Upload
vuongkhue
View
213
Download
0
Embed Size (px)
Citation preview
BIOWINTM
MODELING OF THE STARTUP OF AN ANAEROBIC DIGESTER
USED IN WASTEWATER TREATMENT PLANTS
A Thesis
Submitted to the Faculty of Graduate Studies and Research
In Partial Fulfillment of the Requirements
For the Degree of
Master of Applied Science
in
Environment Systems Engineering
University of Regina
By
Wenwen Yang
Regina, Saskatchewan
March, 2014
Copyright 2014: Wenwen Yang
UNIVERSITY OF REGINA
FACULTY OF GRADUATE STUDIES AND RESEARCH
SUPERVISORY AND EXAMINING COMMITTEE
Miss Wenwen Yang, candidate for the degree of Master of Applied Science in Environmental Systems Engineering, has presented a thesis titled, BIOWINTM Modeling of the Startup of an Anaerobic Digester Used in Wastewater Treatment Plants, in an oral examination held on March 14, 2014. The following committee members have found the thesis acceptable in form and content, and that the candidate demonstrated satisfactory knowledge of the subject material. External Examiner: Mr. Sean Bayer, KGS Group Consulting Engineering
Co-Supervisor: Dr. Stephanie Young, Environmental Systems Engineering
Co-Supervisor: Dr. Christine Chan, Software Systems Engineering
Committee Member: *Dr. Guo H. Huang, Environmental Systems Engineering
Committee Member: Dr. Liming Dai, Industrial Systems Engineering
Committee Member: Dr. Ezeddin Shirif, Petroleum Systems Engineering
Chair of Defense: Dr. Martin Hewson, Department of Political Science *Not present at defense
i
ABSTRACT
Anaerobic digestion involves biochemical and physiochemical processes. It is an
effective process for sludge stabilization and methane gas production. However, the
digester capacity decreases with time due to the buildup of solid deposits at the bottom of
the digester. Therefore, routine shutdown and cleanup are commonly practiced at
Wastewater Treatment Plants (WWTPs). Currently, WWTP operators face the challenge
of starting up an anaerobic digester in a timely, cost-effective manner with effective
methane gas production. This challenge can be addressed by computer modeling and
simulations of different operating conditions, which is a cost-effective solution in
comparison to experimentation. In this research, the commercially available BioWinTM
software was used to build an Anaerobic Digestion Model (BioWinTM
model) for the
simulation of the startup of an anaerobic digester. BioWinTM
dynamic simulations were
conducted under different operating conditions to determine optimal seed sludge volume,
sludge feed rate, and bicarbonate concentration to be used during the digester startup.
Strategies for a timely and cost-effective startup using the minimum amount of available
seed sludge and primary sludge feed were developed, based on the results of dynamic
simulations conducted using field data gathered from the Regina WWTP. The result of
this research was to decrease digester startup time and operational costs while increasing
methane gas production. This will provide significant economic and environmental
benefits, especially for WWTPs currently facing digester startup challenges, limited
sludge treatment capacities, and low methane gas production.
ii
ACKNOWLEDGEMENTS
I wish to express my appreciation toward my supervisor, Dr. Stephanie Young,
for her continuous support, encouragement, and guidance throughout the course of this
research and my studies at the University of Regina. Her vision and ambition contributed
to my motivation during this research project. Dr. Young made herself available to assist
me at all times and was always willing to share her knowledge and guidance with me. My
appreciation is also extended toward my co-supervisor, Dr. Christine Chan, who provided
me with valuable direction and the opportunity to explore my own inquires and to freely
develop this research.
I wish to express my deep appreciation and sincere thanks toward Alex Munoz
(Senior Process Engineer with Stantec Consulting Ltd.) for his continuous support,
valuable suggestions, endless and patient guidance, and assistance in overcoming the
technical problems encountered during this research. I would like to give special thanks
to Matthew Palmarin for his time, encouragement, and assistance.
I would also like to acknowledge the City of Regina Wastewater Treatment Plant
for providing the field data, and the Faculty of Engineering and Applied Science, and the
Faculty of Graduate Studies and Research for their financial support, which contributed
to the success of this research.
Finally, I wish to express a heartfelt thank you to my family for their everlasting
love and their unrelenting support for my graduate education.
iii
TABLE OF CONTENTS
ABSTRACT ......................................................................................................................... i
ACKNOWLEDGEMENTS ................................................................................................ ii
TABLE OF CONTENTS ................................................................................................... iii
LIST OF TABLES ............................................................................................................. vi
LIST OF FIGURES ......................................................................................................... viii
LIST OF ABBREVIATION .............................................................................................. xi
LIST OF APPENDICES .................................................................................................. xiii
1.0 INTROUDCTION ........................................................................................................ 1
1.1 Problem Statement .................................................................................................... 2
1.2 Objectives of the Research ........................................................................................ 6
1.3 Significance of the Research ..................................................................................... 7
2.0 LITERATURE REVIEW ............................................................................................. 8
2.1 Sludge Digestion ....................................................................................................... 8
2.1.1 Sludge ................................................................................................................ 9
2.1.2 Anaerobic Digestion ........................................................................................ 10
2.2 Anaerobic Digestion Startup ................................................................................... 17
2.3 Anaerobic Digestion Model Development ............................................................. 17
2.3.1 Anaerobic Digestion Model No.1 - IWA ......................................................... 18
2.3.2 BioWinTM
Model .............................................................................................. 20
2.4 Background of the Regina WWTP ......................................................................... 23
2.4.1 WWTP Processes ............................................................................................. 24
3.0 METHODOLOGY ..................................................................................................... 27
iv
3.1 Configuration of BioWinTM
Model ......................................................................... 28
3.2. Parameters for Calibration and Validation ............................................................ 29
3.2.1 Wastewater Characteristics – Data from the Regina WWTP .......................... 30
3.2.2 Wastewater Fractions - BioWinTM
................................................................... 32
3.2.3 Kinetic and Stoichiometric Parameters - BioWinTM
........................................ 34
3.3 Steady-state Calibration .......................................................................................... 34
3.4 Steady-state Validation ........................................................................................... 39
3.5 Dynamic Calibration ............................................................................................... 41
3.6 Dynamic Validation ................................................................................................ 45
4.0 RESULTS AND DISCUSSION ................................................................................. 48
4.1 Dynamic Simulation for the Startup of an Anaerobic Digester .............................. 48
4.1.1 Model Configuration ........................................................................................ 51
4.1.2 Dynamic Simulation ........................................................................................ 51
4.2 Optimization of Startup........................................................................................... 55
4.2.1 Optimization of Sludge Feed Rate ................................................................... 55
4.2.2 Optimization of Seed Sludge ........................................................................... 65
4.2.3 Optimization of Bicarbonate Concentration .................................................... 75
4.3 Development of Strategies for Optimal Digester Startup ....................................... 75
5.0 CONCLUSIONS......................................................................................................... 77
6.0 RECOMMENDATIONS ............................................................................................ 81
REFERENCES ................................................................................................................. 82
APPENDIX A ................................................................................................................... 88
APPENDIX B ................................................................................................................... 92
v
APPENDIX C ................................................................................................................... 96
APPENDIX D ................................................................................................................. 100
APPENDIX E ............................................................................................................... ..117
vi
LIST OF TABLES
Table 2.1 Summary and brief description of ADM1 ........................................................ 20
Table 2.2 Summary and brief description of anaerobic digestion in BioWin ................. 23
Table 3.1 Dimensions of each configuration.....................................................................29
Table 3.2 Measured and adjusted primary influent characteristics (the Regina WWTP,
2007)..................................................................................................................31
Table 3.3 Characteristics of Scum 1 and Scum 2 to the digesters .................................... 32
Table 3.4 Raw influent (sewage) wastewater fractions (EnviroSim Associates Ltd.) ...... 33
Table 3.5 Model kinetic parameters - Methanogens (EnviroSim Associates Ltd.) .......... 34
Table 3.6 Calibration - digesters effluent ......................................................................... 37
Table 3.7 Calibration - digesters operation and performance ........................................... 38
Table 3.8 Calibration - steady-state simulation results vs. plant measured results ........... 39
Table 3.9 Validation – digestes effluent ........................................................................... 39
Table 3.10 Validation - digesters operation and performance .......................................... 40
Table 3.11 Validation - steady-state simulation results vs. plant measured results .......... 41
Table 4.1 Situation of each model dynamic simulation for optimization of startup..........57
Table A-1: Raw influent variable for calibration - July, 2007...........................................88
Table A-2: Scums 1 & 2 variable for calibration - July, 2007 ......................................... .89
Table A-3: Sedimentation, splitter, gravity thickener and BFP variable for calibration -
July, 2007 ...................................................................................................... 91
Table B-1: Raw influent variable for validation - August, 2007.......................................92
Table B-2: Scums 1 & 2 variable for validation - August, 2007.......................................93
vii
Table B-3: Sedimentation, splitter, gravity thickener and BFP variable for validation -
August, 2007 .................................................................................................. .95
Table C-1: Raw influent constant..................................................................................... 96
Table C-2: Lagoon Dimension.......................................................................................... 96
Table C-3: Other units constant ........................................................................................ 96
Table C-4: Tertiary effluent .............................................................................................. 97
Table C- 5: Primary effluent to lagoons ........................................................................... 98
Table D- 1: Bicarbonate and seed constant for base case - April to September.............100
Table D-2: Raw influent variable for base case and Run #1 to Run #6 - April to
September, 2012 ......................................................................................... ..102
Table D-3: Sedimentation, splitter13, splitter14, gravity thickener, and BFP dewatering
variable for base case and Run #1 to #6 - April to September, 2012 ........... 108
Table D-4: Scum 2 variable for base case - April to September, 2012 .......................... 111
Table D-5: Bicarbonate variable for base case - April to September, 2012 ................... 112
Table D-6: Seed sludge 40 m3 for base case and Run #3 and #6 - April to September,
2012............................................................................................................... 114
Table E-1: F/M proportion sludge feed rate for Run #1, #2 and #3 - April to September,
2012............................................................................................................. 117
Table E-2: Flow proportion sludge feed rate for Run #4, #5 and #6 - April to September,
2012............................................................................................................... 119
Table E-3: Seed sludge for 80 m3 Run #2 and #5 - April to September, 2012 ............... 120
Table E-4: Seed sludge 120 m3 for Run #1 and #4 - April to September, 2012 ............. 122
Table E-5: Bicarbonate addition for Run #3 and #6 - April to September, 2012 ........... 124
viii
LIST OF FIGURES
Figure 2.1 Anaerobic digestion processes ...................................................................... ..13
Figure 2.2 Regina WWTP process flow diagram (courtesy of the City of Regina) ......... 25
Figure 3.1 Configuration of BioWinTM
model for calibration and validation...................28
Figure 3.2 Calibration - Digester 1 gas flow rate .............................................................. 43
Figure 3.3 Calibration - Digester 2 gas flow rate .............................................................. 43
Figure 3.4 Calibration - Digester 1 pH ............................................................................. 44
Figure 3.5 Calibration - Digester 2 pH ............................................................................. 44
Figure 3.6 Calibration - Digester 1 alkalinity ................................................................... 44
Figure 3.7 Calibration - Digester 2 alkalinity ................................................................... 44
Figure 3.8 Calibration - Digester 1 VFA .......................................................................... 45
Figure 3.9 Calibration - Digester 2 VFA .......................................................................... 45
Figure 3.10 Validation - Digester 1 gas flow rate ............................................................. 46
Figure 3.11 Validation - Digester 2 gas flow rate ............................................................. 46
Figure 3.12 Validation - Digester 1 alkalinity .................................................................. 46
Figure 3.13 Validation - Digester 2 alkalinity .................................................................. 47
Figure 3.14 Validation - Digester 1 VFA ......................................................................... 47
Figure 3.15 Validation - Digester 2 VFA ......................................................................... 47
Figure 3.16 Validation - Digester 1 pH ............................................................................ 47
Figure 3.17 Validation - Digester 2 pH ............................................................................ 48
Figure 4.1 Configuration of the BioWinTM
model for anaerobic digestion startup .......... 51
Figure 4. 2 Actual startup simulation - Digester 2 VFA ................................................... 52
Figure 4.3 Actual startup simulation - Digester 2 pH ....................................................... 52
ix
Figure 4.4 Actual startup simulation - Digester 2 gas flow rate ....................................... 52
Figure 4.5 Actual startup simulation - Digester 2 alkalinity ............................................. 53
Figure 4.6 Actual startup simulation - Digester 2 TSS......................................................53
Figure 4.7 Actual startup simulation - Digester 2 methane content ................................. 53
Figure 4.8 Sludge feed rate calculated on F/M proportion ............................................... 56
Figure 4.9 Sludge feed rate calculated on percent of digester volume proportion ........... 57
Figure 4.10 Run #1 simulation results of VFA ................................................................. 58
Figure 4.11 Run #1 simulation results of gas flow rate .................................................... 59
Figure 4.12 Run #1 simulation results of alkalinity .......................................................... 60
Figure 4.13 Run #1 simulation results of TSS .................................................................. 60
Figure 4.14 Run #4 simulation results of VFA ................................................................. 61
Figure 4.15 Run #4 simulation results of gas flow rate .................................................... 62
Figure 4.16 Run #4 simulation results of alkalinity .......................................................... 63
Figure 4.17 Run #4 simulation results of TSS .................................................................. 63
Figure 4.18 Run #2 simulation results of VFA ................................................................. 66
Figure 4.19 Run #2 simulation results of gas flow rate .................................................... 67
Figure 4.20 Run #2 simulation results of alkalinity .......................................................... 67
Figure 4.21 Run #2 simulation results of TSS .................................................................. 67
Figure 4.22 Run #3 simulation results of VFA ................................................................. 68
Figure 4.23 Run #3 simulation results of gas flow rate .................................................... 68
Figure 4.24 Run #3 simulation results of alkalinity .......................................................... 69
Figure 4.25 Run #3 simulation results of TSS .................................................................. 70
Figure 4.26 Run #3 simulation results of pH .................................................................... 70
x
Figure 4.27 Run #5 simulation results of VFA ................................................................. 70
Figure 4.28 Run #5 simulation results of gas flow rate .................................................... 71
Figure 4.29 Run #5 simulation results of alkalinity .......................................................... 72
Figure 4.30 Run #5 simulation results of TSS .................................................................. 72
Figure 4.31 Run #6 simulation results of VFA ................................................................. 73
Figure 4.32 Run #6 simulation results of gas flow rate .................................................... 73
Figure 4.33 Run #6 simulation results of alkalinity .......................................................... 73
Figure 4.34 Run #6 simulation results of TSS .................................................................. 74
Figure 4.35 Run #6 simulation results of pH .................................................................... 74
Figure C-1: Configuration of the Regina WWTP model...................................................96
xi
LIST OF ABBREVIATION
ADM Anaerobic Digestion Model
ADM1 IWA Anaerobic Digestion Model No. 1
ALK Alkalinity
ASM Activate sludge model
ASDM Activate sludge/anaerobic digestion model
BOD Biochemical oxygen demand
BOD5 Five-day biochemical oxygen demand
BFP Belt filter press
COD Chemical oxygen demand
DO Dissolved oxygen
HRT Hydraulic retention time
IFAS Integrated fixed film activated sludge
IWA International Water Association
LCFA Long chain fatty acid
MBBR Moving bed biofilm reactor
OUR Oxygen uptake rate
PS Primary sludge
PTP Primary treatment plant
SBR Sequencing batch reactor
SRT Solids retention time
TKN Total Kjeldahl Nitrogen
TS Total solids
TSS Total suspended solids
xii
VFA Volatile fatty acid
VSD Volatile solid destruction
VSS Volatile suspended solids
WAS Waste activated sludge
WWTP Wastewater treatment plant
xiii
LIST OF APPENDICES
Appendix A - Field Data from the Regina WWTP for Calibration
Appendix B - Field Data from the Regina WWTP for Validation
Appendix C - Steady-state simulation for the Regina WWTP
Appendix D - Field Data from the Regina WWTP and Model Data from
Calibration/Validation for Startup Simulation
Appendix E - Optimal Sludge Feed Rate, Seed and Bicarbonate Addition for Model Run
#1 to #6
1
1.0 INTROUDCTION
Anaerobic digestion is widely used for sludge stabilization for health and
aesthetic reasons in medium and large wastewater treatment plants (WWTPs). The
purposes of anaerobic digestion of sludge are to reduce pathogens, eliminate offensive
odors, and inhibit, reduce, or eliminate the potential for putrefaction. It is also used for
sludge volume reduction, production of usable methane gas for energy production, and
for improving sludge dewaterability.
The anaerobic digestion of sludge includes three biochemical and
physicochemical processes (Batstone et al., 2002): hydrolysis, acidogenesis
(fermentation), and methanogenesis. Therefore, strong skills are needed to startup and
operate an anaerobic digester. The skills can be gained from past experiences,
experiments, and computer simulations. In general, experimentation on anaerobic
digestion processes is expensive and time consuming. Alternatively, computer software
simulation is more cost-effective for optimizing the startup of the anaerobic digester
process and for predicting and then reducing operational problems, improving digestion
performance, and increasing biogas production (Dursun et al., 2011).
In this study, an Anaerobic Digestion Model was implemented into BioWinTM
software and is called the BioWinTM
model in this study. This is currently the most
widely used software in North America to optimize the startup and operation of anaerobic
digestion of sludge.
This chapter provides an introduction to the thesis. It includes a problem
statement on the startup and operation of anaerobic digesters in the Regina WWTP, and
the objectives and significance of the research.
2
1.1 Problem Statement
A large amount of concentrated sludge is produced in the Regina WWTP. The
sludge contains various organic and inorganic contaminants and pathogens. Two-stage
anaerobic digestion is currently used in the Regina WWTP to treat the primary sludge
removed from the upstream primary sedimentation process. Two high-rate anaerobic
digesters (No.1 and No.2) are coupled in a series with a third anaerobic digester (No. 3).
The first two tanks, operated in parallel, are used for sludge digestion and methane gas
production. They are heated and equipped with mixing facilities. The third digester is
unheated and used as a sludge thickener and for storage. It allows the sludge to be
separated from the supernatant and to be thickened before being pumped to the
dewatering facilities (City of Regina, 1994).
After several years of operation, the digester capacity decreases and digestion
performance becomes poor. Ideally, organic solids can be converted to digested sludge
and biogas at a constant rate in a complete-mixed digester. However, after several years
of operation, the digester shifts away from the complete mixing condition, because solid
contaminants deposit onto the wall and at the bottom of the digester, which reduces the
digester treatment capacity and further reduces mixing space and mixing efficiency.
There are several potential negative impacts of reduced mixing efficiency on the
anaerobic digestion process: (1) reduced sludge stability, (2) reduced biogas production,
(3) increased process instability due to overloading, (4) reduced pathogen kill, and (5)
inaccuracies in process data (Muller et al., 2011). Therefore, periodic shutdown and
cleaning of anaerobic digesters are needed.
3
After cleaning, an anaerobic digester should be put back into service as soon as
possible to reduce the chance of overloading the other digesters, and to produce methane
gas quickly to offset the natural gas cost ($1,000/day ) for power production during the
shutdown period. However, the operators of the Regina WWTP currently face a major
challenge of how to put back the digesters into service quickly and cost effectively. The
plant operators face the following challenges on startup: (1) it takes a long time (more
than 90 days) to start up the digester, and (2) the sludge in the digester becomes very
acidic (pH<4) during the startup period. The long startup time increases the chance that
the other digesters will become overloaded resulting in a bypass of untreated sludge to
the lagoon. Furthermore, operational costs are increased as natural gas is needed as a
substitute for methane gas during the shutdown period. A low pH of 4 might cause the
startup to fail, while also reducing methane gas production. As such further costs for
natural gas may be incurred.
The long startup time and low pH are attributed to the lack of seed sludge during
the initial startup period, which makes the startup process very complicated. A particular
problem is the initial sludge feed rate versus seed sludge concentration, which directly
determines the time required for a successful digester startup. The long startup time is
also attributed to the lack of proper guidance on criteria used for a cost-effective startup
of the anaerobic digester. To the author’s knowledge, no guiding principles are published
or made publically available. Most startup procedures for anaerobic digesters are based
on the skills and experience of the operators, and conservative rules of thumb. This
makes the startup time longer than necessary, thereby increasing the cost of the overall
sludge treatment process.
4
Therefore, there is a need to develop a computational tool to guide operators
through the startup process of anaerobic digesters quickly and economically, especially
when a lack of seed sludge is present at the initial startup period. Theoretically, the best
way to startup an anaerobic digester is to transfer seed sludge from another functioning
primary digester from the same plant. However, in the Regina WWTP, all digesters
encounter operating problems, and often no healthy sludge is available onsite for sludge
seeding. Therefore, seed sludge is often hauled to the Regina WWTP from the WWTP in
Saskatoon.
Hauling seed sludge from the WWTP in Saskatoon to the Regina WWTP is very
expensive. The capacity of the primary digester in Regina is 3,800 m3. Therefore, it is too
large to introduce a full amount of seed sludge for the startup of an anaerobic digester.
According to the information provided by the Regina WWTP, hauling 40 m3 of seed
sludge (about 1% of the digester’s capacity) from Saskatoon to Regina costs about
$4,000. A volume of 2,000 m3
of seed sludge is ideal to startup a digester quickly and
successfully. This amount would cost $200,000 to haul from Saskatoon to Regina and is
therefore not economically feasible. Therefore, the Regina WWTP elects to startup the
anaerobic digester by introducing a small amount of seed sludge (40 m3) rather than
2,000 m3 of seed sludge, which saves about $196,000. However, the startup process
becomes very long (more than 90 days) and operators encounter many operating
problems. One of the operating problems is a low pH, which makes the anaerobic
digester acidic. If the primary sludge feed rate is beyond the seed sludge acceptability, the
hydrolysis and fermentation processes produce too much acids which lower the pH of the
sludge in the anaerobic digester. The decrease of the pH is attributed to a low
5
concentration of methanogens, and the low pH conditions further inhibit methanogen
growth. Therefore, non-methanogens or acidogens (acid formers) became predominate,
which favors hydrolysis and acidogenesis (fermentation) reactions. This leads to the
excessive production of fatty acids, amino acids, and acetate. The low pH has a negative
impact on the anaerobic digestion process because it inhibits methanogen growth and
reduces the amount of methane gas production. When the pH is below 6.2, methanogenic
bacteria will no longer function (Filbert, 2012). This may cause the startup of the
anaerobic digester to fail. Therefore, pH is the most important factor affecting startup.
Adding bicarbonate increases pH and may be used to improve sludge digestion
performance.
The second problem is the uncertainty about the correlation between the primary
sludge feed rate versus seed sludge concentration during the startup period. The operator
feeds the raw sludge based on rules of thumb and past experience. Primary sludge feed
rate is another crucial factor in determining the success of the startup, because it directly
determines the startup time.
The third problem is the uncertainty about the optimal balance among the primary
sludge feed rate, the amount of seed sludge, and the bicarbonate concentration in order to
achieve a short and successful startup time of the anaerobic digester.
The fourth problem is that the Regina WWTP faces a challenge in effective
biogas production. One of the main purposes of anaerobic sludge digestion is to produce
methane to offset the energy costs. Methane can be used as a power source for: (1)
heating, mixing, and drying sludge, (2) heating the building, (3) incineration, and (4)
engine fuel. In the Regina WWTP, methane can be used as a digester heating source
6
which saves $1,000 per day in natural gas costs. However, the digesters in the Regina
WWTP were unable to treat 200 m3 of raw sludge per day before the digesters were
cleaned in 2012/2013, because the hydrolysis and fermentation steps produced excessive
acids which lowered the pH from 6.8 to 4. The acidic pH reduced the population of
methane formers and reduced methane production. Moreover, the acidic pH caused
corrosion on the concrete wall of the digesters, leading to tank leakage.
The fifth problem is the lack of a customized computer model of the Regina
WWTP to guide the operators during startup, to predict anaerobic digestion performance,
and to optimize the anaerobic digestion process.
In conclusion, the startup of an anaerobic digester is a very complicated process
because of the specific biochemical and physicochemical reactions involved (Batstone et
al. 2002). WWTPs face challenges when starting up and operating an anaerobic digester
cost-effectively. Therefore, there is a need to reduce the startup time when a minimum
amount of seed sludge is available. Therefore, the anaerobic digestion model built into
the BioWin software simulator was chosen for the development of anaerobic digester
startup strategies, the prediction of biogas production capacity, and the optimization of
anaerobic digester operation.
1.2 Objectives of the Research
The objectives of this study are to implement an Anaerobic Digestion Model into
the commercially available simulator software BioWinTM
, developed by EnviroSim
Associates Ltd. of Hamilton, Ontario, Canada. The BioWinTM
model will be used to
develop strategies that address the challenges mentioned above. As such, it will focus on
(1) decreasing startup time and increasing methane gas production by optimizing the
7
digester startup using optimal seed sludge amounts, and (2) optimizing primary sludge
feed rate and bicarbonate concentration so that the anaerobic digesters at the Regina
WWTP can be started up timely and cost-effectively. The BioWinTM
model will also be
used to optimize anaerobic digestion performance and to maximize its economic benefits
by increasing methane production, controlling acid formation and stabilizing the pH of
the sludge, etc.
This study is divided into four stages: (1) collection and compilation of field data
from the Regina WWTP, (2) model calibration, validation, and simulation, (3)
determination of the optimal operating parameters for the Regina WWTP to startup and
operate the anaerobic digesters cost-effectively, and (4) development of general startup
strategies that can be applied to other WWTPs. The parameters to be optimized include:
amount of microorganism seed sludge, primary sludge feed rate, the ratio of primary
sludge feed rate versus microorganism seed sludge concentration, pH, alkalinity, etc. The
BioWinTM
model used in this study can be further implemented to anaerobic digestion
processes in other WWTPs.
1.3 Significance of the Research
The significance of this thesis research is to develop strategies and provide criteria
for the cost-effective startup and operation of an anaerobic digester by decreasing the
startup time and therefore improving early methane gas production. This will reduce the
operating costs of anaerobic sludge digestion and plant energy costs. In addition, it will
increase the overall efficiency of anaerobic digestion system in terms of maximizing the
decomposition of contaminants, minimizing pathogen contamination, and improving odor
control and sludge dewaterability. Moreover, it will provide significant economic and
8
environmental benefits around the world, especially for old WWTPs currently facing
sludge digestion problems, limited sludge treatment capacities, and low methane gas
production, etc.
2.0 LITERATURE REVIEW
2.1 Sludge Digestion
Sludge digestion is a biological process in which organic solids are decomposed
into stable substances through the activities of either anaerobic or aerobic organisms.
Digestion reduces the total mass of solids, destroys pathogens, and makes it easier to
dewater and dry the sludge. Sludge digestion can be applied in two ways: anaerobic
digestion and aerobic digestion.
Aerobic digestion is the process of oxidizing and decomposing the organic part of
the sludge by microorganisms in the presence of oxygen. The end products of aerobic
digestion are primarily carbon dioxide and water which are the stable oxidized forms of
carbon and hydrogen. If the biodegradable starting material contains nitrogen,
phosphorus and sulfur, then the end products may also include their oxidized forms -
nitrate, phosphate and sulfate. In aerobic wastewater treatment systems, microorganisms
feed on organic materials and reduce the suspended solids in the wastewater. Therefore,
aerobic digestion is capable of reducing mass and volume, and reducing pathogenic
organisms. It also has some key advantages for smaller plants when compared to
anaerobic digestion, such as low capital cost and simple operational control.
Anaerobic digestion is based on the biological conversion of degradable
compounds in the absence of oxygen. The end products of this process may include
methane and carbon dioxide. Anaerobic digestion has been widely used for sludge
9
digestion and it is a promising method for solving some energy and ecological problems.
This digestion process is the one that represents the subject of this paper. The process is
used in wastewater treatment plants with the purpose of organic substance and pathogen
reduction. The advantage of using anaerobic digestion as a stabilization method for
sludge is that it generates biogas, biogas that can be used in a cogeneration unit to obtain
the thermal energy needed for the anaerobic digestion in addition to supplying a part of
the electrical energy consumed in the wastewater treatment processes. The only drawback
is hydrogen sulfide, a gas that in contact with oxygen develops sulfuric acid, a strong
mineral acid, which can damage the engines (Manea, 2012). Another strategy used in
developed countries is to obtain products from wastewater treatment sludge that can be
sold, for example recovering valuable components of sludge, such as metals and chemical
compounds.
2.1.1 Sludge
During the treatment processes, solids are removed from wastewater. The sludge
from wastewater treatment plants is derived from primary, secondary and/or tertiary
treatment processes. Most often, the produced sludge has a small concentration and a
high biodegradable load. Digested sludge is inoffensive, having the appearance and
characteristics of a rich potting soil.
Primary sludge is produced following primary treatment, which usually entails the
sedimentation. Suspended solids which are removed from liquids by gravitation settling
in sedimentation tanks form sludge. This primary sludge needs to pass through additional
treatments such as anaerobic digestion in order to reduce its water content, stabilize its
organic matter, reduce its odors, reduce its pathogen load, and reduce its volume and
10
global mass (Manea et al., 2012). Primary sludge treatment in anaerobic digesters is the
topic of this thesis. Secondary sludge is generated from the biological treatment stage.
This stage usually has the purpose of decomposing organic matter through biological
processes. The most often used is the activated sludge process, where the wastewater is
aerated in an aeration basin in which microorganisms metabolize the suspended and
soluble organic matter. At the end of the process, the treated water has to go through a
clarifier in order to be separated from the activated sludge. A part of the sludge separated
in this secondary clarifier returns to the biological treatment stage. The rest of the sludge,
not necessary for the optimum development of the biological processes, is surplus
activated sludge. In the sludge treatment stage of the wastewater treatment plant, the
primary and secondary sludge described above are usually mixed together generating a
type of sludge referred to as a mixed sludge. This sludge has to pass through additional
treatments in order to reduce its water content, stabilize its organic matter, reduce its
odors, reduce its pathogen load, and reduce its volume and global mass.
2.1.2 Anaerobic Digestion
A Frenchman, Mouras, applied anaerobic digestion for the first time to treat
wastewater in his invention of a crude version of a septic tank in 1881, named by him as
the “automatic scavenger” (McCarty et al., 1982 ). Subsequently an Englishman,
Cameron, constructed a tank in 1895 which was similar to Mouras’s “automatic
scavenger” but with better treatment efficiency, and termed it the “septic tank.” Because
of the successful results achieved in using these tanks, the local government of Exeter in
1897 approved the treatment of the entire city’s wastewater by these septic tanks.
Moreover, the value of the methane gas which was generated during sludge
11
decomposition in the septic tanks was recognized by Cameron, and some of the gas was
used for heating and lighting purposes at the disposal worksites (Chawla, 1986 ). During
most of the following century, the development of anaerobic digestion technology
remained exclusively linked to the stabilization of putrescible solids from domestic
wastewaters. This led to the design of heated, fully mixed, reactors of the type widely
used today for the digestion of sewage sludge and animal manures. Application of
anaerobic digestion systems to industrial wastewater depollution was stimulated by the
rise in fossil fuel prices in the early 1970s and by the increasingly stringent pollution
control regulations. The unsuitability of the conventional mixed digester for the treatment
of industrial wastewaters of low-strength and of largely soluble organic material, led to
the concept of biological solids recycling and to the retention of active biomass within the
digester (Abbasi et al., 2012). Anaerobic digestion is now considered a consolidated
technology with more than 2200 high-rate reactors implemented worldwide (Van Lier,
2008). In Europe, between 1995 and 2010, the number of plants installed increased from
15 to 200, which implies an installation capacity rise to nearly 6,000,000 tons per year
(from 200,000 tons per year) (de Baere et al., 2010). Moreover, the number of anaerobic
digester is expected to increase due to both climate change awareness and the significant
boost in the use of renewable energy.
2.1.2.1 Anaerobic Digestion Processes
Anaerobic digestion is a significant process in wastewater treatment processes. It
includes a sequence of biochemical processes under anaerobic conditions for organic
matter degradation by various microorganisms. The byproduct of anaerobic digestion -
methane (CH4) - is a rich source of clean energy, which contributes to environmental
12
conservation and sustainability as oppose to fossil fuels (Chen, 2010). Therefore,
anaerobic digestion is widely used as an attractive means for wastewater treatment
around the world while more and more new process configurations are continuously
being developed.
Anaerobic systems are quite complicated, entailing many chains of interconnected
biological reactions. There are multistep reactions involved in anaerobic digestion for
degrading complex biodegradable materials. Generally three types of chemical and
biochemical reactions are involved in anaerobic digestion: hydrolysis, fermentation, also
called acidogenesis (the formation of soluble organic compounds and short-chain organic
acids), and methanogenesis (the conversion of organic acids and hydrogen into methane
and carbon dioxide) (Tchobanoglous et al., 2003).
The coordinated steps or chemical reactions start with hydrolysis, in which
complex organic materials are hydrolyzed and reduced to small soluble organic
substrates. Fermentation reactions are then carried out to convert amino acids, simple
sugars, and long chain fatty acids into short-chain fatty acids, including acetic acid. Co-
generative products included formic acid, acetic acid, propionic acid and ethanol (Oh et
al., 2003).
Acetic acid, propionic acid, and H2 are end products of the anaerobic oxidation of
long chain fatty acids (Shin et al. 2003). Another pathway for acetic acid generation is
acetogenesis from short-chain fatty acids (McCarty &Mosey, 1991). Short-chain
fatty acids such as formic acid, propionic acid, lactic acid, butyric acid, and pyruvic
acid are resources for acetic acid formation. While carbon dioxide and hydrogen are
generated as initial biogas components, methane becomes the dominant gas later due
13
to methanogensis. This process includes acetotrophic methanogensis, which converts
acetate to methane and hydrogenotrophic methanogensis, which converts carbon dioxide
and hydrogen gas to methane. Details of the anaerobic digestion processes (Chen, 2010)
are presented in follow:
Complex Biodegradable Particulates
Figure 2.1 Anaerobic digestion processes
2.1.2.2 Anaerobic Digestion Microbiology
Anaerobic digestion is a complex process that is performed by a variety of
microorganisms. Both Archaea and Bacteria are involved in anaerobic digestion. The
Hydrolysis
Fermentation
Volatile acids Acetic acids
(short chain)
Hydrogen Hydrogen
Methanogenesis
Methane & Carbon dioxide
Proteins Amino acids
Carbohydrates Simple carbohydrates (sugars)
Fats Long chain fatty acids
14
three major groups of anaerobic microorganisms in a digester population include: (1)
hydrolytic fermentative bacteria, (2) syntrophic acetogenic bacteria, and (3) Archaea
(methanogens). The consortia of microorganism involved in the overall conversion of
complex organic matter to methane begins with bacteria that hydrolyze complex organic
matter – such as carbohydrates, proteins, and fats – into simple carbohydrates, amino
acids, and fatty acids. The simple carbohydrates and acids are then utilized to obtain
energy for growth by fermenting bacteria, producing organic acids and hydrogen as the
dominant intermediate products. The organic acids are then partially oxidized by other
fermenting bacteria which produce additional hydrogen and acetic acid. Hydrogen and
acetic acid are the main substrates used by Archaea methanogens, which convert them
into methane (Rittmann & McCarty, 2001). The chemical equations are shown as
follows:
4H2 + CO2 → CH4 + 2H2O
4HCOO- + 4H
+ → CH4 + 3CO2 + 2H2O
4CO + 2H2O → CH4 + 3CO2
4CH3OH → 3CH4 + CO2 + 2H2O
4(CH3)3N + H2O → 9CH4 + 3CO2 + 6H2O + 4NH3
CH3COOH → CH4 + CO2
2.1.2.3 Effects Parameters on Anaerobic Digestion
The successful startup and operation of an anaerobic system requires a proper
balance between the hydrolytic and fermentative organisms involved in the first step and
the methanogenic organisms responsible for the second step. This balance is
accomplished through proper seeding, as well as through the control of organic-acid
15
production and pH during startup, when the microbial populations are establishing
themselves. Therefore, environmental factors affect the operational performance of
anaerobic digestion. General characteristics of anaerobic digestion include mixed
suspended solids, complex microorganism communities, long hydraulic and solids
residence time (30-60 days), and mesophilic temperature (35° C) (Tchobanoglous et al.,
2003). Important environmental factors in anaerobic digestion processes include
(Tchobanoglous et al., 2003): (1) solids retention time, (2) hydraulic retention time, (3)
temperature, (4) alkalinity, (5) pH, (6) the presence of inhibitory substances, i.e., toxic
materials, and (7) the bioavailability of nutrients and trace metals. The first three factors
are important in process selection. Alkalinity is a function of feed solids and is important
in controlling the digestion process. The rest of the parameters are discussed below.
Solids Retention Time
Solids retention time (SRT) is the average time the solids are held in the digestion
process, and the hydraulic retention time is the average time the liquid is held in the
digestion process. For soluble substrates, the SRT can be determined by dividing the
mass of solids in the reactor (M) by the mass of solids removed daily (M/d). The
hydraulic retention time is equal to the volume of liquid in the reactor (L3) divided by
the quantity of biosolids removed (L3/d). For a digestion system without recycling, SRT
= . The three reactions (hydrolysis, fermentation, and methanogenesis) are directly
related to SRT (or ). There is a minimum SRT for each reaction. If the SRT is less than
the minimum SRT, bacteria cannot grow rapidly enough and the digestion process will
fail eventually.
Temperature
16
In anaerobic digestion, temperature is important in determining the rate of
digestion, particularly the rates of hydrolysis and methane formation. Most anaerobic
digestion systems are designed to operate in the mesophilic temperature range, between
30 and 38° C (85 and 100°F). While the selection of the design operating temperature is
important, maintaining a stable operating temperature is more important because the
bacteria, especially the methane formers, are sensitive to temperature changes. Generally,
temperature changes greater than 1° C /d affects process performance, and changes of
less than 0.5° C /d are recommended.
Alkalinity
A well-established digester has a total alkalinity of 2000 to 5000 mg/L. The
principal consumer of alkalinity in a digester is carbon dioxide, and not volatile fatty
acids as commonly believed. Carbon dioxide is produced in the fermentation and
methanogenesis phases of the digestion process. Due to the partial pressure of the gas in
the digester, the carbon dioxide solubilizes and forms carbonic acid, which consumes
alkalinity. The carbon dioxide concentration in the digester gas is therefore reflective of
the alkalinity requirements. Supplemental alkalinity can be supplied by the addition of
sodium bicarbonate, lime, or sodium carbonate.
pH
pH is an important factor in maintaining functional anaerobic digestion. A typical
pH is in the range of 6.5-7.6 (Parkin and Owen 1986). The accumulation of intermediate
acids leads to a pH drop during fermentation. In order to maintain a stable operation, it is
necessary to add bicarbonate or carbonate as an alkalinity buffer to neutralize volatile
fatty acids and carbon dioxide (Chen, 2010).
17
2.2 Anaerobic Digestion Startup
During reactor startup, the operator must maintain a sufficiently small loading on
the reactor so that organic acids produced by the much faster growing fermentative
bacteria do not exceed the buffering capacity of the system. If this occurs, the pH will
drop and the methanogenic population may die. According to Rittmann and McCarty
(Rittmann & McCarty, 2001) the crucial steps during startup are: (1) begin with as much
good anaerobic seed as possible, (2) fill the digester with this seed and water, (3) bring
the system up to temperature, (4) add buffering material in the form of a chemical, such
as sodium bicarbonate, to protect against a pH drop, and (5) add a small amount of
organic waste sufficient to let the organic acid content from fermentation reach no more
than 2000 to 4000 mg/l while keeping the pH between 6.8 and 7.6. These organic acids
are a food source required for the methanogenic population to grow.
2.3 Anaerobic Digestion Model Development
Anaerobic digestion modeling is a recognized and widely used tool across all
anaerobic digestion technology and scientific activities. Mathematical modeling of the
anaerobic digestion process was motivated by the need for efficient operation of
anaerobic systems in the early 70’s (Hill & Barth, 1997). The first models were relatively
simple due to the limited knowledge about the process. Experimental investigation,
system analysis, and increased computing power led to the development of much more
detailed models in recent years. It is not the goal of this review to list all available models
for anaerobic digestion, but a brief overview is given in the following paragraphs.
The first modeling approaches focused on describing the rate limiting step of the
process, considering that anaerobic digestion is a multistep process where one slower step
18
controls the global rate (Hill & Barth, 1997). The limiting step can, however, be different
under different operating conditions. Some authors considered methanogenesis as the
limiting step or the conversion of fatty acids into biogas or the hydrolysis of suspended
solids. These series of models were simple and easy to use but were unable to adequately
describe the process performance, especially under transient conditions. A second
generation of models considered the concentration of volatile fatty acids as the key
parameter, incorporating acidogenesis and acetogenesis separately (Hill, 1982). The
hydrogen partial pressure, as a key regulatory parameter influencing the redox potential
in the liquid phase, and bacterial groups, with differentiated acetoclastic and
hydrogenotroph methanogens, were included in several models. The redox potential is a
function of the hydrogen partial pressure and determines the volatile fatty acid (VFA)
production in this family of models.
Recently, computer modeling is able to support the increased application of
anaerobic technology as a sustainable waste treatment option and a viable alternative to
other energy generating processes. These models incorporate additional processes and
species, more detailed kinetics with inhibition, and consideration to different substrates
(Donoso-Bravo et al., 2011).
2.3.1 Anaerobic Digestion Model No.1 - IWA
A recent development in anaerobic digestion modeling is the landmark model
named Anaerobic Digestion Model, No.1 (ADM1) that was developed by the
International Water Association (IWA) Task Group (Boltes et al., 2008). It was
established in 1997 with the goal of developing a generalized anaerobic digestion model
and to reach a common basis for further model development and validation studies with
19
comparable results. This model supplied a fundamental basis for kinetic modeling of
anaerobic digestion with a set of default kinetic parameters. The structured model
includes multiple steps describing biochemical as well as physicochemical processes. The
biochemical steps include disintegration from homogeneous particulates to
carbohydrates, proteins and lipids; extracellular hydrolysis of these particulate substrates
to sugars, amino acids, and long chain fatty acids (LCFA), respectively; acidogenesis
from sugars and amino acids to VFAs and hydrogen; acetogenesis of LCFA and VFAs to
acetate; and separate methanogenesis steps from acetate and hydrogen/CO2 (Batstone et
al., 2002).
Several benefits were expected from the development of this first generic model
of anaerobic digestion (Batstone et al., 2002):
• Increased model application for full-scale plant design, operation, and
optimization
• Further development work on process optimization and control, aimed at direct
implementation in full-scale plants
• Common basis for further model development and validation studies to make
outcomes more comparable and compatible
• Assisting technology transfer from research to industry
ADM1 has become available in Matlab and Simulink, but also in specific water
related simulation software, such as WEST, BioWinTM
and Aquasim (Lauwers et al.,
2013).
A summary and brief description of the studies found in the literature about
modeling in anaerobic digestion systems are shown below:
20
Table 2. 1 Summary and brief description of ADM1
Reference Model Measurements
Batstone, D.J., et al. 2009 ADM1 - IWA Biogas, VSS
Palatsi, J., et al. 2010 ADM1 - IWA Methane, acetic, butyric, Propionic
acid
Flotats, X., et al. 2003 ADM1 - IWA Acetal, propionate, valerate,
methane
Batstone, D.J., et al. 2003 ADM1 - IWA VFA, biogas, pH, methane content
Kalfas, H., et al. 2006 ADM1 - IWA TSS, VSS, COD, VFA, biogas,
gas composition, pH
Koch, K., et al. 2010 ADM1 - IWA Biogas, gas composition, NH4,
NKT, VFA, alkalinity, TS
2.3.2 BioWinTM
Model
BioWinTM
is a wastewater treatment process simulator. It is used for designing,
upgrading, and optimizing wastewater treatment plants. The package was developed with
the primary objective of providing a powerful tool to aid both the process designer and
the operators of these facilities.
According to the BioWinTM
software manual (EnviroSim Associates Ltd.), most types
of wastewater treatment systems can be configured in BioWinTM
using many process
modules:
A range of activated sludge bioreactor modules – suspended growth reactors
(diffused air or surface aeration), various SBRs, media reactors for IFAS and
MBBR systems, variable volume reactors
Anaerobic and aerobic digesters
Various settling tank modules – primary, ideal, and 1-D model settlers
21
Different input elements – wastewater influent (COD- or BOD-based), user-
defined (state variable concentrations), metal addition for chemical
phosphorus precipitation (ferric or alum), methanol for denitrification
Other process modules – holding tanks, equalization tanks, dewatering units,
flow splitters, and combiners
BioWinTM
is a Chemical Oxygen Demand (COD) based simulation. COD is a
measure of wastewater strength, specifically the electron donating capacity of organic
material. In the BioWinTM
software, characterization of the carbonaceous material in
municipal wastewater is in terms of the COD. This selection is based on a number of
factors, but primarily because COD provides a consistent basis for describing of the
activated sludge process, and for quantifying sludge production, oxygen demand, etc.
However, Biochemical Oxygen Demand (BOD) is the test that measures the portion of
organic substrate utilized for energy generation and ignores the portion transformed into
new cell mass. Therefore, the suitability of COD is established by considering the
utilization of organic substrate and can be used as the basis for a mass balance.
The BioWinTM
software suite presently includes two modules (EnviroSim
Associates Ltd.):
1. A steady state module for analyzing systems based on constant influent
loading and/or flow weighted averages of time-varying inputs. This unit is
also very useful for mass balancing over complex plant configurations.
2. An interactive dynamic simulator where the user can operate and
manipulate the treatment system "on the fly". This module is ideal for
22
training and for analyzing system response when subjected to time-
varying inputs or changes in operating strategy.
This complete model approach frees the user from having to map one model’s
output to another model’s input which significantly reduces the complexity of building
full plant models, particularly those incorporating many different process units.
The anaerobic digestion model in BioWin contains the following functional categories
(EnviroSim Associates Ltd.):
(1) Heterotrophic growth through fermentation which achieves VFA generation.
There are two pathways for the fermentation of readily biodegradable substrate to
acetate, propionate, carbon dioxide, and hydrogen. The dominant pathway is governed by
the dissolved hydrogen concentration. These processes are mediated by the ordinary
heterotrophic organisms. This base rate is modified to account for nutrient limitations
(ammonia, phosphate, other cations and anions) and pH inhibition.
(2) Growth and decay of propionic acetogens in order to conduct anaerobic digestion.
These two processes describe the growth and decay of propionic acetogens,
converting propionate to acetate, CO2, and hydrogen. This base rate is modified to
account for environmental conditions (anaerobic conditions, inhibition by hydrogen and
acetate), nutrient limitations (nitrogen, phosphate, other cations and anions), and pH
inhibition. The decay process has a rate that varies according to the electron acceptor
environment.
(3) Growth and decay of methanogens in anaerobic digestion.
These processes describe the growth and decay of two of the principal groups of
obligate anaerobic microorganisms (acetoclastic methanogens), converting acetate or
23
methanol to methane and CO2; and hydrogenotrophic methanogens, converting CO2 or
methanol and hydrogen to methane and water.
This base rate is modified to account for nutrient limitations (ammonia, phosphate,
other cations and anions) and pH inhibition. For both populations, the decay rate varies
according to the electron acceptor environment.
Table 2. 2 Summary and brief description of anaerobic digestion in BioWinTM
Reference Model Substrate Measurements
Dursun, D., et al.,
2011
ASDM - BioWinTM
PS + WAS Biogas
Parker, W.J., et al.
2008
ASM & ADM -
BioWinTM
WAS COD, OUR, TSS, VSS,
methane
Parker, W.J., et al.
2007
ADM - BioWinTM
WAS Biogas
Jones, R., et al. 2008 ASM - BioWinTM
WAS COD, TSS, VSS, OUR,
methane, TKN, NH3
Muller, C., et al. 2011 Integrated Model -
BioWinTM
PS + WAS VSD
Liwarska-Bizukojc,
E., et al. 2010
ASM - BioWinTM
WAS Modified parameters
note: ASDM: activated sludge/anaerobic digestion model; ASM: activated sludge model.
2.4 Background of the Regina WWTP
The Regina WWTP is located west of the City of Regina. On average, it treats 70
to 75 ML/d of wastewater prior to discharging it to the Wascana Creek. The plant is
capable of reducing the environmental impact of four main pollutant types: (1) organic
and inorganic suspended solids measured as total suspended solids (TSS), (2) soluble
24
organic material or Biochemical Oxygen Demand (BOD), (3) pathogenic microorganisms
and bacteria for which fecal coliform is used as an indicator organism, and (4) the macro-
nutrient phosphorus which has been implicated in causing downstream eutrophication.
The plant achieves excellent effluent quality:
• BOD < 16 mg/L
• TSS < 20 mg/L
• Total Phosphorus < 1.0 mg/L
• Fecal Coliforms <100 Coliforms /100 ML (April through October)
However, only about 15 to 20% of the total nitrogen is removed from the
wastewater. This is done through biological treatment, where nitrogen-bearing
compounds are incorporated into bacteria, protozoans, and algae cells in lagoons. A large
portion of the nitrogen in the wastewater is discharged into Wascana Creek in the form of
ammonia. The City of Regina is currently in the process of selecting a consortium for the
upgrade of the plant to reduce ammonia and nutrients to lower limits.
2.4.1 WWTP Processes
Briefly stated, wastewater from the City of Regina is conveyed through four
distinct processes, as presented in Figure 2.1:
1) Preliminary treatment by screening and grit removal.
2) Primary treatment by settling 50 to 60% of the organic solids.
3) Secondary treatment by biodegradation in aerated lagoons for 90%
removal of organic matters and solids.
25
4) Tertiary treatment by alum addition and chemical precipitation of
phosphorus, algae and pathogens; seasonal effluent disinfection by UV
irradiation to meet bacteriological discharge standards.
Figure 2. 2 Regina WWTP process flow diagram (courtesy of the City of Regina)
Preliminary Treatment Process
Raw sewage is collected at the McCarthy Blvd. Pump Station , where it is
screened before being pumped through two 1,050 mm steel force mains to the Primary
Treatment Plant (PTP) located 5km west of the McCarthy Blvd. Pump Station. At the
PTP screened sewage undergoes grit removal where suspended solids are removed using
two aerated grit removal tanks and three primary sedimentation tanks. Within the grit
removal tanks, heavy inorganic solids are settled and the liquid is aerated and mixed by
26
compressed air. Every one to two months the flow is diverted and the grit is removed,
flushed, loaded onto trucks and hauled to the landfill.
After the grit removal operation, wastewater flows by gravity over a weir into the
primary sedimentation tanks. At this stage the flow velocity is slowed down through three
large rectangular tanks, thereby permitting separation of solids by settling and scum by
flotation. Primary effluent is then pumped to the aerated lagoons located 2km from the
preliminary treatment process. Sludge and scum are collected every two hours by a
bridge collector mechanism that travels at a low speed. The scum and sludge are then
pumped to the digesters, undergoing biological stabilization under mesophilic anaerobic
conditions in the primary digesters. The digestion results in the production of methane
and other gases. The methane gas is utilized in two ways. One way is to compress the gas
and inject it back into the digesters for mixing. The other way is to use it to heat the
buildings by burning it in a dual feed boiler. This also helps off-set potential costs for
burning natural gas. After 18 days, the digested sludge is then pumped to the dewatering
process where the digested sludge is centrifuged to reduce its water content before
disposal. The dewatering processes produce two streams: a solids stream called “cake”
and a liquid stream known as “concentrate”. Concentrate is pumped to the influent
channel of the sedimentation tanks. The cake is conveyed via a belt conveyor onto a truck
and hauled to an onsite stockpile located one kilometer away from the plant.
Secondary Treatment Process
Secondary treatment within the Regina WWTP is comprised of five aerated
treatment lagoons (Cells 2A, 2, 3, 1S, and 4). The aerated lagoons consist of earth basin
bioreactors with submerged aeration supporting a suspended growth activated sludge
27
process with a mixed liquor concentration below 800 mg/L. In this process, mainly
organic carbon is degraded by aerobic bacteria and higher organisms in the sludge.
It is common practice in lagoon systems to divide the wastewater into two streams at the
valve chamber. Between 10 to 20% of the primary effluent is sent to cell 1S. The rest of
the primary effluent is sent to cells 2A, 2 and 3. The effluent from cells 1S and 3 are
discharged to cell 4 for storage before it is conveyed by gravity to the tertiary treatment
plant for further treatment.
Tertiary Treatment Process
After biological treatment in the lagoons, the lagoon effluent flows by gravity into
the tertiary clarifier where it is treated with alum and polymer to precipitate phosphorus,
suspended solids, algae, and pathogens. In the clarifier, the flow velocity is slowed down,
permitting separation of solids by settling and scum by flotation. Tertiary effluent is then
conveyed by gravity to the UV disinfection system before being discharged to Wascana
Creek. Sludge is collected continuously by a sludge scrapper and pumped to a sludge
storage lagoon. Scum is periodically withdrawn by a sewer truck and discharged into the
cell.
3.0 METHODOLOGY
In this study, BioWinTM
model was used to simulate the startup of an anaerobic
digester. BioWinTM
is a widely recognized commercially available dynamic modelling
and simulation package for wastewater treatment processes used in North America. It
was developed by the EnviroSim Associates of Canada.
This chapter presents an analysis of the startup process for an anaerobic digester.
It includes a discussion of the five stages of the simulation process: (1) configuration of
28
the wastewater treatment process in the BioWinTM
; (2) data collection for the calibration
of the BioWinTM
model; (3) calibration of the BioWinTM
model; (4) validation of the
BioWinTM
model; and (5) application of the BioWinTM
model to achieve the objectives of
the research. The objectives of the research are to develop strategies for the timely and
cost-effective startup and operation of anaerobic digesters, and to maximize methane gas
production.
3.1 Configuration of BioWinTM
Model
The configured of BioWinTM
model is presented in Figure 3.1. The dimensions of
each component are summarized in Table 3.1. As shown in Figure 3.1, the configuration
of the primary treatment processes consists of the following components: a raw influent
element, a grit tank element, grit icons, a sedimentation tank element, primary effluent to
lagoons icon, scum 1 and scum 2 elements, digester 1 and digester 2 elements, gravity
thickener elements, dewatering elements, and a cake icon. Figure 3.1 also shows that
mixer 1 is located between the grit tank and the sedimentation tank. Mixer 2 is located
between the scum 1 element and the digester 1 element. Mixer 3 is located between the
scum 2 element and the digester 2 element. A flow splitter is located between the
sedimentation tank and the scum 1/scum 2 elements.
Figure 3.1 Configuration of BioWinTM
model for calibration and validation
29
Table 3.1 Dimensions of each configuration
Volume
m3
Area
m2
Depth
m
Width
m
Head space
volume m3
Head space
pressure KPa
Grit tank 940 235 4 4
Primary
sedimentation tank
7,582 2,106 3.6
Digester No.1 3,796 406 9.36 492 103
Digester No.2 3,390 406 8.36 492 103
Gravity thickener 3,796 406 9.36
3.2. Parameters for Calibration and Validation
The BioWinTM
model developed in this study was calibrated using the Regina
WWTP testing data collected in July 2007. In this case, detailed data concerning the
organic fraction of the influent wastewater, measured as COD, was not available.
Therefore, literature data, default values, and assumptions were used to set influent
wastewater characteristics.
In calibrating the model to deal with small unconformities, it was necessary to
make small adjustments on certain parameters in the model until the predicted results
matched the measured plant performance. The parameters which can be adjusted are the
reliable data which are not available from data collection and have large effects on the
model simulation. Therefore, engineering knowledge and experiences were used to
determine these important parameters. However, it is not enough to understand if a
certain parameter plays an important role in the model performance without a sensitivity
analysis. Literature sensitivity analysis results, engineering experiences and knowledge,
and model defaults were used in model calibration.
30
Anaerobic digestion parameters used in model calibration included wastewater
fractions, operational parameters, kinetic parameters, and stoichiometric parameters.
Wastewater fractions were used to specify the fractional composition of the influent
wastewater. Kinetics parameters in BioWinTM
stand for the rate of conversion reaction.
Stoichiometric parameters in BioWinTM
stand for the ratio of conversion of different
compounds (EnviroSim Associates Ltd., Canada). Default stoichiometric parameters in
BioWinTM
are tailored for municipal wastewater treatment systems (EnviroSim
Associates Ltd., Canada) which can be used directly for this research without any
adjustment.
3.2.1 Wastewater Characteristics – Data from the Regina WWTP
The Regina WWTP data collected between July and August of 2007 were
selected for model calibration and validation for two reasons: (1) the performance of the
digesters in 2007 were stable, which provided good historical data for calibration and
validation, (2) the characteristics of the wastewater in the summer (July and August)
showed good variation; therefore, it helped to evaluate the flexibility of the digesters in
the Regina WWTP.
Table 3.2 summarizes the measured and adjusted primary influent characteristics
between July and August of 2007. In assessing the validity of data, it is often useful to
examine the ratios of certain parameters rather than the absolute values of the parameters
themselves. The expected COD/BOD5 ratio for typical domestic wastewater should be in
the range of 2.0 to 2.2 and 1.9 to 2.1 for raw sewage and primary effluent, respectively
(Melcer et al., 2003).
31
Table 3.2 Measured and adjusted primary influent characteristics (the Regina WWTP,
2007)
Name Influent characteristics
July 2007
Influent characteristics
August 2007
Measured Adjusted Measured Adjusted
Total COD
mgCOD/L
243 455 241 457
TKN mgN/L 34.6 32.35
Total P mgP/L 5.53 5.25
Nitrate N mgN/L 7.79 0.01
pH 7.53 7.49
Alkalinity mmol/L 5 4.88
Inorganic S.S.
mgISS/L
55 43
Calcium mg/L 79 92
Magnesium mg/L 29 22
TSS mgTSS/L 232 218
VSS mgVSS/L 178 177
NH3-N 24.7 22.2
BOD5 mg/L 182 227.5 183 228.75
Flow m3/d 67,910
DO mg/L 0
Ratios
COD : BOD5 1.34 2 1.32 2
COD : VSS 1.37 2.56 1.36 2.58
VSS : TSS 0.73 0.81
TKN : COD 0.14 0.076 0.13 0.071
NH3-N : TKN 0.71 0.69
According to the Regina WWTP 2007 annual report, BOD5 was 182 mg/L, but
was adjusted to 227.5 mg/L because the Regina per capita BOD5 generation was
consistently lower than 0.08 kg/cap/d when no kitchen sink grinders were used. Thus
BOD5 = 0.1/0.08 ×182=227.5 (Tchobanoglous, et al., 2003). Moreover, the measured
BOD5 to COD ratio was 1.29, which was much lower than the normal ratio. In this case,
BOD5 was adjusted to 227.5 mg/L, and COD was adjusted to 455 mg/L by using a
32
COD/BOD5 ratio of 2.0. As such, the same method was used to adjust BOD5 and COD
measured in August of 2007 to 228.75 mg/L and 457 mg/L, respectively.
In the Regina WWTP, the scum collected in the primary sedimentation tanks is
also pumped to the digester, which contributes to biogas production. Therefore, scum 1
and scum 2 were considered two other streams of influent to the digesters, besides the
primary influent.
Table 3.3 Characteristics of Scum 1 and Scum 2 to the digesters
Name Scum 1 Scum 2
Flowa
11 11
Total CODb
mgCOD/L 130,000 130,000
TKNb mgN/L 130 130
Total Pb
mgP/L 10 10
Nitrate Na mgN/L 0.2 0.2
pHa
7.5 7.5
Alkalinitya mmol/L 5 5
Inorganic S.Sb. mgISS/L 1 1
Calciuma mg/L 79 79
Magnesiuma mg/L 29 29
DOa mg/L 0 0
a The Regina WWTP, 2007;
b URS Corp., 2009.
3.2.2 Wastewater Fractions - BioWinTM
According to Dursun's research (Dursun et al., 2011), the results from the
sensitivity analysis revealed that gas production is sensitive to (1) the wastewater fraction
Fxsp (non-colloidal slowly biodegradable fraction of COD), and (2) the wastewater
fraction Fup (unbiodegradable particulate fraction of COD). In Parker's work, it was found
that a fraction of Fup and Fxsp affected anaerobic digestion performance for digesting
33
wasted activated sludge (Parker et al., 2008). Moreover, fraction Fna was adjusted during
steady-state simulation for the purpose of matching the plant’s measured data. The
wastewater fractions of raw influent are presented in Table 3.4.
Table 3.4 Raw influent (sewage) wastewater fractions (EnviroSim Associates Ltd.)
Element name Default Adjusted
Fbs - Readily biodegradable (including Acetate) [gCOD/g of total
COD] 0.16
Fac - Acetate [gCOD/g of readily biodegradable COD] 0.15
Fxsp - Non-colloidal slowly biodegradable [gCOD/g of slowly
degradable COD] 0.75 0.8
Fus - Unbiodegradable soluble [gCOD/g of total COD] 0.05
Fup - Unbiodegradable particulate [gCOD/g of total COD] 0.13 0.15
Fna - Ammonia [gNH3-N/gTKN] 0.66 0.63
Fnox - Particulate organic nitrogen [gN/g Organic N] 0.5
Fnus - Soluble unbiodegradable TKN [gN/gTKN] 0.02
FupN - N:COD ratio for unbiodegradable part. COD [gN/gCOD] 0.035
Fpo4 - Phosphate [gPO4-P/gTP] 0.5
FupP - P:COD ratio for unbiodegradable part. COD [gP/gCOD] 0.011
FZbh - Non-poly-P heterotrophs [gCOD/g of total COD] 0.0001
FZbm - Anoxic methanol utilizers [gCOD/g of total COD] 0.0001
FZaob - Ammonia oxidizers [gCOD/g of total COD] 0.0001
FZnob - Nitrite oxidizers [gCOD/g of total COD] 0.0001
FZamob - Anaerobic ammonia oxidizers [gCOD/g of total COD] 0.0001
FZbp - PAOs [gCOD/g of total COD] 0.0001
FZbpa - Propionic acetogens [gCOD/g of total COD] 0.0001
FZbam - Acetoclastic methanogens [gCOD/g of total COD] 0.0001
FZbhm - H2-utilizing methanogens [gCOD/g of total COD] 0.0001
34
3.2.3 Kinetic and Stoichiometric Parameters - BioWinTM
According to Dursun's research (Dursun et al., 2011), the results from the
sensitivity analysis show that gas production is sensitive to kinetic parameters, hydrolysis
rate, and hydrolysis half saturation constants. VFA in the digester is affected by the
kinetic parameters of the methanogens, namely, the acetolastic maximum rate coefficient,
and the acetoclastic decay rate.
Experience has shown that all stoichiometric and kinetic parameters do not
change dramatically for different systems treating municipal wastewater, and the default
values shown in Table 3.5 can be used directly (Melcer et al., 2003).
Table 3.5 Model kinetic parameters - Methanogens (EnviroSim Associates Ltd.)
Name Default Value
Acetoclastic Mu Max [1/d] 0.3 0.31
Acetoclastic decay rate [1/d] 0.13 0.11
Hydrolysis rate 0.1 0.1
Hydrolysis half saturation 0.15 0.15
3.3 Steady-state Calibration
Model calibration is defined as the adaptation of a model so that it fits a certain
set of data from the full-scale WWTP being studied (Petersen et al., 2003). Calibration
generally involves combining the "operational" or "controllable" aspects of the treatment
plant with the input wastewater characteristics and making adjustments to selected
parameters to fit a set of plant performance data (Melcer et al., 2003). Good calibration
requires knowledge of both model parameters and influent wastewater characteristics,
which have significant effects on the sludge digestion performance.
35
Steady-state simulation provides a solution to the system based on the flow-
weighted average influent loading to the system (EnviroSim Associates Ltd.). The
general approach to steady-state calibration of BioWinTM
is to initially fit the predicted
gas production generated from the model to the measured data. Once this is done,
subsequent refinements are made to the pH, VFA, and alkalinity predictions so that they
also correspond to the values measured at the plant. A step-by-step trial procedure is used
to adjust each parameter one at a time and to compare the model prediction to the
measured data.
Model Run #1. An initial model run was made using the average measured and
adjusted 2007 influent data from Table 3.2. Scum concentrations were taken from
Table 3.3. The splitter flow ratio of digester 1 to digester 2 was set to 1:1.
BioWinTM
default values were used for the wastewater fractions, kinetic and
stoichiometric parameters. Tentative conclusions drawn from the Model Run #1
are: (1) the BioWinTM
default values for wastewater fractions and kinetic
parameters have to be adjusted to better predict measured gas production,
alkalinity, and VFA, and (2) the adjusted COD value worked well.
Model Run #2. The second model run was made by increasing and decreasing the
raw influent Fxsp fraction stepwise in increments of 0.01 to values of 0.83 and 0.7,
respectively. When Fxsp = 0.8, the model predicted gas production was the best fit
to the measured values.
Model Run #3. The third model run was made by increasing and decreasing the
raw influent Fup fraction stepwise in increments of 0.01 to values of 0.16 and 0.1,
36
respectively, in order to improve gas predictions. A value of Fup = 0.15 was
chosen for model calibration.
Model Run #4. The forth model run was made by increasing and decreasing the
hydrolysis rate kinetic parameter stepwise in increments of 0.01 to values of 0.13
and 0.07, respectively. The default value of 0.1 was chosen because it yielded the
best gas predictions.
Model Run #5. The fifth model run was made by increasing and decreasing the
hydrolysis half saturation kinetic parameter in increments of 0.01 to values of
0.18 and 0.12, respectively, in order to better fit the gas prediction. However, like
the hydrolysis rate, a default value of 0.15 was chosen to be used.
Model Run #6. The sixth model run was made by increasing the Fbs fraction of the
scum stepwise in increments of 0.05 up to a maximum value of 0.80. A value of
0.75 was chosen because it best predicted gas production relative to the measured
values and adjusted values. However, using an Fbs fraction as high as 0.75,
resulted in very low FupN and FupP fractions. FupN = 5E10-10
and FupP = 5E10-10
were the selected values.
Model Run #7. The seventh model run was made by increasing and decreasing the
"Acetoclastic Mu Max - Methanogens" kinetic parameters stepwise in increments
of 0.01 to values of 0.27 and 0.33, respectively, to better predict VFA
concentrations relative to the measured values. A value of 0.31 of Acetoclastic
Mu Max was chosen.
Model Run #8. The eighth model run was made by increasing and decreasing the
acetoclastic decay rate stepwise in increments of 0.01 to values of 0.16 and 0.1
37
respectively. A value of 0.11 was chosen because it was the best at predicting
VFA concentrations relative to the measured values.
Model Run #9. The ninth model run was made by increasing and decreasing Fna
stepwise in increments of 0.01 to values of 0.61 and 0.71, respectively. Fna = 0.63
gave the best prediction of alkalinity relative to the measured values.
The calibration results of the digester effluent are presented in Table 3.6, and the
calibration results of the digester’s operation and performance are summarized in Table
3.7.
Table 3.6 Calibration - digesters effluent
Digester 1 Digester 2
Parameters Conc.
(mg/L)
Mass rate
(kg/d)
Conc.
(mg/L)
Mass rate
(kg/d)
Notes
Volatile suspended
solids
12,069.37 2,123.89 12,471.11 2,195.24
Total suspended solids 14,977.45 2,635.64 15,382.8 2,707.78
Particulate COD 19,108.97 3,362.68 19,744.3 3,475.52
Filtered COD 513.85 90.42 517.59 91.11
Total COD 19,622.83 3,453.10 20,261.9 3,566.63
Soluble PO4-P 168.46 29.64 161.56 28.44
Total P 379.67 66.81 379.68 66.83
Filtered TKN 362.47 63.78 346.62 61.01
Particulate TKN 637.82 112.24 656.47 115.56
Total Kjeldahl
Nitrogen
1,000.29 176.02 1,003.1 176.57
Filtered Carbonaceous
BOD
59.18 10.41 61.93 10.90
Total Carbonaceous
BOD
4,003.2 704.46 4,353.78 766.38
Nitrite + Nitrate 0 0 0 0
Total N 1,000.29 176.02 1,003.10 176.57
38
Total inorganic N 359.70 63.30 343.86 60.53
Alkalinity 38.10 6.71 37.18 6.54 mmol/L and
kmol/d
pH 6.68 6.68
Volatile fatty acids 82.33 14.49 86.18 15.17
Total precipitated
solids
0 0 0 0
Total inorganic
suspended solids
2,908.08 511.75 2,911.74 512.54
Ammonia N 359.70 63.30 343.86 60.53
Nitrate N 0 0 0 0
Table 3.7 Calibration - digesters operation and performance
Parameters Digester 1 Value Digester 2 Value Units
Hydraulic residence time 21.6 19.3 Days
Digester influent flow 175.97 176.03 m3 /d
Gas flow rate (dry) 3,129.23 3,061.25 m3 /d
Methane content 63.13 63.11 %
Carbon dioxide content 36.37 36.41 %
Hydrogen content 0.05 0.05 %
Ammonia content 0.34 0.32 %
VSS destruction 53.91 52.38 %
For comparison, the steady-state calibration results and the plant measured results
are shown in Table 3.8. Only important parameters which can indicate digester
performance are listed. Overall, steady-state calibration results of each parameter
matched the plant measured results. This indicated that the steady-state calibration was
successful.
39
Table 3.8 Calibration - steady-state simulation results vs. plant measured results
Calibration results Measurement
results
Normal range Match status
Digester 1 Digester 2 Digester 1 Digester 2
pH 6.68 6.68 6.78 6.8 6.6-7.6
(Technical Practice
Committee, 2012)
Acceptable
VFA 82.33
mg/L
86.18
mg/L
94.25
mg/L
96.375
mg/L
50 - 150 mg/L
(Technical Practice
Committee, 2012)
Acceptable
Alkalinity 38.1
mmol/L
37.18
mmol/L
32.53
mmol/L
35.7
mmol/L
40 - 100 mmol/L
(Tchobanoglous
et al., 2003)
Acceptable
Methane
content
63.13% 63.11% 62.2% 63.2% Excellent
Gas flow
rate
3,129
m3
3,061
m3
3,054
m3
2,404
m3
Acceptable
VSS
destruction
53.91% 52.38% 38-60 %
(Muller et al., 2011)
HRT 21.6
days
19.3
days
18days 18days 20 days
(Filbert, 2012)
Acceptable
3.4 Steady-state Validation
To check how the model fit to other data, a validation was carried out after the
calibration. Validation involves applying the calibrated model to a different set of
operating data than that used for calibration. As the average data from July 2007 were
used for calibration, the average data from August 2007 were used for validation. This
data was entered into each component of the BioWinTM
model to conduct a steady-state
validation. The validation results of the digester effluent and the results of the digester’s
operation and performance are show in Tables 3.9 and 3.10.
Table 3.9 Validation – digesters effluent
Digester 1 Digester 2
Parameters Conc.
(mg/L)
Mass rate
(kg/d)
Conc.
(mg/L)
Mass rate
(kg/d)
Notes
40
Volatile suspended solids 12,413.11 2,091.08 12,928.39 2,281.6
Total suspended solids 14,901.4 2,510.25 15,428.2 2,722.78
Particulate COD 19,657.49 3,311.45 20,473.6 3,613.19
Filtered COD 495.09 83.4 499.37 88.13
Total COD 20,152.58 3,394.85 20,973 3,701.32
Soluble PO4-P 167.68 28.25 160.76 28.37
Total P 383.13 64.54 384.59 67.87
Filtered TKN 355.83 59.94 339.72 59.95
Particulate TKN 651.08 109.68 673.55 118.87
Total Kjeldahl Nitrogen 1,006.92 169.62 1,013.27 178.82
Filtered Carbonaceous
BOD
62.32 10.5 66.48 11.73
Total Carbonaceous BOD 4,054.36 682.99 4,485.84 791.66
Nitrite + Nitrate 0 0 0 0
Total N 1,006.92 169.62 1,013.27 178.82
Total inorganic N 353.15 59.49 337.04 59.48
Alkalinity 36.32 6.12 35.32 6.23 mmol/L
and kmol/d
pH 6.66 6.66
Volatile fatty acids 86.7 14.61 92.53 16.33
Total precipitated solids 0 0 0 0
Total inorganic
suspended solids
2,488.3 419.17 2,499.86 441.18
Ammonia N 353.15 59.49 337.04 59.48
Nitrate N 0 0 0 0
Table 3.10 Validation - digesters operation and performance
Parameters Digester 1 Value Digester 2 Value Units
Hydraulic residence
time
22.2 19.7 Days
Digester influent flow 168.46 176.48 m3 /d
Gas flow rate (dry) 3,206.06 3,186 m3 /d
Methane content 62.98 62.98 %
41
Carbon dioxide content 36.59 36.62 %
Hydrogen content 0.05 0.04 %
Ammonia content 0.31 0.29 %
VSS destruction 55.55 53.71 %
For comparison, the steady-state validation results and the plant measured results
are shown in Table 3.11. Only important parameters which indicate digester performance
are listed. The close match between the model and the data indicates that the steady-state
validation was successful.
Table 3.11 Validation - steady-state simulation results vs. plant measured results
Validation results Measurement results Normal range Match
status Digester 1 Digester 2 Digester 1 Digester 2
pH 6.66 6.66 6.84 6.86 6.6-7.6
(Technical Practice
Committee, 2012)
Acceptable
VFA 86.70
mg/L
92.53
mg/L
98.43
mg/L
99.43
mg/L
50 - 150 mg/L
(Technical Practice
Committee, 2012)
Acceptable
Alkalinity 36.32
mmol/L
35.32
mmol/L
33.18
mmol/L
36.06
mmol/L
40 - 100 mmol/L
(Tchobanoglous
et al., 2003)
Acceptable
Methane
content
62.98% 62.98% 62.25% 63.5% Excellent
Gas flow
rate
3,206
m3
3,186
m3
3,066
m3
2,349 m3 Acceptable
VSS
destruction
55.55% 53.71% 38-60 %
(Muller et al., 2011)
HRT 22.2 days 19.7 days 18 days 18 days 20 days
(Filbert, 2012)
Acceptable
3.5 Dynamic Calibration
Dynamic simulation shows the time-varying system response based on the time-
varying influent loading to the system (EnviroSim Associates Ltd.). The dynamic
calibration was run for 30 days. The influent characteristics are presented in Tables A-1,
A-2, and A-3.
42
A selection of diagrams showing gas flow rate, pH, VFA, and alkalinity are shown in
Figures 3.2 to 3.9, respectively, to demonstrate the comparison of the dynamic simulation
results and the plant measured results. The conclusions drawn from Figures 3.2 to 3.9 are
as follows:
Figure 3.2 shows the gas flow rate profiles. It demonstrates that the model
predicted values (solid lines) fit the measured values (squares) for digester 1.
Figure 3.3 indicates that the model predicted values for digester 2 are higher than
the measured values.
Figure 3.4 and 3.5 show that the model predicted pH values are lower than the
measured values.
Figure 3.6 and 3.7 show that the measured alkalinity values and model predicted
values are in good agreement with one another.
Though available measured VFA values are limited, the Figure 3.8 and 3.9 show
that the measured values and model predicted values are in close agreement.
The predicted values generated from the model and the measured data show a
relatively close fit. It was not possible to get all model outputs to correspond exactly to
the plant measurements. The measurements had high variability, but model correlation
with “reasonable accuracy” was achieved which indicated that the dynamic calibration
was successful.
43
Figure 3.2 Calibration - Digester 1 gas flow rate
Figure 3.3 Calibration - Digester 2 gas flow rate
Digester 1 Gas Flow Rate
Digester 1 Gas flow rate (dry) "Digester 1 Gas flow rate (actual)"
DATE
7/31/20077/29/20077/27/20077/25/20077/23/20077/21/20077/19/20077/17/20077/15/20077/13/20077/11/20077/9/20077/7/20077/5/20077/3/20077/1/2007
GA
S F
LO
W R
AT
E (
DR
Y)
(m3
/d)
4,400
4,200
4,000
3,800
3,600
3,400
3,200
3,000
2,800
2,600
2,400
2,200
2,000
1,800
1,600
1,400
1,200
1,000
800
600
400
200
0
Digester 2 Gas Flow Rate
Digester 2 Gas flow rate (dry) "Digester 1 Gas flow rate (actual)"
DATE
7/31/20077/29/20077/27/20077/25/20077/23/20077/21/20077/19/20077/17/20077/15/20077/13/20077/11/20077/9/20077/7/20077/5/20077/3/20077/1/2007
GA
S F
LO
W R
AT
E (
DR
Y)
(m3
/d)
4,200
4,000
3,800
3,600
3,400
3,200
3,000
2,800
2,600
2,400
2,200
2,000
1,800
1,600
1,400
1,200
1,000
800
600
400
200
0
44
Figure 3.4 Calibration - Digester 1 pH
Figure 3.5 Calibration - Digester 2 pH
Figure 3.6 Calibration - Digester 1 alkalinity
Figure 3.7 Calibration - Digester 2 alkalinity
Digester 1 pH
Digester 1 pH "Digester 1 pH (actual)"
DATE
7/31/20077/29/20077/27/20077/25/20077/23/20077/21/20077/19/20077/17/20077/15/20077/13/20077/11/20077/9/20077/7/20077/5/20077/3/20077/1/2007
pH
6.8
6.75
6.7
6.65
6.6
Digester 2 pH
Digester 2 pH "Digester 2 pH (actual)"
DATE
7/31/20077/29/20077/27/20077/25/20077/23/20077/21/20077/19/20077/17/20077/15/20077/13/20077/11/20077/9/20077/7/20077/5/20077/3/20077/1/2007
pH
6.8
6.75
6.7
6.65
6.6
Digester 1 Alkalinity
Digester 1 Alkalinity "Digester 1 ALK (actual)"
DATE
7/31/20077/29/20077/27/20077/25/20077/23/20077/21/20077/19/20077/17/20077/15/20077/13/20077/11/20077/9/20077/7/20077/5/20077/3/20077/1/2007
CO
NC
. (m
mo
l/L
)
45
40
35
30
25
20
15
10
5
0
Digester 2 Alkalinity
Digester 2 Alkalinity "Digester 2 ALK (actual)"
DATE
7/31/20077/29/20077/27/20077/25/20077/23/20077/21/20077/19/20077/17/20077/15/20077/13/20077/11/20077/9/20077/7/20077/5/20077/3/20077/1/2007
CO
NC
. (m
mo
l/L
)
45
40
35
30
25
20
15
10
5
0
45
Figure 3.8 Calibration - Digester 1 VFA
Figure 3.9 Calibration - Digester 2 VFA
3.6 Dynamic Validation
To validate the dynamic calibration, dynamic validation was conducted using the
influent characteristics presented in Table B-1, B-2 and B-3. A selection of plots showing
gas flow rate, pH, VFA, and alkalinity are shown in Figures 3.10 to 3.17, respectively.
The conclusions drawn from the analyses of the dynamic validation figures are:
From Figure 3.10 and 3.11, the model predicted gas flow rate values for digester 1
(solid lines) are fit to the measured values (squares) for digester 1. But for
digester 2, the model predicted values are higher than the measured values.
Figure 3.12 and 3.13 present the measured alkalinity values and model predicted
values for both digesters are in good agreement.
Though available measured data for VFA are limited, the Figure 3.14 and 3.15
show that the measured values and predicted values are in close agreement.
Digester 1 VFA
Digester 1 Volatile fatty acids "Digester 1 VFA (actual)"
DATE
7/31/20077/29/20077/27/20077/25/20077/23/20077/21/20077/19/20077/17/20077/15/20077/13/20077/11/20077/9/20077/7/20077/5/20077/3/20077/1/2007
CO
NC
. (m
g/L
)
140
120
100
80
60
40
20
0
Digester 2 VFA
Digester 2 Volatile fatty acids "Digester 2 VFA (actual)"
DATE
7/31/20077/29/20077/27/20077/25/20077/23/20077/21/20077/19/20077/17/20077/15/20077/13/20077/11/20077/9/20077/7/20077/5/20077/3/20077/1/2007
CO
NC
. (m
g/L
)
140
120
100
80
60
40
20
0
46
The model predicted pH values (Figure 3.16 and 3.17) are lower than the
measured values.
These observations confirm that the dynamic validation was successful.
Figure 3.10 Validation - Digester 1 gas flow rate
Figure 3.11 Validation - Digester 2 gas flow rate
Figure 3.12 Validation - Digester 1 alkalinity
Digester 1 Gas Flow Rate
Digester 1 Gas flow rate (dry) "Digester 1 Gas flow rate (actual)"
DATE
9/1/20078/30/20078/28/20078/26/20078/24/20078/22/20078/20/20078/18/20078/16/20078/14/20078/12/20078/10/20078/8/20078/6/20078/4/20078/2/2007GA
S F
LO
W R
AT
E (
DR
Y)
(m3
/d)
4,500
4,000
3,500
3,000
2,500
2,000
1,500
1,000
500
0
Digester 2 Gas Flow Rate
Digester 2 Gas flow rate (dry) "Digester 2 Gas flow rate (actual)"
DATE
9/1/20078/30/20078/28/20078/26/20078/24/20078/22/20078/20/20078/18/20078/16/20078/14/20078/12/20078/10/20078/8/20078/6/20078/4/20078/2/2007GA
S F
LO
W R
AT
E (
DR
Y)
(m3
/d)
4,500
4,000
3,500
3,000
2,500
2,000
1,500
1,000
500
0
Digester 1 Alkalinity
Digester 1 Alkalinity "Digester 1 ALK (actual)"
DATE
9/1/20078/30/20078/28/20078/26/20078/24/20078/22/20078/20/20078/18/20078/16/20078/14/20078/12/20078/10/20078/8/20078/6/20078/4/20078/2/2007
CO
NC
. (m
mo
l/L
)
45
40
35
30
25
20
15
10
5
0
47
Figure 3.13 Validation - Digester 2 alkalinity
Figure 3.14 Validation - Digester 1 VFA
Figure 3.15 Validation - Digester 2 VFA
Figure 3.16 Validation - Digester 1 pH
Digester 2 Alkalinity
Digester 2 Alkalinity "Digester 2 Alkalinity (actual)"
DATE
9/1/20078/30/20078/28/20078/26/20078/24/20078/22/20078/20/20078/18/20078/16/20078/14/20078/12/20078/10/20078/8/20078/6/20078/4/20078/2/2007
CO
NC
. (m
mo
l/L
)
45
40
35
30
25
20
15
10
5
0
Digester 1 VFA
Digester 1 Volatile fatty acids "Digester 1 VFA (actual)"
DATE
9/1/20078/30/20078/28/20078/26/20078/24/20078/22/20078/20/20078/18/20078/16/20078/14/20078/12/20078/10/20078/8/20078/6/20078/4/20078/2/2007
CO
NC
. (m
g/L
)
160
140
120
100
80
60
40
20
0
Digester 2 VFA
Digester 2 Volatile fatty acids "Digester 2 VFA (actual)"
DATE
9/1/20078/30/20078/28/20078/26/20078/24/20078/22/20078/20/20078/18/20078/16/20078/14/20078/12/20078/10/20078/8/20078/6/20078/4/20078/2/2007
CO
NC
. (m
g/L
)
160
140
120
100
80
60
40
20
0
Digester 1 pH
Digester 1 pH "Digester 1 pH (actual)"
DATE
9/1/20078/30/20078/28/20078/26/20078/24/20078/22/20078/20/20078/18/20078/16/20078/14/20078/12/20078/10/20078/8/20078/6/20078/4/20078/2/2007
pH
7
6.95
6.9
6.85
6.8
6.75
6.7
6.65
6.6
6.55
6.5
48
Figure 3.17 Validation - Digester 2 pH
4.0 RESULTS AND DISCUSSION
This section presents a dynamic simulation of the startup of an anaerobic digester
fed with primary sludge. The results of the dynamic simulation were also used to develop
general strategies that can be used to assist in the startup of anaerobic digesters at other
WWTPs.
4.1 Dynamic Simulation for the Startup of an Anaerobic Digester
Dynamic simulations presented in this section were conducted using the data
collected from digester 2 at the Regina WWTP. This is because digester 1 at the Regina
WWTP was out of service for cleaning during the time period in which data was
available. Digester 2 was cleaned in the winter of 2010 and it was ready for startup in
early spring. It became stable late fall. Thus, the dynamic simulations presented here
encompass the period from April 16, 2012 when sludge seed was first introduced to the
digester to September 30, 2012 when the maximum feed rate of 300 m3 of primary sludge
was reached.
The startup procedure consists of 10 well-defined steps:
1. Filling: the digester was filled to 1.0 m below normal water level with a mixture
of primary effluent and tertiary effluent to minimize the presence of DO, high
Digester 2 pH
Digester 2 pH "Digester 2 pH (actual)"
DATE
9/1/20078/30/20078/28/20078/26/20078/24/20078/22/20078/20/20078/18/20078/16/20078/14/20078/12/20078/10/20078/8/20078/6/20078/4/20078/2/2007
pH
7
6.95
6.9
6.85
6.8
6.75
6.7
6.65
6.6
6.55
6.5
49
COD, sulfate, and toxins that could be potentially harmful to the anaerobic
digester seed.
2. Pressure test biogas piping: nitrogen gas was introduced downstream of the gas
compressor to purge and pressure test the biogas piping before the roof access
was sealed. This was done to ensure that sections of piping removed for
maintenance were completely sealed.
3. Pressure test gas head space: the digester’s roof access hatches were closed and
natural gas was introduced through the vacuum relief line to increase the digester
pressure to 125 mm H2O. The digester was then pressure tested by raising the
water level in the digester by 40 mm, which increased the digester gas pressure to
500 mm H2O. Soap tests were conducted on all threaded or flanged connections
on the digester.
4. Heating: the digester heating system was started and the temperature was set to
35 °C.
5. Dilution of potential explosive gas mixture: biogas from digester 1 was
transferred to digester 2 to ensure that any potential pockets of explosive gas were
diluted. Biogas from digester 1 had a methane concentration of 62%. After mixing
with air contained in digester 2, the methane concentration was reduced to 30%,
which is well above the maximum explosive limit.
6. Mixing: to attain uniform temperatures in the digester, a gas recirculation
compressor was started after it was confirmed that the biogas mixture was above
the maximum explosive limit.
50
7. Seeding: the digester was seeded with 40 m3 of anaerobically digested sludge
hauled from the City of Saskatoon WWTP. This volume of seed was selected
based on transportation costs, which were about $4,000 per 40 m3 of sludge.
8. Feeding: digester 2 was initially fed 100 kg of primary sludge. The feed rate was
progressively increased as presented in Table E-1 and E-2 in the Appendix E.
9. Alkalinity: sodium bicarbonate was used to adjust the digester pH to 6.8 to 7.2.
Bicarbonate was added in the event that the digester pH decreased to 6.3.
10. Monitoring: digester startup processes were monitored by sampling the digester
twice daily at 7:30 AM and 2:00 PM for the analysis of the following parameters:
a. Volatile acids – A range of operation between 100 to 300 mg/L was set for
the startup. If the VA exceeded 300 mg/L, the sludge feed would need to
be reduced or stopped entirely.
b. Total alkalinity – A range of operation between 1000 to 2000 mg/L (20 to
40 mmol/L) was set for the startup.
c. pH – A range of operation between 6.5 and 7.0 was set for the startup. If
the pH decreased below 6.5, the sludge feed would need to be reduced or
stopped entirely. If the pH decrease below 6.3, sodium bicarbonate would
need to be added.
d. TS – Total solids was used as an indicator of the biomass production (TS
= TSS (total suspended solids) + TDS (total dissolved solids)).
e. Gas production and gas composition were also used as an indicator of the
overall progress of the digester startup process.
51
4.1.1 Model Configuration
The BioWinTM
model configuration is shown in Figure 4.1. It includes the
following influent streams: a raw influent element, a grit tank element, a sedimentation
tank element, scum 1 and scum 2 elements, and new bicarbonate and seed elements.
Input parameters for these streams are given in Appendix D. It should be noted that on
Day 1 the bicarbonate stream was given the values of a primary effluent/tertiary effluent
(Tables C-4 and C-5 in the Appendix C) mixture to minimize the presence of DO, high
COD, sulfate, and toxins that could potentially harm the anaerobic digester seed. The
primary effluent/tertiary effluent was taken from the whole plant steady-state simulation
model (Appendix C).
Figure 4.1 Configuration of the BioWinTM
model for anaerobic digestion startup
4.1.2 Dynamic Simulation
A dynamic startup simulation can be conducted by giving a fit status of the model
predicted values to the actual measured values (base case). A selection of plots from the
dynamic simulation are shown in Figures 4.2 to 4.7.
Influent
Digester 1
Grit Tank
Digester 2
Primary Effluent to Lagoons
Cake
GritScum 1
Scum 2
PS to lagoons
Bicarbonate Seed
52
Figure 4. 2 Actual startup simulation - Digester 2 VFA
Figure 4.3 Actual startup simulation - Digester 2 pH
Figure 4.4 Actual startup simulation - Digester 2 gas flow rate
VFA
Digester 2 Volatile fatty acids "Digester 2 VFA (actual)"
9/2
9/2
01
2
9/2
2/2
01
2
9/1
5/2
01
2
9/8
/20
12
9/1
/20
12
8/2
5/2
01
2
8/1
8/2
01
2
8/1
1/2
01
2
8/4
/20
12
7/2
8/2
01
2
7/2
1/2
01
2
7/1
4/2
01
2
7/7
/20
12
6/3
0/2
01
2
6/2
3/2
01
2
6/1
6/2
01
2
6/9
/20
12
6/2
/20
12
5/2
6/2
01
2
5/1
9/2
01
2
5/1
2/2
01
2
5/5
/20
12
4/2
8/2
01
2
4/2
1/2
01
2
4/1
4/2
01
2
4/7
/20
12
CO
NC
. (m
g/L
)
700
600
500
400
300
200
100
0
Digester 2 pH
Digester 2 pH "Digester 2 pH (actual)"
9/2
9/2
01
2
9/2
2/2
01
2
9/1
5/2
01
2
9/8
/20
12
9/1
/20
12
8/2
5/2
01
2
8/1
8/2
01
2
8/1
1/2
01
2
8/4
/20
12
7/2
8/2
01
2
7/2
1/2
01
2
7/1
4/2
01
2
7/7
/20
12
6/3
0/2
01
2
6/2
3/2
01
2
6/1
6/2
01
2
6/9
/20
12
6/2
/20
12
5/2
6/2
01
2
5/1
9/2
01
2
5/1
2/2
01
2
5/5
/20
12
4/2
8/2
01
2
4/2
1/2
01
2
4/1
4/2
01
2
4/7
/20
12
pH
7
6
5
Digester 2 gas flow rate
Digester 2 Gas flow rate (dry) "Digester 2 Gas flow rate (actual)"
9/2
9/2
01
2
9/2
2/2
01
2
9/1
5/2
01
2
9/8
/20
12
9/1
/20
12
8/2
5/2
01
2
8/1
8/2
01
2
8/1
1/2
01
2
8/4
/20
12
7/2
8/2
01
2
7/2
1/2
01
2
7/1
4/2
01
2
7/7
/20
12
6/3
0/2
01
2
6/2
3/2
01
2
6/1
6/2
01
2
6/9
/20
12
6/2
/20
12
5/2
6/2
01
2
5/1
9/2
01
2
5/1
2/2
01
2
5/5
/20
12
4/2
8/2
01
2
4/2
1/2
01
2
4/1
4/2
01
2
4/7
/20
12
GA
S F
LO
W R
AT
E (
DR
Y)
(m3
/d)
5,000
4,500
4,000
3,500
3,000
2,500
2,000
1,500
1,000
500
0
53
Figure 4.5 Actual startup simulation - Digester 2 alkalinity
Figure 4.6 Actual startup simulation - Digester 2 TSS
Figure 4.7 Actual startup simulation - Digester 2 methane content
Alkalinity
Digester 2 Alkalinity "Digester 2 Alkalinity(actual)"
9/2
9/2
01
2
9/2
2/2
01
2
9/1
5/2
01
2
9/8
/20
12
9/1
/20
12
8/2
5/2
01
2
8/1
8/2
01
2
8/1
1/2
01
2
8/4
/20
12
7/2
8/2
01
2
7/2
1/2
01
2
7/1
4/2
01
2
7/7
/20
12
6/3
0/2
01
2
6/2
3/2
01
2
6/1
6/2
01
2
6/9
/20
12
6/2
/20
12
5/2
6/2
01
2
5/1
9/2
01
2
5/1
2/2
01
2
5/5
/20
12
4/2
8/2
01
2
4/2
1/2
01
2
4/1
4/2
01
2
4/7
/20
12
CO
NC
. (m
mo
l/L
)
45
40
35
30
25
20
15
10
5
0
TSS
Digester 2 Total suspended solids TS (actual)
9/2
9/2
01
2
9/2
2/2
01
2
9/1
5/2
01
2
9/8
/20
12
9/1
/20
12
8/2
5/2
01
2
8/1
8/2
01
2
8/1
1/2
01
2
8/4
/20
12
7/2
8/2
01
2
7/2
1/2
01
2
7/1
4/2
01
2
7/7
/20
12
6/3
0/2
01
2
6/2
3/2
01
2
6/1
6/2
01
2
6/9
/20
12
6/2
/20
12
5/2
6/2
01
2
5/1
9/2
01
2
5/1
2/2
01
2
5/5
/20
12
4/2
8/2
01
2
4/2
1/2
01
2
4/1
4/2
01
2
4/7
/20
12
CO
NC
. (m
gT
SS
/L)
24,00024,000
22,00022,000
20,00020,000
18,00018,000
16,00016,000
14,00014,000
12,00012,000
10,00010,000
8,0008,000
6,0006,000
4,0004,000
2,0002,000
00
Methane content
Digester 2 Methane content "Digester 1 methane content (actual)"9
/29
/20
12
9/2
2/2
01
2
9/1
5/2
01
2
9/8
/20
12
9/1
/20
12
8/2
5/2
01
2
8/1
8/2
01
2
8/1
1/2
01
2
8/4
/20
12
7/2
8/2
01
2
7/2
1/2
01
2
7/1
4/2
01
2
7/7
/20
12
6/3
0/2
01
2
6/2
3/2
01
2
6/1
6/2
01
2
6/9
/20
12
6/2
/20
12
5/2
6/2
01
2
5/1
9/2
01
2
5/1
2/2
01
2
5/5
/20
12
4/2
8/2
01
2
4/2
1/2
01
2
4/1
4/2
01
2
4/7
/20
12
ME
TH
AN
E C
ON
TE
NT
(%
)
100
90
80
70
60
50
40
30
20
10
0
54
From the data presented in Figures 4.2 – 4.7, the following conclusions were
drawn:
Figure 4.2 and Figure 4.3 indicate that increasing VFA leads to a decrease in pH,
which is an indicator of startup performance problems.
Figure 4.2 indicates that the measured VFA values and model predicted values are
in good agreement before scum was added. However, during April 28 to May 12,
the values of VFA exceeded 300 mg/L for both of model prediction and the base
case. This would make the digester nonfunctional and cause the startup to fail.
Figure 4.3 shows that the model predicted values for pH are lower than the
measured values. Model predicted values overestimate the drop in pH between
April 21 and May 19.
Figure 4.4 presents the model predicted biogas flow rate in close agreement with
the measured values up to August 28. On August 28, scum was added to the
digester. After the scum addition, the gas prediction was lower than the measured
values. The scum provided additional substrate for digestion which promoted
greater gas production. This change in substrate addition was not accounted for in
the model predicted values.
Figure 4.5 shows that the measured alkalinity values were higher than the model
predicted values.
Figure 4.7 depicts a good fit between the predicted methane content and the
measured values. On April 14, the plant measured a high methane content value
because additional methane was introduced into the digester to avoid explosive
55
dilute gases. After April 16 seed sludge was transferred to the digester, there was
a linear increase in methane content up to June 23, when the anaerobic digester
stabilized. At this point the methane content remained at a plateau for both the
model prediction and the measured values.
In summary, the values predicted from the dynamic simulation fit very well to the
measured values, especially for the following parameters: VFA, gas flow rate, alkalinity,
TSS, and methane content. The values predicted for pH did not fit well to the measured
values during the first 30 days of the dynamic simulation. Therefore, VFA was used as
the major criteria to monitor the anaerobic digester performance, along with gas flow
rate, alkalinity, and TSS.
4.2 Optimization of Startup
Three strategies have been developed for a timely and cost-effective startup of an
anaerobic digester based on a simulation of the BioWinTM
model. From these strategies,
the optimal sludge feed rate, the optimal seed sludge amount, and the optimal bicarbonate
concentration can be determined under different startup conditions.
4.2.1 Optimization of Sludge Feed Rate
Sludge feed rate is the most important parameter for the successful startup of an
anaerobic digester. A proper sludge feed rate will prevent the digester from becoming
acidic and failing to start up. The model simulation has identified that the best way to
feed raw sludge during the startup procedures is to feed the sludge into the digester at a
gradually increasing feed rate. In this research, the sludge feed rate strategies were
developed based on a seed volume of 120 m3.
56
The first strategy developed for the sludge feed rate was called F/M proportion
(Figure 4.8) which was calculated based on the feed to mass ratio (F/M ratio). The second
strategy developed for the sludge feed rate was called flow proportion which was
calculated based on increasing percentages of digester capacity. This is shown in Figure
4.9. The digester sludge feed rate was limited to values less than 300 m3/d based on a
SRT of 12 days at 35 °C. A lower SRT limit of 10 days may wash out a portion of the
menthanogenic population, while a higher SRT (over 20 days) may dilute the contents of
the digester.
Figure 4.8 Sludge feed rate calculated on F/M proportion
0
50
100
150
200
250
300
17-A
pr
24-A
pr
1-M
ay
8-M
ay
15-M
ay
22-M
ay
29-M
ay
5-J
un
12
-Jun
19
-Jun
26
-Jun
3-J
ul
10-J
ul
17-J
ul
24-J
ul
31-J
ul
7-A
ug
14-A
ug
21-A
ug
28-A
ug
4-S
ep
11-S
ep
18-S
ep
25-S
ep
2-O
ct
Slu
dge
m3
Sludge feed rate F/M proportion m3/d
Y = 0.008X3 - 0.0262X
2 +0.6537X + 7.6413
R2 = 0.9984
57
Figure 4.9 Sludge feed rate calculated on percent of digester volume proportion
Table 4.1 shows six model dynamic simulations conducted under different
situations:
Table 4.1 Situation of each model dynamic simulation for optimization of startup
Dynamic
simulation
Seed volume Sludge feed rate Sodium
bicarbonate
Scum
Base case 40 m3 Slow: actual plant
feed rate
Added Added
Run #1 120 m3 F/M proportion No No
Run #2 80 m3 F/M proportion No No
Run #3 40 m3 F/M proportion Yes No
Run #4 120 m3 Flow proportion No No
Run #5 80 m3 Flow proportion No No
Run #6 40 m3 Flow proportion Yes No
The base case is the actual plant startup of the anaerobic digester. It is based on a
seed volume of 40 m3 and a slow feed rate with bicarbonate addition to control the pH
0 25 50 75
100 125 150 175 200 225 250 275 300
17-A
pr
24-A
pr
1-M
ay
8-M
ay
15-M
ay
22-M
ay
29-M
ay
5-J
un
12-J
un
19-J
un
26-J
un
3-J
ul
10-J
ul
17-J
ul
24-J
ul
31-J
ul
7-A
ug
14-A
ug
21-A
ug
28-A
ug
4-S
ep
11
-Sep
18-S
ep
25-S
ep
2-O
ct
Ssl
udge
m3
Sludge feed rate ( percent of digester volume proportion) m3/d
Y1 = 0.751X + 1.7273
Y2 = 7.6X - 311.6
58
and the digester performance. In addition, scum was added on August 28 to increase
biogas production.
Dynamic simulation runs from #1 to #6 are the trials for the optimization of the
startup:
Run #1 was conducted on a seed volume of 120 m3 with an F/M proportioned
sludge feed rate. No bicarbonate or scum was added. A selection of plots showing
VFA, gas flow rate, alkalinity, TSS, and pH of the dynamic simulation results are
shown as follows:
Figure 4.10 Run #1 simulation results of VFA
From Figure 4.10, the following conclusions can be made:
After April 16, seed was transferred into the digester. This resulted in a linear
increase in the VFA predicted by Run #1. On April 27, the VFA reached a peak
value of 175 mg/L. This value is in the range of 100 mg/L to 300 mg/L and even
lower than 200 mg/L. This provides very good startup performance.
After April 27, the value of VFA (Run #1) decreased to a value between 80 mg/L
and 200 mg/L for the remainder of the run. This value of VFA is optimal for
biogas production.
Digester VFA
Run # 1 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
g/L
)
600
500
400
300
200
100
0
59
Figure 4.11 Run #1 simulation results of gas flow rate
From Figure 4.11, the following conclusions can be made:
After the seed transfer on April 16, it took 79 days (April 16 to July 4) for Run #1
to obtain over 2000 m3/d of biogas production based on the F/M proportioned
sludge feed rate. The maximum feed volume reached was 275 m3.
After July 4, the feed rate was maintained at a constant maximum rate of 275 m3.
Soon after, a maximum biogas production of 3400 m3/d was achieved (Run #1).
However, following this peak, the biogas production suddenly decreased. This
was most likely caused by excessive feed which led to acid buildup and death for
a significant portion of the methanogenic population. The loss of methanogens
reduced the amount of sludge digested, which in turn reduced biogas production.
However, the methanogenic population can recover during operation. On July 20,
the biogas production increased to 3000 m3/d and then stabilized over the
remainder of the run. This indicated at least partial recovery and stabilization of
the methanogenic population.
Digester 2 gas flow rate
Run # 1 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
GA
S F
LO
W R
AT
E (
DR
Y)
(m3
/d)
5,000
4,500
4,000
3,500
3,000
2,500
2,000
1,500
1,000
500
0
60
Figure 4.12 Run #1 simulation results of alkalinity
From Figure 4.12, the following conclusions can be made:
From the beginning to the end of Run #1, alkalinity gradually increased up to
July 30, when it began to level off and stabilize.
Because no bicarbonate was added during Run #1, the bicarbonate value did not
suddenly increase in concentration on May 18 like the base case.
Likewise, there was no scum addition after August 28 during Run #1. For this
reason, the predicted alkalinity values are lower than the base case.
Figure 4.13 Run #1 simulation results of TSS
Digester 2 Alkalinity
Run # 1 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
mo
l/L
)
45
40
35
30
25
20
15
10
5
0
Digester 2 TSS
Run # 1 Base case1
0/1
/20
12
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
gT
SS
/L)
22,000
20,000
18,000
16,000
14,000
12,000
10,000
8,000
6,000
4,000
2,000
0
61
From Figure 4.13, the following conclusions can be made:
Total suspended solids can be used as an indicator of biomass production. The
decrease in TSS observed in Run #1 during July 12 to July 20 was caused by the
death of a significant portion of the methanogenic population. The result of this
die-off, directly impacted biomass concentration and TSS. However, data
observed on later dates indicate recovery and stabilization of the methanogenic
population.
The trends observed in the model prediction of TSS are similar to the trends
observed in the model prediction of biogas generation. This is because the amount
of biomass in the digester directly affects biogas production.
Overall, Run #1 of the dynamic simulation, with a seed volume of 120 m3 and an
optimized sludge feed rate (based on F/M), provided very good startup performance
relative to the base case.
Run #4 was conducted on a seed volume of 120 m3 with a flow proportioned
sludge feed rate. No bicarbonate or scum was added during this run. The dynamic
simulation results are shown in Figures 4.14 to 4.17.
Figure 4.14 Run #4 simulation results of VFA
Digester VFA
Run # 4 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
g/L
)
600
500
400
300
200
100
0
62
It was found from Figure 4.14 that the predicted values for VFA at the beginning
of startup were around 120 mg/L. This ensured a very well controlled startup
performance. The values remained within the range of 80 mg/L and 200 mg/L for the
remainder of the run. These values are optimal for providing maximum biogas
production.
Figure 4.15 Run #4 simulation results of gas flow rate
Figure 4.15 resembles the biogas production predicted during Run #1. After the
seed transfer on April 16, it took 76 days (April 16 to July 1) for Run #4 to obtain 2000
m3/d of biogas production based on the flow proportioned sludge feed rate. The
maximum volume of feed reached was 266 m3. After July 1, the feed rate was maintained
constant at the maximum rate, and the digester soon achieved its maximum biogas
production of 3400 m3/d (Run #4). However, the biogas production suddenly decreased
due to over feeding which produced excessive acid accumulation and a reduction in the
Digester 2 gas flow rate
Run # 4 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
GA
S F
LO
W R
AT
E (
DR
Y)
(m3
/d)
5,000
4,500
4,000
3,500
3,000
2,500
2,000
1,500
1,000
500
0
63
methanogenic population. The methanogenic population recovered within one month,
and on July 20, biogas production increased to 3000 m3/d and then became stable.
Figure 4.16 Run #4 simulation results of alkalinity
From Figure 4.16, it was observed that alkalinity gradually increased up to July
30. After this time, the values of Run #4 stabilized. There was no scum addition after
August 28 during Run #4. As a result, the alkalinity values were lower during this time
compared to the base case.
Figure 4.17 Run #4 simulation results of TSS
Digester 2 Alkalinity
Run # 4 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
mo
l/L
)
45
40
35
30
25
20
15
10
5
0
Digester 2 TSS
Run # 4 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
gT
SS
/L)
22,000
20,000
18,000
16,000
14,000
12,000
10,000
8,000
6,000
4,000
2,000
0
64
From Figure 4.17, it was found that the reduction in TSS during Run #4, from
July 12 to July 20, was caused by the death of a significant portion of the methanogenic
population. The result of this die-off was a reduction in the amount of biomass observed
in the digester. The trend for the model predicted TSS values are similar to the trend of
the predicted biogas values. This is because the amount of biomass in the digester affects
the amount of biogas produced.
From Run #1 and Run #4, it can be found that a seed volume of 120 m3, with the
two developed sludge feed rate strategies, provided ideal startup performance. As such, it
was not necessary to conduct a dynamic simulation for seed volumes higher than 120 m3,
since high seed volumes are undesirable.
The following conclusions are drawn from the dynamic simulation Run #1 and
Run #4:
1. Both sludge feed rate (F/M proportioned and flow proportioned) provided good
startup performance.
2. An equation was developed for to calculate the sludge feed rate during the startup
period for a sludge seed volume of 120 m3. The feed rate in this equation is
proportionate to F/M:
Y = 0.008X3 - 0.0262X
2 +0.6537X + 7.6413, R
2 = 0.9984 (4.1)
The sludge feed rate cannot exceed maximum sludge feed rate (
to
prevent washout of methanogenic bacteria. The SRTmin defined in this study is 12
days.
Equation 4.2 describes the food to mass regression (F/Mregression) ratio that took
into consideration food to mass for feeding which was developed based on the
65
Regina WWTP. This equation was used to calculate the sludge feed rate further to
develop Equation 4.1.
Y = 0.0549X2 - 8.0382X + 329, R
2 = 1 (4.2)
3. The flow proportioned feed rate during startup at the Regina WWTP can be
determined by two equations:
Y1 = 0.751X + 1.7273 (4.3)
Y2 = 7.6X - 311.6 (4.4)
As such, the sludge feed rate cannot exceed maximum sludge feed rate that is
. The SRTmin defined in this study is 12 days.
4. For WWTPs transferring seed sludge from adjacent digesters, the minimum
amount of seed sludge that would allow the maximum feed rate is about half of
the normal total solids concentration in the digester. This means that the required
amount of seed sludge is 50% of the digester capacity.
4.2.2 Optimization of Seed Sludge
The amount of initial seed sludge affects the digester startup performance. In this
research, different initial seed volumes were selected with different sludge feed rates to
develop a correlation between the amount of seed volume versus sludge feed rate. The
F/M proportioned and flow proportioned sludge feed rates were developed based on a
seed volume of 120 m3. But a seed volume 40 m
3 and 80 m
3 were also used in dynamic
simulations with the two developed sludge feed rate strategies for the purpose of
selecting the most cost-effective seed volume. The results of using a seed volume of 120
m3 have been presented above. The follow section will present the dynamic simulation
results when a seed volume of 80 m3 and 40 m
3 are used.
66
Run #2 was conducted using a seed volume of 80 m3 with a F/M proportioned
sludge feed rate. No bicarbonate or scum was added during this run. The dynamic
simulation results are shown in Figure 4.18 to 4.21.
Figure 4.18 Run #2 simulation results of VFA
From Figure 4.18, it can be seen that the VFA values during the first startup
period (April 16 to May 7) reached a peak value of 240 mg/L. However, the VFA
concentration did not exceed the VFA maximum value of 300 mg/L. Therefore, a seed
volume of 80 m3 with an F/M proportioned sludge feed rate can be implemented during
digester startup. After May 7, the VFA values remained between 80 mg/L to 180 mg/L
which yielded high amounts of biogas.
Figure 4.19 presents the gas flow rate over time. The amount of biogas predicted
closely resembles Run #1, because the feed rate is the same and the VFA concentrations
were within the optimal operating range. From Figure 4.20 and Figure 4.21, it was found
that the predicted alkalinity and TSS values had no significant deviations from the results
generated in Run #1.
Therefore, the F/M proportioned sludge feed rate developed on a seed volume of
120 m3 closely resembles the dynamic simulation using a seed volume of 80 m
3.
Digester VFA
Run # 2 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
g/L
)
600
500
400
300
200
100
0
67
Figure 4.19 Run #2 simulation results of gas flow rate
Figure 4.20 Run #2 simulation results of alkalinity
Figure 4.21 Run #2 simulation results of TSS
Digester 2 gas flow rate
Run # 2 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
GA
S F
LO
W R
AT
E (
DR
Y)
(m3
/d)
5,000
4,500
4,000
3,500
3,000
2,500
2,000
1,500
1,000
500
0
Digester 2 Alkalinity
Run # 2 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
mo
l/L
)
45
40
35
30
25
20
15
10
5
0
Digester 2 TSS
Run # 2 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
gT
SS
/L)
20,000
15,000
10,000
5,000
68
Run #3 was conducted on a seed volume of 40 m3 with an F/M proportioned
sludge feed rate. Bicarbonate was added but scum was not added. The dynamic
simulation results are shown in Figures 4.22 to 4.26:
Figure 4.22 Run #3 simulation results of VFA
Figure 4.23 Run #3 simulation results of gas flow rate
An additional run using the same parameters as Run #3 was conducted, but
without the addition of bicarbonate. In this run, the VFA values increased linearly to
Digester VFA
Run # 3 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
g/L
)
600
500
400
300
200
100
0
Digester 2 gas flow rate
Run # 3 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
GA
S F
LO
W R
AT
E (
DR
Y)
(m3
/d)
5,000
4,500
4,000
3,500
3,000
2,500
2,000
1,500
1,000
500
0
69
4000 mg/L before plateauing. The pH values decreased to below 5.0 and did not recover.
These predicted values were far beyond the ranges required for a successful startup.
Therefore, the bicarbonate addition was needed for optimal performance.
With the addition of bicarbonate, Figure 4.22 shows that during the first startup
period (April 16 to May 7), a maximum VFA value of 320 mg/L was reached on April
30. This value exceeds the maximum value of 300 mg/L. A VFA concentration in excess
of 300 mg/L requires a reduction or stoppage in the sludge feed rate. Although
bicarbonates had been added and the alkalinity and pH values were optimized, from April
25 to May 14 (Figure 4.24 and 4.26), the alkalinity and pH rapidly increased. The
addition of bicarbonate cannot be used to bring the VFA value under 300 mg/L. Finally,
the F/M proportioned sludge feed rate developed using a seed volume of 120 m3 does not
fit with the values predicted using a seed volume of 40 m3. Thus, a slower and smaller
sludge feed rate was required for a seed volume of 40 m3. This results in a longer startup
time for a seed volume of 40 m3 compared to a seed volume of 80 m
3 or 120 m
3.
Figure 4.24 Run #3 simulation results of alkalinity
Digester 2 Alkalinity
Run # 3 Base case1
0/1
/20
12
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
mo
l/L
)
45
40
35
30
25
20
15
10
5
0
70
Figure 4.25 Run #3 simulation results of TSS
Figure 4.26 Run #3 simulation results of pH
Run #5 was conducted on a seed volume of 80 m3 with a flow proportioned
sludge feed rate. No bicarbonate or scum was added during this run. The dynamic
simulation results are shown in Figures 4.27 to 4.30:
Figure 4.27 Run #5 simulation results of VFA
Digester 2 TSS
Run # 3 TS (actual)
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
gT
SS
/L)
20,000
15,000
10,000
5,000
0
Digester 2 pH
Run # 3 Base case
DATE
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
pH
7.0
6.0
Digester 2 VFA
Run # 5 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
g/L
)
600
500
400
300
200
100
0
71
From Figure 4.27, it can be seen that the VFA predicted values during the first
startup period (April 16 to May 7) achieved 200 mg/L. During the remainder of the run,
the VFA concentration did not exceed the VFA maximum value of 300 mg/L. Therefore,
a seed volume of 80 m3 with a flow proportioned sludge feed rate can yield a successful
digester startup. After May 7, the VFA values remained between 80 to 180 mg/L and
high amounts of biogas were predicted. Figure 4.19 presents the gas flow rate. The
amount of biogas production closely resembles Run #4, because it possesses the same
sludge feed rate and similar VFA values. From Figure 4.20 and Figure 4.21, it was found
that the model prediction alkalinity and TSS values had no significant deviations from the
values predicted during Run #4.
Therefore, the flow proportioned sludge feed rate developed on a seed volume of
120 m3 is in agreement with the values predicted using a seed volume of 80 m
3.
Figure 4.28 Run #5 simulation results of gas flow rate
Digester 2 gas flow rate
Run # 5 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
GA
S F
LO
W R
AT
E (
DR
Y)
(m3
/d)
5,000
4,500
4,000
3,500
3,000
2,500
2,000
1,500
1,000
500
0
72
Figure 4.29 Run #5 simulation results of alkalinity
Figure 4.30 Run #5 simulation results of TSS
Run #6 was conducted on a seed volume of 40 m3 with a flow proportioned
sludge feed rate. Bicarbonate was added but scum was not added. The dynamic
simulation results are shown in Figures 4.31 to 4.35.
An additional run using the same parameters as Run #6 was conducted, but
without the addition of bicarbonate. In this run, the VFA values increased linearly to
4000 mg/L before plateauing. The pH values decreased to below 5.0 and did not recover.
These predicted values were far beyond the ranges required for a successful startup.
Therefore, bicarbonate addition was needed for optimal performance.
Digester 2 Alkalinity
Run # 5 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
mo
l/L
)
45
40
35
30
25
20
15
10
5
0
Digester 2 TSS
Run # 5 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
gT
SS
/L)
22,000
20,000
18,000
16,000
14,000
12,000
10,000
8,000
6,000
4,000
2,000
0
73
Figure 4.31 Run #6 simulation results of VFA
Figure 4.32 Run #6 simulation results of gas flow rate
Figure 4.33 Run #6 simulation results of alkalinity
Digester 2 VFA
Run # 6 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
g/L
)
600
500
400
300
200
100
0
Digester 2 gas flow rate
Run # 6 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
GA
S F
LO
W R
AT
E (
DR
Y)
(m3
/d)
5,000
4,500
4,000
3,500
3,000
2,500
2,000
1,500
1,000
500
0
Digester 2 Alkalinity
Run # 6 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
mo
l/L
)
45
40
35
30
25
20
15
10
5
0
74
With the addition of bicarbonate, Figure 4.31 shows that during the first startup
period (April 16 to May 7), a maximum VFA value of 360 mg/L was obtained. This
value exceeded the maximum value of 300 mg/L, meaning that a reduction or stoppage in
sludge feed was needed. Although bicarbonates had been added to optimize the alkalinity
and pH values, from April 28 to May 17 (Figure 4.33 and 4.35), the alkalinity and pH
values rapidly increased. The biogas and TSS predicted values matched well to the actual
measured values. It was determined that the addition of bicarbonate could not reduce the
VFA value below 300 mg/L. Finally, the flow proportioned sludge feed rate developed
using a seed volume of 120 m3 does not fit with the values predicted using a seed volume
of 40 m3. Thus, a slower and smaller sludge feed rate was required for a seed volume of
40 m3 compared to a seed volume of 80 m
3 or 120 m
3.
Figure 4.34 Run #6 simulation results of TSS
Figure 4.35 Run #6 simulation results of pH
Digester 2 TSS
Run # 6 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
CO
NC
. (m
gT
SS
/L)
22,000
20,000
18,000
16,000
14,000
12,000
10,000
8,000
6,000
4,000
2,000
0
Digester 2 pH
Run # 6 Base case
10
/1/2
01
2
9/2
4/2
01
2
9/1
7/2
01
2
9/1
0/2
01
2
9/3
/20
12
8/2
7/2
01
2
8/2
0/2
01
2
8/1
3/2
01
2
8/6
/20
12
7/3
0/2
01
2
7/2
3/2
01
2
7/1
6/2
01
2
7/9
/20
12
7/2
/20
12
6/2
5/2
01
2
6/1
8/2
01
2
6/1
1/2
01
2
6/4
/20
12
5/2
8/2
01
2
5/2
1/2
01
2
5/1
4/2
01
2
5/7
/20
12
4/3
0/2
01
2
4/2
3/2
01
2
4/1
6/2
01
2
pH
7.0
6.0
75
Overall, it can be concluded from Runs #1 to #6 that a seed volume of 120 m3
can
be replaced by a seed volume of 80 m3 in conjunction with the developed sludge feed rate
strategies. But a seed volume of 40 m3 with the developed sludge feed rate strategies and
even adding bicarbonate did not work well. Therefore, a seed volume of 80 m3 with
either F/M or flow proportioned sludge feed rates, even without bicarbonate addition, can
achieve the objectives of a timely, cost-effective, and successful startup.
4.2.3 Optimization of Bicarbonate Concentration
Optimization of digester startup performance by using bicarbonate to maintain pH
and increase alkalinity is implemented in WWTPs. In fact, the amount of bicarbonate
added must be considered in the development of startup strategies. If the pH drops below
6.3, the digester cannot properly cultivate microorganisms (Filbert, 2012). Therefore,
bicarbonate addition is needed. Creating an alkaline environment helps prevent acidic pH
values and maintains normal operation.
Sodium bicarbonate was used by the Regina WWTP to increase pH and
alkalinity. Sodium bicarbonate is highly soluble and will not create a solids deposition
problem since there is no CO2 uptake with its addition; therefore creation of a vacuum is
not possible. The sodium bicarbonate used at the Regina WWTP is 200 lbs/bag (91
kg/bag, 0.25m3).
Based on Run #3 and Run #6, the amount of bicarbonate to be added was
determined to be 1 lb (454 g) sodium bicarbonate per 10 m3 of digester volume.
4.3 Development of Strategies for Optimal Digester Startup
The follow section presents a set of general rules for optimal startup of an
anaerobic digester fed with primary sludge. These rules are based on the advantages of
76
the above simulations, sludge feed rate strategies, proper seed volume, and bicarbonate
concentration.
1. For general WWTPs, the calculation of sludge feed rate during the startup period
is shown in Equation 4.5:
(4.5)
Where, Feed = sludge feed rate each day during digester startup, m3/d.
F/Mreg.= food to mass regression ratio (F/Mregression).
Mass = mass of biological solids synthesized daily, kg/d.
TSPS = Total solids in primary sludge, usually 35 kg/m3.
2. For WWTPs that hauling seed sludge from other plants, the initial amount of seed
sludge is: , m3. (4.6)
3. According to flow proportion feed rate, the sludge feed rate can be increased daily
with the maximum rate increase up to 8% of the previous day’s sludge feed rate
when one of the following conditions occurs: 1) after 45 days of the startup, 2)
when the total solids concentration in the digester reaches about 0.5%, 3) when
the biogas production reaches one third of its normal value. The 8% of feed rate
increase is related to 1/SRTmin. The SRTmin defined in this study is 12 days.
4. For WWTPs transferring seed sludge from adjacent digesters, the minimum
amount of seed sludge that would allow the maximum feed rate is about half of
the normal total solids concentration in the digester. This means that the required
amount of seed sludge is 30% of the digester capacity.
m3 (4.7)
77
5. For WWTPs that cannot afford to transfer or haul large amounts of seed sludge,
the addition of sodium bicarbonate is recommended during the initial stage of the
startup, before pH drops below 6.3. The recommended amount of bicarbonate
addition is:
. (4.8)
6. Gas production can be increased by the addition of scum after the digester has
reached its maximum design feed rate. The scum has a high methane value with a
very low hydraulic rate that provided additional substrate for digestion to promote
greater gas production.
5.0 CONCLUSIONS
This study demonstrated that it is feasible to predict the performance of an
anaerobic digester during startup using an Anaerobic Digestion Model implemented in
BioWinTM
. The BioWinTM
model was calibrated using actual anaerobic digester
performance data from the Regina WWTP for steady state during normal operation and
dynamic state during startup. The BioWinTM
model was used to compute five operating
trends for the following parameters: VFA, pH, alkalinity, digester solids concentration,
and biogas production. These trends provided detailed information about the operation of
the digester during startup and were invaluable in the development of general strategies
for successfully starting up a new or existing anaerobic digester.
The real potential of the BioWinTM
model lies in its capability to provide detailed
information on how to start up a digester in a short amount of time with low cost relative
to alternative experimental approaches such as bench-scale tests. The BioWinTM
model is
advantageous because it allows engineers and plant operators to: (1) identify the best
course of action to start up the digester; (2) reduce the probability of selecting startup
78
conditions that could lead to the development of excessive volatile acids; (3) reduce the
amount of time before consistent biogas production can be achieved; (4) speed up the
evaluation time of digester startup strategies; and (5) tailor startup strategies for unique
sludge characteristics or digester configurations.
The BioWinTM
model was used to provide a better understanding of the effect of
various parameters on the performance of the digester during the startup process. When
attempting to reduce the startup time, three parameters should be carefully considered:
the amount of seed sludge, the primary sludge feed rate, and the addition of pH control
agents. Using high seed sludge amount and low primary sludge feed rates reduces the
likelihood of developing acidic conditions. This is beneficial since the development of
acidic conditions can negatively impact the digester for as long as six to eight weeks.
Using a pH control agent, such as bicarbonate, provides buffering capacity to maintain
the volatile acid to alkalinity ratio to a level suitable for the growth of methanogens. The
addition of bicarbonate reduces the seed sludge volume requirement as well as the need
for a high primary sludge feed rate. However, the bicarbonate dose requires careful
calculation to ensure that sufficient alkalinity is added to the digester.
For WWTPs with limited seed sludge available, either due to poor quality sludge
from adjacent digesters or relatively long hauling distances from another location, plant
operators face a significant challenge in determining a suitable startup strategy that will
allow for a successful startup of the digester in a short period of time while maintaining
the volatile acid to alkalinity ratio to within acceptable levels.
This study has identified cost-effective strategies for the startup of an anaerobic
digester fed with primary sludge. These strategies are summarized as follows:
79
For WWTPs hauling seed sludge from a relatively distant plant, the minimum
amount of seed sludge is 2% of the digester volume (
m3). The primary sludge feed rate should be proportional to the food to
biomass ratio given in Equation 4.5. This combination allows the digester to start
up without exceeding the acceptable level of volatile acids.
The sludge feed rate can be increased daily up to a maximum rate increase of 8%
of the previous day’s sludge feed rate under the following conditions: (1) 45 days
have elapsed since startup; (2) the total solids concentration in the digester has
reached about 0.5%; and (3) the biogas production has reached one third of its
normal value. The 8% feed rate increase is related to 1/SRTmin. The SRTmin
defined in this study was 12 days.
The sludge feed rate cannot exceed the maximum sludge feed rate, otherwise the
methanogenic bacteria may be washed out of the digester. The maximum sludge
feed rate was determined by the volume of the digester divided by the SRTmin.
For WWTPs transferring seed sludge from adjacent digesters, the minimum
amount of seed sludge that would allow the maximum feed rate is about half of
the normal total solids concentration in the digester. This means that the required
amount of seed sludge is 30% of the digester’s capacity.
For WWTPs that cannot afford to transfer or haul large amounts of seed sludge,
the addition of sodium bicarbonate is recommended during the initial stage of
startup (i.e. before a pH drop below 6.3 has been observed). The recommended
amount of bicarbonate addition is 45 g per cube meter of digester volume per day.
80
Early and consistent gas production can be achieved if the above listed guidelines
are followed. Gas production can be increased by the addition of scum after the
digester has reached its maximum design feed rate. This is because scum has a
high methane value with a very low hydraulic rate.
The calibrated and validated BioWinTM
model can be used by any WWTP to
determine the most cost-effective startup strategy that can produce stable digester
operation within a short time span with rapid biogas production. The ability of the
BioWinTM
model to produce accurate predictions of the parameters used for the startup
depends on the correct specification of the wastewater fractions and kinetic parameters.
This research has identified the factors that have significant effects on the predicted gas
production or volatile solids reduction. These factors are: Fxsp, Fup, Fna, the acetoclastic
Mu Max of methanogens, and the acetoclastic decay rate of methanogens. The study also
demonstrated that the accuracy of the BioWinTM
model depends on properly setting the
wastewater characteristics for the following streams: digester filling, seed sludge, scum,
and bicarbonate. Overall, the developed strategies reduced the digester startup time and
costs, while simultaneously reducing the amount of time needed to begin methane gas
production. As such, this model may provide significant economic and environmental
benefits, especially for WWTPs currently facing sludge digestion problems, limited
sludge treatment capacities, and low methane gas production.
It should be emphasized that the above conclusions are limited to anaerobic
digesters fed with primary sludge. The results may be extrapolated to include anaerobic
digesters fed with waste activated sludge or a mixture of primary and waste activated
81
sludge. However, in these cases, careful consideration should be given to the sludge feed
rate.
6.0 RECOMMENDATIONS
Recommendations for further research include the following:
1. To conduct a sensitivity analysis to verify which model parameters used for
calibration most significantly affect model performance.
2. To conduct bench-scale experiments to verify the composition of the wastewater
fractions used in the BioWinTM
model.
3. To conduct a dynamic simulation of an anaerobic digester with scum added to the
feed influent to maximize biogas production.
4. To develop a built-in BioWinTM
Activated Sludge/Anaerobic Digestion Model for
an anaerobic digester fed with either activated sludge alone or a mixture of
primary sludge and activated sludge.
5. To verify the built-in BioWinTM
Activated Sludge/Anaerobic Digestion Model by
pilot testing it at a WWTP where activated sludge is used for digester feed.
82
REFERENCES
Abbasi, T., Tauseef, S.M., & Abbasi, S.A. (2012). A brief history of anaerobic digestion
and "biogas". SpringerBriefs in environmental science 2 (pp. 11-23). New York,
NY: Springer. doi: 10.1007/978-1-4614-1040-9_2
Batstone, D.J., Keller, J. (2003). Industrial applications of the IWA anaerobic digestion
model No. 1 (ADM1). Water Science and Technology, 47 (12), 199-206.
Batstone, D.J., Keller, J., Angelidaki, I., Kalyuzhnyi, S.V., Pavlostathis, S.G., Rozzi,
A.,... Vavilin, V. A. (2002). The IWA anaerobic digestion model No.1 (ADM1).
Water Science and technology, 45(10), 65-73.
Batstone, D.J., Tait, S., & Starrenburg, D. (2009). Estimation of hydrolysis parameters in
full-scale anaerobic digesters. Biotechnology and Bioengineering, 102 (5), 1513-
1520.
Boltes, K., Leton, P. & Garcia-Calvo, E. (2008). Volatile fatty acid anaerobic
degradation: Kinetic modeling with an inoculum under controlled conditions.
Industrial and Engineering Chemistry Research, 47(15), 5337-5345.
Chawla OP (1986). Advances in biogas technology. Publications and Information
Division, Indian Council of Agricultural Research, New Delhi.
Chen, Q. (2010). Kinetics of anaerobic digestion of selected C1 to C4 organic acids.
(Master's thesis). University of Missouri, Columbia.
City of regina,1994. Wastewater treatment facilities operations and maintenance manual.
de Baere, L. A., Mattheeuws, B., & Velghe, F. (2010). State of the art of anaerobic
digestion in Europe. 12th World Congress on Anaerobic Digestion (AD12),
Guadalajara, Mexico, October 31st to November 4th, 2010. Retrieved from
83
http://www.dakofa.dk/Aktiviteter/konferencer_seminarer/120207/Materiale/1415,
%20Bruno%20Mattheeuws.pdf on Dec. 6, 2013.
Donoso-Bravo, A., Mailierm J., Martin, C., Rodriguez, J., Acevec-Lara, C.A., &
Wouwer, A.V. (2011). Model selection, identification and validation in anaerobic
digestion: a review. Water research, 45,5347-5364.
Dursun, D., Jimenez, J., & Bratny, J. (2011). Whole plant modeling to optimize the
biogas production in anaerobic digesters. Energy and Water. Retrieved from
Water Environment Federation database.
EnviroSim Associates Ltd. Advanced topics with BioWin. Flamborough, Ontario:
EnviroSim Associates Ltd.
EnviroSim Associates Ltd. Introductory topics with BioWin. Flamborough, Ontario:
EnviroSim Associates Ltd.
EnviroSim Associates Ltd. User Manual for BioWin 3. Flamborough, Ontario:
EnviroSim Associates Ltd.
Filbert, J.W. (2012). Produces and problems of digester startup. Water Pollution Control
Federation, 39(3), 367-372.
Flotats, X., Ahring, B.K., & Angelidaki, I. (2003). Parameter identification of
thermophilic anaerobic degradation of valerate. Applied Biochemistry and
Biotechnology, 109, (1-3), 47-62.
Hill, D.T. (1982). A comprehensive dynamic model for animal waste methanogenesis.
Transactions of the ASAE, 25 (5), 1374-1380.
Hill, D.T., & Barth, C. (1977). A dynamical model for simulation of animal waste
digestion. Journal of Water Pollution Control Association, 10, 2129-2143.
84
Jones, R., Parker, W., Zhu, H., Houweling, D., & Murthy, S. (2008). Predicting the
degradability of waste activated sludge. Water Environment Research: a Research
Publication of the Water Environment Federation, 81(8), 765-771.
Kalfas, H., Skiadas, I.V., Gavala, H.N., Stamatelatou, K., & Lyberatos, G. (2006).
Application of ADM1 for the simulation of anaerobic digestion of olive pulp
under mesophilic and thermophilic conditions. Water Science and Technology, 54
(4), 149-156.
Koch, K., Lubken, M., Gehring, T., Wichern, M., & Horn, H. (2010). Biogas from grass
silage-measurements and modeling with ADM1. Bioresource Technology, 101
(21), 8158-8165.
Lauwers, J., Apples, L., Thompson, I.P., Degreve, J., Impe, J.F.V., Dewil, R. (2013).
Mathematical modeling of anaerobic digestion of biomass and waste: power and
limitations. Progress in Energy and Combustion Science, 39, 383-402.
doi: 10.1016/j.pecs.2013.03.003
Liwarska-Bizukojc, E., Biernacki, R. (2010). Identification of the most sensitive
parameters in the activated sludge model implemented in BioWin software.
Bioresource Technology, 101, 7278-7285. doi: 10.1016/j.biortech.2010.04.065
Manea, E., Ronescu, D. N., Manea, D., & Robescu, D. L. (2012). Parameter influence on
the anaerobic digestion kinetics. UPB Scientific Bulletin Series D, 74, 219-226.
McCarty, P.L. & Mosey, F.E. (1991). Modelling of anaerobic digestion processes (a
discussion of concepts). Water Science and Technology, 24(8), 17-33.
McCarty, P.L. (1982). One hundred years of anaerobic treatment. In: Hughes DE,
Stafford DA, Wheatley BI et al (eds) Anaerobic digestion, 1981: proceedings of
85
the second international symposium on anaerobic digestion. Elsevier Biomedical,
Amsterdam, pp 3-22.
Melcer, H., Dold, P.L., Jones, R.M., Bye, C.M., Takacs, I., Stensel, H.D.,... Bury, S.
(2003). Methods for Wastewater Characterization in Activated Sludge Modeling.
Water Environment Research Foundation. Retrieved from
https://docs.google.com/file/d/0B8OWJ6fFTTdpOFFMQW15YzdsSW8/edit?pli=
1 on Nov.12, 2013.
Muller, C., Dursan, D., Merlo, R., Krugel, S., Ekster, A., & Yerrapotu, B. (2011).
Deriving more information from volatile solids data. Residuals and Biosolids.
Proceedings of the Water Environment Federation, Residuals and Biosolids,
2011, pp. 364-380(17).
Oh, S.E., Van Ginkel, S. &Logan, B.E. (2003). The Relative Effectiveness of pH Control
and Heat Treatment for Enhancing Biohydrogen Gas Production. Environmental
Science and Technology, 37(22), 5186-5190.
Palatsi, J., Illa, J., Prenafeta-Boldu, F.X., Laureni, M., Fernandez, B., Angelidaki, I., &
Flotats, X. (2010). Long-chain fatty acids inhibition and adaptation process in
anaerobic thermophilic digestion: batch tests, microbial community structure and
mathematical modelling. Bioresource Technology, 101 (7), 2243-2251.
Parker, W. Jones, R., Zhu, H., Houweling, D., Murthy, S., & Rupke, M. (2008). Tools for
modeling sludge digestibility. Proceedings of the Water Environment Federation,
Residuals and Biosolids, 2008, pp. 10-23(14).
86
Parker, W.J., Jones, R.M., & Murthy, S. (2008). Characteristics of the COD/VSS ratio
during anaerobic digestion of waste activated sludge: experimental and modeling
studies. Water Environment Federation, WEFTEC, 2008, pp. 524-533.
Parker, W.J., Jones, R.M., Murthy, S & Rupke, M. (2007). Modeling anaerobic digestion
of municipal wastewater sludge: an elemental approach. Water Environment
Federation, WEFTEC, 2007, pp. 1450-1459.
Parkin, G. & Owen, W.F. (1986). Fundamentals of anaerobic digestion of wastewater
sludges. Journal of Environmental Engineering, 112(5), 867-920.
Petersen, B., Gernaey, K., Henze, M., Vanrolleghem, P.A., 2003. Calibration of activated
sludge models: a critical review of experimental designs. In: Agathos, S.N.,
Reineke, W. (Eds.), Biotechnology for the Environment: Wastewater Treatment
and Modelling. Waste Gas Handling. Kluwer Academic Publishers, Dordrecht.
Rittmann, B.E., McCarty, P.L. (2001). Environmental Biotechnology: Principles and
Applications . New York, NY.
Shin, H.S., Kim, S.H., Lee, C.Y. &Nam, S.Y. (2003). Inhibitory effects of long-chain
fatty acids on VFA degradation and β-oxidation. Water Science and Technology,
47(10), 139-146.
The Regina WWTP - Sewage works annual summary 2007. Regina Wastewater
Treatment Plant.
Tchobanoglous, G., Burton, F.L., & Stensel, H.D. (2003). Wastewater Engineering:
Treatment and Reuse, 4th Ed. New York, NY: Metcalf & Eddy, Inc.
Technical Practice Committee (2012). Anaerobic sludge digestion - MOP16. Water
Pollution Control Federation, 38(12), 1925-1943.
87
URS Corp. (2009). FOG control & beneficial reuse: a case study in San Francisco. URS
Corporation. Retrieved from
http://pprc.org/browngreasesymposium/docs/Presentations/URS_Presentation_15
APR09.pdf on Sept. 15, 2013.
Van Lier, J.B. (2008). High-rate anaerobic wastewater treatment: diversifying from end-
of-the-pipe treatment to resource-oriented conversion techniques. Water Science
and Technology, 57 (8), 1137-1148.
88
APPENDIX A
Field Data from the Regina WWTP for Calibration
Table A-1: Raw influent variable for calibration - July, 2007
Day Flow m3/d
Total COD
mgCOD/L
TKN
mgN/L
Total P
mgP/L
Nitrate N
mgN/L pH
Alkalinity
mmol/L
Inorganic
S.S. mgISS/L
Calcium
mg/L
Magnesium
mg/L
DO
mg/L
1-Jul 5.99E+04 4.53E+02 34.6 5.53 7.79 7.53 5 44 79 29 0
2-Jul 5.73E+04 5.12E+02 34.6 5.47 7.79 7.82 5 34 79 29 0
3-Jul 6.68E+04 4.53E+02 34.6 5.53 7.79 7.53 5 44 79 29 0
4-Jul 6.77E+04 4.56E+02 34.6 5.49 7.79 7.54 5 44 79 29 0
5-Jul 6.80E+04 4.30E+02 34.6 5.37 7.79 7.5 5 34 79 29 0
6-Jul 6.94E+04 4.53E+02 34.6 5.53 7.79 7.53 5 44 79 29 0
7-Jul 6.70E+04 4.53E+02 34.6 5.53 7.79 7.53 5 44 79 29 0
8-Jul 6.56E+04 3.79E+02 34.6 5.25 7.79 7.58 5 24 79 29 0
9-Jul 6.57E+04 4.86E+02 34.6 5.74 7.79 7.54 5 36 79 29 0
10-Jul 7.02E+04 5.63E+02 37.1 5.54 7.79 7.55 5.12 60 76 32 0
11-Jul 6.64E+04 5.12E+02 34.6 6.02 7.79 7.51 5 38 79 29 0
12-Jul 3.75E+04 3.07E+02 34.6 5.1 7.79 7.54 5 96 79 29 0
13-Jul 3.72E+04 4.53E+02 34.6 5.53 7.79 7.53 5 44 79 29 0
14-Jul 6.49E+04 4.53E+02 34.6 5.53 7.79 7.53 5 44 79 29 0
15-Jul 6.36E+04 4.71E+02 34.6 5.06 7.79 7.44 5 28 79 29 0
16-Jul 6.57E+04 5.02E+02 34.6 5.66 7.79 7.47 5 36 79 29 0
17-Jul 6.98E+04 4.53E+02 34.7 5.86 7.79 7.46 4.94 76 88 24 0
18-Jul 6.87E+04 4.53E+02 34.6 5.57 7.79 7.47 5 60 79 29 0
19-Jul 6.94E+04 4.40E+02 34.6 6.02 7.79 7.53 5 34 79 29 0
20-Jul 6.85E+04 4.53E+02 34.6 5.53 7.79 7.53 5 44 79 29 0
21-Jul 6.70E+04 4.53E+02 34.6 5.53 7.79 7.53 5 44 79 29 0
22-Jul 8.64E+04 4.25E+02 34.6 4.74 7.79 7.52 5 18 79 29 0
23-Jul 7.02E+04 3.84E+02 34.6 5.24 7.79 7.5 5 36 79 29 0
24-Jul 6.97E+04 4.30E+02 32 5.14 7.79 7.48 4.94 26 72 32 0
25-Jul 7.03E+04 4.15E+02 34.6 6.13 7.79 7.5 5 76 79 29 0
89
26-Jul 6.93E+04 5.17E+02 34.6 6.03 7.79 7.59 5 60 79 29 0
27-Jul 6.85E+04 4.53E+02 34.6 5.53 7.79 7.53 5 44 79 29 0
28-Jul 6.64E+04 4.53E+02 34.6 5.53 7.79 7.53 5 44 79 29 0
29-Jul 6.50E+04 4.30E+02 34.6 5.53 7.79 7.6 5 24 79 29 0
30-Jul 6.58E+04 5.27E+02 34.6 5.53 7.79 7.51 5 44 79 29 0
31-Jul 6.81E+04 4.61E+02 34.6 5.66 7.79 7.47 5 38 79 29 0
Table A-2: Scums 1 & 2 variable for calibration - July, 2007
Day
Scum 1
flow
m3/d
Scum 2
flow
m3/d
Total COD
mgCOD/L
TKN
mgN/L
Total P
mgP/L
Nitrate N
mgN/L pH
Alkalinity
mmol/L
Inorganic S.S.
mgISS/L
Calcium
mg/L
Magnesium
mg/L
DO
mg/L
1-Jul 11.42 11.84 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
2-Jul 8.57 7.67 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
3-Jul 11.60 13.89 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
4-Jul 8.34 7.91 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
5-Jul 17.12 16.50 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
6-Jul 8.57 7.29 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
7-Jul 8.56 11.06 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
8-Jul 8.56 7.82 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
9-Jul 7.03 6.53 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
10-Jul 13.05 13.54 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
11-Jul 9.62 9.31 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
12-Jul 8.34 8.57 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
13-Jul 2.03 2.59 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
14-Jul 5.71 5.49 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
15-Jul 11.46 9.54 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
16-Jul 13.74 13.78 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
17-Jul 17.71 18.25 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
18-Jul 20.01 20.91 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
19-Jul 22.71 20.79 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
20-Jul 22.16 22.85 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
21-Jul 6.99 8.57 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
22-Jul 28.32 28.59 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
23-Jul 3.49 2.85 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
90
24-Jul 9.06E 8.57 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
25-Jul 10.43 11.43 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
26-Jul 5.66 5.71 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
27-Jul 7.46 5.71 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
28-Jul 5.53 5.72 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
29-Jul 9.54 11.36 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
30-Jul 14.33 14.37 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
31-Jul 11.37 11.23 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
91
Table A-3: Sedimentation, splitter, gravity thickener and BFP variable for calibration -
July, 2007
Day Sedimentation
variable m3/d
Splitter ratio
variable m3/d
Gravity thickener underflow
variable m3/d
BFP (dewatering)
underflow m3/d
1-Jul 205 0.8211 80 16.4195
2-Jul 333 0.8153 54 12.3006
3-Jul 377 1.0693 91 18.5818
4-Jul 631 0.8687 78 15.1868
5-Jul 219 1.0352 75 14.1762
6-Jul 358 1.1163 86 16.1968
7-Jul 231 0.9892 0.5 0.0859
8-Jul 260 1.0112 81 15.3267
9-Jul 347 1.0293 76 9.2867
10-Jul 405 1.1492 77 9.8364
11-Jul 447 0.9665 0 0
12-Jul 334 0.9615 0 0
13-Jul 419 0.8936 0 0
14-Jul 151 1.0406 0.7 0.1436
15-Jul 193 0.9962 48 10.2291
16-Jul 232 1.0508 0 0
17-Jul 447 1.0920 80 17.0984
18-Jul 277 0.9718 86 18.4261
19-Jul 274 0.9060 93 18.6919
20-Jul 249 1.0753 0 0
21-Jul 854 1.0353 92 18.5206
22-Jul 173 1.0083 86 17.3108
23-Jul 387 0.9359 88 18.6025
24-Jul 274 1.0642 58 12.2983
25-Jul 430 0.9957 2 0.4449
26-Jul 209 0.9898 69 15.2662
27-Jul 216 0.9623 20 4.3537
28-Jul 226 1.0980 7 14.6016
29-Jul 405 1.0264 83 18.5062
30-Jul 530 0.9882 94 19.7588
31-Jul 192 1.0465 74 15.4899
92
APPENDIX B
Field Data from the Regina WWTP for Validation
Table B-1: Raw influent variable for validation - August, 2007
Day Flow m3/d
Total COD
mgCOD/L
TKN
mgN/L
Total P
mgP/L
Nitrate N
mgN/L pH
Alkalinity
mmol/L
Inorganic S.S.
mgISS/L
Calcium
mg/L
Magnesium
mg/L
DO
mg/L
1-Aug 6.86E+04 461 32.3 5.25 0.01 7.43 4.88 40 92 22 0
2-Aug 6.87E+04 497 32.3 5.64 0.01 7.5 4.88 34 92 22 0
3-Aug 6.73E+04 453 32.3 5.25 0.01 7.49 4.88 21 92 22 0
4-Aug 6.72E+04 453 32.3 5.25 0.01 7.49 4.88 9 92 22 0
5-Aug 6.28E+04 453 32.3 5.25 0.01 7.49 4.88 25 92 22 0
6-Aug 6.10E+04 532 34.6 5.03 0.01 7.31 4.88 74 92 22 0
7-Aug 1.03E+05 507 31.4 5.25 0.01 7.49 4.88 12 92 22 0
8-Aug 7.38E+04 410 32.3 5.25 0.01 7.41 4.88 26 92 22 0
9-Aug 7.26E+04 451 32.3 5.25 0.01 7.47 4.88 32 92 22 0
10-Aug 7.07E+04 453 32.3 5.25 0.01 7.49 4.88 183 92 22 0
11-Aug 8.33E+04 453 32.3 5.25 0.01 7.49 4.88 49 92 22 0
12-Aug 7.15E+04 456 32.3 5.25 0.01 7.5 4.88 28 92 22 0
13-Aug 7.21E+04 292 32.3 5.25 0.01 7.49 4.88 24 92 22 0
14-Aug 6.94E+04 453 32.3 5.25 0.01 7.43 4.88 41 92 22 0
15-Aug 6.75E+04 456 32.3 5.33 0.01 7.43 4.88 90 92 22 0
16-Aug 6.95E+04 492 32.3 5.25 0.01 7.49 4.88 28 92 22 0
17-Aug 6.95E+04 453 32.3 5.25 0.01 7.49 4.88 53 92 22 0
18-Aug 6.93E+04 453 32.3 5.25 0.01 7.49 4.88 87 92 22 0
19-Aug 7.27E+04 466 32.3 5.25 0.01 7.59 4.88 38 92 22 0
20-Aug 7.09E+04 497 32.3 5.29 0.01 7.56 4.88 46 92 22 0
21-Aug 7.33E+04 379 33 4.79 0.01 7.55 4.88 20 92 22 0
22-Aug 7.04E+04 453 32.3 5.35 0.01 7.56 4.88 41 92 22 0
23-Aug 6.86E+04 512 32.3 5.25 0.01 7.58 4.88 76 92 22 0
24-Aug 6.76E+04 453 32.3 5.25 0.01 7.49 4.88 41 92 22 0
25-Aug 6.83E+04 453 32.3 5.25 0.01 7.49 4.88 41 92 22 0
93
26-Aug 6.72E+04 440 32.3 5.25 0.01 7.47 4.88 24 92 22 0
27-Aug 7.09E+04 394 32.3 5.3 0.01 7.56 4.88 30 92 22 0
28-Aug 7.13E+04 430 32.5 5.25 0.01 7.5 4.88 48 92 22 0
29-Aug 7.03E+04 497 32.3 5.25 0.01 7.49 4.88 46 92 22 0
30-Aug 5.95E+04 445 32.3 5.25 0.01 7.49 4.88 34 92 22 0
31-Aug 5.88E+04 453 32.3 5.25 0.01 7.49 4.88 27 92 22 0
Table B-2: Scums 1 & 2 variable for validation - August, 2007
Day Scum1
flow m3/d
Scum2
flow m3/d
Total COD
mgCOD/L
TKN
mgN/L
Total P
mgP/L
Nitrate N
mgN/L pH
Alkalinity
mmol/L
Inorganic S.S.
mgISS/L
Calcium
mg/L
Magnesium
mg/L
DO
mg/L
1-Aug 7.88 5.90 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
2-Aug 16.37 17.13 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
3-Aug 21.43 20.99 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
4-Aug 17.12 18.02 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
5-Aug 17.47 18.09 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
6-Aug 17.68 17.13 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
7-Aug 28.96 28.55 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
8-Aug 15.83 14.75 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
9-Aug 0 0 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
10-Aug 0 0 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
11-Aug 10.73 10.98 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
12-Aug 6.39 8.56 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
13-Aug 8.56 6.08 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
14-Aug 3.18 5.34 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
15-Aug 11.11 9.05 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
16-Aug 5.71 7.56 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
17-Aug 7.72 6.25 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
18-Aug 9.40 9.68 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
19-Aug 9.48 10.32 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
20-Aug 10.51 8.78 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
21-Aug 5.71 7.71 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
22-Aug 8.88 9.21 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
23-Aug 9.26 8.58 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
24-Aug 10.39 10.10 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
94
25-Aug 4.10 4.19 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
26-Aug 5.22 5.71 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
27-Aug 10.66 8.82 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
28-Aug 13.09 14.04 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
29-Aug 9.73 9.72 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
30-Aug 14.28 15.04 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
31-Aug 11.43 11.50 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
95
Table B-3: Sedimentation, splitter, gravity thickener and BFP variable for validation -
August, 2007
Day Sedimentation
variable m3/d
Splitter ratio
variable m3/d
Gravity thickener underflow
variable m3/d
BFP (dewatering)
underflow m3/d
1-Aug 192 1.1223 5.3 1.11177
2-Aug 310 1.0657 86 10.66266
3-Aug 294 1.0493 77 9.54174
4-Aug 288 1.0315 63 7.794
5-Aug 317 0.8778 57 7.04941
6-Aug 354 1.0724 77 9.48649
7-Aug 833 0.99 73 9.06231
8-Aug 187 1.0149 86 10.67081
9-Aug 282 0.9258 83 18.16188
10-Aug 285 0.9389 7.7 16.59871
11-Aug 610 0.9478 48 10.38721
12-Aug 345 0.9913 83 18.01839
13-Aug 258 1.0897 88 20.15393
14-Aug 279 0.8543 72 15.7587
15-Aug 324 0.9357 63 14.05168
16-Aug 546 0.9614 92 17.74352
17-Aug 210 0.8732 86 17.17066
18-Aug 245 1.1547 88 17.57933
19-Aug 396 0.9972 107 21.28226
20-Aug 335 1.0777 108 27.60331
21-Aug 386 0.9098 96 24.01981
22-Aug 350 0.9922 16 3.9528
23-Aug 317 1.0556 9.4 23.49045
24-Aug 418 0.9895 0 0
25-Aug 273 1.1409 0 0
26-Aug 190 0.9607 0 0
27-Aug 183 1.011 69 14.40796
28-Aug 205 1.0318 0.2 0.0371
29-Aug 231 1.0189 1 0.20401
30-Aug 355 1.006 27 5.52479
31-Aug 322 1.0506 73 15.83573
96
APPENDIX C
Steady-state simulation for the Regina WWTP
Figure C-1: Configuration of the Regina WWTP model
Table C-1: Raw influent constant
Name Value
Flow 6.79E+04
Total COD mgCOD/L 455
Total Kjeldahl Nitrogen mgN/L 34.6
Total P mgP/L 5.53
Nitrate N mgN/L 7.79
pH 7.53
Alkalinity mmol/L 5
Inorganic S.S. mgISS/L 55
Calcium mg/L 79
Magnesium mg/L 29
Dissolved oxygen mg/L 0
Table C-2: Lagoon Dimension
Volume m3 Area m
2 Depth m Width m
350000 60344.828 5.8 4
Table C-3: Other units constant
Grit tank flow split underflow constant 260 m3/d
sedimentation tank flow split underflow constant 330 m3/d
Gravity thickener flow split underflow constant 56 m3/d
BFP (dewatering) flow split underflow 9 m3/d
splitter13 flow split constant ratio[S/M] 1.0
Tertiary clarifier flow split underflow 3500 m3/d.
Influent
Digester 1
Grit Tank
Digester 2
Tertiary
Cake
Grit
Lagoon 1 Lagoon 2 Lagoon 3
Sludge
Alum
Scum 1
Scum 2
97
Table C-4: Tertiary effluent
State variable Conc. (mg/L) Mass rate (kg/d) Notes
Non-polyP heterotrophs 0.01 0.47
Anoxic methanol utilizers 0 0
Ammonia oxidizing biomass 0 0.02
Nitrite oxidizing biomass 0 0.01
Anaerobic ammonia oxidizers 0 0
PolyP heterotrophs 0 0
Propionic acetogens 0 0
Acetoclastic methanogens 0 0
Hydrogenotrophic methanogens 0 0
Endogenous products 0.1 6.37
Slowly bio. COD (part.) 0 0.01
Slowly bio. COD (colloid.) 0 0
Part. inert. COD 0.05 3.34
Part. bio. org. N 0 0
Part. bio. org. P 0 0
Part. inert N 0 0.12
Part. inert P 0 0.04
Stored PHA 0 0
Releasable stored polyP 0 0
Fixed stored polyP 0 0
PolyP bound cations 0 0
Readily bio. COD (complex) 0.7 43.83
Acetate 0 0
Propionate 0 0
Methanol 0 0
Dissolved H2 0 0
Dissolved methane 0 0
Ammonia N 0.05 2.86
Sol. bio. org. N 1.02 63.32
Nitrite N 0.01 0.56
Nitrate N 32.33 2010.8
Dissolved nitrogen gas 14.32 890.89
PO4-P (Sol. & Me Complexed) 0.93 57.59
Sol. inert COD 23.96 1490.74
Sol. inert TKN 0.69 43.07
Inorganic S.S. 0.02 1.03
Struvite 0 0
Hydroxy-dicalcium-phosphate 0 0
Hydroxy-apatite 0 0
Magnesium 29.03 1805.99
Calcium 78.96 4911.9
Metal 0 0.26
Other Cations (strong bases) 4.96 308.34 meq/L and keq/d
Other Anions (strong acids) 7.51 467.29 meq/L and keq/d
Total CO2 1.55 96.18 mmol/L and kmol/d
User defined 1 0 0
User defined 2 0 0
User defined 3 0 0
User defined 4 0 0
Dissolved oxygen 2 124.41
98
Table C- 5: Primary effluent to lagoons
State variable Conc. (mg/L) Mass rate (kg/d) Notes
Non-polyP heterotrophs 0.05 3.01
Anoxic methanol utilizers 0.02 1.14
Ammonia oxidizing biomass 0.02 1.13
Nitrite oxidizing biomass 0.02 1.13
Anaerobic ammonia oxidizers 0.02 1.14
PolyP heterotrophs 0.02 1.14
Propionic acetogens 0.02 1.20
Acetoclastic methanogens 0.06 3.66
Hydrogenotrophic methanogens 0.04 2.49
Endogenous products 0.05 3.21
Slowly bio. COD (part.) 94.31 5761.90
Slowly bio. COD (colloid.) 66.58 4067.54
Part. inert. COD 28.57 1745.67
Part. bio. org. N 1.86 113.90
Part. bio. org. P 0.51 30.91
Part. inert N 1.00 60.91
Part. inert P 0.31 19.14
Stored PHA 0.00 0.00
Releasable stored polyP 0.00 0.11
Fixed stored polyP 0.00 0.00
PolyP bound cations 0.00 0.08
Readily bio. COD (complex) 70.83 4327.79
Acetate 12.72 777.27
Propionate 0.01 0.58
Methanol 0 0.00
Dissolved H2 0.00 0.00
Dissolved methane 0.07 4.14
Ammonia N 24.79 1514.86
Sol. bio. org. N 5.25 321.01
Nitrite N 0.00 0.00
Nitrate N 0.50 30.47
Dissolved nitrogen gas 15.96 974.94
PO4-P (Sol. & Me Complexed) 2.53 154.64
Sol. inert COD 26.74 1633.92
Sol. inert TKN 0.76 46.45
Inorganic S.S. 4.63 282.72
Struvite 0 0.00
Hydroxy-dicalcium-phosphate 0 0.00
Hydroxy-apatite 0 0.00
Magnesium 75.89 4636.80
Calcium 0.25 15.55
Metal 0 0.00
Other Cations (strong bases) 5.02 306.66 meq/L and keq/d
Other Anions (strong acids) 8.02 489.75 meq/L and keq/d
Total CO2 5.15 314.72 mmol/L and kmol/d
User defined 1 0 0.00
User defined 2 0 0.00
User defined 3 0 0.00
User defined 4 0 0.00
Dissolved oxygen 0.00 0.00
99
Parameters Value Units
pH 7.29
Ionized ammonium 1.76 mmol/L
Unionized ammonia 0.01 mmol/L
Nitrous acid 0.00 mmol/L
Nitrite 0.00 mmol/L
Total dissolved CO2 0.51 mmol/L
Bicarbonate 4.64 mmol/L
Carbonate 0.01 mmol/L
Unionized ortho-P 0.00 mmol/L
H2PO4- 0.03 mmol/L
HPO4-- 0.05 mmol/L
PO4--- 0.00 mmol/L
Metal phosphate (solid) 0 mmol/L
Metal hydroxide (solid) 0 mmol/L
Metal ion 0 mmol/L
MeH2PO4++ 0 mmol/L
MeHPO4+ 0 mmol/L
Acetic acid 0.00 mmol/L
Acetate 0.20 mmol/L
Propionic acid 0.00 mmol/L
Propionate 0.00 mmol/L
Ionic strength 0.02
Monvalent Act. Coeff. 0.88
Divalent Act. Coeff. 0.60
Trivalent Act. Coeff. 0.32
Flow 61097.03 m3/d
100
APPENDIX D
Field Data from the Regina WWTP and Model Data from Calibration/Validation
for Startup Simulation
Table D- 1: Bicarbonate and seed constant for base case - April to September
Name Bicarbonate constant Seed constant
Flow m3/d 1 8
Non-polyP heterotrophs mgCOD/L 345.55 345.55
Anoxic methanol utilizers mgCOD/L 3.64 3.64
Ammonia oxidizing biomass mgCOD/L 1.98 1.98
Nitrite oxidizing biomass mgCOD/L 1.98 1.98
Anaerobic ammonia oxidizers mgCOD/L 4.47 4.47
PolyP heterotrophs mgCOD/L 3.91 3.91
Propionic acetogens mgCOD/L 15.37 15.37
Acetoclastic methanogens mgCOD/L 400.84 400.84
Hydrogenotrophic methanogens mgCOD/L 244.8 244.8
Endogenous products mgCOD/L 511.16 511.16
Slowly bio. COD (part.) mgCOD/L 6620 6620
Slowly bio. COD (colloid.) mgCOD/L 2.23 2.23
Part. inert. COD mgCOD/L 9581.33 9581.33
Part. bio. org. N mgN/L 162.54 162.54
Part. bio. org. P mgP/L 73.91 73.91
Part. inert N mgN/L 291.16 291.16
Part. inert P mgP/L 91.51 91.51
Stored PHA mgCOD/L 0.69 0.69
Releasable stored polyP mgP/L 0 0
Fixed stored polyP mgP/L 0 0
PolyP bound cations mg/L 0.05 0.05
Readily bio. COD (complex) mgCOD/L 0.58 0.58
Acetate mgCOD/L 126.24 126.24
Propionate mgCOD/L 3.99 3.99
Methanol mgCOD/L 0 0
Dissolved H2 mgCOD/L 0.02 0.02
Dissolved methane mg/L 30.72 30.72
Ammonia N mgN/L 247.99 247.99
Sol. bio. org. N mgN/L 1.65 1.65
Nitrite N mgN/L 0 0
Nitrate N mgN/L 0 0
Dissolved nitrogen gas mgN/L 0.03 0.03
PO4-P (Sol. & Me Complexed) mgP/L 168.19 168.19
Sol. inert COD mgCOD/L 442.39 442.39
Sol. inert TKN mgN/L 0.85 0.85
Inorganic S.S. mgISS/L 2172.16 2172.16
Struvite mgISS/L 0 0
Hydroxy-dicalcium-phosphate mgISS/L 0 0
Hydroxy-apatite mgISS/L 0 0
Magnesium mg/L 29.13 29.13
Calcium mg/L 79.08 79.08
Metal mg/L 0 0
Other Cations (strong bases) meq/L 17.99 17.99
101
Other Anions (strong acids) meq/L 6.16 6.16
Total CO2 mmol/L 38.63 38.63
User defined 1 mg/L 0 0
User defined 2 mg/L 0 0
User defined 3 mgVSS/L 0 0
User defined 4 mgISS/L 0 0
Dissolved oxygen mg/L 0 0
102
Table D-2: Raw influent variable for base case and Run #1 to Run #6 - April to September, 2012
Day Flow m3/d
Total COD
mgCOD/L
TKN
mgN/L
Total P
mgP/L
Nitrate N
mgN/L pH
Alkalinity
mmol/L
Inorganic S.S.
mgISS/L
Calcium
mg/L
Magnesium
mg/L
DO
mg/L
1-Apr 0 660.48 38 5.38 0.225 7.55 6.32 32 84 46 0
2-Apr 0 532.48 38 5.06 0.225 7.52 6.32 28 84 46 0
3-Apr 0 399.36 38 5.64 0.2 7.54 6.32 20 84 46 0
4-Apr 0 501.76 38 4.88 0.225 7.59 6.32 30 84 39 0
5-Apr 5.93E+04 552.96 38 5.53 0.225 7.6 6.32 28 84 39 0
6-Apr 6.39E+04 517.12 38 5.53 0.225 7.6 6.32 34 92 39 0
7-Apr 6.52E+04 778.24 38 5.53 0.225 7.6 6.32 34 92 39 0
8-Apr 8.39E+04 455.68 38 5.53 0.225 7.6 6.22 102 92 39 0
9-Apr 8.14E+04 604.16 38 4.78 0.225 7.46 6.22 18 92 39 0
10-Apr 7.26E+04 798.72 38 11.62 0.225 7.39 6.22 96 92 39 0
11-Apr 7.17E+04 547.84 38 4.77 0.2 7.51 6.22 26 92 39 0
12-Apr 6.91E+04 506.88 38 4.83 0.225 7.65 6.22 22 92 20 0
13-Apr 6.83E+04 542.72 38 5.53 0.225 7.6 6.22 35 92 20 0
14-Apr 6.70E+04 542.72 38 5.53 0.225 7.6 6.86 32 92 20 0
15-Apr 6.61E+04 537.6 38 5.26 0.225 7.64 6.86 22 92 20 0
16-Apr 6.57E+04 537.6 38 4.89 0.225 7.8 6.86 100 92 20 0
17-Apr 6.89E+04 512 38 5.63 0.4 7.81 6.86 44 92 20 0
18-Apr 6.66E+04 501.76 38 5.5 0.225 7.73 6.86 28 88 20 0
19-Apr 6.44E+04 552.96 38 5.26 0.225 7.71 6.86 22 88 20 0
20-Apr 6.16E+04 542.72 38 5.53 0.225 7.6 6.86 9 88 46 0
21-Apr 6.49E+04 542.72 38 5.53 0.225 7.6 7.02 30 88 46 0
22-Apr 6.35E+04 496.64 38 5.78 0.225 7.51 7.02 18 88 46 0
23-Apr 6.48E+04 476.16 38 5.47 0.225 7.65 7.02 28 88 46 0
24-Apr 6.74E+04 599.04 38 5.18 0.1 7.53 7.02 26 88 46 0
25-Apr 6.41E+04 614.4 38 5.36 0.225 7.56 7.02 32 88 46 0
26-Apr 6.28E+04 506.88 38 5.34 0.225 7.66 7.02 50 88 46 0
27-Apr 6.30E+04 542.72 38 5.53 0.225 7.6 6.61 19 88 46 0
28-Apr 6.46E+04 542.72 38 5.53 0.225 7.6 6.61 35 88 46 0
29-Apr 7.07E+04 373.76 38 4.59 0.225 7.6 6.61 12 88 56 0
30-Apr 7.23E+04 496.64 38 5.47 0.225 7.61 6.61 32 88 56 0
1-May 6.86E+04 465.92 38 3.76 0.1 7.48 6.6 26 68 56 0
103
2-May 6.82E+04 481.28 38 4.67 0.2 7.74 6.6 28 68 56 0
3-May 7.39E+04 824.32 38 4.1 0.2 7.73 6.6 44 68 56 0
4-May 6.89E+04 476.16 38 4.1 0.2 7.56 6.6 27 68 56 0
5-May 6.81E+04 476.16 38 4.1 0.2 7.56 6.6 28 68 56 0
6-May 1.05E+05 496.64 38 3.44 0.2 7.56 7.62 36 68 41 0
7-May 8.43E+04 389.12 38 3.64 0.2 7.71 7.62 22 68 41 0
8-May 9.62E+04 512 38 4.02 0.2 7.59 7.62 20 112 41 0
9-May 8.31E+04 614.4 38 4.42 0.2 7.66 7.62 24 112 41 0
10-May 7.57E+04 445.44 38 4.52 0.2 7.63 7.62 40 112 41 0
11-May 7.21E+04 476.16 38 4.1 0.2 7.56 6.72 9 112 41 0
12-May 7.31E+04 476.16 38 4.1 0.2 7.56 6.72 71 112 20 0
13-May 7.15E+04 460.8 38 4.52 0.2 7.64 6.72 26 112 20 0
14-May 6.92E+04 476.16 38 4.1 0.2 7.51 6.72 25 112 20 0
15-May 7.29E+04 373.76 38 4.37 0.2 7.54 6.72 22 112 20 0
16-May 7.30E+04 481.28 38 4.84 0.2 7.51 6.72 18 112 20 0
17-May 7.39E+04 558.08 38 3.94 0.2 7.44 6.72 22 112 20 0
18-May 7.45E+04 476.16 38 4.1 0.2 7.56 5.7 3 140 17 0
19-May 7.33E+04 476.16 38 4.1 0.2 7.56 5.7 91 140 17 0
20-May 7.39E+04 476.16 38 4.1 0.2 7.56 5.7 7 140 17 0
21-May 7.17E+04 450.56 38 4.54 0.2 7.45 5.7 18 140 17 0
22-May 7.00E+04 450.56 38 4.5 0.2 7.45 5.7 48 140 17 0
23-May 7.45E+04 409.6 38 4.06 0.2 7.62 6.68 26 140 27 0
24-May 9.21E+04 430.08 38 4.12 0.2 7.65 6.68 24 140 27 0
25-May 8.33E+04 476.16 38 4.1 0.2 7.56 6.68 21 144 27 0
26-May 8.36E+04 476.16 38 4.1 0.2 7.56 6.68 31 144 27 0
27-May 7.68E+04 394.24 38 3.96 0.2 7.47 6.68 34 144 27 0
28-May 7.03E+04 368.64 38 3.11 0.2 7.49 6.68 18 144 27 0
29-May 1.51E+05 573.44 38 2.89 0.3 7.51 6.68 16 144 27 0
30-May 1.06E+05 373.76 38 4.59 0.2 7.42 6.68 24 144 27 0
31-May 8.77E+04 471.04 38 4.3 0.2 7.43 6.68 20 144 27 0
1-Jun 8.20E+04 465.92 38 4.83 0.67 7.37 5.92 33 108 32 0
2-Jun 7.95E+04 465.92 38 4.83 0.67 7.37 5.92 32 108 32 0
3-Jun 7.37E+04 399.36 38 4.53 0.67 7.37 5.92 12 108 32 0
4-Jun 7.43E+04 322.56 38 4.57 0.67 7.41 5.92 14 108 32 0
5-Jun 7.70E+04 486.4 38 5.66 0.67 7.42 5.92 42 108 32 0
104
6-Jun 7.52E+04 460.8 38 5.68 0.67 7.41 5.92 38 112 29 0
7-Jun 7.43E+04 527.36 38 4.67 0.67 7.36 5.92 26 112 29 0
8-Jun 6.97E+04 465.92 38 4.83 0.67 7.37 5.92 30 112 29 0
9-Jun 6.91E+04 465.92 38 4.83 0.67 7.37 6.2 17 112 29 0
10-Jun 6.85E+04 476.16 38 4.67 0.67 7.34 6.2 24 112 29 0
11-Jun 6.90E+04 373.76 38 4.56 0.67 7.43 6.2 20 112 29 0
12-Jun 7.14E+04 476.16 38 4.64 0.7 7.42 6.2 20 112 29 0
13-Jun 6.97E+04 465.92 38 4.77 0.67 7.36 6.2 20 104 41 0
14-Jun 6.58E+04 286.72 38 3.88 0.67 7.36 6.2 4 104 41 0
15-Jun 6.85E+04 465.92 38 4.83 0.67 7.37 5.8 30 104 41 0
16-Jun 7.02E+04 465.92 38 4.83 0.67 7.37 5.8 18 104 41 0
17-Jun 6.70E+04 517.12 38 4.67 0.67 7.3 5.8 30 104 41 0
18-Jun 6.53E+04 512 38 5.05 0.67 7.45 5.8 26 104 41 0
19-Jun 6.96E+04 501.76 38 5.11 0.67 7.28 5.8 36 104 41 0
20-Jun 6.99E+04 537.6 38 4.82 0.5 7.32 5.8 108 112 41 0
21-Jun 7.39E+04 435.2 38 4.6 0.67 7.39 5.8 34 112 24 0
22-Jun 8.30E+04 465.92 38 4.83 0.67 7.37 5.8 30 112 24 0
23-Jun 7.35E+04 465.92 38 4.83 0.67 7.37 5.8 30 112 24 0
24-Jun 7.03E+04 558.08 38 5.08 0.67 7.32 4.54 30 112 24 0
25-Jun 6.83E+04 496.64 38 5 0.67 7.31 4.54 28 112 24 0
26-Jun 6.87E+04 742.4 38 4.99 0.67 7.34 4.54 120 112 24 0
27-Jun 7.13E+04 552.96 38 5.9 0.67 7.36 4.54 72 112 24 0
28-Jun 8.72E+04 199.68 38 4.34 0.8 7.41 4.54 104 112 24 0
29-Jun 7.50E+04 465.92 38 4.83 0.67 7.37 4.54 30 112 24 0
30-Jun 7.05E+04 465.92 38 4.83 0.37 7.37 4.54 30 112 24 0
1-Jul 7.10E+04 271.36 38 4.11 0.63 7.36 3.3 32 112 29 0
2-Jul 6.41E+04 419.84 38 3.51 0.63 7.29 3.3 50 112 29 0
3-Jul 8.12E+04 419.84 38 3.63 0.63 7.37 3.3 24 112 29 0
4-Jul 8.23E+04 471.04 38 3.97 0.7 7.35 3.3 36 112 29 0
5-Jul 7.49E+04 389.12 38 4.44 0.63 7.32 3.3 20 112 22 0
6-Jul 6.89E+04 399.36 38 4.11 0.63 7.36 3.3 45 136 22 0
7-Jul 6.64E+04 399.36 38 4.11 0.63 7.36 4.6 6 136 22 0
8-Jul 6.67E+04 547.84 38 4.56 0.63 7.26 4.6 34 136 22 0
9-Jul 6.36E+04 583.68 38 4.39 0.63 7.22 4.6 38 136 22 0
10-Jul 6.66E+04 225.28 38 3.55 0.4 7.48 4.6 20 136 22 0
105
11-Jul 6.83E+04 281.6 38 3.85 0.63 7.25 4.6 18 120 29 0
12-Jul 6.76E+04 245.76 38 4.27 0.63 7.44 4.6 10 120 29 0
13-Jul 7.25E+04 399.36 38 4.11 0.63 7.36 4.6 17 120 29 0
14-Jul 6.76E+04 399.36 38 4.11 0.63 7.36 5.18 10 120 29 0
15-Jul 6.65E+04 537.6 38 4.28 0.63 7.32 5.18 22 120 29 0
16-Jul 7.02E+04 322.56 38 3.26 0.63 7.27 5.18 48 120 29 0
17-Jul 7.29E+04 256 38 3.38 0.63 7.41 5.18 24 120 29 0
18-Jul 7.93E+04 348.16 38 3.75 0.63 7.35 5.18 20 120 29 0
19-Jul 9.62E+04 378.88 38 4.13 0.63 7.5 5.02 18 120 20 0
20-Jul 8.06E+04 399.36 38 4.11 0.63 7.36 5.02 24 136 20 0
21-Jul 7.53E+04 399.36 38 4.11 0.63 7.36 5.02 18 136 20 0
22-Jul 7.30E+04 409.6 38 4.44 0.63 7.43 5.02 8 136 20 0
23-Jul 6.95E+04 296.96 38 3.9 0.63 7.3 5.02 14 136 20 0
24-Jul 6.77E+04 465.92 38 4.45 0.63 7.39 5.02 40 136 20 0
25-Jul 7.18E+04 409.6 38 4.5 0.63 7.46 5.02 30 136 20 0
26-Jul 7.65E+04 455.68 38 4.46 0.8 7.43 5.02 20 136 20 0
27-Jul 6.96E+04 399.36 38 4.11 0.63 7.36 4.84 24 108 20 0
28-Jul 6.85E+04 399.36 38 4.11 0.63 7.36 4.84 19 108 20 0
29-Jul 6.70E+04 430.08 38 4.43 0.63 7.38 4.84 10 108 20 0
30-Jul 6.67E+04 496.64 38 4.56 0.63 7.34 4.84 22 108 20 0
31-Jul 6.80E+04 512 38 4.78 0.4 7.37 4.84 20 108 20 0
1-Aug 6.75E+04 327.68 38 4.32 0.65 7.26 4.66 10 80 41 0
2-Aug 6.62E+04 532.48 38 4.83 0.65 7.39 4.66 64 80 41 0
3-Aug 6.85E+04 499.2 38 4.48 0.65 7.29 4.66 25 80 41 0
4-Aug 8.29E+04 499.2 38 4.48 0.65 7.29 4.66 31 80 41 0
5-Aug 7.19E+04 499.2 38 4.48 0.65 7.29 4.66 49 80 41 0
6-Aug 6.59E+04 465.92 38 4.29 0.65 7.2 4.66 32 80 41 0
7-Aug 6.32E+04 486.4 38 4.75 0.65 7.26 4.66 42 80 41 0
8-Aug 6.98E+04 537.6 38 5.25 0.65 7.28 4.66 50 80 41 0
9-Aug 7.07E+04 655.36 38 4.62 0.65 7.24 4.44 30 76 41 0
10-Aug 6.73E+04 499.2 38 4.48 0.65 7.29 4.44 63 76 41 0
11-Aug 6.45E+04 499.2 38 4.48 0.65 7.29 4.44 61 76 41 0
12-Aug 6.36E+04 501.76 38 4.36 0.65 7.29 4.44 38 76 41 0
13-Aug 6.81E+04 527.36 38 4.67 0.65 7.19 4.44 34 76 41 0
14-Aug 6.48E+04 353.28 38 4.1 0.65 7.24 4.44 24 76 41 0
106
15-Aug 6.20E+04 512 38 4.79 0.65 7.25 4.44 35 96 41 0
16-Aug 6.24E+04 537.6 38 4.43 0.65 7.26 4.54 30 96 27 0
17-Aug 6.67E+04 499.2 38 4.48 0.65 7.29 4.54 91 96 27 0
18-Aug 6.56E+04 499.2 38 4.48 0.65 7.29 4.54 55 96 27 0
19-Aug 6.79E+04 527.36 38 4.76 0.65 7.26 4.54 32 96 27 0
20-Aug 6.55E+04 501.76 38 4.62 0.65 7.2 4.54 38 96 27 0
21-Aug 6.74E+04 537.6 38 3.02 0.65 7.19 4.54 54 96 27 0
22-Aug 6.90E+04 501.76 38 4.49 0.65 7.21 4.54 30 96 27 0
23-Aug 6.79E+04 460.8 38 4.42 0.6 7.37 4.54 22 96 27 0
24-Aug 6.53E+04 499.2 38 4.48 0.65 7.29 5.08 17 100 27 0
25-Aug 6.60E+04 499.2 38 4.48 0.65 7.29 5.08 51 100 27 0
26-Aug 6.55E+04 471.04 38 4.6 0.65 7.4 5.08 26 100 27 0
27-Aug 6.56E+04 583.68 38 4.5 0.65 7.47 5.08 30 100 27 0
28-Aug 6.69E+04 532.48 38 4.56 0.7 7.47 5.08 20 100 27 0
29-Aug 6.81E+04 465.92 38 4.42 0.65 7.44 5.08 24 100 27 0
30-Aug 6.70E+04 450.56 38 4.35 0.65 7.2 5.08 2 100 27 0
31-Aug 6.98E+04 499.2 38 4.48 0.65 7.29 5.08 60 100 27 0
1-Sep 6.93E+04 471.04 38 4.32 0.5 7.31 4.78 15 116 27 0
2-Sep 6.84E+04 471.04 38 4.32 0.5 7.31 4.78 20 116 27 0
3-Sep 6.42E+04 537.6 38 4.38 0.5 7.31 4.78 32 116 27 0
4-Sep 6.60E+04 368.64 38 3.64 0.6 7.54 4.78 34 116 27 0
5-Sep 7.04E+04 471.04 38 3.86 0.5 7.45 4.78 32 116 27 0
6-Sep 6.69E+04 512 38 4.6 0.5 7.31 4.78 32 116 76 0
7-Sep 6.62E+04 471.04 38 4.32 0.5 7.31 4.78 38 116 76 0
8-Sep 6.63E+04 471.04 38 4.32 0.5 7.31 4.78 38 116 76 0
9-Sep 6.47E+04 271.36 38 4.62 0.5 7.31 4.78 128 116 76 0
10-Sep 6.52E+04 471.04 38 4.45 0.5 7.39 4.78 24 96 76 0
11-Sep 6.85E+04 337.92 38 4.04 0.3 7.23 4.24 18 96 76 0
12-Sep 6.91E+04 471.04 38 4.26 0.5 7.13 4.24 44 96 15 0
13-Sep 6.78E+04 481.28 38 4.57 0.5 7.1 4.24 52 96 15 0
14-Sep 6.62E+04 471.04 38 4.32 0.5 7.31 4.24 20 96 15 0
15-Sep 6.43E+04 471.04 38 4.32 0.5 7.31 4.24 38 96 15 0
16-Sep 6.50E+04 532.48 38 4.74 0.5 7.3 4.24 36 96 15 0
17-Sep 6.59E+04 517.12 38 4.77 0.5 7.34 4.24 38 96 15 0
18-Sep 6.70E+04 573.44 38 4.6 0.5 7.24 4.24 40 96 15 0
107
19-Sep 6.51E+04 501.76 38 4.61 0.5 7.37 4.24 80 96 15 0
20-Sep 6.43E+04 465.92 38 4.66 0.8 7.38 4.24 54 96 15 0
21-Sep 6.57E+04 471.04 38 4.32 0.5 7.31 4.78 49 0 15 0
22-Sep 6.57E+04 471.04 38 4.32 0.5 7.31 4.78 62 0 76 0
23-Sep 6.68E+04 609.28 38 4.55 0.5 7.22 4.78 46 0 76 0
24-Sep 6.43E+04 496.64 38 4.43 0.3 7.33 4.78 62 0 76 0
25-Sep 6.84E+04 532.48 38 4.67 0.5 7.32 4.78 66 0 76 0
26-Sep 7.03E+04 486.4 38 3.92 0.5 7.32 4.78 46 0 76 0
27-Sep 6.83E+04 266.24 38 2.37 0.5 7.26 4.78 140 0 76 0
28-Sep 6.24E+04 471.04 38 4.32 0.5 7.31 4.78 40 0 76 0
29-Sep 6.32E+04 471.04 38 4.32 0.5 7.31 4.78 44 0 76 0
30-Sep 6.15E+04 522.24 38 4.61 0.5 7.32 4.78 36 0 76 0
108
Table D-3: Sedimentation, splitter13, splitter14, gravity thickener, and BFP dewatering variable for base case and Run #1 to #6 -
April to September, 2012
Day
Sedimentation
underflow
m3/d
Splitter14
rate in side
m3/d
Splitter13
rate in side
m3/d
Gravity
thickener
m3/d
BFP
m3/d
1-Apr 318.5033 0 0 0 0
2-Apr 282.113 0 0 0 0
3-Apr 274.3742 0 0 0 0
4-Apr 390.2159 0 0 0 0
5-Apr 375.8254 0 0 0 0
6-Apr 397.1225 0 0 0 0
7-Apr 628.1489 0 0 0 0
8-Apr 370.9679 0 0 0 0
9-Apr 302.0255 0 0 0 0
10-Apr 347.0012 0 0 0 0
11-Apr 365.971 0 0 0 0
12-Apr 697.0756 0 0 0 0
13-Apr 249.9056 0 0 0 0
14-Apr 351.4481 0 0 0 0
15-Apr 393.0792 0 0 0 0
16-Apr 410.4609 0 0 0 0
17-Apr 743.4112 77.8 55 0 0
18-Apr 201.0419 12.7144 2.7144 0 0
19-Apr 269.8397 3.6058 3.6058 0 0
20-Apr 253.9379 4.6362 4.6362 0 0
21-Apr 328.5813 4.6474 4.6474 0 0
22-Apr 351.988 2.1801 2.1801 0 0
23-Apr 297.8687 1.9089 1.9089 0 0
24-Apr 335.9933 4.7363 4.7363 0.0099 0.0021
25-Apr 257.8903 4.3147 4.3147 4.0097 1.3048
26-Apr 395.0429 8.5108 8.5108 0 0
27-Apr 558.632 7.6077 7.6077 5.1305 1.089
28-Apr 403.5306 15.5827 15.5827 0 0
Day
Sedimentation
underflow
m3/d
Splitter14
rate in side
m3/d
Splitter13
rate in side
m3/d
Gravity
thickene
r m3/d
BFP
m3/d
29-Apr 354.4536 8.4857 8.4857 0 0
30-Apr 292.1409 8.9143 8.9143 1.90E-04 4.04E-05
1-May 296.1627 9.3429 9.3429 0 0
2-May 716.5259 9.8286 9.8286 0 0
3-May 200.3695 0 0 0 0
4-May 262.8477 0 0 0 0
5-May 806.5033 0 0 0 0
6-May 282.3159 0 0 0 0
7-May 532.225 0 0 0 0
8-May 393.2584 0 0 0 0
9-May 322.8099 0 0 0 0
10-May 347.2469 0 0 0 0
11-May 533.4396 0 0 0.0346 0.3213
12-May 210.9001 0 0 0 0
13-May 252.6137 0 0 0 0
14-May 396.8276 0 0 0 0
15-May 356.2964 0 0 0 0
16-May 334.1645 0 0 0 0
17-May 695.4925 1.8815 1.8815 0 0
18-May 330.1543 3.0727 3.0727 0 0
19-May 319.5845 6.1546 6.1546 0 0
20-May 292.4051 6.1914 6.1914 0 0
21-May 347.908 5.5105 5.5105 0 0
22-May 273.4048 6.9055 6.9055 0 0
23-May 575.09 5.053 5.053 0 0
24-May 304.7247 3.2141 3.2141 0 0
25-May 325.0992 8.4199 8.4199 0 0
26-May 313.4002 10.6 10.6 0 0
109
27-May 318.2601 8.322 8.322 0 0
28-May 562.6492 10.4461 10.4461 0 0
29-May 756.9513 8.3862 8.3862 0 0
30-May 394.5494 9.895 9.895 0 0
31-May 319.6203 11.6208 11.6208 0 0
1-Jun 355.2033 5.4556 5.4556 0 0
2-Jun 368.7681 21.0949 21.0949 0 0
3-Jun 398.8006 0 0 0 0
4-Jun 480.1652 16.0385 16.0385 0 0
5-Jun 461.1768 9.1987 9.1987 0 0
6-Jun 543.9571 17.7531 17.7531 0 0
7-Jun 563.7093 12.7242 12.7242 0 0
8-Jun 461.0119 32.8107 32.8107 0 0
9-Jun 516.3666 17.6789 17.6789 0 0
10-Jun 584.8743 16.2113 16.2113 0 0
11-Jun 480.4763 30.1016 30.1016 0 0
12-Jun 589.1598 23.2534 23.2534 0 0
13-Jun 339.2712 43.5277 43.5277 0 0
14-Jun 378.1253 31.0928 31.0928 2.3102 0.5824
15-Jun 321.8088 41.7143 41.7143 0.1577 0.0398
16-Jun 388.4524 75.8219 75.8219 0 0
17-Jun 387.3696 27.9159 27.9159 0 0
18-Jun 422.5364 29.6371 29.6371 2.33E-04 5.87E-05
19-Jun 419.8816 34.7466 34.7466 2.7719 0.6988
20-Jun 433.9396 32.1526 32.1526 0 0
21-Jun 968.3871 31.4817 31.4817 0 0
22-Jun 271.651 46.0477 46.0477 0 0
23-Jun 307.6327 53.9672 53.9672 0 0
24-Jun 228.126 63.3575 63.3575 0 0
25-Jun 392.6119 65.2161 65.2161 0 0
26-Jun 419.9541 38.8503 38.8503 0 0
27-Jun 884.5734 56.4275 56.4275 0 0
28-Jun 371.398 45.0309 45.0309 0 0
29-Jun 173.6706 67.945 67.945 0 0
30-Jun 395.1725 76.8188 76.8188 0 0
1-Jul 255.2906 48.8169 48.8169 0 0
2-Jul 507.795 77.8204 77.8204 9.70E-04 2.07E-04
3-Jul 404.9604 77.8204 77.8204 0 0
4-Jul 208.1162 76.5575 76.5575 0 0
5-Jul 264.164 99.9741 99.9741 8.3418 1.7767
6-Jul 195.4946 73.9083 73.9083 4.2056 0.8958
7-Jul 291.959 79.0681 79.0681 0 0
8-Jul 324.5153 80.0774 80.0774 0 0
9-Jul 335.9541 62.8545 62.8545 0 0
10-Jul 438.7099 126.197 126.197 3.0186 0.6429
11-Jul 655.3126 16.2044 16.2044 1.4582 0.3747
12-Jul 509.3181 116.1675 116.1675 4.9661 1.0577
13-Jul 373.8962 15.2209 15.2209 20.0159 4.2632
14-Jul 288.9957 77.5074 77.5074 0 0
15-Jul 442.9038 106.4443 106.4443 0 0
16-Jul 551.216 70.0909 70.0909 0 0
17-Jul 475.4097 137.0478 137.0478 0 0
18-Jul 848.0601 80.0647 80.0647 0 0
19-Jul 439.3677 95.8452 95.8452 0 0
20-Jul 325.9261 110.1922 110.1922 0 0
21-Jul 349.9327 73.307 73.307 0 0
22-Jul 384.302 107.7786 107.7786 0 0
23-Jul 402.8545 137.0468 137.0468 0 0
24-Jul 451.9229 95.7922 95.7922 21.4113 4.5604
25-Jul 548.3026 155.9171 155.9171 24.0215 3.9178
26-Jul 234.5237 124.5069 124.5069 11.5043 2.4503
27-Jul 230.8126 122.7413 122.7413 4.1401 0.8818
28-Jul 237.6055 123.526 123.526 0 0
29-Jul 460.9095 231.7147 231.7147 0 0
30-Jul 319.7892 58.3726 58.3726 0 0
31-Jul 332.3301 146.8698 146.8698 3.9546 0.8423
1-Aug 411.8029 0 0 0.7011 0.0869
2-Aug 269.0217 145.7148 145.7148 7.526 1.3112
3-Aug 586.8494 175 175 7.1781 1.2506
4-Aug 400.2757 200 200 0 0
110
5-Aug 291.763 157.7418 157.7418 0 0
6-Aug 382.9365 219.1212 219.1212 0 0
7-Aug 337.9727 237.1029 237.1029 0 0
8-Aug 441.1378 251.0108 251.0108 0 0
9-Aug 453.0149 276.2583 276.2583 0 0
10-Aug 456.8218 304.631 304.631 0 0
11-Aug 368.9406 218.7161 218.7161 0 0
12-Aug 460.171 349.8423 349.8423 0 0
13-Aug 400.1712 232.0485 232.0485 0 0
14-Aug 371.9828 242.8192 242.8192 20.7872 3.6212
15-Aug 323.7161 192.0334 192.0334 28.6546 5.2914
16-Aug 357.5099 228.394 228.394 22.9542 3.999
17-Aug 735.7607 470.3267 470.3267 31.0766 5.4141
18-Aug 398.451 212.2712 212.2712 0 0
19-Aug 393.1226 300.0997 300.0997 0 0
20-Aug 449.6321 277.9294 277.9294 6.3457 1.1055
21-Aug 289.5805 136.4959 136.4959 0.1499 0.0278
22-Aug 383.2497 172.4609 172.4609 0.0014 2.49E-04
23-Aug 329.852 235.0477 235.0477 0 0
24-Aug 243.6309 200.1036 200.1036 0 0
25-Aug 499.6831 368.8413 368.8413 0 0
26-Aug 520.666 181.3267 181.3267 0.0094 0
27-Aug 309.9512 229.0754 229.0754 0 0
28-Aug 441.4091 441.3985 441.3985 0 0
29-Aug 587.6841 347.9718 347.9718 0 0
30-Aug 493.5634 382.5317 382.5317 0.2017 0.0351
31-Aug 418.9437 242.4878 242.4878 0 0
1-Sep 253.706 192.4184 192.4184 0 0
2-Sep 274.0539 240.3366 240.3366 5.1561 0.8962
3-Sep 323.7001 271.259 271.259 0 0
4-Sep 515.6249 462.9749 462.9749 0 0
5-Sep 482.484 150.0043 150.0043 28.2777 5.5711
6-Sep 379.0854 378.5656 378.5656 0 0
7-Sep 572.9258 250.0817 250.0817 0 0
8-Sep 455.1451 198.4624 198.4624 0 0
9-Sep 319.8809 290.7265 290.7265 0 0
10-Sep 532.6428 252.5479 252.5479 0.0016 2.73E-04
11-Sep 858.1854 258.0121 258.0121 0 0
12-Sep 251.9159 67 67 1323.679 212.0377
13-Sep 197.4349 197.4349 197.4349 687.6259 119.5186
14-Sep 440.9473 200 200 0 0
15-Sep 396.7048 200 200 0 0
16-Sep 579.1769 200 200 22.4916 4.3566
17-Sep 601.9713 200 200 0 0
18-Sep 325.862 200 200 17.9899 3.1269
19-Sep 203.9442 203.9442 203.9442 0 0
20-Sep 655.5275 200 200 0 0
21-Sep 710.769 100 100 24.9161 4.3308
22-Sep 363.5847 100 100 21.0527 3.6592
23-Sep 332.1617 100 100 7.82E-04 1.36E-04
24-Sep 414.0006 100 100 0.8598 0.1418
25-Sep 302.4747 100 100 30.0629 5.2253
26-Sep 415.0604 100 100 41.1507 7.1525
27-Sep 197.0616 67 67 16.5946 2.8844
28-Sep 223.3473 88 88 7.0544 1.2262
29-Sep 299.2926 100 100 0 0
30-Sep 312.7486 100 100 0 0
111
Table D-4: Scum 2 variable for base case - April to September, 2012
Day Scum 2
flow m3/d
Total COD
mgCOD/L
TKN
mgN/L
Total P
mgP/L
Nitrate N
mgN/L pH
Alkalinity
mmol/L
Inorganic S.S.
mgISS/L
Calcium
mg/L
Magnesium
mg/L
DO
mg/L
1-Apr to
27-Aug 0 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
28-Aug 4.79 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
29-Aug 12.75 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
30-Aug 8.90 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
31-Aug 8.65 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
1-Sep 5.34 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
2-Sep 9.93 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
3-Sep 4.71 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
4-Sep 5.39 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
5-Sep 11.14 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
6-Sep 4.33 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
7-Sep 4.95 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
8-Sep 8.72 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
9-Sep 3.87 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
10-Sep 7.72 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
11-Sep 6.24 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
12-Sep 6.92 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
13-Sep 6.84 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
14-Sep 8.90 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
15-Sep 8.47 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
16-Sep 8.27 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
17-Sep 12.95 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
18-Sep 6.07 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
19-Sep 12.90 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
20-Sep 20.01 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
21-Sep 7.56 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
22-Sep 8.73 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
23-Sep 4.52 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
24-Sep 7.62 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
25-Sep 12.09 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
112
26-Sep 6.77 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
27-Sep 8.61 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
28-Sep 4.25 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
29-Sep 5.64 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
30-Sep 8.41 1.30E+05 130 10 0.2 7.5 5 1 79 29 0
Table D-5: Bicarbonate variable for base case - April to September, 2012
Properties Day with bicarbonate addition Day without
bicarbonate addition
Day 17-May 18-May 28-May 26-Sept Reminder
Flow m3/d 2.5 1.25 0.5 0.25 0
Non-polyP heterotrophs mgCOD/L 354.54 354.54 354.54 354.54 0.01
Anoxic methanol utilizers mgCOD/L 3.63 3.63 3.63 3.63 0.00
Ammonia oxidizing biomass mgCOD/L 1.98 1.98 1.98 1.98 0.00
Nitrite oxidizing biomass mgCOD/L 1.98 1.98 1.98 1.98 0.00
Anaerobic ammonia oxidizers mgCOD/L 4.46 4.46 4.46 4.46 0.00
PolyP heterotrophs mgCOD/L 3.90 3.90 3.90 3.90 0.00
Propionic acetogens mgCOD/L 15.47 15.47 15.47 15.47 0.00
Acetoclastic methanogens mgCOD/L 465.57 465.57 465.57 465.57 0.00
Hydrogenotrophic methanogens mgCOD/L 249.43 249.43 249.43 249.43 0.00
Endogenous products mgCOD/L 517.35 517.35 517.35 517.35 0.10
Slowly bio. COD (part.) mgCOD/L 6,864.20 6,864.20 6,864.20 6,864.20 0.00
Slowly bio. COD (colloid.) mgCOD/L 0.83 0.83 0.83 0.83 0.00
Part. inert. COD mgCOD/L 10,900 10,900 10,900 10,900 0.05
Part. bio. org. N mgN/L 189.57 189.57 189.57 189.57 0.00
Part. bio. org. P mgP/L 72.03 72.03 72.03 72.03 0.00
Part. inert N mgN/L 339.88 339.88 339.88 339.88 0.00
Part. inert P mgP/L 106.82 106.82 106.82 106.82 0.00
113
Stored PHA mgCOD/L 0.69 0.69 0.69 0.69 0.00
Releasable stored polyP mgP/L 0.00 0.00 0.00 0.00 0.00
Fixed stored polyP mgP/L 0.00 0.00 0.00 0.00 0.00
PolyP bound cations mg/L 0.05 0.05 0.05 0.05 0.00
Readily bio. COD (complex) mgCOD/L 0.58 0.58 0.58 0.58 0.70
Acetate mgCOD/L 88.61 88.61 88.61 88.61 0.00
Propionate mgCOD/L 4.14 4.14 4.14 4.14 0.00
Methanol mgCOD/L 0.00 0.00 0.00 0.00 0.00
Dissolved H2 mgCOD/L 0.02 0.02 0.02 0.02 0.00
Dissolved methane mg/L 31.15 31.15 31.15 31.15 0.00
Ammonia N mgN/L 339.57 339.57 339.57 339.57 0.05
Sol. bio. org. N mgN/L 1.88 1.88 1.88 1.88 1.02
Nitrite N mgN/L 0.00 0.00 0.00 0.00 0.01
Nitrate N mgN/L 0.00 0.00 0.00 0.00 32.33
Dissolved nitrogen gas mgN/L 0.03 0.03 0.03 0.03 14.32
PO4-P (Sol. & Me Complexed) mgP/L 158.71 158.71 158.71 158.71 0.93
Sol. inert COD mgCOD/L 412.86 412.86 412.86 412.86 23.96
Sol. inert TKN mgN/L 0.84 0.84 0.84 0.84 0.69
Inorganic S.S. mgISS/L 2,362.29 2,362.29 2,362.29 2,362.29 0.02
Struvite mgISS/L 0.00 0.00 0.00 0.00 0.00
Hydroxy-dicalcium-phosphate mgISS/L 0.00 0.00 0.00 0.00 0.00
Hydroxy-apatite mgISS/L 0.00 0.00 0.00 0.00 0.00
Magnesium mg/L 29.13 29.13 29.13 29.13 29.03
Calcium mg/L 84,500.00 84,500.00 84,500.00 84,500.00 78.96
Metal mg/L 0.00 0.00 0.00 0.00 0.00
Other Cations (strong bases) meq/L 16.94 16.94 16.94 16.94 4.96
Other Anions (strong acids) meq/L 5.95 5.95 5.95 5.95 7.51
114
Total CO2 mmol/L 44.83 44.83 44.83 44.83 1.55
User defined 1 mg/L 0.00 0.00 0.00 0.00 0.00
User defined 2 mg/L 0.00 0.00 0.00 0.00 0.00
User defined 3 mgVSS/L 0.00 0.00 0.00 0.00 0.00
User defined 4 mgISS/L 0.00 0.00 0.00 0.00 0.00
Dissolved oxygen mg/L 0.00 0.00 0.00 0.00 0.00
Table D-6: Seed sludge 40 m3 for base case and Run #3 and #6 - April to September, 2012
Day 1
Apr
2
Apr
3
Apr
4
Apr
5
Apr
6
Apr
7
Apr
8
Apr
9
Apr
10
Apr
11
Apr
12
Apr
13
Apr
14
Apr
15
Apr
16
Apr
14-Apr to
30-Sept
Flow m3/d 800 800 800 800 800 800 800 800 800 800 800 800 800 800 800 40 0
Non-polyP heterotrophs
mgCOD/L 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 354.54 0.01
Anoxic methanol utilizers
mgCOD/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3.63 0
Ammonia oxidizing biomass
mgCOD/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.98 0
Nitrite oxidizing biomass
mgCOD/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.98 0
Anaerobic ammonia oxidizers
mgCOD/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4.46 0
PolyP heterotrophs
mgCOD/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3.9 0
Propionic acetogens
mgCOD/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 15.47 0
Acetoclastic methanogens
mgCOD/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 465.57 0
Hydrogenotrophic
methanogens mgCOD/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 249.43 0
Endogenous products
mgCOD/L 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 517.35 0.1
115
Slowly bio. COD (part.)
mgCOD/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 6864.2 0
Slowly bio. COD (colloid.)
mgCOD/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.83 0
Part. inert. COD mgCOD/L 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 1.09 0.05
Part. bio. org. N mgN/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 189.57 0
Part. bio. org. P mgP/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 72.03 0
Part. inert N mgN/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 339.88 0
Part. inert P mgP/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 106.82 0
Stored PHA mgCOD/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.69 0
Releasable stored polyP
mgP/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Fixed stored polyP mgP/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
PolyP bound cations mg/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.05 0
Readily bio. COD (complex)
mgCOD/L 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.58 0.7
Acetate mgCOD/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 88.61 0
Propionate mgCOD/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4.14 0
Methanol mgCOD/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Dissolved H2 mgCOD/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.02 0
Dissolved methane mg/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 31.15 0
Ammonia N mgN/L 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 339.57 0.05
Sol. bio. org. N mgN/L 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.88 1.02
Nitrite N mgN/L 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0 0.01
Nitrate N mgN/L 32.33 32.33 32.33 32.33 32.33 32.33 32.33 32.33 32.33 32.33 32.33 32.33 32.33 32.33 32.33 0 32.33
Dissolved nitrogen gas
mgN/L 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 14.32 0.03 14.32
PO4-P (Sol. & Me
Complexed) mgP/L 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 158.71 0.93
Sol. inert COD mgCOD/L 23.96 23.96 23.96 23.96 23.96 23.96 23.96 23.96 23.96 23.96 23.96 23.96 23.96 23.96 23.96 412.86 23.96
116
Sol. inert TKN mgN/L 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.84 0.69
Inorganic S.S. mgISS/L 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
2362.2
9 0.02
Struvite mgISS/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Hydroxy-dicalcium-
phosphate mgISS/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Hydroxy-apatite mgISS/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Magnesium mg/L 29.03 29.03 29.03 29.03 29.03 29.03 29.03 29.03 29.03 29.03 29.03 29.03 29.03 29.03 29.03 29.13 29.03
Calcium mg/L 78.96 78.96 78.96 78.96 78.96 78.96 78.96 78.96 78.96 78.96 78.96 78.96 78.96 78.96 78.96 79.07 78.96
Metal mg/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Other Cations (strong bases)
meq/L 4.96 4.96 4.96 4.96 4.96 4.96 4.96 4.96 4.96 4.96 4.96 4.96 4.96 4.96 4.96 16.94 4.96
Other Anions (strong acids)
meq/L 7.51 7.51 7.51 7.51 7.51 7.51 7.51 7.51 7.51 7.51 7.51 7.51 7.51 7.51 7.51 5.95 7.51
Total CO2 mmol/L 1.55 1.55 1.55 1.55 1.55 1.55 1.55 1.55 1.55 1.55 1.55 1.55 1.55 1.55 1.55 44.83 1.55
User defined 1 mg/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
User defined 2 mg/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
User defined 3 mgVSS/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
User defined 4 mgISS/L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Dissolved oxygen mg/L 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 0 2
117
APPENDIX E
Optimal sludge Feed Rate, Seed and Bicarbonate Addition for Model Run #1 to #6
Table E-1: F/M proportion sludge feed rate for Run #1, #2 and #3 - April to September,
2012
Day
Feed rate
m3/d
Food
kg/d
SRT
d
bCOD in
kg/d
bCOD out
kg/d
Mass
kg/d
Mass
cumulative
kg/d
Mass
regression
unitless
F/M
regression
unitless
Feed rate
calculation
kg/d
17-Apr 10 350 380 262.5 78.8 1.2 181.2 1.1 321 10.9
18-Apr 10 350 380 262.5 78.8 1.2 182.4 1.1 313.1 10.6
19-Apr 10 350 380 262.5 78.8 1.2 183.6 1.1 305.4 10.3
20-Apr 10 350 380 262.5 78.8 1.2 184.7 1.2 297.7 10.1
21-Apr 10 350 380 262.5 78.8 1.2 185.9 1.2 290.2 9.8
22-Apr 11 385 345.5 288.8 86.6 1.4 187.4 1.4 282.7 11.5
23-Apr 11 385 345.5 288.8 86.6 1.4 188.8 1.4 275.4 11.2
24-Apr 11 385 345.5 288.8 86.6 1.4 190.2 1.4 268.2 10.9
25-Apr 11 385 345.5 288.8 86.6 1.4 191.6 1.5 261.1 10.6
26-Apr 11 385 345.5 288.8 86.6 1.4 193.0 1.5 254.1 10.3
27-Apr 12 420 316.7 315.0 94.5 1.7 194.7 1.7 247.2 11.9
28-Apr 12 420 316.7 315.0 94.5 1.7 196.4 1.7 240.4 11.5
29-Apr 12 420 316.7 315.0 94.5 1.7 198.1 1.8 233.8 11.2
30-Apr 12 420 316.7 315.0 94.5 1.7 199.8 1.8 227.2 10.9
1-May 12 420 316.7 315.0 94.5 1.7 201.4 1.9 220.8 10.6
2-May 13 455 292.3 341.3 102.4 2.0 203.4 2.1 214.4 12.0
3-May 14 490 271.4 367.5 110.3 2.3 205.6 2.4 208.2 13.4
4-May 14 490 271.4 367.5 110.3 2.3 207.9 2.4 202.1 13.0
5-May 15 525 253.3 393.8 118.1 2.6 210.5 2.7 196.1 14.4
6-May 16 560 237.5 420.0 126.0 2.9 213.4 2.9 190.2 15.7
7-May 17 595 223.5 446.3 133.9 3.2 216.6 3.2 184.4 17.1
8-May 18 630 211.1 472.5 141.8 3.6 220.2 3.5 178.7 18.4
9-May 19 665 200.0 498.8 149.6 4.0 224.2 3.8 173.1 19.7
10-May 20 700 190.0 525.0 157.5 4.4 228.6 4.2 167.7 21.0
11-May 21 735 181.0 551.3 165.4 4.8 233.4 4.5 162.3 22.3
12-May 22 770 172.7 577.5 173.3 5.2 238.6 4.9 157.1 23.5
13-May 23 805 165.2 603.8 181.1 5.7 244.3 5.3 152.0 24.6
14-May 24 840 158.3 630.0 189.0 6.1 250.4 5.7 146.9 25.8
15-May 25 875 152.0 656.3 196.9 6.6 257.0 6.2 142.0 26.8
16-May 26 910 146.2 682.5 204.8 7.1 264.1 6.6 137.2 27.8
17-May 27 945 140.7 708.8 212.6 7.6 271.7 7.1 132.5 28.8
118
18-May 28 980 135.7 735.0 220.5 8.1 279.9 7.7 128.0 29.7
19-May 29 1,015 131.0 761.3 228.4 8.6 288.5 8.2 123.5 30.5
20-May 30 1,050 126.7 787.5 236.3 9.2 297.7 8.8 119.1 31.3
21-May 31 1,085 122.6 813.8 244.1 9.7 307.4 9.4 114.9 32.0
22-May 32 1,120 118.8 840.0 252.0 10.3 317.7 10.1 110.7 32.6
23-May 33 1,155 115.2 866.3 259.9 10.9 328.6 10.8 106.7 33.2
24-May 35 1,225 108.6 918.8 275.6 12.1 340.7 11.9 102.8 35.5
25-May 37 1,295 102.7 971.3 291.4 13.3 354.0 13.1 99.0 37.7
26-May 39 1,365 97.4 1,023.8 307.1 14.6 368.7 14.3 95.3 39.8
27-May 41 1,435 92.7 1,076.3 322.9 15.9 384.6 15.7 91.7 41.8
28-May 43 1,505 88.4 1,128.8 338.6 17.3 401.9 17.1 88.2 43.6
29-May 45 1,575 84.4 1,181.3 354.4 18.7 420.6 18.6 84.8 45.4
30-May 47 1,645 80.9 1,233.8 370.1 20.2 440.8 20.2 81.6 47.0
31-May 49 1,715 77.6 1,286.3 385.9 21.7 462.5 21.9 78.4 48.5
1-Jun 53 1,855 71.7 1,391.3 417.4 24.7 487.2 24.6 75.4 53.2
2-Jun 55 1,925 69.1 1,443.8 433.1 26.3 513.5 26.6 72.4 54.5
3-Jun 58 2,030 65.5 1,522.5 456.8 28.8 542.2 29.2 69.6 57.2
4-Jun 62 2,170 61.3 1,627.5 488.3 32.1 574.4 32.4 66.9 61.4
5-Jun 66 2,310 57.6 1,732.5 519.8 35.6 609.9 35.9 64.3 65.3
6-Jun 70 2,450 54.3 1,837.5 551.3 39.1 649.1 39.6 61.8 69.1
7-Jun 75 2,625 50.7 1,968.8 590.6 43.8 692.8 44.2 59.4 74.3
8-Jun 80 2,800 47.5 2,100.0 630.0 48.5 741.3 49.0 57.1 79.2
9-Jun 85 2,975 44.7 2,231.3 669.4 53.4 794.7 54.1 55.0 83.8
10-Jun 90 3,150 42.2 2,362.5 708.8 58.4 853.1 59.5 52.9 88.2
11-Jun 97 3,395 39.2 2,546.3 763.9 65.6 918.6 66.6 51.0 95.5
12-Jun 104 3,640 36.5 2,730.0 819.0 72.9 991.5 74.1 49.1 102.4
13-Jun 111 3,885 34.2 2,913.8 874.1 80.5 1072.0 81.9 47.4 109.0
14-Jun 118 4,130 32.2 3,097.5 929.3 88.2 1160.3 90.2 45.8 115.4
15-Jun 125 4,375 30.4 3,281.3 984.4 96.1 1256.4 98.8 44.3 121.6
16-Jun 132 4,620 28.8 3,465.0 1,039.5 104.1 1360.5 107.7 42.9 127.6
17-Jun 139 4,865 27.3 3,648.8 1,094.6 112.3 1472.7 116.9 41.6 133.4
18-Jun 146 5,110 26.0 3,832.5 1,149.8 120.5 1593.3 126.4 40.4 139.2
19-Jun 153 5,355 24.8 4,016.3 1,204.9 128.9 1722.1 136.0 39.4 144.9
20-Jun 160 5,600 23.8 4,200.0 1,260.0 137.3 1859.5 145.8 38.4 150.7
21-Jun 167 5,845 22.8 4,383.8 1,315.1 145.9 2,005.4 155.6 37.6 156.6
22-Jun 174 6,090 21.8 4,567.5 1,370.3 154.5 2,159.9 165.4 36.8 162.6
23-Jun 181 6,335 21.0 4,751.3 1,425.4 163.2 2,323.2 175.0 36.2 168.8
24-Jun 188 6,580 20.2 4,935.0 1,480.5 172.0 2,495.2 184.4 35.7 175.4
25-Jun 195 6,825 19.5 5,118.8 1,535.6 180.9 2,676.1 193.5 35.3 182.3
26-Jun 202 7,070 18.8 5,302.5 1,590.8 189.8 2,865.9 202.2 35.0 189.6
27-Jun 209 7,315 18.2 5,486.3 1,645.9 198.8 3,064.7 210.3 34.8 197.5
119
28-Jun 216 7,560 17.6 5,670.0 1,701.0 207.8 3,272.5 217.9 34.7 206.1
29-Jun 223 7,805 17.0 5,853.8 1,756.1 216.9 3,489.5 224.7 34.7 215.3
30-Jun 230 8,050 16.5 6,037.5 1,811.3 226.1 3,715.5 230.8 34.9 225.2
1-Jul 237 8,295 16.0 6,221.3 1,866.4 235.2 3,950.8 236.2 35.1 236.1
2-Jul 244 8,540 15.6 6,405.0 1,921.5 244.5 4,195.2 240.7 35.5 247.8
3-Jul 251 8,785 15.1 6,588.8 1,976.6 253.7 4,449.0 244.3 36.0 260.6
4-Jul 258 9,030 14.7 6,772.5 2,031.8 263 4,712.0 247.2 36.5 274.6
1-Apr to 16-Apr sludge feed rate 0 m3/d
5-Jul to 30-Sept sludge feed rate 275 m3/d
Table E-2: Flow proportion sludge feed rate for Run #4, #5 and #6 - April to September,
2012
Day Feed rate m3/d Day Feed rate m
3/d Day m
3/d Feed rate m
3
1-Apr 0 2-May 12 2-Jun 54
2-Apr 0 3-May 13 3-Jun 57
3-Apr 0 4-May 13 4-Jun 61
4-Apr 0 5-May 14 5-Jun 65
5-Apr 0 6-May 16 6-Jun 69
6-Apr 0 7-May 17 7-Jun 74
7-Apr 0 8-May 18 8-Jun 79
8-Apr 0 9-May 20 9-Jun 84
9-Apr 0 10-May 21 10-Jun 88
10-Apr 0 11-May 22 11-Jun 95
11-Apr 0 12-May 23 12-Jun 102
12-Apr 0 13-May 25 13-Jun 109
13-Apr 0 14-May 26 14-Jun 115
14-Apr 0 15-May 27 15-Jun 122
15-Apr 0 16-May 28 16-Jun 128
16-Apr 0 17-May 29 17-Jun 133
17-Apr 10 18-May 30 18-Jun 139
18-Apr 10 19-May 31 19-Jun 145
19-Apr 10 20-May 31 20-Jun 151
20-Apr 10 21-May 32 21-Jun 157
21-Apr 10 22-May 33 22-Jun 163
22-Apr 11 23-May 33 23-Jun 169
23-Apr 11 24-May 35 24-Jun 175
24-Apr 11 25-May 38 25-Jun 182
25-Apr 11 26-May 40 26-Jun 190
26-Apr 11 27-May 42 27-Jun 198
27-Apr 12 28-May 44 28-Jun 206
28-Apr 12 29-May 45 29-Jun 215
29-Apr 12 30-May 47 30-Jun 225
30-Apr 12 31-May 49 1-Jul 236
1-May 12 1-Jun 53 2-Jul 248
3-Jul 266
4-Jul to 30-Sept 266 m3/d
120
Table E-3: Seed sludge for 80 m3 Run #2 and #5 - April to September, 2012
Day 1-Apr to 15-Apr 16-Apr 17-Apr 18-Apr to30-Sept
Flow m3/d 800 40 40 0
Non-polyP heterotrophs mgCOD/L 0.01 354.54 354.54 0.01
Anoxic methanol utilizers mgCOD/L 0 3.63 3.63 0
Ammonia oxidizing biomass mgCOD/L 0 1.98 1.98 0
Nitrite oxidizing biomass mgCOD/L 0 1.98 1.98 0
Anaerobic ammonia oxidizers mgCOD/L 0 4.46 4.46 0
PolyP heterotrophs mgCOD/L 0 3.9 3.9 0
Propionic acetogens mgCOD/L 0 15.47 15.47 0
Acetoclastic methanogens mgCOD/L 0 465.57 465.57 0
Hydrogenotrophic methanogens mgCOD/L 0 249.43 249.43 0
Endogenous products mgCOD/L 0.1 517.35 517.35 0.1
Slowly bio. COD (part.) mgCOD/L 0 6864.2 6864.2 0
Slowly bio. COD (colloid.) mgCOD/L 0 0.83 0.83 0
Part. inert. COD mgCOD/L 0.05 1.09 1.09 0.05
Part. bio. org. N mgN/L 0 189.57 189.57 0
Part. bio. org. P mgP/L 0 72.03 72.03 0
Part. inert N mgN/L 0 339.88 339.88 0
Part. inert P mgP/L 0 106.82 106.82 0
Stored PHA mgCOD/L 0 0.69 0.69 0
Releasable stored polyP mgP/L 0 0 0 0
Fixed stored polyP mgP/L 0 0 0 0
PolyP bound cations mg/L 0 0.05 0.05 0
Readily bio. COD (complex) mgCOD/L 0.7 0.58 0.58 0.7
Acetate mgCOD/L 0 88.61 88.61 0
121
Propionate mgCOD/L 0 4.14 4.14 0
Methanol mgCOD/L 0 0 0 0
Dissolved H2 mgCOD/L 0 0.02 0.02 0
Dissolved methane mg/L 0 31.15 31.15 0
Ammonia N mgN/L 0.05 339.57 339.57 0.05
Sol. bio. org. N mgN/L 1.02 1.88 1.88 1.02
Nitrite N mgN/L 0.01 0 0 0.01
Nitrate N mgN/L 32.33 0 0 32.33
Dissolved nitrogen gas mgN/L 14.32 0.03 0.03 14.32
PO4-P (Sol. & Me Complexed) mgP/L 0.93 158.71 158.71 0.93
Sol. inert COD mgCOD/L 23.96 412.86 412.86 23.96
Sol. inert TKN mgN/L 0.69 0.84 0.84 0.69
Inorganic S.S. mgISS/L 0.02 2,362 2,362 0.02
Struvite mgISS/L 0 0 0 0
Hydroxy-dicalcium-phosphate mgISS/L 0 0 0 0
Hydroxy-apatite mgISS/L 0 0 0 0
Magnesium mg/L 29.03 29.13 29.13 29.03
Calcium mg/L 78.96 79.07 79.07 78.96
Metal mg/L 0 0 0 0
Other Cations (strong bases) meq/L 4.96 16.94 16.94 4.96
Other Anions (strong acids) meq/L 7.51 5.95 5.95 7.51
Total CO2 mmol/L 1.55 44.83 44.83 1.55
User defined 1 mg/L 0 0 0 0
User defined 2 mg/L 0 0 0 0
User defined 3 mgVSS/L 0 0 0 0
User defined 4 mgISS/L 0 0 0 0
Dissolved oxygen mg/L 2 0 0 2
122
Table E-4: Seed sludge 120 m3 for Run #1 and #4 - April to September, 2012
Day 1-Apr to 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr to 30-Sept
Flow m3/d 800 40 40 40 0
Non-polyP heterotrophs mgCOD/L 0.01 354.54 354.54 354.54 0.01
Anoxic methanol utilizers mgCOD/L 0 3.63 3.63 3.63 0
Ammonia oxidizing biomass mgCOD/L 0 1.98 1.98 1.98 0
Nitrite oxidizing biomass mgCOD/L 0 1.98 1.98 1.98 0
Anaerobic ammonia oxidizers mgCOD/L 0 4.46 4.46 4.46 0
PolyP heterotrophs mgCOD/L 0 3.9 3.9 3.9 0
Propionic acetogens mgCOD/L 0 15.47 15.47 15.47 0
Acetoclastic methanogens mgCOD/L 0 465.57 465.57 465.57 0
Hydrogenotrophic methanogens mgCOD/L 0 249.43 249.43 249.43 0
Endogenous products mgCOD/L 0.1 517.35 517.35 517.35 0.1
Slowly bio. COD (part.) mgCOD/L 0 6,864.2 6,864.2 6,864.2 0
Slowly bio. COD (colloid.) mgCOD/L 0 0.83 0.83 0.83 0
Part. inert. COD mgCOD/L 0.05 1.09 1.09 1.09 0.05
Part. bio. org. N mgN/L 0 189.57 189.57 189.57 0
Part. bio. org. P mgP/L 0 72.03 72.03 72.03 0
Part. inert N mgN/L 0 339.88 339.88 339.88 0
Part. inert P mgP/L 0 106.82 106.82 106.82 0
Stored PHA mgCOD/L 0 0.69 0.69 0.69 0
Releasable stored polyP mgP/L 0 0 0 0 0
Fixed stored polyP mgP/L 0 0 0 0 0
PolyP bound cations mg/L 0 0.05 0.05 0.05 0
Readily bio. COD (complex) mgCOD/L 0.7 0.58 0.58 0.58 0.7
Acetate mgCOD/L 0 88.61 88.61 88.61 0
123
Propionate mgCOD/L 0 4.14 4.14 4.14 0
Methanol mgCOD/L 0 0 0 0 0
Dissolved H2 mgCOD/L 0 0.02 0.02 0.02 0
Dissolved methane mg/L 0 31.15 31.15 31.15 0
Ammonia N mgN/L 0.05 339.57 339.57 339.57 0.05
Sol. bio. org. N mgN/L 1.02 1.88 1.88 1.88 1.02
Nitrite N mgN/L 0.01 0 0 0 0.01
Nitrate N mgN/L 32.33 0 0 0 32.33
Dissolved nitrogen gas mgN/L 14.32 0.03 0.03 0.03 14.32
PO4-P (Sol. & Me Complexed) mgP/L 0.93 158.71 158.71 158.71 0.93
Sol. inert COD mgCOD/L 23.96 412.86 412.86 412.86 23.96
Sol. inert TKN mgN/L 0.69 0.84 0.84 0.84 0.69
Inorganic S.S. mgISS/L 0.02 2,362.29 2,362.29 2,362.29 0.02
Struvite mgISS/L 0 0 0 0 0
Hydroxy-dicalcium-phosphate mgISS/L 0 0 0 0 0
Hydroxy-apatite mgISS/L 0 0 0 0 0
Magnesium mg/L 29.03 29.13 29.13 29.13 29.03
Calcium mg/L 78.96 79.07 79.07 79.07 78.96
Metal mg/L 0 0 0 0 0
Other Cations (strong bases) meq/L 4.96 16.94 16.94 16.94 4.96
Other Anions (strong acids) meq/L 7.51 5.95 5.95 5.95 7.51
Total CO2 mmol/L 1.55 44.83 44.83 44.83 1.55
User defined 1 mg/L 0 0 0 0 0
User defined 2 mg/L 0 0 0 0 0
User defined 3 mgVSS/L 0 0 0 0 0
User defined 4 mgISS/L 0 0 0 0 0
Dissolved oxygen mg/L 2 0 0 0 2
124
Table E-5: Bicarbonate addition for Run #3 and #6 - April to September, 2012
Run #3 Run #6
Day 16-Apr
25-Apr to
14-May Remainder 16-Apr
28-Apr to
17-May Remainder
Flow m3/d 0.50 0.50 0/d 0.50 0.50 0
Non-polyP heterotrophs
mgCOD/L 354.54 354.54 0.01 354.54 354.54 0.01
Anoxic methanol utilizers
mgCOD/L 3.63 3.63 0.00 3.63 3.63 0.00
Ammonia oxidizing biomass
mgCOD/L 1.98 1.98 0.00 1.98 1.98 0.00
Nitrite oxidizing biomass
mgCOD/L 1.98 1.98 0.00 1.98 1.98 0.00
Anaerobic ammonia oxidizers
mgCOD/L 4.46 4.46 0.00 4.46 4.46 0.00
PolyP heterotrophs mgCOD/L 3.90 3.90 0.00 3.90 3.90 0.00
Propionic acetogens
mgCOD/L 15.47 15.47 0.00 15.47 15.47 0.00
Acetoclastic methanogens
mgCOD/L 465.57 465.57 0.00 465.57 465.57 0.00
Hydrogenotrophic
methanogens mgCOD/L 249.43 249.43 0.00 249.43 249.43 0.00
Endogenous products
mgCOD/L 517.35 517.35 0.10 517.35 517.35 0.10
Slowly bio. COD (part.)
mgCOD/L 6,864.2 6,864.2 0.00 6,864.2 6,864.2 0.00
Slowly bio. COD (colloid.)
mgCOD/L 0.83 0.83 0.00 0.83 0.83 0.00
Part. inert. COD mgCOD/L 10,900 10,900 0.05 10,900 10,900 0.05
Part. bio. org. N mgN/L 189.57 189.57 0.00 189.57 189.57 0.00
Part. bio. org. P mgP/L 72.03 72.03 0.00 72.03 72.03 0.00
Part. inert N mgN/L 339.88 339.88 0.00 339.88 339.88 0.00
Part. inert P mgP/L 106.82 106.82 0.00 106.82 106.82 0.00
Stored PHA mgCOD/L 0.69 0.69 0.00 0.69 0.69 0.00
Releasable stored polyP
mgP/L 0.00 0.00 0.00 0.00 0.00 0.00
Fixed stored polyP mgP/L 0.00 0.00 0.00 0.00 0.00 0.00
PolyP bound cations mg/L 0.05 0.05 0.00 0.05 0.05 0.00
Readily bio. COD (complex)
mgCOD/L 0.58 0.58 0.70 0.58 0.58 0.70
Acetate mgCOD/L 88.61 88.61 0.00 88.61 88.61 0.00
Propionate mgCOD/L 4.14 4.14 0.00 4.14 4.14 0.00
Methanol mgCOD/L 0.00 0.00 0.00 0.00 0.00 0.00
Dissolved H2 mgCOD/L 0.02 0.02 0.00 0.02 0.02 0.00
Dissolved methane mg/L 31.15 31.15 0.00 31.15 31.15 0.00
Ammonia N mgN/L 339.57 339.57 0.05 339.57 339.57 0.05
Sol. bio. org. N mgN/L 1.88 1.88 1.02 1.88 1.88 1.02
125
Nitrite N mgN/L 0.00 0.00 0.01 0.00 0.00 0.01
Nitrate N mgN/L 0.00 0.00 32.33 0.00 0.00 32.33
Dissolved nitrogen gas mgN/L 0.03 0.03 14.32 0.03 0.03 14.32
PO4-P (Sol. & Me
Complexed) mgP/L 158.71 158.71 0.93 158.71 158.71 0.93
Sol. inert COD mgCOD/L 412.86 412.86 23.96 412.86 412.86 23.96
Sol. inert TKN mgN/L 0.84 0.84 0.69 0.84 0.84 0.69
Inorganic S.S. mgISS/L 2,362.29 2,362.29 0.02 2,362.29 2,362.29 0.02
Struvite mgISS/L 0.00 0.00 0.00 0.00 0.00 0.00
Hydroxy-dicalcium-phosphate
mgISS/L 0.00 0.00 0.00 0.00 0.00 0.00
Hydroxy-apatite mgISS/L 0.00 0.00 0.00 0.00 0.00 0.00
Magnesium mg/L 29.13 29.13 29.03 29.13 29.13 29.03
Calcium mg/L 84,500 84,500 78.96 84,500 84,500 78.96
Metal mg/L 0.00 0.00 0.00 0.00 0.00 0.00
Other Cations (strong bases)
meq/L 16.94 16.94 4.96 16.94 16.94 4.96
Other Anions (strong acids)
meq/L 5.95 5.95 7.51 5.95 5.95 7.51
Total CO2 mmol/L 44.83 44.83 1.55 44.83 44.83 1.55
User defined 1 mg/L 0.00 0.00 0.00 0.00 0.00 0.00
User defined 2 mg/L 0.00 0.00 0.00 0.00 0.00 0.00
User defined 3 mgVSS/L 0.00 0.00 0.00 0.00 0.00 0.00
User defined 4 mgISS/L 0.00 0.00 0.00 0.00 0.00 0.00
Dissolved oxygen mg/L 0.00 0.00 0.00 0.00 0.00 0.00