. Site Activity Work-Days(Planned)
Start Finish
NIHP - PROJECT SCHEDULE (REV. FC-01) - 30 JUN '14 FC, 30 APR '17 SCNIHP - PROJECT SCHEDULE (REV. FC-01) - 30 JUN '14 FC, 30 APR '17 SCNIHP - PROJECT SCHEDULE (REV. FC-01) - 30 JUN '14 FC, 30 APR '17 SCNIHP - PROJECT SCHEDULE (REV. FC-01) - 30 JUN '14 FC, 30 APR '17 SCNIHP - PROJECT SCHEDULE (REV. FC-01) - 30 JUN '14 FC, 30 APR '17 SCNIHP - PROJECT SCHEDULE (REV. FC-01) - 30 JUN '14 FC, 30 APR '17 SC
KEY MILESTONES & SUMMARY OVERVIEWKEY MILESTONES & SUMMARY OVERVIEWKEY MILESTONES & SUMMARY OVERVIEWKEY MILESTONES & SUMMARY OVERVIEWKEY MILESTONES & SUMMARY OVERVIEWKEY MILESTONES & SUMMARY OVERVIEW
KICKOFFKICKOFFKICKOFFKICKOFFKICKOFF
. CR+CV PREFERRED PROPONENT
. CR+CV KICK-OFF MEETING WITH VIHA
CR+CV FINANCIAL CLOSE
DESIGNDESIGNDESIGNDESIGNDESIGN
CR+CV DESIGN - SD FORMAL SUBMISSION
CR+CV OBTAIN EXCAVATION PERMITS
CR+CV OBTAIN FOUNDATION PERMITS
CR+CV OBTAIN STRUCTURE & ENVELOPE PERMITS
CR+CV DESIGN - DD FORMAL SUBMISSION
CR+CV OBTAIN FULL BUILDING PERMITS
CR+CV DESIGN - CD 50% FITOUT SUBMISSION (L0 & L1)
CR+CV DESIGN - CD 50% FITOUT SUBMISSION (L2 +)
CR+CV DESIGN - CD 95% FITOUT SUBMISSION
CAMPBELL RIVERCAMPBELL RIVERCAMPBELL RIVERCAMPBELL RIVERCAMPBELL RIVER
CR CRH - POSSESSION OF SITE
CR CRH - START FOUNDATIONS
CR CRH - START SUSPENDED SLABS (L1)
CR CRH - START EXTERIOR WALLS (L1)
CR CRH - START INTERIOR LAYOUT & ROUGH-IN (L1)
CR CRH - FINISH SUSPENDED SLABS (L4)
CR CRH - START INTERIOR DRYWALL BOARD (L1)
CR CRH - ENVELOPE SUBSTANTIALLY WEATHERTIGHT (L4)
CR CRH - MAIN ELEC. RM ENERGIZED (L0)
CR CRH - START BUILDING SYSTEMS COMMISSIONING
CR CRH - INTERIOR FITOUT & FINISHES COMPLETE (L3)
CR CRH - OCCUPANCY & SUBSTANTIAL COMPLETION
CR CRH - (FIRST) SERVICE COMMENCEMENT
CR CRH - ZONE B SITE COMPLETION
DESIGN (BOTH SITES)DESIGN (BOTH SITES)DESIGN (BOTH SITES)DESIGN (BOTH SITES)DESIGN (BOTH SITES)DESIGN (BOTH SITES)
SCHEMATIC DESIGNSCHEMATIC DESIGNSCHEMATIC DESIGNSCHEMATIC DESIGNSCHEMATIC DESIGN
SD - DRAFT SUBMISSIONSSD - DRAFT SUBMISSIONSSD - DRAFT SUBMISSIONSSD - DRAFT SUBMISSIONSSD - DRAFT SUBMISSIONS
SD CYCLE #01SD CYCLE #01SD CYCLE #01SD CYCLE #01SD CYCLE #01
CR+CV SD #01 - Design Concept Validation with Core User Group
CR+CV SD #01 - Prepare Draft Submittal Material (at Risk)
CR+CV SD #01 - Issue Draft Submittal Material to VIHA
CR+CV SD #01 - Clinical User Consultation Mtgs
CR+CV SD #01 - Technical User Consultation Mtgs
CR+CV SD #01 - Distribute Live Minutes
CR+CV SD #01 - VIHA Informal Comments
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Black Bars = Critical Tasks
Red Bars = Near-Critical Tasks (Float < 2mo)
Blue/Aqua Bars = Non-Critical Tasks
NIHP - PROJECT SCHEDULE (REV. FC-01) - 30 JUN '14 FC, 30 APR '17 SC
CRH PROJECT SCHEDULE
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 1 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
SD CYCLE #02SD CYCLE #02SD CYCLE #02SD CYCLE #02SD CYCLE #02
CR+CV SD #02 - Incorporate Comments from SD #01
CR+CV SD #02 - Clinical User Consultation Mtgs
CR+CV SD #02 - Technical User Consultation Mtgs
CR+CV SD #02 - Distribute Live Minutes
CR+CV SD #02 - VIHA Informal Comments
SD - FORMAL SUBMISSIONSD - FORMAL SUBMISSIONSD - FORMAL SUBMISSIONSD - FORMAL SUBMISSIONSD - FORMAL SUBMISSION
CR+CV SD (Formal) - Prepare Submittal Pkg
CR+CV SD (Formal) - Issue Submittal Pkg to VIHA
CR+CV SD (Formal) - Presentation to VIHA
CR+CV SD (Formal) - VIHA Review Period
CR+CV SD (Formal) - Distribute VIHA Comments
CR+CV SD (Formal) - Close-out VIHA Comments
CR+CV SD (Formal) - Obtain "Reviewed" Status
DESIGN DEVELOPMENTDESIGN DEVELOPMENTDESIGN DEVELOPMENTDESIGN DEVELOPMENTDESIGN DEVELOPMENT
DD - DRAFT SUBMISSIONSDD - DRAFT SUBMISSIONSDD - DRAFT SUBMISSIONSDD - DRAFT SUBMISSIONSDD - DRAFT SUBMISSIONS
DD CYCLE #01DD CYCLE #01DD CYCLE #01DD CYCLE #01DD CYCLE #01
CR+CV DD #01 - Prepare Draft Subject Material for Consultation Mtgs
CR+CV DD #01 - Issue Draft Subject Material to VIHA
CR+CV DD #01 - Clinical User Consultation Mtgs
CR+CV DD #01 - Technical User Consultation Mtgs
CR+CV DD #01 - Distribute Live Minutes
CR+CV DD #01 - VIHA Informal Comments
DD CYCLE #02DD CYCLE #02DD CYCLE #02DD CYCLE #02DD CYCLE #02
CR+CV DD #02 - Prepare Draft Subject Material for Consultation Mtgs
CR+CV DD #02 - Issue Draft Subject Material to VIHA
CR+CV DD #02 - Clinical User Consultation Mtgs
CR+CV DD #02 - Technical User Consultation Mtgs
CR+CV DD #02 - Distribute Live Minutes
CR+CV DD #02 - VIHA Informal Comments
DD CYCLE #03DD CYCLE #03DD CYCLE #03DD CYCLE #03DD CYCLE #03
CR+CV DD #03 - Prepare Draft Subject Material for Consultation Mtgs
CR+CV DD #03 - Issue Draft Subject Material to VIHA
CR+CV DD #03 - Clinical User Consultation Mtgs
CR+CV DD #03 - Technical User Consultation Mtgs
CR+CV DD #03 - Distribute Live Minutes
CR+CV DD #03 - VIHA Informal Comments
DD - FORMAL SUBMISSIONDD - FORMAL SUBMISSIONDD - FORMAL SUBMISSIONDD - FORMAL SUBMISSIONDD - FORMAL SUBMISSION
CR+CV DD (Formal) - Prepare Submittal Pkg
CR+CV DD (Formal) - Issue Submittal Pkg to VIHA (& Cities for Permit)
CR+CV DD (Formal) - Presentation to VIHA
CR+CV DD (Formal) - VIHA Review Period
CR+CV DD (Formal) - Distribute VIHA Comments
CR+CV DD (Formal) - Close-out VIHA Comments
CR+CV DD (Formal) - Obtain "Reviewed" Status
MOCK-UPSMOCK-UPSMOCK-UPSMOCK-UPSMOCK-UPS
PHASE 1 - 1:1 SCALE TAPE MARKINGSPHASE 1 - 1:1 SCALE TAPE MARKINGSPHASE 1 - 1:1 SCALE TAPE MARKINGSPHASE 1 - 1:1 SCALE TAPE MARKINGSPHASE 1 - 1:1 SCALE TAPE MARKINGS
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 2 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CR+CV Mockups (Ph. 1 - SD #01) - Prepare
CR+CV Mockups (Ph. 1 - SD #01) - Review
CR+CV Mockups (Ph. 1 - SD #02) - Prepare
CR+CV Mockups (Ph. 1 - SD #02) - Review
PHASE 2 - 3D RENDERINGSPHASE 2 - 3D RENDERINGSPHASE 2 - 3D RENDERINGSPHASE 2 - 3D RENDERINGSPHASE 2 - 3D RENDERINGS
CR+CV Mockups (Ph. 2 - SD #01) - Prepare
CR+CV Mockups (Ph. 2 - SD #01) - Review
CR+CV Mockups (Ph. 2 - SD #02) - Prepare
CR+CV Mockups (Ph. 2 - SD #02) - Review
PHASE 3 - FULLY CONSTRUCTED OFF-SITEPHASE 3 - FULLY CONSTRUCTED OFF-SITEPHASE 3 - FULLY CONSTRUCTED OFF-SITEPHASE 3 - FULLY CONSTRUCTED OFF-SITEPHASE 3 - FULLY CONSTRUCTED OFF-SITE
CR+CV Mockups (Ph. 3 - DD #01) - Prepare
CR+CV Mockups (Ph. 3 - DD #02) - Prepare
CR+CV Mockups (Ph. 3 - DD #02) - Review
CR+CV Mockups (Ph. 3 - DD #01) - Review
CR+CV Mockups (Ph. 3 - DD #03) - Prepare
CR+CV Mockups (Ph. 3 - DD #03) - Review
PHASE 4 - IN-SITU PROTOTYPESPHASE 4 - IN-SITU PROTOTYPESPHASE 4 - IN-SITU PROTOTYPESPHASE 4 - IN-SITU PROTOTYPESPHASE 4 - IN-SITU PROTOTYPES
CR+CV Mockups (Ph. 4 - Fitout CD 95%) - Prepare
CR+CV Mockups (Ph. 4 - Fitout CD 95%) - Review
CR+CV Mockups (Ph. 4 - Fitout CD IFC) - Prepare
CR+CV Mockups (Ph. 4 - Fitout CD IFC) - Review
PERMITSPERMITSPERMITSPERMITSPERMITS
TREE CLEARING PERMITSTREE CLEARING PERMITSTREE CLEARING PERMITSTREE CLEARING PERMITSTREE CLEARING PERMITS
CR+CV Permits (Tree Clearing) - Prepare Application Packages (at Risk)
CR+CV Permits (Tree Clearing) - Submit Applications to Cities
CR+CV Permits (Tree Clearing) - Cities Rvw Period & Issue
EXCAVATION PERMITSEXCAVATION PERMITSEXCAVATION PERMITSEXCAVATION PERMITSEXCAVATION PERMITS
CR+CV Permits (Excav.) - Prepare Application Packages (at Risk)
CR+CV Permits (Excav.) - Submit Applications to Cities
CR+CV Permits (Excav.) - Cities Rvw Period & Issue
GEOTECHNICAL PERMIT (CRH ONLY)GEOTECHNICAL PERMIT (CRH ONLY)GEOTECHNICAL PERMIT (CRH ONLY)GEOTECHNICAL PERMIT (CRH ONLY)GEOTECHNICAL PERMIT (CRH ONLY)
CR Permit (Geotech - CRH) - Prepare Application Package (at Risk)
CR Permit (Geotech - CRH) - Submit Applications to Cities
CR Permit (Geotech - CRH) - Cities Rvw Period & Issue
FOUNDATION PERMITSFOUNDATION PERMITSFOUNDATION PERMITSFOUNDATION PERMITSFOUNDATION PERMITS
CR+CV Permits (Fdns) - Prepare Application Packages (at Risk)
CR+CV Permits (Fdns) - Submit Applications to Cities
CR+CV Permits (Fdns) - Cities Rvw Period & Issue
STRUCTURE/ENVELOPE PERMITSSTRUCTURE/ENVELOPE PERMITSSTRUCTURE/ENVELOPE PERMITSSTRUCTURE/ENVELOPE PERMITSSTRUCTURE/ENVELOPE PERMITS
CR+CV Permits (Struc./Env.) - Prepare Application Packages
CR+CV Permits (Struc./Env.) - Submit Applications to Cities
CR+CV Permits (Struc./Env.) - Cities Rvw Period & Issue
FULL BUILDING PERMITSFULL BUILDING PERMITSFULL BUILDING PERMITSFULL BUILDING PERMITSFULL BUILDING PERMITS
CR+CV Permits (Full Bldg) - Prepare Application Packages
CR+CV Permits (Full Bldg) - Submit Applications to Cities
CR+CV Permits (Full Bldg) - Cities Rvw Period & Issue
WORK PACKAGESWORK PACKAGESWORK PACKAGESWORK PACKAGESWORK PACKAGES
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 3 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
SITE PREPARATIONSITE PREPARATIONSITE PREPARATIONSITE PREPARATIONSITE PREPARATION
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Site Prep. (95% CD) - Design (at Risk) & Prepare Submittal Pkg
CR+CV Site Prep. (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Site Prep. (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Site Prep. (IFC CD) - Prep. & Issue
ELEVATORSELEVATORSELEVATORSELEVATORSELEVATORS
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV Elev (50% CD) - Design (at Risk) & Prepare Submittal Pkg
CR+CV Elev (50% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Elev (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Elev (95% CD) - Design & Prepare Submittal Pkg
CR+CV Elev (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Elev (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Elev (IFC CD) - Prep. & Issue
FOUNDATIONSFOUNDATIONSFOUNDATIONSFOUNDATIONSFOUNDATIONS
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV Fdns (50% CD) - Design (at Risk) & Prepare Submittal Pkg
CR+CV Fdns (50% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Fdns (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Fdns (95% CD) - Design & Prepare Submittal Pkg
CR+CV Fdns (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Fdns (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Fdns (IFC CD) - Prep. & Issue
STRUCTURESTRUCTURESTRUCTURESTRUCTURESTRUCTURE
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV Struc (50% CD) - Design (at Risk) & Prepare Submittal Pkg
CR+CV Struc (50% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Struc (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Struc (95% CD) - Design & Prepare Submittal Pkg
CR+CV Struc (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Struc (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Struc (IFC CD - Fwk + Rebar) - Prep. & Issue
CR+CV Struc (IFC CD - L1 Sleeving + Embeds) - Prep. & Issue
CR+CV Struc (IFC CD - Struc. Steel + Pkd) - Prep. & Issue
CR+CV Struc (IFC CD - L2+ Sleeving + Embeds) - Prep. & Issue
CR+CV Struc (IFC CD - M/E Under SoG) - Prep. & Issue
ENVELOPEENVELOPEENVELOPEENVELOPEENVELOPE
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV Env (50% CD) - Design (at Risk) & Prepare Submittal Pkg
CR+CV Env (50% CD) - Issue for VIHA Compliance Team Rvw
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 4 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CR+CV Env (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Env (95% CD) - Design & Prepare Submittal Pkg
CR+CV Env (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Env (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Env (IFC CD) - Prep. & Issue
CIVIL & LANDSCAPINGCIVIL & LANDSCAPINGCIVIL & LANDSCAPINGCIVIL & LANDSCAPINGCIVIL & LANDSCAPING
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV Civil + LS (50% CD) - Design (at Risk) & Prepare Submittal Pkg
CR+CV Civil + LS (50% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Civil + LS (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Civil + LS (95% CD) - Design & Prepare Submittal Pkg
CR+CV Civil + LS (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Civil + LS (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Civil + LS (IFC CD - Deep Util.) - Prep. & Issue
CR+CV Civil + LS (IFC CD - Site Finishes) - Prep. & Issue
MAJOR MECH./ELEC. EQ'TMAJOR MECH./ELEC. EQ'TMAJOR MECH./ELEC. EQ'TMAJOR MECH./ELEC. EQ'TMAJOR MECH./ELEC. EQ'T
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV Major M/E Eq't (50% CD) - Design & Prepare Submittal Pkg
CR+CV Major M/E Eq't (50% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Major M/E Eq't (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Major M/E Eq't (95% CD) - Design & Prepare Submittal Pkg
CR+CV Major M/E Eq't (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Major M/E Eq't (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Major M/E Eq't (IFC CD) - Prep. & Issue
HELIPORTHELIPORTHELIPORTHELIPORTHELIPORT
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV Heliport (50% CD) - Design & Prepare Submittal Pkg
CR+CV Heliport (50% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Heliport (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Heliport (95% CD) - Design & Prepare Submittal Pkg
CR+CV Heliport (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Heliport (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Heliport (IFC CD) - Prep. & Issue
FLOOR LAYOUTS - WALL & DOOR FRAMINGFLOOR LAYOUTS - WALL & DOOR FRAMINGFLOOR LAYOUTS - WALL & DOOR FRAMINGFLOOR LAYOUTS - WALL & DOOR FRAMINGFLOOR LAYOUTS - WALL & DOOR FRAMING
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Floor Layouts (95% CD) - Design & Prepare Submittal Pkg
CR+CV Floor Layouts (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Floor Layouts (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Floor Layouts (IFC CD - Layout, Door Frames) - Prep. & Issue
M/E PRIMARY DISTRIBUTIONM/E PRIMARY DISTRIBUTIONM/E PRIMARY DISTRIBUTIONM/E PRIMARY DISTRIBUTIONM/E PRIMARY DISTRIBUTION
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 5 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV M/E Primary (50% CD) - Design & Prepare Submittal Pkg
CR+CV M/E Primary (50% CD) - Issue for VIHA Compliance Team Rvw
CR+CV M/E Primary (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV M/E Primary (95% CD) - Design & Prepare Submittal Pkg
CR+CV M/E Primary (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV M/E Primary (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV M/E Primary Dist'n (IFC CD) - Prep. & Issue
INTERIOR FITOUT & FINISHESINTERIOR FITOUT & FINISHESINTERIOR FITOUT & FINISHESINTERIOR FITOUT & FINISHESINTERIOR FITOUT & FINISHES
CD 50%CD 50%CD 50%CD 50%CD 50%
L0 & L1L0 & L1L0 & L1L0 & L1L0 & L1
CR+CV Fitout (50% CD - L0 & L1) - Design & Prepare Submittal Pkg
CR+CV Fitout (50% CD - L0 & L1) - Issue for VIHA + Compliance Team Rvw
CR+CV Fitout (50% CD - L0 & L1) - VIHA + Compliance Team Rvw & Issue Comments
CR+CV Fitout (50% CD - L0 & L1) - Distribute VIHA Comments
CR+CV Fitout (50% CD - L0 & L1) - Close-out VIHA Comments
CR+CV Fitout (50% CD - L0 & L1) - Obtain "Reviewed" Status
L2 +L2 +L2 +L2 +L2 +
CR+CV Fitout (50% CD - L2 +) - Design & Prepare Submittal Pkg
CR+CV Fitout (50% CD - L2 +) - Issue for VIHA + Compliance Team Rvw
CR+CV Fitout (50% CD - L2 +) - VIHA + Compliance Team Rvw & Issue Comments
CR+CV Fitout (50% CD - L2 +) - Distribute VIHA Comments
CR+CV Fitout (50% CD - L2 +) - Close-out VIHA Comments
CR+CV Fitout (50% CD - L2 +) - Obtain "Reviewed" Status
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Fitout (95% CD) - Design & Prepare Submittal Pkg
CR+CV Fitout (95% CD) - Issue for VIHA + Compliance Team Rvw
CR+CV Fitout (95% CD) - VIHA + Compliance Team Rvw & Issue Comments
CR+CV Fitout (95% CD) - Distribute VIHA Comments
CR+CV Fitout (95% CD) - Close-out VIHA Comments
CR+CV Fitout (95% CD) - Obtain "Reviewed" Status
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Fitout (IFC CD - L0 & L1 - Clg/Wall Rough-in) - Prep. & Issue
CR+CV Fitout (IFC CD - L2 + - Clg/Wall Rough-in) - Prep. & Issue
CR+CV Fitout (IFC CD - Finishes) - Prep. & Issue
FFE PROCUREMENTFFE PROCUREMENTFFE PROCUREMENTFFE PROCUREMENTFFE PROCUREMENTFFE PROCUREMENT
FFE - EQUIPMENT LISTFFE - EQUIPMENT LISTFFE - EQUIPMENT LISTFFE - EQUIPMENT LISTFFE - EQUIPMENT LIST
CR+CV FFE - Issue Updated Eq't List (3 Vendors per Item)
CR+CV FFE - Validate Eq't List Based on Schematic Design
FFE - MAJOR ITEMSFFE - MAJOR ITEMSFFE - MAJOR ITEMSFFE - MAJOR ITEMSFFE - MAJOR ITEMS
DIAGNOSTIC IMAGING EQ'TDIAGNOSTIC IMAGING EQ'TDIAGNOSTIC IMAGING EQ'TDIAGNOSTIC IMAGING EQ'TDIAGNOSTIC IMAGING EQ'T
CR+CV FFE (DI Eq't) - Prepare RFP
CR+CV FFE (DI Eq't) - Bid Response
CR+CV FFE (DI Eq't) - Bid Analysis
CR+CV FFE (DI Eq't) - Bid Award
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 6 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CR+CV FFE (DI Eq't) - Generate PO Req.
CR+CV FFE (DI Eq't) - Issue/Approve PO
CR+CV FFE (DI Eq't) - Shop Dwgs Prep. & Rvw (Initial Cycle)
CR+CV FFE (DI Eq't) - Shop Dwgs Prep. & Rvw (Final Cycle)
CR+CV FFE (DI Eq't) - Deliveries to Sites
LIGHT BOOMSLIGHT BOOMSLIGHT BOOMSLIGHT BOOMSLIGHT BOOMS
CR+CV FFE (Light Booms) - Prepare RFP
CR+CV FFE (Light Booms) - Bid Response
CR+CV FFE (Light Booms) - Bid Analysis
CR+CV FFE (Light Booms) - Bid Award
CR+CV FFE (Light Booms) - Generate PO Req.
CR+CV FFE (Light Booms) - Issue/Approve PO
CR+CV FFE (Light Booms) - Shop Dwgs Prep. & Rvw (Initial Cycle)
CR+CV FFE (Light Booms) - Shop Dwgs Prep. & Rvw (Final Cycle)
CR+CV FFE (Light Booms) - Deliveries to Sites
OPERATING ROOM BOOMSOPERATING ROOM BOOMSOPERATING ROOM BOOMSOPERATING ROOM BOOMSOPERATING ROOM BOOMS
CR+CV FFE (OR Booms) - Prepare RFP
CR+CV FFE (OR Booms) - Bid Response
CR+CV FFE (OR Booms) - Bid Analysis
CR+CV FFE (OR Booms) - Bid Award
CR+CV FFE (OR Booms) - Generate PO Req.
CR+CV FFE (OR Booms) - Issue/Approve PO
CR+CV FFE (OR Booms) - Shop Dwgs Prep. & Rvw (Initial Cycle)
CR+CV FFE (OR Booms) - Shop Dwgs Prep. & Rvw (Final Cycle)
CR+CV FFE (OR Booms) - Deliveries to Sites
FFE - OTHER ITEMSFFE - OTHER ITEMSFFE - OTHER ITEMSFFE - OTHER ITEMSFFE - OTHER ITEMS
ITEMS WITH STRUC. DESIGN IMPACTITEMS WITH STRUC. DESIGN IMPACTITEMS WITH STRUC. DESIGN IMPACTITEMS WITH STRUC. DESIGN IMPACTITEMS WITH STRUC. DESIGN IMPACT
CR+CV FFE (Struc. Impact) - Prepare RFPs
CR+CV FFE (Struc. Impact) - Bid Responses
CR+CV FFE (Struc. Impact) - Bid Analyses
CR+CV FFE (Struc. Impact) - Bid Awards
CR+CV FFE (Struc. Impact) - Generate PO Req.'s
CR+CV FFE (Struc. Impact) - Issue/Approve PO's
CR+CV FFE (Struc. Impact) - Shop Dwgs Prep. & Rvw (Initial Cycles)
CR+CV FFE (Struc. Impact) - Shop Dwgs Prep. & Rvw (Final Cycles)
CR+CV FFE (Struc. Impact) - Deliveries to Sites
ITEMS WITH FITOUT DESIGN IMPACTITEMS WITH FITOUT DESIGN IMPACTITEMS WITH FITOUT DESIGN IMPACTITEMS WITH FITOUT DESIGN IMPACTITEMS WITH FITOUT DESIGN IMPACT
CR+CV FFE (Fitout Impact) - Prepare RFPs
CR+CV FFE (Fitout Impact) - Bid Responses
CR+CV FFE (Fitout Impact) - Bid Analyses
CR+CV FFE (Fitout Impact) - Bid Awards
CR+CV FFE (Fitout Impact) - Generate PO Req.'s
CR+CV FFE (Fitout Impact) - Issue/Approve PO's
CR+CV FFE (Fitout Impact) - Shop Dwgs Prep. & Rvw (Initial Cycles)
CR+CV FFE (Fitout Impact) - Shop Dwgs Prep. & Rvw (Final Cycles)
CR+CV FFE (Fitout Impact) - Deliveries to Sites
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 7 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
ITEMS WITH NO DESIGN IMPACTITEMS WITH NO DESIGN IMPACTITEMS WITH NO DESIGN IMPACTITEMS WITH NO DESIGN IMPACTITEMS WITH NO DESIGN IMPACT
CR+CV FFE (Other) - Prepare RFPs
CR+CV FFE (Other) - Bid Responses
CR+CV FFE (Other) - Bid Analyses
CR+CV FFE (Other) - Bid Awards
CR+CV FFE (Other) - Generate PO Req.'s
CR+CV FFE (Other) - Issue/Approve PO's
CR+CV FFE (Other) - Shop Dwgs Prep. & Rvw (Initial Cycles)
CR+CV FFE (Other) - Shop Dwgs Prep. & Rvw (Final Cycles)
CR+CV FFE (Other) - Deliveries to Sites
CRH - CAMPBELL RIVER HOSPITALCRH - CAMPBELL RIVER HOSPITALCRH - CAMPBELL RIVER HOSPITALCRH - CAMPBELL RIVER HOSPITALCRH - CAMPBELL RIVER HOSPITALCRH - CAMPBELL RIVER HOSPITAL
CRH - PRE-CONSTRUCTIONCRH - PRE-CONSTRUCTIONCRH - PRE-CONSTRUCTIONCRH - PRE-CONSTRUCTIONCRH - PRE-CONSTRUCTION
CRH (PRE-CON) - SITE PREPARATIONCRH (PRE-CON) - SITE PREPARATIONCRH (PRE-CON) - SITE PREPARATIONCRH (PRE-CON) - SITE PREPARATIONCRH (PRE-CON) - SITE PREPARATION
CR Lead Time - Temp. Gas Main (Fortis)
CR Lead Time - Water Main
CRH (PRE-CON) - FOUNDATIONSCRH (PRE-CON) - FOUNDATIONSCRH (PRE-CON) - FOUNDATIONSCRH (PRE-CON) - FOUNDATIONSCRH (PRE-CON) - FOUNDATIONS
CR Lead Time - Rebar & Fwk (Fdns)
CR Lead Time - Rebar & Fwk (L0 Walls & Col's)
CRH (PRE-CON) - STRUCTURECRH (PRE-CON) - STRUCTURECRH (PRE-CON) - STRUCTURECRH (PRE-CON) - STRUCTURECRH (PRE-CON) - STRUCTURE
CR Lead Time - Rebar & Fwk (Susp. Slabs)
CR Lead Time - Struc. Steel (L4 PH + Stairs)
CR Lead Time - Parkade Precast
CR Lead Time - Helipad Structure
CRH (PRE-CON) - ENVELOPECRH (PRE-CON) - ENVELOPECRH (PRE-CON) - ENVELOPECRH (PRE-CON) - ENVELOPECRH (PRE-CON) - ENVELOPE
CR Lead Time - Curtain Wall
CR Lead Time - Ext. Wall Panel System (incl. Punch Windows)
CR Lead Time - Roofing
CR Lead Time - Ext. Finishes
CRH (PRE-CON) - FITOUT & FINISHESCRH (PRE-CON) - FITOUT & FINISHESCRH (PRE-CON) - FITOUT & FINISHESCRH (PRE-CON) - FITOUT & FINISHESCRH (PRE-CON) - FITOUT & FINISHES
EARLY ROUGH-IN ITEMSEARLY ROUGH-IN ITEMSEARLY ROUGH-IN ITEMSEARLY ROUGH-IN ITEMSEARLY ROUGH-IN ITEMS
CR Lead Time - M/E Primary Dist'n
L0 & L1L0 & L1L0 & L1L0 & L1L0 & L1
CR Lead Time - (L0 & L1) Doorframes
CR Lead Time - (L0 & L1) Steel Supports for Eq't
L2 +L2 +L2 +L2 +L2 +
CR Lead Time - (L2 +) Doorframes
CR Lead Time - (L2 +) Steel Supports for Eq't
MAJOR EQUIPMENT ITEMSMAJOR EQUIPMENT ITEMSMAJOR EQUIPMENT ITEMSMAJOR EQUIPMENT ITEMSMAJOR EQUIPMENT ITEMS
CR Lead Time - Elevators
CR Lead Time - Elec. Head End Eq't
CR Lead Time - Mech. Head End Eq't
CR Lead Time - Headwalls
CR Lead Time - Food Services Eq't
CR Lead Time - LV Systems Eq't
FINISHESFINISHESFINISHESFINISHESFINISHES
CR Lead Time - Flooring
CR Lead Time - Wall Prot'n & Handrails
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 8 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CR Lead Time - Systems Furniture
L0 & L1L0 & L1L0 & L1L0 & L1L0 & L1
CR Lead Time - (L0 & L1) Doors & Hwr
CR Lead Time - (L0 & L1) Light Fixtures
CR Lead Time - (L0 & L1) Millwork
L2 +L2 +L2 +L2 +L2 +
CR Lead Time - (L2 +) Doors & Hwr
CR Lead Time - (L2 +) Light Fixtures
CR Lead Time - (L2 +) Millwork
CRH - CONSTRUCTIONCRH - CONSTRUCTIONCRH - CONSTRUCTIONCRH - CONSTRUCTIONCRH - CONSTRUCTION
CRH - SITE PREPARATIONCRH - SITE PREPARATIONCRH - SITE PREPARATIONCRH - SITE PREPARATIONCRH - SITE PREPARATION
SITE ESTABLISHMENT & RELOCATIONSSITE ESTABLISHMENT & RELOCATIONSSITE ESTABLISHMENT & RELOCATIONSSITE ESTABLISHMENT & RELOCATIONSSITE ESTABLISHMENT & RELOCATIONS
CR Site - Close Parking Areas + Section of Birch St
CR Site - Fencing, Tree Clearing, Site Strip + Access Roads
CR Site - Make Safe & Remove Other Misc. Util.
CR Site - Install & Activate Temp. Gas Main (from Birch St)
CR Site - Install & Activate Temp. Water Main (from 2nd Ave)
CR Site - Decommission & Rmv Extg Gas Main
CR Site - Decommission & Rmv Extg Evergreen Water Main
BULK EXCAVATIONBULK EXCAVATIONBULK EXCAVATIONBULK EXCAVATIONBULK EXCAVATION
CR Bulk Excav. - Parkade + Upper Bench (to L1)
CR Bulk Excav. - Lower Bench (to L0)
CRH - CONSTRUCTION EQ'T & INFRASTRUCTURECRH - CONSTRUCTION EQ'T & INFRASTRUCTURECRH - CONSTRUCTION EQ'T & INFRASTRUCTURECRH - CONSTRUCTION EQ'T & INFRASTRUCTURECRH - CONSTRUCTION EQ'T & INFRASTRUCTURE
SITE OFFICESSITE OFFICESSITE OFFICESSITE OFFICESSITE OFFICES
CR Site Offices - Establish Trailers (Birch St + South Site)
CR Site Offices - Relocate to Zone B & Make Good
CR Site Offices - Final Demob. & Make Good
NORTH TOWER CRANENORTH TOWER CRANENORTH TOWER CRANENORTH TOWER CRANENORTH TOWER CRANE
CR Tower Crane (Nth) - Fdn & Erect
CR Tower Crane (Nth) - In Operation
CR Tower Crane (Nth) - Dismantle
CR Tower Crane (Nth) - Infill & Catch up Int. & Ext. Work
SOUTH TOWER CRANESOUTH TOWER CRANESOUTH TOWER CRANESOUTH TOWER CRANESOUTH TOWER CRANE
CR Tower Crane (Sth) - Fdn & Erect
CR Tower Crane (Sth) - In Operation
CR Tower Crane (Sth) - Dismantle
CR Tower Crane (Sth) - Infill & Catch up Int. & Ext. Work
CRH - STRUCTURECRH - STRUCTURECRH - STRUCTURECRH - STRUCTURECRH - STRUCTURE
L0L0L0L0L0
L0 - NORTH (3500 m2 SOG) (GL 1-6)L0 - NORTH (3500 m2 SOG) (GL 1-6)L0 - NORTH (3500 m2 SOG) (GL 1-6)L0 - NORTH (3500 m2 SOG) (GL 1-6)L0 - NORTH (3500 m2 SOG) (GL 1-6)
CR L0 (Nth) - Excav., FRP Pad Fdns & Cont. Fdns
CR L0 (Nth) - FRP Verticals (to U/S L1)
CR L0 (Nth) - U/S Util. & FRP SoG
L0 - CENTRE (3400 m2 SOG) (GL 6-11)L0 - CENTRE (3400 m2 SOG) (GL 6-11)L0 - CENTRE (3400 m2 SOG) (GL 6-11)L0 - CENTRE (3400 m2 SOG) (GL 6-11)L0 - CENTRE (3400 m2 SOG) (GL 6-11)
CR L0 (Ctr) - Excav., FRP Pad Fdns & Cont. Fdns
CR L0 (Ctr) - FRP Verticals (to U/S L1)
CR L0 (Ctr) - U/S Util. & FRP SoG
L1L1L1L1L1
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 9 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
L1 - NORTH (3500 m2 SS) (GL 1-6)L1 - NORTH (3500 m2 SS) (GL 1-6)L1 - NORTH (3500 m2 SS) (GL 1-6)L1 - NORTH (3500 m2 SS) (GL 1-6)L1 - NORTH (3500 m2 SS) (GL 1-6)
CR L1 (Nth) - FRP Susp Slab
CR L1 (Nth) - FRP Verticals (to U/S L2)
L1 - CENTRE (3400 m2 SS) (GL 6-11)L1 - CENTRE (3400 m2 SS) (GL 6-11)L1 - CENTRE (3400 m2 SS) (GL 6-11)L1 - CENTRE (3400 m2 SS) (GL 6-11)L1 - CENTRE (3400 m2 SS) (GL 6-11)
CR L1 (Ctr) - FRP Susp Slab (GL 6-10)
CR L1 (Ctr) - FRP Verticals (to U/S L2)
CR L1 (Ctr) - FRP Susp Slab (GL 10-12)
L1 - SOUTH (2800 m2 SOG) (GL 11-15)L1 - SOUTH (2800 m2 SOG) (GL 11-15)L1 - SOUTH (2800 m2 SOG) (GL 11-15)L1 - SOUTH (2800 m2 SOG) (GL 11-15)L1 - SOUTH (2800 m2 SOG) (GL 11-15)
CR L1 (Sth) - Excav., FRP Pad Fdns & Cont. Fdns
CR L1 (Sth) - FRP Verticals (to U/S L2)
CR L1 (Sth) - Backfill, U/S Util. & FRP SoG
L2L2L2L2L2
L2 - NORTH (3500 m2 SS) (GL 1-6)L2 - NORTH (3500 m2 SS) (GL 1-6)L2 - NORTH (3500 m2 SS) (GL 1-6)L2 - NORTH (3500 m2 SS) (GL 1-6)L2 - NORTH (3500 m2 SS) (GL 1-6)
CR L2 (Nth) - FRP Susp Slab
CR L2 (Nth) - FRP Verticals (to U/S L3)
L2 - CENTRE (3400 m2 SS) (GL 6-11)L2 - CENTRE (3400 m2 SS) (GL 6-11)L2 - CENTRE (3400 m2 SS) (GL 6-11)L2 - CENTRE (3400 m2 SS) (GL 6-11)L2 - CENTRE (3400 m2 SS) (GL 6-11)
CR L2 (Ctr) - FRP Susp Slab
CR L2 (Ctr) - FRP Verticals (to U/S L3)
L2 - SOUTH (2800 m2 SS) (GL 11-15)L2 - SOUTH (2800 m2 SS) (GL 11-15)L2 - SOUTH (2800 m2 SS) (GL 11-15)L2 - SOUTH (2800 m2 SS) (GL 11-15)L2 - SOUTH (2800 m2 SS) (GL 11-15)
CR L2 (Sth) - FRP Susp Slab
CR L2 (Sth) - FRP Verticals (to U/S L3)
L3L3L3L3L3
L3 - NORTH (2600 m2 SS) (GL 1-6)L3 - NORTH (2600 m2 SS) (GL 1-6)L3 - NORTH (2600 m2 SS) (GL 1-6)L3 - NORTH (2600 m2 SS) (GL 1-6)L3 - NORTH (2600 m2 SS) (GL 1-6)
CR L3 (Nth) - FRP Susp Slab
CR L3 (Nth) - FRP Verticals (to U/S L4)
L3 - CENTRE (3100 m2 SS) (GL 6-11)L3 - CENTRE (3100 m2 SS) (GL 6-11)L3 - CENTRE (3100 m2 SS) (GL 6-11)L3 - CENTRE (3100 m2 SS) (GL 6-11)L3 - CENTRE (3100 m2 SS) (GL 6-11)
CR L3 (Ctr) - FRP Susp Slab
CR L3 (Ctr) - FRP Verticals (to U/S L4)
L3 - SOUTH (2100 m2 SS) (GL 11-15)L3 - SOUTH (2100 m2 SS) (GL 11-15)L3 - SOUTH (2100 m2 SS) (GL 11-15)L3 - SOUTH (2100 m2 SS) (GL 11-15)L3 - SOUTH (2100 m2 SS) (GL 11-15)
CR L3 (Sth) - FRP Susp Slab
CR L3 (Sth) - FRP Verticals, Upstands
L4 + PENTHOUSEL4 + PENTHOUSEL4 + PENTHOUSEL4 + PENTHOUSEL4 + PENTHOUSE
L4 - NORTH (2200 m2 SS) (GL 1-6)L4 - NORTH (2200 m2 SS) (GL 1-6)L4 - NORTH (2200 m2 SS) (GL 1-6)L4 - NORTH (2200 m2 SS) (GL 1-6)L4 - NORTH (2200 m2 SS) (GL 1-6)
CR L4 (Nth) - FRP Susp Slab
CR L4 (Nth) - FRP Verticals, Upstands & Cap Slabs
CR L4 (Nth) - Penthouse Struc. Steel & Deck
L4 - CENTRE (2800 m2 SS) (GL 6-12)L4 - CENTRE (2800 m2 SS) (GL 6-12)L4 - CENTRE (2800 m2 SS) (GL 6-12)L4 - CENTRE (2800 m2 SS) (GL 6-12)L4 - CENTRE (2800 m2 SS) (GL 6-12)
CR L4 (Ctr) - FRP Susp Slab
CR L4 (Ctr) - FRP Verticals, Upstands & Cap Slabs
CR L4 (Ctr) - Penthouse Struc. Steel & Deck
MISC.MISC.MISC.MISC.MISC.
CR Stair Cores - Struc. Steel & Deck
CRH - ENVELOPECRH - ENVELOPECRH - ENVELOPECRH - ENVELOPECRH - ENVELOPE
L0L0L0L0L0
L0 - NTHL0 - NTHL0 - NTHL0 - NTHL0 - NTH
CR L0 (Nth) - Ext. Walls (to Weathertight)
L0 - CENTREL0 - CENTREL0 - CENTREL0 - CENTREL0 - CENTRE
CR L0 (Ctr) - Ext. Walls (to Weathertight)
L1L1L1L1L1
L1 - NTHL1 - NTHL1 - NTHL1 - NTHL1 - NTH
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 10 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CR L1 (Nth) - Ext. Walls (to Weathertight)
L1 - CENTREL1 - CENTREL1 - CENTREL1 - CENTREL1 - CENTRE
CR L1 (Ctr) - Ext. Walls (to Weathertight)
L1 - SOUTHL1 - SOUTHL1 - SOUTHL1 - SOUTHL1 - SOUTH
CR L1 (Sth) - Ext. Walls (to Weathertight)
L2L2L2L2L2
L2 - NTHL2 - NTHL2 - NTHL2 - NTHL2 - NTH
CR L2 (Nth) - Roofs (to Weathertight)
CR L2 (Nth) - Ext. Walls (to Weathertight)
L2 - CENTREL2 - CENTREL2 - CENTREL2 - CENTREL2 - CENTRE
CR L2 (Ctr) - Roofs (to Weathertight)
CR L2 (Ctr) - Ext. Walls (to Weathertight)
L2 - SOUTHL2 - SOUTHL2 - SOUTHL2 - SOUTHL2 - SOUTH
CR L2 (Sth) - Roofs (to Weathertight)
CR L2 (Sth) - Ext. Walls (to Weathertight)
L3L3L3L3L3
L3 - NTHL3 - NTHL3 - NTHL3 - NTHL3 - NTH
CR L3 (Nth) - Roofs (to Weathertight)
CR L3 (Nth) - Ext. Walls (to Weathertight)
L3 - CENTREL3 - CENTREL3 - CENTREL3 - CENTREL3 - CENTRE
CR L3 (Ctr) - Roofs (to Weathertight)
CR L3 (Ctr) - Ext. Walls (to Weathertight)
L3 - SOUTHL3 - SOUTHL3 - SOUTHL3 - SOUTHL3 - SOUTH
CR L3 (Sth) - Roofs (to Weathertight)
L4 + PENTHOUSEL4 + PENTHOUSEL4 + PENTHOUSEL4 + PENTHOUSEL4 + PENTHOUSE
L4 - NTHL4 - NTHL4 - NTHL4 - NTHL4 - NTH
CR L4 (Nth) - Ext. Walls (to Weathertight)
CR L4 (Nth) - Roofs (to Weathertight)
L4 - CENTREL4 - CENTREL4 - CENTREL4 - CENTREL4 - CENTRE
CR L4 (Ctr) - Ext. Walls (to Weathertight)
CR L4 (Ctr) - Roofs (to Weathertight)
L0-L4 - ENVELOPE FINISHESL0-L4 - ENVELOPE FINISHESL0-L4 - ENVELOPE FINISHESL0-L4 - ENVELOPE FINISHESL0-L4 - ENVELOPE FINISHES
CR L0 - L4 - Envelope Finishes
CRH - INTERIOR FITOUTCRH - INTERIOR FITOUTCRH - INTERIOR FITOUTCRH - INTERIOR FITOUTCRH - INTERIOR FITOUT
L0 (6000 m2)L0 (6000 m2)L0 (6000 m2)L0 (6000 m2)L0 (6000 m2)
L0 - 1 (NTH-EAST) - GL 1-6/A-F (FS, MM, ES) - 1900 m2L0 - 1 (NTH-EAST) - GL 1-6/A-F (FS, MM, ES) - 1900 m2L0 - 1 (NTH-EAST) - GL 1-6/A-F (FS, MM, ES) - 1900 m2L0 - 1 (NTH-EAST) - GL 1-6/A-F (FS, MM, ES) - 1900 m2L0 - 1 (NTH-EAST) - GL 1-6/A-F (FS, MM, ES) - 1900 m2
CR L0 - 1 (NE) - Layout, Top Track, Cast Iron
CR L0 - 1 (NE) - Primary Wall Framing, Upper Board
CR L0 - 1 (NE) - Main M/E Runs @ Clg
CR L0 - 1 (NE) - Secondary Wall Framing, Door Frames
CR L0 - 1 (NE) - M/E Rough-in to Clgs & Walls
CR L0 - 1 (NE) - Pre-Close Inspections, Insul., Final Backing
CR L0 - 1 (NE) - Board, Tape & Sand Walls & Bulkheads
CR L0 - 1 (NE) - Paint, T-Bar & M/E Clg Fixtures
CR L0 - 1 (NE) - Sheet Flooring
CR L0 - 1 (NE) - Millwork
CR L0 - 1 (NE) - A/M/E Finishes & Wall Fixtures
CR L0 - 1 (NE) - Substantially Dust Free
CR L0 - 1 (NE) - Med. Eq't & FFE
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 11 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CR L0 - 1 (NE) - Punchlists, Builder's Clean
L0 - 2 (CTR-WEST) - GL 5-11/F-K (MED EQ'T SERVICE) - 1600 mL0 - 2 (CTR-WEST) - GL 5-11/F-K (MED EQ'T SERVICE) - 1600 mL0 - 2 (CTR-WEST) - GL 5-11/F-K (MED EQ'T SERVICE) - 1600 mL0 - 2 (CTR-WEST) - GL 5-11/F-K (MED EQ'T SERVICE) - 1600 mL0 - 2 (CTR-WEST) - GL 5-11/F-K (MED EQ'T SERVICE) - 1600 m
CR L0 - 2 (CW) - Layout, Top Track, Cast Iron
CR L0 - 2 (CW) - Primary Wall Framing, Upper Board
CR L0 - 2 (CW) - Main M/E Runs @ Clg
CR L0 - 2 (CW) - Secondary Wall Framing, Door Frames
CR L0 - 2 (CW) - M/E Rough-in to Clgs & Walls
CR L0 - 2 (CW) - Pre-Close Inspections, Insul., Final Backing
CR L0 - 2 (CW) - Board, Tape & Sand Walls & Bulkheads
CR L0 - 2 (CW) - Paint, T-Bar & M/E Clg Fixtures
CR L0 - 2 (CW) - Sheet Flooring
CR L0 - 2 (CW) - Millwork
CR L0 - 2 (CW) - A/M/E Finishes & Wall Fixtures
CR L0 - 2 (CW) - Substantially Dust Free
CR L0 - 2 (CW) - Med. Eq't & FFE
CR L0 - 2 (CW) - Punchlists, Builder's Clean
L0 - 3 (CTR-EAST) - GL 6-12/A-F (PHARM, OFFICES) - 2000 m2L0 - 3 (CTR-EAST) - GL 6-12/A-F (PHARM, OFFICES) - 2000 m2L0 - 3 (CTR-EAST) - GL 6-12/A-F (PHARM, OFFICES) - 2000 m2L0 - 3 (CTR-EAST) - GL 6-12/A-F (PHARM, OFFICES) - 2000 m2L0 - 3 (CTR-EAST) - GL 6-12/A-F (PHARM, OFFICES) - 2000 m2
CR L0 - 3 (CE) - Layout, Top Track, Cast Iron
CR L0 - 3 (CE) - Primary Wall Framing, Upper Board
CR L0 - 3 (CE) - Main M/E Runs @ Clg
CR L0 - 3 (CE) - Secondary Wall Framing, Door Frames
CR L0 - 3 (CE) - M/E Rough-in to Clgs & Walls
CR L0 - 3 (CE) - Pre-Close Inspections, Insul., Final Backing
CR L0 - 3 (CE) - Board, Tape & Sand Walls & Bulkheads
CR L0 - 3 (CE) - Paint, T-Bar & M/E Clg Fixtures
CR L0 - 3 (CE) - Sheet Flooring
CR L0 - 3 (CE) - Millwork
CR L0 - 3 (CE) - A/M/E Finishes & Wall Fixtures
CR L0 - 3 (CE) - Substantially Dust Free
CR L0 - 3 (CE) - Med. Eq't & FFE
CR L0 - 3 (CE) - Punchlists, Builder's Clean
L1 (9600 m2)L1 (9600 m2)L1 (9600 m2)L1 (9600 m2)L1 (9600 m2)
L1 - 1 (NTH-WEST) - GL 1-6/E-K (OUTPATIENT, REG.) - 2400 mL1 - 1 (NTH-WEST) - GL 1-6/E-K (OUTPATIENT, REG.) - 2400 mL1 - 1 (NTH-WEST) - GL 1-6/E-K (OUTPATIENT, REG.) - 2400 mL1 - 1 (NTH-WEST) - GL 1-6/E-K (OUTPATIENT, REG.) - 2400 mL1 - 1 (NTH-WEST) - GL 1-6/E-K (OUTPATIENT, REG.) - 2400 m
CR L1 - 1 (NW) - Layout, Top Track, Cast Iron
CR L1 - 1 (NW) - Primary Wall Framing, Upper Board
CR L1 - 1 (NW) - Main M/E Runs @ Clg
CR L1 - 1 (NW) - Secondary Wall Framing, Door Frames
CR L1 - 1 (NW) - M/E Rough-in to Clgs & Walls
CR L1 - 1 (NW) - Pre-Close Inspections, Insul., Final Backing
CR L1 - 1 (NW) - Board, Tape & Sand Walls & Bulkheads
CR L1 - 1 (NW) - Paint, T-Bar & M/E Clg Fixtures
CR L1 - 1 (NW) - Sheet Flooring
CR L1 - 1 (NW) - Millwork
CR L1 - 1 (NW) - A/M/E Finishes & Wall Fixtures
CR L1 - 1 (NW) - Substantially Dust Free
CR L1 - 1 (NW) - Med. Eq't & FFE
7Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 12 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CR L1 - 1 (NW) - Punchlists, Builder's Clean
L1 - 2 (NTH-EAST) - GL 1-6/A-E (THERAPY) - 1000 m2L1 - 2 (NTH-EAST) - GL 1-6/A-E (THERAPY) - 1000 m2L1 - 2 (NTH-EAST) - GL 1-6/A-E (THERAPY) - 1000 m2L1 - 2 (NTH-EAST) - GL 1-6/A-E (THERAPY) - 1000 m2L1 - 2 (NTH-EAST) - GL 1-6/A-E (THERAPY) - 1000 m2
CR L1 - 2 (NE) - Layout, Top Track, Cast Iron
CR L1 - 2 (NE) - Primary Wall Framing, Upper Board
CR L1 - 2 (NE) - Main M/E Runs @ Clg
CR L1 - 2 (NE) - Secondary Wall Framing, Door Frames
CR L1 - 2 (NE) - M/E Rough-in to Clgs & Walls
CR L1 - 2 (NE) - Pre-Close Inspections, Insul., Final Backing
CR L1 - 2 (NE) - Board, Tape & Sand Walls & Bulkheads
CR L1 - 2 (NE) - Paint, T-Bar & M/E Clg Fixtures
CR L1 - 2 (NE) - Sheet Flooring
CR L1 - 2 (NE) - Millwork
CR L1 - 2 (NE) - A/M/E Finishes & Wall Fixtures
CR L1 - 2 (NE) - Substantially Dust Free
CR L1 - 2 (NE) - Med. Eq't & FFE
CR L1 - 2 (NE) - Punchlists, Builder's Clean
L1 - 3 (CTR-WEST) - GL 6-12/G-K (IMAGING) - 1600 m2L1 - 3 (CTR-WEST) - GL 6-12/G-K (IMAGING) - 1600 m2L1 - 3 (CTR-WEST) - GL 6-12/G-K (IMAGING) - 1600 m2L1 - 3 (CTR-WEST) - GL 6-12/G-K (IMAGING) - 1600 m2L1 - 3 (CTR-WEST) - GL 6-12/G-K (IMAGING) - 1600 m2
CR L1 - 3 (CW) - Layout, Top Track, Cast Iron
CR L1 - 3 (CW) - Primary Wall Framing, Upper Board
CR L1 - 3 (CW) - Main M/E Runs @ Clg
CR L1 - 3 (CW) - Secondary Wall Framing, Door Frames
CR L1 - 3 (CW) - M/E Rough-in to Clgs & Walls
CR L1 - 3 (CW) - Pre-Close Inspections, Insul., Final Backing
CR L1 - 3 (CW) - Board, Tape & Sand Walls & Bulkheads
CR L1 - 3 (CW) - Paint, T-Bar & M/E Clg Fixtures
CR L1 - 3 (CW) - Sheet Flooring
CR L1 - 3 (CW) - Millwork
CR L1 - 3 (CW) - A/M/E Finishes & Wall Fixtures
CR L1 - 3 (CW) - Substantially Dust Free
CR L1 - 3 (CW) - Med. Eq't & FFE
CR L1 - 3 (CW) - Punchlists, Builder's Clean
L1 - 4 (CTR-EAST) - GL 6-12/A-G (AMB. CARE) - 2600 m2L1 - 4 (CTR-EAST) - GL 6-12/A-G (AMB. CARE) - 2600 m2L1 - 4 (CTR-EAST) - GL 6-12/A-G (AMB. CARE) - 2600 m2L1 - 4 (CTR-EAST) - GL 6-12/A-G (AMB. CARE) - 2600 m2L1 - 4 (CTR-EAST) - GL 6-12/A-G (AMB. CARE) - 2600 m2
CR L1 - 4 (CE) - Layout, Top Track, Cast Iron
CR L1 - 4 (CE) - Primary Wall Framing, Upper Board
CR L1 - 4 (CE) - Main M/E Runs @ Clg
CR L1 - 4 (CE) - Secondary Wall Framing, Door Frames
CR L1 - 4 (CE) - M/E Rough-in to Clgs & Walls
CR L1 - 4 (CE) - Pre-Close Inspections, Insul., Final Backing
CR L1 - 4 (CE) - Board, Tape & Sand Walls & Bulkheads
CR L1 - 4 (CE) - Paint, T-Bar & M/E Clg Fixtures
CR L1 - 4 (CE) - Sheet Flooring
CR L1 - 4 (CE) - Millwork
CR L1 - 4 (CE) - A/M/E Finishes & Wall Fixtures
CR L1 - 4 (CE) - Substantially Dust Free
CR L1 - 4 (CE) - Med. Eq't & FFE
CR L1 - 4 (CE) - Punchlists, Builder's Clean
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 13 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
L1 - 5 (STH) - GL12-15/A-K (EMERGENCY) - 1900 m2L1 - 5 (STH) - GL12-15/A-K (EMERGENCY) - 1900 m2L1 - 5 (STH) - GL12-15/A-K (EMERGENCY) - 1900 m2L1 - 5 (STH) - GL12-15/A-K (EMERGENCY) - 1900 m2L1 - 5 (STH) - GL12-15/A-K (EMERGENCY) - 1900 m2
CR L1 - 5 (S) - Layout, Top Track, Cast Iron
CR L1 - 5 (S) - Primary Wall Framing, Upper Board
CR L1 - 5 (S) - Main M/E Runs @ Clg
CR L1 - 5 (S) - Secondary Wall Framing, Door Frames
CR L1 - 5 (S) - M/E Rough-in to Clgs & Walls
CR L1 - 5 (S) - Pre-Close Inspections, Insul., Final Backing
CR L1 - 5 (S) - Board, Tape & Sand Walls & Bulkheads
CR L1 - 5 (S) - Paint, T-Bar & M/E Clg Fixtures
CR L1 - 5 (S) - Sheet Flooring
CR L1 - 5 (S) - Millwork
CR L1 - 5 (S) - A/M/E Finishes & Wall Fixtures
CR L1 - 5 (S) - Substantially Dust Free
CR L1 - 5 (S) - Med. Eq't & FFE
CR L1 - 5 (S) - Punchlists, Builder's Clean
L2 (7800 m2)L2 (7800 m2)L2 (7800 m2)L2 (7800 m2)L2 (7800 m2)
L2 - 0 (NTH-WEST) - GL 4-10/I-K (OR's) - 800 m2 <SEP. CREW>L2 - 0 (NTH-WEST) - GL 4-10/I-K (OR's) - 800 m2 <SEP. CREW>L2 - 0 (NTH-WEST) - GL 4-10/I-K (OR's) - 800 m2 <SEP. CREW>L2 - 0 (NTH-WEST) - GL 4-10/I-K (OR's) - 800 m2 <SEP. CREW>L2 - 0 (NTH-WEST) - GL 4-10/I-K (OR's) - 800 m2 <SEP. CREW>
CR L2 - 0 (ORs) - Layout, Top Track, Cast Iron
CR L2 - 0 (ORs) - Primary Wall Framing, Upper Board
CR L2 - 0 (ORs) - Main M/E Runs @ Clg
CR L2 - 0 (ORs) - Secondary Wall Framing, Door Frames
CR L2 - 0 (ORs) - M/E Rough-in to Clgs & Walls
CR L2 - 0 (ORs) - Pre-Close Inspections, Insul., Final Backing
CR L2 - 0 (ORs) - Board, Tape & Sand Walls & Bulkheads
CR L2 - 0 (ORs) - Paint, T-Bar & M/E Clg Fixtures
CR L2 - 0 (ORs) - Sheet Flooring
CR L2 - 0 (ORs) - Millwork
CR L2 - 0 (ORs) - A/M/E Finishes & Wall Fixtures
CR L2 - 0 (ORs) - Substantially Dust Free
CR L2 - 0 (ORs) - Med. Eq't & FFE
CR L2 - 0 (ORs) - Punchlists, Builder's Clean
L2 - 1 (NTH-WEST) - GL 1-10/E-I (SURGICAL) - 1900 m2L2 - 1 (NTH-WEST) - GL 1-10/E-I (SURGICAL) - 1900 m2L2 - 1 (NTH-WEST) - GL 1-10/E-I (SURGICAL) - 1900 m2L2 - 1 (NTH-WEST) - GL 1-10/E-I (SURGICAL) - 1900 m2L2 - 1 (NTH-WEST) - GL 1-10/E-I (SURGICAL) - 1900 m2
CR L2 - 1 (NW) - Layout, Top Track, Cast Iron
CR L2 - 1 (NW) - Primary Wall Framing, Upper Board
CR L2 - 1 (NW) - Main M/E Runs @ Clg
CR L2 - 1 (NW) - Secondary Wall Framing, Door Frames
CR L2 - 1 (NW) - M/E Rough-in to Clgs & Walls
CR L2 - 1 (NW) - Pre-Close Inspections, Insul., Final Backing
CR L2 - 1 (NW) - Board, Tape & Sand Walls & Bulkheads
CR L2 - 1 (NW) - Paint, T-Bar & M/E Clg Fixtures
CR L2 - 1 (NW) - Sheet Flooring
CR L2 - 1 (NW) - Millwork
CR L2 - 1 (NW) - A/M/E Finishes & Wall Fixtures
CR L2 - 1 (NW) - Substantially Dust Free
CR L2 - 1 (NW) - Med. Eq't & FFE
CR L2 - 1 (NW) - Punchlists, Builder's Clean
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 14 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
L2 - 2 (NTH-EAST) - GL 1-7/A-E (MATERNITY, PAED.) - 1600 m2L2 - 2 (NTH-EAST) - GL 1-7/A-E (MATERNITY, PAED.) - 1600 m2L2 - 2 (NTH-EAST) - GL 1-7/A-E (MATERNITY, PAED.) - 1600 m2L2 - 2 (NTH-EAST) - GL 1-7/A-E (MATERNITY, PAED.) - 1600 m2L2 - 2 (NTH-EAST) - GL 1-7/A-E (MATERNITY, PAED.) - 1600 m2
CR L2 - 2 (NE) - Layout, Top Track, Cast Iron
CR L2 - 2 (NE) - Primary Wall Framing, Upper Board
CR L2 - 2 (NE) - Main M/E Runs @ Clg
CR L2 - 2 (NE) - Secondary Wall Framing, Door Frames
CR L2 - 2 (NE) - M/E Rough-in to Clgs & Walls
CR L2 - 2 (NE) - Pre-Close Inspections, Insul., Final Backing
CR L2 - 2 (NE) - Board, Tape & Sand Walls & Bulkheads
CR L2 - 2 (NE) - Paint, T-Bar & M/E Clg Fixtures
CR L2 - 2 (NE) - Sheet Flooring
CR L2 - 2 (NE) - Millwork
CR L2 - 2 (NE) - A/M/E Finishes & Wall Fixtures
CR L2 - 2 (NE) - Substantially Dust Free
CR L2 - 2 (NE) - Med. Eq't & FFE
CR L2 - 2 (NE) - Punchlists, Builder's Clean
L2 - 3 (STH-WEST) - GL 10-15/F-K (LAB., MED. STAFF, UBC) - 1600 m2L2 - 3 (STH-WEST) - GL 10-15/F-K (LAB., MED. STAFF, UBC) - 1600 m2L2 - 3 (STH-WEST) - GL 10-15/F-K (LAB., MED. STAFF, UBC) - 1600 m2L2 - 3 (STH-WEST) - GL 10-15/F-K (LAB., MED. STAFF, UBC) - 1600 m2L2 - 3 (STH-WEST) - GL 10-15/F-K (LAB., MED. STAFF, UBC) - 1600 m2
CR L2 - 3 (SW) - Layout, Top Track, Cast Iron
CR L2 - 3 (SW) - Primary Wall Framing, Upper Board
CR L2 - 3 (SW) - Main M/E Runs @ Clg
CR L2 - 3 (SW) - Secondary Wall Framing, Door Frames
CR L2 - 3 (SW) - M/E Rough-in to Clgs & Walls
CR L2 - 3 (SW) - Pre-Close Inspections, Insul., Final Backing
CR L2 - 3 (SW) - Board, Tape & Sand Walls & Bulkheads
CR L2 - 3 (SW) - Paint, T-Bar & M/E Clg Fixtures
CR L2 - 3 (SW) - Sheet Flooring
CR L2 - 3 (SW) - Millwork
CR L2 - 3 (SW) - A/M/E Finishes & Wall Fixtures
CR L2 - 3 (SW) - Substantially Dust Free
CR L2 - 3 (SW) - Med. Eq't & FFE
CR L2 - 3 (SW) - Punchlists, Builder's Clean
L2 - 4 (STH-EAST) - GL 7-14/A-D (ICU) - 1500 m2L2 - 4 (STH-EAST) - GL 7-14/A-D (ICU) - 1500 m2L2 - 4 (STH-EAST) - GL 7-14/A-D (ICU) - 1500 m2L2 - 4 (STH-EAST) - GL 7-14/A-D (ICU) - 1500 m2L2 - 4 (STH-EAST) - GL 7-14/A-D (ICU) - 1500 m2
CR L2 - 4 (SE) - Layout, Top Track, Cast Iron
CR L2 - 4 (SE) - Primary Wall Framing, Upper Board
CR L2 - 4 (SE) - Main M/E Runs @ Clg
CR L2 - 4 (SE) - Secondary Wall Framing, Door Frames
CR L2 - 4 (SE) - M/E Rough-in to Clgs & Walls
CR L2 - 4 (SE) - Pre-Close Inspections, Insul., Final Backing
CR L2 - 4 (SE) - Board, Tape & Sand Walls & Bulkheads
CR L2 - 4 (SE) - Paint, T-Bar & M/E Clg Fixtures
CR L2 - 4 (SE) - Sheet Flooring
CR L2 - 4 (SE) - Millwork
CR L2 - 4 (SE) - A/M/E Finishes & Wall Fixtures
CR L2 - 4 (SE) - Substantially Dust Free
CR L2 - 4 (SE) - Med. Eq't & FFE
CR L2 - 4 (SE) - Punchlists, Builder's Clean
L3 (5100 m2)L3 (5100 m2)L3 (5100 m2)L3 (5100 m2)L3 (5100 m2)
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 15 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
L3 - 1 (WEST) - GL 1-12/A-E (IPU) - 2550 m2L3 - 1 (WEST) - GL 1-12/A-E (IPU) - 2550 m2L3 - 1 (WEST) - GL 1-12/A-E (IPU) - 2550 m2L3 - 1 (WEST) - GL 1-12/A-E (IPU) - 2550 m2L3 - 1 (WEST) - GL 1-12/A-E (IPU) - 2550 m2
CR L3 - 1 (W) - Layout, Top Track, Cast Iron
CR L3 - 1 (W) - Primary Wall Framing, Upper Board
CR L3 - 1 (W) - Main M/E Runs @ Clg
CR L3 - 1 (W) - Secondary Wall Framing, Door Frames
CR L3 - 1 (W) - M/E Rough-in to Clgs & Walls
CR L3 - 1 (W) - Pre-Close Inspections, Insul., Final Backing
CR L3 - 1 (W) - Board, Tape & Sand Walls & Bulkheads
CR L3 - 1 (W) - Paint, T-Bar & M/E Clg Fixtures
CR L3 - 1 (W) - Sheet Flooring
CR L3 - 1 (W) - Millwork
CR L3 - 1 (W) - A/M/E Finishes & Wall Fixtures
CR L3 - 1 (W) - Substantially Dust Free
CR L3 - 1 (W) - Med. Eq't & FFE
CR L3 - 1 (W) - Punchlists, Builder's Clean
L3 - 2 (EAST) - GL 1-12/E-I (IPU) - 2550 m2L3 - 2 (EAST) - GL 1-12/E-I (IPU) - 2550 m2L3 - 2 (EAST) - GL 1-12/E-I (IPU) - 2550 m2L3 - 2 (EAST) - GL 1-12/E-I (IPU) - 2550 m2L3 - 2 (EAST) - GL 1-12/E-I (IPU) - 2550 m2
CR L3 - 2 (E) - Layout, Top Track, Cast Iron
CR L3 - 2 (E) - Primary Wall Framing, Upper Board
CR L3 - 2 (E) - Main M/E Runs @ Clg
CR L3 - 2 (E) - Secondary Wall Framing, Door Frames
CR L3 - 2 (E) - M/E Rough-in to Clgs & Walls
CR L3 - 2 (E) - Pre-Close Inspections, Insul., Final Backing
CR L3 - 2 (E) - Board, Tape & Sand Walls & Bulkheads
CR L3 - 2 (E) - Paint, T-Bar & M/E Clg Fixtures
CR L3 - 2 (E) - Sheet Flooring
CR L3 - 2 (E) - Millwork
CR L3 - 2 (E) - A/M/E Finishes & Wall Fixtures
CR L3 - 2 (E) - Substantially Dust Free
CR L3 - 2 (E) - Med. Eq't & FFE
CR L3 - 2 (E) - Punchlists, Builder's Clean
CRH - MAJOR PLANT & EQ'T ROOMSCRH - MAJOR PLANT & EQ'T ROOMSCRH - MAJOR PLANT & EQ'T ROOMSCRH - MAJOR PLANT & EQ'T ROOMSCRH - MAJOR PLANT & EQ'T ROOMS
L0 - MECH. ROOMSL0 - MECH. ROOMSL0 - MECH. ROOMSL0 - MECH. ROOMSL0 - MECH. ROOMS
CR L0 - Mech Rms - Buildout (incl. Walls, HK Pads etc.)
CR L0 - Mech Rms - Piping, Ductwork, Controls etc.
CR L0 - Mech Rms - Set & Assemble Eq't
CR L0 - Mech Rms - Elec. to Mech. Eq't
CR L0 - Mech Rms - Eq't Energized
L0 - MAIN ELEC. ROOML0 - MAIN ELEC. ROOML0 - MAIN ELEC. ROOML0 - MAIN ELEC. ROOML0 - MAIN ELEC. ROOM
CR L0 - Main Elec Rm - Buildout (incl. Walls, HK Pads etc.)
CR L0 - Main Elec Rm - Feeders, Terminations & Initial Testing
CR L0 - Main Elec Rm - Set & Assemble Eq't
CR L0 - Main Elec Rm - Eq't Energized
L0-L4 - SUB-ELEC. ROOMS & RISERSL0-L4 - SUB-ELEC. ROOMS & RISERSL0-L4 - SUB-ELEC. ROOMS & RISERSL0-L4 - SUB-ELEC. ROOMS & RISERSL0-L4 - SUB-ELEC. ROOMS & RISERS
CR L0-L3 - Sub-Elec Rms/Risers - Buildout (incl. Walls, HK Pads etc.)
CR L0-L3 - Sub-Elec Rms/Risers - Set & Assemble Eq't
CR L0-L3 - Sub-Elec Rms/Risers - Feeders, Terminations & Initial Testing
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 16 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CR L0-L3 - Sub-Elec Rms/Risers - Eq't Energized
L0 - MAIN DATA ROOML0 - MAIN DATA ROOML0 - MAIN DATA ROOML0 - MAIN DATA ROOML0 - MAIN DATA ROOM
CR L0 - Main Data Rm - Buildout (incl. Walls, HK Pads etc.)
CR L0 - Main Data Rm - Set & Assemble Racks, Panels
CR L0 - Main Data Rm - Backbone & Horizontal Cable
CR L0 - Main Data Rm - Live & Ready for Active Eq't
L0-L4 - SUB-DATA ROOMS & RISERSL0-L4 - SUB-DATA ROOMS & RISERSL0-L4 - SUB-DATA ROOMS & RISERSL0-L4 - SUB-DATA ROOMS & RISERSL0-L4 - SUB-DATA ROOMS & RISERS
CR L0-L3 - Sub-Data Rms/Risers - Buildout (incl. Walls, HK Pads etc.)
CR L0-L3 - Sub-Data Rms/Risers - Set & Assemble Racks, Panels
CR L0-L3 - Sub-Data Rms/Risers - Backbone & Horizontal Cable
CR L0-L3 - Sub-Data Rms/Risers - Live & Ready for Active Eq't
L4 - MECH. PENTHOUSEL4 - MECH. PENTHOUSEL4 - MECH. PENTHOUSEL4 - MECH. PENTHOUSEL4 - MECH. PENTHOUSE
CR L4 - Mech Penthouse - Buildout (incl. HK Pads etc.)
CR L4 - Mech Penthouse - Set & Assemble Eq't
CR L4 - Mech Penthouse - Piping, Ductwork, Controls etc.
CR L4 - Mech Penthouse - Elec. to Mech. Eq't
CR L4 - Mech Penthouse - Eq't Energized
L4 - HELIPADL4 - HELIPADL4 - HELIPADL4 - HELIPADL4 - HELIPAD
CR L4 - Helipad Structure
CR L4 - Helipad Systems & Finishes
GENERATORSGENERATORSGENERATORSGENERATORSGENERATORS
CR Generators - Buildout (incl. Ductbank, Slabs etc.)
CR Generators - Set & Assemble Eq't (incl. Fuel Systems)
CR Generators - Feeders, Terminations & Initial Testing
CR Generators - Energized
TANK FARMTANK FARMTANK FARMTANK FARMTANK FARM
CR Tank Farm - Buildout (incl. Ductbank, Slabs etc.)
CR Tank Farm - Set & Assemble Tanks & Eq't
CR Tank Farm - Piping & Hookup
CR Tank Farm - Energized
ELEVATORS & LOBBIESELEVATORS & LOBBIESELEVATORS & LOBBIESELEVATORS & LOBBIESELEVATORS & LOBBIES
PATIENT ELEVATORS (2 EA - L0-L4)PATIENT ELEVATORS (2 EA - L0-L4)PATIENT ELEVATORS (2 EA - L0-L4)PATIENT ELEVATORS (2 EA - L0-L4)PATIENT ELEVATORS (2 EA - L0-L4)
CR Elev. (Patient - 2 ea) - Prep. Shafts & MRs
CR Elev. (Patient - 2 ea) - Install
CR Elev. (Patient - 2 ea) - EMR Eq't Energized (Const'n Power)
CR Elev. (Patient - 2 ea) - Use as Const'n Hoists
CR Elev. (Patient - 2 ea) - Lobby Finishes
PUBLIC ELEVATORS (3 EA - L0-L3)PUBLIC ELEVATORS (3 EA - L0-L3)PUBLIC ELEVATORS (3 EA - L0-L3)PUBLIC ELEVATORS (3 EA - L0-L3)PUBLIC ELEVATORS (3 EA - L0-L3)
CR Elev. (Public - 3 ea) - Prep. Shafts & MRs
CR Elev. (Public - 3 ea) - Install
CR Elev. (Public - 3 ea) - EMR Eq't Energized (Perm. Power)
CR Elev. (Public - 3 ea) - Lobby Finishes
SERVICE ELEVATORS (4 EA - L0-VARIOUS)SERVICE ELEVATORS (4 EA - L0-VARIOUS)SERVICE ELEVATORS (4 EA - L0-VARIOUS)SERVICE ELEVATORS (4 EA - L0-VARIOUS)SERVICE ELEVATORS (4 EA - L0-VARIOUS)
CR Elev. (Service - 4 ea) - Prep. Shafts & MRs
CR Elev. (Service - 4 ea) - Install
CR Elev. (Service - 4 ea) - EMR Eq't Energized (Const'n Power)
CR Elev. (Service - 4 ea) - Lobby Finishes
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
'n Hoists
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 17 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CRH - SITE UTILITIES & FINISHESCRH - SITE UTILITIES & FINISHESCRH - SITE UTILITIES & FINISHESCRH - SITE UTILITIES & FINISHESCRH - SITE UTILITIES & FINISHES
SITE UTILITIES (SEQUENCE TBD)SITE UTILITIES (SEQUENCE TBD)SITE UTILITIES (SEQUENCE TBD)SITE UTILITIES (SEQUENCE TBD)SITE UTILITIES (SEQUENCE TBD)
SEWERSEWERSEWERSEWERSEWER
CR Site - Sewer Mains & Tie-ins
STORMSTORMSTORMSTORMSTORM
CR Site - Storm Mains & Tie-ins
WATERWATERWATERWATERWATER
CR Site - Water Mains & Tie-ins
GASGASGASGASGAS
CR Site - Fortis Gas Mains & Tie-ins
ELECELECELECELECELEC
CR Site - Elec. Ductbank
CR Site - BC Hydro Pull Feeders & Energize
COMM.COMM.COMM.COMM.COMM.
CR Site - Comm. Ductbank
CR Site - Shaw/Telus Comm. Lines & Energize
SOUTH PARKING & ACCESSSOUTH PARKING & ACCESSSOUTH PARKING & ACCESSSOUTH PARKING & ACCESSSOUTH PARKING & ACCESS
CR Site (South) - Clear Laydown Areas + Rough Grade
CR Site (South) - Shallow Utilities, Paving + Site Finishes
CR Site (South) - Re-Open Section of Birch St
NORTH PARKING & ACCESSNORTH PARKING & ACCESSNORTH PARKING & ACCESSNORTH PARKING & ACCESSNORTH PARKING & ACCESS
CR Site (North) - Clear Laydown Areas + Rough Grade
CR Site (North) - Shallow Utilities, Paving + Site Finishes
CRH - PARKADECRH - PARKADECRH - PARKADECRH - PARKADECRH - PARKADE
CR Parkade - Excav., FRP Pad Fdns
CR Parkade - U/S Util. & FRP SoG
CR Parkade - Precast Erection, Toppings
CR Parkade - Initial Rough-in + Fitout
CR Parkade - Use as Trades / Storage / Lockups
CR Parkade - Demob. Lockups + Final Fitout
CRH - COMPLETIONCRH - COMPLETIONCRH - COMPLETIONCRH - COMPLETIONCRH - COMPLETION
TESTING & COMMISSIONINGTESTING & COMMISSIONINGTESTING & COMMISSIONINGTESTING & COMMISSIONINGTESTING & COMMISSIONING
CR CR - Hydronic Systems Test & Balance
CR CR - Air Systems Test & Balance
CR CR - Arch. Inspections & Deficiencies
CR CR - Power, Ltg & LV Systems Test & Commission
CR CR - Fire Alarm Test & Verify
CR CR - FFE/Eq't Demonstration & Training
CR CR - Elevators Test & Commission
OCCUPANCY & SERVICE COMMENCEMENTOCCUPANCY & SERVICE COMMENCEMENTOCCUPANCY & SERVICE COMMENCEMENTOCCUPANCY & SERVICE COMMENCEMENTOCCUPANCY & SERVICE COMMENCEMENT
CR CR - Integrated Life Safety Tests + Operational Scenarios
CR CR - Consultant Letters of Assurance & Final City Signoffs
CR CR - Occupancy + Subst. Completion
CR CR - Post Substantial Deficiencies
CR CR - Final IC Certification
CR CR - Anticipated (First) Service Commencement
CRH - ZONE B (POST SERVICE COMMENCEMENT)CRH - ZONE B (POST SERVICE COMMENCEMENT)CRH - ZONE B (POST SERVICE COMMENCEMENT)CRH - ZONE B (POST SERVICE COMMENCEMENT)CRH - ZONE B (POST SERVICE COMMENCEMENT)
CR CR - Zone B - Owner Transition Period (6 months)
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Open Section of Birch St
es
mission
ng
Operational Scenarios
urance & Final City Signoffs
pletion
ntial Deficiencies
Certification
ted (First) Service Commencement
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 18 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CR CR - Zone B - Extg Bldg Hazmat Removal/Abatement
CR CR - Zone B - Extg Bldg Strip-out
CR CR - Zone B - Extg Bldg Structural Demolition
CR CR - Zone B - New Surface Parking + Site Finishes
CR CR - Zone B - Completion
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CRH PROJECT SCHEDULE (printed - 29-May-14) p. 19 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
NIHP - PROJECT SCHEDULE (REV. FC-01) - 30 JUN '14 FC, 30 APR '17 SCNIHP - PROJECT SCHEDULE (REV. FC-01) - 30 JUN '14 FC, 30 APR '17 SCNIHP - PROJECT SCHEDULE (REV. FC-01) - 30 JUN '14 FC, 30 APR '17 SCNIHP - PROJECT SCHEDULE (REV. FC-01) - 30 JUN '14 FC, 30 APR '17 SCNIHP - PROJECT SCHEDULE (REV. FC-01) - 30 JUN '14 FC, 30 APR '17 SCNIHP - PROJECT SCHEDULE (REV. FC-01) - 30 JUN '14 FC, 30 APR '17 SC
KEY MILESTONES & SUMMARY OVERVIEWKEY MILESTONES & SUMMARY OVERVIEWKEY MILESTONES & SUMMARY OVERVIEWKEY MILESTONES & SUMMARY OVERVIEWKEY MILESTONES & SUMMARY OVERVIEWKEY MILESTONES & SUMMARY OVERVIEW
KICKOFFKICKOFFKICKOFFKICKOFFKICKOFF
. CR+CV PREFERRED PROPONENT
. CR+CV KICK-OFF MEETING WITH VIHA
CR+CV FINANCIAL CLOSE
DESIGNDESIGNDESIGNDESIGNDESIGN
CR+CV DESIGN - SD FORMAL SUBMISSION
CR+CV OBTAIN EXCAVATION PERMITS
CR+CV OBTAIN FOUNDATION PERMITS
CR+CV OBTAIN STRUCTURE & ENVELOPE PERMITS
CR+CV DESIGN - DD FORMAL SUBMISSION
CR+CV OBTAIN FULL BUILDING PERMITS
CR+CV DESIGN - CD 50% FITOUT SUBMISSION (L0 & L1)
CR+CV DESIGN - CD 50% FITOUT SUBMISSION (L2 +)
CR+CV DESIGN - CD 95% FITOUT SUBMISSION
COMOX VALLEYCOMOX VALLEYCOMOX VALLEYCOMOX VALLEYCOMOX VALLEY
CV CVH - POSSESSION OF SITE
CV CVH - START FOUNDATIONS
CV CVH - START SUSPENDED SLABS (L1)
CV CVH - START EXTERIOR WALLS (L1)
CV CVH - START INTERIOR LAYOUT & ROUGH-IN (L1)
CV CVH - FINISH SUSPENDED SLABS (L5)
CV CVH - START INTERIOR DRYWALL BOARD (L1)
CV CVH - MAIN ELEC. RM ENERGIZED (L0)
CV CVH - ENVELOPE SUBSTANTIALLY WEATHERTIGHT (L5)
CV CVH - START BUILDING SYSTEMS COMMISSIONING
CV CVH - INTERIOR FITOUT & FINISHES COMPLETE (L3/L4)
CV CVH - OCCUPANCY & SUBSTANTIAL COMPLETION
CV CVH - (FULL) SERVICE COMMENCEMENT
DESIGN (BOTH SITES)DESIGN (BOTH SITES)DESIGN (BOTH SITES)DESIGN (BOTH SITES)DESIGN (BOTH SITES)DESIGN (BOTH SITES)
SCHEMATIC DESIGNSCHEMATIC DESIGNSCHEMATIC DESIGNSCHEMATIC DESIGNSCHEMATIC DESIGN
SD - DRAFT SUBMISSIONSSD - DRAFT SUBMISSIONSSD - DRAFT SUBMISSIONSSD - DRAFT SUBMISSIONSSD - DRAFT SUBMISSIONS
SD CYCLE #01SD CYCLE #01SD CYCLE #01SD CYCLE #01SD CYCLE #01
CR+CV SD #01 - Design Concept Validation with Core User Group
CR+CV SD #01 - Prepare Draft Submittal Material (at Risk)
CR+CV SD #01 - Issue Draft Submittal Material to VIHA
CR+CV SD #01 - Clinical User Consultation Mtgs
CR+CV SD #01 - Technical User Consultation Mtgs
CR+CV SD #01 - Distribute Live Minutes
CR+CV SD #01 - VIHA Informal Comments
SD CYCLE #02SD CYCLE #02SD CYCLE #02SD CYCLE #02SD CYCLE #02
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Black Bars = Critical Tasks
Red Bars = Near-Critical Tasks (Float < 2mo)
Blue/Aqua Bars = Non-Critical Tasks
NIHP - PROJECT SCHEDULE (REV. FC-01) - 30 JUN '14 FC, 30 APR '17 SC
CVH PROJECT SCHEDULE
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 1 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CR+CV SD #02 - Incorporate Comments from SD #01
CR+CV SD #02 - Clinical User Consultation Mtgs
CR+CV SD #02 - Technical User Consultation Mtgs
CR+CV SD #02 - Distribute Live Minutes
CR+CV SD #02 - VIHA Informal Comments
SD - FORMAL SUBMISSIONSD - FORMAL SUBMISSIONSD - FORMAL SUBMISSIONSD - FORMAL SUBMISSIONSD - FORMAL SUBMISSION
CR+CV SD (Formal) - Prepare Submittal Pkg
CR+CV SD (Formal) - Issue Submittal Pkg to VIHA
CR+CV SD (Formal) - Presentation to VIHA
CR+CV SD (Formal) - VIHA Review Period
CR+CV SD (Formal) - Distribute VIHA Comments
CR+CV SD (Formal) - Close-out VIHA Comments
CR+CV SD (Formal) - Obtain "Reviewed" Status
DESIGN DEVELOPMENTDESIGN DEVELOPMENTDESIGN DEVELOPMENTDESIGN DEVELOPMENTDESIGN DEVELOPMENT
DD - DRAFT SUBMISSIONSDD - DRAFT SUBMISSIONSDD - DRAFT SUBMISSIONSDD - DRAFT SUBMISSIONSDD - DRAFT SUBMISSIONS
DD CYCLE #01DD CYCLE #01DD CYCLE #01DD CYCLE #01DD CYCLE #01
CR+CV DD #01 - Prepare Draft Subject Material for Consultation Mtgs
CR+CV DD #01 - Issue Draft Subject Material to VIHA
CR+CV DD #01 - Clinical User Consultation Mtgs
CR+CV DD #01 - Technical User Consultation Mtgs
CR+CV DD #01 - Distribute Live Minutes
CR+CV DD #01 - VIHA Informal Comments
DD CYCLE #02DD CYCLE #02DD CYCLE #02DD CYCLE #02DD CYCLE #02
CR+CV DD #02 - Prepare Draft Subject Material for Consultation Mtgs
CR+CV DD #02 - Issue Draft Subject Material to VIHA
CR+CV DD #02 - Clinical User Consultation Mtgs
CR+CV DD #02 - Technical User Consultation Mtgs
CR+CV DD #02 - Distribute Live Minutes
CR+CV DD #02 - VIHA Informal Comments
DD CYCLE #03DD CYCLE #03DD CYCLE #03DD CYCLE #03DD CYCLE #03
CR+CV DD #03 - Prepare Draft Subject Material for Consultation Mtgs
CR+CV DD #03 - Issue Draft Subject Material to VIHA
CR+CV DD #03 - Clinical User Consultation Mtgs
CR+CV DD #03 - Technical User Consultation Mtgs
CR+CV DD #03 - Distribute Live Minutes
CR+CV DD #03 - VIHA Informal Comments
DD - FORMAL SUBMISSIONDD - FORMAL SUBMISSIONDD - FORMAL SUBMISSIONDD - FORMAL SUBMISSIONDD - FORMAL SUBMISSION
CR+CV DD (Formal) - Prepare Submittal Pkg
CR+CV DD (Formal) - Issue Submittal Pkg to VIHA (& Cities for Permit)
CR+CV DD (Formal) - Presentation to VIHA
CR+CV DD (Formal) - VIHA Review Period
CR+CV DD (Formal) - Distribute VIHA Comments
CR+CV DD (Formal) - Close-out VIHA Comments
CR+CV DD (Formal) - Obtain "Reviewed" Status
MOCK-UPSMOCK-UPSMOCK-UPSMOCK-UPSMOCK-UPS
PHASE 1 - 1:1 SCALE TAPE MARKINGSPHASE 1 - 1:1 SCALE TAPE MARKINGSPHASE 1 - 1:1 SCALE TAPE MARKINGSPHASE 1 - 1:1 SCALE TAPE MARKINGSPHASE 1 - 1:1 SCALE TAPE MARKINGS
CR+CV Mockups (Ph. 1 - SD #01) - Prepare
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14)
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CR+CV Mockups (Ph. 1 - SD #01) - Review
CR+CV Mockups (Ph. 1 - SD #02) - Prepare
CR+CV Mockups (Ph. 1 - SD #02) - Review
PHASE 2 - 3D RENDERINGSPHASE 2 - 3D RENDERINGSPHASE 2 - 3D RENDERINGSPHASE 2 - 3D RENDERINGSPHASE 2 - 3D RENDERINGS
CR+CV Mockups (Ph. 2 - SD #01) - Prepare
CR+CV Mockups (Ph. 2 - SD #01) - Review
CR+CV Mockups (Ph. 2 - SD #02) - Prepare
CR+CV Mockups (Ph. 2 - SD #02) - Review
PHASE 3 - FULLY CONSTRUCTED OFF-SITEPHASE 3 - FULLY CONSTRUCTED OFF-SITEPHASE 3 - FULLY CONSTRUCTED OFF-SITEPHASE 3 - FULLY CONSTRUCTED OFF-SITEPHASE 3 - FULLY CONSTRUCTED OFF-SITE
CR+CV Mockups (Ph. 3 - DD #01) - Prepare
CR+CV Mockups (Ph. 3 - DD #02) - Prepare
CR+CV Mockups (Ph. 3 - DD #02) - Review
CR+CV Mockups (Ph. 3 - DD #01) - Review
CR+CV Mockups (Ph. 3 - DD #03) - Prepare
CR+CV Mockups (Ph. 3 - DD #03) - Review
PHASE 4 - IN-SITU PROTOTYPESPHASE 4 - IN-SITU PROTOTYPESPHASE 4 - IN-SITU PROTOTYPESPHASE 4 - IN-SITU PROTOTYPESPHASE 4 - IN-SITU PROTOTYPES
CR+CV Mockups (Ph. 4 - Fitout CD 95%) - Prepare
CR+CV Mockups (Ph. 4 - Fitout CD 95%) - Review
CR+CV Mockups (Ph. 4 - Fitout CD IFC) - Prepare
CR+CV Mockups (Ph. 4 - Fitout CD IFC) - Review
PERMITSPERMITSPERMITSPERMITSPERMITS
TREE CLEARING PERMITSTREE CLEARING PERMITSTREE CLEARING PERMITSTREE CLEARING PERMITSTREE CLEARING PERMITS
CR+CV Permits (Tree Clearing) - Prepare Application Packages (at Risk)
CR+CV Permits (Tree Clearing) - Submit Applications to Cities
CR+CV Permits (Tree Clearing) - Cities Rvw Period & Issue
EXCAVATION PERMITSEXCAVATION PERMITSEXCAVATION PERMITSEXCAVATION PERMITSEXCAVATION PERMITS
CR+CV Permits (Excav.) - Prepare Application Packages (at Risk)
CR+CV Permits (Excav.) - Submit Applications to Cities
CR+CV Permits (Excav.) - Cities Rvw Period & Issue
FOUNDATION PERMITSFOUNDATION PERMITSFOUNDATION PERMITSFOUNDATION PERMITSFOUNDATION PERMITS
CR+CV Permits (Fdns) - Prepare Application Packages (at Risk)
CR+CV Permits (Fdns) - Submit Applications to Cities
CR+CV Permits (Fdns) - Cities Rvw Period & Issue
STRUCTURE/ENVELOPE PERMITSSTRUCTURE/ENVELOPE PERMITSSTRUCTURE/ENVELOPE PERMITSSTRUCTURE/ENVELOPE PERMITSSTRUCTURE/ENVELOPE PERMITS
CR+CV Permits (Struc./Env.) - Prepare Application Packages
CR+CV Permits (Struc./Env.) - Submit Applications to Cities
CR+CV Permits (Struc./Env.) - Cities Rvw Period & Issue
FULL BUILDING PERMITSFULL BUILDING PERMITSFULL BUILDING PERMITSFULL BUILDING PERMITSFULL BUILDING PERMITS
CR+CV Permits (Full Bldg) - Prepare Application Packages
CR+CV Permits (Full Bldg) - Submit Applications to Cities
CR+CV Permits (Full Bldg) - Cities Rvw Period & Issue
WORK PACKAGESWORK PACKAGESWORK PACKAGESWORK PACKAGESWORK PACKAGES
SITE PREPARATIONSITE PREPARATIONSITE PREPARATIONSITE PREPARATIONSITE PREPARATION
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Site Prep. (95% CD) - Design (at Risk) & Prepare Submittal Pkg
CR+CV Site Prep. (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Site Prep. (95% CD) - VIHA Compliance Team Rvw & Issue Comments
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 3 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Site Prep. (IFC CD) - Prep. & Issue
ELEVATORSELEVATORSELEVATORSELEVATORSELEVATORS
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV Elev (50% CD) - Design (at Risk) & Prepare Submittal Pkg
CR+CV Elev (50% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Elev (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Elev (95% CD) - Design & Prepare Submittal Pkg
CR+CV Elev (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Elev (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Elev (IFC CD) - Prep. & Issue
FOUNDATIONSFOUNDATIONSFOUNDATIONSFOUNDATIONSFOUNDATIONS
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV Fdns (50% CD) - Design (at Risk) & Prepare Submittal Pkg
CR+CV Fdns (50% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Fdns (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Fdns (95% CD) - Design & Prepare Submittal Pkg
CR+CV Fdns (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Fdns (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Fdns (IFC CD) - Prep. & Issue
STRUCTURESTRUCTURESTRUCTURESTRUCTURESTRUCTURE
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV Struc (50% CD) - Design (at Risk) & Prepare Submittal Pkg
CR+CV Struc (50% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Struc (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Struc (95% CD) - Design & Prepare Submittal Pkg
CR+CV Struc (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Struc (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Struc (IFC CD - Fwk + Rebar) - Prep. & Issue
CR+CV Struc (IFC CD - L1 Sleeving + Embeds) - Prep. & Issue
CR+CV Struc (IFC CD - Struc. Steel + Pkd) - Prep. & Issue
CR+CV Struc (IFC CD - L2+ Sleeving + Embeds) - Prep. & Issue
CR+CV Struc (IFC CD - M/E Under SoG) - Prep. & Issue
ENVELOPEENVELOPEENVELOPEENVELOPEENVELOPE
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV Env (50% CD) - Design (at Risk) & Prepare Submittal Pkg
CR+CV Env (50% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Env (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Env (95% CD) - Design & Prepare Submittal Pkg
CR+CV Env (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Env (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 4 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CR+CV Env (IFC CD) - Prep. & Issue
CIVIL & LANDSCAPINGCIVIL & LANDSCAPINGCIVIL & LANDSCAPINGCIVIL & LANDSCAPINGCIVIL & LANDSCAPING
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV Civil + LS (50% CD) - Design (at Risk) & Prepare Submittal Pkg
CR+CV Civil + LS (50% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Civil + LS (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Civil + LS (95% CD) - Design & Prepare Submittal Pkg
CR+CV Civil + LS (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Civil + LS (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Civil + LS (IFC CD - Deep Util.) - Prep. & Issue
CR+CV Civil + LS (IFC CD - Site Finishes) - Prep. & Issue
MAJOR MECH./ELEC. EQ'TMAJOR MECH./ELEC. EQ'TMAJOR MECH./ELEC. EQ'TMAJOR MECH./ELEC. EQ'TMAJOR MECH./ELEC. EQ'T
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV Major M/E Eq't (50% CD) - Design & Prepare Submittal Pkg
CR+CV Major M/E Eq't (50% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Major M/E Eq't (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Major M/E Eq't (95% CD) - Design & Prepare Submittal Pkg
CR+CV Major M/E Eq't (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Major M/E Eq't (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Major M/E Eq't (IFC CD) - Prep. & Issue
HELIPORTHELIPORTHELIPORTHELIPORTHELIPORT
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV Heliport (50% CD) - Design & Prepare Submittal Pkg
CR+CV Heliport (50% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Heliport (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Heliport (95% CD) - Design & Prepare Submittal Pkg
CR+CV Heliport (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Heliport (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Heliport (IFC CD) - Prep. & Issue
FLOOR LAYOUTS - WALL & DOOR FRAMINGFLOOR LAYOUTS - WALL & DOOR FRAMINGFLOOR LAYOUTS - WALL & DOOR FRAMINGFLOOR LAYOUTS - WALL & DOOR FRAMINGFLOOR LAYOUTS - WALL & DOOR FRAMING
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Floor Layouts (95% CD) - Design & Prepare Submittal Pkg
CR+CV Floor Layouts (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV Floor Layouts (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Floor Layouts (IFC CD - Layout, Door Frames) - Prep. & Issue
M/E PRIMARY DISTRIBUTIONM/E PRIMARY DISTRIBUTIONM/E PRIMARY DISTRIBUTIONM/E PRIMARY DISTRIBUTIONM/E PRIMARY DISTRIBUTION
CD 50%CD 50%CD 50%CD 50%CD 50%
CR+CV M/E Primary (50% CD) - Design & Prepare Submittal Pkg
CR+CV M/E Primary (50% CD) - Issue for VIHA Compliance Team Rvw
CR+CV M/E Primary (50% CD) - VIHA Compliance Team Rvw & Issue Comments
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV M/E Primary (95% CD) - Design & Prepare Submittal Pkg
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 5 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days Start Finish
CR+CV M/E Primary (95% CD) - Issue for VIHA Compliance Team Rvw
CR+CV M/E Primary (95% CD) - VIHA Compliance Team Rvw & Issue Comments
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV M/E Primary Dist'n (IFC CD) - Prep. & Issue
INTERIOR FITOUT & FINISHESINTERIOR FITOUT & FINISHESINTERIOR FITOUT & FINISHESINTERIOR FITOUT & FINISHESINTERIOR FITOUT & FINISHES
CD 50%CD 50%CD 50%CD 50%CD 50%
L0 & L1L0 & L1L0 & L1L0 & L1L0 & L1
CR+CV Fitout (50% CD - L0 & L1) - Design & Prepare Submittal Pkg
CR+CV Fitout (50% CD - L0 & L1) - Issue for VIHA + Compliance Team Rvw
CR+CV Fitout (50% CD - L0 & L1) - VIHA + Compliance Team Rvw & Issue Comme
CR+CV Fitout (50% CD - L0 & L1) - Distribute VIHA Comments
CR+CV Fitout (50% CD - L0 & L1) - Close-out VIHA Comments
CR+CV Fitout (50% CD - L0 & L1) - Obtain "Reviewed" Status
L2 +L2 +L2 +L2 +L2 +
CR+CV Fitout (50% CD - L2 +) - Design & Prepare Submittal Pkg
CR+CV Fitout (50% CD - L2 +) - Issue for VIHA + Compliance Team Rvw
CR+CV Fitout (50% CD - L2 +) - VIHA + Compliance Team Rvw & Issue Comments
CR+CV Fitout (50% CD - L2 +) - Distribute VIHA Comments
CR+CV Fitout (50% CD - L2 +) - Close-out VIHA Comments
CR+CV Fitout (50% CD - L2 +) - Obtain "Reviewed" Status
CD 95%CD 95%CD 95%CD 95%CD 95%
CR+CV Fitout (95% CD) - Design & Prepare Submittal Pkg
CR+CV Fitout (95% CD) - Issue for VIHA + Compliance Team Rvw
CR+CV Fitout (95% CD) - VIHA + Compliance Team Rvw & Issue Comments
CR+CV Fitout (95% CD) - Distribute VIHA Comments
CR+CV Fitout (95% CD) - Close-out VIHA Comments
CR+CV Fitout (95% CD) - Obtain "Reviewed" Status
CD IFCCD IFCCD IFCCD IFCCD IFC
CR+CV Fitout (IFC CD - L0 & L1 - Clg/Wall Rough-in) - Prep. & Issue
CR+CV Fitout (IFC CD - L2 + - Clg/Wall Rough-in) - Prep. & Issue
CR+CV Fitout (IFC CD - Finishes) - Prep. & Issue
FFE PROCUREMENTFFE PROCUREMENTFFE PROCUREMENTFFE PROCUREMENTFFE PROCUREMENTFFE PROCUREMENT
FFE - EQUIPMENT LISTFFE - EQUIPMENT LISTFFE - EQUIPMENT LISTFFE - EQUIPMENT LISTFFE - EQUIPMENT LIST
CR+CV FFE - Issue Updated Eq't List (3 Vendors per Item)
CR+CV FFE - Validate Eq't List Based on Schematic Design
FFE - MAJOR ITEMSFFE - MAJOR ITEMSFFE - MAJOR ITEMSFFE - MAJOR ITEMSFFE - MAJOR ITEMS
DIAGNOSTIC IMAGING EQ'TDIAGNOSTIC IMAGING EQ'TDIAGNOSTIC IMAGING EQ'TDIAGNOSTIC IMAGING EQ'TDIAGNOSTIC IMAGING EQ'T
CR+CV FFE (DI Eq't) - Prepare RFP
CR+CV FFE (DI Eq't) - Bid Response
CR+CV FFE (DI Eq't) - Bid Analysis
CR+CV FFE (DI Eq't) - Bid Award
CR+CV FFE (DI Eq't) - Generate PO Req.
CR+CV FFE (DI Eq't) - Issue/Approve PO
CR+CV FFE (DI Eq't) - Shop Dwgs Prep. & Rvw (Initial Cycle)
CR+CV FFE (DI Eq't) - Shop Dwgs Prep. & Rvw (Final Cycle)
CR+CV FFE (DI Eq't) - Deliveries to Sites
LIGHT BOOMSLIGHT BOOMSLIGHT BOOMSLIGHT BOOMSLIGHT BOOMS
37ul
2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 6 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CR+CV FFE (Light Booms) - Prepare RFP
CR+CV FFE (Light Booms) - Bid Response
CR+CV FFE (Light Booms) - Bid Analysis
CR+CV FFE (Light Booms) - Bid Award
CR+CV FFE (Light Booms) - Generate PO Req.
CR+CV FFE (Light Booms) - Issue/Approve PO
CR+CV FFE (Light Booms) - Shop Dwgs Prep. & Rvw (Initial Cycle)
CR+CV FFE (Light Booms) - Shop Dwgs Prep. & Rvw (Final Cycle)
CR+CV FFE (Light Booms) - Deliveries to Sites
OPERATING ROOM BOOMSOPERATING ROOM BOOMSOPERATING ROOM BOOMSOPERATING ROOM BOOMSOPERATING ROOM BOOMS
CR+CV FFE (OR Booms) - Prepare RFP
CR+CV FFE (OR Booms) - Bid Response
CR+CV FFE (OR Booms) - Bid Analysis
CR+CV FFE (OR Booms) - Bid Award
CR+CV FFE (OR Booms) - Generate PO Req.
CR+CV FFE (OR Booms) - Issue/Approve PO
CR+CV FFE (OR Booms) - Shop Dwgs Prep. & Rvw (Initial Cycle)
CR+CV FFE (OR Booms) - Shop Dwgs Prep. & Rvw (Final Cycle)
CR+CV FFE (OR Booms) - Deliveries to Sites
FFE - OTHER ITEMSFFE - OTHER ITEMSFFE - OTHER ITEMSFFE - OTHER ITEMSFFE - OTHER ITEMS
ITEMS WITH STRUC. DESIGN IMPACTITEMS WITH STRUC. DESIGN IMPACTITEMS WITH STRUC. DESIGN IMPACTITEMS WITH STRUC. DESIGN IMPACTITEMS WITH STRUC. DESIGN IMPACT
CR+CV FFE (Struc. Impact) - Prepare RFPs
CR+CV FFE (Struc. Impact) - Bid Responses
CR+CV FFE (Struc. Impact) - Bid Analyses
CR+CV FFE (Struc. Impact) - Bid Awards
CR+CV FFE (Struc. Impact) - Generate PO Req.'s
CR+CV FFE (Struc. Impact) - Issue/Approve PO's
CR+CV FFE (Struc. Impact) - Shop Dwgs Prep. & Rvw (Initial Cycles)
CR+CV FFE (Struc. Impact) - Shop Dwgs Prep. & Rvw (Final Cycles)
CR+CV FFE (Struc. Impact) - Deliveries to Sites
ITEMS WITH FITOUT DESIGN IMPACTITEMS WITH FITOUT DESIGN IMPACTITEMS WITH FITOUT DESIGN IMPACTITEMS WITH FITOUT DESIGN IMPACTITEMS WITH FITOUT DESIGN IMPACT
CR+CV FFE (Fitout Impact) - Prepare RFPs
CR+CV FFE (Fitout Impact) - Bid Responses
CR+CV FFE (Fitout Impact) - Bid Analyses
CR+CV FFE (Fitout Impact) - Bid Awards
CR+CV FFE (Fitout Impact) - Generate PO Req.'s
CR+CV FFE (Fitout Impact) - Issue/Approve PO's
CR+CV FFE (Fitout Impact) - Shop Dwgs Prep. & Rvw (Initial Cycles)
CR+CV FFE (Fitout Impact) - Shop Dwgs Prep. & Rvw (Final Cycles)
CR+CV FFE (Fitout Impact) - Deliveries to Sites
ITEMS WITH NO DESIGN IMPACTITEMS WITH NO DESIGN IMPACTITEMS WITH NO DESIGN IMPACTITEMS WITH NO DESIGN IMPACTITEMS WITH NO DESIGN IMPACT
CR+CV FFE (Other) - Prepare RFPs
CR+CV FFE (Other) - Bid Responses
CR+CV FFE (Other) - Bid Analyses
CR+CV FFE (Other) - Bid Awards
CR+CV FFE (Other) - Generate PO Req.'s
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 7 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CR+CV FFE (Other) - Issue/Approve PO's
CR+CV FFE (Other) - Shop Dwgs Prep. & Rvw (Initial Cycles)
CR+CV FFE (Other) - Shop Dwgs Prep. & Rvw (Final Cycles)
CR+CV FFE (Other) - Deliveries to Sites
CVH - COMOX VALLEY HOSPITALCVH - COMOX VALLEY HOSPITALCVH - COMOX VALLEY HOSPITALCVH - COMOX VALLEY HOSPITALCVH - COMOX VALLEY HOSPITALCVH - COMOX VALLEY HOSPITAL
CVH - PRE-CONSTRUCTIONCVH - PRE-CONSTRUCTIONCVH - PRE-CONSTRUCTIONCVH - PRE-CONSTRUCTIONCVH - PRE-CONSTRUCTION
CVH (PRE-CON) - FOUNDATIONSCVH (PRE-CON) - FOUNDATIONSCVH (PRE-CON) - FOUNDATIONSCVH (PRE-CON) - FOUNDATIONSCVH (PRE-CON) - FOUNDATIONS
CV Lead Time - Rebar & Fwk (Fdns)
CV Lead Time - Rebar & Fwk (L0 Walls & Col's)
CVH (PRE-CON) - STRUCTURECVH (PRE-CON) - STRUCTURECVH (PRE-CON) - STRUCTURECVH (PRE-CON) - STRUCTURECVH (PRE-CON) - STRUCTURE
CV Lead Time - Rebar & Fwk (Susp. Slabs)
CV Lead Time - Struc. Steel (L5 PH + Stairs)
CV Lead Time - Parkade Precast
CV Lead Time - Heliport Structure
CVH (PRE-CON) - ENVELOPECVH (PRE-CON) - ENVELOPECVH (PRE-CON) - ENVELOPECVH (PRE-CON) - ENVELOPECVH (PRE-CON) - ENVELOPE
CV Lead Time - Curtain Wall
CV Lead Time - Ext. Wall Panel System (incl. Punch Windows)
CV Lead Time - Roofing
CV Lead Time - Ext. Finishes
CVH (PRE-CON) - FITOUT & FINISHESCVH (PRE-CON) - FITOUT & FINISHESCVH (PRE-CON) - FITOUT & FINISHESCVH (PRE-CON) - FITOUT & FINISHESCVH (PRE-CON) - FITOUT & FINISHES
EARLY ROUGH-IN ITEMSEARLY ROUGH-IN ITEMSEARLY ROUGH-IN ITEMSEARLY ROUGH-IN ITEMSEARLY ROUGH-IN ITEMS
CV Lead Time - M/E Primary Dist'n
L0 & L1L0 & L1L0 & L1L0 & L1L0 & L1
CV Lead Time - (L0 + L1) Doorframes
CV Lead Time - (L0 + L1) Steel Supports for Eq't
L2 +L2 +L2 +L2 +L2 +
CV Lead Time - (L2 +) Doorframes
CV Lead Time - (L2 +) Steel Supports for Eq't
MAJOR EQUIPMENT ITEMSMAJOR EQUIPMENT ITEMSMAJOR EQUIPMENT ITEMSMAJOR EQUIPMENT ITEMSMAJOR EQUIPMENT ITEMS
CV Lead Time - Elevators
CV Lead Time - Elec. Head End Eq't
CV Lead Time - Mech. Head End Eq't
CV Lead Time - Headwalls
CV Lead Time - Food Services Eq't
CV Lead Time - LV Systems Eq't
FINISHESFINISHESFINISHESFINISHESFINISHES
CV Lead Time - Flooring
CV Lead Time - Wall Prot'n & Handrails
CV Lead Time - Systems Furniture
L0 & L1L0 & L1L0 & L1L0 & L1L0 & L1
CV Lead Time - (L0 + L1) Doors & Hwr
CV Lead Time - (L0 + L1) Light Fixtures
CV Lead Time - (L0 + L1) Millwork
L2 +L2 +L2 +L2 +L2 +
CV Lead Time - (L2 +) Doors & Hwr
CV Lead Time - (L2 +) Light Fixtures
CV Lead Time - (L2 +) Millwork
CVH - CONSTRUCTIONCVH - CONSTRUCTIONCVH - CONSTRUCTIONCVH - CONSTRUCTIONCVH - CONSTRUCTION
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 8 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CVH - SITE PREPARATIONCVH - SITE PREPARATIONCVH - SITE PREPARATIONCVH - SITE PREPARATIONCVH - SITE PREPARATION
SITE ESTABLISHMENT & RELOCATIONSSITE ESTABLISHMENT & RELOCATIONSSITE ESTABLISHMENT & RELOCATIONSSITE ESTABLISHMENT & RELOCATIONSSITE ESTABLISHMENT & RELOCATIONS
CV Site - Traffic Pattern Changes
CV Site - Fencing, Tree Clearing, Site Strip + Access Roads
CV Site - Make Safe & Remove Other Misc. Util.
BULK EXCAVATIONBULK EXCAVATIONBULK EXCAVATIONBULK EXCAVATIONBULK EXCAVATION
CV Bulk Excav. - Basement (to L0)
CV Bulk Excav. - Rough Grade Upper Bench (to L1)
CVH - CONSTRUCTION EQ'T & INFRASTRUCTURECVH - CONSTRUCTION EQ'T & INFRASTRUCTURECVH - CONSTRUCTION EQ'T & INFRASTRUCTURECVH - CONSTRUCTION EQ'T & INFRASTRUCTURECVH - CONSTRUCTION EQ'T & INFRASTRUCTURE
SITE OFFICESSITE OFFICESSITE OFFICESSITE OFFICESSITE OFFICES
CV Site Offices - Establish Trailers
CV Site Offices - Demob. & Make Good
NORTH TOWER CRANENORTH TOWER CRANENORTH TOWER CRANENORTH TOWER CRANENORTH TOWER CRANE
CV Tower Crane (Nth) - Fdn & Erect
CV Tower Crane (Nth) - In Operation
CV Tower Crane (Nth) - Dismantle
CV Tower Crane (Nth) - Infill & Catch up Int. & Ext. Work
SOUTH TOWER CRANESOUTH TOWER CRANESOUTH TOWER CRANESOUTH TOWER CRANESOUTH TOWER CRANE
CV Tower Crane (Sth) - Fdn & Erect
CV Tower Crane (Sth) - In Operation
CV Tower Crane (Sth) - Dismantle
CV Tower Crane (Sth) - Infill & Catch up Int. & Ext. Work
CVH - STRUCTURECVH - STRUCTURECVH - STRUCTURECVH - STRUCTURECVH - STRUCTURE
L0L0L0L0L0
L0 - NORTH (3500 m2 SOG) (GL 1-6)L0 - NORTH (3500 m2 SOG) (GL 1-6)L0 - NORTH (3500 m2 SOG) (GL 1-6)L0 - NORTH (3500 m2 SOG) (GL 1-6)L0 - NORTH (3500 m2 SOG) (GL 1-6)
CV L0 (Nth) - Excav., FRP Pad Fdns & Cont. Fdns
CV L0 (Nth) - FRP Verticals (to U/S L1)
CV L0 (Nth) - U/S Util. & FRP SoG
L0 - CENTRE (3900 m2 SOG) (GL 6-12)L0 - CENTRE (3900 m2 SOG) (GL 6-12)L0 - CENTRE (3900 m2 SOG) (GL 6-12)L0 - CENTRE (3900 m2 SOG) (GL 6-12)L0 - CENTRE (3900 m2 SOG) (GL 6-12)
CV L0 (Ctr) - Excav., FRP Pad Fdns & Cont. Fdns
CV L0 (Ctr) - FRP Verticals (to U/S L1)
CV L0 (Ctr) - U/S Util. & FRP SoG
L1L1L1L1L1
L1 - NORTH (3500 m2 SS) (GL 1-6)L1 - NORTH (3500 m2 SS) (GL 1-6)L1 - NORTH (3500 m2 SS) (GL 1-6)L1 - NORTH (3500 m2 SS) (GL 1-6)L1 - NORTH (3500 m2 SS) (GL 1-6)
CV L1 (Nth) - FRP Susp Slab
CV L1 (Nth) - FRP Verticals (to U/S L2)
L1 - CENTRE (3900 m2 SS) (GL 6-12)L1 - CENTRE (3900 m2 SS) (GL 6-12)L1 - CENTRE (3900 m2 SS) (GL 6-12)L1 - CENTRE (3900 m2 SS) (GL 6-12)L1 - CENTRE (3900 m2 SS) (GL 6-12)
CV L1 (Ctr) - FRP Susp Slab (GL 6-10)
CV L1 (Ctr) - FRP Verticals (to U/S L2)
CV L1 (Ctr) - FRP Susp Slab (GL 10-12)
L1 - SOUTH (2900 m2 SOG) (GL 12-16)L1 - SOUTH (2900 m2 SOG) (GL 12-16)L1 - SOUTH (2900 m2 SOG) (GL 12-16)L1 - SOUTH (2900 m2 SOG) (GL 12-16)L1 - SOUTH (2900 m2 SOG) (GL 12-16)
CV L1 (Sth) - Excav., FRP Pad Fdns & Cont. Fdns
CV L1 (Sth) - FRP Verticals (to U/S L2)
CV L1 (Sth) - Backfill, U/S Util. & FRP SoG
L2L2L2L2L2
L2 - NORTH (3500 m2 SS) (GL 1-6)L2 - NORTH (3500 m2 SS) (GL 1-6)L2 - NORTH (3500 m2 SS) (GL 1-6)L2 - NORTH (3500 m2 SS) (GL 1-6)L2 - NORTH (3500 m2 SS) (GL 1-6)
CV L2 (Nth) - FRP Susp Slab
CV L2 (Nth) - FRP Verticals (to U/S L3)
L2 - CENTRE (4100 m2 SS) (GL 6-12)L2 - CENTRE (4100 m2 SS) (GL 6-12)L2 - CENTRE (4100 m2 SS) (GL 6-12)L2 - CENTRE (4100 m2 SS) (GL 6-12)L2 - CENTRE (4100 m2 SS) (GL 6-12)
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 9 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CV L2 (Ctr) - FRP Susp Slab
CV L2 (Ctr) - FRP Verticals (to U/S L3)
L2 - SOUTH (2800 m2 SS) (GL 12-16)L2 - SOUTH (2800 m2 SS) (GL 12-16)L2 - SOUTH (2800 m2 SS) (GL 12-16)L2 - SOUTH (2800 m2 SS) (GL 12-16)L2 - SOUTH (2800 m2 SS) (GL 12-16)
CV L2 (Sth) - FRP Susp Slab
CV L2 (Sth) - FRP Verticals (to U/S L3)
L3L3L3L3L3
L3 - NORTH (3000 m2 SS) (GL 1-6)L3 - NORTH (3000 m2 SS) (GL 1-6)L3 - NORTH (3000 m2 SS) (GL 1-6)L3 - NORTH (3000 m2 SS) (GL 1-6)L3 - NORTH (3000 m2 SS) (GL 1-6)
CV L3 (Nth) - FRP Susp Slab
CV L3 (Nth) - FRP Verticals (to U/S L4)
L3 - CENTRE (3500 m2 SS) (GL 6-12)L3 - CENTRE (3500 m2 SS) (GL 6-12)L3 - CENTRE (3500 m2 SS) (GL 6-12)L3 - CENTRE (3500 m2 SS) (GL 6-12)L3 - CENTRE (3500 m2 SS) (GL 6-12)
CV L3 (Ctr) - FRP Susp Slab
CV L3 (Ctr) - FRP Verticals (to U/S L4)
L3 - SOUTH (2200 m2 SS) (GL 12-16)L3 - SOUTH (2200 m2 SS) (GL 12-16)L3 - SOUTH (2200 m2 SS) (GL 12-16)L3 - SOUTH (2200 m2 SS) (GL 12-16)L3 - SOUTH (2200 m2 SS) (GL 12-16)
CV L3 (Sth) - FRP Susp Slab
CV L3 (Sth) - FRP Verticals, Upstands
L4L4L4L4L4
L4 - NORTH (2200 m2 SS) (GL 1-6)L4 - NORTH (2200 m2 SS) (GL 1-6)L4 - NORTH (2200 m2 SS) (GL 1-6)L4 - NORTH (2200 m2 SS) (GL 1-6)L4 - NORTH (2200 m2 SS) (GL 1-6)
CV L4 (Nth) - FRP Susp Slab
CV L4 (Nth) - FRP Verticals (to U/S L5)
L4 - CENTRE (2800 m2 SS) (GL 6-12)L4 - CENTRE (2800 m2 SS) (GL 6-12)L4 - CENTRE (2800 m2 SS) (GL 6-12)L4 - CENTRE (2800 m2 SS) (GL 6-12)L4 - CENTRE (2800 m2 SS) (GL 6-12)
CV L4 (Ctr) - FRP Susp Slab
CV L4 (Ctr) - FRP Verticals (to U/S L5)
L5 + PENTHOUSEL5 + PENTHOUSEL5 + PENTHOUSEL5 + PENTHOUSEL5 + PENTHOUSE
L5 - NORTH (2200 m2 SS) (GL 1-6)L5 - NORTH (2200 m2 SS) (GL 1-6)L5 - NORTH (2200 m2 SS) (GL 1-6)L5 - NORTH (2200 m2 SS) (GL 1-6)L5 - NORTH (2200 m2 SS) (GL 1-6)
CV L5 (Nth) - FRP Susp Slab
CV L5 (Nth) - FRP Verticals, Upstands & Cap Slabs
CV L5 (Nth) - Penthouse Struc. Steel & Deck
L5 - CENTRE (2800 m2 SS) (GL 6-12)L5 - CENTRE (2800 m2 SS) (GL 6-12)L5 - CENTRE (2800 m2 SS) (GL 6-12)L5 - CENTRE (2800 m2 SS) (GL 6-12)L5 - CENTRE (2800 m2 SS) (GL 6-12)
CV L5 (Ctr) - FRP Susp Slab
CV L5 (Ctr) - FRP Verticals, Upstands & Cap Slabs
CV L5 (Ctr) - Penthouse Struc. Steel & Deck
MISC.MISC.MISC.MISC.MISC.
CV Stair Cores - Struc. Steel & Deck
CVH - ENVELOPECVH - ENVELOPECVH - ENVELOPECVH - ENVELOPECVH - ENVELOPE
L0L0L0L0L0
L0 - NTHL0 - NTHL0 - NTHL0 - NTHL0 - NTH
CV L0 (Nth) - Ext. Walls (to Weathertight)
L0 - CENTREL0 - CENTREL0 - CENTREL0 - CENTREL0 - CENTRE
CV L0 (Ctr) - Ext. Walls (to Weathertight)
L1L1L1L1L1
L1 - NTHL1 - NTHL1 - NTHL1 - NTHL1 - NTH
CV L1 (Nth) - Ext. Walls (to Weathertight)
L1 - CENTREL1 - CENTREL1 - CENTREL1 - CENTREL1 - CENTRE
CV L1 (Ctr) - Ext. Walls (to Weathertight)
L1 - SOUTHL1 - SOUTHL1 - SOUTHL1 - SOUTHL1 - SOUTH
CV L1 (Sth) - Ext. Walls (to Weathertight)
L2L2L2L2L2
L2 - NTHL2 - NTHL2 - NTHL2 - NTHL2 - NTH
CV L2 (Nth) - Roofs (to Weathertight)
CV L2 (Nth) - Ext. Walls (to Weathertight)
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 10 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
L2 - CENTREL2 - CENTREL2 - CENTREL2 - CENTREL2 - CENTRE
CV L2 (Ctr) - Roofs (to Weathertight)
CV L2 (Ctr) - Ext. Walls (to Weathertight)
L2 - SOUTHL2 - SOUTHL2 - SOUTHL2 - SOUTHL2 - SOUTH
CV L2 (Sth) - Roofs (to Weathertight)
CV L2 (Sth) - Ext. Walls (to Weathertight)
L3L3L3L3L3
L3 - NTHL3 - NTHL3 - NTHL3 - NTHL3 - NTH
CV L3 (Nth) - Roofs (to Weathertight)
CV L3 (Nth) - Ext. Walls (to Weathertight)
L3 - CENTREL3 - CENTREL3 - CENTREL3 - CENTREL3 - CENTRE
CV L3 (Ctr) - Roofs (to Weathertight)
CV L3 (Ctr) - Ext. Walls (to Weathertight)
L3 - SOUTHL3 - SOUTHL3 - SOUTHL3 - SOUTHL3 - SOUTH
CV L3 (Sth) - Roofs (to Weathertight)
L4L4L4L4L4
L4 - NTHL4 - NTHL4 - NTHL4 - NTHL4 - NTH
CV L4 (Nth) - Ext. Walls (to Weathertight)
L4 - CENTREL4 - CENTREL4 - CENTREL4 - CENTREL4 - CENTRE
CV L4 (Ctr) - Ext. Walls (to Weathertight)
CV L4 (Ctr) - Roof (to Weathertight)
L5 + PENTHOUSEL5 + PENTHOUSEL5 + PENTHOUSEL5 + PENTHOUSEL5 + PENTHOUSE
L5 - NTHL5 - NTHL5 - NTHL5 - NTHL5 - NTH
CV L5 (Nth) - Roofs (to Weathertight)
CV L5 (Nth) - Ext. Walls (to Weathertight)
L5 - CENTREL5 - CENTREL5 - CENTREL5 - CENTREL5 - CENTRE
CV L5 (Ctr) - Ext. Walls (to Weathertight)
CV L5 (Ctr) - Roofs (to Weathertight)
L0-L5 - ENVELOPE FINISHESL0-L5 - ENVELOPE FINISHESL0-L5 - ENVELOPE FINISHESL0-L5 - ENVELOPE FINISHESL0-L5 - ENVELOPE FINISHES
CV L1 - L5 - Envelope Finishes
CVH - INTERIOR FITOUTCVH - INTERIOR FITOUTCVH - INTERIOR FITOUTCVH - INTERIOR FITOUTCVH - INTERIOR FITOUT
L0 (6000 m2)L0 (6000 m2)L0 (6000 m2)L0 (6000 m2)L0 (6000 m2)
L0 - 1 (NTH-EAST) - GL 1-6/A-F (FS, MM, ES) - 2500 m2L0 - 1 (NTH-EAST) - GL 1-6/A-F (FS, MM, ES) - 2500 m2L0 - 1 (NTH-EAST) - GL 1-6/A-F (FS, MM, ES) - 2500 m2L0 - 1 (NTH-EAST) - GL 1-6/A-F (FS, MM, ES) - 2500 m2L0 - 1 (NTH-EAST) - GL 1-6/A-F (FS, MM, ES) - 2500 m2
CV L0 - 1 (NE) - Layout, Top Track, Cast Iron
CV L0 - 1 (NE) - Primary Wall Framing, Upper Board
CV L0 - 1 (NE) - Main M/E Runs @ Clg
CV L0 - 1 (NE) - Secondary Wall Framing, Door Frames
CV L0 - 1 (NE) - M/E Rough-in to Clgs & Walls
CV L0 - 1 (NE) - Pre-Close Inspections, Insul., Final Backing
CV L0 - 1 (NE) - Board, Tape & Sand Walls & Bulkheads
CV L0 - 1 (NE) - Paint, T-Bar & M/E Clg Fixtures
CV L0 - 1 (NE) - Sheet Flooring
CV L0 - 1 (NE) - Millwork
CV L0 - 1 (NE) - A/M/E Finishes & Wall Fixtures
CV L0 - 1 (NE) - Substantially Dust Free
CV L0 - 1 (NE) - Med. Eq't & FFE
CV L0 - 1 (NE) - Punchlists, Builder's Clean
L0 - 2 (CTR-WEST) - GL 5-11/F-K (MED EQ'T SERVICE) - 1700 m2L0 - 2 (CTR-WEST) - GL 5-11/F-K (MED EQ'T SERVICE) - 1700 m2L0 - 2 (CTR-WEST) - GL 5-11/F-K (MED EQ'T SERVICE) - 1700 m2L0 - 2 (CTR-WEST) - GL 5-11/F-K (MED EQ'T SERVICE) - 1700 m2L0 - 2 (CTR-WEST) - GL 5-11/F-K (MED EQ'T SERVICE) - 1700 m2
CV L0 - 2 (CW) - Layout, Top Track, Cast Iron
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 11 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CV L0 - 2 (CW) - Primary Wall Framing, Upper Board
CV L0 - 2 (CW) - Main M/E Runs @ Clg
CV L0 - 2 (CW) - Secondary Wall Framing, Door Frames
CV L0 - 2 (CW) - M/E Rough-in to Clgs & Walls
CV L0 - 2 (CW) - Pre-Close Inspections, Insul., Final Backing
CV L0 - 2 (CW) - Board, Tape & Sand Walls & Bulkheads
CV L0 - 2 (CW) - Paint, T-Bar & M/E Clg Fixtures
CV L0 - 2 (CW) - Sheet Flooring
CV L0 - 2 (CW) - Millwork
CV L0 - 2 (CW) - A/M/E Finishes & Wall Fixtures
CV L0 - 2 (CW) - Substantially Dust Free
CV L0 - 2 (CW) - Med. Eq't & FFE
CV L0 - 2 (CW) - Punchlists, Builder's Clean
L0 - 3 (CTR-EAST) - GL 6-12/A-F (PHARM, OFFICES) - 1600 m2L0 - 3 (CTR-EAST) - GL 6-12/A-F (PHARM, OFFICES) - 1600 m2L0 - 3 (CTR-EAST) - GL 6-12/A-F (PHARM, OFFICES) - 1600 m2L0 - 3 (CTR-EAST) - GL 6-12/A-F (PHARM, OFFICES) - 1600 m2L0 - 3 (CTR-EAST) - GL 6-12/A-F (PHARM, OFFICES) - 1600 m2
CV L0 - 3 (CE) - Layout, Top Track, Cast Iron
CV L0 - 3 (CE) - Primary Wall Framing, Upper Board
CV L0 - 3 (CE) - Main M/E Runs @ Clg
CV L0 - 3 (CE) - Secondary Wall Framing, Door Frames
CV L0 - 3 (CE) - M/E Rough-in to Clgs & Walls
CV L0 - 3 (CE) - Pre-Close Inspections, Insul., Final Backing
CV L0 - 3 (CE) - Board, Tape & Sand Walls & Bulkheads
CV L0 - 3 (CE) - Paint, T-Bar & M/E Clg Fixtures
CV L0 - 3 (CE) - Sheet Flooring
CV L0 - 3 (CE) - Millwork
CV L0 - 3 (CE) - A/M/E Finishes & Wall Fixtures
CV L0 - 3 (CE) - Substantially Dust Free
CV L0 - 3 (CE) - Med. Eq't & FFE
CV L0 - 3 (CE) - Punchlists, Builder's Clean
L1 (10000 m2)L1 (10000 m2)L1 (10000 m2)L1 (10000 m2)L1 (10000 m2)
L1 - 1 (NTH-WEST) - GL 1-6/E-K (OUTPATIENT, REG.) - 2600 m2L1 - 1 (NTH-WEST) - GL 1-6/E-K (OUTPATIENT, REG.) - 2600 m2L1 - 1 (NTH-WEST) - GL 1-6/E-K (OUTPATIENT, REG.) - 2600 m2L1 - 1 (NTH-WEST) - GL 1-6/E-K (OUTPATIENT, REG.) - 2600 m2L1 - 1 (NTH-WEST) - GL 1-6/E-K (OUTPATIENT, REG.) - 2600 m2
CV L1 - 1 (NW) - Layout, Top Track, Cast Iron
CV L1 - 1 (NW) - Primary Wall Framing, Upper Board
CV L1 - 1 (NW) - Main M/E Runs @ Clg
CV L1 - 1 (NW) - Secondary Wall Framing, Door Frames
CV L1 - 1 (NW) - M/E Rough-in to Clgs & Walls
CV L1 - 1 (NW) - Pre-Close Inspections, Insul., Final Backing
CV L1 - 1 (NW) - Board, Tape & Sand Walls & Bulkheads
CV L1 - 1 (NW) - Paint, T-Bar & M/E Clg Fixtures
CV L1 - 1 (NW) - Sheet Flooring
CV L1 - 1 (NW) - Millwork
CV L1 - 1 (NW) - A/M/E Finishes & Wall Fixtures
CV L1 - 1 (NW) - Substantially Dust Free
CV L1 - 1 (NW) - Med. Eq't & FFE
CV L1 - 1 (NW) - Punchlists, Builder's Clean
L1 - 2 (NTH-EAST) - GL 1-6/A-E (THERAPY) - 1200 m2L1 - 2 (NTH-EAST) - GL 1-6/A-E (THERAPY) - 1200 m2L1 - 2 (NTH-EAST) - GL 1-6/A-E (THERAPY) - 1200 m2L1 - 2 (NTH-EAST) - GL 1-6/A-E (THERAPY) - 1200 m2L1 - 2 (NTH-EAST) - GL 1-6/A-E (THERAPY) - 1200 m2
CV L1 - 2 (NE) - Layout, Top Track, Cast Iron
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 12 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CV L1 - 2 (NE) - Primary Wall Framing, Upper Board
CV L1 - 2 (NE) - Main M/E Runs @ Clg
CV L1 - 2 (NE) - Secondary Wall Framing, Door Frames
CV L1 - 2 (NE) - M/E Rough-in to Clgs & Walls
CV L1 - 2 (NE) - Pre-Close Inspections, Insul., Final Backing
CV L1 - 2 (NE) - Board, Tape & Sand Walls & Bulkheads
CV L1 - 2 (NE) - Paint, T-Bar & M/E Clg Fixtures
CV L1 - 2 (NE) - Sheet Flooring
CV L1 - 2 (NE) - Millwork
CV L1 - 2 (NE) - A/M/E Finishes & Wall Fixtures
CV L1 - 2 (NE) - Substantially Dust Free
CV L1 - 2 (NE) - Med. Eq't & FFE
CV L1 - 2 (NE) - Punchlists, Builder's Clean
L1 - 3 (CTR-WEST) - GL 6-12/G-K (IMAGING) - 1900 m2L1 - 3 (CTR-WEST) - GL 6-12/G-K (IMAGING) - 1900 m2L1 - 3 (CTR-WEST) - GL 6-12/G-K (IMAGING) - 1900 m2L1 - 3 (CTR-WEST) - GL 6-12/G-K (IMAGING) - 1900 m2L1 - 3 (CTR-WEST) - GL 6-12/G-K (IMAGING) - 1900 m2
CV L1 - 3 (CW) - Layout, Top Track, Cast Iron
CV L1 - 3 (CW) - Primary Wall Framing, Upper Board
CV L1 - 3 (CW) - Main M/E Runs @ Clg
CV L1 - 3 (CW) - Secondary Wall Framing, Door Frames
CV L1 - 3 (CW) - M/E Rough-in to Clgs & Walls
CV L1 - 3 (CW) - Pre-Close Inspections, Insul., Final Backing
CV L1 - 3 (CW) - Board, Tape & Sand Walls & Bulkheads
CV L1 - 3 (CW) - Paint, T-Bar & M/E Clg Fixtures
CV L1 - 3 (CW) - Sheet Flooring
CV L1 - 3 (CW) - Millwork
CV L1 - 3 (CW) - A/M/E Finishes & Wall Fixtures
CV L1 - 3 (CW) - Substantially Dust Free
CV L1 - 3 (CW) - Med. Eq't & FFE
CV L1 - 3 (CW) - Punchlists, Builder's Clean
L1 - 4 (CTR-EAST) - GL 6-12/A-G (AMB. CARE) - 2400 m2L1 - 4 (CTR-EAST) - GL 6-12/A-G (AMB. CARE) - 2400 m2L1 - 4 (CTR-EAST) - GL 6-12/A-G (AMB. CARE) - 2400 m2L1 - 4 (CTR-EAST) - GL 6-12/A-G (AMB. CARE) - 2400 m2L1 - 4 (CTR-EAST) - GL 6-12/A-G (AMB. CARE) - 2400 m2
CV L1 - 4 (CE) - Layout, Top Track, Cast Iron
CV L1 - 4 (CE) - Primary Wall Framing, Upper Board
CV L1 - 4 (CE) - Main M/E Runs @ Clg
CV L1 - 4 (CE) - Secondary Wall Framing, Door Frames
CV L1 - 4 (CE) - M/E Rough-in to Clgs & Walls
CV L1 - 4 (CE) - Pre-Close Inspections, Insul., Final Backing
CV L1 - 4 (CE) - Board, Tape & Sand Walls & Bulkheads
CV L1 - 4 (CE) - Paint, T-Bar & M/E Clg Fixtures
CV L1 - 4 (CE) - Sheet Flooring
CV L1 - 4 (CE) - Millwork
CV L1 - 4 (CE) - A/M/E Finishes & Wall Fixtures
CV L1 - 4 (CE) - Substantially Dust Free
CV L1 - 4 (CE) - Med. Eq't & FFE
CV L1 - 4 (CE) - Punchlists, Builder's Clean
L1 - 5 (STH) - GL12-15/A-K (EMERGENCY) - 2000 m2L1 - 5 (STH) - GL12-15/A-K (EMERGENCY) - 2000 m2L1 - 5 (STH) - GL12-15/A-K (EMERGENCY) - 2000 m2L1 - 5 (STH) - GL12-15/A-K (EMERGENCY) - 2000 m2L1 - 5 (STH) - GL12-15/A-K (EMERGENCY) - 2000 m2
CV L1 - 5 (S) - Layout, Top Track, Cast Iron
CV L1 - 5 (S) - Primary Wall Framing, Upper Board
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 13 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CV L1 - 5 (S) - Main M/E Runs @ Clg
CV L1 - 5 (S) - Secondary Wall Framing, Door Frames
CV L1 - 5 (S) - M/E Rough-in to Clgs & Walls
CV L1 - 5 (S) - Pre-Close Inspections, Insul., Final Backing
CV L1 - 5 (S) - Board, Tape & Sand Walls & Bulkheads
CV L1 - 5 (S) - Paint, T-Bar & M/E Clg Fixtures
CV L1 - 5 (S) - Sheet Flooring
CV L1 - 5 (S) - Millwork
CV L1 - 5 (S) - A/M/E Finishes & Wall Fixtures
CV L1 - 5 (S) - Substantially Dust Free
CV L1 - 5 (S) - Med. Eq't & FFE
CV L1 - 5 (S) - Punchlists, Builder's Clean
L2 (8500 m2)L2 (8500 m2)L2 (8500 m2)L2 (8500 m2)L2 (8500 m2)
L2 - 0 (NTH-WEST) - GL 2-11/I-K (OR's) - 1100 m2 <SEP. CREW>L2 - 0 (NTH-WEST) - GL 2-11/I-K (OR's) - 1100 m2 <SEP. CREW>L2 - 0 (NTH-WEST) - GL 2-11/I-K (OR's) - 1100 m2 <SEP. CREW>L2 - 0 (NTH-WEST) - GL 2-11/I-K (OR's) - 1100 m2 <SEP. CREW>L2 - 0 (NTH-WEST) - GL 2-11/I-K (OR's) - 1100 m2 <SEP. CREW>
CV L2 - 0 (ORs) - Layout, Top Track, Cast Iron
CV L2 - 0 (ORs) - Primary Wall Framing, Upper Board
CV L2 - 0 (ORs) - Main M/E Runs @ Clg
CV L2 - 0 (ORs) - Secondary Wall Framing, Door Frames
CV L2 - 0 (ORs) - M/E Rough-in to Clgs & Walls
CV L2 - 0 (ORs) - Pre-Close Inspections, Insul., Final Backing
CV L2 - 0 (ORs) - Board, Tape & Sand Walls & Bulkheads
CV L2 - 0 (ORs) - Paint, T-Bar & M/E Clg Fixtures
CV L2 - 0 (ORs) - Sheet Flooring
CV L2 - 0 (ORs) - Millwork
CV L2 - 0 (ORs) - A/M/E Finishes & Wall Fixtures
CV L2 - 0 (ORs) - Substantially Dust Free
CV L2 - 0 (ORs) - Med. Eq't & FFE
CV L2 - 0 (ORs) - Punchlists, Builder's Clean
L2 - 1 (NTH-WEST) - GL 1-10/E-I (SURGICAL) - 2000 m2L2 - 1 (NTH-WEST) - GL 1-10/E-I (SURGICAL) - 2000 m2L2 - 1 (NTH-WEST) - GL 1-10/E-I (SURGICAL) - 2000 m2L2 - 1 (NTH-WEST) - GL 1-10/E-I (SURGICAL) - 2000 m2L2 - 1 (NTH-WEST) - GL 1-10/E-I (SURGICAL) - 2000 m2
CV L2 - 1 (NW) - Layout, Top Track, Cast Iron
CV L2 - 1 (NW) - Primary Wall Framing, Upper Board
CV L2 - 1 (NW) - Main M/E Runs @ Clg
CV L2 - 1 (NW) - Secondary Wall Framing, Door Frames
CV L2 - 1 (NW) - M/E Rough-in to Clgs & Walls
CV L2 - 1 (NW) - Pre-Close Inspections, Insul., Final Backing
CV L2 - 1 (NW) - Board, Tape & Sand Walls & Bulkheads
CV L2 - 1 (NW) - Paint, T-Bar & M/E Clg Fixtures
CV L2 - 1 (NW) - Sheet Flooring
CV L2 - 1 (NW) - Millwork
CV L2 - 1 (NW) - A/M/E Finishes & Wall Fixtures
CV L2 - 1 (NW) - Substantially Dust Free
CV L2 - 1 (NW) - Med. Eq't & FFE
CV L2 - 1 (NW) - Punchlists, Builder's Clean
L2 - 2 (NTH-EAST) - GL 1-7/A-E (MATERNITY, PAED.) - 1900 m2L2 - 2 (NTH-EAST) - GL 1-7/A-E (MATERNITY, PAED.) - 1900 m2L2 - 2 (NTH-EAST) - GL 1-7/A-E (MATERNITY, PAED.) - 1900 m2L2 - 2 (NTH-EAST) - GL 1-7/A-E (MATERNITY, PAED.) - 1900 m2L2 - 2 (NTH-EAST) - GL 1-7/A-E (MATERNITY, PAED.) - 1900 m2
CV L2 - 2 (NE) - Layout, Top Track, Cast Iron
CV L2 - 2 (NE) - Primary Wall Framing, Upper Board
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 14 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CV L2 - 2 (NE) - Main M/E Runs @ Clg
CV L2 - 2 (NE) - Secondary Wall Framing, Door Frames
CV L2 - 2 (NE) - M/E Rough-in to Clgs & Walls
CV L2 - 2 (NE) - Pre-Close Inspections, Insul., Final Backing
CV L2 - 2 (NE) - Board, Tape & Sand Walls & Bulkheads
CV L2 - 2 (NE) - Paint, T-Bar & M/E Clg Fixtures
CV L2 - 2 (NE) - Sheet Flooring
CV L2 - 2 (NE) - Millwork
CV L2 - 2 (NE) - A/M/E Finishes & Wall Fixtures
CV L2 - 2 (NE) - Substantially Dust Free
CV L2 - 2 (NE) - Med. Eq't & FFE
CV L2 - 2 (NE) - Punchlists, Builder's Clean
L2 - 3 (STH-WEST) - GL 10-15/F-K (LAB., MED. STAFF, UBC) - 1800 L2 - 3 (STH-WEST) - GL 10-15/F-K (LAB., MED. STAFF, UBC) - 1800 L2 - 3 (STH-WEST) - GL 10-15/F-K (LAB., MED. STAFF, UBC) - 1800 L2 - 3 (STH-WEST) - GL 10-15/F-K (LAB., MED. STAFF, UBC) - 1800 L2 - 3 (STH-WEST) - GL 10-15/F-K (LAB., MED. STAFF, UBC) - 1800
CV L2 - 3 (SW) - Layout, Top Track, Cast Iron
CV L2 - 3 (SW) - Primary Wall Framing, Upper Board
CV L2 - 3 (SW) - Main M/E Runs @ Clg
CV L2 - 3 (SW) - Secondary Wall Framing, Door Frames
CV L2 - 3 (SW) - M/E Rough-in to Clgs & Walls
CV L2 - 3 (SW) - Pre-Close Inspections, Insul., Final Backing
CV L2 - 3 (SW) - Board, Tape & Sand Walls & Bulkheads
CV L2 - 3 (SW) - Paint, T-Bar & M/E Clg Fixtures
CV L2 - 3 (SW) - Sheet Flooring
CV L2 - 3 (SW) - Millwork
CV L2 - 3 (SW) - A/M/E Finishes & Wall Fixtures
CV L2 - 3 (SW) - Substantially Dust Free
CV L2 - 3 (SW) - Med. Eq't & FFE
CV L2 - 3 (SW) - Punchlists, Builder's Clean
L2 - 4 (STH-EAST) - GL 7-14/A-D (ICU) - 1700 m2L2 - 4 (STH-EAST) - GL 7-14/A-D (ICU) - 1700 m2L2 - 4 (STH-EAST) - GL 7-14/A-D (ICU) - 1700 m2L2 - 4 (STH-EAST) - GL 7-14/A-D (ICU) - 1700 m2L2 - 4 (STH-EAST) - GL 7-14/A-D (ICU) - 1700 m2
CV L2 - 4 (SE) - Layout, Top Track, Cast Iron
CV L2 - 4 (SE) - Primary Wall Framing, Upper Board
CV L2 - 4 (SE) - Main M/E Runs @ Clg
CV L2 - 4 (SE) - Secondary Wall Framing, Door Frames
CV L2 - 4 (SE) - M/E Rough-in to Clgs & Walls
CV L2 - 4 (SE) - Pre-Close Inspections, Insul., Final Backing
CV L2 - 4 (SE) - Board, Tape & Sand Walls & Bulkheads
CV L2 - 4 (SE) - Paint, T-Bar & M/E Clg Fixtures
CV L2 - 4 (SE) - Sheet Flooring
CV L2 - 4 (SE) - Millwork
CV L2 - 4 (SE) - A/M/E Finishes & Wall Fixtures
CV L2 - 4 (SE) - Substantially Dust Free
CV L2 - 4 (SE) - Med. Eq't & FFE
CV L2 - 4 (SE) - Punchlists, Builder's Clean
L3 (5000 m2)L3 (5000 m2)L3 (5000 m2)L3 (5000 m2)L3 (5000 m2)
L3 - 1 (WEST) - GL 1-12/E-I (IPU) - 2500 m2L3 - 1 (WEST) - GL 1-12/E-I (IPU) - 2500 m2L3 - 1 (WEST) - GL 1-12/E-I (IPU) - 2500 m2L3 - 1 (WEST) - GL 1-12/E-I (IPU) - 2500 m2L3 - 1 (WEST) - GL 1-12/E-I (IPU) - 2500 m2
CV L3 - 1 (W) - Layout, Top Track, Cast Iron
CV L3 - 1 (W) - Primary Wall Framing, Upper Board
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 15 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CV L3 - 1 (W) - Main M/E Runs @ Clg
CV L3 - 1 (W) - Secondary Wall Framing, Door Frames
CV L3 - 1 (W) - M/E Rough-in to Clgs & Walls
CV L3 - 1 (W) - Pre-Close Inspections, Insul., Final Backing
CV L3 - 1 (W) - Board, Tape & Sand Walls & Bulkheads
CV L3 - 1 (W) - Paint, T-Bar & M/E Clg Fixtures
CV L3 - 1 (W) - Sheet Flooring
CV L3 - 1 (W) - Millwork
CV L3 - 1 (W) - A/M/E Finishes & Wall Fixtures
CV L3 - 1 (W) - Substantially Dust Free
CV L3 - 1 (W) - Med. Eq't & FFE
CV L3 - 1 (W) - Punchlists, Builder's Clean
L3 - 2 (EAST) - GL 1-12/A-E (IPU) - 2500 m2L3 - 2 (EAST) - GL 1-12/A-E (IPU) - 2500 m2L3 - 2 (EAST) - GL 1-12/A-E (IPU) - 2500 m2L3 - 2 (EAST) - GL 1-12/A-E (IPU) - 2500 m2L3 - 2 (EAST) - GL 1-12/A-E (IPU) - 2500 m2
CV L3 - 2 (E) - Layout, Top Track, Cast Iron
CV L3 - 2 (E) - Primary Wall Framing, Upper Board
CV L3 - 2 (E) - Main M/E Runs @ Clg
CV L3 - 2 (E) - Secondary Wall Framing, Door Frames
CV L3 - 2 (E) - M/E Rough-in to Clgs & Walls
CV L3 - 2 (E) - Pre-Close Inspections, Insul., Final Backing
CV L3 - 2 (E) - Board, Tape & Sand Walls & Bulkheads
CV L3 - 2 (E) - Paint, T-Bar & M/E Clg Fixtures
CV L3 - 2 (E) - Sheet Flooring
CV L3 - 2 (E) - Millwork
CV L3 - 2 (E) - A/M/E Finishes & Wall Fixtures
CV L3 - 2 (E) - Substantially Dust Free
CV L3 - 2 (E) - Med. Eq't & FFE
CV L3 - 2 (E) - Punchlists, Builder's Clean
L4 (4800 m2)L4 (4800 m2)L4 (4800 m2)L4 (4800 m2)L4 (4800 m2)
L4 - 1 (WEST) - GL 1-11/E-I (PSYCH IPU) - 2200 m2L4 - 1 (WEST) - GL 1-11/E-I (PSYCH IPU) - 2200 m2L4 - 1 (WEST) - GL 1-11/E-I (PSYCH IPU) - 2200 m2L4 - 1 (WEST) - GL 1-11/E-I (PSYCH IPU) - 2200 m2L4 - 1 (WEST) - GL 1-11/E-I (PSYCH IPU) - 2200 m2
CV L4 - 1 (W) - Layout, Top Track, Cast Iron
CV L4 - 1 (W) - Primary Wall Framing, Upper Board
CV L4 - 1 (W) - Main M/E Runs @ Clg
CV L4 - 1 (W) - Secondary Wall Framing, Door Frames
CV L4 - 1 (W) - M/E Rough-in to Clgs & Walls
CV L4 - 1 (W) - Pre-Close Inspections, Insul., Final Backing
CV L4 - 1 (W) - Board, Tape & Sand Walls & Bulkheads
CV L4 - 1 (W) - Paint, T-Bar & M/E Clg Fixtures
CV L4 - 1 (W) - Sheet Flooring
CV L4 - 1 (W) - Millwork
CV L4 - 1 (W) - A/M/E Finishes & Wall Fixtures
CV L4 - 1 (W) - Substantially Dust Free
CV L4 - 1 (W) - Med. Eq't & FFE
CV L4 - 1 (W) - Punchlists, Builder's Clean
L4 - 2 (EAST) - GL 1-12/A-E (IPU) - 2600 m2L4 - 2 (EAST) - GL 1-12/A-E (IPU) - 2600 m2L4 - 2 (EAST) - GL 1-12/A-E (IPU) - 2600 m2L4 - 2 (EAST) - GL 1-12/A-E (IPU) - 2600 m2L4 - 2 (EAST) - GL 1-12/A-E (IPU) - 2600 m2
CV L4 - 2 (E) - Layout, Top Track, Cast Iron
CV L4 - 2 (E) - Primary Wall Framing, Upper Board
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 16 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CV L4 - 2 (E) - Main M/E Runs @ Clg
CV L4 - 2 (E) - Secondary Wall Framing, Door Frames
CV L4 - 2 (E) - M/E Rough-in to Clgs & Walls
CV L4 - 2 (E) - Pre-Close Inspections, Insul., Final Backing
CV L4 - 2 (E) - Board, Tape & Sand Walls & Bulkheads
CV L4 - 2 (E) - Paint, T-Bar & M/E Clg Fixtures
CV L4 - 2 (E) - Sheet Flooring
CV L4 - 2 (E) - Millwork
CV L4 - 2 (E) - A/M/E Finishes & Wall Fixtures
CV L4 - 2 (E) - Substantially Dust Free
CV L4 - 2 (E) - Med. Eq't & FFE
CV L4 - 2 (E) - Punchlists, Builder's Clean
CVH - MAJOR PLANT & EQ'T ROOMSCVH - MAJOR PLANT & EQ'T ROOMSCVH - MAJOR PLANT & EQ'T ROOMSCVH - MAJOR PLANT & EQ'T ROOMSCVH - MAJOR PLANT & EQ'T ROOMS
L0 - MECH. ROOMSL0 - MECH. ROOMSL0 - MECH. ROOMSL0 - MECH. ROOMSL0 - MECH. ROOMS
CV L0 - Mech Rms - Buildout (incl. Walls, HK Pads etc.)
CV L0 - Mech Rms - Piping, Ductwork, Controls etc.
CV L0 - Mech Rms - Set & Assemble Eq't
CV L0 - Mech Rms - Elec. to Mech. Eq't
CV L0 - Mech Rms - Eq't Energized
L0 - MAIN ELEC. ROOML0 - MAIN ELEC. ROOML0 - MAIN ELEC. ROOML0 - MAIN ELEC. ROOML0 - MAIN ELEC. ROOM
CV L0 - Main Elec Rm - Buildout (incl. Walls, HK Pads etc.)
CV L0 - Main Elec Rm - Feeders, Terminations & Initial Testing
CV L0 - Main Elec Rm - Set & Assemble Eq't
CV L0 - Main Elec Rm - Eq't Energized
L0-L4 - SUB-ELEC. ROOMS & RISERSL0-L4 - SUB-ELEC. ROOMS & RISERSL0-L4 - SUB-ELEC. ROOMS & RISERSL0-L4 - SUB-ELEC. ROOMS & RISERSL0-L4 - SUB-ELEC. ROOMS & RISERS
CV L0-L4 - Sub-Elec Rms/Risers - Buildout (incl. Walls, HK Pads etc.)
CV L0-L4 - Sub-Elec Rms/Risers - Set & Assemble Eq't
CV L0-L4 - Sub-Elec Rms/Risers - Feeders, Terminations & Initial Testing
CV L0-L4 - Sub-Elec Rms/Risers - Eq't Energized
L0 - MAIN DATA ROOML0 - MAIN DATA ROOML0 - MAIN DATA ROOML0 - MAIN DATA ROOML0 - MAIN DATA ROOM
CV L0 - Main Data Rm - Buildout (incl. Walls, HK Pads etc.)
CV L0 - Main Data Rm - Set & Assemble Racks, Panels
CV L0 - Main Data Rm - Backbone & Horizontal Cable
CV L0 - Main Data Rm - Live & Ready for Active Eq't
L0-L4 - SUB-DATA ROOMS & RISERSL0-L4 - SUB-DATA ROOMS & RISERSL0-L4 - SUB-DATA ROOMS & RISERSL0-L4 - SUB-DATA ROOMS & RISERSL0-L4 - SUB-DATA ROOMS & RISERS
CV L0-L4 - Sub-Data Rms/Risers - Buildout (incl. Walls, HK Pads etc.)
CV L0-L4 - Sub-Data Rms/Risers - Set & Assemble Racks, Panels
CV L0-L4 - Sub-Data Rms/Risers - Backbone & Horizontal Cable
CV L0-L4 - Sub-Data Rms/Risers - Live & Ready for Active Eq't
L5 - MECH. PENTHOUSEL5 - MECH. PENTHOUSEL5 - MECH. PENTHOUSEL5 - MECH. PENTHOUSEL5 - MECH. PENTHOUSE
CV L5 - Mech Penthouse - Buildout (incl. HK Pads etc.)
CV L5 - Mech Penthouse - Set & Assemble Eq't
CV L5 - Mech Penthouse - Piping, Ductwork, Controls etc.
CV L5 - Mech Penthouse - Elec. to Mech. Eq't
CV L5 - Mech Penthouse - Eq't Energized
L5 - HELIPADL5 - HELIPADL5 - HELIPADL5 - HELIPADL5 - HELIPAD
CV L5 - Helipad Structure
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 17 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CV L5 - Helipad Systems & Finishes
GENERATORSGENERATORSGENERATORSGENERATORSGENERATORS
CV Generators - Buildout (incl. Ductbank, Slabs etc.)
CV Generators - Set & Assemble Eq't (incl. Fuel Systems)
CV Generators - Feeders, Terminations & Initial Testing
CV Generators - Energized
TANK FARMTANK FARMTANK FARMTANK FARMTANK FARM
CV Tank Farm - Buildout (incl. Ductbank, Slabs etc.)
CV Tank Farm - Set & Assemble Tanks & Eq't
CV Tank Farm - Piping & Hookup
CV Tank Farm - Energized
ELEVATORS & LOBBIESELEVATORS & LOBBIESELEVATORS & LOBBIESELEVATORS & LOBBIESELEVATORS & LOBBIES
PATIENT ELEVATORS (2 EA - L0-L4)PATIENT ELEVATORS (2 EA - L0-L4)PATIENT ELEVATORS (2 EA - L0-L4)PATIENT ELEVATORS (2 EA - L0-L4)PATIENT ELEVATORS (2 EA - L0-L4)
CV Elev. (Patient - 2 ea) - Prep. Shafts & MRs
CV Elev. (Patient - 2 ea) - Install
CV Elev. (Patient - 2 ea) - EMR Eq't Energized (Const'n Power)
CV Elev. (Patient - 2 ea) - Use as Const'n Hoists
CV Elev. (Patient - 2 ea) - Lobby Finishes
PUBLIC ELEVATORS (3 EA - L0-L3)PUBLIC ELEVATORS (3 EA - L0-L3)PUBLIC ELEVATORS (3 EA - L0-L3)PUBLIC ELEVATORS (3 EA - L0-L3)PUBLIC ELEVATORS (3 EA - L0-L3)
CV Elev. (Public - 3 ea) - Prep. Shafts & MRs
CV Elev. (Public - 3 ea) - Install
CV Elev. (Public - 3 ea) - EMR Eq't Energized (Perm. Power)
CV Elev. (Public - 3 ea) - Lobby Finishes
SERVICE ELEVATORS (4 EA - L0-VARIOUS)SERVICE ELEVATORS (4 EA - L0-VARIOUS)SERVICE ELEVATORS (4 EA - L0-VARIOUS)SERVICE ELEVATORS (4 EA - L0-VARIOUS)SERVICE ELEVATORS (4 EA - L0-VARIOUS)
CV Elev. (Service - 4 ea) - Prep. Shafts & MRs
CV Elev. (Service - 4 ea) - Install
CV Elev. (Service - 4 ea) - EMR Eq't Energized (Const'n Power)
CV Elev. (Service - 4 ea) - Lobby Finishes
CVH - SITE UTILITIES & FINISHESCVH - SITE UTILITIES & FINISHESCVH - SITE UTILITIES & FINISHESCVH - SITE UTILITIES & FINISHESCVH - SITE UTILITIES & FINISHES
SITE UTILITIES (SEQUENCE TBD)SITE UTILITIES (SEQUENCE TBD)SITE UTILITIES (SEQUENCE TBD)SITE UTILITIES (SEQUENCE TBD)SITE UTILITIES (SEQUENCE TBD)
SEWERSEWERSEWERSEWERSEWER
CV Site - Sewer Mains & Tie-ins
STORMSTORMSTORMSTORMSTORM
CV Site - Storm Mains & Tie-ins
WATERWATERWATERWATERWATER
CV Site - Water Mains & Tie-ins
GASGASGASGASGAS
CV Site - Fortis Gas Mains & Tie-ins
ELECELECELECELECELEC
CV Site - Elec. Ductbank
CV Site - BC Hydro Pull Feeders & Energize
COMM.COMM.COMM.COMM.COMM.
CV Site - Comm. Ductbank
CV Site - Shaw/Telus Comm. Lines & Energize
SOUTH PARKING & ACCESSSOUTH PARKING & ACCESSSOUTH PARKING & ACCESSSOUTH PARKING & ACCESSSOUTH PARKING & ACCESS
CV Site (South) - Clear Laydown Areas + Rough Grade
CV Site (South) - Shallow Utilities, Paving + Site Finishes
NORTH PARKING & ACCESSNORTH PARKING & ACCESSNORTH PARKING & ACCESSNORTH PARKING & ACCESSNORTH PARKING & ACCESS
CV Site (North) - Clear Laydown Areas + Rough Grade
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 18 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY
. Site Activity Work-Days(Planned)
Start Finish
CV Site (North) - Shallow Utilities, Paving + Site Finishes
CVH - PARKADECVH - PARKADECVH - PARKADECVH - PARKADECVH - PARKADE
CV Parkade - Excav., FRP Pad Fdns
CV Parkade - U/S Util. & FRP SoG
CV Parkade - Precast Erection, Toppings
CV Parkade - Initial Rough-in + Fitout
CV Parkade - Use as Trades / Storage / Lockups
CV Parkade - Demob. Lockups + Final Fitout
CVH - COMPLETIONCVH - COMPLETIONCVH - COMPLETIONCVH - COMPLETIONCVH - COMPLETION
TESTING & COMMISSIONINGTESTING & COMMISSIONINGTESTING & COMMISSIONINGTESTING & COMMISSIONINGTESTING & COMMISSIONING
CV CV - Hydronic Systems Test & Balance
CV CV - Air Systems Test & Balance
CV CV - Arch. Inspections & Deficiencies
CV CV - Power, Ltg & LV Systems Test & Commission
CV CV - Fire Alarm Test & Verify
CV CV - FFE/Eq't Demonstration & Training
CV CV - Elevators Test & Commission
OCCUPANCY & SERVICE COMMENCEMENTOCCUPANCY & SERVICE COMMENCEMENTOCCUPANCY & SERVICE COMMENCEMENTOCCUPANCY & SERVICE COMMENCEMENTOCCUPANCY & SERVICE COMMENCEMENT
CV CV - Integrated Life Safety Tests + Operational Scenarios
CV CV - Consultant Letters of Assurance & Final City Signoffs
CV CV - Occupancy + Subst. Completion
CV CV - Post Substantial Deficiencies
CV CV - Final IC Certification
CV CV - Anticipated (Full) Service Commencement
-4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2014 2015 2016 2017
Project - NIHP-FC-01 CVH PROJECT SCHEDULE (printed - 29-May-14) p. 19 of 19
5104425.01 Appendix 2E Initial Project Schedule (North Island Hospitals Project) EXECUTION COPY