Upload
barrysmith77
View
212
Download
0
Embed Size (px)
DESCRIPTION
Solvent upgrade
Citation preview
1BLENDED AMINES
By: Charalambos Patsatzis
Houston Refining LP
Overview In August of 2002 LCR underwent a solvent
upgrade from conventional DEA (25-28 wt%) to a formulated UcarsolTM LE-713 DEA and UcarsolTM LE-713 supplied by the same
company Solvent upgrade took approximately 4 months to
complete No unit shutdowns No equipment upgrades
Except for reliability improvements that were identified
2Outline Reason for Change DEA Regeneration Overview Unit Limitations Contactor Limitations
Tighter specifications on product stream
Available Options Capital expenditure Solvent upgrade
Solvent Upgrade What Changed Since 2002?
Reason for Change
FCCU and Coker off gas streams had to be rerouted to an alternate processing unit. Existing processing location was scheduled for an
extensive outage This meant increased amine circulation to meet product
specifications
Product specifications were reduced from 160 to 30 ppmw for H2S CO2 specification remained at the same target
If specifications were not met refinery would have to route the streams to the flare system Extensive environmental implications
3DEA System
Typical System Capacity Needs Regenerators
Regenerator Capacity
Available Excess
Capacity431 1250 B/H 431-A 900 B/H
431-B 600 B/H 250 B/H
DEA Regeneration OverviewPlant Amine Regenerators
Built in 1968 - upgrade to 431B regenerator
Original unit 1954 First amine regenerator
DEA System
Typical System Capacity Needs Regenerators
Regenerator Capacity
Available Excess
Capacity431 1250 B/H 431-A 900 B/H
431-B 600 B/H 250 B/H436 1750 B/H 436-A 1000 B/H
436-B 1000 B/H 250 B/H
DEA Regeneration OverviewPlant Amine Regenerators
Built in 1974 - Part of sulfur/refinery expansion
4DEA System
Typical System Capacity Needs Regenerators
Regenerator Capacity
Available Excess
Capacity431 1250 B/H 431-A 900 B/H
431-B 600 B/H 250 B/H436 1750 B/H 436-A 1000 B/H
436-B 1000 B/H 250 B/H441 2500 B/H 441 3000 B/H 500 B/H
5500 B/H 6500 B/H 1000 B/H
DEA Regeneration OverviewPlant Amine Regenerators
Built in 1995 - Part of major sulfur/refinery expansion
DEA Regeneration Overview Contd
Gas Phase Contactors: Liquid Phase Contactors:Unit Process Stream Unit Process Stream
230 GP Fuel Gas ARU C3/C5 Idle631-A&B Recycle H2 LPG LPG
632 Recycle H2 FCCU Liquid PPs633 Recycle H2 736 Liquid PPs634 Recycle H2 737 Liquid PPs635 Recycle H2636 Recycle H2
FCCU Dry Gas736 Dry Gas737 Dry GasMag Recycle H2BTU Recycle H2
There are 17 Amine Absorbers in the Refinery
5DEA Regeneration Overview Contd
Amine Loading Lean amine loading 0.01-0.02 mol H2S/mol solvent Rich amine loading 0.4-0.6 mol H2S/mol solvent
Amine Velocities Lean/Rich velocities between 4-7 ft/sec No PWHT on older amine system piping
1 out of 3 systems
Corrosion Rates Corrosion coupons indicate 8-16 mils/yr on rich amine
system piping
Amine Regenerator Flow Diagram
6431-A&B DEA REGENERATORS
431-A 431-B
436-A&B DEA REGENERATORS
7441 DEA REGENERATOR
Unit Limitations
Amine Regenerators Lean amine cooling In excess of 140oF Rate limitations Already at 125% of design capacity Reboiler duty Steam supply limitation Throw-away limitation For ammonia control Metallurgy limitations No PWHT
Amine Piping Line velocities (specially around control loops)
Single Storage Tank Feeds all Three Systems Rich Amine Flash Drums
With higher rates amine retention times are reduced
8Contactor Limitations Absorbers
Lean amine cooling Rich amine loading Instrumentation limitations CO2 loading Metallurgy limitations No PWHT
Amine Piping (IBL) Line velocities (rich amine return outlet) Hydraulic constraints
Contactor Limitations ContdBrimstone Analysis
Component Molar%
H2 14.394N2 7.44
CH4 36.002CO 1.293CO2 1.669C2H4 17.984C2H6 15.118H2S 0.581C3H8 2.927i-C4 1.049n-C4 0.925i-C5 0.382n-C5 0.174C6+ 0.062Total 100
Untreated 732 Before LE-713
High CO2 in the contactor feed
9Contactor Limitations ContdBrimstone Analysis
CO2 within acceptable range
Component Molar%
H2 14.104N2 7.593
CH4 36.969CO 1.279CO2 0.369C2H4 18.465C2H6 15.471H2S Non DetectedC3H8 2.784i-C4 1.099n-C4 1.076i-C5 0.474n-C5 0.215C6+ 0.102Total 100
Treated 732 Before LE-713
Contactor Limitations Contd
Component Molar%
H2 6.293N2 0.095
CH4 51.506CO 0.534CO2 0.231C2H4 2.277C2H6 20.437H2S 11.072C3H8 7.433i-C4 0.058n-C4 0.041i-C5 0.006n-C5 0.019C6+ Non DetectedTotal 100.0
Untreated 737 Before LE-713
No CO2 concern on this contactorBrimstone Analysis
10
Available Options
Capital Upgrade Upgrade existing
regenerator(s) Invest on new
regenerator
Solvent Upgrade Upgrade single
amine system Upgrade entire
amine system (three amine systems)
Available Options Contd
Capital Upgrade Time constraints ROI below 50% OBL piping
upgrades would be required
Solvent Upgrade Relatively quick
transition ROI at 75% No equipment
upgrades would be necessary
11
Solvent Upgrade
Engineering analysis was performed on entire amine system Simulations were constructed with new solvent
properties for amine system including contactors Economics were evaluated
Energy savings Reliability Solvent losses Solvent selection Solvent percent strength
Choice was to upgrade solvent on the entire amine system
Solvent Upgrade Contd
Initial charge was performed using UcarsolTM to get system volume up to desired UcarsolTM LE-713 formulation
Due to the large system volume capacity ~600,000 gallon Solvent strength was to be stepped in three different
phases 30% 35% (target) 40% (if needed)
Solvent loaded directly into the individual systems Monitor closely solvent losses Monitor solvent performance for absorbers in different
service
12
Solvent Upgrade Contd Target UcarsolTM LE-713 formulation was
achieved approximately 4 months from the time that system was initially charged Primary driver for the extended time was cost Fresh amine tank was then converted to UcarsolTM LE-
713 tank System leveled at 35 wt% on solvent strength Fresh amine tank was then converted to UcarsolTM
LE-713 tank Brimstone Engineering Services conducted plant
wide performance testing Testing performed before initial charge Testing performed 1 year after system was at steady
state
Solvent Upgrade Contd Systems in place for monitoring
Purchased state of the art GC for in house sampling Training to mitigate system losses
Technical department Operations department
Supplier Involvement
Instrumentation upgrades on key amine absorbers Updated control configuration Temperature control Upgraded analyzers Real time rich loading equations
More intense corrosion monitoring system Going away from corrosion probes and focusing more on TML
readings Ion exchange system for anion and HSAS control
13
Solvent Upgrade Contd
Current Situation Amine concentration at 40 wt%
Primarily from circulation reduction
Energy savings 27.5 MMBtu/hr Amine losses Down by17%
Primarily due to increased awareness and training Better instrumentation on amine absorbers
Solvent Upgrade Contd
Current Situation Amine Loading
Lean amine loading 0.01-0.015 mol H2S/mol solvent
Rich amine loading 0.4-0.45 mol H2S/mol solvent
Amine Velocities Lean/Rich velocities
14
Summary
Solvent upgrade was successfully completed Refinery has increased solvent concentration for
energy savings (currently at 40%) COS and trace sulfur species removal was within
target after solvent upgrade No equipment upgrades No unit shutdowns were required
What Changed Since 2002?
FCCU Dry Gas Contactor CO2 specifications changed New contract signed in conjunction with a
compression station New CO2 specification at 500 ppmv
Operation of FCCU has changed over the last two years causing more CO2 slip to the absorber
15
What Changed Since 2002?
Pilot plant data (tests performed at DOWs pilot plant facilities) confirmed that a solvent upgrade was required to meet product specification
Solvent upgrade would be specific to this system only Upgrade is planned for 2nd week of October
Equipment that would allow system optimization had to be installed
What Changed Since 2002?
Equipment that would allow system optimization had to be installed Installation complete
Training on new system Technical department Operations department
Product exports to 3rd party facility to begin in November
Supplier Involvement