15
1 “BLENDED AMINES” By: Charalambos Patsatzis Houston Refining LP Overview In August of 2002 LCR underwent a solvent upgrade from conventional DEA (25-28 wt%) to a formulated Ucarsol TM LE-713 DEA and Ucarsol TM LE-713 supplied by the same company Solvent upgrade took approximately 4 months to complete No unit shutdowns No equipment upgrades Except for reliability improvements that were identified

Blended Amines

Embed Size (px)

DESCRIPTION

Solvent upgrade

Citation preview

  • 1BLENDED AMINES

    By: Charalambos Patsatzis

    Houston Refining LP

    Overview In August of 2002 LCR underwent a solvent

    upgrade from conventional DEA (25-28 wt%) to a formulated UcarsolTM LE-713 DEA and UcarsolTM LE-713 supplied by the same

    company Solvent upgrade took approximately 4 months to

    complete No unit shutdowns No equipment upgrades

    Except for reliability improvements that were identified

  • 2Outline Reason for Change DEA Regeneration Overview Unit Limitations Contactor Limitations

    Tighter specifications on product stream

    Available Options Capital expenditure Solvent upgrade

    Solvent Upgrade What Changed Since 2002?

    Reason for Change

    FCCU and Coker off gas streams had to be rerouted to an alternate processing unit. Existing processing location was scheduled for an

    extensive outage This meant increased amine circulation to meet product

    specifications

    Product specifications were reduced from 160 to 30 ppmw for H2S CO2 specification remained at the same target

    If specifications were not met refinery would have to route the streams to the flare system Extensive environmental implications

  • 3DEA System

    Typical System Capacity Needs Regenerators

    Regenerator Capacity

    Available Excess

    Capacity431 1250 B/H 431-A 900 B/H

    431-B 600 B/H 250 B/H

    DEA Regeneration OverviewPlant Amine Regenerators

    Built in 1968 - upgrade to 431B regenerator

    Original unit 1954 First amine regenerator

    DEA System

    Typical System Capacity Needs Regenerators

    Regenerator Capacity

    Available Excess

    Capacity431 1250 B/H 431-A 900 B/H

    431-B 600 B/H 250 B/H436 1750 B/H 436-A 1000 B/H

    436-B 1000 B/H 250 B/H

    DEA Regeneration OverviewPlant Amine Regenerators

    Built in 1974 - Part of sulfur/refinery expansion

  • 4DEA System

    Typical System Capacity Needs Regenerators

    Regenerator Capacity

    Available Excess

    Capacity431 1250 B/H 431-A 900 B/H

    431-B 600 B/H 250 B/H436 1750 B/H 436-A 1000 B/H

    436-B 1000 B/H 250 B/H441 2500 B/H 441 3000 B/H 500 B/H

    5500 B/H 6500 B/H 1000 B/H

    DEA Regeneration OverviewPlant Amine Regenerators

    Built in 1995 - Part of major sulfur/refinery expansion

    DEA Regeneration Overview Contd

    Gas Phase Contactors: Liquid Phase Contactors:Unit Process Stream Unit Process Stream

    230 GP Fuel Gas ARU C3/C5 Idle631-A&B Recycle H2 LPG LPG

    632 Recycle H2 FCCU Liquid PPs633 Recycle H2 736 Liquid PPs634 Recycle H2 737 Liquid PPs635 Recycle H2636 Recycle H2

    FCCU Dry Gas736 Dry Gas737 Dry GasMag Recycle H2BTU Recycle H2

    There are 17 Amine Absorbers in the Refinery

  • 5DEA Regeneration Overview Contd

    Amine Loading Lean amine loading 0.01-0.02 mol H2S/mol solvent Rich amine loading 0.4-0.6 mol H2S/mol solvent

    Amine Velocities Lean/Rich velocities between 4-7 ft/sec No PWHT on older amine system piping

    1 out of 3 systems

    Corrosion Rates Corrosion coupons indicate 8-16 mils/yr on rich amine

    system piping

    Amine Regenerator Flow Diagram

  • 6431-A&B DEA REGENERATORS

    431-A 431-B

    436-A&B DEA REGENERATORS

  • 7441 DEA REGENERATOR

    Unit Limitations

    Amine Regenerators Lean amine cooling In excess of 140oF Rate limitations Already at 125% of design capacity Reboiler duty Steam supply limitation Throw-away limitation For ammonia control Metallurgy limitations No PWHT

    Amine Piping Line velocities (specially around control loops)

    Single Storage Tank Feeds all Three Systems Rich Amine Flash Drums

    With higher rates amine retention times are reduced

  • 8Contactor Limitations Absorbers

    Lean amine cooling Rich amine loading Instrumentation limitations CO2 loading Metallurgy limitations No PWHT

    Amine Piping (IBL) Line velocities (rich amine return outlet) Hydraulic constraints

    Contactor Limitations ContdBrimstone Analysis

    Component Molar%

    H2 14.394N2 7.44

    CH4 36.002CO 1.293CO2 1.669C2H4 17.984C2H6 15.118H2S 0.581C3H8 2.927i-C4 1.049n-C4 0.925i-C5 0.382n-C5 0.174C6+ 0.062Total 100

    Untreated 732 Before LE-713

    High CO2 in the contactor feed

  • 9Contactor Limitations ContdBrimstone Analysis

    CO2 within acceptable range

    Component Molar%

    H2 14.104N2 7.593

    CH4 36.969CO 1.279CO2 0.369C2H4 18.465C2H6 15.471H2S Non DetectedC3H8 2.784i-C4 1.099n-C4 1.076i-C5 0.474n-C5 0.215C6+ 0.102Total 100

    Treated 732 Before LE-713

    Contactor Limitations Contd

    Component Molar%

    H2 6.293N2 0.095

    CH4 51.506CO 0.534CO2 0.231C2H4 2.277C2H6 20.437H2S 11.072C3H8 7.433i-C4 0.058n-C4 0.041i-C5 0.006n-C5 0.019C6+ Non DetectedTotal 100.0

    Untreated 737 Before LE-713

    No CO2 concern on this contactorBrimstone Analysis

  • 10

    Available Options

    Capital Upgrade Upgrade existing

    regenerator(s) Invest on new

    regenerator

    Solvent Upgrade Upgrade single

    amine system Upgrade entire

    amine system (three amine systems)

    Available Options Contd

    Capital Upgrade Time constraints ROI below 50% OBL piping

    upgrades would be required

    Solvent Upgrade Relatively quick

    transition ROI at 75% No equipment

    upgrades would be necessary

  • 11

    Solvent Upgrade

    Engineering analysis was performed on entire amine system Simulations were constructed with new solvent

    properties for amine system including contactors Economics were evaluated

    Energy savings Reliability Solvent losses Solvent selection Solvent percent strength

    Choice was to upgrade solvent on the entire amine system

    Solvent Upgrade Contd

    Initial charge was performed using UcarsolTM to get system volume up to desired UcarsolTM LE-713 formulation

    Due to the large system volume capacity ~600,000 gallon Solvent strength was to be stepped in three different

    phases 30% 35% (target) 40% (if needed)

    Solvent loaded directly into the individual systems Monitor closely solvent losses Monitor solvent performance for absorbers in different

    service

  • 12

    Solvent Upgrade Contd Target UcarsolTM LE-713 formulation was

    achieved approximately 4 months from the time that system was initially charged Primary driver for the extended time was cost Fresh amine tank was then converted to UcarsolTM LE-

    713 tank System leveled at 35 wt% on solvent strength Fresh amine tank was then converted to UcarsolTM

    LE-713 tank Brimstone Engineering Services conducted plant

    wide performance testing Testing performed before initial charge Testing performed 1 year after system was at steady

    state

    Solvent Upgrade Contd Systems in place for monitoring

    Purchased state of the art GC for in house sampling Training to mitigate system losses

    Technical department Operations department

    Supplier Involvement

    Instrumentation upgrades on key amine absorbers Updated control configuration Temperature control Upgraded analyzers Real time rich loading equations

    More intense corrosion monitoring system Going away from corrosion probes and focusing more on TML

    readings Ion exchange system for anion and HSAS control

  • 13

    Solvent Upgrade Contd

    Current Situation Amine concentration at 40 wt%

    Primarily from circulation reduction

    Energy savings 27.5 MMBtu/hr Amine losses Down by17%

    Primarily due to increased awareness and training Better instrumentation on amine absorbers

    Solvent Upgrade Contd

    Current Situation Amine Loading

    Lean amine loading 0.01-0.015 mol H2S/mol solvent

    Rich amine loading 0.4-0.45 mol H2S/mol solvent

    Amine Velocities Lean/Rich velocities

  • 14

    Summary

    Solvent upgrade was successfully completed Refinery has increased solvent concentration for

    energy savings (currently at 40%) COS and trace sulfur species removal was within

    target after solvent upgrade No equipment upgrades No unit shutdowns were required

    What Changed Since 2002?

    FCCU Dry Gas Contactor CO2 specifications changed New contract signed in conjunction with a

    compression station New CO2 specification at 500 ppmv

    Operation of FCCU has changed over the last two years causing more CO2 slip to the absorber

  • 15

    What Changed Since 2002?

    Pilot plant data (tests performed at DOWs pilot plant facilities) confirmed that a solvent upgrade was required to meet product specification

    Solvent upgrade would be specific to this system only Upgrade is planned for 2nd week of October

    Equipment that would allow system optimization had to be installed

    What Changed Since 2002?

    Equipment that would allow system optimization had to be installed Installation complete

    Training on new system Technical department Operations department

    Product exports to 3rd party facility to begin in November

    Supplier Involvement