93
© Husch Blackwell LLP Best Practices for Managing Construction Delay and Interference Claims Kenneth A. Slavens 314.345.6419 WELCOME

Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

© Husch Blackwell LLP

Best Practices for Managing Construction Delay and Interference Claims

Kenneth A. Slavens314.345.6419

WELCOME

Page 2: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Topics to be covered

DelayAccelerationDisruption

© 2014 Husch Blackwell LLP. All rights reserved.

Page 3: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – Impact on Project Participants

For the contractorAdjustments in timeAdjustment in costs

For the ownerLoss of useLiquidated damages

© 2014 Husch Blackwell LLP. All rights reserved.

Page 4: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Escalation – Impact on Project Participants

More resources need to complete the project on schedule

Completion date need not be delayedIncreased cost attributable to performing work at a date later than plannedImpact of changes in sequence can cause escalation in costs

© 2014 Husch Blackwell LLP. All rights reserved.

Page 5: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Disruption – Effect on Project

Potential impact of extra work:Disruption in the planned sequence of the workExtend the work into inclement weatherImpact productivity of the trades

© 2014 Husch Blackwell LLP. All rights reserved.

Page 6: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – Why talk about it?

For the contractorMay need additional timeMay consume additional resources

For the ownerProject not delivered when promised (loss of use)Not generating revenueEntitlement to Actual or Liquidated Damages

© 2014 Husch Blackwell LLP. All rights reserved.

Page 7: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – Entitlement to Additional Time

Contractor's entitlement to additional time to complete:

If the delay is excusable

Potentially can recover increased costs as well

© 2014 Husch Blackwell LLP. All rights reserved.

Page 8: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delays – If an excusable delay

For the contractor, an excusable delay will:Justify time extensionsPreclude termination of the contract for the delayPreclude recovery of actual or liquidated damage

© 2014 Husch Blackwell LLP. All rights reserved.

Page 9: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – Is the delay excusable?

Read the Contract: frequently defines “excusable” delays

Examples common in contracts or if the contract is silentOwner or architect delaysActs of God / Unforeseeable EventsStrikesOwner Supplied materials

© 2014 Husch Blackwell LLP. All rights reserved.

Page 10: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delays – What if the delay was foreseeability?

Some circumstances, even if the cause of the delay is an otherwise “excusable” event, it may not be excused

If the event is "known or knowable," i.e.: contractor knows that there is an impending strike when the contract is signed

© 2014 Husch Blackwell LLP. All rights reserved.

Page 11: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – Impact of foreseeability on an otherwise excusable delay

Dicon, Inc. v. Marben Corp.

Contractor knew the owner would be late delivering plans and specs

Cannot rely on this owner delay for extra time

© 2014 Husch Blackwell LLP. All rights reserved.

Page 12: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – Foundation Underlying an Excusable Delay

Implied term of every contract: Neither party will do anything to prevent performance by the other party or permit an act that will hinder or delay performance

Owner prevents or hinders the contractor's performance: excusable

Changes in the work at the direction of the Owner, for example, may cause an excusable delay

© 2014 Husch Blackwell LLP. All rights reserved.

Page 13: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – Liquidated Damages

Generally enforceable

May need to show that the calculation of damages from late completion is impossible or very difficult to estimate at time of execution of the contract

Amount is a reasonable forecast of the harm of late completion

© 2014 Husch Blackwell LLP. All rights reserved.

Page 14: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – Liquidated Damages and the Public Project

For public works contracts a reasonable approximate is not necessary

Public body needs to only show unexcused late completion

© 2014 Husch Blackwell LLP. All rights reserved.

Page 15: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – Liquidated Damages

Liquidated Damage are the owner’s sole recovery for late completion

Even if the actual damages exceed the liquidated damage amount - as long a not “unreasonably disproportionate” to actual damages

© 2014 Husch Blackwell LLP. All rights reserved.

Page 16: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – Notice of Delay

Read the contractFrequently required by the contractWhen in doubt – give the notice even if the contract is unclear

Failure to give the notice can bar an extension for an otherwise excusable delay.

See: Southwest Engineering Co. v. Reorganized School District R-9

© 2014 Husch Blackwell LLP. All rights reserved.

Page 17: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – It's Excusable, but is it compensable?

May be excusable, but does not equate to compensable (more money)

Excusable delay will entitle a contractor to more time

Must be compensable to be entitled to more money

© 2014 Husch Blackwell LLP. All rights reserved.

Page 18: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – What is compensable?

Compensable: damages are recoverable from the party that "caused" the delay

Neither party caused the delay: neither is entitled to recover from the other

© 2014 Husch Blackwell LLP. All rights reserved.

Page 19: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – Compensable Delay

Examples of events for which the owner may have liability:

Work suspensionsInterferencesHindrancesDesign DefectsDiffering site conditions

© 2014 Husch Blackwell LLP. All rights reserved.

Page 20: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Protection from Delay Damages: No Damage for Delay Clauses

“No Damage for Delay” clauses – theoretically Protect the owner from all delays

Downside: contractor may build additional funds into the bid to account for the risk and drive up the cost (you may end up paying for an event that never happens)

Generally enforceable on private projects

© 2014 Husch Blackwell LLP. All rights reserved.

Page 21: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Protection from Delay Damages: No Damage for Delay Clauses

For public projects:

Many states have statutes invalidating these clauses on public works projects

Void in Missouri: Section 34.058, RSMo 2000

© 2014 Husch Blackwell LLP. All rights reserved.

Page 22: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – What Damages can be Recovered

Reasonably foreseeable damages caused by a compensable delay are recoverable

Increased labor Equipment Office overheadGeneral conditionsInterest

© 2014 Husch Blackwell LLP. All rights reserved.

Page 23: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – What Damages can be Recovered

Owner Damages:

Loss of use of the projectLoss of revenue which would have been generatedLiquidated Damages

© 2014 Husch Blackwell LLP. All rights reserved.

Page 24: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Overriding Principal to Damage Recovery

Increased costs are recoverableif the costs would not have been incurred, but for the delay

© 2014 Husch Blackwell LLP. All rights reserved.

Page 25: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – Proving Damages

Methods of proving damages

Total Cost MethodModified Total Cost MethodJury Verdict Method

© 2014 Husch Blackwell LLP. All rights reserved.

Page 26: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Total Cost

Total Cost Method is highly disfavoredViewed with caution Considered a last resort

Underlying premise of Total Cost MethodContractor’s compensable damages are the difference between the costs expected at the outset (the contractor’s estimate) and the actual costs

Assumes the only reason for the delay is the owner-caused delay

© 2014 Husch Blackwell LLP. All rights reserved.

Page 27: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Total Cost

Assumes the project would have occurred exactly as expected, but for the excusable delay

Assumes:Original estimate of the contractor was accurateAll increased costs were caused by the other party

© 2014 Husch Blackwell LLP. All rights reserved.

Page 28: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Total Cost

To have the Total Cost Method accepted, must show:Impossible to estimate actual damages with a reasonable degree of certaintyThe estimate was accurateActual cost of performing the work was reasonableNo other causes for increased costs aside from the compensable delayContractor used a reasonable accounting system to accumulate job costs

© 2014 Husch Blackwell LLP. All rights reserved.

Page 29: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Total Cost

Fundamental Concept of Total Cost Recovery: the contractor cannot share any of the liability for the delays

Concept is virtually impossible to prove

© 2014 Husch Blackwell LLP. All rights reserved.

Page 30: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Modified Total Cost

Avoids inflexibility of Total Cost Method

Allows flexibility – particularly two main elementsAccuracy of the estimate

Can address inaccuraciesCan address mistakes

Actual Costs incurred: remove those costs not the responsibility of the Owner

© 2014 Husch Blackwell LLP. All rights reserved.

Page 31: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Jury Verdict Method

Different spin on the Total Cost MethodNeed to establish:

Contractor is damagedDefendant is responsible

Must prove damages "beyond speculation"Allows the “jury” to make a fair and reasonable approximation of the contractor’s damages

No Missouri case has accepted this method

© 2014 Husch Blackwell LLP. All rights reserved.

Page 32: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Schedule Analysis

Generally accepted – more reliable than the Total Cost Method, Modified Total Cost, or Jury Verdict

Use General Conditions ApproachSpecifically identify the effect of the delay on each element of increased costQuantify

The delay The increased costs

© 2014 Husch Blackwell LLP. All rights reserved.

Page 33: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Common Components of Delay Damages

Most commonly associated with a delay claimGeneral conditions (direct overhead)Office overhead (indirect overhead)Equipment CostsProductivity LossesAdditional Interest

© 2014 Husch Blackwell LLP. All rights reserved.

Page 34: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – General Conditions / Direct Overhead

Common elementsProject managers and project administratorsUtilitiesProject Trailer or OfficeSecurityEquipment

Generally can show a direct connection between increased project time and increased costs

© 2014 Husch Blackwell LLP. All rights reserved.

Page 35: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages - Extended Home Office Overhead / Indirect Overhead

Often called “indirect overhead” or “general and administrative costs”

Damages claimed in this area are often attackedThey are often thought of as “soft” damagesThey vary greatly depending on the accounting methods

No generally accepted protocol for what is included in home office overhead

© 2014 Husch Blackwell LLP. All rights reserved.

Page 36: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Extended Home Office Overhead / Indirect Overhead

Most of the home office overhead is time drivenIf a project is extended beyond the reasonable projection, home office costs are also extended

Not absorbed by the project

Costs incurred benefit all of the contractor’s projects

© 2014 Husch Blackwell LLP. All rights reserved.

Page 37: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Extended Home Office Overhead / Indirect Overhead

Virtually impossible to directly allocate overhead costs to a specific delay period

Fraught with accounting difficulties

Multiple jobs with varying start dates and completion dates makes it almost impossible

© 2014 Husch Blackwell LLP. All rights reserved.

Page 38: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Extended Home Office Overhead / Indirect Overhead

Recovery is based on the argument that there should be recovery because the delay precluded other projects from being able to absorb the overhead

Need to prove: Other work is available and the contractor would have been able to obtain that work; orThe contractor tried to obtain that work to absorb the overhead

© 2014 Husch Blackwell LLP. All rights reserved.

Page 39: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Extended Home Office Overhead / Indirect Overhead

Eichleay allocates home office overhead on a ratioDelayed project’s billings to the firm’s total contract billingsDuring the period of the performance of the delayed project

Total overhead amount for the period of the delayed project is divided by the number of actual contract days to determine daily rate

Multiply the number of days of delay by the daily overhead rate

© 2014 Husch Blackwell LLP. All rights reserved.

Page 40: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Home Office Overhead / Indirect Overhead

Use of Eichleay: still “estimates” the overhead

Fails to consider:Inefficient managementTiming of the delay on the overhead levelsImpact of other work during the project’s delay

© 2014 Husch Blackwell LLP. All rights reserved.

Page 41: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Recovery of Equipment Costs

Idle or under-utilized equipmentConsider

Ownership costsMaintenance RepairStorage Depreciation

Rental Rates

© 2014 Husch Blackwell LLP. All rights reserved.

Page 42: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Interest

Review the contractMay have circumstances when you can recoverMay have the rate for interest

Refer to the statute if no contract provisionSection 408.020 RSMo 2000Interest at 9%

If liquidatedLiquidated: amount can be determined by mathematical computation

© 2014 Husch Blackwell LLP. All rights reserved.

Page 43: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay Damages – Interest

Interest generally does not begin to accrue until there is a demand for payment

Make your liquidated claim as soon as possible to trigger the interest

© 2014 Husch Blackwell LLP. All rights reserved.

Page 44: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delays – Problems caused by Concurrent or Joint Cause

General proposition: no liability for the other party’s delays unless

Caused by the partyCaused by circumstances under the party’s control

Contractual clauses can change this allocation of risk

© 2014 Husch Blackwell LLP. All rights reserved.

Page 45: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delay – Early Completion

Even if the contractor finishes earlier than the contractual completion date

Can still claim a delay if the party can show the project would have finished earlier than it did but for the compensable delay

© 2014 Husch Blackwell LLP. All rights reserved.

Page 46: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Impact, Escalation, and Acceleration

Conduct of others may hinder productivity - even if finished on time

May cause:Out of sequence workStacking of tradesCongestionShift workAccess issues

© 2014 Husch Blackwell LLP. All rights reserved.

Page 47: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Impact, Escalation, and Acceleration

Escalation: increased cost attributable to performing the work at a later date than planned

Acceleration: process of adding resources to the project to complete on schedule

© 2014 Husch Blackwell LLP. All rights reserved.

Page 48: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Disruption

Generally associated with change ordersRipple effect impacts the project aside from the direct costs associated with the changeContractors will often try to preserve the indirect impact from the changesAbsent the preservation, the Owner may well have a valid defense to subsequent claims

The Change Order is “accord and satisfaction”Relieves the Owner from responsibility for the ripple effect

© 2014 Husch Blackwell LLP. All rights reserved.

Page 49: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Delays and Interference Claims

Ken [email protected]

314-345-6419

© 2014 Husch Blackwell LLP. All rights reserved.

Page 50: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Best Practices for Managing Construction Delay

and Interference Claims

Prepared and Presented by:

Quackenbush & Associates

April 23, 2014

© 2014 Husch Blackwell LLP. All rights reserved.

Page 51: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

A step by step presentation of a contemporaneous schedule

analysis performed during the project.

(Resolving delays as they occur)

© 2014 Husch Blackwell LLP. All rights reserved.

Page 52: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

A RESTAURANT RENOVATION

30

Final Trimout - Project

Complete

47 3 89 3 7 4

Floor & Wall Tile In Kitchen

Laminate Panels In Kitchen

Sawcut Concrete Slab -Install Gas &

Plumbing Patch

Concrete

Kitchen WallFraming

Kitchen Rough-In Electrical

20 24 284 8 12 16

5 5 4 35 4 5 6

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

Dining Area Carpet

NTP & Complete Interior

Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

14 18 22 261 2 6 10

KitchenDrywall

Set, Hook-Up

& TestAll KitchenEquipment

© 2014 Husch Blackwell LLP. All rights reserved.

Page 53: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS TECHNIQUE

0 5 5 9 9 14 14 20 20 25 25 30 30 34 34 37

5 14 14 17 17 24 24 28 28 35 35 38 38 46 46 50

A RESTAURANT RENOVATION

+9 +9 +9 +90 +3 +3 +4

1 2 6 10 14 18 22 26

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

Dining Area Carpet

5 4 5 6 5 5 4 3

0 0 00 0 0 0

20 24 284 8 12 16

Floor & Wall Tile In Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

7 3 89 3 7 4

0

30

4

FLOAT

CRITICAL PATH KitchenDrywall

Set, Hook-Up & Test

All KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

© 2014 Husch Blackwell LLP. All rights reserved.

Page 54: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION

QUACKENBUSH & ASSOCIATES, INC.

IMPACTSTEP

DELAYSTARTDATE

DATADATE

SCHEDULERUN

NUMBER DESCRIPTION

PROJECTEDCOMPLETION

DATE

DAYSOF

DELAY CONCURRENCY

0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0

© 2014 Husch Blackwell LLP. All rights reserved.

Page 55: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS TECHNIQUE

0 5 5 9 9 14 14 20 20 25 25 30 30 34 34 37

5 14 16 19 19 26 26 30 30 37 37 40 40 48 49 53

14 16 48 49

A RESTAURANT RENOVATIONIMPACT #1 - ADD 2ND DEEP FRYER

1

0

I10

2

0

I11

0

30

47 3 89 3 7 4

Floor & Wall Tile In

Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

20 24 284 8 12 16

0 0 00 0 0 0

5 5 4 35 4 5 6

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

Dining Area Carpet

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

14 18 22 261 2 6 10

0 +5 +5 +6 +12 +12 +12 +12

KitchenDrywall

Set, Hook-Up

& TestAll KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

Original CompletionDate = 50Net Delay -3

Saw Cutting &

PipingFor 2nd

Deep Fryer

Install 2nd

Deep Fryer

© 2014 Husch Blackwell LLP. All rights reserved.

Page 56: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION

QUACKENBUSH & ASSOCIATES, INC.

IMPACTSTEP

DELAYSTARTDATE

DATADATE

SCHEDULERUN

NUMBER DESCRIPTION

PROJECTEDCOMPLETION

DATE

DAYSOF

DELAY CONCURRENCY

0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0

1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3

© 2014 Husch Blackwell LLP. All rights reserved.

Page 57: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS TECHNIQUE

100% 5 75% 4

55% 9

UPDATE A - END OF DAY 10

1

I10

2

I11

30

47 3 83 7 4

Floor & Wall Tile In

Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

20 24 284 8 12 16

4 35 6 5 5

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

Dining Area Carpet

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

14 18 22 261 2 6 10

KitchenDrywall

Set, Hook-Up

& Test

All KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

Saw Cutting &

PipingFor 2nd

Deep Fryer

Install 2ndDeep Fryer

0 1

4

Update AEnd of Day 10

© 2014 Husch Blackwell LLP. All rights reserved.

Page 58: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS TECHNIQUE

11 11 16 16 22 22 27 27 32 32 36 36 39

100% 5 75% 4

14 16 19 19 26 26 30 30 37 37 40 40 48 49 53

55% 9

14 16 48 49

UPDATE A - END OF DAY 10

+10 +10 +10 +10+3 +3 +4

1 2 6 10 14 18 22 26

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

Dining Area Carpet

5 6 5 5 4 3

0 0 00 0 0 0

20 24 284 8 12 16

Floor & Wall Tile In

Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

7 3 83 7 4

0

30

4

1

0

I10

2

0

I11

KitchenDrywall

Set, Hook-Up

& TestAll KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

Project CompletionUnchanged - NetDelay = 0Some Float UsedOn Non-CriticalActivities

Saw Cutting &

PipingFor 2nd

Deep Fryer

Install 2ndDeep Fryer

0 1

4

Update AEnd of Day 10

© 2014 Husch Blackwell LLP. All rights reserved.

Page 59: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION

QUACKENBUSH & ASSOCIATES, INC.

IMPACTSTEP

DELAYSTARTDATE

DATADATE

SCHEDULERUN

NUMBER DESCRIPTION

PROJECTEDCOMPLETION

DATE

DAYSOF

DELAY CONCURRENCY

0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0

1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3

2 N/A DAY 10 2 STATUS UPDATE – END OF DAY 10 53 0

© 2014 Husch Blackwell LLP. All rights reserved.

Page 60: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS TECHNIQUE

5

100% 0 75% 1

55% 4

IMPACT #2 - FIND AND MOBILIZE NEW ELECTRICAL SUBCONTRACTOR

I20

New Electrical Sub

1 2 6 10 14 18 22 26

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

Dining Area Carpet

5 6 5 5

20 24 284 8 12 16

Floor & Wall Tile In

Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

7 3 83 7 4

30

4

I11

4 3

1

I10

2

KitchenDrywall

Set, Hook-Up

& TestAll KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

Saw Cutting &

PipingFor 2nd

Deep Fryer

Install 2ndDeep Fryer

© 2014 Husch Blackwell LLP. All rights reserved.

Page 61: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS TECHNIQUE15

5

11 15 20 20 26 26 31 31 36 36 40 40 43

100% 0 75% 1

14 16 19 20 27 27 31 31 38 38 41 41 49 50 54

55% 4

14 16 49 50

IMPACT #2 - FIND AND MOBILIZE NEW ELECTRICAL SUBCONTRACTOR

1

I10

2

I11

4 3

30

47 3 83 7 4

Floor & Wall Tile In

Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

20 24 284 8 12 16

5 6 5 5

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

Dining Area Carpet

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

14 18 22 261 2 6 10

I20

New Electrical Sub

KitchenDrywall

Set, Hook-Up

& Test

All KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

Project CompletionExtended by 1 Day = Total Delays to Date -4

Saw Cutting &

PipingFor 2nd

Deep Fryer

Install 2ndDeep Fryer

© 2014 Husch Blackwell LLP. All rights reserved.

Page 62: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Was Impact #2 – Electrical Subcontractor Replacement paced?What other options did contractor have?1. Pay premium to start ASAP.2. Hire on time and materials basis.

What if contractor mis-judges the amount of pacing time available?Is it still pacing?

© 2014 Husch Blackwell LLP. All rights reserved.

Page 63: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION

QUACKENBUSH & ASSOCIATES, INC.

IMPACTSTEP

DELAYSTARTDATE

DATADATE

SCHEDULERUN

NUMBER DESCRIPTION

PROJECTEDCOMPLETION

DATE

DAYSOF

DELAY CONCURRENCY

0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0

1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3

2 N/A DAY 10 2 STATUS UPDATE – END OF DAY 10 53 0

3 DAY 10 DAY 10 3 IMPACT #2 – REPLACE ELECTRICAL SUBCONTRACTOR

54 -1 SEE BELOW

Summary of Delays (If Impact #2 Was Paced)

Owner Responsible (Impact #1 & #3)

Contractor Responsible (Impact #2)

Summary of Delays (If Impact #2 Was Not Paced)

Owner Responsible (Impact #3)

Contractor Responsible (Last Day Impact #2)

Concurrent (Impact #1 & First 3 Days of Impact #2)© 2014 Husch Blackwell LLP. All rights reserved.

Page 64: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS TECHNIQUE

100% 5

20 20 26 26 31 31 36 36 40 40 43

100% 0 75% 1 60% 5

20 20 27 27 31 31 38 38 41 41 49 50 54

55% 4 3

49 50

UPDATE B - END OF DAY 18

47 3 8

3020 24 284 8 12

1

I10

2

I11

4 3

7 4

Floor & Wall Tile In

Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

16

6 5 5

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

Dining Area Carpet

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

14 18 22 261 2 6 10

I20

New Electrical Sub

KitchenDrywall

Set, Hook-Up

& Test

All KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

Saw Cutting &

PipingFor 2nd

Deep Fryer

Install 2ndDeep Fryer

Update BEnd of Day 18

2

0

0100%

100% 0

100% 0

30% 2

Project CompletionDate UnchangedDelays to Date -4

© 2014 Husch Blackwell LLP. All rights reserved.

Page 65: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION

QUACKENBUSH & ASSOCIATES, INC.

IMPACTSTEP

DELAYSTARTDATE

DATADATE

SCHEDULERUN

NUMBER DESCRIPTION

PROJECTEDCOMPLETION

DATE

DAYSOF

DELAY CONCURRENCY

0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0

1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3

2 N/A DAY 10 2 STATUS UPDATE – END OF DAY 10 53 0

3 DAY 10 DAY 10 3 IMPACT #2 – REPLACE ELECTRICAL SUBCONTRACTOR

54 -1 SEE BELOW

4 N/A DAY 18 4 STATUS UPDATE – END OF DAY 18 54 0

Summary of Delays (If Impact #2 Was Paced)

Owner Responsible (Impact #1 & #3)

Contractor Responsible (Impact #2)

Summary of Delays (If Impact #2 Was Not Paced)

Owner Responsible (Impact #3)

Contractor Responsible (Last Day Impact #2)

Concurrent (Impact #1 & First 3 Days of Impact #2)© 2014 Husch Blackwell LLP. All rights reserved.

Page 66: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS TECHNIQUE

100% 0

20 20 26 26 31 31 36 36 40 40 43

100% 0 100% 0 60% 2

20 20 27 30 34 34 41 41 44 44 52 53 57

100% 0 2

27 30 52 53

IMPACT #3 CITY REQUIRES ELECTRICAL IMPROVEMENTS

I30

3

I20

New Electrical Sub

14

6 5

1 2 6 10 18 22 26

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

Dining Area Carpet

5

20 24 284 8 12 16

Floor & Wall Tile In

Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

7 3 87 4

30

4

4 3

1

I10

0

I11

KitchenDrywall

Set, Hook-Up

& Test

All KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

Saw Cutting &

Piping

For 2nd Deep Fryer

Install 2ndDeep Fryer

100%

30%

Project CompletionExtended by -3 DaysProject Delay to Date = -7

CityRequiresElectrical

Improvements

© 2014 Husch Blackwell LLP. All rights reserved.

Page 67: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION

QUACKENBUSH & ASSOCIATES, INC.

IMPACTSTEP

DELAYSTARTDATE

DATADATE

SCHEDULERUN

NUMBER DESCRIPTION

PROJECTEDCOMPLETION

DATE

DAYSOF

DELAY CONCURRENCY

0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0

1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3

2 N/A DAY 10 2 STATUS UPDATE – END OF DAY 10 53 0

3 DAY 10 DAY 10 3 IMPACT #2 – REPLACE ELECTRICAL SUBCONTRACTOR

54 -1 SEE BELOW

4 N/A DAY 18 4 STATUS UPDATE – END OF DAY 18 54 0

5 DAY 22 DAY 18 5 IMPACT #3 – CITY REQUIRES ELECTRICAL UPGRADE

57 -3

Summary of Delays (If Impact #2 Was Paced)

Owner Responsible (Impact #1 & #3)

Contractor Responsible (Impact #2)

Summary of Delays (If Impact #2 Was Not Paced)

Owner Responsible (Impact #3)

Contractor Responsible (Last Day Impact #2)

Concurrent (Impact #1 & First 3 Days of Impact #2)© 2014 Husch Blackwell LLP. All rights reserved.

Page 68: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS TECHNIQUE

100% 0

35 35 40 40 44 44 47

100% 0 100% 0 60% 2

34 34 41 41 44 44 52 53 57

100% 0 2

52 53

UPDATE C END OF DAY 31

1

I10

0

I11

4 3

30

47 3 87 4

Floor & Wall Tile In

Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

24 284 8 12 16 20

Dining Area Carpet

5

18 22 26

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

1 2 6 10

I30

3

I20

New Electrical Sub

14

6 5

KitchenDrywall

Set, Hook-Up

& TestAll KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

Saw Cutting &

PipingFor 2nd

Deep Fryer

Install 2ndDeep Fryer

100%

30%

Project CompletionDate - UnchangedDelays to Date -7

CityRequiresElectrical

Improvements

100%0

100%0 100% 0

100% 0

100% 20% 4

25% 3

0

Update CEnd of Day 31

© 2014 Husch Blackwell LLP. All rights reserved.

Page 69: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION

QUACKENBUSH & ASSOCIATES, INC.

IMPACTSTEP

DELAYSTARTDATE

DATADATE

SCHEDULERUN

NUMBER DESCRIPTION

PROJECTEDCOMPLETION

DATE

DAYSOF

DELAY CONCURRENCY

0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0

1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3

2 N/A DAY 10 2 STATUS UPDATE – END OF DAY 10 53 0

3 DAY 10 DAY 10 3 IMPACT #2 – REPLACE ELECTRICAL SUBCONTRACTOR

54 -1 SEE BELOW

4 N/A DAY 18 4 STATUS UPDATE – END OF DAY 18 54 0

5 DAY 22 DAY 18 5 IMPACT #3 – CITY REQUIRES ELECTRICAL UPGRADE

57 -3

6 N/A DAY 31 6 STATUS UPDATE – END OF DAY 31 57 0

Summary of Delays (If Impact #2 Was Paced)

Owner Responsible (Impact #1 & #3)

Contractor Responsible (Impact #2)

Summary of Delays (If Impact #2 Was Not Paced)

Owner Responsible (Impact #3)

Contractor Responsible (Last Day Impact #2)

Concurrent (Impact #1 & First 3 Days of Impact #2)© 2014 Husch Blackwell LLP. All rights reserved.

Page 70: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS TECHNIQUE

100% 0

41 41 46 46 50 50 53

100% 0 100% 0 100% 0

41 41 44 44 52 53 57

100% 0 100% 0

52 53

UPDATE D END OF DAY 40

I30

0

I20

New Electrical Sub

14

0 5

1 2 6 10 18 22 26

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

Dining Area Carpet

5

20 24 284 8 12 16

Floor & Wall Tile In Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

7 3 80 4

30

4

4 3

1

I10

0

I11

KitchenDrywall

Set, Hook-Up

& TestAll KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

Saw Cutting &

PipingFor 2nd

Deep Fryer

Install 2ndDeep Fryer

100%

Project CompletionDate - UnchangedDelays to Date -7

CityRequiresElectrical

Improvements

100%

100%

100% 80% 1

100% 0

Update DEnd of Day 40

90% 1

Update DEnd of Day 40

© 2014 Husch Blackwell LLP. All rights reserved.

Page 71: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION

QUACKENBUSH & ASSOCIATES, INC.

IMPACTSTEP

DELAYSTARTDATE

DATADATE

SCHEDULERUN

NUMBER DESCRIPTION

PROJECTEDCOMPLETION

DATE

DAYSOF

DELAY CONCURRENCY

0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0

1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3

2 N/A DAY 10 2 STATUS UPDATE – END OF DAY 10 53 0

3 DAY 10 DAY 10 3 IMPACT #2 – REPLACE ELECTRICAL SUBCONTRACTOR

54 -1 SEE BELOW

4 N/A DAY 18 4 STATUS UPDATE – END OF DAY 18 54 0

5 DAY 22 DAY 18 5 IMPACT #3 – CITY REQUIRES ELECTRICAL UPGRADE

57 -3

6 N/A DAY 31 6 STATUS UPDATE – END OF DAY 31 57 0

7 N/A DAY 40 7 STATUS UPDATE – END OF DAY 40 57 0

Summary of Delays (If Impact #2 Was Paced)

Owner Responsible (Impact #1 & #3)

Contractor Responsible (Impact #2)

Summary of Delays (If Impact #2 Was Not Paced)

Owner Responsible (Impact #3)

Contractor Responsible (Last Day Impact #2)

Concurrent (Impact #1 & First 3 Days of Impact #2)© 2014 Husch Blackwell LLP. All rights reserved.

Page 72: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS TECHNIQUE

100% 0

53

100% 0 100% 0 100% 0

53 57

100% 0 100% 0

51 52

UPDATE E END OF DAY 51

1

I10

0

I11

4 3

30

47 3 80 0

Floor & Wall Tile In

Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

24 284 8 12 16 20

Dining Area Carpet

5

18 22 26

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

1 2 6 10

I30

0

I20

New Electrical Sub

14

0 15

KitchenDrywall

Set, Hook-Up

& TestAll KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

Saw Cutting &

PipingFor 2nd

Deep Fryer

Install 2ndDeep Fryer

100%

CityRequiresElectrical

Improvements

100%

100%

100% 100%

100%

Update EEnd of Day 51

100% 0

Update EEnd of Day 51

100% 0

100% 0 100% 0 30% 2

100% 0

0

Project CompletionDate - UnchangedDelays to Date -7

© 2014 Husch Blackwell LLP. All rights reserved.

Page 73: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION

QUACKENBUSH & ASSOCIATES, INC.

IMPACTSTEP

DELAYSTARTDATE

DATADATE

SCHEDULERUN

NUMBER DESCRIPTION

PROJECTEDCOMPLETION

DATE

DAYSOF

DELAY CONCURRENCY

0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0

1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3

2 N/A DAY 10 2 STATUS UPDATE – END OF DAY 10 53 0

3 DAY 10 DAY 10 3 IMPACT #2 – REPLACE ELECTRICAL SUBCONTRACTOR

54 -1 SEE BELOW

4 N/A DAY 18 4 STATUS UPDATE – END OF DAY 18 54 0

5 DAY 22 DAY 18 5 IMPACT #3 – CITY REQUIRES ELECTRICAL UPGRADE

57 -3

6 N/A DAY 31 6 STATUS UPDATE – END OF DAY 31 57 0

7 N/A DAY 40 7 STATUS UPDATE – END OF DAY 40 57 0

8 N/A DAY 51 8 STATUS UPDATE – END OF DAY 51 57 0

Summary of Delays (If Impact #2 Was Paced)

Owner Responsible (Impact #1 & #3) = -6 Compensable Days

Contractor Responsible (Impact #2) = -1 Non-Compensable Days

Summary of Delays (If Impact #2 Was Not Paced)

Owner Responsible (Impact #3) = -3 Compensable Days

Contractor Responsible (Last Day Impact #2) = -1 Non-Compensable Days

Concurrent (Impact #1 & First 3 Days of Impact #2) = -3 Excusable/Non-Compensable Days© 2014 Husch Blackwell LLP. All rights reserved.

Page 74: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

COLLAPSED AS-BUILT ANALYSIS

5 4 5

9 3

14

6 5

6 10 26

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

1 2

4 8 12 16

Kitchen WallFraming

Kitchen Rough-In Electrical

7 4

Floor & Wall Tile In

Kitchen

30

47 3 8

24 2820

4 3

Dining Area Carpet

5

18 22

KitchenDrywall

Set, Hook-Up

& TestAll KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

RESTAURANT RENOVATION - AS-PLANNED SCHEDULE

© 2014 Husch Blackwell LLP. All rights reserved.

Page 75: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

THE BUT-FOR LEGAL CONCEPT

You can only claim damages (money and/or time) for delays that would not have been experienced “but-for” the delay in question.– Basis of concurrent delay theory– If you would have finished the project at the

same time – even if delay in question had not occurred – then you have a concurrent delay.

(Maybe! – Must Consider Pacing!)© 2014 Husch Blackwell LLP. All rights reserved.

Page 76: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

“BUT-FOR” SCHEDULE ANALYSIS

(If it makes sense in evaluating concurrent delays – why doesn’t it make sense in schedule analysis?)

© 2014 Husch Blackwell LLP. All rights reserved.

Page 77: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

THE PIT BULL PROJECT

© 2014 Husch Blackwell LLP. All rights reserved.

Page 78: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

© 2014 Husch Blackwell LLP. All rights reserved.

Page 79: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

PIT BULL MOVES IN NEXT DOOR

Pit Bulls can jump 3’ wall.Pit Bulls cannot jump 6’ wall.Owner directs contractor to build wall 6’ high instead of 3’ high.Contractor says – ok – but it will cost more and take 2 weeks longer.Owner OK’s added work

© 2014 Husch Blackwell LLP. All rights reserved.

Page 80: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

© 2014 Husch Blackwell LLP. All rights reserved.

Page 81: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

© 2014 Husch Blackwell LLP. All rights reserved.

Page 82: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

© 2014 Husch Blackwell LLP. All rights reserved.

Page 83: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

COLLAPSED AS-BUILT ANALYSIS

0 5 5 9 9 14 14 20 20 25 25 30 30 34 34 37

5 4 5

5 14 14 17 17 24 24 28 28 35 35 38 38 46 46 50

9 3

24 28

8

30

47 37 4

Floor & Wall Tile In

Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

4 8 12 16 20

Dining Area Carpet

5 4 3

18 22 26

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

1 2 6 14

6 5

10

KitchenDrywall

Set, Hook-Up

& TestAll KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

RESTAURANT RENOVATION - AS-PLANNED SCHEDULE

© 2014 Husch Blackwell LLP. All rights reserved.

Page 84: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

COLLAPSED AS-BUILT ANALYSIS0 15

15

0 5 5 9 15 20 20 26 26 41 41 46 46 50 50 53

5 4 5

5 14 16 20 20 27 30 34 34 41 41 44 44 51 53 57

9 4

14 16 27 30 51 52

AS-BUILT SCHEDULE

1

I10

2

I11

4 3

30

47 3 77 4

Floor & Wall Tile In

Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

24 284 8 12 16 20

Dining Area Carpet

5

18 22 26

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

Painting Dining Area

Dining Area Décor &

Woodwork

1 2 6 10

I30

3

I20

New Electrical Sub

14

6 15

KitchenDrywall

Set, Hook-Up

& TestAll KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

Saw Cutting &

PipingFor 2nd

Deep Fryer

Install 2ndDeep Fryer

CityRequires

ElectricalImprovements

As-BuiltCritical Path

LightFixtures

& ElectricalTerminations

Note: this work took longer than planned.

Note: this work was performed faster than planned.

Note: this work was paced to known project delays.

© 2014 Husch Blackwell LLP. All rights reserved.

Page 85: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

COLLAPSED AS-BUILT ANALYSIS

15

5 4 5

9 4

COLLAPSE OWNER DELAYS

1

I10

2

I11

4 3

30

47 3 77 4

Floor & Wall Tile In

Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

24 284 8 12 16 20

Dining Area Carpet

5

18 22 26

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

1 2 6 10

I30

3

I20

New Electrical Sub

14

6 15

KitchenDrywall

Set, Hook-Up

& TestAll KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

Saw Cutting &

PipingFor 2nd

Deep Fryer

Install 2ndDeep Fryer

CityRequiresElectrical

ImprovementsWhen would project have been completed if owner delays had not occurred?

0 0 0

© 2014 Husch Blackwell LLP. All rights reserved.

Page 86: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

COLLAPSED AS-BUILT ANALYSIS0 15

15

0 5 5 9 15 20 20 26 26 41 41 46 46 50 50 53

5 4 5

5 14 14 18 20 27 27 31 31 38 38 41 41 48 53 57

9 4

COLLAPSE OWNER DELAYS - RECALCULATE CRITICAL PATH

I30

3

I20

New Electrical Sub

14

6 15

1 2 6 10 18 22 26

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

Dining Area Carpet

5

20 24 284 8 12 16

Floor & Wall Tile In

Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

7 3 77 4

30

4

4 3

1

I10

2

I11

KitchenDrywall

Set, Hook-Up

& TestAll KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

Saw Cutting &

PipingFor 2nd

Deep Fryer

Install 2ndDeep Fryer

CityRequiresElectrical

ImprovementsWhen would project have been completed if owner delays had not occurred?0 0 0

Owner Delays Collapsed From Schedule - No Change In Completion Date - No Compensable Delays

Critical Path With Owner's Delays Collapsed Out

© 2014 Husch Blackwell LLP. All rights reserved.

Page 87: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

COLLAPSED AS-BUILT ANALYSIS

15

5 4 5

9 4

COLLAPSE CONTRACTOR DELAYS

1

I10

2

I11

4 3

30

47 3 77 4

Floor & Wall Tile In

Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

24 284 8 12 16 20

Dining Area Carpet

5

18 22 26

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

1 2 6 10

I30

3

I20

New Electrical Sub

14

6 15

KitchenDrywall

Set, Hook-Up

& TestAll KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

Sawcut Concrete

Slab - Install Gas

& Plumbing Patch Conc.

Saw Cutting &

PipingFor 2nd

Deep Fryer

Install 2ndDeep Fryer

CityRequiresElectrical

ImprovementsIf contractor delays had not occurred when would the project have finished?

3

5

0

© 2014 Husch Blackwell LLP. All rights reserved.

Page 88: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

COLLAPSED AS-BUILT ANALYSIS0 0

15

0 5 5 9 9 14 14 20 20 25 25 30 30 34 34 37

5 4 5

5 14 16 19 19 26 29 33 33 40 40 43 43 50 51 55

9 4

14 16 26 29 50 51

COLLAPSE CONTRACTOR DELAYS - RECALCULATE CRITICAL PATH

I30

3

I20

New Electrical Sub

14

6 15

1 2 6 10 18 22 26

NTP & Complete

Interior Demolition

Wall & Soffit Framing

Dining Area

Electrical Rough-In

Dining Area

Drywall In Dining Area

Painting Dining Area

Light Fixtures & Electrical

Terminations

Dining Area Décor &

Woodwork

Dining Area Carpet

5

20 24 284 8 12 16

Floor & Wall Tile In

Kitchen

Kitchen WallFraming

Kitchen Rough-In Electrical

7 3 77 4

30

4

4 3

1

I10

2

I11

KitchenDrywall

Set, Hook-Up

& TestAll KitchenEquipment

Laminate Panels InKitchen

Final Trimout -Project

Complete

SawcutConcrete

Slab - Install Gas

& Plumbing Patch Conc.

Saw Cutting &

PipingFor 2nd

Deep Fryer

Install 2ndDeep Fryer

CityRequiresElectrical

ImprovementsIf contractor delays had not occurred when would the project have finished?

3

5

0

Contractor Delays Collapsed From Schedule Completion Date 2 Days Earlier, Contractor Responsible for 2 Days of Delay

Critical Path With Contractor's Delays Collapsed Out

© 2014 Husch Blackwell LLP. All rights reserved.

Page 89: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

COLLAPSED AS-BUILT SCHEDULE ANALYSISRESTAURANT RENOVATION

QUACKENBUSH & ASSOCIATES, INC.

PROJECTED DAYSCOMPLETION OF

STEP DESCRIPTION DATE DELAY CONCURRENCY

1 As-Planned Schedule 50 0

2 As-Built Schedule 57 -7

3 Collapse Owner Delays 57 0

4 Collapse Contractor Delays 55 -2

5 Remainder of Delays Concurrent Between Owner & Contractor 55-50 -5

Summary of Delays:Owner Responsible 0Contractor Responsible 2Concurrent Responsible 5

© 2014 Husch Blackwell LLP. All rights reserved.

Page 90: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

Concurrency CriteriaTwo or More Delays in Same Time FrameBoth Delays Must be on Critical Path– Both Must Control the Project Completion

DateBut – For The Other Delay

Both Delays Must be Completely Independent

PhysicallyManagerially (No Pacing)

© 2014 Husch Blackwell LLP. All rights reserved.

Page 91: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONCURRENT DELAYSMEETING AT DENNY’S

SCENARIO #1Bill and Dan agree to have a business meeting at Denny’s the next morning at 7:00AM. Both Bill and Dan leave their home with enough time to arrive at Denny’s by 7:00 AM.Bill decides to stop at the dry cleaners on the way, which consumes 10 minutes.Dan has a flat tire and it takes him 15 minutes to change the tire.Bill arrives at Denny’s at 7:10 AM and is relieved to see that Dan has not yet arrived.Dan arrives at 7:15AM. Bill says “Boy, Dan you are 15 minutes late. I have been waiting here a long time. You really need to be more responsible.”

WHO DELAYED THIS BREAKFAST MEETING AND BY HOW MANY MINUTES?

Answer: Dan and Bill jointly delayed the meeting by 10 minutes, Dan delayed the meeting an additional 5 minutes. Reason: Both Bill and Dan were required at the meeting or it could not occur, thus they were both on the critical path, and both individuals acted independently. (Neither party knew the other was running late.) Thus a 10 minute Concurrent Delay. © 2014 Husch Blackwell LLP. All rights reserved.

Page 92: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

CONCURRENT DELAYSMEETING AT DENNY’S

SCENARIO #2Bill and Dan agree to have a business meeting at Denny’s the next morning at 7:00AM. Both Bill and Dan leave home with enough time to arrive at Denny’s by 7:00 AM.Bill has dry-cleaning to drop off but decides he better do that later so he can be on time to the meeting.Dan gets a flat tire and he immediately calls Bill on his cell phone to tell him he will be 15 minutes late. Bill decides he now has the time to drop the dry cleaning off and arrives at Denny’s at 7:10 AM. Dan arrives at 7:15 AM.

WHO DELAYED THIS BREAKFAST MEETING AND BY HOW MANY MINUTES?

Answer: Dan delayed the meeting by 15 minutes. Bill did not delay the meeting at all. No Concurrent Delay Reason: Both Bill and Dan were required at the meeting, thus they were both on the critical path, but both individuals did not act independently. (Bill modified his planned approach based on information provided by Dan.) THIS IS COMMONLY CALLED PACING. Bill adjusted his activities based on Dan’s delay.

© 2014 Husch Blackwell LLP. All rights reserved.

Page 93: Best Practices for Managing Construction Delay …...Delay – Impact on Project Participants For the contractor sAdjustments in time sAdjustment in costs For the owner sLoss of use

QUESTIONS?THANK YOUhuschblackwell.com

© 2014 Husch Blackwell LLP. All rights reserved.