00 0.77

    Total ( C) 24.54 22.50 2.03 6.75

    (D) Consolidation 4.50 4.50 0.00 0.00

    Total (D) 4.50 4.50 0.00 0.00

    Grand Total 152.04 150.00 2.03 13.50

    Conservation measures for arable land (private land)

    Conservation measures For non arable land

    Drainage line treatment

    Production measures for arable land

    Micro Enterprise

    PROPOSED DEVELOPMENT PLAN

    Unit Unit Cost

    Preparatory Phase activities capacity building trainings & EPA

    Activity

    Gram Panchayat Pannasar

  • (A)

    Quanitiy Total CostCost From Project

    Fund

    Convergen

    ce Fund

    Beneficiary

    Contribution

    Admn. 10% - 0 15.00 15.00 0.00 0.00

    Monitoring 1% - 0 1.50 1.50 0.00 0.00

    Evaluation 1% - 0 1.50 1.50 0.00 0.00

    EPA 4% - 0 6.00 6.00 0.00 0.00

    I & CB 5% - 0 7.50 7.50 0.00 0.00

    DPR 1% - 0 1.50 1.50 0.00 0.00

    Total (A) 33.00 33.00 0 0

    (B)

    Earthen Bund Mtr 139 1450 2.02 2.02 0.00 0.15

    Tanka Num. 50000 40 20.00 20.00 0.00 1.50

    dhora (Small) Num. 200000 9 18.00 18.00 0.00 1.35

    khadeen Num. 300000 10 30.00 30.00 0.00 2.25

    Khet talai Num. 350000 2 7.00 7.00 0.00 0.53

    Bank Stabilisation/

    Peripheral BundsMtr 0 0 0.00 0.00 0.00 0.00

    Pasture Development hact. 50000 10 5.00 5.00 0.00 0.38

    V- ditch Mtr 27.69 5000 1.38 1.38 0.00 0.10

    Water Harvesting Structure Num. 85000 1 0.85 0.85 0.00 0.06

    Afforestation hact. 50000 10 5.00 5.00 0.00 0.38

    MMS Num. 0 0 0.00 0.00 0.00 0.00

    LSCD Num. 15000 5 0.75 0.75 0.00 0.06

    WHS Num. 0 0 0.00 0.00 0.00 0.00

    Gully Plugs (ECD) Num. 0 0 0.00 0.00 0.00 0.00

    Ground water recharge

    StructureNum. 0 0 0.00 0.00 0.00 0.00

    Total (B) 90.00 90.00 0.00 6.75

    (C)

    Horticulture Plantation Num. 250 1665 4.16 2.50 1.67 0.75

    Sprinklers and Drip

    irrigationhact. 20000 20 4.00 4.00 0.00 1.20

    Floriculture Num. 0 0 0.00 0.00 0.00 0.00

    Vegetables Num. 0 0 0.00 0.00 0.00 0.00

    Medicinal Plants hact. 40000 3.35 1.34 0.80 0.54 0.24

    Vermi compost Num. 5000 10 0.50 0.50 0.00 0.15

    Crop Demonstration Num. 2000 185 3.70 3.70 0.00 1.11

    Dairy Num. 1000 200 2.00 2.00 0.00 0.60

    Annual Camp Num. 50000 6 3.00 3.00 0.00 0.90

    Poultry Num. 0 0 0.00 0.00 0.00 0.00

    Local Artisans/ crafts Num. 10000 5 0.50 0.50 0.00 0.15

    Animal Minral/ Mixar Num. 1000 200 2.00 2.00 0.00 0.60

    SHG Land less/ BPL Num. 50000 2 1.00 1.00 0.00 0.30

    Food Processing Num. 1000 250 2.50 2.50 0.00 0.75

    Total ( C) 24.70 22.50 2.20 6.75

    (D) Consolidation 4.50 4.50 0.00 0.00

    Total (D) 4.50 4.50 0.00 0.00

    Grand Total 152.20 150.00 2.20 13.50

    Conservation measures for arable land (private land)

    Conservation measures For non arable land

    Drainage line treatment

    Production measures for arable land

    Micro Enterprise

    PROPOSED DEVELOPMENT PLAN

    Unit Unit Cost

    Preparatory Phase activities capacity building trainings & EPA

    Activity

    Gram Panchayat Swamiji ki Dhani

  • (A)

    Quanitiy Total CostCost From Project

    Fund

    Convergen

    ce Fund

    Beneficiary

    Contribution

    Admn. 10% - 0 15.00 15.00 0.00 0.00

    Monitoring 1% - 0 1.50 1.50 0.00 0.00

    Evaluation 1% - 0 1.50 1.50 0.00 0.00

    EPA 4% - 0 6.00 6.00 0.00 0.00

    I & CB 5% - 0 7.50 7.50 0.00 0.00

    DPR 1% - 0 1.50 1.50 0.00 0.00

    Total (A) 33.00 33.00 0 0

    (B)

    Earthen Bund Mtr 139 1450 2.02 2.02 0.00 0.15

    Tanka Num. 50000 30 15.00 15.00 0.00 1.13

    dhora (Small) Num. 200000 10 20.00 20.00 0.00 1.50

    khadeen Num. 300000 11 33.00 33.00 0.00 2.48

    Khet talai Num. 350000 2 7.00 7.00 0.00 0.53

    Bank Stabilisation/

    Peripheral BundsMtr 0 0 0.00 0.00 0.00 0.00

    Pasture Development hact. 50000 10 5.00 5.00 0.00 0.38

    V- ditch Mtr 27.69 5000 1.38 1.38 0.00 0.10

    Water Harvesting Structure Num. 85000 1 0.85 0.85 0.00 0.06

    Afforestation hact. 50000 10 5.00 5.00 0.00 0.38

    MMS Num. 0 0 0.00 0.00 0.00 0.00

    LSCD Num. 15000 5 0.75 0.75 0.00 0.06

    WHS Num. 0 0 0.00 0.00 0.00 0.00

    Gully Plugs (ECD) Num. 0 0 0.00 0.00 0.00 0.00

    Ground water recharge

    StructureNum. 0 0 0.00 0.00 0.00 0.00

    Total (B) 90.00 90.00 0.00 6.75

    (C)

    Horticulture Plantation Num. 250 2000 5.00 3.00 2.00 0.90

    Sprinklers and Drip

    irrigationhact. 20000 15 3.00 3.00 0.00 0.90

    Floriculture Num. 0 0 0.00 0.00 0.00 0.00

    Vegetables Num. 0 0 0.00 0.00 0.00 0.00

    Medicinal Plants hact. 40000 5 2.00 1.20 0.80 0.36

    Vermi compost Num. 5000 10 0.50 0.50 0.00 0.15

    Crop Demonstration Num. 2000 200 4.00 4.00 0.00 1.20

    Dairy Num. 1000 225 2.25 2.25 0.00 0.68

    Annual Camp Num. 50000 5 2.50 2.50 0.00 0.75

    Poultry Num. 0 0 0.00 0.00 0.00 0.00

    Local Artisans/ crafts Num. 10000 5 0.50 0.50 0.00 0.15

    Animal Minral/ Mixar Num. 1000 180 1.80 1.80 0.00 0.54

    SHG Land less/ BPL Num. 50000 2 1.00 1.00 0.00 0.30

    Food Processing Num. 1000 275 2.75 2.75 0.00 0.83

    Total ( C) 25.30 22.50 2.80 6.75

    (D) Consolidation 4.50 4.50 0.00 0.00

    Total (D) 4.50 4.50 0.00 0.00

    Grand Total 152.80 150.00 2.80 13.50

    Conservation measures for arable land (private land)

    Conservation measures For non arable land

    Drainage line treatment

    Production measures for arable land

    Micro Enterprise

    PROPOSED DEVELOPMENT PLAN

    Unit Unit Cost

    Preparatory Phase activities capacity building trainings & EPA

    Activity

    Gram Panchayat Bhandewa

  • s

  • Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin

    Admn. 10% 0% 150.00 150.00 0 15.00 0 15.00 0 45.00 0 36.00 0 24.00 0 15.00 0 150.00

    Monitoring 1% 0% 15.00 15.00 0 1.50 0 1.50 0 3.00 0 3.00 0 3.00 0 3.00 0 15.00

    Evaluation 1% 0% 15.00 15.00 0 2.25 0 2.25 0 2.70 0 2.55 0 2.70 0 2.55 0 15.00

    EPA 4% 0% 60.00 60.00 0 60.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 60.00

    I & CB 5% 0% 75.00 75.00 0 22.50 0 22.50 0 11.25 0 11.25 0 3.75 0 3.75 0 75.00

    DPR 1% 0% 15.00 15.00 0 15.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 15.00

    Total (A) 330.00 116.25 41.25 61.95 52.80 33.45 24.30 330.00

    Earthen Bund Mtr 13570 0.01 18.86 975 1.36 1825 2.54 3595 5.00 4985 6.93 1785 2.48 1235 1.72 14400 20.02

    Tanka Num. 376 3.50 188.00 19 9.50 32 16.00 72 36.00 110 55.00 93 46.50 55 27.50 381 190.50

    Dhora Num. 93 14.00 186.00 7 14.00 10 20.00 22 44.00 28 56.00 17 34.00 10 20.00 94 188.00

    Khadin Num. 101 21.00 303.00 3 9.00 3 9.00 23 69.00 34 102.00 20 60.00 16 48.00 99 297.00

    Khet Talai Num. 21 24.50 73.50 1 3.50 1 3.50 5 17.50 6 21.00 5 17.50 2 7.00 20 70.00

    Bank Stabilization /Peripheral Bunds Mtr 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Conservation measures for non arable land

    Pasture Development hact. 98 3.50 49.00 6 3.00 11 5.25 21 10.38 32 15.75 21 10.63 10 5.00 100 50.00

    V - ditch Mtr 52880 0.00 14.64 3425 0.95 10175 2.82 12650 3.50 17450 4.83 6250 1.73 4350 1.20 54300 15.04

    Water Harvesting Structure Num. 13 5.95 11.05 0 0.00 1 0.85 6 5.10 4 3.40 2 1.70 0 0.00 13 11.05

    Afforestation hact. 96 3.50 48.00 7 3.25 12 5.75 22 11.00 29 14.50 19 9.38 12 6.13 100 50.00

    Drainage line treatment MMS Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    LSCD Num. 53 1.05 7.95 6 0.90 9 1.35 13 1.95 16 2.40 8 1.20 4 0.60 56 8.40

    WHS Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Gully Plugs(ECD) Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Ground water recharge Structure Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Total (B) 900.00 45.45 67.05 203.42 281.81 185.11 117.15 900.00

    Horticulture plantation (vegetable,Medicine) Num. 16490 0.01 24.74 575 0.86 1235 1.85 3850 5.78 6360 9.54 2680 4.02 1790 2.69 16490 24.74

    Sprinklers and Drip irrigation hact. 196.5 1.40 39.30 8 1.60 19 3.80 55 11.00 86 17.20 19 3.70 10 2.00 197 39.30

    foriculture Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Vegetables Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Medicinal Plants hact. 35.05 1.68 8.41 1 0.29 5 1.09 9 2.22 13 3.06 5 1.14 3 0.61 35 8.41

    Vermi compost Num. 97 0.35 4.85 9 0.45 19 0.95 23 1.15 27 1.35 13 0.65 6 0.30 97 4.85

    Crop Demonstration Num. 1950 0.14 39.00 87 1.74 200 4.00 540 10.80 740 14.80 226 4.52 157 3.14 1950 39.00

    Micro Enterprise

    Dairy Num. 1980 0.07 19.80 67 0.67 101 1.01 575 5.75 742 7.42 318 3.18 177 1.77 1980 19.80

    Animal camp/Breed improovement Num. 56 3.50 28.00 2 1.00 7 3.50 18 9.00 22 11.00 5 2.50 2 1.00 56 28.00

    Poultry Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Local Artisans/craft Num. 48 0.70 4.80 2 0.20 7 0.70 13 1.30 16 1.60 8 0.80 2 0.20 48 4.80

    Animal Minral/ Mixar Num. 1980 0.07 19.80 148 1.48 270 2.70 487 4.87 680 6.80 237 2.37 158 1.58 1980 19.80

    SHG Land less/ BPL Num. 22 3.50 11.00 0 0.00 1 0.50 8 4.00 9 4.50 3 1.50 1 0.50 22 11.00

    Food Processing Num. 2530 0.07 25.30 55 0.55 105 1.05 635 6.35 1050 10.50 420 4.20 265 2.65 2530 25.30

    Total (C) 225.00 8.84 21.15 62.22 87.77 28.58 16.44 225.00

    (D) Consolidation 3% 0.00 45.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 45.00 0 45.00Grand Total 1500.00 170.54 129.46 327.59 422.38 247.14 202.88 1500.00

    Conservation measures for arable land(private land)

    (C) Production System and micro enterprise(15%)

    Production measures for arable land

    4th year 5th year 6th year Total

    (A) Preparatory phase activities capacity building trainings & EPA

    (B) Natural resource management (60%)

    ANNUAL ACTION PLAN-(THROUGH PROJECT FUND)

    Activity Unit Qty.Unit

    Cost

    Total

    cost

    1st year 2nd year 3rd year

  • Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin

    Admn. 10% 0% 37.50 37.50 0 3.75 0 3.75 0 11.25 0 9.00 0 6.00 0 3.75 0 37.50

    Monitoring 1% 0% 3.75 3.75 0 0.38 0 0.38 0 0.75 0 0.75 0 0.75 0 0.75 0 3.75

    Evaluation 1% 0% 3.75 3.75 0 0.56 0 0.56 0 0.68 0 0.64 0 0.68 0 0.64 0 3.75

    EPA 4% 0% 15.00 15.00 0 15.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 15.00

    I & CB 5% 0% 18.75 18.75 0 5.63 0 5.63 0 2.81 0 2.81 0 0.94 0 0.94 0 18.75

    DPR 1% 0% 3.75 3.75 0 3.75 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 3.75

    Total (A) 82.50 29.06 10.31 15.49 13.20 8.36 6.08 82.50

    Earthen Bund Mtr 3600 0.00139 5.00 200 0.28 450 0.63 800 1.11 1200 1.67 600 0.83 350 0.49 3600 5.00

    Tanka Num. 100 0.5 50.00 3 1.50 8 4.00 20 10.00 28 14.00 30 15.00 11 5.50 100 50.00

    Dhora Num. 22 2 44.00 1 2.00 2 4.00 6 12.00 8 16.00 3 6.00 2 4.00 22 44.00

    Khadin Num. 25 3 75.00 1 3.00 1 3.00 6 18.00 8 24.00 5 15.00 4 12.00 25 75.00

    Khet Talai Num. 5 3.5 17.50 1 3.50 0 0.00 1 3.50 1 3.50 1 3.50 1 3.50 5 17.50

    Bank Stabilization /Peripheral Bunds Mtr 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00

    Conservation measures for non arable land

    Pasture Development hact. 25 0.5 12.50 2 1.00 3 1.50 5 2.50 8 4.00 4 2.00 3 1.50 25 12.50

    V - ditch Mtr 12800 0.00028 3.54 400 0.11 2400 0.66 2600 0.72 4000 1.11 1750 0.48 1650 0.46 12800 3.54

    Water Harvesting Structure Num. 3 0.85 2.55 0 0.00 0 0.00 1 0.85 1 0.85 1 0.85 0 0.00 3 2.55

    Afforestation hact. 25 0.5 12.50 2 1.00 3 1.50 6 3.00 6 3.00 4 2.00 4 2.00 25 12.50

    Drainage line treatment MMS Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    LSCD Num. 16 0.15 2.40 1 0.15 2 0.30 4 0.60 6 0.90 2 0.30 1 0.15 16 2.40

    WHS Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Gully Plugs(ECD) Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Ground water recharge Structure Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Total (B) 225.00 12.54 15.59 52.28 69.03 45.97 29.59 225.00

    Horticulture plantation (vegetable,Medicine) Num. 4165 0.0015 6.25 250 0.38 490 0.74 1000 1.50 1410 2.12 600 0.90 415 0.62 4165 6.25

    Sprinklers and Drip irrigation hact. 50 0.20 10.00 0 0.00 5 1.00 15 3.00 25 5.00 5 1.00 0 0.00 50.0 10.00

    foriculture Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Vegetables Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Medicinal Plants hact. 8.35 0.24 2.00 0.25 0.06 2 0.48 2.25 0.54 2.25 0.54 1.00 0.24 0.60 0.14 8.35 2.00

    Vermi compost Num. 25 0.05 1.25 2 0.10 3 0.15 6 0.30 8 0.40 4 0.20 2 0.10 25 1.25

    Crop Demonstration Num. 465 0.02 9.30 30 0.60 80 1.60 100 2.00 150 3.00 60 1.20 45 0.90 465 9.30

    Micro Enterprise

    Dairy Num. 500 0.01 5.00 20 0.20 35 0.35 150 1.50 195 1.95 75 0.75 25 0.25 500 5.00

    Animal camp/Breed improovement Num. 15 0.50 7.50 1 0.50 1 0.50 5 2.50 6 3.00 1 0.50 1 0.50 15 7.50

    Poultry Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Local Artisans/craft Num. 12 0.10 1.20 0 0.00 1 0.10 4 0.40 5 0.50 1 0.10 1 0.10 12 1.20

    Animal Minral/ Mixar Num. 500 0.01 5.00 25 0.25 50 0.50 125 1.25 200 2.00 60 0.60 40 0.40 500 5.00

    SHG Land less/ BPL Num. 5 0.50 2.50 0 0.00 0 0.00 2 1.00 2 1.00 1 0.50 0 0.00 5 2.50

    Food Processing Num. 625 0.01 6.25 0 0.00 0 0.00 150 1.50 250 2.50 150 1.50 75 0.75 625 6.25

    Total (C) 56.25 2.09 5.42 15.49 22.01 7.49 3.77 56.25

    (D) Consolidation 3% 11.25 0.00 0.00 0.00 0.00 0.00 11.25 11.25Grand Total 375.00 43.69 31.32 83.26 104.23 61.82 50.68 375.00

    Conservation measures for arable land(private land)

    (C) Production System and micro enterprise(15%)

    Production measures for arable land

    4th year 5th year 6th year Total

    (A) Preparatory phase activities capacity building trainings & EPA

    (B) Natural resource management (60%)

    ANNUAL ACTION PLAN-(THROUGH PROJECT FUND)

    Gram Panchayat Barath Ka Gaon

    Activity Unit Qty.Unit

    Cost

    Total

    cost

    1st year 2nd year 3rd year

  • Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin

    Admn. 10% 0% 45.00 45.00 0 4.50 0 4.50 0 13.50 0 10.80 0 7.20 0 4.50 0 45.00

    Monitoring 1% 0% 4.50 4.50 0 0.45 0 0.45 0 0.90 0 0.90 0 0.90 0 0.90 0 4.50

    Evaluation 1% 0% 4.50 4.50 0 0.68 0 0.68 0 0.81 0 0.77 0 0.81 0 0.77 0 4.50

    EPA 4% 0% 18.00 18.00 0 18.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 18.00

    I & CB 5% 0% 22.50 22.50 0 6.75 0 6.75 0 3.38 0 3.38 0 1.13 0 1.13 0 22.50

    DPR 1% 0% 4.50 4.50 0 4.50 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 4.50

    Total (A) 99.00 34.88 12.38 18.59 15.84 10.04 7.29 99.00

    Earthen Bund Mtr 3440 0.00139 4.78 200 0.28 500 0.70 900 1.25 1200 1.67 350 0.49 290 0.40 3440 4.78

    Tanka Num. 120 0.5 60.00 5 2.50 10 5.00 21 10.50 34 17.00 30 15.00 20 10.00 120 60.00

    Dhora Num. 27 2 54.00 1 2.00 2 4.00 6 12.00 8 16.00 6 12.00 4 8.00 27 54.00

    Khadin Num. 30 3 90.00 1 3.00 2 6.00 6 18.00 12 36.00 5 15.00 4 12.00 30 90.00

    Khet Talai Num. 6 3.5 21.00 0 0.00 1 3.50 1 3.50 2 7.00 1 3.50 1 3.50 6 21.00

    Bank Stabilization /Peripheral Bunds Mtr 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00

    Conservation measures for non arable land

    Pasture Development hact. 30 0.5 15.00 2 1.00 3 1.50 5 2.50 12 6.00 6 3.00 2 1.00 30 15.00

    V - ditch Mtr 16500 0.00028 4.57 500 0.14 3025 0.84 4000 1.11 6500 1.80 1500 0.42 975 0.27 16500 4.57

    Water Harvesting Structure Num. 4 0.85 3.40 0 0.00 1 0.85 1 0.85 1 0.85 1 0.85 0 0.00 4 3.40

    Afforestation hact. 30 0.5 15.00 1 0.50 3 1.50 6 3.00 11 5.50 5 2.50 4 2.00 30 15.00

    Drainage line treatment MMS Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    LSCD Num. 15 0.15 2.25 1 0.15 2 0.30 3 0.45 4 0.60 3 0.45 2 0.30 15 2.25

    WHS Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Gully Plugs(ECD) Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Ground water recharge Structure Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Total (B) 270.00 9.57 24.18 53.16 92.42 53.20 37.47 270.00

    Horticulture plantation (vegetable,Medicine) Num. 5000 0.0015 7.50 135 0.20 400 0.60 1200 1.80 2000 3.00 800 1.20 465 0.70 5000 7.50

    Sprinklers and Drip irrigation hact. 60 0.20 12.00 5 1.00 5 1.00 15 3.00 25 5.00 5 1.00 5 1.00 60 12.00

    foriculture Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Vegetables Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Medicinal Plants hact. 10 0.24 2.40 0.25 0.06 0.50 0.12 3.00 0.72 4.50 1.08 1.25 0.30 0.50 0.12 10.00 2.40

    Vermi compost Num. 30 0.05 1.50 2 0.10 6 0.30 7 0.35 9 0.45 4 0.20 2 0.10 30 1.50

    Crop Demonstration Num. 555 0.02 11.10 25 0.50 50 1.00 150 3.00 200 4.00 70 1.40 60 1.20 555 11.10

    Micro Enterprise

    Dairy Num. 600 0.01 6.00 10 0.10 25 0.25 175 1.75 205 2.05 110 1.10 75 0.75 600 6.00

    Animal camp/Breed improovement Num. 18 0.50 9.00 1 0.50 1 0.50 6 3.00 8 4.00 1 0.50 1 0.50 18 9.00

    Poultry Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Local Artisans/craft Num. 15 0.10 1.50 1 0.10 2 0.20 3 0.30 5 0.50 3 0.30 1 0.10 15 1.50

    Animal Minral/ Mixar Num. 600 0.01 6.00 50 0.50 72 0.72 150 1.50 200 2.00 80 0.80 48 0.48 600 6.00

    SHG Land less/ BPL Num. 6 0.50 3.00 0 0.00 1 0.50 2 1.00 2 1.00 0 0.00 1 0.50 6 3.00

    Food Processing Num. 750 0.01 7.50 25 0.25 50 0.50 200 2.00 350 3.50 75 0.75 50 0.50 750 7.50

    Total (C) 67.50 3.31 5.69 18.42 26.58 7.55 5.95 67.50

    (D) Consolidation 3% 13.50 0.00 0.00 0.00 0.00 0.00 13.50 13.50Grand Total 450.00 47.75 42.25 90.16 134.84 70.79 64.21 450.00

    Conservation measures for arable land(private land)

    (C) Production System and micro enterprise(15%)

    Production measures for arable land

    4th year 5th year 6th year Total

    (A) Preparatory phase activities capacity building trainings & EPA

    (B) Natural resource management (60%)

    ANNUAL ACTION PLAN-(THROUGH PROJECT FUND)

    Gram Panchayat Balar

    Activity Unit Qty.Unit

    Cost

    Total

    cost

    1st year 2nd year 3rd year

  • Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin

    Admn. 10% 0% 7.50 7.50 0 0.75 0 0.75 0 2.25 0 1.80 0 1.20 0 0.75 0 7.50

    Monitoring 1% 0% 0.75 0.75 0 0.08 0 0.08 0 0.15 0 0.15 0 0.15 0 0.15 0 0.75

    Evaluation 1% 0% 0.75 0.75 0 0.11 0 0.11 0 0.14 0 0.13 0 0.14 0 0.13 0 0.75

    EPA 4% 0% 3.00 3.00 0 3.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 3.00

    I & CB 5% 0% 3.75 3.75 0 1.13 0 1.13 0 0.56 0 0.56 0 0.19 0 0.19 0 3.75

    DPR 1% 0% 0.75 0.75 0 0.75 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.75

    Total (A) 16.50 5.81 2.06 3.10 2.64 1.67 1.22 16.50

    Earthen Bund Mtr 260 0.00139 0.36 25 0.03 60 0.08 45 0.06 40 0.06 50 0.07 40 0.06 260 0.36

    Tanka Num. 20 0.5 10.00 2 1.00 2 1.00 3 1.50 6 3.00 4 2.00 3 1.50 20 10.00

    Dhora Num. 5 2 10.00 0 0.00 1 2.00 1 2.00 1 2.00 2 4.00 0 0.00 5 10.00

    Khadin Num. 5 3 15.00 0 0.00 0 0.00 1 3.00 2 6.00 1 3.00 1 3.00 5 15.00

    Khet Talai Num. 1 3.5 3.50 0 0.00 0 0.00 1 3.50 0 0.00 0 0.00 0 0.00 1 3.50

    Bank Stabilization /Peripheral Bunds Mtr 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00

    Conservation measures for non arable land

    Pasture Development hact. 5 0.5 2.50 0.25 0.13 1 0.50 1.00 0.50 1.25 0.63 1 0.50 0.50 0.25 5 2.50

    V - ditch Mtr 2500 0.00028 0.69 200 0.06 200 0.06 800 0.22 900 0.25 200 0.06 200 0.06 2500 0.69

    Water Harvesting Structure Num. 0 0.85 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Afforestation hact. 5 0.5 2.50 0.5 0.25 0.75 0.38 1.25 0.63 1.25 0.63 1 0.50 0.25 0.13 5 2.50

    Drainage line treatment MMS Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    LSCD Num. 3 0.15 0.45 0 0.00 1 0.15 1 0.15 1 0.15 0 0.00 0 0.00 3 0.45

    WHS Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Gully Plugs(ECD) Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Ground water recharge Structure Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Total (B) 45.00 1.47 4.16 11.56 12.70 10.12 4.99 45.00

    Horticulture plantation (vegetable,Medicine) Num. 830 0.0015 1.25 20 0.03 40 0.06 250 0.38 475 0.71 30 0.05 15 0.02 830 1.25

    Sprinklers and Drip irrigation hact. 10 0.20 2.00 0 0.00 1 0.20 3 0.60 4 0.80 1 0.20 1 0.20 10 2.00

    foriculture Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Vegetables Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Medicinal Plants hact. 1.66 0.24 0.40 0 0.00 0.25 0.06 0.50 0.12 0.50 0.12 0.25 0.06 0.16 0.04 1.66 0.40

    Vermi compost Num. 5 0.05 0.25 0 0.00 1 0.05 1 0.05 1 0.05 1 0.05 1 0.05 5 0.25

    Crop Demonstration Num. 120 0.02 2.40 0 0.00 5 0.10 30 0.60 45 0.90 30 0.60 10 0.20 120 2.40

    Micro Enterprise

    Dairy Num. 100 0.01 1.00 5 0.05 5 0.05 25 0.25 37 0.37 28 0.28 0 0.00 100 1.00

    Animal camp/Breed improovement Num. 2 0.50 1.00 0 0.00 1 0.50 1 0.50 0 0.00 0 0.00 0 0.00 2 1.00

    Poultry Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Local Artisans/craft Num. 2 0.10 0.20 0 0.00 1 0.10 1 0.10 0 0.00 0 0.00 0 0.00 2 0.20

    Animal Minral/ Mixar Num. 50 0.01 0.50 10 0.10 20 0.20 10 0.10 10 0.10 0 0.00 0 0.00 50 0.50

    SHG Land less/ BPL Num. 2 0.50 1.00 0 0.00 0 0.00 1 0.50 1 0.50 0 0.00 0 0.00 2 1.00

    Food Processing Num. 125 0.01 1.25 0 0.00 0 0.00 25 0.25 50 0.50 30 0.30 20 0.20 125 1.25

    Total (C) 11.24 0.18 1.32 3.45 4.05 1.54 0.71 11.24

    (D) Consolidation 3% 2.25 0.00 0.00 0.00 0.00 0.00 2.25 2.25Grand Total 75.00 7.46 7.55 18.10 19.40 13.33 9.16 75.00

    Conservation measures for arable land(private land)

    (C) Production System and micro enterprise(15%)

    Production measures for arable land

    4th year 5th year 6th year Total

    (A) Preparatory phase activities capacity building trainings & EPA

    (B) Natural resource management (60%)

    ANNUAL ACTION PLAN-(THROUGH PROJECT FUND)

    Gram Panchayat Dantal

    Activity Unit Qty.Unit

    Cost

    Total

    cost

    1st year 2nd year 3rd year

  • Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin

    Admn. 10% 0% 15.00 15.00 0 1.50 0 1.50 0 4.50 0 3.60 0 2.40 0 1.50 0 15.00

    Monitoring 1% 0% 1.50 1.50 0 0.15 0 0.15 0 0.30 0 0.30 0 0.30 0 0.30 0 1.50

    Evaluation 1% 0% 1.50 1.50 0 0.23 0 0.23 0 0.27 0 0.26 0 0.27 0 0.26 0 1.50

    EPA 4% 0% 6.00 6.00 0 6.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 6.00

    I & CB 5% 0% 7.50 7.50 0 2.25 0 2.25 0 1.13 0 1.13 0 0.38 0 0.38 0 7.50

    DPR 1% 0% 1.50 1.50 0 1.50 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 1.50

    Total (A) 33.00 11.63 4.13 6.20 5.28 3.35 2.43 33.00

    Earthen Bund Mtr 1870 0.00139 2.60 100 0.14 250 0.35 400 0.56 600 0.83 300 0.42 220 0.31 1870 2.60

    Tanka Num. 37 0.5 18.50 2 1.00 4 2.00 8 4.00 14 7.00 5 2.50 4 2.00 37 18.50

    Dhora Num. 10 2 20.00 1 2.00 1 2.00 2 4.00 2 4.00 2 4.00 2 4.00 10 20.00

    Khadin Num. 8 3 24.00 0 0.00 0 0.00 2 6.00 2 6.00 2 6.00 2 6.00 8 24.00

    Khet Talai Num. 3 3.5 10.50 0 0.00 0 0.00 1 3.50 1 3.50 1 3.50 0 0.00 3 10.50

    Bank Stabilization /Peripheral Bunds Mtr 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00

    Conservation measures for non arable land

    Pasture Development hact. 10 0.5 5.00 1 0.50 2 1.00 3 1.50 3 1.50 1 0.50 0 0.00 10 5.00

    V - ditch Mtr 6500 0.00028 1.80 525 0.15 1150 0.32 1750 0.48 1800 0.50 700 0.19 575 0.16 6500 1.80

    Water Harvesting Structure Num. 2 0.85 1.70 0 0.00 0 0.00 1 0.85 1 0.85 0 0.00 0 0.00 2 1.70

    Afforestation hact. 10 0.5 5.00 1 0.50 2 1.00 3 1.50 3 1.50 1 0.50 0 0.00 10 5.00

    Drainage line treatment MMS Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    LSCD Num. 6 0.15 0.90 1 0.15 1 0.15 2 0.30 1 0.15 1 0.15 0 0.00 6 0.90

    WHS Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Gully Plugs(ECD) Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Ground water recharge Structure Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Total (B) 90.00 4.43 6.82 22.69 25.83 17.76 12.47 90.00

    Horticulture plantation (vegetable,Medicine) Num. 1330 0.0015 2.00 40 0.06 80 0.12 200 0.30 445 0.67 300 0.45 265 0.40 1330 2.00

    Sprinklers and Drip irrigation hact. 22.5 0.20 4.50 1 0.20 2 0.40 8 1.60 10 2.00 1.50 0.30 0 0.00 22.50 4.50

    foriculture Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Vegetables Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Medicinal Plants hact. 3.35 0.24 0.80 0.2 0.05 0.3 0.07 0.50 0.12 1.50 0.36 0.50 0.12 0.35 0.08 3.35 0.80

    Vermi compost Num. 8 0.05 0.40 1 0.05 1 0.05 2 0.10 3 0.15 1 0.05 0 0.00 8 0.40

    Crop Demonstration Num. 225 0.02 4.50 5 0.10 20 0.40 75 1.50 100 2.00 20 0.40 5 0.10 225 4.50

    Micro Enterprise

    Dairy Num. 180 0.01 1.80 10 0.10 10 0.10 45 0.45 75 0.75 20 0.20 20 0.20 180 1.80

    Animal camp/Breed improovement Num. 5 0.50 2.50 0 0.00 1 0.50 1 0.50 2 1.00 1 0.50 0 0.00 5 2.50

    Poultry Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Local Artisans/craft Num. 5 0.10 0.50 0 0.00 1 0.10 1 0.10 2 0.20 1 0.10 0 0.00 5 0.50

    Animal Minral/ Mixar Num. 200 0.01 2.00 10 0.10 20 0.20 60 0.60 70 0.70 20 0.20 20 0.20 200 2.00

    SHG Land less/ BPL Num. 2 0.50 1.00 0 0.00 0 0.00 0 0.00 1 0.50 1 0.50 0 0.00 2 1.00

    Food Processing Num. 250 0.01 2.50 10 0.10 30 0.30 60 0.60 80 0.80 40 0.40 30 0.30 250 2.50

    Total (C) 22.50 0.76 2.24 5.87 9.13 3.22 1.28 22.50

    (D) Consolidation 3% 4.50 0.00 0.00 0.00 0.00 0.00 4.50 4.50Grand Total 150.00 16.82 13.18 34.76 40.24 24.33 20.68 150.00

    Conservation measures for arable land(private land)

    (C) Production System and micro enterprise(15%)

    Production measures for arable land

    4th year 5th year 6th year Total

    (A) Preparatory phase activities capacity building trainings & EPA

    (B) Natural resource management (60%)

    ANNUAL ACTION PLAN-(THROUGH PROJECT FUND)

    Gram Panchayat Didaniya

    Activity Unit Qty.Unit

    Cost

    Total

    cost

    1st year 2nd year 3rd year

  • Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin

    Admn. 10% 0% 15.00 15.00 0 1.50 0 1.50 0 4.50 0 3.60 0 2.40 0 1.50 0 15.00

    Monitoring 1% 0% 1.50 1.50 0 0.15 0 0.15 0 0.30 0 0.30 0 0.30 0 0.30 0 1.50

    Evaluation 1% 0% 1.50 1.50 0 0.23 0 0.23 0 0.27 0 0.26 0 0.27 0 0.26 0 1.50

    EPA 4% 0% 6.00 6.00 0 6.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 6.00

    I & CB 5% 0% 7.50 7.50 0 2.25 0 2.25 0 1.13 0 1.13 0 0.38 0 0.38 0 7.50

    DPR 1% 0% 1.50 1.50 0 1.50 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 1.50

    Total (A) 33.00 11.63 4.13 6.20 5.28 3.35 2.43 33.00

    Earthen Bund Mtr 1500 0.00139 2.09 75 0.10 100 0.14 625 0.87 800 1.11 430 0.60 300 0.42 2330 3.24

    Tanka Num. 29 0.5 14.50 2 1.00 4 2.00 8 4.00 11 5.50 5 2.50 4 2.00 34 17.00

    Dhora Num. 10 2 20.00 1 2.00 2 4.00 2 4.00 3 6.00 2 4.00 1 2.00 11 22.00

    Khadin Num. 12 3 36.00 0 0.00 0 0.00 2 6.00 3 9.00 3 9.00 2 6.00 10 30.00

    Khet Talai Num. 2 3.5 7.00 0 0.00 0 0.00 0 0.00 1 3.50 0 0.00 0 0.00 1 3.50

    Bank Stabilization /Peripheral Bunds Mtr 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00

    Conservation measures for non arable land

    Pasture Development hact. 8 0.5 4.00 0.25 0.13 0.75 0.38 3.00 1.50 3.00 1.50 2.50 1.25 0.50 0.25 10 5.00

    V - ditch Mtr 4580 0.00028 1.27 250 0.07 500 0.14 1500 0.42 2250 0.62 1000 0.28 500 0.14 6000 1.66

    Water Harvesting Structure Num. 2 0.85 1.70 0 0.00 0 0.00 1 0.85 1 0.85 0 0.00 0 0.00 2 1.70

    Afforestation hact. 6 0.5 3.00 1 0.50 1 0.50 2 1.00 3 1.50 2 1.00 1 0.50 10 5.00

    Drainage line treatment MMS Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    LSCD Num. 3 0.15 0.45 1 0.15 1 0.15 1 0.15 1 0.15 1 0.15 1 0.15 6 0.90

    WHS Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Gully Plugs(ECD) Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Ground water recharge Structure Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Total (B) 90.00 3.95 7.30 18.78 29.74 18.77 11.46 90.00

    Horticulture plantation (vegetable,Medicine) Num. 1500 0.0015 2.25 30 0.05 80 0.12 400 0.60 690 1.04 200 0.30 100 0.15 1500 2.25

    Sprinklers and Drip irrigation hact. 19 0.20 3.80 2 0.40 2 0.40 5 1.00 7 1.40 2 0.40 1 0.20 19 3.80

    foriculture Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Vegetables Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Medicinal Plants hact. 3.34 0.24 0.80 0.25 0.06 0.75 0.18 0.75 0.18 0.75 0.18 0.50 0.12 0.34 0.08 3.34 0.80

    Vermi compost Num. 9 0.05 0.45 1 0.05 3 0.15 2 0.10 2 0.10 1 0.05 0 0.00 9 0.45

    Crop Demonstration Num. 200 0.02 4.00 6 0.12 12 0.24 45 0.90 95 1.90 25 0.50 17 0.34 200 4.00

    Micro Enterprise

    Dairy Num. 175 0.01 1.75 4 0.04 9 0.09 60 0.60 80 0.80 10 0.10 12 0.12 175 1.75

    Animal camp/Breed improovement Num. 5 0.50 2.50 0 0.00 1 0.50 2 1.00 2 1.00 0 0.00 0 0.00 5 2.50

    Poultry Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Local Artisans/craft Num. 4 0.10 0.40 1 0.10 0 0.00 1 0.10 1 0.10 1 0.10 0 0.00 4 0.40

    Animal Minral/ Mixar Num. 250 0.01 2.50 15 0.15 35 0.35 50 0.50 70 0.70 45 0.45 35 0.35 250 2.50

    SHG Land less/ BPL Num. 3 0.50 1.50 0 0.00 0 0.00 1 0.50 1 0.50 1 0.50 0 0.00 3 1.50

    Food Processing Num. 255 0.01 2.55 0 0.00 0 0.00 60 0.60 120 1.20 45 0.45 30 0.30 255 2.55

    Total (C) 22.50 0.97 2.03 6.08 8.92 2.97 1.54 22.50

    (D) Consolidation 3% 4.50 0.00 0.00 0.00 0.00 0.00 4.50 4.50Grand Total 150.00 16.54 13.46 31.06 43.93 25.09 19.93 150.00

    Conservation measures for arable land(private land)

    (C) Production System and micro enterprise(15%)

    Production measures for arable land

    4th year 5th year 6th year Total

    (A) Preparatory phase activities capacity building trainings & EPA

    (B) Natural resource management (60%)

    ANNUAL ACTION PLAN-(THROUGH PROJECT FUND)

    Gram Panchayat Pannasar

    Activity Unit Qty.Unit

    Cost

    Total

    cost

    1st year 2nd year 3rd year

  • Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin

    Admn. 10% 0% 15.00 15.00 0 1.50 0 1.50 0 4.50 0 3.60 0 2.40 0 1.50 0 15.00

    Monitoring 1% 0% 1.50 1.50 0 0.15 0 0.15 0 0.30 0 0.30 0 0.30 0 0.30 0 1.50

    Evaluation 1% 0% 1.50 1.50 0 0.23 0 0.23 0 0.27 0 0.26 0 0.27 0 0.26 0 1.50

    EPA 4% 0% 6.00 6.00 0 6.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 6.00

    I & CB 5% 0% 7.50 7.50 0 2.25 0 2.25 0 1.13 0 1.13 0 0.38 0 0.38 0 7.50

    DPR 1% 0% 1.50 1.50 0 1.50 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 1.50

    Total (A) 33.00 11.63 4.13 6.20 5.28 3.35 2.43 33.00

    Earthen Bund Mtr 1450 0.00139 2.02 225 0.31 290 0.40 400 0.56 530 0.74 5 0.01 0 0.00 1450 2.02

    Tanka Num. 40 0.5 20.00 3 1.50 2 1.00 6 3.00 9 4.50 12 6.00 8 4.00 40 20.00

    Dhora Num. 9 2 18.00 2 4.00 1 2.00 2 4.00 2 4.00 1 2.00 1 2.00 9 18.00

    Khadin Num. 10 3 30.00 0 0.00 0 0.00 3 9.00 4 12.00 2 6.00 1 3.00 10 30.00

    Khet Talai Num. 2 3.5 7.00 0 0.00 0 0.00 1 3.50 0 0.00 1 3.50 0 0.00 2 7.00

    Bank Stabilization /Peripheral Bunds Mtr 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00

    Conservation measures for non arable land

    Pasture Development hact. 10 0.5 5.00 0.25 0.13 0.25 0.13 2.50 1.25 2.75 1.38 3.00 1.50 1.25 0.63 10 5.00

    V - ditch Mtr 5000 0.00028 1.38 800 0.22 1400 0.39 1000 0.28 1000 0.28 600 0.17 200 0.06 5000 1.38

    Water Harvesting Structure Num. 1 0.85 0.85 0 0.00 0 0.00 1 0.85 0 0.00 0 0.00 0 0.00 1 0.85

    Afforestation hact. 10 0.5 5.00 0.5 0.25 1.25 0.63 2.75 1.38 2.75 1.38 1.75 0.88 1.00 0.50 10 5.00

    Drainage line treatment MMS Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    LSCD Num. 5 0.15 0.75 1 0.15 1 0.15 1 0.15 2 0.30 0 0.00 0 0.00 5 0.75

    WHS Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Gully Plugs(ECD) Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Ground water recharge Structure Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Total (B) 90.00 6.56 4.69 23.96 24.56 20.05 10.18 90.00

    Horticulture plantation (vegetable,Medicine) Num. 1665 0.0015 2.50 50 0.08 70 0.11 400 0.60 500 0.75 350 0.53 295 0.44 1665 2.50

    Sprinklers and Drip irrigation hact. 20 0.20 4.00 0 0.00 2 0.40 5 1.00 10 2.00 2 0.40 1 0.20 20 4.00

    foriculture Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Vegetables Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Medicinal Plants hact. 3.35 0.24 0.80 0.25 0.06 0.5 0.12 0.75 0.18 1.25 0.30 0.50 0.12 0.10 0.02 3.35 0.80

    Vermi compost Num. 10 0.05 0.50 2 0.10 1 0.05 3 0.15 3 0.15 1 0.05 0 0.00 10 0.50

    Crop Demonstration Num. 185 0.02 3.70 6 0.12 8 0.16 60 1.20 70 1.40 21 0.42 20 0.40 185 3.70

    Micro Enterprise

    Dairy Num. 200 0.01 2.00 14 0.14 11 0.11 70 0.70 75 0.75 15 0.15 15 0.15 200 2.00

    Animal camp/Breed improovement Num. 6 0.50 3.00 0 0.00 1 0.50 2 1.00 2 1.00 1 0.50 0 0.00 6 3.00

    Poultry Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Local Artisans/craft Num. 5 0.10 0.50 0 0.00 1 0.10 1 0.10 2 0.20 1 0.10 0 0.00 5 0.50

    Animal Minral/ Mixar Num. 200 0.01 2.00 23 0.23 48 0.48 52 0.52 65 0.65 7 0.07 5 0.05 200 2.00

    SHG Land less/ BPL Num. 2 0.50 1.00 0 0.00 0 0.00 1 0.50 1 0.50 0 0.00 0 0.00 2 1.00

    Food Processing Num. 250 0.01 2.50 10 0.10 15 0.15 60 0.60 75 0.75 50 0.50 40 0.40 250 2.50

    Total (C) 22.50 0.83 2.18 6.55 8.45 2.84 1.67 22.50

    (D) Consolidation 3% 4.50 0.00 0.00 0.00 0.00 0.00 4.50 4.50Grand Total 150.00 19.01 10.99 36.70 38.29 26.23 18.78 150.00

    Conservation measures for arable land(private land)

    (C) Production System and micro enterprise(15%)

    Production measures for arable land

    4th year 5th year 6th year Total

    (A) Preparatory phase activities capacity building trainings & EPA

    (B) Natural resource management (60%)

    ANNUAL ACTION PLAN-(THROUGH PROJECT FUND)

    Gram Panchayat Swamiji Ki Dhani

    Activity Unit Qty.Unit

    Cost

    Total

    cost

    1st year 2nd year 3rd year

  • Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin Phy Fin

    Admn. 10% 0% 15.00 15.00 0 1.50 0 1.50 0 4.50 0 3.60 0 2.40 0 1.50 0 15.00

    Monitoring 1% 0% 1.50 1.50 0 0.15 0 0.15 0 0.30 0 0.30 0 0.30 0 0.30 0 1.50

    Evaluation 1% 0% 1.50 1.50 0 0.23 0 0.23 0 0.27 0 0.26 0 0.27 0 0.26 0 1.50

    EPA 4% 0% 6.00 6.00 0 6.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 6.00

    I & CB 5% 0% 7.50 7.50 0 2.25 0 2.25 0 1.13 0 1.13 0 0.38 0 0.38 0 7.50

    DPR 1% 0% 1.50 1.50 0 1.50 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 1.50

    Total (A) 33.00 11.63 4.13 6.20 5.28 3.35 2.43 33.00

    Earthen Bund Mtr 1450 0.00139 2.02 150 0.21 175 0.24 425 0.59 615 0.85 50 0.07 35 0.05 1450 2.02

    Tanka Num. 30 0.5 15.00 2 1.00 2 1.00 6 3.00 8 4.00 7 3.50 5 2.50 30 15.00

    Dhora Num. 10 2 20.00 1 2.00 1 2.00 3 6.00 4 8.00 1 2.00 0 0.00 10 20.00

    Khadin Num. 11 3 33.00 1 3.00 0 0.00 3 9.00 3 9.00 2 6.00 2 6.00 11 33.00

    Khet Talai Num. 2 3.5 7.00 0 0.00 0 0.00 0 0.00 1 3.50 1 3.50 0 0.00 2 7.00

    Bank Stabilization /Peripheral Bunds Mtr 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00

    Conservation measures for non arable land

    Pasture Development hact. 10 0.5 5.00 0.25 0.13 0.5 0.25 1.25 0.63 1.50 0.75 3.75 1.88 2.75 1.38 10 5.00

    V - ditch Mtr 5000 0.00028 1.38 750 0.21 1500 0.42 1000 0.28 1000 0.28 500 0.14 250 0.07 5000 1.38

    Water Harvesting Structure Num. 1 0.85 0.85 0 0.00 0 0.00 1 0.85 0 0.00 0 0.00 0 0.00 1 0.85

    Afforestation hact. 10 0.5 5.00 0.5 0.25 0.5 0.25 1 0.50 2 1.00 4 2.00 2 1.00 10 5.00

    Drainage line treatment MMS Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    LSCD Num. 5 0.15 0.75 1 0.15 1 0.15 1 0.15 1 0.15 1 0.15 0 0.00 5 0.75

    WHS Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Gully Plugs(ECD) Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Ground water recharge Structure Num. 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Total (B) 90.00 6.94 4.31 20.99 27.53 19.23 10.99 90.00

    Horticulture plantation (vegetable,Medicine) Num. 2000 0.0015 3.00 50 0.08 75 0.11 400 0.60 840 1.26 400 0.60 235 0.35 2000 3.00

    Sprinklers and Drip irrigation hact. 15 0.20 3.00 0 0.00 2 0.40 4 0.80 5 1.00 2 0.40 2 0.40 15 3.00

    foriculture Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Vegetables Num. 0 0.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00

    Medicinal Plants hact. 5 0.24 1.20 0 0.00 0.25 0.06 1.50 0.36 2.00 0.48 0.75 0.18 0.50 0.12 5.00 1.20

    Vermi compost Num. 10 0.05 0.50 1 0.05 4 0.20 2 0.10 1 0.05 1 0.05 1 0.05 10 0.50

    Crop Demonstration Num. 200 0.02 4.00 15 0.30 25 0.50 80 1.60 80 1.60 0 0.00