Blatnik Bridge Virtual Open House #1 Pat Huston | MnDOT District 1 Pippi Mayfield | MnDOT District 1 Jessica Felix | WisDOT Northwest Region Beth Kunkel | Kimley-Horn September 10, 2020

Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

Blatnik Bridge Virtual Open House #1

Pat Huston | MnDOT District 1 Pippi Mayfield | MnDOT District 1

Jessica Felix | WisDOT Northwest Region Beth Kunkel | Kimley-Horn

September 10, 2020

Page 2: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

2

Welcome

• Project website: MnDOT: https://www.dot.state.mn.us/d1/projects/blatnik-bridge/

• Contact: Pat Huston, MnDOT District 1 Major Projects [email protected] (218) 348-9902

Page 3: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

3

Introductions

• MnDOT District 1:

• Duane Hill – District Engineer

• Pat Huston – Project Director

• WisDOT NW Region Team:

• Jessica Felix – Deputy Director

• Tim Mason – Planning and Operations Chief

• MnDOT Blatnik Team:

• John Krysiak – Project Manager

• Pippi Mayfield – Communications

• Keith Molnau – Bridge

• WisDOT Blatnik Team:

• Marc Bowker – Project Manager

• Christena O’Brien –Communications

• Aaron Bonk – Bridge

• Consultants:

• Vince Gastoni – Parsons: Project Management, Bridge Alternatives

• Beth Kunkel – Kimley-Horn: Outreach & Environmental

• SRF: Traffic

• SEH: Geometric Alternatives

Page 4: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

4

Partnership – MnDOT and WisDOT

• Two DOTs but one Twin Ports

• Frequent Collaboration

• Border bridges

• Maintenance

• Inspection

Top: Eisenhower Bridge of Valor

Bottom: Snooper truck / inspection

Page 5: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

5

Agenda

• Provide an overview

• Blatnik Bridge history

• Scope of the project

• Project process

• Outreach opportunities

• Key decision-making happens now - next 12 to 24 months

Page 6: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

6

Why are we here?

• Significant deterioration developed in truss elements

• Maintenance issues• Safety inspection required yearly

• Additional maintenance ongoing

• Structural maintenance required every 4 years for safety and serviceability

• Next project scheduled for 2022

Page 7: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

7

Why are you here?

Page 8: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

8

Do we need two bridges?

• Considerations• Service and maintenance require closures or lane

restrictions

• Redundancy

• Freight efficiency, emergency response, accessibility

Photos: 1994 redecking

Page 9: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

9

Blatnik Bridge Facts (1/2)

• Opened to traffic in 1961

• Connects Duluth, MN and Superior, WI via I-535/US 53

• 120 foot maximum vertical clearance over St. Louis River/Bay

• 52 total spans; navigation channel 600 ft

• Carries 4 traffic lanes (2 in each direction)

• Accommodates 33,021 vehicles per day (2019)

• Permit load restriction due to condition

Photo: Archival photo of bridge

Page 10: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

10

Blatnik Bridge Facts (2/2)

• At nearly 8,000 feet long it is the second longest bridge in MN and third longest in WI, spanning the Twin Ports

• The Twin Ports is the largest port on the Great Lakes with 800 vessel visits annually

Page 11: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

11

Blatnik Bridge History (1/8)

• 1958: High Bridge under construction, with the interstate bridge underneath.

Page 12: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

12

Blatnik Bridge History (2/8)

• 1959: Looking towards Duluth from atop the High Bridge while it is under construction. The St. Louis Bay Bridge is at the upper left.

Page 13: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

13

Blatnik Bridge History (3/8)

• 1960: An aerial view, looking from Superior toward Duluth, of the High Bridge under construction.

Page 14: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

14

Blatnik Bridge History (4/8)

• 1960: Looking toward Superior during construction, with the Interstate Bridge on the left.

Page 15: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

15

Blatnik Bridge History (5/8)

• 1960: The steel framework of the High Bridge – later known as the Blatnik Bridge – rises above St. Louis Bay.

Page 16: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

16

Blatnik Bridge History (6/8)

• 1961: Workers pour concrete on the High Bridge. St. Louis Bay can be seen in the background.

Page 17: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

17

Blatnik Bridge History (7/8)

• 1961: Crowds gather on the High Bridge on grand opening day, December 2. Minnesota Gov. Elmer Anderson speaks at the official grand opening.

Page 18: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

18

Blatnik Bridge History (8/8)

• 1994: View from the top of the Blatnik Bridge looking toward Duluth, as the bridge undergoes reconstruction in 1994. Port Terminal is to the right.

Page 19: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

19

Blatnik Bridge Maintenance History (1/2)

• 1958 – 1961: Construction

• 1961: Opens to traffic• Designed for max vehicle weight of 154,000 pounds

• 1973: Median change from curb to median barrier

• 1994: Widening project

• 1995: Painting and repair project

• 2008: Emergency gusset repair and spot paint• First load restriction to 80,000 pounds

Page 20: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

20

Blatnik Bridge Maintenance History (2/2)

• 2010: Suspender rope replacement project

• 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system• Changed max vehicle weight back to 154,000 pounds

• 2016: Repair project (emergency gussets and cable)• Load rating reduced again to 104,000 pounds

• 2019: Inspection • Load rating further reduced to 80,000 pounds (legal loads only)

• 2021/2022: Planned maintenance work

Page 21: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

21

What is a legal load? (1/2)

Page 22: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

22

What is a legal load? (2/2)

Note: 2020 is partial year data and includes restrictions in Superior, WI

Page 23: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

23

What is being investigated?

• Project purpose:

• Safe crossing of the Saint Louis Bay navigation channel

• Evaluate rehabilitation or replacement of truss

• Evaluate the option of extending service life of the approach spans or replace in entirety

• On existing or new alignment

Page 24: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

24

Blatnik Bridge – Truss Spans

• Navigation channel

• 600 ft span

• 120 ft clearance

• Truss – 1,140 ft long

Page 25: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

25

Blatnik Bridge – Approach Spans

A span is the segment of bridge between two piers, or a pier and an abutmentApproach spans:

• 49 approach spans • 14 piers – MN side• 33 piers – WI side

Truss spans:• 3 truss spans

• 4 piers

Page 26: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

26

Blatnik Bridge Today

Page 27: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

27

Why now? (1/2)

• Significant deterioration developed in truss elements

• Maintenance issues• Safety inspection required yearly

• Additional maintenance ongoing

• Structural maintenance required every 4 years for safety and serviceability

• Next project scheduled for 2022

Page 28: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

28

Why now? (2/2)

• June 2019 – Load restriction at 80,000 pounds and can no longer accommodate overweight loads

• Increased road user delays due to more frequent bridge maintenance activities and inspections

• Planning and design process takes several years

• Key decision-making needed in next 12 to 24 months

Page 29: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

29

What will it cost?

• Project scoping and preliminary engineering has not been completed on the Blatnik Bridge project to date

• Appropriate project cost levels cannot be determined without that work

• High level planning cost estimates for a range of alternatives will be developed by the project team

• Scoping level cost estimates will be developed as part of the Blatnik preliminary engineering contract

• Timeframe: 2-3 years

• MnDOT/WisDOT share costs on all border bridges

Page 30: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

30

What do we know now?

• Multiple studies have been completed:

• Bridge Management Study (2017)

• MnDOT Existing Bridge Condition Assessment (2018 to present)

• Load rating analysis (2019)

• Subsurface pile investigation (2020)

• Freight and Traffic Model (2019)

• WisDOT Safety and Operational Study of US 53 and City of Superior (2019)

Page 31: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

31

How long before construction starts?

• 2020 to 2024: Preferred Alternative Selection and Environmental Documentation

• 2024 to 2026: Preliminary Design

• 2026 to 2028: Final Design

• 2028 to 2031: Construction

Page 32: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

32

Where are we in the NEPA process?

2020 2021 2022 2023 2024

Define framework for scope Select Alternative Environmental Documentation

Kickoff

Develop Concepts

Purpose and Need

Preliminary Layouts

Alternatives Evaluation

Select Preferred

Alternative

Environmental Studies

EA/EAW Documentation

FONSI

Public and Stakeholder Engagement

Page 33: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

33

What happens next?

• Preliminary design steps:

• Develop purpose and need statement

• Develop screening criteria

• Develop potential alternatives

• Screen alternatives to determine feasible alternatives for further study

• Evaluate social, economic, and environmental impacts for feasible alternatives

• Select preferred alternative

Page 34: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

34

Blatnik Bridge Location and Study Area

Page 35: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

35

How will an environmental review be conducted?

• Documentation will include:

• Purpose and need

• Evaluation of alternatives

• Impact assessment

• Natural, cultural, social

• Environmental commitments

• Preferred alternative

• DOT/FHWA approvals

Page 36: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

36

How can I get involved, stay informed?

• Inform

• Project website / Govdelivery sign up

• Public Information Meetings (~monthly)

• Open houses

• Consult

• Stakeholder small group meetings

• Collaborate

• Public Advisory Committee (PAC)

Page 37: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

28

Questions?

Project Website: MnDOT: https://www.dot.state.mn.us/d1/projects/blatnik-bridge/

WisDOT: https://wisconsindot.gov/Pages/projects/by-region/nw/blatnikbridge/default.aspx

Contact: Pat Huston, MnDOT District 1 Major Projects Engineer

(218)348-9902 [email protected]

Pippi Mayfield, MnDOT District 1 Public Engagement and Communications Director (218) 348-9902 [email protected]

Page 38: Blatnik Bridge Virtual Open House #1...2020/09/10  · • 2012 - 2013: Repaint truss in splash zone, perform truss strengthening and install new lighting system • Changed max vehicle

Thank you!