Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
BEST VALUE MODEL FOR PUBLIC PRIVATE PARTNERSHIP
INFRASTRUCTURE PROJECTS IN MALAYSIA
MUHAMMAD MUSTAPHA GAMBO
A thesis submitted in
fulfillment of the requirement for the award of the
Doctor of Philosophy in Real Estate and Facilities Management
Faculty of Technology Management and Business
Universiti Tun Hussein Onn Malaysia
JULY 2015
iii
DEDICATION
To my late father, Alhaji Gambo Dauda Paiko, may ALLAH (S.W.A) make
AL JANNAH to be your final abode.
iv
ACKNOWLEDGEMENT
All praise be to ALLAH, the most exalted and the most high, and to whom we
all depend for sustenance and cherishment. My heartfelt thanks and gratitude extend to
all the people who have contributed in any capacity either intellectually or emotionally
throughout the three and half years of my doctoral studies.
First and foremost, I would like to express my deepest gratitude to my supervisor
Associate Professor Dr Christy Pathrose Gomez for his valuable supervision during the
entire period of my research study in Universiti Tun Hussein Onn Malaysia.
I would also like to thank the management of Universiti Tun Hussein Onn Malaysia for
offering me the Graduate Research Project Grant Incentive Scheme (Vote No. 0819) and
the International Students Scholarship for the duration of this program. Furthermore, I
would also like to thank the entire academic and non-academic staff of the Faculty of
Technology Management and Business also the Graduate School for their support.
Most importantly, I would like to express my immense gratitude to my mother, Hajiya
Zainab Salihu for all the love, moral support and prayers.
I would also like to express my heartfelt gratitude to my brothers and sisters, for all their
constant support and prayers, also to my brothers and sisters in law, and lastly to all my
uncles, aunties, nieces and nephews.
My special thanks to my friends who were jointly pursuing their postgraduate studies in
Malaysia, Ahmad Hussaini Jagaba, Muhammad Yahaya Musa, Ashwin Narendra Raut,
Mansur Dodo, Abdulazeez Umar Raji, Ibrahim Salihu Anka, Abdulnasir & Nuhu Isah
and all those whose names have not been stated here, i wish to thank them for their
support. And also to my friends in Nigeria; Adamu Sambo, Bazallahi Muhammad,
Usman Sulaiman and many others, thank you.
v
ABSTRACT
The rapid human population growth rate coupled with the need for improved
infrastructure project delivery has necessitated the participation of private sector for the
procurement of such projects. Public Private Partnerships (PPP) is one such private
sector driven procurement approach which has evolved to serve the growing demand for
infrastructure development in Malaysia. However, the Value for Money (VfM)
evaluative aspect of the PPP procurement form has faced criticism. Much of the
criticism is directed to the PPP practice being riddled with issues identified as being
related to the ineffective structuring of the private sector led project-specific Special
Purpose Vehicle (SPV) to deliver VfM. Exploratory preliminary research findings
indicate that there is a lack of overall long-term strategic focus by the SPV for
delivering VfM objectives in PPP projects. Questionnaire survey data was obtained from
a purposive sample of 48 public and private PPP practitioners in Peninsular Malaysia to
determine the needed skills (core skills) and critical success factors (CSFs) required by
the SPV to achieve their VfM objectives for PPP projects, and hence the successful
delivery of PPP projects. The aim of the research is to develop a conceptual tool for
delivering Best Value (BV) on PPP infrastructure projects. The notion of „skill sets‟ is
used as a means to scope the capability necessary with respect to agreed planning targets
on specific projects. A Best Value PPP conceptual framework is developed as a heuristic
tool for managers which proposes the embedding of the VfM aligned PPP SPV
organizational skills into the operational structure of the SPV and then effecting the SPV
organizational strategic measures according to the four perspectives of the Balanced
Scorecard performance measurement strategy with respect to the CSFs. Drawing on the
understanding that VfM objectives are critical denominators for effective PPP project
delivery, this research will influence the development of appropriate guidelines for the
effective structuring of the SPV‟s to enable the delivery of enhanced VfM objectives in
the form of BV for PPP concession projects.
vi
ABSTRAK
Kepesatan peningkatan bilangan penduduk serta keperluan kemajuan dalam persediaan
infrastruktur telah memerlukan penglibatan pihak swasta dalam proses perolehan
projek-projek tersebut. Perkongsian Awam Swasta atau Public Private Partnership
(PPP) adalah salah satu kaedah perolehan berdasarkan penglibatan pihak swasta yang
telah berkembang bagi tujuan memenuhi keperluan peningkatan penyediaan
infrastruktur di Malaysia. Walaubagaimanapun penilaian berdasarkan konsep Nilai
Untuk Wang atau Value for Money (VfM) berkaitan dengan kaedah perolehan PPP telah
banyak menerima kritikan. Kebanyakan kritikan ini ditumpu pada pengamalan PPP
yang telah dikenalpasti dengan isu yang melibatkan kurang berkesannya struktur
Syarikat Tujuan Khas atau Special Purpose Vehicle (SPV) yang ditubuhkan oleh pihak
swasta bagi tujuan menunaikan tanggungjawab memenuhi kriteria VfM. Dapatan kajian
penerokaan awalan menunjukkan bahawa kurangnya fokus jangka panjang yang
strategik oleh SPV dalam mencapai objektif-objektif VfM bagi projek PPP di Malaysia.
Data hasil kaji selidik yang melibatkan „sampel bertujuan‟ (purposive sample) yang
terdiri daripada pengamal PPP swasta dan awam telah dikumpul bagi tujuan
mengenalpasti kemahiran yang diperlukan serta faktor-faktor kejayaan kritikal yang
harus diperolehi oleh SPV bagi tujuan mencapai objektif-objektif VfM serta memastikan
kejayaan projek infrastruktur berjenis PPP. Satu rangkakerja konseptual Nilai Terbaik
atau Best Value (BV) yang terdiri daripada Elemen-elemen Kemahiran Syarikat SPV
untuk mencapai objektif-objektif VfM dalam struktur operasinya SPV serta penubuhan
langkah-langkah strategik SPV mengikut perspektif pelaksanaan strategik Balanced
Scorecard (BSC) telah dihasilkan. Tujuan kajian ini adalah untuk membangunkan
model konsepsual bagi menyampaikan Best Value (BV) projek-projek infrastruktur PPP.
Set Kemahiran digunakan untuk tujuan mengenalpasti keupayaan yang diperlukan
berkenaan dengan sasaran perancangan yang telah di persetujui seiring dengan projek-
vii
projek tertentu. Berdasarkan kefahaman bahawa objektif VfM adalah asas yang kritikal
bagi tujuan menyempurnakan projek PPP, kajian ini dijangka akan mempengaruhi
pembentukkan garis panduan yang sesuai bagi tujuan membentukkan struktur organisasi
SPV supaya dapat mencapai objektif VfM dengan lebih berkesan yang dapat dihasilkan
dalam bentuk BV bagi projek konsesi PPP.
viii
CONTENTS
TITLE i
DECLARATION ii
DEDICATION iii
ACKNOWLEDGEMENT iv
ABSTRACT v
ABSTRAK vi
CONTENTS viii
LIST OF TABLES xiv
LIST OF FIGURES xvi
LIST OF SYMBOLS AND ABBREVIATIONS xvii
LIST OF APPENDICES xviii
CHAPTER 1 INTRODUCTION 1
1.1 Background of the study 1
1.1.1 The role of the SPV organization
in the delivery of PPP infrastructure project 6
1.2 Problem statement 9
1.3 Research questions 11
1.4 Aim of the research 12
1.5 Objectives of the research 12
1.6 Scope of the research 13
1.7 Significance of the research 13
1.8 Limitations of the research 14
1.9 Organization of the thesis 14
ix
CHAPTER 2 LITERATURE REVIEW 16
2.1.1 Infrastructure projects as it relates to social
and economic development 16
2.1.2 Categorization and characterization of
infrastructural facilities 17
2.1.3 The role of infrastructure to national development 18
2.1.4 Need for private sector participation in the provision
of infrastructure facilities 19
2.2 The business philosophy behind public and private
sector collaboration in infrastructure delivery 21
2.2.1 Public-private partnership as a means of
collaboration for infrastructure delivery 21
2.2.2 Distinction between public – private – partnerships,
privatization and private finance initiative 23
2.2.3 Forms of PPP for delivering infrastructure projects 26
2.3 Key project participants in PPP project delivery 31
2.3.1 Advantages and disadvantages of the PPP form
of infrastructure delivery with respect
to the stakeholders 32
2.4 Contractual relationships in PPP 35
2.4.1 Agreements in the PPP contract 36
2.5 Tendering procedures in the PPP form
of infrastructure delivery 40
2.5.1 Procedures for PPP tendering 40
2.5.2 Criteria for private partner selection in
PPP tendering 43
2.5.3 Best value source selection in PPP 45
2.5.4 Public sector comparator 47
2.6 Risk management in the PPP form
of infrastructure delivery 47
2.6.1 PPP risks in developing countries 48
x
2.6.2 Risk allocation in PPP projects 49
2.7 Value for money approach for PPP
infrastructure projects 52
2.7.1 VfM drivers in PPP 54
2.7.2 Value management in project delivery 55
2.7.3 Best value approach in PPP infrastructure projects 56
2.8 Skills sets for SPV organizations in
PPP infrastructure project delivery 58
2.9 Success factors for PPP infrastructure projects 61
2.9.1 Critical success factors for Public–Private
Partnerships identified in previous studies 62
2.10 Performance measurement techniques 65
2.10.1 Balanced scorecard performance measurement
methodology 66
2.10.2 The four perspectives of the Balanced scorecard 69
2.11 Malaysian economy and the focus on private sector
participation in infrastructure delivery 71
2.11.1 Infrastructure development in Malaysia 72
2.11.2 PPP form of infrastructure delivery in Malaysia 73
CHAPTER 3 RESEARCH METHODOLOGY 77
3.1 Introduction 77
3.2 Research approaches 77
3.3 Research framework 79
3.3.1 Secondary research data 81
3.3.2 Pilot study 81
3.3.2.1 Pilot study research strategy 82
3.3.2.2 Selecting the pilot study respondents 83
3.4 Primary research questionnaire survey 85
3.4.1 Collection of research data through the
questionnaire survey 85
xi
3.4.2 Questionnaire survey sampling 87
3.5 Research aim and objectives and approaches
adopted to achieve them 89
CHAPTER 4 RESULTS AND DISCUSSIONS 92
4.1 Introduction 92
4.2 Pilot study questionnaire survey 97
4.2.1 Analysis and result of pilot study questionnaire
survey 94
4.2.2 Pilot study semi structured interviews 95
4.2.3 Pilot study conclusions 98
4.3 Phase 2: Primary research analysis
and discussion 100
4.3.1 Phase 2: Primary objective one analysis and
and discussion 100
4.4 Phase 2: Primary objectives 2 and 3 questionnaire
survey findings analysis and discussion 106
4.4.1 Phase 2: Primary objective two: Determining
the SPV organization skills required for PPP
project delivery 108
4.4.2 PPP SPV organization skills survey data
analysis and results 110
4.4.2.1 Factor analysis for skill sets for the SPV
organization in PPP infrastructure projects 115
4.5 Phase 2: Primary objective three 120
4.5.1 PPP CSF‟s for SPV organizations
questionnaire survey data analysis and results 122
xii
CHAPTER 5 PPP BEST VALUE FRAMEWORK
DEVELOPMENT AND ITS VALIDATION 133
5.1 Introduction 133
5.2 BV conceptual framework for PPP
infrastructure projects 134
5.3 PPP BV framework validation 140
5.3.1 Design of the conceptual PPP BV framework
validation questionnaire 141
5.3.2 Framework validation respondents
characteristics 141
5.3.3 Results of the PPP BV framework validation
survey 143
CHAPTER 6 CONCLUSIONS AND RECOMMENDATIONS 146
6.1 Introduction 146
6.2 Review of the research objectives 146
6.3 Research findings 148
6.3.1 Preliminary objective 148
6.3.2 Undertaking a comparison between different
forms of PPP with regards to their effectiveness
(appropriateness) in terms of achieving VfM
objectives for PPP projects in Malaysia 149
6.3.3 Determining the skills required by the SPV
organization for effective PPP projects
delivery 150
6.3.4 Determining the CSF‟s to enable the SPV
organizations to achieve their VfM objectives
in PPP delivery in Malaysia aligned to the
BSC methodology 152
xiii
6.3.5 Developing a conceptual framework to
enable the effective structuring of SPV
organizations for the delivery of BV
objectives for PPP projects 153
6.4 Value, significance and implications
of the research 154
6.5 Limitations of the research and
recommendations for future studies 155
REFERENCES 157
APPENDICES 178
xiv
LIST OF TABLES
2.1 Categorization of infrastructure facilities and their
related associated features 17
2.2 Distinction between PPP, privatization, corporatization
and PFI 25
2.3 Summary of the features for the various PPP types 30
2.4 Roles of different stakeholders in the PPP process 31
2.5 Interests of Stakeholders in the PPP Process 32
2.6 Advantages of the PPP form of Infrastructure delivery
with respect to the stakeholders 33
2.7 Disadvantages of the PPP form of infrastructure delivery
with respect to the stakeholders 34
2.8 Criteria for bid evaluations 44
2.9 Risk matrix for PPP infrastructure projects 51
2.10 SPV organization skills for PPP infrastructure
project delivery 60
2.11 Summary of CSF‟s for PPP infrastructure projects
according to the BSC perspectives 64
2.12 Economic transformation of Malaysia 75
2.13 Details of some existing PPP projects in Malaysia 76
3.1 Pilot study respondents profile 84
3.2 Questionnaire survey respondents profile 87
4.1 Ten PPP SPV organization skills ranking 94
xv
4.2 VfM objectives for all forms of PPP projects 103
4.3 PPP rationality domain in terms of VfM 105
4.4 Perception of survey respondents concerning the
relative importance of the SPV organization skills for
PPP infrastructure projects delivery 111
4.5 Perception of public and private sector respondents
concerning the relative importance of the SPV organization
skills for PPP infrastructure projects delivery 114
4.6 Factor loading of SPV organizational skills for the
delivery of PPP infrastructure projects 116
4.7 Perception of survey respondents concerning the relative
importance of SPV organization CSF‟s to deliver VfM
in PPP projects based on the BSC methodology 124
4.8 Perception of public and private sector respondents
concerning the relative importance of the SPV
organization CSF‟s to deliver VfM in PPP projects
based on the BSC methodology 129
5.1 Strategic objectives and measures for the SPV
organization in delivering BV objectives in PPP
projects adopting the BSC performance
measurement methodology 137
5.2 Details of survey respondents for the SPV BV
conceptual framework for PPP infrastructure projects 140
5.3 SPV BV conceptual framework for PPP
project validation survey results 143
5.4 SPV BV conceptual framework for PPP project
validation survey results 144
6.1 Tools adopted to achieve research objective 148
xvi
LIST OF FIGURES
1.1 Annual investment of infrastructure projects with private
participation in developing countries between 1990
and 2006 4
1.2 SPV structure in PPP 7
2.1 The relationship between infrastructure to economic
growth and improving welfare of the citizenry 18
2.2 Infrastructure provision under the public sector in the early
1990s - the annual costs of mis-pricing and inefficiency 20
2.3 PPP contractual relationship 35
2.4 The PPP tendering stages up to financial close 41
2.5 Economy and efficiency considerations as part of
value for money 53
2.6 The relationship between success factors, project
performance and project success 61
2.7 The four perspectives of the Balanced scorecard 69
2.8 PPP chronology in Malaysia 74
3.1 Research design 78
3.2 Research process flow chart 80
3.3 Pilot study framework 82
4.1 Methodological flow to achieve the effective adoption of
PPP options to deliver project specific VfM objectives using
the PPP rationality domain in terms of VfM categorization 102
4.2 Flow chart describing the analysis of objectives 2 and 3 107
5.1 SPV BV conceptual framework for PPP project delivery 139
xvii
LIST OF SYMBOLS AND ABBREVIATIONS
PPP - Public private partnership
SPV - Special purpose vehicle
VfM - Value for money
BV - Best Value
W - Summation of the weighing to each skill
A - Highest ranking
N - Total number of respondents for that skill
xviii
LIST OF APPENDICES
APPENDIX TITLE PAGE
1 List of Publications 178
2 SPSS results 180
3 Data collection instruments 198
CHAPTER 1
INTRODUCTION
1.1 Background of the study
Effective infrastructure is being considered as an important aspect of every nation‟s
economy towards realizing its full potential of becoming a developed nation. According
to Sanghi et al., (2007), effective infrastructure plays a major role in determining the
success of the key sectors of every economy, and also the provision of effective
infrastructure in housing, water, energy and transport which are critical in achieving
improved standard of living and also helps towards poverty reduction.
The growing participation of the developing nations in the free market system
and also their active participation in the world economy has necessitated the need for
improved infrastructural facilities to enable a sustained economic development.
However, it is a known fact that these nations cannot effectively cope with the huge
capital investments needed for the provision of these infrastructures (Pongsiri, 2002;
Jamali, 2004).
2
Governments primarily face an ever increasing need to find sufficient financing to
develop and maintain infrastructure required to support growing populations.
Traditionally, this has been the reason for the private sector participation in resolving the
infrastructure challenges facing the public sector (Cheung & Kajewski, 2010; Akintoye
et al., 2005); which was originally initiated under the banner of privatization and
subsequently Public Private Partnerships (PPP).
As nations continue to witness a shortfall in the funds available for the provision
of public infrastructure, PPP is being considered as an effective means of mitigating the
problem of insufficient capital provided for the execution of infrastructure projects. The
private capital that is being injected into the provision of such projects can go a long
way in reducing the major risks that are being associated with the delays in progress
payments by public clients. Thus, this will improve the effectiveness of the fiscal
responsibilities of the government departments (Pongsiri, 2002; Akintoye et al., 2005;
Huang et al., 2005), which is considered to be one of the key challenges faced by wholly
public financed projects.
PPP can be described as a form of procuring public infrastructure which has
evolved to solve infrastructural deficits. It is a system which is primarily aimed at
achieving the best output possible by pulling together and mobilizing of funds,
technologies, managerial skills, operational efficiencies and facilitating innovations that
exists in the private sector (Njikamp et al., 2002; Zhang, 2005). Basically, this is
achieved by the transfer of the risks and responsibilities that are being associated with
the provision of such infrastructure to the private sector. As noted by Pongsiri (2002),
PPP provides a means of collaboration between the public and private sector in order to
pursue common goals of providing infrastructural facilities, while taking advantage of
the resources, strengths, competencies and capabilities that do exists in the public and
private sectors.
According to Walker et al., (1995) the several advantages that PPP offers as a
means of procuring public infrastructure includes:
3
a) The achievement and maintenance of a balance risk return structure as a result of
the private sector participation in the provision of such public infrastructure,
thereby utilizing the private sector capability of providing effective services.
b) The private sector is known in possessing better mobility than the public sector,
as it is known to offer cost savings in projects in such aspects as planning,
design, construction and eventually, operation. Furthermore, it offers additional
advantages of mitigating and relieving all the bureaucracies and administrative
burden that is associated with the public provision of infrastructural facilities and
services.
c) Additionally, the private sector participation of providing infrastructure relieves
the government of the huge financial burden that is associated with large scale
infrastructure projects, as the government is known to be lacking in providing
such huge resources that are required in the provision of such projects.
However, despite these advantages of the PPP, the infrastructure delivery
approach is also known to have its disadvantages. Which these includes high tendering
costs, payments of high operating costs by the public sector for rentals and leases, and
also the costs savings achieved by the private sector are being retained as profits rather
than passed on to the public sector (New Zealand Treasury, 2006; Gunawasa, 2012). Of
late, PPP form of procurement for delivering services has progressed into various
sectors of industry. Hence, other advantages that the PPP offers include enabling the
government to focus on the provision of such social services as pension, health and
education.
Traditionally, PPP projects were viewed as a feasible option for countries
wanting to provide infrastructure facilities whilst being financially strapped, as in the
case of many developing countries. The use of PPP as a means of providing
infrastructure dates back to as far back as the 17th century, where the private sector was
involved in the executioning of infrastructure projects like road tolling in the form of
turnpikes in America and the United Kingdom (UK), and also public water systems in
France. But then, it was only during the 1990‟s that the system became prominent where
the Private Finance Initiative (PFI) became a well-known method of delivering public
4
infrastructure and services especially in the UK (Grimsey & Lewis, 2007; Cheung &
Kajewski, 2010). PPP was first launched in the form of PFI in 1992 by the UK
government with the main aim of getting infrastructural projects off the public balance
sheet, cutting public spendings and also mitigating the constraints associated with the
borrowing limits of the public sector (Li et al., 2005). Since then, the system became a
globally adopted approach for delivering public infrastructure projects. PPP
infrastructure projects accounts for approximately 15 per cent of expenditure in
infrastructure in the UK and 8 per cent in Australia (Ernst & Young, 2005). The system
has also played a significant role in the provision of infrastructural projects and services
in developing nations, where the level of annual investments in infrastructure projects
by PPP in such countries has continued to grow consistently right from 1990 as shown
in Figure 1.1.
Figure 1.1: Annual investment of infrastructure projects with private participation in
developing countries between 1990 and 2006 (World Bank, 2007).
As described in the figure above, there had been a steady rise in private sector
investment in infrastructure from 1990 to 1997. Whereas from the year 1998 up to 2002,
there was a fall in investments as a result of the 1997 Asian financial crises (FRBSF,
5
2015). Malaysia is considered a newly industrialized market economy with an annual
growth rate of about 5-7%, this makes it the 3rd largest economy in South East Asia and
the 28th in the world (World Bank, 2012). In 2010, Malaysia launched the New
Economic Model (NEM) which aims for the nation to achieve a high income and fully
developed status by the year 2020. Consequently, with this status that the nation seeks to
achieve massive investment is required in order to have world class infrastructural
facilities which befits that of a fully developed nation. However, it is apparent that the
government on its own cannot provide such investment as there is increased shortage of
funds that are required to finance the provision of such infrastructure (Ismail & Rashid,
2014). Moreover, the main idea behind the NEM is to propel economic growth that is
primarily driven by the private sector, so as to ensure the utilization of the efficiency,
expertise and technical know how that is associated with the private sector (World Bank,
2012; EPU, 2010). This then warrants a mechanism such as PPP to serve as the vehicle
towards achieving the much needed private sector particpation in the delivery of the
necessary infrastructural facilities.
In Malaysia, PPP has enabled the implementation of large-scale infrastructure
projects, such as highways, bridges and energy projects. This appears to be mainly due
to the ability of the private sector to raise massive funds and also by enhancing the role
of the public entity in terms of effectively managing regulatory and policy issues. On the
whole, the concept of PPP has contributed greatly to the infrastructure development in
Malaysia within the last 29 years (Ismail et al., 2009). This is besides the fact that there
have been a few problematic instances related to PPP mode of infrastructure delivery.
Examples of which are the Indah Water Consortium that was set up to handle the
national sewerage system and also the Selangor Mass Housing project which was
initiated in order to achieve the zero squatter policy (Abdul-Aziz & Kassim, 2011; El-
Gohary et al., 2006).
In general, due to the known benefits that the PPP offers towards the provision
of infrastructural facilities and services, the PPP procurement system in Malaysia is
becoming increasingly popular in both the procurement of new infrastructural projects
and also the management and operations of existing ones. PPP as a project delivery
approach is characterized by having different forms, and these distinction in terms of the
6
PPP variations mainly refers to its representation as it relates to the major components
that describes the PPP as means of achieving the client‟s objective of having a built
infrastructure project. According to UNESCAP (2009), PPP forms can be mainly
described in terms of ownership of the project‟s capital assets, responsibility for
investment, assumption and apportionment of risks, and lastly the duration of the
contract, i.e the concessioning period. Moreover, the PPP arrangement involves a host
government/public sector granting a concession to a private consortium
(concessionaire), which is in the form of an independent business entity known as a
Special Purpose/Project Vehicle (SPV).
1.1.1 The role of the SPV organization in the delivery of PPP infrastructure
project
The creation of the SPV which is considered a separate commercial venture is a key
feature for the implementation of the PPP for delivering infrastructure projects. The
SPV is a new standalone firm that owns and manages the infrastructure assets until the
investment costs are recuperated. The SPV is managed by a sponsor or an equity
investor responsible for bidding, developing, and managing the PPP infrastructure
project throughout the concessioning period (ADB, 2008). Hence, the SPV is
fundamentally a legal entity that undertakes a project and negotiates contract agreements
with other parties including the government.
In a more specific sense, a SPV is an independent commercial entity established
under the relevant statutory act of a country where the PPP infrastructure project is to be
domiciled. The SPV is set up through an agreement (which is also known as
memorandum of association) between the shareholders or sponsors that are saddled with
the responsibility of providing the needed funds and the eventual execution and
managing the PPP infrastructure project throughout the concessioning period. The
shareholders agreement sets out the basis on which the SPV company is established,
giving such details as its name, ownership and organizational structure, management
control and corporate matters, authorized share capital and the extent of the liabilities of
its members. The authorized share capital is the maximum amount of equity capital,
7
measured at par value, by which the SPV company is allowed to raise by issuing shares
to existing or potential shareholders (or investors). Furthermore, other details that are
spelt out in the agreement are issues related to how the shareholders of the SPV can be
granted special privileges on matters such as elections to the company‟s board, the right
to purchase new shares issued by the company and the right to share in distribution of
the company‟s income (UNESCAP, 2009).
According to UKAS (2009), the roles of the SPV in the delivery of PPP
infrastructure projects include the following:
a) Raising the funds to develop and maintain the assets;
b) Making payments to the subcontractors, financiers and other creditors;
c) Delivering the agreed services to the public sector according to the levels,
quality and timeliness of the service provision throughout the contract
period;
d) Ensuring the assets are well maintained and available for use throughout the
concession period;
e) Ensuring that revertible assets/facilities are transferred in the specified
condition (good working order) to the public sector at the end of the
concession period.
Figure 1.2: SPV structure in PPP
Source: Indian PPP guide (2007)
8
Figure 1.2 represents the PPP structure as it relates to the interlinking relationships
between the private sector led SPV organization and the various stakeholders involved
in the PPP project delivery.
In the PPP mode of delivering infrastructure facilities, the SPV in most cases has
the responsibility to finance, design, build, and subsequently operate and maintain the
infrastructure project for a set period of time known as the concession period. The
sources of financing that are available to fund the infrastructure project through PPP
includes obtaining loan facilities from financial institutions such as commercial banks,
multilateral development banks (MDB‟s), and also funds from export credit agencies
(ECA‟s).
Additionally, the SPV can raise the needed funds for the PPP infrastructure
project by offering shares to the public which in turn enables them to have an equity
stake in the SPV unit. In the PPP form of infrastructure delivery, the SPV enters into
further subcontract agreements with the contractors and operators/facilities managers
who have the responsibility of executing the construction of the needed infrastructure
project and that of operating and managing the project upon completion respectively.
Moreover, the services of experts/strategic consultants are also engaged who are
expected to perform some of the following roles among others: responsibilities of
reviewing the existing framework and propose reforms, acting as facilitators for co-
operation among stakeholders and also providing unbiased evaluation of options for PPP
(World Bank, 2006; Booth & Skilling, 2007).
Payments to the SPV to fund debt service normally commence after the
completion of the construction when the services have been made available to the public
for use, and the debt servicing is facilitated through the services of an escrow agent,
which is an entity that holds and transfers payments pursuant to the instructions of the
parties involved. During the operating period, the SPV receives income (in form of the
tariffs paid by the users) based on the usage of the facility, then at the end of the
concessioning period, the fully operational project is transferred back to the host
government, usually at nominal or no cost (ADBI, 2009; Price Water House Coopers,
2010). The fundamental principle of securing projects using the PPP mode of delivery is
9
to maximize the benefits for the public wherein the PPP mode of delivery is found to
have a greater value compared to the traditional public sector mode of delivery.
1.2 Problem statement
In the PPP form of delivering infrastructure projects, value for money (VfM) is
considered a pivotal requirement when adopting the innovative partnership
collaboration to deliver the needed infrastructure (HM Treasury, 1997; Bell, 2002;
Shaoul, 2002: Ismail & Pendlebury, 2006).
Value for money is “the optimum combination of whole-of-life costs and quality
(or fitness for purpose) of the good or service to meet the user‟s requirement‟‟ (HM,
Treasury 2006, p.7). The term whole-of-life is used to refer to the lifecycle of the good
or service. And moreover, VfM is about striking the best balance between the “three
E‟s” with respect to the delivery of a project, these being economy, efficiency and
effectiveness.
According to UKAS (2009), in the delivery of PPP projects, the public sector
expects the PPP project to adhere to the following principles with respect to achieving
the VfM objectives, these include:
a) There should be optimum risk transfer between the public and private sector in
relation to the parties considered in best position to handle such risks;
b) The contract should be long term and to include whole life cycle costing;
c) Project output specifications are efficient and effective;
d) Competition leading to fair value projects, and
e) Payments based on performance, and private sector management expertise.
However, with regards to the practice of the PPP for delivering infrastructure
projects in Malaysia, the following issues have been identified:
10
a) Despite the various advantages that PPP form of infrastructure delivery
offers, the level of adoption of the system in Malaysia is significantly low
compared to other forms of private sector involvement in the delivery of
infrastructure facilities, and also the implementation of the system is not well
structured as the procedures needed to facilitate the effective adoption of the
PPP approach are not fully available (Salleh & Siong, 2008; Khaderi &
AbdulAziz, 2010).
b) The implementation and policy of VfM has been the subject of critiques, as
the VfM objectives with regards to the achievement of the end user‟s
expectations in the Malaysian practice of PPP for infrastructure projects are
not being achieved (Takim et al., 2009; Ismail et al., 2011). It is noted by
Burger & Hawkesworth (2011) that in practice, the VfM objective is very
often blurred, and the choice between using a PPP and traditional
infrastructure procurement may be skewed by factors other than the VfM
objectives, which are not in tandem with the underlying time, cost and
quality objectives of the infrastructure projects. Moreover, as the concept
includes both qualitative and quantitative aspects and typically involves an
element of judgment on the part of government; a precise measure for VfM
concept does not exist but is merely regarded as what a government judges to
be an optimal combination of quantity, quality, features and price (i.e. cost),
over the whole of the project‟s lifetime.
c) Furthermore, Akintoye et al., (2003) speculated that political, economic and
social developments can change the definition of VfM in a particular
jurisdiction. However, with these underlying issues identified with respect to
achieving VfM in PPP project delivery, the only question being asked by the
end users when government procures public infrastructure through the PPP
approach is that “has VfM been achieved?” (Watermeyer, 2013).
This research takes into account the work of Yuan et al., (2009), Zhang (2006)
and Takim et al., (2011), in situating the context of performance measurement in
relation to the SPV organizations. Thereby, this research argues for a more strategic
11
approach towards leading indicators of Best Value (BV) rather than solely concentrating
on lagging operational indicators of VfM. Hence, the attempt here is to situate the PPP
research debate into the broader Business and Management field, and as such draw
attention to the work of Kaplan & Norton (1996) on the Balanced Scorecard (BSC);
with the key strategic aim of achieving BV rather than settling for VfM. The BSC is
seen as being more than adequate to be adapted for the purpose of establishing a
comprehensive systemic framework that can align the SPV‟s necessary operational
measures (the VfM) with a coherent set of leading performance measures aimed at
achieving BV.
The BV perspective is described as a notion which refers to the optimum
outcome of a business process (Akintoye et al., 2003; Zhang, 2006). While Value for
money is defined as “the optimum combination of whole-of-life costs and quality (or
fitness for purpose) of the good or service to meet the user‟s requirement‟‟ (HM, 2006).
It is argued in this research that in the PPP form of infrastructure delivery, there needs to
be a clear alignment between the BV and VfM, wherein the VfM is considered to be
enabling the achievement of the BV objective in general.
This research centers on the fact that the current research on PPPs seems to be
mainly concerned with examining PPPs at a broad social or organizational level, whilst
lacking in the management of inter-organizational relationships and process control
(Yuan et al., 2009). Thereby, the focus of this research is on the micro-management and
stage-specific analysis of PPP project delivery. Utilizing the concept of the BSC
methodology, this research attempts to review the current contextual rules that seem
lacking; leading to a weak PPP project organization, thereby ultimately deterring the
ability of the SPV organization towards achieving their VfM objectives in the delivery
of the PPP projects.
1.3 Research questions
This research is undertaken as an attempt to address the above identified
problems with the current practice of PPP infrastructure project delivery in Malaysia. It
12
was found necessary to develop a conceptual framework to provide a hands - on
practical approach to achieving the strategic objectives of alignment and structuring of
measures to enable the SPV organizations to deliver enhanced VfM objectives in the
form of BV for PPP projects. In order to develop the framework, the following basic
questions of “WHAT” and “HOW” must be addressed in order to achieve the objectives
of setting up a systematic and practical framework to enable the delivery of enhanced
VfM objectives for PPP projects:
a) What is the role of VfM in delivering infrastructure projects through the PPP
approach?
b) How can the VfM be delivered by the private sector in a systematic and practical
manner towards achieving the overall objective of the PPP in infrastructure project
delivery?
1.4 Aim of the research
The research is focused on carrying out an in depth appraisal of the SPV‟s structural
formation for PPP infrastructure project implementation in Malaysia based on the
current practice through the adoption of the BSC performance management
methodology in order to develop a PPP conceptual framework that will enable the
delivery of enhanced VfM objectives in the form of BV for PPP projects.
1.5 The objectives of the research
a) To compare between the different forms of PPP (options) with regards to their
effectiveness (appropriateness) in terms of achieving VfM objectives for PPP
projects in Malaysia.
b) To determine the skills required by the SPV organization for effective PPP
projects delivery.
c) To determine the CSF‟s that would enable the SPV organizations achieve their
VfM objectives for PPP projects delivery in Malaysia aligned to the BSC
methodology.
13
d) To develop a conceptual framework to enable the effective structuring of SPV
organizations for the delivery of BV objectives for PPP projects.
1.6 Scope of the research
The scope of the study is focused on PPP infrastructure projects in Malaysia, and the
target respondents include regulators, SPV organizations, financiers and consultants that
are involved in the delivery and management of PPP infrastructure projects in Malaysia
Furthermore this research is focused on hard infrastructure projects that are procured
under the PPP mode of project delivery.
1.7 Significance and implications of the research
Certainly, SPV‟s play a vital role in the achievement of VfM objectives in PPP projects
(Ismail et al., 2011); thereby, the structuring of the SPV organization is considered an
important criteria towards achieving of these VfM objectives that the PPP form of
project delivery tends to offer. Potential PPP projects are likely to fail if the PPP
developers that do drive the implementation of the PPP projects are not effectively
structured as to enable to deliver the VfM objectives for the PPP projects, for instance
the Malaysian Indah Water Consurtium sewerage project which failed due to the SPV‟s
lack of appropriate stakeholder management techniques and also the Philippines
Novotas 1 power project which was not able to achieve its objectives as a result of the
SPV organization‟s deficient VfM assessment techniques (El-Gohary et al., 2006;
Chowdhury et al., 2009). This research examines the structuring of the SPV
organizations for PPP projects in Malaysia with respect to achieving their VfM
objectives by delivering enhanced VfM objectives in the form of BV. In this research,
using the BSC approach, the operational indicators are being matched with project-
specific VfM outcomes and aligned with the concepts of BV; linking cause to effect, for
the successful delivery of PPP projects.
In addition, through the formulation of the conceptual framework for the
structuring of the SPV‟s to deliver the BV objectives for PPP projects, this research will
14
enable key PPP project stakeholders to identify how to go about the effective practice of
the PPP delivery system. This approach to a structured delivery of PPP infrastructure
projects would surely go a long way in solving the existing infrastructure deficits and
consequently the realization of the full economic potentials of utilizing the PPP route for
delivering successful infrastructure projects in Malaysia. Moreover, the study will serve
as a platform whereby the Malaysian PPP implementation will serve as a benchmark to
other PPP projects in other developing countries, which this will also in turn result to the
improved implementation of PPP systems in Malaysia. Thus serving as a catalyst
towards enabling the Malaysian economy to achieve its full potential with regards to the
provision of best value infrastructural facilities, which is a major step towards the
nation‟s quest to achieving a fully developed nation status by the year 2020.
1.8 Limitations of the research
The limitation of this study is related to obtaining low response rate through the
quantitative research approach adopted. This is mainly contributed by the fact that there
is a paucity of relevant stakeholders with sufficient experience in PPP projects delivery
in Malaysia. However, in order to improve on this, a triangulation method is suggested
through the qualitative research approach be also undertaken to make up for the smaller
number of respondents.
1.9 Organization of the thesis
Chapter one gives an outline of the background of the study, the problem statement, the
aim and objectives of the study, the scope of the study and lastly significance and
implications of the study.
Chapter two is the literature review which gives an overview of PPP as a project
delivery approach. The literature review is primarily aimed at providing the underlying
basis for objectively understanding the basic features that describes the PPP and
15
consequently serving as a basis to develop the survey instrument necessary to achieve
the objectives of the research.
Chapter three discusses the research methodology adopted in order to achieve
the aim and objectives of the study. The chapter discusses the fundamental theories and
the research procedures adopted for the study, which includes the primary and
secondary data collection and how the data collected was analyzed in order to achieve
the set out research objectives.
Chapter four discusses the results obtained and the findings arising from the
analysis conducted.
Chapter five discusses the PPP BV conceptual framework developed in the
study, and also the procedure adopted in validating the framework, and finally;
Chapter six initially reviews the objectives achieved in the study. Additionally,
the value, practical implications and significance of the research are described. Lastly,
conclusions to the research are provided and the limitations of the research and
recommendations for further studies are discussed.
CHAPTER 2
LITERATURE REVIEW
2.1.1 Infrastructure projects as it relates to social and economic development
The American Heritage Dictionary, defines the term „infrastructure‟ as the basic
facilities, services, and installations needed for the functioning of a community or
society, such as transportation and communications systems, water and power lines, and
public institutions including schools, post offices, and prisons. But then in the broad
scale, infrastructure can be referred to all basic inputs and requirements needed for the
proper functioning of the economy (UN HABITAT, 2011).
As Grimsey & Lewis (2002) and UN HABITAT (2011) put it, infrastructure is
easier to recognize than define, and it is mostly described in respect of its characteristics,
which usually refers to its longevity, scale, inflexibility and high investment costs.
Infrastructure is further described as a term which connotes credibility, confidence, low-
cost production, and market competitiveness because of its far reaching effects towards
achieving overall economic development, enhancement of trade and poverty reduction
(Geethanjali, 2007). Effective investments in infrastructure is known to offer key input
to ensuring economic activities, growth and moreover offering basic services to industry
and households (Threadgold, 1996).
17
2.1.2 Categorization and characterization of infrastructural facilities
Infrastructure can be categorized into hard infrastructure and soft infrastructure. Hard
infrastructure refers to the physical structures or facilities that supports or enables the
working of the society and economy, these include infrastructure in transport (e.g.,
ports, roads, railways); energy (e.g., electricity generation electrical grids, gas and oil
pipelines); telecommunications (e.g., telephone and internet); and basic utilities (e.g.,
drinking water supply, hospitals and health clinics, schools, irrigation, etc)
Table 2.1: Categorization of infrastructure facilities and their related associated features
Service Associated Features
Transportation Road, bridges, tunnels, rail tracks,
harbors, etc
Water supply Dams, reservoirs, pipes, treatment
plants, etc
Waste water disposal Waste water treatment plants
Irrigation Dams, canals
Garbage disposal Engineered Landfills
District Heating Plant, network
Telecommunications Telephone exchanges
Power/Energy Power plants, transmission and
distribution lines.
Source: ADB (2008)
Table 2.1 shows the categorization of various infrastructure services and their
associated features. While the soft infrastructure refers to those non-tangibles supporting
the development and operation of hard infrastructure, such as policy, regulatory, and
institutional frameworks; governance mechanisms; systems and procedures; social
networks; and transparency and accountability of financing and procurement systems
(Bhattacharyay, 2009). This research is centered on the hard infrastructure projects that
are procured under the PPP and the reason for this is borne out of the underlying role
that it plays as it pertains to ensuring nations achieving their social and economic
development objectives.
18
2.1.3 The role of infrastructure to national development
The relationship between infrastructure and the economy is evidently critical to
promoting inclusive growth and sustainable development and moreover, the linkage
between the economy and infrastructure is multi-faceted and multi-dimensional in the
context that economic growth provides both the need and the reason for, and the needed
resources to fund the provision of the various types of infrastructure (Nepad, 2011).
The importance of the provision of effective infrastructure for ensuring
development in both the developed and developing economies cannot be over
emphasized. As in the case of the developed nations, effective infrastructure has
generally been found to be a major determinant of growth and productivity. Whilst in
that of developing economies, its relevance is much more emphasized and glaring as
infrastructure is considered to play an important role in promoting growth and
productivity and reducing disparities between rich and poor regions (Briceno-
Garmendia & Estache, 2004).
Figure 2.1: The relationship between infrastructure to economic growth and
improving welfare of the citizenry.
Source: Prudhomme (2004).
Infrastructure
Benefit
households Benefit
enterprises
Improve
welfare
Enlarge
markets Lower
costs
Growth
19
Figure 2.1 describes the interlinking relationships between infrastructure to
ultimately ensure growth and also improve the welfare of the citizenry. In the economic
context, infrastructure ensures economic growth by benefitting the business enterprises
through enlarging the markets for their products and lowering their costs of production,
while in the social aspect, the provision of infrastructure benefits the households through
improving their welfare and condition of living.
2.1.4 Need for private sector participation in the provision of infrastructure
facilities and services
Prior to the surge of private sector‟s involvement in the provision of infrastructure
facilities in the 1990‟s, governments have presumed that the technology and economics
of infrastructure provision precluded any substantial role for the private sector. This
reason can be related to the natural monopolies in terms of the earlier known
consideration that it is only the public sector that controls all forms of investments in
infrastructure, economies of scale, externalities and other social factors that are involved
in the production and distribution of these needed infrastructure services, which these
then made infrastructure services provision to be considered more suitable for public
provision than for private (Yaacob & Naidu, 1997).
However as Yepes (2005) identified, with annual global investment needs in
infrastructure facilities which stands at US$ 848 billion, which accounts to
approximately 2% of the global G.D.P, it is a glaring fact that the world faced a huge
infrastructure deficit. Thereby, in the increasingly competitive and challenging global
environment, governments around the world are seeking out new ways to finance
projects to meet the ever growing infrastructure needs of their populace.
Additionally, in the late 1970‟s to early 1980‟s there was wide spread complaints
of public sector monopoly notably by the state owned enterprises in developing
countries that tended to be plagued by inefficiency and failure to expand services to
meet rapidly growing demand. However, consumers were becoming more concerned
20
and aware of the need for improved value for money for the services offered by the
public sector as there is global improvement of democratic and more transparent
governance and the resultant strengthening of the civil societies (Harris, 2003).
Consequently, this has necessitated for the private sector participation towards solving
the infrastructure challenges that are facing the public sector (Pongsiri, 2002; Cheung &
Kajewski, 2010).
Figure 2.2 : Infrastructure provision under the public sector in the early 1990s – the
annual costs of mis-pricing and inefficiency.
Source: World Bank (1994)
It is noted by Harris (2003) that by the early 1990s, it was evident that the annual
losses from inefficiencies and unsustainable pricing policies in the public sector‟s
delivery of infrastructural utilities were estimated to be nearly equal (US$178 billion) to
annual investments (US$ 200 billion) in the infrastructure itself (see Figure 2.2). This
has not in any way been consumerable with these public utilities ability to meet up with
increasing demand and needs of the citizenry. These challenges prompted the
governments to introduce measures to improve the performance of the public sector
entities through the adoption of more privately inclined policies such as corporatization
and the introduction of more formal arrangements such as performance contracts.
However, these measures were also not able to achieve the target needed as these public
utilities continued to be marred by inefficiencies and failure to meet up with its set
21
objectives. Hence, full private sector involvement became the only viable alternative
that was left to be explored to enable these public infrastructure facilities to deliver at
the needed optimal level.
2.2 The business philosophy behind public and private sector collaboration in
infrastructure delivery
Public-private collaboration in infrastructure delivery had been a concept which had
evolved and adopted from time immemorial. It is basically an arrangement which
involves the private sector in their entrepreneurship capacity participating or providing
the necessary support needed for the delivery of public infrastructure. The private sector
is described as that sector of the economy which is owned and run by private entities, in
the form of individuals, groups or business entities with the sole aim of making profit.
While the public sector which is also referred to as the government is that entity which
has the sole leadership responsibility of its citizenry, and is represented at various levels
including the federal, state, regional or local government. The public-private
collaboration is a partnering process which gives the public and private entities the
opportunity to collaborate in the delivery of a certain project or activity (Adetola et al.,
2011).
However, as Jamali (2004) notes, the recent rise of ideals of free market
operation of the economy in the developing world has made the public and private
sectors to revisit the nature of the relationship that does exists between them. The age
long traditional clear cut roles of these sectors are being challenged with an engaging
partnership collaboration, towards delivering the needed infrastructure facilities and
services.
2.2.1 Public-private partnership as a means of collaboration for infrastructure
delivery
The word partnerships means “a contract between two or more competent persons for
joining together their money, goods, labor, and skill, or any or all of them, under an
22
understanding that there shall be a communion of profit between them, and for the
purpose of carrying on a legal trade, business, or adventure‟‟ (Webster‟s dictionary,
2012). According to Adetola et al., (2011), partnership is a process through which
individuals, groups, organisations or entities have the opportunity to become actively
involved in a project or programme of activity.
The concept of public-private sectors collaboration may be difficult to be given a
clear cut definition due to the wide and encompassing meaning of the partnership
concept and the interchanging role that the PPP seems to have between the traditional
and full privatisation form of infrastructure delivery and services provision. As many
authors have defined PPP differently, Boeuf (2003) concluded that the only consensus is
that there is no one-size-fits-all definition of PPP.
However, in a general sense, PPP can be described as a private sector driven
collaboration with the public sector for procuring public infrastructure which has
evolved to solve infrastructural deficits. Akintoye (2006) offers a comprehensive
definition of PPP as “a contractual agreement of shared ownership between a public
agency and a private company, whereby they pool resources together and share risks and
rewards, to create efficiency in the production and provision of public or private goods”.
In more simple terms, PPP is referred to as a system which is primarily aimed at
achieving the best output possible by pulling together and mobilizing funds,
technologies, managerial skills, operational efficiencies and facilitating innovations that
exists in the private sector (Bing et al., 2005; Huang et al., 2005).
Pongsiri (2002) in his work, described PPP as a means of collaboration between
the public and private sector in order to pursue common goals of providing
infrastructural facilities, while taking advantage of the resources, strengths,
competencies and capabilities that do exists in the public and private sectors. From a
broader perspective PPP is seen as a range of possible relationships among public and
private entities in the context of infrastructure delivery and other services, which
involves the allocation of the tasks, obligations, and risks among the public and private
partners in an optimal way (ADB, 2008). While Quimm (2011) described PPP as a
legally binding contract to share responsibilities related to implementation and/or
23
operation and management of an infrastructure project; whereby this collaboration or
partnership is built on the expertise of each partner that meets clearly defined public
needs through the appropriate allocation of resources, risks, responsibilities and rewards.
However, with respect to the Malaysian context, PPP was defined under the
Ninth Malaysia Plan report (2006), as “the transfer to the private sector the
responsibility to finance and manage a package of capital investment and services
including the construction, management, maintenance, refurbishment and replacement
of the public sector assets which creates a standalone business. The private sector will
create the asset and deliver a service to the public sector client. In return, the private
sector will receive payment commensurate with the levels, quality and timeliness of the
service provision throughout the concession period” (Ninth Malaysia Plan, 2006).
It can be deduced that though PPP has varying definitions with respect to
infrastructure delivery, the aim of the partnership is to put in place a collaborative
venture between the public and private sector as a joint partnership in terms of skills,
mobilizing funds, technologies, operational efficiencies and facilitating innovations
towards delivering the required infrastructure facilities for the benefit of the public and
society at large.
2.2.2 Distinction between public – private – partnerships, privatization,
corporatization and private finance initiative
With the global rise in private sector participation in infrastructure delivery, the terms
PPP and privatization have been used loosely as interchangable terms. This is because of
the private sector features that are inherent in these two forms of private sector
involvement in the delivery of infrastructure and services. However, there is the need to
have a clear understanding of the distinctions that characterizes these two forms of
private sector led infrastructure delivery.
Privatization as a form of infrastructure delivery is mainly characterized by the
introduction and use of market forces based competition by the government for the
delivery of public services or goods by the private sector. The term “privatization”
denotes an entire shift of government activities or functions from a public agency to that
24
of the private sector (CDIAC, 2007). It is an umbrella term used to account for greater
private sector participation in the delivery of public services. With the privatization
form of infrastructure delivery, the government is completely relieved of any form of
ownership and control of responsibilities as there is no binding service contract or fee-
for-service agreement between the public and the private sector after the entity or
enterprise has been privatized.
Whereas corporatization is described as the process by which a public-sector
department is transformed into a distinct legal entity (with the government as owner),
whose assets, finances, and functions are segregated from other government operations.
Corporatization in infrastructure project delivery aims to capture the advantages of a
privately run company, including productivity, streamlined processes, commercial
orientation and financial sustainability, while remaining accountable to the public and
serving the public interest (World Economic Forum, 2014) .
While PPP as a form of private sector involvement in the delivery of
infrastructure is described as “a contractual agreement of shared ownership between a
public agency and a private company, whereby they pool resources together and share
risks and rewards, to create efficiency in the production and provision of public or
private goods” (Akintoye, 2006). It can be characterized as a range of possible
relationships among public and private entities in the context of infrastructure delivery
and other services, which involves the allocation of the tasks, obligations, and risks
among the public and private partners in an optimal way.
157
REFERENCES
Abdul-Aziz, A. R., & Kassim, P. J. (2011). Objectives, success and failure factors of
housing public–private partnerships in Malaysia. Habitat International, 35(1),
150-157.
Abdul-Aziz, A. R. (2012). Control mechanisms exercised in Malaysian housing public-
private partnerships. Construction Management and Economics, 30 (1): 37-55.
Abdul Rashid, K. (2012). Understanding the Malaysian PPP. In Winch, G. M., Onishi,
M. & Schmidt, S. (2012) Taking Stock of PPP and PFI around the World.
London: ACCA.
Abdulrashid, K., (2002). Construction Procurement in Malaysia. Kuala Lumpur: IIUM
Press.
ADB. (2008). Public-Private Partnership Handbook. Manila : Asian Development
Bank.
ADBI, (2009): Asian Development Bank and Asian Development Bank Institute (2009).
Infrastructure for a Seamless Asia. Tokyo: ADB/ADBI. Available from www
adbi org/files/2009 08 31 book infrastructure seamless Asia pdf. (Accessed on
11th
October 2013).
Adetola, A., Goulding, J., & Liyanage, C. (2011). Collaborative Engagement
Approaches for Delivering Sustainable Infrastructure Projects in the AEC Sector.
International Journal of Construction Supply Chain Management , 1-24.
Akintoye, A. (1994). Design and Build: A Survey of Construction Contractors‟ Views.
Construction Management and Economics, 155-163.
Akintoye, A. (2006). Public Private Partnerships for Sustainable Development of
Infrastructure in Developing Countries. International Conference on the Built
Environment , (pp. 433-445). Ota.
Akintoye, A., & Malcolm J. MacLeod. (1997). Risk analysis and management in
construction. International Journal of Project Management 15 (1) 31-38.
158
Akintoye, A., Bing, L., & Edwards, P. J. (2005). The allocation of risk in PPP/PFI
construction projects in the UK. International Journal of Project Management,
23(1), 25-35.
Akintoye, A., Hardcastle, C., Beck, M., Chinyio, E. & Asenova, D. (2003). Achieving
best value in private finance initiative project procurement. Construction
Management and Economics, 21 (5), 461-470.
Alaba, A., Goulding, J., & Liyanage, C. (2011). Collaborative Engagement Approaches
for Delivering Sustainable Infrastructure Projects in the AEC Sector: A Review.
International Journal of Construction Supply Chain Management, 1-24.
Al Haadir, S., & Panuwatwanich, K. (2011). Critical success factors for safety program
implementation among construction companies in Saudi Arabia. Procedia
engineering, 14, 148-155.
Amaratunga, D., Baldry, D., Sarshar, M., & Newton, R. (2002). Quantitative and
qualitative research in the built environment: application of “mixed” research
approach. Work Study, 51(1), 17-31.
Amaratunga, D., Baldry, D., & Sarshar, M. (2000). Performance evaluation in facilities
management: Using the balanced scorecard approach. The Construction,
Building and Real Estate Research Conference of the Royal Institute of
Chartered Surveyors. London: Royal Institute of Chartered Surveyors.
Amaratunga, D., Haigh, R., Sarshar, M., & Baldry, D. (2002). Application of the
Balanced Score-Card Concept to Develop a Conceptual Framework to
Measure Facilities Management Performance within NHS Facilities.
International Journal of Health Care Quality Assurance, 15(4), 141-151.
American Society of Photogrammetry and Remote Sensing (2013).
http://architecture.mt.gov/content/designconstruction/docs/Best_Value_Definitio
n.pdf (Accessed on 20th November 2013).
Bartlett, M.S. (1954). A note on the multiplying factors for various chi square
approximations. Journal of the Royal Statistical Society, 16 (Series B): 296 –
298.
Bartlett, E.J., Kotrlik, J.W & Chadwick, C. H. (2001). Organizational research:
Determining appropriate sample size in survey research. Information
Technology, Learning, and Performance Journal, Vol. 19, No. 1.
159
Bhagwat, R., & Sharma, M. K. (2007). Performance measurement of supply chain
management: A balanced scorecard approach. Computers & Industrial
Engineering, 53(1), 43-62.
Bell, R. (2002), Keys to Effective Procurement. PFI: Practical Perspectives, ACCA,
April, pp. 24-2.
Beidleman, C.R., Fletcher, D. & Veshosky, D. (1990). On Allocating Risk: The essence
of project finance. Sloan Management Review, 31(3), 47-55.
Bessire, D., & Baker, C. R. (2005). The French Tableau de bord and the American
Balanced Scorecard: a critical analysis. Critical Perspectives on Accounting,
16(6), 645-664.
Bernard, H. R. (2011). Research methods in anthropology: Qualitative and quantitative
approaches. Altamira Press. Plymouth.
Bhattacharyay, B. N. (2009). Infrastructure Development for ASEAN Economic
Integration. Manila : Asian Development Bank Institute.
Bieker, T. (2003). Sustainability Management with the Balanced Scorecard. Proceedings
of 5th international summer academy on technology studies, Graz. 17-34.
Bieker, T. (2003). Sustainability Management with the Balanced Scorecard.
International Summer Academy on Technology Studies-Corporate Sustainability.
California.
Bing, L., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005). The Allocation of Risk
in PPP/PFI Construction Projects in the UK. International Journal of Project
Management, 25-35.
Birnie, J. (1999). Private Finance Initiative (PFI) – UK Construction Industry Response.
Journal of Construction Procurement. 5(1). pp 5-14.
Booth, K. & Skilling, H. (2007). Structuring a PPP: selecting the option.
http://www.adb.org/Documents/Handbooks/Public-Private
Partnership/Chapter5.pdf. (Accessed on 12th
August 2013).
Boynton, A. C., & Zmud, R. (1984). An assessment of critical success factors. Sloan
Management Review (pre-1986), 25(4), 17-27.
Bourne, L. & Walker, D. H. (2008). Project relationship management and the
stakeholder circle. International Journal of Managing Projects in Business, 1(1):
125-130.
160
Brewer, G., Gajendran, T., Jefferies, M., McGeorge, D., Rowlinson, S., & Dainty, A.
(2013). Value through innovation in long-term service delivery: Facility
management in an Australian PPP. Built Environment Project and Asset
Management, 3(1), 74-88.
Briceno-Garmendia, C., & Estache, A. (2004). Infrastructure Services in Developing
Countries: Access, Quality, Costs, and Policy Reform. Washington : World
Bank.
Briggs, A., Morrison, R.M., & Coleman, M (Eds.). (2012). Research methods in
educational leadership and management. Sage Publications.
Brink Groep, (2013). PPP Services. from Corporate Resources. www.Brink Groep.com.
(Assessed on July 23rd 2013).
Brinkerhoff, D. W. & Brinkerhoff, J. M. (2011). Public - private partnerships:
perspectives on purposes, publicness, and good governance. Public
Administration and Development, 31(1): 2-14.
Brown, T. & Potoski, M. (2003). Managing contract performance: a transaction cost
approach. Journal of Policy Analysis and Management, 22(2): 275-297.
Boeuf, P. (2003). Public Private Partnership for Transport Infrastructure Projects.
ECMT-EC-UNECE-EIB Seminar - Transport Infrastructure Development for
a wider Europe. Paris.
Buckley, J. W., Buckley, M. H., Chiang, H. F., National Association of Accountants,
Société des comptables en administration industrielle du Canada, & Society
of Industrial Accountants of Canada. (1976). Research methodology & business
decisions.
Burger, P & Hawkesworth, I. (2011). How to attain value for money: comparing PPP
and traditional infrastructure public procurement‟‟. OECD Journal on
Budgeting, 2001(1).
CCPPP (2001). 100 Projects: Selected Public–Private Partnerships. Ottawa: Canadian
Council for PPP.
Carbonara, N., Gunnigan, L., Pellegrino, R .& Sciancalepore, F. (2012) Tendering
Procedures in PPP: A Literature Review, published in Public Private
Partnerships in Transport: Trends & Theory 2011 Discussion Papers (eds)
Roumboutsos, A., and Carbonara,N.) COST Action TU1001, Bari, Italy.
161
CDIAC (2007). Privatization Vs. Public - Private Partnerships: A Comparative
Analysis. California : California Debt & Investment Advisory Commision .
Chan, A.P.C, Scott, D. & Lam, E.W.M. (2002). Framework of success criteria for
Design/Build projects. Journal of Engineering in Management, 18(3), pp.120-
28.
Chan, A. P., Lam, P. T., Chan, D. W., Cheung, E., & Ke, Y. (2010). Critical success
factors for PPPs in infrastructure developments: Chinese perspective.
Journal of Construction Engineering and Management, 136(5), 484-494.
Chan, F. T., & Qi, H. J. (2003). An innovative performance measurement method for
supply chain management. Supply chain management: An international Journal,
8(3), 209-223.
Chavan, M. (2009). The balanced scorecard: a new challenge. Journal of Management
Development, 28(5), 393-406.
Chege, L. W., & Rwelamila, P. D. (2001). Private Financing of Construction Projects
and Procurement Systems: An Integrated Approach. CIB World Building
Congress. CIB.
Cheung, E. (2009). Developing a Best Practice Framework for Implementing Public
Private Partnerships (PPP) in Hong Kong. Brisbane. PhD thesis. Queensland
University of Technology.
Cheung, E., & Kajewski, S. (2010). The Researcher's Perspective on Procuring Public
Works. Structural Survey, 300-313.
Cheung, E., & Chan, A. P. (2011). Risk factors of public-private partnership projects in
China: Comparison between the water, power, and transportation sectors.
Journal of Urban Planning and Development.
Chew, S., & Ismail, S. (2006). From privatization to PFI. Kuala Lumpur : The Edge
Daily.
Chowdhury, A.B.U., Orr, R.J. & Settel, D. (2009), Multilaterals and infrastructure
funds: a new era. Journal of Structured Finance, 14(4): 68-74.
Connelly, L. M. (2008). Pilot studies. Medsurg Nursing, 17(6), 411-2.
Credo Group (2013). Build-Own-Operate, from Resources Portal: Credo Group.com
(Assessed on November 8th, 2013).
162
Creswell, J.W (2012). Educational Research: Planning, Conducting, and Evaluating
Quantitative and Qualitative Research (4th Edition). Boston: Pearson.
Crotty, M. (1998). The Foundations of Social Research: Meaning and Perspective in the
Research Process: Sage.
Cruz, C. O., & Marques, R. C. (2013). Public Sector Comparator. In Infrastructure
Public-Private Partnerships (pp. 21-51). Springer Berlin Heidelberg.
Delmon, J. (2009). Private sector investment in infrastructure: Project finance, PPP
Projects and risks. Kluwer Law International. Netherlands.
De Palma, A., Picard, N., & Andrieu, L. (2012). Risk in transport investments. Networks
and Spatial Economics, 12(2), 187-204.
Denscombe, M. (2002). Ground Rules for Good Research: Open University Press.
Devkar, G. A., & Kalidindi, S. N. (2013). External agencies for supplementing
competencies in Indian urban PPP projects. Built Environment Project and Asset
Management, 3(1):58-73.
DETR (1999). Implementing Best Value: A Consultation Paper on Draft Guidance.
HMSO. London.
Dey, P. K., & Ogunlana, S. O. (2004). Selection and application of risk management
tools and techniques for build-operate-transfer projects. Industrial Management
& Data Systems, 104(4), 334-346.
Easterby-Smith, M., Thorpe, R., & Lowe. (1991). Management Research: An
Introduction. Sage.
Economic Planning Unit. (2010). Ninth Malaysian Plan (9MP). Putrajaya: Prime
Minister's Department.
Eggers, W; Dovey, T. (2007). Closing America‟s Infrastructure Gap: The Role of
Public-Private Partnerships. Chicago : Deloitte Research.
El-Gohary, N. M., Osman, H. and El-Diraby, T. E. (2006). Stakeholder management for
public private partnerships. International Journal of Project Management, 24(7):
595-604.
Ellis, RCT, Wood, GD & Keel, DA (2005). 'Value management practices of leading UK
cost consultants', Construction Management & Economics, vol. 23, no. 5, pp.
483-493.
163
Elliott, R., & Timulak, L. (2005). Descriptive and interpretive Approaches to
Qualitative Research. A Handbook of Research Methods for Clinical and Health
Psychology, 147-159.
Ernst & Young (2005). Australian PPP Survey – Issues Facing the Australian
PPP Market, Ernst & Young, London. November.
European Commission. (2003). Guidelines for successful public–private partnerships.
Brussels, Belgium.
http://europa.eu.int/comm/regional_policy/sources/docgener/guides/PPPguide.ht
ml (Accessed on 19th December 2013).
Fellows, R. F., & Liu, A. M. (2009). Research Methods for Construction. John Wiley &
Sons.
Frankfort-Nachmias, C., & Leon-Guerrero, A. (2010). Social Statistics for a Diverse
Society. Sage Publications. (Accessed on 15th
August 2015).
FRBSF (2015). Federal Reserve Bank of San Francisco. http://www.frbsf.org/economic
- research/publications/economics.
GENI (2015): Global Energy Network Institute.
http://www.geni.org/globalenergy/library/national_energy_grid/malaysia/index.s
html on (Assessed on 11th
February 2015).
Geethanjali, N (2007): Infrastructure challenges in South Asia: The role of public-
private partnerships, ADB Institute Discussion Papers, No. 80. Asian
Development Bank.
Goh, C. S., & Abdul-Rahman, H. (2013). The identification and management of major
risks in the Malaysian construction industry. Journal of Construction in
Developing Countries, 18(1), 19-32.
Guba, E. G., & Lincoln, Y. S. (1994). Competing paradigms in qualitative research. In
N. K. Denzin & Y. S. Lincoln (Eds.), Handbook of qualitative research (pp.
105-117). London: Sage.
Gupta, M. C. & Narasimham, S. V. (1998). Discussion on the paper „CSFs in
competitive tendering and negotiation model for BOT projects‟. Journal of
Construction Engineering and Management. 124(5): 430.
Gatti, S. (2012). Project Finance in Theory and Practice: Designing, Structuring, and
Financing Private and Public Projects. Academic Press.
164
Ghauri, P. N., & Grønhaug, K. (2005). Research methods in business studies: A
practical guide. Pearson Education.
Gransberg, D. D., & Ellicott, M. A. (1997). Best value contracting criteria. Cost
Engineering, 39 (6), 31–34.
Gransberg, D., Koch, J. & Molenaar, K., (2006). Preparing for Design and Build
Projects. 1st ed. New York: ASCE.
Griffith, A., Knight, A., & King, A. (2003). Best Practice Tendering for Design and
Build Projects. London : Thomas Telford.
Grimsey, D., & Lewis, M. (2007). Public private partnerships: The worldwide
revolution in infrastructure provision and project finance. Surrey : Edward Elgar
Publishing.
Grimsey, D., & Lewis, M. K. (2002). Evaluating the Risks of Public Private
Partnerships for Infrastructure Projects. International Journal of Project
Management, 107-118.
Grimsey, D., & Lewis, K. K. (2004). Public private partnerships. Cheltman. Edward
Elgar, 28(3), 205.
Grout, P. (1997). The economics of the private finance initiative. Oxford Review of
Economic Policy, 53 – 66.
Gunawasa, A. (2012). Public private partnerships for major infrastructure projects in
developing countries in Ofori , G. (ed.). Contemporary Issues in Construction in
Developing Countries, UK: SPON Press.
Harris, T. (2003). Private Participation in Infrastructure In Developing Countries:
Trends, Impacts, and Policy Lessons. Washington : World Bank .
Heravi, G. R., & Alkass, S. (2008). Risk areas versus critical success factors in public–
private partnership construction project agreements. Annual Conference of the
Canadian Society for Civil Engineering, Quebec City.
Hart, C. (1998). Doing a Literature Review: Releasing the Social Science Research
Imagination. Sage.
HM Treasury (1997). Appraisal in Evaluation of Central Government, „The Green
Book‟, London, HM Treasury, London.
HM Treasury. (2006). Value for Money Assessment Guidance. London.
Horna, J. (1994). The Study of Leisure. Oxford: Oxford University Press.
165
Holt, G.D. (2014). Asking questions, analyzing answers: relative importance
revisited. Construction Innovation. Vol. 14 (1), pp. 2-16.
Huang, T., Shen, L., Yam, C., & Zhao, Z. Y (2005). An analysis to the existing practice
of managing government-invested project in China. Construction Economics,
16-20.
Huang, H. C., Lai, M. C., & Lin, L. H. (2011). Developing strategic measurement and
improvement for the biopharmaceutical firm: Using the BSC hierarchy. Expert
Systems with Applications, 38(5), 4875-4881.
ICRC (2012): Nigeria Public-Private Partnerships Manual (online). Available at
http://ppptoolkit.icrc.gov.ng/contract-management/types-of-ppp-contracts/
(Assessed on 23rd
February 2015).
Indian PPP guide (2007). Public Private Partnership in India.
http://www.pppinindia.com/ . (Assessed on 14th January 2014).
Ismail, S., & Rashid, K. A. (2014). Private finance Initiative (PFI) in Malaysia: The
need for and issues related to the public sector comparator (PSC). Jurnal
Akuntansi dan Keuangan Indonesia, 4(2), 137-154.
Ismail, K., Takim, R. & Nawawi, A. H. (2011). The Evaluation Criteria Of Value for
Money (VfM) of Public Private Partnership (PPP) bids. International Conference
on Intelligent Building and Management. Singapore: 349-355.
Ismail, S., & Pendlebury, M. (2006). The private finance initiative (PFI) in schools: The
experiences of users. Financial Accountability & Management, 22(4), 381-404.
Ismail, S. (2012). What drives value for money of public private partnership (PPP)
projects implementation in Malaysia? In Proceedings of the National conference
of the Malaysian economy. Kuala Lumpur (pp. 473-483).
Ismail, K., Takim, R., Nawawi, A. H., & Jaafar, A. (2009). The Malaysian private
finance initiative and value for money. Asian Social Science, 5(3), p103.
Ismail, S., & Azzahra Haris, F. (2014). Rationales for public private partnership (PPP)
implementation in Malaysia. Journal of Financial Management of Property and
Construction, 19(3), 188-201.
Ismail, S. (2013). Critical success factors of public private partnership (PPP)
implementation in Malaysia. Asia-Pacific Journal of Business Administration,
5(1), 6-19.
166
Jamali, D. (2004). Sucess and failure mechanisms of Pubic Private Partnerships (PPP) in
Developing Countries: Insigths from the Lebaneese Context. International
Journal of Public Sector Management , 414 - 430.
Jacobs, K. (1998) .Value for Money Auditing in New Zealand: Competing for Control
in the Public Sector‟. British Accounting Review. 30(3).343-60.
Jacobson, C., & Ok Choi, S. (2008). Success factors: public works and public-private
partnerships. International Journal of Public Sector Management, 21(6), 637-
657.
Jaidka, K., Khoo, C. S., & Na, J. C. (2013). Literature Review Writing: How
Information is Selected and Transformed. In Aslib Proceedings (Vol. 65, No. 3,
pp. 303-325). Emerald Group Publishing Limited.
Jefferies, M., (2006). Critical success factors of public private sector partnerships: A
case study of the Sydney super dome. Engineering, Construction and
Architectural Management, 13(5), 451-462.
Juran, J. M. (1954). Universals in management planning and controlling. Management
Review, 43(11), 748-761.
Kandampully, J. (2002). Innovation as the core competency of a service organisation:
the role of technology, knowledge and networks. European Journal of
Innovation Management, 5(1), 18-26.
Kaplan, R.S. & Norton, D.P. (1996).Translating Strategy into Action: The Balanced
Scorecard:Harvard Business School Press. USA.
Kelly, E. S., Haskins, S., & Reiter, P. D. (1998). Implementing a DBO Project. Journal-
American Water Works Association, 34-46.
Khaderi, S.S and Aziz, A.R.A (2010). Adoption of Private Finance Initiative (PFI) in
Malaysian Public Works Projects: Are we ready?. Proceedings edited by:
P.Barett, D. Amaratunga, R. Haigh, K. Keraminiyage and C. Pathirage. 18th
CIB
World Building Congress, Salford, United Kingdom, 105 – 120.
Knight, A. (2003). Best Practice Tendering for Design and Build Projects. London:
Thomas Telford.
Koch, C., & Buser, M. (2006). Emerging metagovernance as an institutional framework
for public private partnership networks in Denmark. International Journal of
Project Management, 24(7): 548-556.
167
Kumaraswamy, M. M., & Zhang, X. (2001). Governmental Role in BOT- led
Infrastructure Development. International Journal of Project Management, 195-
205.
Kwah Y.H., Chih Y-Y & Ibbs C.W. (2009). Towards a Comprehensive Understanding
of Public Private Partnerships for Infrastructure Development. California
Management Review, Vol. 51, No.2, pp. 51-78.
Kwawu, W. , Elhag, T. & Ballal, T. (2010). Knowledge transfer processes in PFI/PPP:
critical success factors. In 26th Annual ARCOM Conference, 6-8th September
2010, Leeds, pp. 839-848.
Lam, E. W., Chan, A. P., & Chan, D. W. (2004). Benchmarking design-build
procurement systems in construction. Benchmarking: An International
Journal, 11(3), 287-302.
Li, B., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005). Critical success factors for
PPP/ PFI projects in the UK construction industry. Construction management
and economics, 459-471.
Li, B. (2003). Risk management of construction public-private partnership projects.
Brisbane: QUT Doctoral Theses.
Li, H. & Liu, K. J. (2009). “Research on risk evaluation of PFI projects with many-sided
viewpoint.” Proceedings of International Symposium on Advancement of
Construction Management and Real Estate, Renmin University of China,
Beijing, 3, 1343–1350.
Ling, F.Y.Y., (2004). How project managers can better control the performance of
design-build projects. International Journal of Project Management, 22(1),
pp.477-88.
Loosemore M, Raftery J, Reilly C & Higgon D. (2006). Risk Management in Projects.
London. Taylor & Francis.
L. S. E Enterprise & Anderson, A. (2000). Value for money drivers in the private
finance initiative, report commissioned by the UK Treasury Task Force on
public–private partnerships. London: The Stationery Office.
Lubis, H. al-Rasyid & Majid, N.N. (2013). Developing a Standardized Assessment for
PPP Infrastructure Project. Proceedings of the Eastern Asia Society for
Transportation Studies, Vol.9.
168
Malaysian Government (2015): Malaysian Government Website.
https://www.malaysia.gov.my/about-malaysia?type=2&categoryId=3208945
(Accessed on February 18th
2015).
Male, S, Kelly, J, Fernie, S, Gronqvist, M & Bowles, G (1998). Value management: the
value management benchmark: Research results of an international benchmark
study. Thomas Telford Publishing, London.
Mathur, V. N., Price, A. D. & Austin, S. (2008). Conceptualizing stakeholder
engagement in the context of sustainability and its assessment. Construction
Management and Economics , 26(6): 601-609.
Malhotra, M. K., & Grover, V. (1998). An assessment of survey research in POM: from
constructs to theory. Journal of Operations Management, 16(4), 407-425.
Masterman, J., (2002). Introduction to Building Procurement Systems. London: Spon
Press.
Mea Culpa (2001).The Juran Institute. www.juran.com/research/articles/sp7515.html.
(Assessed on 15th
December 2014).
MIDA (2009). Malaysian Investment Development Authority Guidebook on Expatriate
Living in
Malaysia.http://www.mida.gov.my/env3/uploads/Publications_pdf/ExpatriateLiv
ing/expatriate2009.pdf. (Accessed on 11th
February 2015).
McCowan, A. K., & Mohamed, S. (2002). Evaluation of Build-Operate-Transfer (BOT)
Project Opportunities in Developing Countries. In Proceedings of the First
International Conference on Creating a Sustainable Construction Industry in
Developing Countries (pp. 377-386), Stellenbosch.
Mickaliger, M. J. (2001). Best value contracting: Selection by perception. Association
of Proposal Management Professionals, 52-56.
Miles, M.B & Huberman, A.M. (1994). Qualitative Data Analysis: An Expanded
Sourcebook, CA:.Sage.
Mistarih, A., Al Refai, M., Al Qaid, B. & Qeed, M. (2012). Competency requirements
for managing public private partnerships. International Journal of Business
Management, 7(12): 60-73.
Matthew B. Miles, & A. Michael Huberman. (1994). Qualitative data analysis: An
expanded sourcebook. Sage.
169
Mizrachi, Y. & Ben-Attar, D. (2011). “Downtown” and “suburbia” public-private
partnerships (PPP) in the application of information and communication
technologies for development (ICT4D). The Paradox in Partnership: The Role of
Conflict in Partnership Building.
Morallos, D., & Amekudzi, A. (2008). The state of the practice of value for money
analysis in comparing public private partnerships to traditional procurements.
Public Works Management & Policy, 13(2), 114-125.
Naidu, G. (2008). Infrastructure Development in Malaysia, in Kumar, N. (ed.),
International Infrastructure Development in East Asia – Towards Balanced
Regional Development and Integration, ERIA Research Project Report 2007-2,
Chiba: IDE-JETRO, pp.204-227.
Nau, D. (1995). Mixing methodologies: Can bimodal research be a viable post-positivist
tool.The Qualitative Report, 2(3), 1-5.
Nataraj, G. (2007). Infrastructure challenges in South Asia: The Role of Public-Private
Partnerships. Manila : Asian Development Bank.
National Council of PPP (2013). Types of Partnerships. PPP Resources: ncppp.org
(Assessed on September 15th
2013).
Neely, A. (1999). The performance measurement revolution: why now and what next?
International Journal of Operations & Production Management, 19(2), 205-228.
NEPAD (2011). Infrastructure Development as Catalyst For Economic Growth In
Africa. Nepad African Partnership Forum (pp. 24-56). Addis Ababa: New
Partnership for African Development (NEPAD) .
Nettleton, B. (2000). Best value and direct services. Proceedings of Institution of Civil
Engineers, Paper 12 272, 83–90.
New Zealand Treasury (2006). http://www.treasury.govt.nz/publications/research-
policy/ppp/2006/06-02/06.htm.
(Assessed on 7th
March 2015).
Ninth Malaysia Plan (2006-2010). http://www.epu.jpm.my/rm9/html/english.htm.
(Accessed on 12th
April 2012).
Nijkamp, P., Van Der Burch, M., & Vindigni, G. (2002). A comparative institutional
evaluation of public-private partnerships in Dutch urban land-use and
revitalisation projects. Urban Studies, 1865-1880.
170
Nooriha, A., Sufian, A., Asenova, D. & Bailey, S. J. (2014). PPP/PFI in Malaysian
development plans: purpose, structure, implementation, financing and risk
transfer. 5th
Asia-Pacific Business Research Conference. Kuala Lumpur.
Norusis, M. J. (1992). SPSS for Windows: Base System User's Guide. New York: SPSS
Incorporated.
OECD (2008). Value for money and international development: Deconstructing myths
to promote a more constructive discussion.
http://www.oecd.org/dac/aideffectiveness (Accessed on 13th
August 2012).
Office of the Auditor-General. (2008). Good Practice Guide for Public Sector
Procurement Guidance. Wellington.
O'Leary, Z. (2005). Researching real-world problems: A guide to methods of inquiry:
Sage.
Orlikowski W.J. & Baroudi J.J. (1991). 'Studying information technology in
organizations: Research Approaches and Assumptions' Information Systems
Research 2, 1-28.
Pacitti B.J (1998). Organizational Learning in R&D Organizations: A Study of New
Product Development Projects, unpublished PhD theses, University of
Manchester, Manchester.
Pakistan PPP (2015): Pakistan PPP Unit.https://pppsinpakistan.wordpress.com/ppp-
models/ .(Assessed on November 11th
2013).
Pallant, J. (2013). SPSS survival manual. McGraw-Hill Education (UK).
Parfitt, M.K. & Sanvido, V., 1992. Critical success factors for construction projects.
Journal of Construction Engineering and Management, 118(1), pp.94-111.
Patton, M. Q. (2002). Qualitative Research and Evaluation Methods (3rd ed.). Thousand
Oaks, California: Sage.
PFI Report. (2002). Super contractors for super hospitals.
http://www.publications.parliament.uk/pa/cm201012/cmselect/cmtreasy/1146/11
46.pdf (Assessed on 18th
February 2002).
Peterson, T. O. & Van Fleet, D. D. (2004). The ongoing legacy of RL Katz: An updated
typology of management skills. Management Decision, 42(10):1297-1308.
Pongsiri, N. (2002). Regulations and Public Private Partnerships. International Journal
of Public Sector Management, 487-495.
171
Prudhomme, R. (2004). The Relationship Between Infrastructure to Economic Growth
and Improving Welfare of the Citizenry . Annual Bank Conference on
Developing Economies (pp. 1-388). Washigton : World Bank .
Price Water House Coopers (2010). http://www.pwc.com/gx/en/government-
infrastructure/pdf/promisereport.pdf. (Assessed on 11th
June 2013).
Punniyamoorthy, M. & Murali, R. (2008), Balanced score for the balanced scorecard: a
benchmarking tool. Benchmarking: An International Journal, Vol. 15 No. 4, pp.
420-43.
Qiao, L., Wang, S. Q., Tiong, R. L., & Chan, T. S. (2001). Framework for critical
success factors of BOT projects in China. The Journal of Structured Finance,
7(1), 53-61.
Quimm, A. (2011). A Guidebook on Public–Private Partnership in Infrastructure.
Manila : United Nations Economic and Social Commison for Asia and Pacific.
Raisbeck, P. (2009) Considering design and ppp innovation: A review of design factors
in PPP research. In: Dainty, A. (Ed) Procs 25th Annual ARCOM Conference, 7-9
September 2009, Nottingham, UK, Association of Researchers in Construction
Management, 239-47
Remenyi, D., Williams, B., Money, A., & Swartz, E.(1998). Doing Research in
Business and Management: Sage Publications, London.
Royal Institution of Chartered Surveyors (2015).
https://consultations.rics.org/consult.ti/value_engineering/viewCompoundDoc?d
ocid=863924&partid=864340&sessionid=&voteid=
(Accessed on 12th
January 2015)
Robinson, H. S. & Scott, J. (2009). Service delivery and performance monitoring in
PFI/PPP projects. Construction Management and Economics, 27 (2):181-197.
Rockart, J.F. (1982). The changing role of the information systems executive: A critical
success factors perspective. Sloan Management Review, 24(1).
Rose, Kenneth H. (2005). Project Quality Management: Why, What and How.
Fort Lauderdale, Florida: J. Ross Publishing.
Rosenau, P. (2000). Public-Private Policy Partnerships. Massachusetts: Scotsman.
Rowlinson, S., (1999). Selection Criteria in Procurement Systems: A guide to best
practice. London: E and F.N. Spon.
172
Royal Literary Fund (2015): http://www.rlf.org.uk/resource/what-is-a-literature-
review/. (Accessed on 12th
January 2015).
Rudzianskaite-Kvaraciejiene R., Apanaviciene, R.& Butauskas A., (2010), Evaluation
of road investment project effectiveness, Inzinerine Ekonomika Engineering
Economics, Vol. 21, No. 4, pp. 368-376.
SADC. (2009). Development Status Report for Council and Summit . Botswana : South
African Development Commision .
Sadler, G. R., Lee, H. C., Lim, R. S. H., & Fullerton, J. (2010). Recruitment of hard‐to‐
reach population subgroups via adaptations of the snowball sampling strategy.
Nursing & health sciences, 12(3), 369-374.
Salleh, D. & Siong, H.C., (2008). The involvement of private sector in local
infrastructure development in Malaysia. Jurnal Alam Bina, 11 (2), pp.74 - 100.
Sanghi, A.,Sundakov, A.& Hankinson, D. (2007). Designing and using Public- Private
Partnership Units in Infrastructure: Lessons from Case Studies around the
World. Washington : World Bank .
https://openknowledge.worldbank.org/handle/10986/10644. (Assesed on 12th
May 2013).
Sanvido, V., Grobler, F., Parfitt, K., Guvenis, M., & Coyle, M. (1992). Critical success
factors for construction projects. Journal Of Construction Engineering and
Management, 118(1), 94-111.
Saunders, M. N., Saunders, M., Lewis, P., & Thornhill, A. (2011). Research methods for
business students, 5/e: Pearson Education India.
Shaoul, J. (2002). New Developments: A financial appraisal of the London underground
public-private partnership. Public Money and Management, 22(2), 53-60.
Spencer, D. (1997). Spotlight on Best Value 1, Raising the Curtain. Local Government
Information Unit. London.
Stewart, A.C. & Carpenter-Hubin, J. (2000). The Balanced Scorecard Beyond Reports
and Rankingsé, Planning for Higher Education. Vol. 29, No. 2, pp. 37-42.
Storey, J. (1994). New Wave Manufacturing Strategies: Organization and Human
Resource Management Dimensions, Chapman and Hall. London.
Tam, C. M., Li, W. Y., & Chan, A. P. C. (1994). BOT applications in the power
industry of South East Asia: A case study in China. In East meets
173
West.Procurement Systems Symposium CIB W92 Proceedings Publication 175,
CIB, Hong Kong, 315–322.
Takim, R., Ismail, K., Nawawi, A.H. & Jaafar, A. (2009). The Malaysian private
finance initiative and value for money. Asian Social Science, 5(3): 103 - 111.
Takim, R. & Akintoye, A., (2002). Performance Indicators for Successful Construction
Project Performance. In 18th Annual ARCOM Conference. Nothumbria, 2002.
University of Northumbria.
Takim, R., Ismail, K. & Nawawi, A.H. (2011). A Value for Money Assessment Method
for Public Private Partnership: A lesson from Malaysian approach. In
International Conference on Economics and Finance Research, 4 (2011)
IACSIT Press, Singapore.
Thabane, L., Ma, J., Chu, R., Cheng, J., Ismaila, A., Rios, L. P., & Goldsmith, C. H.
(2010). A tutorial on pilot studies: the what, why and how. BMC Medical
Research Methodology, 10(1), 1.
Threadgold, A. (1996). Private Financing of Infrastructure and other Long-Term Capital
Projects. Journal of Applied Finance and Investment, 7-12.
Tiong, R. L., Yeo, K. T., & McCarthy, S. C. (1992). Critical success factors in winning
BOT contracts. Journal of Construction Engineering and Management, 118(2),
217-228.
Tiong, R. L. (1996). CSFs in competitive tendering and negotiation model for BOT
projects. Journal of Construction Engineering and Management, 122(3), 205-
211.
Tsukada, S. (2015). Adoption of shadow bid pricing for enhanced application of
“value for money” methodology to PPP programs. Public Works Management
& Policy, 16 (1).
TTF (1997). Treasury Taskforce Guidance, Partnerships for Prosperity, HMSO,
London.
Turner, J. R. (2004). Farsighted project contract management: incomplete in its entirety.
Construction Management and Economics , 22 (1): 75-83.
UKAS (2009). Garispanduan kerjasama awam swasta or guideline on PPP. PPP Unit
Malaysia www.3pu.gov.my . (Accessed on 15 September 2012).
UNESCAP (2009). A Guidebook on Public - Private Partnership in Infrastructure.
Bangkok: United Nations Economic and Social Commison for Asia and Pacific.
174
UNESCAP (2014). United Nations.
http://www.unescap.org/sites/default/files/8.%20PPP%20Structure%20
%20Financing%20Source.pdf. (Accessed on 11th
January 2015).
U. N. Habitat (2011). Infrastructure for Economic Development and Poverty Reduction
in Africa. United Nations Human Settlements Programme, p14. http://mirror.
unhabitat.org/pmss/listItemDetails. aspx. (Assessed on 15th
June 2014).
Van Teijlingen, E. R., Rennie, A. M., Hundley, V., & Graham, W. (2001). The
importance of conducting and reporting pilot studies: the example of the
Scottish Births Survey. Journal of Advanced Nursing, 34(3), 289-295.
Wacker J.G (1998). A definition of Theory: Research Guidelines for Different Theory-
Building Research Methods in Operations Management. Journal of Operations
Management, Vol 16 No(4), pp 361-385.
Waggoner, D.B., Neely A.D., and Kennelly, M.P (1999). The forces that shape
organizational performance measurement systems: an interdisciplinary review.
International Journal of Production Economics. Vol. 60, pp 53-60
Walker, C. T. (1995). Privatized Infrastructure: The Build Operate Transfer Approach.
London : Thomas Telford.
Wang, D & Dai D. (2010). Research on the Concessionaire selection for Build -
Operate-Transfer Projects, Proceedings of International Conference on
Management and Service Science (MASS), Wuhan (China), 24-26 August.
Weber, B. & Alfen, H.W. (2010), Infrastructure as an Asset Class: Investment
Strategies, Project Finance, and PPP. John Wiley & Sons, West Sussex.
Weinberg, D. (2008). The Philosophical Foundations of Constructionist Research.
Handbook of constructionist research: Guilford Publications. 13-39.
Wen-xiong, W., Qi-ming, L., Xiao-peng, D., Li-hua, L., & Yuan, C. A. I. (2007).
Selecting Optimal Private-Sector Partner in Infrastructure Projects under PPP
Model. In International Conference on Management Science and Engineering,
ICMSE 2007. (pp. 2264-2270). Institute of Electrical and Electronics Engineers.
Whetten, D. (2005). Developing Managerial Skills. India: Pearson - Prentice Hall.
Wibowo, A. & Mohamed, S. (2010). Risk criticality and allocation in privatised water
supply projects in Indonesia. International Journal of Project Management.
Vol. 28 No. 5, pp. 504-513.
Walsham G. (1993). Interpreting Information Systems in Organizations: Wiley.
175
Watermeyer, R. (2013), “Value for money in the delivery of public infrastructure”, in
Laryea, S. & Agyepong, S. (Eds), Proceedings of 5th West Africa Built
Environment Research (WABER) Conference, Accra, Ghana, 12-14 August, pp.
3-19.
Webster‟s Dictionary (2012). http://www.merriam- webster.com/dictionary/. (Assessed
on April 25th
2012).
Winberg, C. (1997). How to Research and Evaluate. Juta: Cape Town, South Africa.
Woodhouse, E. (2006a). IPP study case selection and project outcomes: an additional
note. Working paper: program on energy and sustainable development at the
center for environmental science and policy, Stanford University.
http://www.iisdb stanford.edu/pubs/21262/IPP_Study_-
_Country_and_Project_Annex.pdf . (Accessed on 20th
November 2014).
World Bank (1994). World Development Report: Infrastructure for Development. New
York. Oxford University Press.
World Bank (1997). Selecting an Option for Private Sector Participation, Washington,
D.C.
World Bank, (2006). World Bank.
https://www.openknowledge.worldbank.org/bitstream/handle/10986/10743/3754
00Gridlines0401PUBLIC1.pdf?sequence=1. (Accessed on 14th December
2013).
World Bank, (2007). World Bank.
https://openknowledge.worldbank.org/bitstream/handle/10986/11023/419760BR
I0Acti10060321443B01PUBLIC1.pdf?sequence=1. (Accessed on 19th
November 2013).
World Bank (2012): Public Private Infrastructure Advisory Facility (PPIAF). World
Bank. http://ppp.worldbank.org/public-private-
partnership/agreements/concessions-bots-dbos. (Accessed on 11th
November
2013).
World Bank, (2013). Public Private Partnership Infrastructure Advisory Facility
(PPIAF). PPP In Infrastructure Resource Center: World Bank.org.
http://ppp.worldbank.org/public-private-partnership/agreements/concessions-
bots-dbos. (Assessed on August 20th
2013).
176
World Bank (2015). World Bank.
http://ppp.worldbank.org/public-private-partnership/overview/ppp-objectives
(Assessed on 18th
January 2015).
World Bank (2006). World Bank.
https://openknowledge.worldbank.org/bitstream/handle/10986/10743/375400Gri
dlines0401PUBLIC1.pdf?sequence=1
(Assessed on 16th
May 2015).
World Economic Forum (2014). WEF.
http://reports.weforum.org/strategic-infrastructure-2014/2-enabling-om-best-
practices/2-3-reform-governance/ (Assessed on 15th
April 2015).
Xu, Y., Sun, C., Skibniewski, M. J., Chan, A. P., Yeung, J. F., & Cheng, H. (2012).
System Dynamics (SD)-based concession pricing model for PPP highway
projects. International Journal of Project Management, 30(2), 240-251.
Yaacob, Y & Naidu, G. In Kohli, H. S., Mody, A., & Walton, M. (Eds.). (1997).
Choices for Efficient Private Provision of Infrastructure in East Asia (Vol. 961).
World Bank Publications.
Yaacob, Y & Naidu, G. (2000). Contracting for private provision of infrastructure: The
Malaysian experience. In Harinder Kohli, Ashoka Mody and Michael
Walton(2000). Choices for Efficient Private Infrastructure Provision in East
Asia. (Eds.). World Bank, Washington, D.C.
Yepes, T. (2005). Expenditure on Infrastructure in East Asia Region. Manila : Asian
Development Bank .
Yuan, J., Skibniewski, M. J., & Li, Q. (2008). Managing the Performance of Public
Private Partnership Projects to Achieve Value for Money: Key performance
indicators selection. International Conference on Multi-national Construction
Projects, Shanghai, China.
Yeung, F.Y. (2007). Developing a Partnering Performance Index (PPI) for
Construction Projects – A Fuzzy Set Theory Approach. PhD theses. The Hong
Kong Polytechnic University, Hong Kong.
Zhang, X. (2005). Critical success factors for public– private partnerships in
infrastructure development. Journal of Construction Engineering and
Management, 3-14.
177
Zhang, X. (2006). Factor analysis of public clients best-value objective in public –
privately partnered infrastructure projects. Journal of Construction Engineering
and Management.132(9), pp. 956 –965.
Zhang, X. (2004). Concessionaire selection: methods and criteria. Journal of
Construction Engineering and Management, 130(2), 235-244.
Zhang, X. (2009). Win–win concession period determination methodology. Journal of
Construction Engineering and Management, 135(6), 550-558.