April 19-21, 2016
Blaine Pritchett, P.E.PCGP Project DirectorWilliams Company
2© 2012 The Williams Companies, Inc. All rights reserved.
3© 2012 The Williams Companies, Inc. All rights reserved.
Presentation Topics
Project ScopePipeline Precedent AgreementsLand Classification and Acquisition ProgressPermitsTheoretical Project TimelineEPC TenderProject OppositionProject Support
4© 2012 The Williams Companies, Inc. All rights reserved.
Williams Northwest Pipeline in Oregon1956/1963 year built750 miles of pipe12”-30” pipeline size7 compressor stations50 MLV’s
5© 2012 The Williams Companies, Inc. All rights reserved.
PCGP Fact Sheet
$1.74B+ private investment232-mile 36-inch diameter pipelineProvides up to 1,060,000 Dth/d of firm transportation1,480 psig Maximum Allowable Operating Pressure223 miles of Class 1 location; rural population density1 compressor station with 61,500 of installed HP2 receipt and 2 delivery meter stations
17 mainline valves; 3 intermediate launcher/receivers50-foot wide permanent easement + 45-foot
construction easement
6© 2012 The Williams Companies, Inc. All rights reserved.
Pipeline Precedent Agreements Executed
817,354 Dth/d of firm service contracted77% of pipeline capacity subscribedMacquarie Energy LLC agreement for 215,000 Dth/d firm serviceAvista Corp. agreement for 10,000 Dth/d firm serviceJordan Cover Energy Project agreement for 592,354 Dth/d firm serviceReserves capacity for JERA, ITOCHU, and JCEP
sales
Open Season2016Opportunity to subscribe to the remaining capacity
7© 2012 The Williams Companies, Inc. All rights reserved.
Land Ownership Classification
Land ClassificationDescription Miles % of RoutePublic Lands 75 32%
Private Lands 96 41%
Timber Company Lands 61 27%
TOTAL 232 100%
8© 2012 The Williams Companies, Inc. All rights reserved.
Timberlands Classification
Timber ClassificationDescription MilesOld Growth(100+ yr old timber stands)
41
Mid-Seral(40-100 yr old stands)
44
Reproduction and Clear Cut(0-40 yr olds stands)
61
TOTAL 146
47% of the remaining land classified as agricultural, range land, and off shore
9© 2012 The Williams Companies, Inc. All rights reserved.
Land Rights Acquisition Progress
Land Rights AcquisitionDescription Landowners1 Land Rights AcquiredPublic Lands 3 0
Private Lands 264 66
Timber Company Lands 23 2
TOTAL 290 68
Limited land acquisition program pre FID
90% of route landowners granted survey permission
Limited condemnation proceedings
1. Permanent right of way, construction right of way, and temporary extra work areas
10© 2012 The Williams Companies, Inc. All rights reserved.
PermitsEnvironmental Permits
7 Federal Permit Agencies8 State Permit Agencies4 County Permit Agencies
Non-Environmental Permits183 crossing permits: roads, railroads, transmission lines, etc.
Critical Path Environmental PermitsFERC CertificateBureau of Land Management Record of Decision and Land Grant
Permits Received to DateFederal and State - 0County - 4 (Conditional Use Permits)
11© 2012 The Williams Companies, Inc. All rights reserved.
Potential Pipeline Project Timeline
PermitsLand RightsFinal Investment DecisionEngineeringProcurementConstructionCommissioningFirst Gas
Months MonthsTaskYear 1 Year 2Months Months
Year 3Months
Year 5Year 4
12© 2012 The Williams Companies, Inc. All rights reserved.
Solicit Tender from 5 EPC Contractors April 20164 months for EPC Contractors to prepare and submit TenderAward EPC Contract by the end of 2016
2016 EPC Construction Strategy
13© 2012 The Williams Companies, Inc. All rights reserved.
Current OppositionProtest• Pacific Connector land office, Medford, Oregon on 8/7/2015 and 9/30/2015• Will not impede on any citizens constitutional right of freedom of speech or to peaceably
assemble.
ture Oppositionmples of Direct ons:ree Sittingripodsleeping Dragons
David Ludlum, Executive Director, West Slope Colorado Oil and Gas AssociationPat McCown, Williams Parachute Plant Manager of OperationsRockies Producers who submitted support letters to FERCPublic Officials and Organizations who submitted support letters to FERCAll project proponents are encouraged to submit their expression of Project support on the FERC web siteFERC Docket Number CP13-492-000
and CP13-483-000
ANK YOU
Questions