Parallel Big Bowl CD 600 Slim Line Hydraulic Centrifuges Installed onboard Ensco 107 at KFEL
Shipyard Singapore for Premier Oil Vietnam
CHALLENGES
Limited deck space on shaker module roof.
Share of shaker module roof with MWD / Logging Containers
Big bowl Centrifuges had to fit the same footprint deck space for duel standard 518 centrifuges
Due to combined weight of the centrifuges / MWD & Logging containers the Shaker module had to have additional strengthening carried out
Centrifuge support frame required Ensco Engineering and ABS approval, structural analysis to withstand towing conditions
Due to wide load road limitations in Singapore the Centrifuge support frame was designed as pre fabricated modular flanged sections which also reduced hot work requirements during install with consideration for a cold work de mobilization on
completion of contract
A total of 8 sacrificial welded anchor pads were fitted and to compensate for deck deviations the tie brackets were designed to adjust height prior to welding down the
sacrificial Anchor pad, The solids hoppers were pre fabricated and were flanged for ease of install and de mob multiple spray bars and Teflon sheets fitted internal to ensure the large
volume of solids discharged from the big bowl centrifuges are flushed freely overboard
Positioning and securing the Centrifuge Bowl frames to base frame
Positioning and securing the 2 pre fabricated support frames for the Centrifuge Hydraulic Power packs which will be located on the upper level of the frame
Installation of the pre fabricated walk ways / hand rails and access ladder to the Hydraulic power pack platform,
Centrifuge Hydraulic Power Packs positioned and secured on the upper level of support frame, the only hot work required to get to this stage was the 8 sacrificial anchor pads, matching
flanges for the 2 solids hoppers and deck flanges for the 2 feed tube lines everything else is flanged and bolted
Left Picture showing the hard pipe feed line tie in with certified crimped flanged jumper hoses to the feed tubes.
Right picture showing PLC touch screens mounted on substantial support frame with rubber vibration dampers also shown is the ABS approved removable sea fasteners that
are installed when rig is on tow to location pictures taken after commissioning
Centrifuge feed pumps positioned and secured Hard pipe suction and discharge lines with certified crimped flanged jumper hoses on the discharges