Bijou Erosion Control ProjectProject Kickoff TAC Meeting
May 4, 2007
City of South Lake TahoeENTRIX, Inc.
California Tahoe Conservancy
Project Planning Process
Existing Conditions• Bijou ECP ECAM
– “We are not starting at the beginning, we are picking up and finishing what has been started”
• East Pioneer Trail Watershed Hydrology Study– History of Project/Study– Status of Project/Study– Future of Project/Study
Existing Conditions Memorandum
East Pioneer Trail Watershed Hydrology Study
Items/sections to be completed– Updated Base Map– Drainage Conveyance/Problem
Flooding Area Summary– Land Capability Verification– Existing Vegetation Summary– Environmental Resources– Utility Mapping– Photo Monitoring– Groundwater Monitoring– Surface Water Monitoring
Completed items/sections– Watershed Map– Drainage Map– Pollutant Source Summary– Pollutant Load Estimates– Land Use Map– Ownership Map– Precipitation Data– Soils and Geology Summary– Impervious Area Summary– Hydrologic Model– Initial Stream Stability
Assessment
Project Planning Process
SWQIC Process (Watershed)• Existing Conditions• Monitoring Plan Development• Formulation of Alternatives• Evaluation of Alternatives• Selection and Development of
Preferred Alternative• Construction Phasing Plan
Implementation Process (Phased)• 30% Design• Environmental Documentation• 60% Design• 75% Design• 90% Design• Project Permit Applications• Final Construction Documents
Existing ConditionsMay 2007 thru
September 2007
Formulation of AlternativesSeptember 2007
Thru March 2008
Evaluation of AlternativesMarch 2008
Thru May 2008
Selection ofRecommended
AlternativeMay 2008 thru
June 2008
Development of Recommended Alternative(30% plans)
June 2008 thruSeptember 2008
Phase 1 Design,Environmental,
and PermitsSeptember 2008 thru
April 2009
Phase 1 Construction Summer 2009
Project Schedule
TAC InvolvementKey TAC Involvement Times (Commitment)• Existing Conditions Memo Review/Meeting
– Late August 2007
• Formulation of Alternative Mapping Review/Meeting– Early December 2007
• Formulation of Alternatives Memo Review/Meeting– Early February 2008
• Evaluation of Alternatives Memo Review/Meeting– Mid April 2008
• 30% Design Review/Meeting– Mid August 2008
• 60% Design Review/Meeting– Late November 2008
• 90% Design Review/Meeting– Mid February 2009
Q & A
City of South Lake TahoeENTRIX, Inc.
California Tahoe Conservancy