Upload
akshat-mehrotra
View
407
Download
0
Embed Size (px)
Citation preview
Information Memorandum
Volume I
450 MW Thermal Power ProjectBajaj Energy Private Limited
(A Subsidiary of Bajaj Hindusthan
Limited)
Prepared By
SBI Capital Markets Limited
6th Floor, World Trade Tower Barakhamba Lane, New Delhi
110001
Draft Project Information Memorandum - BHL (5 x 90 MW)
Head Office: 202, Maker Tower ‘E’, Cuffe Parade, Mumbai
400 005
April 2010
Strictly Private & Confidential 2
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
IMPORTANT NOTICE
This Information Memorandum (“IM”) has been prepared for 450 MW (2 X 45 MW at 5 locations) Thermal Power Project (“the Project”) being set up by Bajaj Energy Private Limited (“BEPL” or ‘the Company”), a wholly owned subsidiary of Bajaj Hindusthan Limited (BHL), at Barkhera (district: Pilibhit), Khambarkhera (district: Lakhimpuri Kheri), Maqsudapur (district: Shajhanpur), Kundarkhi (district: Gonda), Utraula (district: Balrampur), of Uttar Pradesh. Its contents are strictly confidential and accordingly, this IM and its contents are circulated on the basis that they will be held in and with complete confidentiality. By accepting a copy of this IM, the recipient agrees to keep its contents and any other information, which is disclosed to such recipient, confidential and shall not divulge, distribute or disseminate any information contained herein, in part or in full, without the prior written approval of SBI Capital Markets Limited (“SBICAP”). The recipient also agrees to indemnify SBICAP against any claims that may arise as a result of a breach of any confidentiality arrangement, which governs the contents of this IM.
This IM has been prepared for the internal use of prospective lenders for 450 MW Thermal Power Project of BEPL and may contain proprietary and confidential information about the Project and the Sponsor. This IM has been prepared by SBICAP, inter alia, on the basis of the information and documents available in the public domain, data made available by the Sponsor and in-house databases available to SBICAP as a part of its professional practice & which SBICAP believes to be reliable. SBICAP has not carried out any independent verification for the accuracy or truthfulness of the same.
This IM constitutes an opinion expressed by SBICAP and each party concerned has to draw its own conclusions on making independent enquiries & verifications and SBICAP cannot be held liable for any financial loss incurred by anyone based on this IM. Further, on accepting a copy of this IM, the recipient accepts the terms of this Notice, which forms an integral part of this IM and the recipient shall be deemed to have agreed to indemnify SBICAP against any claims that may be raised against SBICAP as a result of or in connection with the data & opinions presented in this IM.
The delivery of this IM does not imply that the information in it is correct as of any time after the date set out on the cover page hereof, or that there has been no change in the operation, financial condition, prospects, creditworthiness, status or affairs of the subject or anyone else since that date. Further, capital costs and operating expenditures are subject to uncertainties concerning the effects that change in
Strictly Private & Confidential 1
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
legislation or economic or other circumstances may have on future events, and different people may have a different view in future. There will usually be differences between projected & actual results because events & circumstances do not occur as expected and those differences may be material. Under the circumstances, no assurance can be provided that the assumptions or data, upon which any projections have been based, are accurate or whether these financial projections will actually materialize.
Neither SBICAP, nor State Bank of India or any of its associates, nor any of their respective directors, employees or advisors make any expressed or implied representation or warranty and no responsibility or liability is accepted by any of them with respect to the accuracy, completeness or reasonableness of the facts, opinions, estimates, forecasts, projections, or other information set forth in this IM or the underlying assumptions on which they are based or the accuracy of any computer model used and nothing contained herein is, or shall be relied upon as a promise or representation regarding the historic or current position or performance of the Sponsor, or any future events or performance of the Sponsor.
This IM is divided into sections & sub-sections only for the purpose of reading convenience. Any partial reading of this IM may lead to inferences, which may be at divergence with the conclusions and opinions based on the entirety of this IM. Neither this IM, nor the information contained herein, may be reproduced or passed to any person or used for any purpose other than stated above.
Strictly Private & Confidential 2
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Contact Persons
SBI CAPITAL MARKETS
LIMITED
(A Subsidiary of State Bank of
India)
6th Floor, World Trade Tower,
Barakhambha Lane,
New Delhi 110 001
Tel. +91-11 2341 8460
Fax. +91-11 2341 7783
Website: www.sbicaps.com
Mr. Mukul ModiVice President, Project Advisory & Structured FinancePh. 011- 2341 8491Fax 011- 2341 6292Mob. +91-9811776510e-mail: [email protected]
Ms. Neha GoelManager,Project Advisory & Structured FinancePh. 011 – 2341 8460 (Extn: 413)Fax 011 – 2341 6292Mob. +91-9560397199e-mail: [email protected]
Mr. Lovkesh KapoorManager, Project Advisory & Structured FinancePh. 011- 2341 8460 (Extn: 409)Mob. 91-9560397202e-mail: [email protected]
Mr. Pulkit BhandariDeputy Manager, Project Advisory & Structured FinancePh. 011- 2341 8460 (Extn: 403)
Strictly Private & Confidential 3
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Mob. 91-9818678668e-mail: [email protected]
Table of Contents
1 Introduction....................................................................................10
2 The Company.................................................................13
2.1 General Particulars – The Company.........................................13
2.2 Background of the Company...................................................13
2.3 Key Management Personnel....................................................14
2.4 Capital Structure – BEPL..........................................................14
2.5 Board of Directors - BEPL.........................................................15
2.6 Historical Financial Performance of BEPL.................................16
2.7 Promoter Company – BHL........................................................17
3 Project Details................................................................27
3.1 Location of the Project.............................................................27
3.2 Key Project Inputs....................................................................28
3.3 Primary Fuel Requirement and Availability..............................29
3.4 Evacuation of Power................................................................31
4 Implementation Framework............................................33
4.1 Project Implementation Framework.........................................33
4.2 State Support - MoU with Government of Uttar Pradesh.........33
4.3 Technical Arrangements..........................................................34
4.4 Operation & Maintenance Arrangement..................................42
Strictly Private & Confidential 4
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
4.5 Power Sale Arrangements.......................................................42
4.6 Power Evacuation Arrangement..............................................46
4.7 Schedule of Implementation....................................................46
5 Industry Scenario...........................................................48
5.1 Power Sector Scenario in India: A Perspective.........................48
5.2 Region wise Demand Supply Scenario.....................................52
5.3 Analysis of Present Capacity....................................................53
5.4 Capacity Addition Program......................................................55
5.5 Power Trading Scenario...........................................................58
5.6 Regulatory Scenario................................................................60
5.7 Conclusion...............................................................................61
6 Project Cost and Means of Financing...............................63
6.1 Components of Project Cost....................................................63
6.2 Means of Financing..................................................................67
7 Financial Projections – Snapshot.....................................68
7.1 Project Financials.....................................................................68
7.2 Sensitivity Analysis..................................................................69
8 Status of Approvals and Clearances................................71
9 Risk Analysis..................................................................74
9.1 Risk Analysis – Allocation & Mitigation.....................................74
10 Conclusion...................................................................80
11 Indicative Term Sheet..................................................82
11.1 Indicative Terms and Conditions – Rupee Term Loan..............82
12 Annexure...................................................................103
12.1 Annexure I: Historical Financials of BHL................................103
12.2 Annexure II: Detailed Banking Arrangement of BHL..............105
12.3 Annexure III: Project Implementation Schedule.....................108
12.4 Annexure IV: Key Assumptions..............................................109
12.5 Annexure V: Award of Coal Linkage for the Project...............112
12.6 Annexure VI: Brief profile of Contractors...............................113
12.7 Annexure VII: Projected Financials of Project.........................119
Strictly Private & Confidential 5
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Strictly Private & Confidential 6
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
List of Tables
Table 1: Particulars of BEPL..................................................................13
Table 2: Key Management Personnel...................................................14
Table 3: Capital Structure of BEPL........................................................14
Table 4: Share Holding pattern of BEPL................................................15
Table 5: Board of Directors of BEPL......................................................15
Table 6: Snapshot of Balance Sheet of BEPL........................................16
Table 7: Particulars of BHL...................................................................17
Table 8: Location of existing cogeneration power plants.....................18
Table 9: Board of Directors of BHL.......................................................20
Table 10: Capital Structure of BHL.......................................................22
Table 11: Share Holding pattern of BHL...............................................22
Table 12: Snapshot of Profit & Loss account of BHL.............................23
Table 13: Snapshot of Balance Sheet of BHL.......................................23
Table 14: Credit Rating........................................................................25
Table 15: Snapshot of Debt Arrangement of BHL.................................25
Table 16: Details of Accessibility of sites.............................................27
Table 17: Break-up of land requirement..............................................28
Table 18: Coal Requirement Estimation...............................................29
Table 19: Transportation details of Coal...............................................30
Table 20: Estimation of cost of coal for the project..............................30
Table 21: UPPCL Sub-stations...............................................................31
Table 22: Key personnel of BIDCO.......................................................35
Table 23: Details of BTG contracts.......................................................37
Table 24: Key features of contracts for Boiler and Auxiliaries..............37
Table 25: Key features of contracts for Steam Turbine and Generator 40
Table 26: Schedule of Implementation.................................................46
Table 27: Year Wise Power Demand Supply Scenario..........................50
Table 28: Power Deficit vs Highest Power Consumption in India..........51
Table 29: AT&C losses..........................................................................51
Strictly Private & Confidential 7
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Table 30: Region Wise Demand-Supply Scenario.................................52
Table 31: Demand Supply Scenario in Northern Region States...........52
Table 32: Projected Power Requirement in Northern Region...............53
Table 33: Ownership Mix of the Installed Generation Capacity............54
Table 34 : Capacity Additions Required in Uttar Pradesh.....................57
Table 35: Power Trading Entities and Respective Market Shares in
2007-08................................................................................................59
Table 36: Estimation of Cost of Project................................................63
Table 37: Components of Financing.....................................................67
Table 38: Snapshot of financial parameters of the Project...................68
Table 39: Sensitivity Analysis...............................................................69
Table 40: Status of Approvals and Clearances....................................71
Table 41: Risk Analysis.........................................................................74
List of Figures
Figure 1: Holding Structure of BEPL.....................................................13
Figure 2: Family Tree of Bajaj Group....................................................19
Figure 3: Location Map.........................................................................27
Figure 4: Project Structure...................................................................33
Figure 5: Installed Generation Capacity...............................................48
Figure 6: Per Capita Consumption........................................................49
Figure 7: Growth in Private Participation in Power Sector....................54
Figure 8: Installed Capacity by Type of Fuel........................................55
Figure 9: Long Term Capacity Addition Projections..............................55
Figure 10: Plan Wise Capacity Additions..............................................57
Figure 11: Historical Trend of Merchant Power Transaction.................58
Figure 12: Price Analysis of Traded Power...........................................60
List of Abbreviations
Strictly Private & Confidential 8
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Abbreviations
Descriptions
AAI Airport Authority Of IndiaAOA Articles Of AssociationAT&C Aggregate Technical and Commercial BEPL Bajaj Energy Private LimitedBHL Bajaj Hindusthan LimitedBHSIL Bajaj Hindusthan Sugar & Industries LimitedBIDCO Bajaj Infrastructure Development Company
LimitedBOD Board Of DirectorsCEA Central Electricity AuthorityCERC Central Electricity Regulatory CommissionCOD Commercial Operation DateCTU Central Transmission UtilityDPR Detailed Project ReportEA03 Electricity Act 2003EPC Engineering, Procurement And ConstructionEPS Electric Power SurveyFM Force MajeureFSA Fuel Supply AgreementGCV Gross Calorific ValueGOI Government Of IndiaGoM Group of MinistersGoUP Government of Uttar PradeshGW Giga WattHFO Heavy Fuel OilIDC Interest During ConstructionIPP Independent Power ProducerKV Kilo VoltKWh Kilowatt HourLD Liquidated DamagesLDO Light Diesel OilLOI Letter Of IntentMDO Mine, Develop, OperateMLD Million Liters Per DayMOA Memorandum Of AssociationMoEF Ministry Of Environment And ForestMoU Memorandum Of Understanding
Strictly Private & Confidential 9
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Abbreviations
Descriptions
MT Million TonneMTPA Million Tonne Per AnnumMU Million UnitsMW Mega WattNTP Notice To ProceedO&M Operation And MaintenancePDC Pre-Disbursement ConditionPLF Plant Load FactorPNB Punjab National BankPPA Power Purchase AgreementPTC Ptc India LimitedSG Steam GeneratorSTG Steam Turbine GeneratorTCD Tonnes Crushed Per DayTG Turbine GeneratorUPERC Uttar Pradesh Electricity Regulatory CommissionUPPCL Uttar Pradesh Power Corporation Limited
Strictly Private & Confidential 10
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
1 Introduction
Bajaj Energy Private Limited (BEPL) is promoted by Bajaj Hindusthan
Limited (BHL), the flagship company of Shishir Bajaj Group. BEPL
proposes to set up 450 MW (2 x 45 MW at 5 locations) coal fired
Thermal Power Project under the current proposal.
The promoter company, BHL is India’s leading sugar and ethanol
manufacturing company, headquartered at Mumbai. BHL has fourteen
sugar units spread across the north Indian state of Uttar Pradesh (UP)
with ten units functioning under it and balance four units operating
under its subsidiary, Bajaj Hindusthan Sugar and Industries Limited
(BHSIL). The aggregate crushing capacity of BHL is 136,000 tonnes
crushed per day (tcd) including capacity of BHSIL of 40,000 tcd.
BHL is the pioneer of India’s fuel ethanol programme, being the largest
ethanol producer in the country. It produced 52 million litres of
industrial alcohol (ethanol being the major contributor) during FY 2008-
09. It also has a distillery capacity to produce 800,000 litres of alcohol
per day.
BHL has also set up small co-generation power units (8-40 MW) at its
existing sugar units. The total generation capacity of the plants is
around 428 MW.
Under the current proposal, BEPL is setting up 450 MW coal fired power
plant in the premises of five (5) of existing sugar units of BHL and
BHSIL at Barkhera (district: Pilibhit), Khambarkhera (district:
Lakhimpuri Kheri), Maqsudapur (district: Shajhanpur), Kundarkhi
(district: Gonda), Utraula (district: Balrampur), of Uttar Pradesh.
Strictly Private & Confidential 11
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
The project is expected to be commissioned by November 1st 2011 and
is one of the few projects to be commissioned under 11th Five Year
Plan. The land for the project is already available and site development
and civil works are already being carried out. The contracts for BTG
and civil works have already been placed with reputed suppliers. BHL
has already incurred expenditure around Rs. 438 crores on the Project.
Moreover, BHL has vast experience in implementing projects and has
commissioned 1,06,000 tcd of green field sugar units across Uttar
Pradesh.
Initially the Project was envisaged to be implemented by BHL and
accordingly the process of obtaining statutory and other clearances
and award of major project contracts was initiated by BHL. However,
subsequently BHL decided to implement the Project through a special
purpose vehicle viz Bajaj Energy Private Limited, which is presently its
wholly owned subsidiary.
On December 24, 2009, BHL awarded a Project Co-ordination,
Management Consultancy and Implementation Support contract to
Bajaj Infrastructure Development Company Limited (BIDCO). As per the
Letter of Award (LoA), BIDCO shall be responsible for overall
implementation of the Project including award of major project
contracts, project management and construction supervision etc.
BIDCO has placed major orders including Boiler and Auxiliaries to
ThyssenKrupp Industries India and Thermax Limited and Turbine &
Generator package to Siemens Limited. BIDCO has also awarded Civil
Works packages to ERA Building Systems Limited, K.K Construction
Builders Limited and Petron Civil Engineering Private Limited.
An MoU was executed on 14th January, 2010 between Government of
Strictly Private & Confidential 12
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Uttar Pradesh (GoUP) and BHL for setting up the project in the state of
Uttar Pradesh. GoUP has assured its help in expediting various
statutory approvals/clearances for the Project.
An MoU was signed between Uttar Pradesh Power Corporation Limited
(UPPCL) and BHL on 31st December, 2009 for sale of power from the
Project. As per the MoU, UPPCL will procure at least 50% of the net
power generated from the Project. Subsequently, UPPCL and BHL have
initialled the Draft Power Purchase Agreement (PPA) for sale of 90% of
net power generated from the Project. The final PPA is expected to be
signed soon. The tariff under the PPA shall be calculated as per the
Uttar Pradesh Electricity Regulatory Commission (UPERC) tariff
determination guidelines. Balance 10% power from the Project is
proposed to be sold on merchant basis.
The Project is proposed to commence commercial operations in 22
months from the date of issuance of Letter of Award to BIDCO, i.e. by
November 01, 2011.
Estimated cost of the Project is Rs. 2,320 Crores and is proposed to be
funded at a Debt: Equity ratio of 75:25. The proposed financing mix
entails Debt of Rs. 1740 Crores and Equity of Rs. 580 Crores. The
entire equity requirement for the Project would be contributed by
BHL/Promoter Group.
In order to facilitate its debt raising efforts, BHL has appointed SBI
Capital Markets Limited (“SBICAP”) to prepare the Information
Memorandum for the Project and approach Commercial Banks and
Financial Institutions on its behalf to arrange funds.
Strictly Private & Confidential 13
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
2 The Company
2.1 General Particulars – The Company
Table 1: Particulars of BEPL
Name : Bajaj Energy Private Limited (BEPL)Incorporation Date : 27th June, 2008Sector : Power GenerationCorporate Office : Bajaj Bhawan, Jamnalal Bajaj Marg, B-10,
Sector-3, Noida-201301, Uttar Pradesh Registered Office : Bajaj Bhawan, Jamnalal Bajaj Marg, 226,
Nariman Point, Mumbai-400021
2.2 Background of the Company
The Company was incorporated on 27th June, 2008 as Bajaj Eco-Chem
Products Private Limited. Subsequently, on 19th March, 2010 the name
of the Company was changed to Bajaj Energy Private Limited (BEPL).
Fresh certificate of incorporation has been received from Registrar of
Companies (Enclosed in Volume II of this IM).
The Company is promoted by Bajaj Hindusthan Limited (BHL), the
flagship company of Shishir Bajaj Group. The Company is a wholly
owned subsidiary of BHL. Pictorial presentation of the Group holding
structure is as under:
Figure 1: Holding Structure of BEPL
Strictly Private & Confidential 14
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
2.3 Key Management Personnel
BEPL is establishing a team of qualified and experienced personnel for
implementation and subsequent operation of the Project. Brief details
of the key management personnel for the Project are given below.
Table 2: Key Management Personnel
Name DesignationEducational Qualification
Experience
(years)Dr. Sanjeev Kumar Director (Legal &
Corporate Affairs)M.Com, LL.B,
30
Mr. N. K. Balasubramanian
Advisor (Power) BE (Mech.), 48
Mr. D.L. Narasimham Advisor (Power)BE (Mech.), PGDM (International Marketing)
41
Mr. Manoj Maheshwari Chief Financial Officer B.Com (H), FCA, FCS 23
Mr. Sachin Sharma Executive President PGDM8
Mr. Vivek Srivastava Vice President - Group HR
MSW, BA21
Mr. Birendra Kr. Agarwal
Vice President (Corporate Commercial)
B.Com.(H), MBA, Lead Auditor
26
Mr. Ajay Vikram Singh Vice President (EHS)
M.Sc., PG Diploma(Industrial Safety & Environment)
25
Mr. N. K .Kashyap Vice President (Indirect Taxation)
B.Com., Diploma (Excise & Custom)
29
Mr. Subodh Kumar Garg
General Manager (Finance & Accounts)
B.Com, C.A.24
2.4 Capital Structure – BEPL
The capital structure of BEPL as on 31st March, 2010 is as under –
Table 3: Capital Structure of BEPL
Particulars Rs. CroreAuthorized Share Capital30,00,000 Equity shares of Rs. 10/- each
3.00
Issued, Subscribed and Paid-up 0.81
Strictly Private & Confidential 15
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Particulars Rs. CroreCapital of 8,10,000 Equity shares of Rs. 10/- each
The shareholding pattern of BEPL as on 31st March, 2010 is as under:
Table 4: Share Holding pattern of BEPLCategory of Shareholder Total
number of shares
Percentage)
(A) Promoter and Promoter GroupIndian – Bajaj Hindusthan Limited
100.00
Total 100.00
Currently, the entire shareholding of BEPL is being held by BHL. The
Company proposes to expand its capital base shortly. It is expected
that BHL and Promoter Group would subscribe to entire shareholding of
BEPL initially. The exact shareholding/equity contribution pattern of
BEPL is expected to be finalised in next 2-3 months (finalization of
exact shareholding pattern is stipulated as a Pre-commitment
Condition). During the currency of the loan, BHL and Promoter Group
would maintain a minimum equity shareholding of 51% with BHL
holding a minimum of 26% stake (maintenance of aforesaid interests in
BEPL stipulated as a Negative Covenant).
2.5 Board of Directors - BEPL
Presently, BEPL is managed by a Board of Directors comprising of two
(2) directors. The Company proposes to suitably broad-base and
strengthen its Board of Directors shortly. Present composition of the
Board of Directors is as shown below:
Table 5: Board of Directors of BEPLName of the Director Designation
1. Mr. Pradeep Parakh Director2. Mr. Chandresh Chhaya Director
Strictly Private & Confidential 16
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
A brief profile of the directors of the Company is given below:
Mr. Pradeep Parakh, has been on Board of BEPL since its inception.
He joined BHL in March 2001 and is presently designated as its
President and Company Secretary. He holds a B. Com (Honours)
degree and is a Chartered Accountant and Company Secretary by
qualification. He has over 21 years of experience with strengths in
areas of Corporate Law, Corporate Governance and Finance.
Mr Chandresh Chhaya, is currently on the Board of BEPL as one of its
directors. He is employed with BHSIL as Manager and Company
Secretary. He is a graduate in Commerce and Law and is a fellow
member of The Institute of Company Secretaries of India as well as The
Institute of Cost and Works Accountants of India. He has over 20 years
of experience in areas of Corporate Law and Secretarial Practice.
The Company has confirmed that the name of none of the directors
appears in defaulters list of RBI, CIBIL defaulters list and ECGC SAL.
The letter certifying the same is enclosed in Volume II of this IM.
2.6 Historical Financial Performance of BEPL
A brief summary of Balance Sheet of the Company (Financial Year
ending March 31) is given below:
Table 6: Snapshot of Balance Sheet of BEPLRs. lakh
FY Ending March 31,2009 As on
December, 2009
Net Fixed Assets - - Capital work in progress 62.58 72.72 Investments - - Current assets 15.12 4.87
Strictly Private & Confidential 17
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
FY Ending March 31,2009 As on
December, 2009
Total Assets 77.7 77.59 Equity share capital 81.00 81.00 Reserves and surplus - -Current liabilities and provisions
0.11 -
Less: Miscellaneous Expenses 3.41 3.41 Total Liabilities and Provisions
77.7 77.59
There have been no major business operations in BEPL since its
incorporation and the Company now proposes to focus mainly on its
power operations.
2.7 Promoter Company – BHL
2.7.1General Particulars
Table 7: Particulars of BHLName : Bajaj Hindusthan Limited (BHL)Incorporation Date : 23rd November, 1931Sector : Sugar ManufacturingRegistered Office : Bajaj Bhawan, Jamnalal Bajaj Marg, 226,
Nariman Point, Mumbai-400021Existing Operations : 10 sugar units with capacity of 96,000
tcd under BHL and 4 sugar units with capacity of 40,000 tcd under its subsidiary BHSIL;
428 MW bagasse based co-generation power plant is in operation.
BHL, promoter of BEPL, was incorporated on 23rd November, 1931 as
Hindusthan Sugar Mills Limited. BHL was founded by Late Shri Jamnalal
Bajaj.
BHL started its operations by setting up its first sugar unit at
Golagokarannath, district Lakhimpur Kheri of Uttar Pradesh. In 1967, a
new company - Sharda Sugar & Industries Limited - was established as
Strictly Private & Confidential 18
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
a subsidiary of Hindusthan Sugar Mills Limited. Under this new
subsidiary, a sugar plant with a cane crushing capacity of 1400 tcd was
set up in 1972 at Palia Kalan about 70 kilometers from
Golagokarannath. The capacity was subsequently increased in stages
to reach 11,000 tcd. In 1988, Hindusthan Sugar Mills Limited was
renamed as Bajaj Hindusthan Limited and shortly thereafter in 1990,
Sharda Sugar & Industries Limited was amalgamated with Bajaj
Hindusthan Limited. BHL embarked on an aggressive Greenfield
expansion drive in 2003-2007, starting with a plant at Kinauni, near
Meerut (UP), which was completed in a record time of seven months.
The facility commenced commercial production in November 2004.
In December 2005, BHL acquired Pratappur Sugar and Industries
Limited (PSIL), district Deoria, Eastern UP. PSIL was subsequently
renamed Bajaj Hindusthan Sugar and Industries Limited (BHSIL). This
acquisition provided BHL a strategic foothold in the sugar-deficient
region of Eastern UP.
BHSIL embarked upon significant expansions and set up three new
sugar units were Eastern UP at Rudauli (district Basti), Kundarkhi
(district Gonda) and Utraula (district Balrampur). BHSIL now has a
crushing capacity of 40,000 tcd and a distillery with the capacity to
manufacture 160 kilo-liter (KL) per day of ethanol. The total industrial
alcohol/ ethanol capacity of the company, including its subsidiary, is
800 KL/ day.
BHL also generates around 428 MW of power from the co-generation
plant. After meeting its own energy needs, BHL has a surplus of over
90 MW. It has already begun to supply a significant part of this surplus
power to the UP state grid. The details are as follows:
Table 8: Location of existing cogeneration power plants
Strictly Private & Confidential 19
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Units LocationPower MW)
Unit in BHL Golagokarannath Lakhimpur 30 Palia Kalan Lakhimpur 40 Khambarkhera Lakhimpur 35 Barkhera Pilibhit 35 Maqsoodapur Shahjahanpur 30 Kinauni Meerut 35 Bilai Bijnore 35 Thanabhawan Muzaffarnagar 35 Budhana Muzaffarnagar 40 Gangnauli Saharanpur 25
Total in BHL 340Unit in BHSIL Pratappur Deoria 8 Kunderki Gonda 43 Utraula Balrampur 21 Rudauli Basti 46
Total in BHSIL 88Total Group Capacity 428
2.7.2Promoter Profile of BHL
BHL belongs to Shishir Bajaj Group which is part of “Bajaj Group”. Bajaj
Group of companies was founded by Late Shri Jamnalal Bajaj in the
1930s. The group now has 24 companies, including 6 listed companies.
The family tree of the Bajaj Group is as follows:
Figure 2: Family Tree of Bajaj Group
Strictly Private & Confidential 20
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Mr. Shishir Bajaj, 62, is the Chairman and Managing Director of BHL
for over twenty (20) years. Mr Bajaj holds an MBA degree from New
York University in finance. He joined BHL in 1974 and has been
responsible for overall management of the company since then. He is
the Managing Director of the company since July 1988.
2.7.3Board of Directors
BHL is managed by a Board of Directors comprising eight directors.
Composition of the Board of Directors is as shown below:
Table 9: Board of Directors of BHLName of the Director Designation
1 Mr. Shishir Bajaj Chairman & Managing Director
2 Mr. Kushagra Bajaj Vice Chairman3 Mr. D S Mehta Director4 Mr. M.L. Apte Director5 Mr. Ravindrakumar V. Ruia Director6 Mr. Dinesh Kumar Shukla Director7 Mr. Alok Krishna Agarwal Director8 Dr. Sanjeev Kumar Whole Time Director
As mentioned earlier, Mr. Shishir Bajaj serves as the Chairman and
Managing Director on the Board of BHL. A brief profile of other
directors of the company is given below:
Mr. Kushagra Bajaj, is the Vice Chairman of BHL. He joined
BHL in 2001 as Chief Executive and was inducted on its board in
April, 2007. He has a Bachelor of Science degree in Economics,
Political Philosophy and Finance from Carnegie Mellon,
Pittsburgh, USA and has a master degree in Marketing from
North-western University, Chicago, USA. He is responsible for
overall operations of the company.
Mr. D S Mehta has been on the Board of BHL since January
Strictly Private & Confidential 21
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
1986. He also holds directorship in various other Bajaj group
companies. He graduated with an honours degree in commerce
from Mumbai University and he is an alumnus of Sydenham
College. He is a fellow member of the Institute of Chartered
Accountants of India and the Institute of Company Secretaries of
India. He has been associated with the Bajaj Group of companies
since 1966 and has more than 30 years experience in corporate
law, taxation, finance and investment.
Mr. M.L. Apte, is associated with BHL as director for over 33
years. He has held various prestigious positions including Sheriff
of Mumbai; he was also a former President of Maharashtra
Chamber of Commerce, Bombay Chamber of Commerce, Cricket
Club of India, Indian Sugar Mills Association, Member of the
Indian Cotton Mills Federation and Chairman of the Textiles
Committee.
Mr. Ravindrakumar V Ruia, joined the Board of BHL in April
2001. He is the Executive Director of the Dawn Mills Company
Limited. He is also a Director of Special Paints Ltd. and Special
Paints (Karnataka) Ltd. apart from various other Ruia group
companies. He is also Committee Member of The Bombay Mill
owners' Association, Indian Cotton Mills Federation and Bombay
Textile Research Association and is associated with various
public charity trusts as Trustee.
Mr. Dinesh Kumar Shukla, has been associated with BHL as
nominee of LIC since October, 2001 and also as a member of the
Audit Committee. He is a B. A. and Masters of Social Work
(M.S.W). He retired as an Executive Director (Personnel) in
February, 2003 from Life Insurance Corporation of India (LIC).
Strictly Private & Confidential 22
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
During his tenure with LIC, he occupied positions like Regional
Manager – Marketing, Group Pension and Superannuation
Schemes of LIC at Kolkata (Eastern Zone) as well as in-charge of
3 LIC divisions viz. Raipur, Jabalpur and Bhopal.
Mr. Alok Krishna Agarwal, joined the Board of BHL in April,
2007. He is the founder managing partner of Juris Consultus, New
Delhi. In 1988 he was admitted to Bar Council in India. He is also
an associate member of Bar Council of Delhi, Supreme Court Bar
Association, International Bar Association, Indo American
Chamber of Commerce & FICCI.
Dr. Sanjeev Kumar, is presently working as Group President
(Corporate & Legal Affairs) of BHL with experience of more than
20 years. He was appointed as a Whole Time Director from 12
March, 2009. He has degrees in Masters of Commerce,
Doctorate, LL.B, Diploma in Intellectual Property Rights Laws,
Cost Accountant and Company Secretary.
BHL has confirmed that the name of none of the directors appears in
defaulters list of RBI, CIBIL defaulters list and ECGC SAL. The letter
certifying the same is enclosed in Volume II of this IM.
2.7.4Capital Structure- BHL
The capital structure of BHL as on 31st December 2009 is as under –
Table 10: Capital Structure of BHLParticulars Rs. CroreAuthorized Share Capital80,00,00,000 Equity shares of Rs. 1/- each
80.00
Issued, Subscribed and Paid-up Capital of 17,68,57,111 Equity shares of Rs. 1/- each
17.68
Strictly Private & Confidential 23
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
The shareholding pattern of BHL as on 31st December 2009 was as
under:
Table 11: Share Holding pattern of BHLCategory of Shareholder Total
number of shares
As a percentage of
(A+B+C)(A) Promoter and Promoter
GroupIndian 65561186 37.07
(B) Public Holding1 Institutions
Mutual Funds/ UTI 15161871 8.57 Financial Institutions/ Banks 1224034 0.69 Central Government/ State Government(s)
1500 0.00
Insurance Companies 9696465 5.48 Foreign Institutional Investors 41285678 23.34 Sub-Total (B)(1) 67369548 38.09
2 Non-institutions Bodies Corporate 17080800 9.66 Individuals 22362803 12.64Others 2882174 1.63Sub-Total (B)(2) 42325777 23.93 Total Public Shareholding (B)= (B)(1)+(B)(2)
109695325 62.02
Total (A)+(B) 175256511 99.09
(C) Shares held by Custodians and against which Depository Receipts have been issued
1600600 0.91
Grand Total (A)+(B)+(C) 176857111 100.00
2.7.5Historical Financial Performance of BHL
A brief summary of Profit & Loss account and Balance Sheet of the
company for the past four years (BHL follows accounting year ending
September 30) is given below:
Strictly Private & Confidential 24
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Table 12: Snapshot of Profit & Loss account of BHLRs crore
FY Ending September 30,
2006 2007 2008 2009
Net Sales 1,447
.24 1,713.0
11,756.2
8 1,583.7
4 PBDIT 350.42 248.46 218.54 595.29 PBT 280.17 37.89 (108.13) 206.00
PAT190.83 45.
70 (47.69)
156.23
Depreciation 72.39 146.88 187.22 202.21
Cash Profit347.85
183.49 77.
71 407.5
5 PBDIT / Net Sales (%) 24% 15% 12% 38%
Table 13: Snapshot of Balance Sheet of BHLRs. Crore
FY Ending September 30, 2006 2007 2008 2009
Net Fixed Assets 1,013.48 2,220.6
4 2,478.8
3 2,632.
50 Capital work in progress 1,223.08 562.97 138.69 131.28 Investments 205.81 437.47 488.26 549.11
Current assets 941.83 2,109.0
5 2,525.4
7 3,034.
42
Total Assets 3,384.2
15,330.
13 5,631.
25 6,347.
30 Equity share capital 14.14 14.14 14.14 36.59
Reserves and surplus1,354.53 1,420.1
91330.9
672257.0
78Current liabilities and provisions 475.45
1,868.87
1,676.67
1,409.96
Secured loans 344.2
1 1,051.
04 1,949.
54 1,417.
22
Unsecured loans 1,065.92
855.01 600.99 1118.4
2 Deferred tax liabilities 129.96 120.88 58.94 108.04 Total Liabilities and Provisions
3,384.21
5,330.13
5,631.25
6,347.31
Net worth 1,498.
63 1,555.
21 1,404.
04 2,401.
70 Current Ratio 1.98 2.39 3.09 3.49Debt Equity Ratio 1.03 2.02 2.53 1.34TOL/TNW 1.26 2.43 3.01 1.64
Strictly Private & Confidential 25
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
For FY 2008-09, BHL reported sales of around Rs 1,584 crore and
PAT of Rs 156.23 crore. BHL incurred operational losses in FY
2007-08 mainly due to higher sugarcane prices and excess
production of sugar. Due to excess supply of sugar globally, the
sugar prices declined but the raw material cost i.e. sugar cane
prices remained high which resulted in aforesaid losses.
Net Fixed Assets of BHL have more than doubled from Rs 1,013
crore in FY 2005-06 to Rs 2,632 crore in FY 2008-09 mainly on
account of expansion in sugar crushing capacity.
Net worth of the company has also grown at a CAGR of around
18% from FY 2005-06 to FY 2008-09.
TOL/ TNW of BHL has reduced from 3.01 in FY 2007-08 to 1.64 in
FY 2008-09 mainly on account of repayment of secured loans
from the receipts of Qualified Institutional Placement of equity of
around Rs. 720 crore. In addition, debt-equity ratio of the
company has also improved to 1.34 in FY 2008-09 against 2.53 in
FY 2007-08.
Detailed historical financials of BHL are given in Annexure I .
2.7.6Stock Market Performance
The shares of BHL are listed on BSE and NSE. The stock was quoted at
Rs. 136.101 on BSE with its 52-week high and low of Rs. 242 and Rs. 39
respectively.
2.7.7Credit Rating
Fitch Rating has affirmed the following ratings of the various bank lines
of BHL.
Table 14: Credit Rating
1 As on April 16, 2010
Strictly Private & Confidential 26
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Particulars Rating Date of award of
Rating
National Long Term Rating
A+(ind) August 27, 2009
Cash Credit/ Fund Based Limits (Rs 14,500 mn)
A+(ind) August 27, 2009
Short Term Non-Fund based limits (Rs 3,500 mn)
F1 (ind) August 27, 2009
2.7.8Present Arrangement with Banks/Financial Institutions
The snapshot of debt availed by BHL as on December 31, 2009 is as
given below.
Table 15: Snapshot of Debt Arrangement of BHL Rs. crore
S. No.
Type of Loan SanctionedOutstanding
Secured Loan1. Non Convertible Debentures 15.00 15.00
2. Term Loans 953.83 690.64
3. Corporate Loans 1,620.00 1,460.014. Working Capital Loans 1,555.00 514.525. Other Loans 123.77 70.04
Sub Total 4,267.59 2,750.21Unsecured Loan
6. Public Deposits 0.08 0.087. Short Term Loan 100 1008. Mutual Funds 550.00 400.009. FCCB 549.22 464.80
Sub Total 1,199.30 964.88Total 5,466.89 3,715.09
The detailed arrangement of debt availed by BHL as on December 31,
2009 is provided in Annexure II.
Strictly Private & Confidential 27
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
3 Project Details
3.1 Location of the Project
The Project would be located in the premises of five (5) existing sugar
units of BHL and BHSIL, located at Barkhera (district: Pilibhit),
Khambarkhera (district: Lakhimpuri Kheri), Maqsudapur (district:
Shajhanpur)`, Kundarkhi (district: Gonda), Utraula (district: Balrampur)
of Uttar Pradesh. All the sites are accessible by road and rail network.
Location map and accessibility details are given below:
Figure 3: Location Map
Table 16: Details of Accessibility of sites
Name of the Unit
Name of the nearest Railway Station
Distance from Plant (kms.)
Connectivity by Road
Barkhera Shahjahanpur 70 YesMaqsoodapur Shahjahanpur 65 YesKhambarkhera Sitapur 60 YesKundarkhi Gonda 20 YesUtraula Gonda 50 Yes
Strictly Private & Confidential 28
Project
Locations
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
3.2 Key Project Inputs
3.2.1Land
Total land requirement for the Project at all sites is around 104 acres.
Entire land requirement shall be met from the surplus land available
within the premises of existing sugar units of BHL and BHSIL. The
break up of the land requirement at difference sites is as under:
Table 17: Break-up of land requirementin acres
S. No.
Plant Sites
Power Plant Land
Ash Pond Land
Total Land Requireme
nt
1Khambarkhera
16 4 20
2 Barkhera 20 4 243 Utraula 16 4 204 Kundarkhi 16 4 205 Maqsoodapur 16 4 20
BHL and BHSIL have initiated the process of transferring required
project land to BEPL. The transfer of land shall be at the notified circle
rate of land for industrial use.
3.2.2Water
Total consumptive water requirement for the Project is estimated to be
about 34920 m³/day (6984 m³ per day per site). Entire water
requirement is proposed to be met through extraction of Ground water.
Water is proposed to be drawn through 2 bore-wells at each project
site. Final approval to draw the requisite quantity of water from all the
five sites has been obtained from Central Ground Water Authority, GoI
vide their letters dated January 27, 2010 and February 4, 2010
(Enclosed in Volume II of this IM).
Strictly Private & Confidential 29
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
3.2.3Construction Power
Apart from availability of co-gen plants at each site, project sites
receive power from the existing UPPCL sub-stations. As per the various
contracts awarded by BIDCO, construction power would be arranged by
the respective contractors. Contractors may also use their own DG sets
before supply of power commences from UPPCL sub-stations to support
the project construction activities.
3.3 Primary Fuel Requirement and Availability
3.3.1Coal Requirement
The Project will use domestic coal as primary fuel for power
generation. Annual primary fuel requirement works out to about 2.34
MTPA based on following parameters:
Table 18: Coal Requirement EstimationS.
No.Parameter Value Basis
1Gross Station Heat Rate (GSHR)
2675 kcal/kwh
As per the back-to-back BTG contracts awarded by BIDCO
2Gross Calorific Value (GCV)
3865 kcal/kg
Grade ‘F’ Coal
3Plant Load Factor (PLF)
85%As per prevalent operating norms in the Industry
Aggregate primary fuel requirement over an operating life of 25 years
works out to about 58.19 MT of coal.
3.3.2Coal Source & Availability:
Coal Linkage: BHL had requested Ministry of Coal (MoC) for grant of
long term coal linkage from Northern Coalfields Limited (NCL) (NCL
mines being the stated preference in the request letter) vide letter
dated 19th October, 2009 (application copy enclosed in Volume II of this
Strictly Private & Confidential 30
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
IM). Standing Linkage Committee (Long-term) [SLC (LT)] met on 8th
April, 2010 to discuss the award of coal linkage to various power
projects including the Project. As informed by BHL, it has been
awarded long-term coal linkage by MoC in the aforesaid meeting (letter
from company confirming the same is presented at Annexure V of this
IM). For the purpose of financial projections, Grade F coal from
Northern Coal Fields Limited (NCL) mines near Singrauli, Madhya
Pradesh is assumed.
3.3.3Coal Transportation
For supply of domestic coal from NCL mines, under long term coal
linkage, coal would be transported through the Indian Railways rail
network to the nearest railway stations of the proposed sites of the
units. About 600 km Indian Railways network would be used to transfer
coal to two of the Project sites and around 800-900 km would be used
for the remaining Project sites and thereafter the coal would be
transported through road. The transportation details of coal are as
follows:
Table 19: Transportation details of Coal
S.No
Plant SiteNearest railway siding
Distance from CIL/
NCL Mines (in km)
Distance from Railway siding to
Plant (Km)
1 Kundarki Gonda 618 202 Utraula Gonda 618 50
3Khamberkhera Sitapur 817 60
4 MaqsudapurShahjahanpur 896 65
5 BarkheraShahjahanpur 896 70
3.3.4Coal Pricing
As Grade F coal is assumed to be received from NCL mines, fuel pricing
has been estimated accordingly in the DPR. Based on the existing
Strictly Private & Confidential 31
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
notifications of CIL, the delivered cost of coal from NCL has been
estimated at Rs. 1880 per tonne as mentioned below.
Table 20: Estimation of cost of coal for the project
Long Term Linkage
Rate (Rs./ton
ne)Run of mine Price 580Royalty 84SED (Special Excise Duty) 10CDM cess 50Crushing charges 39MPGAT SVA 44Total delivered cost (w/o tax) 807VAT/ CST (2%) 16Entry tax (2%) 16Total Cost (ex-mine including tax) 839Estimated Average Transportation & Handling Cost 1041Total Landed Cost (average at 5 sites) 1880
3.4 Evacuation of Power
The power would be evacuated by using already placed 132 KV
transmission line at four out of the five plant sites. UPPCL sub-stations
are located at around 15-25 km from the respective project sites. At
Utraula, UPPCL sub-station is being built within the premises of the
existing sugar unit. The details are as given under:
Table 21: UPPCL Sub-stations
S. No. Plant SitesName of UPPCL
Sub-station
Distance from respective
site (in Km)
1Khambarkhera
Lakhimpur, Kheri 14.6
2 Bartkhera Ruppur kamalu, Pilibhit
16.6
3 Kundarki Mankapur, Gonda 15.5
4 Maqsoodapur Baragaon, Puwaya, Maqsoodapur
26.7
5 Utraula To be installed within the premises of
Strictly Private & Confidential 32
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
S. No. Plant SitesName of UPPCL
Sub-station
Distance from respective
site (in Km)
the existing sugar unit
BEPL will build the evacuation system at Utraula and suitably augment
the existing transmission network, as required, at each of the
remaining 4 project sites. Cost of such augmentation has been
considered in the project cost estimates.
3.4.1Environmental Aspects
BHL has applied for the Environment Clearance to State Level Expert
Appraisal Committee (SEAC), GoUP vide letter no. BHSIL/02/SEAC/09
dated 12th November, 2009 (copy of letter enclosed in Volume II of this
IM). The approved Terms of Reference (TOR) have been received by
BHL from Directorate of Environment, Uttar Pradesh. BHL has also
carried out the Environmental Impact Assessment (EIA) study and
prepared the Environment Management Plan in line with the approved
TOR. The same have been submitted to Uttar Pradesh Pollution Control
Board (UPPCB). BHL has requested UPPCB to conduct Public hearing for
the proposed project vide letter dated April 5, 2010 (copy of letter
enclosed in Volume II of this IM). BHL has also made application to
Pollution Control Board for a No-Objection Certificate (NOC) for the
Project vide letter dated 7th December, 2009(copy of letter enclosed in
Volume II of this IM).
The Project takes into consideration establishment of the entire
essential pollution control systems / processes viz. chimney, waste
water treatment, recycling, etc. and expenditure for the same has
been included in the project cost estimates. Further, the Project sites
are free of any environmentally fragile features viz, national park,
sanctuaries, historical monuments within 25 Km from the Project sites
Strictly Private & Confidential 33
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
and no encroachment of forest land or any water body is envisaged by
the proposed Project.
Strictly Private & Confidential 34
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
4 Implementation Framework
4.1 Project Implementation Framework
The broad framework for implementation & subsequent operation of
the Project is depicted in the figure below:
Figure 4: Project Structure
4.2 State Support - MoU with Government of Uttar Pradesh
An MoU has been executed on 14th January, 2010 between Government
of Uttar Pradesh (GoUP) and BHL for setting the project in the state of
Uttar Pradesh at the aforesaid sites. GoUP has also assured help in
obtaining various statutory approvals/ clearances regarding the Project
like availability of water, environment clearance, recommendation to
Ministry of Coal for coal linkage, etc. GoUP has also assured in
purchasing power at the price decided/ approved by UPERC.
4.3 Technical Arrangements
Strictly Private & Confidential 35
BEPL450 MW
UPPCL
O&M
(In-house/Limited
Outsourcing)
BIDCO –
Project Management
BHL/
Promoter
Coal India
Limited
Lender
s
Debt
TRA
Cash Flow
PPAEquity
LIE,
LLC &
LIA
FSA
GoUP
State Support MoU
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
4.3.1Technical Consultant
The Company has appointed M/s Mantech Technical Services Private
Limited (MTSPL) vide letter dated 25.12.2009 (Copy enclosed in
Volume II of this IM) for the preparation of Detailed Project Report
(DPR) for the Project incorporating the following:
Basis of site selection and land requirement
Compliance statutory requirements
Fuel type and availability
Suitability of technology selected
Project schedule
Project cost and cost of generation
Status of permits/ approvals/ clearances/
Drawings
Design basis and technical features of main plant equipment
Basic requirements like land, fuel, water, power evacuation,
etc
A brief profile MTSPL and past projects handled by it is given in
Annexure VI.
4.3.2Project Management Company (PMC)
The PMC contract for the Project has been awarded to Bajaj
Infrastructure Development Company (BIDCO) through a Letter of
Award dated 24/12/2009. BIDCO was incorporated in 2006 to focus and
expand group’s infrastructure and real estate initiatives. BIDCO
focuses on developing high quality infrastructure, commercial, retail,
industrial and residential projects in India. Following are some of the
projects under execution by BIDCO:
Integrated township, Warangal Highway, Andhra Pradesh
Commercial Mall, Old Hyderabad, Andhra Pradesh
Redevelopment of prime land in Bandra and Kurla, BKC,
Strictly Private & Confidential 36
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Mumbai
Following are the projects in pipeline, all in Mumbai:
Redevelopment of 42000 sq. ft, Andheri (W)
Own plot development of 30,000 sq. ft, Santacruz (E)
Greenfield development of over 2,00,000 sq. ft, King’s Circle
BIDCO has a team of qualified professionals with vast experience of
implementing power projects throughout India. BIDCO shall function as
a dedicated central resource with the overall responsibility for
formulation of concepts, systems, basic and detailed engineering,
procurement, construction and management service, erection &
testing management services, inspection, quality control, obtaining
approvals and clearances, training of manpower & project
management concepts.
Brief details of the key personnel of BIDCO are given below:
Table 22: Key personnel of BIDCO
Name DesignationQualificatio
n
Experience
(yrs)
Previous Organizati
onMr. Kailash Bihari Dubey
Director (Project)
B. Tech (Mechanical)
35 NTPC
Mr. Ripon JainVice President - Finance & Operations
B.Com., LLB(Gen), C.A.
19Keystone Reality Pvt. Ltd.
Mr. Dwarkesh Sharma
Asst. Vice President (Commercial)
B.E. (Mechanical)
13Electro Steel Castings Ltd.
Mr. Sunil Kr. OjhaGeneral Manager (F&A)
ICSI, ICWAI, CA, B.Com
18 BHSIL
Mr. Pramod Kr. Mishra
General Manager (Group Technical Services)
B.E. (Electronics)
17Yokogawa India Ltd.
Mr. Lalit Kumar Singhal
General Manager (Civil)
B.E. (Civil) 19Reliance Energy Ltd.
Strictly Private & Confidential 37
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
4.3.3Major Contracts Awarded by BIDCO
BIDCO has initiated the process of project implementation by placing
orders for major project contracts as under:
A. Engineering Services
BIDCO has awarded the contract for Engineering Services to Powertech
Engineering Pvt. Limited (PEPL) vide letter dated 21/1/2010 (letter
enclosed in Volume II of this IM). The broad scope of work for PEPL
includes the following:
1. Detailed preparation of Design Basis documents;
2. Evaluation and Technical recommendation for placement of POs
by BIDCO;
3. Layout of system integration of various packages;
4. Control & Instrumentation Designs;
5. Civil and Structural Design Services.
A brief profile of PEPL and assignments executed by PEPL in the past is
enclosed in Annexure VI.
BIDCO shall also appoint an Owner’s Engineer to bring in requisite
expertise in various aspects of project supervision, management
services and overall wrapping of project packages in order to deliver
the performance as per the norms set out (stipulated as a pre-
disbursement condition).
B. BTG Contract
BIDCO has issued Letters of Awards (LOA) to the following suppliers for
the Boiler, Turbine & Generator package. BIDCO had appointed SMC
Power Limited to provide support/advisory services to ensure quality
sourcing and procurement.
Strictly Private & Confidential 38
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Table 23: Details of BTG contracts
Supplier Date of
LOA by
BIDCO
Date of
Acceptance of
LOA by the
supplier
Cost per
unit
(Rs
crore)
No.
of
Unit
s
Total
Cost
excl.
Taxes
(Rs
crore)
Boilers & Auxiliaries
ThyssenKrupp
Industries India
26/12/0
928/12/2009 116 3 348
Thermax
Limited
26/12/0
928/12/2009 120 2 240
Steam Turbine & Generator (STG)
Siemens
Limited
26/12/0
928/12/2009 45.50 5 227.5
Brief Scope of Work for ThyssenKrupp and Thermax
Design, engineering, manufacture, shop testing, packing,
forwarding, supply of boiler & its auxiliaries;
Complete erection, testing, trial run and commissioning of the
Boilers.
Supply of mandatory spare for two (2) years for trouble free
operation of the equipments
Supply of special tools for operation, maintenance, inspection
and repair of the equipments
Training of owners personnel in the operation and maintenance
of equipments/ systems
Commissioning: Commissioning of Boilers shall be done within
18-21 months from the date of LOA.
Strictly Private & Confidential 39
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Key features of the contracts awarded to ThyssenKrupp and
Thermax:
Table 24: Key features of contracts for Boiler and Auxiliaries
S.N
o
ParticularsDetails
Performance Guarantees
1. Guaranteed Boiler Efficiency
o Thermax
o Thyssenkrupp
86.0%
84.7% ± 1.0%
2. Steam output at the outlet of
main steam stop valve (MCR –
100%) while firing design
performance guarantee fuel with
feed water temperatures at
economizer inlet as per design
details (Thermax and
Thyssenkrupp)
190 TPH
(MCR)
3. Power consumption at Motor
input for continuously run
auxiliaries (in KW)
o Thermax
o Thyssenkrupp
3600
3476
Liquidated Damages (LDs)
4. Boiler efficiency - 84.7%
(Thyssenkrupp)
Boiler efficiency – 86.0%
(Thermax)
Rs 145 lacs for every
percentage fall below
guaranteed parameter
5. Auxiliary power consumption
(Thermax and Thyssenkrupp)
Rs 80,000/- per KW
increase beyond the
Strictly Private & Confidential 40
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
S.N
o
ParticularsDetails
guaranteed parameter
6. Maximum continuous rating –
100%
o Thyssenkrupp
o Thermax
1% of contract value for
every 1% reduction in MCR
1% of contract value for
every 1% reduction in MCR
7. Delay in Delivery (Thermax and
Thyssenkrupp)
0.50% of contract value per
week delay of delay or part
thereof
8. Cap on LDs LDs on account of
Shortfall in
Performance:
7.5% of contract price
LDs on account of Delay
in Delivery:
7.5% of contract price
Brief Scope of Work for Siemens Limited
Design, engineering, manufacture of Steam Turbine, Generator &
Auxiliaries, Station Control & Instrumentation package,
Generator Control Relay panels, Bunker Bay structure;
Complete erection, testing and commissioning of Steam &
Turbine Generators including Generator Transformer (GT),
Station Transformers (ST) and Auxiliary Transformers (UAT).
Supply of mandatory spare for two (2) years for trouble free
operation of the equipments (one set per site)
Supply of special tools and tackles required for operation,
maintenance, inspection, removal and repair of generator rotor,
Strictly Private & Confidential 41
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
etc.
Training of owners personnel in the operation and maintenance
of equipments/ systems
Commissioning & Taking Over: Commissioning of Boiler shall be
done within 18 months from the date of LOA along with advance.
The taking over shall be completed with in 2 months from
schedule date of commissioning.
Performance Guarantee test to be conducted at 45 MW.
Key features of the contracts awarded to Siemens
Limited:
Table 25: Key features of contracts for Steam Turbine and Generator
S.N
o
ParticularsDetails
Performance Guarantees
1. Turbine Heat Rate 2281 Kcal/kWh
2. Auxiliary power consumption 198 kW
Liquidated Damages (LDs)
3. For every 1 Kcal/ KWh
deterioration in performance
figure of heat rate
Rs 6.5 lacs
4. For every kW increase in auxiliary
power consumption
Rs 80,000/-
5. For every M³/ hr increase in water
requirement
Rs 1.2 lac/M³
6. Reduction in gross power output To be compulsorily rectified
7. Increase in sound levels To be compulsorily rectified
8. Delay in Delivery 0.50% of contract value per
week of delay or part
thereof
Strictly Private & Confidential 42
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
S.N
o
ParticularsDetails
9. Cap on LDs LDs on account of
Shortfall in
Performance:
7.5% of contract price
LDs on account of Delay
in Delivery:
7.5% of contract price
A brief profile of ThyssenKrupp, Thermax and Siemens along with the
details of similar assignments handled in the past is enclosed in
Annexure VI.
C. Civil Work and Structural Services
Contract for Design Services
BIDCO had awarded the contract for preliminary Architectural, Civil and
Structural Design Services to Sijcon Consultants (P) Ltd (Sijcon) vide
letter dated 11.01.2010. Sijcon’s broad scope of services included the
following:
Soil investigation work for the land
Drawings for site levelling, filling and grading based on survey
drawing
Drawings for roads, pathways, etc.
Scheme for de-watering in the plant area and drainage scheme
Design detailed engineering drawings
Preparation of machinery foundations
Quality assurance
Control room layout
Sanitary and other plumbing works
Finishing works like plastering, paintings, etc.
Strictly Private & Confidential 43
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Subsequently, for the complete project Architectural, Civil and
Structural Design Services, contract has been awarded to TPSC (India)
Pvt. Ltd which has taken over the previous contract awarded to Sijcon.
Contract for Civil Works
BIDCO has awarded the contract for Civil Works to ERA Building
Systems Ltd (ERA), K.K Construction Builders (KKCB) and Petron Civil
Engineering Pvt. Limited (Petron) vide letters dated 14.01.2010. The
broad scope of work under the Civil Works Package is as under:
Earthwork for relevant area
PCC/ RCC works of relevant area
Foundations including pilling wherever required
Masonry works
Structural steel work
Plastering, paintings, skirting, flooring, etc
Water supply and drainage
Road work, storm water drain work, etc
Post completion site clearance
Dismantling and shifting work of existing structures
A brief profile of TPSCI, ERA, KKCB and Petron along with the details of
recent projects executed is enclosed in Annexure VI.
In addition to the above, minor civil works not covered under the above
mentioned contracts will be awarded as per requirement to other
parties of repute.
4.4 Operation & Maintenance Arrangement
BHL Group has extensive experience in operating more than ten co-
generation power plants. The operation & maintenance (O&M) of the
Project would be undertaken by BEPL’s in-house O&M team. The O&M
Strictly Private & Confidential 44
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
team of the power station would be headed by a Senior Vice President,
under whom separate groups viz. Operation, Mechanical, Electrical,
Civil and C&I maintenance would operate. In addition to these groups,
operation and efficiency improvement group and maintenance
planning group would monitor the efficiency in operations and
maintenance management respectively and suggest continual
improvements. In order to bring expertise and state-of-the-art
technology and systems, O&M activities may also be outsourced
partially.
4.5 Power Sale Arrangements
U.P. Power Corporation Limited (UPPCL) and BHL have initialled Draft
PPA for sale of 90% of the net power generated by the Project.
The following are the key features of the Draft PPA:
4.5.1Power Sale to UPPCL
4.5.2Term of Agreement
The PPA shall become effective after receiving due approval from Uttar
Pradesh Energy Regulatory Commission (UPERC) and shall be valid for
a period of twenty five (25) years, which can be extended further on
mutually agreed terms.
4.5.3Tariff
The tariff shall be determined in accordance to the UPERC Guidelines
and shall consist of the following:
4.5.3.1 Capacity Charge
The Capacity Charge, payable by UPPCL, shall comprise of the
following:
Strictly Private & Confidential 45
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Interest on loan capital as per the financial package approved by
the UPERC.
Debt-equity ratio shall be considered as 70:30 with equity being
limited to 30% if equity employed is more than 30%.
Depreciation shall be calculated on Straight Line Method and at
prescribed rates. Depreciation shall be allowed up to 90% of the
historical cost of the plant.
Advance Against Depreciation, as under:
o AAD = Debt repayment amount subject to a ceiling of 1/10th
of debt minus Depreciation
Return on equity @ 15.50% p.a. If the project is completed before
the stipulated time as per Regulatory Norms, additional return of
0.5% shall be provided.
O&M Expenses (including insurance) as determined by UPERC
guidelines.
Interest on Working Capital @ short term prime lending rate of State
Bank of India, calculated on the aggregate of the following:
o Cost of coal for two months consumption;
o Cost of secondary fuel for two months;
o O&M Expenses for one month
o Maintenance spares at rates determined by UPERC
o Receivables equivalent to two months of fixed and variable
charges for sale of electricity;
o Any other component as may be approved by UPERC.
Recovery of Capacity Charges
The Capacity Charge shall be recoverable at target availability as
approved by UPERC, but is subject to a pro rata reduction if the Plant
Availability is below target availability as approved by UPERC.
Strictly Private & Confidential 46
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
4.5.3.2 Energy Charge
The Energy Charge payable by UPPCL includes the following:
Landed cost of both Primary and Secondary fuel.
Fuel costs shall be worked out on the basis of ex-bus energy
scheduled to be sent out from the Project as per the following
formula:
o Energy Charge = Rate of Energy Charge in Rs/ kWh x
Scheduled Energy (ex-bus) for the month in kWh
corresponding to scheduled generation.
o Where, Rate of Energy Charge shall be the sum of the cost of
normative quantities of primary and secondary fuels for
delivering ex-bus one kWh of electricity in Rs./ kWh.
4.5.3.3 Tax on Income and Statutory Levies
Tax on income streams of the Company from sale of electricity shall be
computed as an expense and shall be allowed to be recovered in the
same proportion as Capacity Charge. Apart from this, Statutory taxes,
duties and levies paid by the Company in relation to generation of
electricity from the Project shall be recovered in Tariff.
4.5.4 Incentive for Timely Completion
In case the plant/ unit is commissioned before schedule as approved
by UPERC the Company shall be eligible for the incentive of an amount
equivalent to reduction of interest during construction as UPERC
guidelines.
4.5.5Billing and Payment Security Mechanism
The Company shall raise a monthly bill to UPPCL based on the monthly
joint meter reading of the main meters. For payment of bills through a
Letter of Credit on presentation, a rebate of 2% shall be allowed to
Strictly Private & Confidential 47
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
UPPCL. If the payment is made by a mode other than the Letter of
Credit but within one month of presentation of bill, a rebate of 1% will
be allowed to UPPCL. Payments delayed by a period of more than 2
months from date of billing shall bear surcharge of 1.25% per month.
4.5.5.1 Letter of Credit
UPPCL is required to maintain an irrevocable, revolving, self-
replenishing Letter of Credit in favour of the Company throughout the
term of the PPA. The Letter of Credit shall be valid for a period of at
least 1 year and have a face value equal to one month’s billing amount
based on 85% target availability for the first three operating months
following CoD of the First Unit and thereafter equal to the average
monthly billing for last three operating months. The Letter of Credit
shall be reinstated/replenished within 5 days of drawdown.
Notwithstanding the mechanism described herein, UPPCL shall have
the right to make direct payment of any bill by cheque or otherwise.
4.5.5.2 Escrow Account
UPPCL shall establish an Escrow Account to maintain funds equivalent
to 1.25 times of the monthly Tariff amount and other payables based
on 85% target availability for the purpose of guaranteeing the
reinstatement of the Letter of Credit on a monthly basis as and when
the same becomes due and payable. The Company shall have a
recourse to the Escrow Account at all times during the term of the PPA.
4.5.6Merchant Sale
BEPL proposes to sell balance power, i.e. around 45 MW project
capacity on merchant basis. The commercial aspects of saleability of
merchant power are discussed in Chapter 5.
Strictly Private & Confidential 48
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
4.6 Power Evacuation Arrangement
The power would be evacuated by using existing 132 KV transmission
line at four out of the five plant sites. UPPCL sub-stations are located at
around 15-25 km from the respective project sites. At Utraula, UPPCL
sub-station is being built within the premises of the existing sugar unit.
BEPL will build the evacuation system at Utraula and suitably augment
the existing transmission network at each of the remaining 4 project
sites.
4.7 Schedule of Implementation
As per the LOA given to BIDCO by BHL (and corresponding back to
back contracts awarded by BIDCO to project contractors) all the five
(5) units of the Project are expected to be completed within 22 months
of award of LoA to BIDCO. Indicative timelines for achievement of key
project implementation milestones are as follows:
Table 26: Schedule of Implementation
Milestone/Activity Timeline
Letter of Award to BIDCO24th December, 2009
Coal Linkage Meeting 8th April, 2010Finalization of Draft PPA with UPPCL
April, 2010
Signing of Final PPA with UPPCL July, 2010Completion of Land Transfer July, 2010Financial Closure July, 2010Environment Clearance by MoEF, GoI
September, 2010
Commencement of Commercial operations of Project
1st November, 2011
The detailed time schedule for implementation of the Project is given in
Annexure III.
Strictly Private & Confidential 49
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
5 Industry Scenario
5.1 Power Sector Scenario in India: A Perspective
The power sector provides one of the most important inputs for the
development of a country and availability of reliable and inexpensive
power is critical for its sustainable economic development. To sustain
GDP growth rate of around 9-10 %, it is imperative that the power
sector also grows at the same rate.
The Indian power sector has grown manifold in size and capacity since
independence. Power installed generating capacity has increased from
1,362 MW in 1947 to 1,56,092 MW as on 31st December, 2009. Even
after the considerable growth in the power sector infrastructure and
the supply of electricity, many parts of the country continue to face
severe power shortages as consumption by commercial and industrial
consumers has been increasing at much faster rate than electricity
supply. The following chart depicts growth in the installed generation
capacity since 2003.
Figure 5: Installed Generation Capacity
Strictly Private & Confidential 50
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Growth in Installed Generation Capacity
020000400006000080000
100000120000140000160000
2003 2004 2005 2006 2007 2008 2009
Year
In M
W
RES
Hydro
Nuclear
Thermal
(Source CEA)5.1.1Historical Demand-Supply scenario
The annual per capita consumption of electricity in India has increased
by CAGR of about 4% from FY 2003 (566.7 Kwh) to FY 2008 (704.2
Kwh). World’s average per capita consumption stands at 2600 Kwh as
on 31st October, 2008. The low per capita consumption is a result of
the low penetration of electricity at the household level especially in
rural areas.
Figure 6: Per Capita Consumption
Strictly Private & Confidential 51
Per Capita Consumption
0
100
200
300
400
500
600
700
800
2002-03 2003-04 2004-05 2005-06 2006-07 2007-08
Per Capita Consumption(Kwh) (As per U.Nmethodology)
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
(Source CEA)
Though there has been substantial growth in power sector
infrastructure in India over the last few years, the power supply
position in still characterized by shortages, both in terms of supply
during peak period and the overall electricity supply. Many parts of the
country continue to face severe power shortages. In fact, power supply
position in the country has worsened over the last few years with
growth in power demand outstripping new capacity addition with peak
power deficit being worst at 16.6% in 2007-08. The energy deficit at
the national level has increased from 7.1% in 2003-04 to 11% in 2008-
09.
Table 27: Year Wise Power Demand Supply ScenarioYear Energy (MU) Peak (MW)
Requirement
Availability
% Shorta
geDeman
d Met
% Shorta
ge2002-03
545,674 497,589 8.8 81,492 71,547 12.20
2003-04
559,264 519,398 7.1 84,574 75,066 11.20
2004- 591,373 548,115 7.3 87,906 77,652 11.70
Strictly Private & Confidential 52
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Year Energy (MU) Peak (MW)
Requirement
Availability
% Shorta
geDeman
d Met
% Shorta
ge052005-06
631,554 578,819 8.4 93,255 81,792 12.30
2006-07
690,587 624,495 9.6 100,715 86,818 13.80
2007-08
739,345 666,007 9.9 108,866 90,793 16.60
2008-09
774,324 689,021 11 109,809 96,685 12.00
Apr 09-Nov 09
549,257 495,821 9.7 116,281 101,60
912.60
(Source CEA)
The power deficit scenario is particularly worse in the northern and
western regions, two of the most industrialized regions of the country.
Peak power deficit in the northern and western regions were 10.7%
and 19% respectively in 2009. The reasons for power shortage are:-
Low Plant Load Factor of some of the thermal generating units,
mostly in State sector.
High transmission and distribution losses.
Inadequate sub-transmission and distribution network in some
States.
Inadequate inter regional transmission capacity, for supplying
power from surplus regions to deficit regions.
Poor financial position of State utilities rendering it difficult for
them to raise the resources necessary for making required
investments to create adequate generation, transmission and
distribution system.
The table below shows the base load and peak load deficit for the top
five states on the basis of power consumption.
Strictly Private & Confidential 53
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Table 28: Power Deficit vs Highest Power Consumption in India
State
Base Load Deficit (%) Peak Load Deficit (%)
November
2009
April2009
April
2008
November
2009
April
2009
April 2008
Maharashtra 16.8 21.7 21.4 25.1 23.3 28.2Gujarat 8.1 3.3 23.1 9.2 5.5 28.5Tamil Nadu 6.8 8.4 4.2 4.4 9.8 8.5Andhra Pradesh
3.511.8 4.6 4.2 10.1 12.7
Uttar Pradesh
23.110.8 15.7 24.6 21.9 25
(Source: CRISIL Research)
As seen above UP is amongst the top five states power deficit states of
the country.
5.1.2Relatively Higher Aggregate Technical and Commercial
(AT&C) Losses
The key factor for sustainability of the power sector is to keep the
Aggregate Technical and Commercial (AT&C) losses at low levels, as
against the current high level of around 28%. To address this issue, GoI
started an initiative named as Accelerated Power Development and
Reform Programme (APDRP) to leverage distribution reforms in the
states. Priority is given to the states that have committed themselves
to a time-bound programme of reforms as elaborated in the
Memorandum of Understanding and Memorandum of Agreement with
the Central Government, and are progressing on those commitments.
GOI aims to bring AT&C losses down to 15% by the end of the 11th five
year plan.
Table 29: AT&C losses
Strictly Private & Confidential 54
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
AT&C Loss (%) for SEBs, PDs & Discoms for FY 2002 – 2007
Region2001-
022002-
032003-
042004-
052005-
062006-
07Eastern 47.34 44.37 44.81 43.16 41.8 38.21North Eastern 40.65 44.1 40.56 39.01 35.92 41.33Northern 46.01 37.85 40.14 41.54 40.44 37.18Southern 27.63 28.05 22.71 24.18 23.93 22.69Western 39.6 40.45 37.55 35.19 38.29 37.37
(Source CRISIL Research)
Northern (19.2%) and Eastern (19.3%) region have shown substantial
reduction in these losses during the five year period while other
regions have made only marginal improvements.
5.2 Region wise Demand Supply Scenario
Details of the region wise demand-supply scenario in India are given
herein.
Table 30: Region Wise Demand-Supply Scenario(MUs)
2009-10 (till Nov’09) 2008-09Region
Requirement
Availability
Deficit (%)
Requirement
Availability
Deficit (%)
Northern
173719 152708 12.1 224218 199928 10.8
Western
166766 146408 12.2 254486 213724 16
Southern
143454 134693 6.1 204086 188865 7.5
Eastern
58949 56430 4.3 82127 78370 4.6
NE Region
6369 5582 12.4 9407 8134 13.5
All India
549257 495821 9.7 774324 689021 11
(Source: CEA)
5.2.1Demand-Supply Scenario in Northern Region
The Northern region experienced an energy shortage of 10.8% and a
peak power deficit of 10.7% during 2008-09. Details of the prevailing
Strictly Private & Confidential 55
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
power situation in Northern region states during April 2008 to March
2009 are provided in the table below:
Table 31: Demand Supply Scenario in Northern Region States
Region Energy Requirement (MU) Peak Load (MW)Requirement
Available
Deficit
Demand
MetDeficit
Delhi 22,249 22,123 0.6% 4,036 4,034 0.0%Haryana
28,791 26,331 8.5% 5,511 4,79113.1
%Himachal Pradesh
6,261 6,246 0.2% 1,055 1,014 3.9%
Jammu & Kashmir
11,148 8,564 23.2% 2,120 1,40533.7
%Punjab
41,297 36,900 10.6% 8,690 7,30915.9
%Rajasthan 37,306 36,898 1.1% 6,303 6,101 3.2%U.P.
68,003 53,796 20.9% 10,587 8,24822.1
%Uttaranchal 7,762 7,669 1.2% 1,267 1,267 0.0%Chandigarh 1,401 1,401 0.0% 279 279 0.0%Northern region
224,218199,92
810.8
%33,03
429,5
0410.7
%(Source CEA)
The worst affected states in the Northern region are Uttar Pradesh and
Jammu & Kashmir with severe energy and peaking power deficit.
5.2.2Projected Power Requirement in Northern Region
The projected power requirement in the aforementioned states is given
below:
Table 32: Projected Power Requirement in Northern Region
StateEnergy Requirement (MU)
Peak Load (MW)
2011-12 2016-17 2011-12 2016-17Delhi 36,293 52,762 6,092 8,729Haryana 38,417 54,305 6,839 9,375Himachal Pradesh
9,504 13,136 1,611 2,194
Jammu & Kashmir
11,202 15,272 2,063 2,790
Strictly Private & Confidential 56
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
StateEnergy Requirement (MU)
Peak Load (MW)
2011-12 2016-17 2011-12 2016-17Punjab 60,489 82,572 11,000 14,441Rajasthan 48,916 67,767 8,482 11,404Uttar Pradesh 79,268 110,665 13,947 19,623Uttaranchal 8,445 11,668 1,533 2,085Chandigarh 2,308 3,367 420 602Northern region
294,841 411,513 48,137 66,583
(Source: 17th Electricity Power Survey (EPS) of CEA)
There would be projected shortage of about 14,286 MW power by the
year 2011-12 pan India. The major shortfall would be evident
especially in Northern region.
5.3 Analysis of Present Capacity
Electricity being a concurrent subject, both the Centre and the States
has to play a decisive role in this sector. While the Centre has a
significant share in the transmission segment, the distribution segment
is in the domain of the States. However, for creation of generation and
transmission capacity, in line with the growing needs of economy, all
the sectors namely Central, State and Private need to play a vital role.
The ownership mix of the installed generation capacity in the country
as on December 31, 2009 is as depicted below:
Table 33: Ownership Mix of the Installed Generation Capacity(in MW)
Secto
r
Hydr
o Thermal
Nucle
ar R.E.S Total
Coal Gas Diesel Total(MNRE)
State2708
74405
54046 603
48703
0 26247841
4Central
85653042
56702 0
37127
4120 04981
3Private
1233 7126 6308 5971403
10 12602
27866
Strictly Private & Confidential 57
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Total3688
58160
61705
61200
99861
4120 152251560
92(Source: CEA)
As a matter of legacy, the central and state sectors together constitute
over 86% of the installed capacity. However, with opening up of sector
in 1990s with further reforms pursuant to the Electricity Act, 2003, the
share of private-sector in the ownership-mix for the generation sector
has improved substantially. The graph below shows the growth in
private players’ participation in power sector from 1993 onwards:
Figure 7: Growth in Private Participation in Power Sector
(Source: Central Electricity Authority, CRISIL Research)
There has been no significant change in the fuel mix over the past 11
years. The thermal-hydel mix changed from 75:25 in 1997-98 to 72:28
in 2007-08. The share of nuclear power plants in the overall installed
capacity remains low.
Figure 8: Installed Capacity by Type of Fuel
Strictly Private & Confidential 58
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
(Source: Central Electricity Authority, CRISIL Research)
5.4 Capacity Addition Program
Assuming 8% and 9% GDP growth rate scenario with 1:1 elasticity
between economic growth and energy intensity, the following
projections have been set forth by the Ministry of Power in its
Integrated Energy Policy.
Figure 9: Long Term Capacity Addition Projections
(Source: Central Electricity Authority)
Government of India has formulated an ambitious capacity addition
programme over the 11th and 12th plan periods in order to meet its
“Power for all” objective by 2012. GOI, under its ‘Power For All by
2012’ mission, plans to increase per capita power consumption to 1000
KW by 2012. Under Rajiv Gandhi Grameen Vidhyutikaran Yojana,
Ministry of Power is planning to achieve 100% rural electrification. This
Strictly Private & Confidential 59
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
provides a tremendous investment opportunity in the Indian power
generation market for both public and private sector. Government is
also emphasizing on use of renewable sources of energy generation,
like solar power, biomass, hydro power, biogas and wind power.
Moreover, parallel focus is being given on demand side management
with initiatives like energy conservation and energy efficiency and
supply side management with initiatives like reduction in Transmission
& Distribution (T&D) losses, improvement in transmission and sub-
transmission networks.
11th five year plan (April 2007- March 2012) for power aims at adding
78,700 MW. However, the actual capacity addition in 2008-09 is about
3,453.7 MW against the target of 11,061.2 MW for the period2. The
capacity additions are significantly lower than the projected
requirements and the current power deficit situation is likely to
continue in medium term. The following have been identified as the
main reasons for repeated failures in achievement of the targets by
thermal power plants:
Delay in land acquisition;
Delay in water linkage;
Environmental clearances;
Road and Railway connectivity for approach;
Delay in award of coal linkage/gas linkage by Government;
Financial problems related to the health of SEBs as also delay in
achieving financial closures of the project.
The chart below shows the capacity deficits in comparison to target
levels in different five year plans. In the coming times, manifold
increase is expected in power demand due to high economic growth
and hence it is imperative to ensure that the targets are met.
2 (Source: Ministry of Power)
Strictly Private & Confidential 60
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Figure 10: Plan Wise Capacity Additions
(Source: CEA)
As against the 14,507 MW capacity addition planned by the
government in 2009-10, only 6250 MW has been setup till 31st
December 2009 (CRISIL Research).
5.4.1Capacity Additions Required in Uttar Pradesh (UP)
Capacity additions required to meet the Peak and Energy deficit in the
UP is given in the table below:
Table 34 : Capacity Additions Required in Uttar Pradesh
S.No.
Details
Unit (MW)Starting year of XI five year plan(2007-08)
End Year of
XI five year plan(2011-12)
End year of XII five year plan(2016-17)
1Planned capacity addition during XI-th plan (MW)
NA 3600 4640*
2Total capacity available during the year (MW)
9335 12935 17575
3Peak power availability (MW)
6578 9054 12478
4Peak power demand(MW)
10193 13947 19623
Strictly Private & Confidential 61
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
S.No.
Details
Unit (MW)Starting year of XI five year plan(2007-08)
End Year of
XI five year plan(2011-12)
End year of XII five year plan(2016-17)
5Power deficit (MW)(+ for surplus, - for deficit)
-3615 -4893 -7145
6Additional installed Capacity required to offset the deficit (MW)
5092 6850 10003
*Assuming PAF of 71%
(Source: www.cea.nic.in 1.Capacity addition target during 11th plan set by planning commission and 2. International conclave on key inputs for accelerated development of Indian power sector for 12th plan and beyond)
Installed capacity required to offset the power deficit in U.P. is about
6,850 MW by the year 2011-12 and by the year 2016-17 it is about
10,003 MW.
5.5 Power Trading Scenario
5.5.1Trading Volume & Power Traders
The merchant power generated is sold in the open market via bilateral
transactions or through power exchanges.
Figure 11: Historical Trend of Merchant Power Transaction
Strictly Private & Confidential 62
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
(Source: CERC)
Trading of power has increased substantially over the last few years
with the emergence of several power traders. Power trading volumes
have increased from 11,028.96 MU in 2003-04 to 20,964.77 MU in
2007-08 depicting a CAGR of ~17.4%. However, the total power traded
in the country is still a meagre 3.57% of the total power generation
(2008-09) but is expected to reach 10% of total energy generation by
2012 maintaining double digit CAGR. PTC India Ltd was the first entrant
in the sector and is today the largest power trading entity in the
country with over 45.57% market share in 2007-08. Few key power
trading entities in the country and their respective market share are as
follows:
Table 35: Power Trading Entities and Respective Market Shares in 2007-08S.No Name Market Share
1. PTC India Ltd 45.57%
2. Adani Exports Ltd 6.31%
3. JSW Power Trading Co. Ltd 7.05%
4. Lanco Electric Utility Ltd 12.4%
5. NTPC Vidyut Vyapar Nigam Ltd 15.86%
6. Tata Power Trading Co. Ltd 8.02%
7. Reliance Energy Trading Ltd 3.70%
5.5.2Price of Traded Power
The weighted average price of traded power has also increased
substantially which is reflective of the widening demand-supply
mismatch and huge seasonal variations in power demand. The
weighted average price of traded power has increased from Rs 4.52
per Kwh in 2007-08 to Rs 7.31 per Kwh in 2008-09. A detailed analysis
of the volume of power traded at various price levels over the last four
years is presented in the figure below.
Strictly Private & Confidential 63
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Figure 12: Price Analysis of Traded Power
(Source: CERC)
5.6 Regulatory Scenario
5.6.1The Electricity Act, 2003
The Act moves towards creating a market-based regime in the power
sector. The Act seeks to consolidate, update and rationalize laws
related to generation, transmission, distribution, trading and use of
power. It focuses on:
Creating competition in the industry
Protecting consumer interests
Ensuring supply of electricity to all areas
Rationalizing tariff and thus lowering the cross-subsidization
levels
Encouraging autonomous regulation with the separation of
policy, regulatory and operational aspects
Strictly Private & Confidential 64
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
5.6.2National Tariff Policy
In compliance with the provisions under the Electricity Act, 2003, GoI
notified the Tariff Policy on January 06, 2006. The policy deals with
various parameters with respect to fixation of tariffs, like providing
adequate return on investment to the power generator and ensuring
reasonable user charges for the customers. The policy moots the
procurement of power separately for base and peak load requirements
and introduction of differential tariffs for peak and off-peak hours, for
better load management.
The MoP notified the Guidelines for Determination of Tariff by Bidding
Process for Procurement of Power by Distribution Licensees
(Competitive Bidding Guidelines) on 19th January 2005, under the
provisions of Section 63 of EA03.
5.7 Conclusion
Given the prevalent demand supply deficit scenario and projected
growth in power requirement, huge addition in generation capacity is
required in the country over the coming decade. Consequently, there
exists an attractive business and market opportunity especially in the
northern & western regions of the country. As discussed earlier, 90% of
the net energy generated from the Project will be delivered to the state
of Uttar Pradesh, under a long term PPA with UPPCL. Uttar Pradesh
(U.P.) is the largest power consumer of Northern India with the highest
energy deficit among all north Indian states. As a result of the
continuing power deficit situation in the state, price of power sold in
the short-term market has also risen sharply. Based on the Annual
Revenue Requirements (ARR) filed by the U.P. distribution utilities to
UPERC for tariff fixation for FY 2009-10, the price of short term power
approved is Rs. 7.70/kWh. Recent PPAs for long-term sale of power in
U.P. have also followed the increase in price of power and have been in
Strictly Private & Confidential 65
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
excess of Rs. 3/KWh.
Additionally, power procured from electricity surplus states of eastern
and north-eastern region is being sold at higher tariff due to additional
wheeling charges and associated transmission losses involved.
The proposed Project is one of the few power projects expected to be
commissioned in the state of Uttar Pradesh in the 11th five year plan
period. Given the acute shortage of power in U.P., there is low risk
foreseen in the off-take of power from the Project.
Strictly Private & Confidential 66
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
6 Project Cost and Means of Financing
6.1 Components of Project Cost
The Project is estimated to be set up at an aggregate cost of Rs. 2,320
crore. This includes hard cost of Rs. 1,878.72 crore and soft cost of Rs.
441.28 crore. The hard cost estimates are as per the DPR prepared by
Mantech Technical Services Private Limited and are inclusive of all
indirect taxes as may be applicable for the Project. A breakup of the
Project cost estimate is provided in the Table below:
Table 36: Estimation of Cost of ProjectRs. crore
Particulars Amount
Land and Site Development 57.50Civil Works 345.00BTG 949.53BoP – Mechanical 321.91BoP – Electrical 97.87Control and Instrumentation 39.56Augmentation of Evacuation System 44.75Initial Spares 22.60Total Hard Cost 1878.72Project Monitoring, Supervision and Quality Control 82.00Trial & Pre-commissioning Expenses 50.00Pre-operative Expenditure 29.36Interest During Construction Period 174.86Margin Money for Working Capital 48.70Contingency 56.36Total Soft Cost 441.28Total Cost 2320.00
Based on the estimated Project cost indicated above, the cost per MW
of the Project works out to Rs 5.16 crore/MW. Capital cost of the
proposed Project is comparable with other coal based power projects
being currently developed using similar technology and configuration.
Strictly Private & Confidential 67
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Rural Electrification Corporation has sanctioned loan for a 2 x 50 MW
Brownfield thermal power project using similar technology and
equipment configuration. Per MW cost in the aforesaid project is
estimated at around Rs. 5.33 crore which is comparable to the
proposed Project.
6.1.1Cost of Land and Site Development
Aggregate land requirement for the Project is about 104 acres. The
total cost of the land is estimated at around Rs. 12.50 Crores for the
Project at the rate ranging from Rs. 6 Lacs to Rs. 20 Lacs per Acre.
There is no Rehabilitation and Resettlement (R&R) involved at the
Proposed Project Site. The cost of Site Development has been
estimated at Rs. 45.00 crores.
6.1.2Cost of Civil Works
Cost of civil works includes expenditure on all plant civil work including
foundation, structures, main plant and ancillary buildings, site civil
work including piling, chimney including ladder, ash dyke, raw water
reservoir, de-watering system, essential housing, security and store
buildings, roads and drains, boundary walls, watch towers and other
necessary infrastructures.
6.1.3BTG Cost
BTG package has been awarded to ThyssenKrupp Industries India (for 3
Boilers) for Rs 348 crore, Thermax Limited (for 2 Boilers) for Rs 240
crore and Siemens Limited (for all 5 Steam Turbine & Generator
package) for Rs 227.50 crore on fixed cost basis exclusive of taxes and
duties. Aggregate cost of BTG package after applying relevant taxes
and duties of works out to Rs. 949.53 Crore. The company is required
to pay the contract price in INR only.
Strictly Private & Confidential 68
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
6.1.4Balance of Plant (BOP) Cost
BoP is divided under Mechanical and Electrical BoP. BoP Mechanical
includes expenditure on all piping, cooling towers, DM Plant, coal and
ash handling plant, air-conditioning, fire fighting & protection system,
Effluent Treatment Plant, EOT cranes, etc. BoP Electrical includes cost
of all panels, transformers, switch gears, cables, switchyard, etc. The
cost of BoP Mechanical is estimated at Rs. 321.91 crores and BoP
Electrical at Rs. 97.87 crores.
6.1.5Control and Instrumentation
Control and Instrumentation comprises of distributed control system
for centralized control and monitoring of the plant parameters, BoP
instrumentation, cable laying , steam and water analysis system,
erection and commissioning of all the C&I systems.
6.1.6Augmentation of Evacuation System
This cost includes strengthening of transmission lines and addition of
Bay equipment with associated civil work at the respective UPPCL Sub-
stations, as required.
6.1.7 Initial Spares
The cost of initial spares for various plant and machinery equipment is
estimated at Rs. 22.60 crores.
6.1.8Project Monitoring, Supervision and Quality Control
The total cost towards project monitoring, supervision and quality
control is estimated at Rs. 82 crores. This includes the payment to the
Project Management Company for co-ordination and appointment of
sub-consultants with requisite expertise to provide civil, structural
design and architectural services, Soil related studies, Seismic study
and other civil work related study and investigations, Owner’s
Strictly Private & Confidential 69
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Engineering services including integration and inter-facing of package,
critical piping routing etc., complete plant/design engineering,
including complete procurement and logistics management, project
supervision, monitoring, co-ordination with owner’s engineers,
architects, quality control services, legal advisors and other
professional service providers for and in relation to plant and project
execution. Project monitoring and supervision will ensure timely
implementation of project, synchronisation of plant in co-ordination
with Equipment Suppliers and other agencies while adhering to quality
in erection and commissioning in order to achieve successful trial as
per agreed performance parameters.
6.1.9Trial and Pre-commissioning Expenses
The trial and pre-commissioning expenses are estimated at Rs. 50
crores to be incurred mainly towards start-up fuel and coal to be used
while undertaking the trial operations for various units.
6.1.10 Contingency
To provide for any unforeseen expenditures and variations in the
estimates of costs on account of change in contract scope, escalation
in cost of key inputs like steel and cement etc., a contingency of 3% of
the Total Hard Cost has been assumed at Rs. 56.36 crores.
6.1.11 Pre-Operative Expenses
Pre-operative Expenses are estimated to be Rs. 29.36 crore for the
Project which consists of preliminary expenses including establishment
charges, fees to be paid towards technical studies conducted by
various consultants, legal expenses, manpower training, overheads
and other administrative expenses.
Strictly Private & Confidential 70
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
6.1.12 Interest during Construction Period
The debt drawdown schedule has been made in accordance to the
expenditure phasing assumptions enumerated in Annexure IV. The
interest rate considered for the construction period is 11.5% per
annum. The Interest during Construction (IDC) for the Project works out
to be Rs. 174.85 crore.
6.1.13 Margin Money
The margin money has been estimated at 25% of projected net
working capital requirement of Project in the first full year of operation.
For the purpose of estimates, the current assets comprising of
receivables of 1.5 month, primary fuel stock of 1.5 month, secondary
fuel stock of 1.5 month, O&M expenses of 1 month and spares
requirement equal to 20% of the O&M expenses has been assumed.
The provision for margin money for working capital has been made at
Rs. 48.70 crore for the Project.
6.2 Means of Financing
The cost of the Project is estimated at Rs. 2320 crore and is proposed
to be financed with debt and equity in ratio of 75:25. The proposed
components of financing are as under:
Table 37: Components of Financing
ParticularsRs.
Crore%
Promoter Contribution 580.00 25%Rupee Term Loan 1740.00 75%
Total 2320.00 100
%
6.2.1Promoter Equity Contribution
The equity requirement for the Project is Rs. 580 crore and is proposed
to be funded by internal accruals of BHL and through equity
contribution from Promoter Group. Out of the total equity requirement
for the Project, 60% of total equity requirement would be brought
Strictly Private & Confidential 71
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
upfront prior to the initial drawdown of the Rupee Term Loan.
6.2.2Rupee Term Loan
Rupee Term Loan for the Project will be sourced from various domestic
banks and Financial Institutions (FIs) and the indicative terms for the
proposed debt are mentioned in Chapter 11. Rupee Term Loan is
expected to be contracted for a door-to-door tenor of up to 12 years.
7 Financial Projections – Snapshot
The key assumptions underlying the profitability projections for the
Project are detailed in Annexure IV. Based on these assumptions key
financial parameters are given below. Detailed Profit & Loss Account,
Cash Flow Statement, Balance Sheet and DSCR Calculations are given
in Annexure VII.
7.1 Project Financials
Table 38: Snapshot of financial parameters of the Project (Rs. Crores)
FY Ending March 31,
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
No. of months of operation
5 12 12 12 12 12 12 12 12 12 12
Capacity(MW)
450 450 450 450 450 450 450 450 450 450 450
PLF 80% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85%
Net Generation (MU's)
1182
.6
3015
.6
3015
.6
3015
.6
3015
.6
3015
.6
3015
.6
3015
.6
3015
.6
3015
.6
3015
.6
Total Revenue
393.
5
982.
5
980.
7
979.
5
978.
8
978.
8
979.
5
980.
8
982.
8
985.
5
990.
2
Total operating cost
202.
8
528.
2
543.
5
559.
2
575.
5
592.
4
609.
7
627.
7
646.
3
665.
5
685.
4
PBDIT190.
7
454.
3
437.
2
420.
2
403.
3
386.
5
369.
7
353.
1
336.
5
320.
0
304.
8
Strictly Private & Confidential 72
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
FY Ending March 31,
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Total Interest 87.9207.
3
187.
4
167.
5
147.
7
127.
8
108.
088.2 68.4 48.6 28.5
PBDT102.
8
247.
0
249.
8
252.
7
255.
6
258.
6
261.
7
264.
9
268.
1
271.
4
276.
3
Depreciation 45.5109.
2
109.
2
109.
2
109.
2
109.
2
109.
2
109.
2
109.
2
109.
2
109.
2
PBT 57.3137.
8
140.
6
143.
5
146.
4
149.
4
152.
5
155.
6
158.
8
162.
2
167.
1
Total Tax 19.0 45.8 46.7 47.7 48.6 49.6 50.6 51.7 52.8 53.9 55.5
PAT 38.3 92.0 93.9 95.8 97.8 99.8101.
8
103.
9
106.
1
108.
3
111.
6
PBDIT/Total Revenue
48.5
%
46.2
%
44.6
%
42.9
%
41.2
%
39.5
%
37.7
%
36.0
%
34.2
%
32.5
%
30.8
%
PBT/Total Revenue
14.6
%
14.0
%
14.3
%
14.6
%
15.0
%
15.3
%
15.6
%
15.9
%
16.2
%
16.5
%
16.9
%
PAT /Total Revenue
9.7% 9.4% 9.6% 9.8%10.0
%
10.2
%
10.4
%
10.6
%
10.8
%
11.0
%
11.3
%
Annual DSCR 2.12 1.35 1.38 1.41 1.44 1.48 1.53 1.58 1.64 1.72 1.66
Average DSCR
1.51
Minimum DSCR
1.35
Project IRR15.0
%
From the above financial projections it may be observed that the
Project is financially viable with a Project IRR of around 15.0%. It may
also be noted that the average DSCR for the Project debt is 1.51 while
minimum DSCR is 1.35. The DSCR levels of the Project are satisfactory.
7.2 Sensitivity Analysis
As discussed in Chapter 4, BHL has initialled a Draft PPA with UPPCL for
Strictly Private & Confidential 73
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
sale of 90% of the net saleable power from the Project. Tariff as per
the PPA shall be determined on cost-plus basis i.e. all
proportionate operating and financing charges shall be
recovered from UPPCL. Any increase in the operating/financing
charges will be recovered through a corresponding increase in
tariff.
However, the impact of variation in key operating assumptions on
DSCR/PIRR has been studied by assuming that the adverse deviations
in operating/financing charges will not be recovered through an
increase in tariff. The results of the sensitivity analysis are given
below:
Table 39: Sensitivity AnalysisAverage
DSCRMinimum DSCR
PIRR
Base Case 1.51 1.35 15.00%
Case 1: Reduction in PLF by 5%
1.42 1.28 13.82%
Case 2: Increase in O&M Cost by 10%
1.49 1.34 14.63%
Case 3: Increase in Station Heat Rate (SHR) by 100 Kcal/Kwh
1.45 1.31 14.17%
Case 4: Increase in Interest Rate by 1% p.a.
1.46 1.29 15.00%
As seen above, the Project is able to withstand various adverse
deviations in the operating assumptions and its debt servicing capacity
is satisfactory.
Strictly Private & Confidential 74
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
8 Status of Approvals and Clearances
Status of some of the major statutory/ regulatory approvals and
clearances for the Project are as under:
Table 40: Status of Approvals and ClearancesSr. No.
Type Of Clearance/ Approval
Authority/Entity Remarks
1. Land Acquisition and Availability
BHL/BHSIL Project is being set up on the surplus land available in the premises of existing sugar plants of BHL and its subsidiary, BHSIL. BEPL has already demarcated around 104 acres of land required at various project sites. BHL/BHSIL shall transfer the demarcated parcels of land to BEPL at the state notified circle rate for industrial land. BHL/BHSIL are in the process of obtaining requisite approvals/NoCs from the lenders. All NoCs shall be obtained and land shall be transferred in the name of BEPL before seeking first disbursement from the Lenders.
2. Pollution Control Board Clearance
Uttar Pradesh Pollution Control Board (UPPCB)
BHL has already applied for NoC from UPPCB vide letter dated 7th December, 2009.
3. Environment Clearance
State Level Expert Appraisal Committee
BHL has applied for the Environment Clearance to State Level Expert Appraisal Committee (SEAC), GoUP vide letter no. BHSIL/02/SEAC/09 dated 12th
Strictly Private & Confidential 75
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Sr. No.
Type Of Clearance/ Approval
Authority/Entity Remarks
November, 2009. The Terms of Reference (TOR) have been received. EIA study and EMP have been submitted to UPPCB and request for public hearing has been made vide letter dated 5.04.2010.
4. Coal Linkage MoC As informed by the Company, BHL understands that it has been granted long term coal linkage for the project vide SLC-LT meeting held on April 08, 2010.
5. Defence Clearance
Ministry of Defence (MoD)
The power plants at respective sites do not have any defence establishment/ land with in 15 kilometres of radius. Hence, defence clearance is not required from MoD.
6. Civil Aviation Clearance for Chimney Height
Airport Authority of India (AAI)
BHL has applied for a ‘No Objection Certificate’ from AAI vide letter dated March 30, 2010.
7. Rehabilitation and Resettlement (R&R)
GoUP The plant is being set up on the land available in the premises of existing sugar plants of BHL and its subsidiary, BHSIL. Hence no R&R is required.
8. Forest Clearance Ministry of Environment and Forest (MoEF), Government of India/State
No Forest land is involved in the development of Project. Hence Forest Clearance is not required.
Strictly Private & Confidential 76
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Sr. No.
Type Of Clearance/ Approval
Authority/Entity Remarks
Government9. Water Linkage Central Ground
Water Authority (CWGA), GoI/ CWGB, Northern region, Lucknow
For the total requirement of 34920 m³/day (6984 m³/ day per site) water per annum, final approval from has been obtained for the drawl of the required ground water vide letter dated 4.02.2010.
Strictly Private & Confidential 77
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
9 Risk Analysis
9.1 Risk Analysis – Allocation & Mitigation
Table 41: Risk AnalysisRisk Factor Allocated
ToProposed Mitigation Mechanism
Management RiskImplementation Capability & Experience
BEPL/ BHL The group is the largest sugar and ethanol manufacturer in India and has displayed excellent project executions skills in the past. The group has commissioned 11 Greenfield and integrated sugar plants with aggregate capacity of 1,06,000 TCD. The group has commissioned most of these projects much ahead of the schedules and created a benchmark in the industry. The group has also implemented various co-generation power projects at its existing sugar manufacturing facilities. The group is already operating co-gen power plants aggregating a capacity of around 428 MW. The group has mobilized an experienced and reliable team of personnel with requisite skills. The Company would be able to leverage the vast experience of the group in the execution of various larger size projects.
Pre-Completion RisksConstruction Risk
BEPL / BIDCO/ BTG Contractor/ Other Contractors
BHL has retained BIDCO as the overall co-ordinator for the implementation of the Project. BIDCO has awarded contracts to ThyssenKrupp Industries India (for 3 Boilers), Thermax Limited (for 2 Boilers) and Siemens Limited (for all 5 Steam Turbine & Generator package) on fixed price and fixed time basis. The contracts provide for adequate liquidated damages (LD)
Strictly Private & Confidential 78
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Risk Factor Allocated To
Proposed Mitigation Mechanism
provisions in case of delay in implementation and for plant’s various performance parameters. Contracts for civil works have also been awarded to reputed contractors with similar LD provisions.
The group has implemented various small size co-gen power projects of aggregate capacity of around 428 MW power project.
BIDCO shall also appoint an Owner’s Engineer to bring in requisite expertise in various aspects of project supervision, management services and overall wrapping of project packages in order to deliver the performance as per the norms set out.
The Project is in advanced stage of development with a balance gestation period of around 17 months.
Sponsor Risk BHL/Group Promoters
An amount of Rs. 438 crores has already been spent by BHL and Promoter Group on the Project, out of total equity requirement of Rs. 580 crore. BHL and Group Promoters have sufficient resources to contribute the requisite equity for the Project.
Land Availability BEPL The plant is being set up on the surplus land available in the premises of BHL’s existing sugar plants and its subsidiary, BHSIL. The Company has already identified land required for the Project and BHL and BHSIL have initiated the process of transfer/assignment of land and obtaining NoCs from various lenders.
Cost and Time Over-run
Contractors/ BEPL/ BHL
The group has extensive experience of successfully implementing large projects in
Strictly Private & Confidential 79
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Risk Factor Allocated To
Proposed Mitigation Mechanism
the past. Further, BIDCO has awarded BTG contract to ThyssenKrupp Industries India (for 3 Boilers), Thermax Limited (for 2 Boilers) and Siemens Limited (for all 5 Steam Turbine & Generator package) on fixed price and fixed time basis. The contracts provide for strict Liquidated Damages provisions in case of delay in implementation and deviation from performance parameters.
The cost estimates for the Project, have been broadly arrived based on the awarded contracts and the estimates of the technical consultant.
Further, a contingency provision of 3% of the total Hard Cost has been considered in the Project Cost.
Further, any cost overrun shall be funded by BHL from its own sources.
Post-Completion RisksEnvironmental Risks
BEPL The Terms of Reference (ToR) for undertaking the EIA study have already been approved by State Level Expert Appraisal Committee, GoUP. EIA study and EMP have been submitted to UPPCB and request for public hearing has been made vide letter dated 5.04.2010.
Water Availability
BEPL For the total requirement of 34920 m³/day (6984 m³/ day per site) water per annum, final approval from Central Ground Water Authority, GoI has been obtained for the drawl of the required ground water.
Fuel Supply BEPL/ BHL/MoC/ CIL
As informed by BHL, it has been granted coal linkage in Standing Linkage Committee (Long-term) [SLC (LT)] meeting held on April 8, 2010.
Strictly Private & Confidential 80
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Risk Factor Allocated To
Proposed Mitigation Mechanism
The linkage is expected to be granted from NCL mines near Singrauli, Madhya Pradesh.
Coal Transportation
BEPL For supply of coal from the allotted mines, under long term coal linkage, coal would be transported through Indian Railways rail network and by road. All the project sites are well connected through road and rail network.
Fuel Price BEPL Fuel pricing under the long-term linkage of from CIL/NCL will be subject to price variations on account of change in government notified prices though the historical rise in price of Linkage coal has been gradual.
Also, fluctuation in the price of secondary fuel shall impact the operating cost structure of BEPL. However, this is a very small component of the total operating costs.
However, as per the draft PPA initialled by UPPCL and BHL, delivered fuel cost (both primary and secondary) including ex-mine price and transportation cost shall be a pass-through in tariff. This will ensure that the profitability and debt servicing capability of the Project remain robust.
To assess the viability and debt servicing capability of the Project, 2.5% p.a. escalation has been considered in the fuel price in line with past trends in coal prices.
Evacuation Risks BEPL The power would be evacuated by using the existing 132 KV transmission line at four out of the five project sites. Further, the
Strictly Private & Confidential 81
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Risk Factor Allocated To
Proposed Mitigation Mechanism
evacuation network is being augmented and strengthened suitably for which Cost has been provided for in the Project cost. UPPCL sub-stations are located within 15-25 km from these sites. For Utraula, UPPCL sub-station is being constructed within the premises of the existing sugar unit for which land has already been provided to UPPCL.
Market RiskOff Take Risk UPPCL/
others BHL has already initialled the
Draft Power Purchase Agreement with UPPCL for sale of 90% of the net power produced on long term basis for 25 years. Final PPA is expected to be signed soon.
Balance 10% power from the Project would be sold on merchant basis. The tariff considered for merchant sale is reasonable and in line with the long term tariff derived as per UPERC guidelines and the Company would be in position to sell the entire power given the power deficit stage in the state of Uttar Pradesh.
Payment Risk UPPCL/ Other Off-takers
The Company proposes to sell 90% of the net saleable energy to UPPCL on long term Take or Pay basis. The draft PPA initialled by BHL and UPPCL provides for a strong payment security mechanism in the form of Letter of Credit and Escrow Account to secure the payments from UPPCL.
The balance power from the Project would also be sold against adequate payment security.
Technology RiskPlant BTG The BTG package has been
Strictly Private & Confidential 82
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Risk Factor Allocated To
Proposed Mitigation Mechanism
Performance Contractor /BIDCO
awarded to ThyssenKrupp Industries India (for 3 Boilers), Thermax Limited (for 2 Boilers) and Siemens Limited (for all 5 Steam Turbine & Generator package) through the appointed Project Management Consultant, BIDCO.
The aforesaid companies have an established track record of manufacturing and installing power equipment for 45 MW size units.
Back to back contracts awarded by BIDCO to the aforesaid contractors provide for stringent Performance Tests and in case of performance below the stipulated parameters, the suppliers will be required to pay liquidated damages.
The O&M shall be carried out by BEPL in-house with the support of its technical team of experts. Adequate level of stocks of spare parts would be maintained as per the recommendations of BIDCO/ Equipment Suppliers. The group has an established track record of operating and maintaining the existing units of power plants of aggregate capacity of 428 MW on bagasse technology.
Force Majeure BEPL / Insurers
BHL proposes to take out a comprehensive insurance policy package during the construction/ operations period for the Project for insurable Force Majeure events.
Financial RiskInterest Rate BEPL Interest on project loan will be
allowed as a pass-through expense in the tariff to be
Strictly Private & Confidential 83
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Risk Factor Allocated To
Proposed Mitigation Mechanism
approved by UPERC; Sensitivity has been carried out at
interest rate of 12% p.a. against base case rate of 11.50% p.a., and holding revenues constant, and the financials and DSCR are found to be comfortable.
Strictly Private & Confidential 84
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
10 Conclusion
BEPL proposes to set-up 450 MW Coal fired Thermal Power Project in
the premises of five (5) existing sugar units of BHL and BHSIL. Salient
features of the proposed Project are as under:
Credible Promoters: Bajaj Hindusthan Limited (BHL) is the largest
sugar and ethanol manufacturer of India with robust business
operations and adequate financial strength. Additionally, BHL has
successfully set up various green field projects including sugar units
and co-generation power plants across Uttar Pradesh and has vast
experience in such projects.
Significant progress in project development activities as
under:
BHL has already spent around Rs. 438 crore on the Project. The
Project is in advanced stage of implementation and is expected
to commence commercial operations on 1st November, 2010.
Entire land requirement to be met through the surplus land
available in the premises of sugar units of BHL and BHSIL. Land
parcels have already been identified and site development work
has already commenced;
Contract for Boiler, Turbine & Generator has already been
awarded to ThyssenKrupp Industries India (for 3 Boilers),
Thermax Limited (for 2 Boilers) and Siemens Limited (for all 5
Steam Turbine & Generator package);
Contract for Engineering services and Civil Works has already
been awarded to Powertech Engineering (P) Limited, Toshiba
Plant Systems & Services Corporation India Private Limited, KK
Construction & Builders, ERA Building Systems Limited and
Strictly Private & Confidential 85
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Petron Civil Engineering (P) Limited.
Ministry of Coal has granted long term coal linkage to the Project
in the SLC-LT meeting held on 8th April, 2010. Coal is expected to
be provided from the mines of Northern Coalfields Limited in
Madhya Pradesh.
Draft Power Purchase Agreement for sale of 90% of the net
power produced from the Project has been initialled by BHL and
UPPCL. Power to be procured on cost-plus tariff, determined in
accordance with the UPERC tariff determination guidelines.
Power to be evacuated through the already existing 132 KV
transmission line at four out of the five project sites to different
UPPCL sub-stations located 15-20 km from the respective sites.
Final approval to draw the requisite quantity of ground water for
all the five sites has been obtained from Central Ground Water
Authority, GoI.
BHL has already applied for all major statutory clearances/
approvals required for the Project. EIA study and EMP already
submitted to Uttar Pradesh Pollution Control Board for conduct of
public hearing and subsequent grant of Environment Clearance
for the Project.
This Information Memorandum analyzes the project development
structure and projected financial performance of the Project as per
information provided by BHL. The Base Case business projections have
been prepared based on the information pertaining to the project cost,
financing plan, regulatory environment and prevalent market
conditions. Sensitivity analysis has also been carried out to test the
robustness of project financials in respect of DSCR and PIRR. The
projected financials of the project as required to service the project
debt over proposed tenor are reasonably comfortable under different
sensitivity scenarios.
Strictly Private & Confidential 86
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Based on the projected financials, sensitivity analysis and risks factors,
the proposed Project may be viewed as financially viable.
11 Indicative Term Sheet
11.1 Indicative Terms and Conditions – Rupee Term Loan
1. Borrower Bajaj Energy Private Limited (BEPL)
2. Project
2 X 45 MW Thermal Power Projects at 5
separate locations viz. Barkhera (district:
Pilibhit), Khambarkhera (district: Lakhimpuri
Kheri), Maqsudapur (district: Shajhanpur),
Kundarkhi (district: Gonda), Utraula (district:
Balrampur), in the state of Uttar Pradesh,
aggregating to a total capacity 0f 450 MW.
3. Sponsor Bajaj Hindusthan Limited/ Promoter Group
4. Lenders
Indian Banks/ Institutions, collectively the
“Lenders”, who are participating in funding the
Project by way of Rupee Term Loan.
5.Facility Agent/Lead
Bank
State Bank of India
(subject to approval of the Lenders)
6. Project Cost Rs 2,320 crore
7. Debt Equity Ratio 75:25
8. Means of Finance
The cost of the project is proposed to be
funded at a Debt Equity Ratio of 3:1 as under:
Rupee Term Loan: Rs.1740 Cr
Sponsor’s Contribution/ Equity : Rs.580 Cr
9. Upfront Equity60% of the total equity contribution for the
Project
10. Facility Rupee Term Loan of Rs. 1740 crore and
Sub Limit:
Strictly Private & Confidential 87
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
100% of the sanctioned rupee loan by way of
Letter of Credit (LC) as a sub limit of the Rupee
Term Loan.
11.Purpose of the
Facility
The proceeds of the Facility will be utilized
towards the following:
1. Funding of the Project Cost;
2. Repayment of bridge loans, if any, availed
to meet the ongoing capital expenditure
pending disbursement of Rupee Term Loan.
12. Availability PeriodThe availability period for the Facility shall be
up to six (6) months from the CoD.
13. Validity PeriodThe sanction terms shall be valid up to a period
of six (6) months from the date of sanction.
14.Financial Closure
DateDate of signing of Facility Agreement.
15. First Disbursement
First Disbursement shall mean the earlier of:
1. First Drawdown under the Rupee Term
Loan;
2. Opening of LC under the Facility.
16.
Commercial
Operation Date
(CoD)
CoD shall be the earlier of the following:
1. November 01, 2011;
2. Actual commercial operations date of the
last unit of the Project as certified by the
Lenders’ Independent Engineer (LIE).
17. Door to Door Tenor
Upto 12 years (Construction Period plus
Moratorium of 6 months and Repayment period
of 10 years)
18. MoratoriumMoratorium period of six (6) months from the
CoD.
19. RepaymentPrincipal repayment in forty equated quarterly
instalments post Moratorium.
Strictly Private & Confidential 88
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
20.
(i) Interest Rate on
Rupee Term Loan
(ii) LC Charges
The Borrower shall pay the interest on the
outstanding principal amount of the Rupee
Term Loan at the end of every month to the
Lenders as under :
State Bank Advance Rate (SBAR) minus a
Spread of 0.25%, present effective being
11.50% p.a., floating, payable monthly.
Interest Rate shall be suitably adjusted in
accordance to the Base Rate Provisions, as and
when applicable to the Rupee Term Loan as
per the provisions to be introduced by the
Reserve Bank of India.
LC charges shall be decided mutually with the
Lenders at the time of opening of LC.
21. Interest Reset Date
Lenders would have the option to reset the
Spread on CoD and at annual intervals
thereafter, such date(s) being called the
Interest Reset Date(s).
Between two consecutive Interest Reset Dates,
the Spread would remain constant and SBAR
would be floating.
Facility Agent would advise the Borrower about
the reset of Interest Rate 30 days prior to each
Interest Reset Date.
22.Interest Tax, Levies
& Duties
Interest tax / other levies / duties, if any,
applicable as per Facility Agreement, shall be
payable by the Borrower over and above the
Interest Rate mentioned above.
23. Up-front Fees 0.25% of the Rupee Term Loan, payable at the
Strictly Private & Confidential 89
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
time of signing of Facility Agreement.
24. Commitment Fee
1.20% p.a. on the undrawn amount with
respect to the quarterly Drawdown Schedule
provided by the Borrower on Financial Closure
Date with flexibility to amend/revise/replace
the Drawdown Schedule with fifteen (15) days
written notice by the Borrower to the Facility
Agent prior to beginning of each quarter.
Commitment Fee shall not be payable in case
of such amendments or replacement.
25.Pre-Payment
penalty
2% of the amount pre-paid. No pre-payment
penalty, however, shall be payable if the pre-
payment is effected in any of the following
events:
a. At the instance of the Lenders;
b. From surplus cash accruals generated by
the Project,
c. On Interest Reset Date, the Borrower
shall have the option to prepay the
outstanding Rupee Term Loan by
advising its intention to prepay with an
advance written notice of 15 days and
prepay the Rupee Term Loan within 4
months from Interest Reset Date;
26.
Liquidated
damages on
defaulted
payments
2% p.a. for the period of default on the
outstanding amount in respect of Principal &
interest, up-front fees or any other monies
specified in the Facility Agreement due on their
respective due dates.
27. Security The Rupee Term Loan alongwith interest, fees,
commission and other monies in respect
thereof and Working Capital Limits, to the
extent assessed and revised from time to time,
Strictly Private & Confidential 90
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
shall be secured by way of:
a) Security to be created prior to the First
Disbursement:
1) First pari-passu charge by way of
hypothecation of all the movable assets
including, but not limited to plant &
machinery, machinery spares, tools &
accessories of the Project;
2) First pari-passu charge on all the bank
accounts of the Project including but not
limited to the Trust & Retention Account
(TRA) and Debt Service Reserve Account
(DSRA).
3) First pari-passu charge on book debts,
operating cash flows, commissions,
revenues of whatsoever nature and
wherever arising, present and future,
intangibles, goodwill, uncalled capital,
present and future relating to the Project;
4) First pari-passu charge on other Current
Assets of the Project;
b) Security to be created within six months
from the date of First Disbursement:
1) First pari-passu charge by way of
mortgage and charge over all immovable
assets (including mortgage of leasehold
rights in case of leasehold land, if any) of
the Project;
2) Assignment by way of security of all
rights, titles and interests of the Borrower
in, to and under all project documents,
Strictly Private & Confidential 91
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
contracts, insurance policies, permits /
approvals etc. to which the Borrower is a
party and which can be legally assigned
related to the Project.
28. Collateral
Pledge of 51% of the fully paid-up equity
shares of BEPL by the Sponsor, at all times
during the currency of the Rupee Term Loan in
favour of the Lenders. The pledgor to ensure
that the voting rights of the pledged shares do
not fall below 51%.
Pledge of shares shall be created on the
Financial Closure Date.
29. Undertaking by BHL
BHL shall provide Undertaking backed by
Board Resolution for the following purposes:
1) Infuse sufficient money in the Borrower, in
case of any shortfall in equity, in a manner
and form to the satisfaction of the Lenders;
2) That the completion cost of the Project
shall not exceed the Project Cost indicated
above and in case of any cost over-run, the
same shall be met by BHL through
additional equity contribution /
subordinated debt from BHL or loans
arranged by BHL without recourse to the
Security and Collateral, in a manner and
form to the satisfaction of the Lenders.
30. Additional interest The Borrower shall create the security as per
Clause 27 (b) within six (6) months from the
date of First Disbursement. If the Borrower fails
to create the security within six (6) months
from the date of First Disbursement, the
Borrower shall pay an additional interest of 1%
p.a. on the entire outstanding Rupee Term
Strictly Private & Confidential 92
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Loan amount from 1st day of the seventh (7th)
month from the date of first disbursement till
creation of security. Any further disbursements
pending perfection of security shall be at the
sole discretion of the Lenders.
31.Financial
Covenants
Starting from first full year of operations post
CoD, for any adverse deviation of any two out
of the first three covenants i), ii) and iii)
indicated below by more than 10% from the
levels stipulated hereunder and any deviation
in covenant iv) stipulated hereunder, Penal
Interest of 1% p.a. will be levied for the period
of non-adherence, subject to a minimum period
of one year. The measurement of deviation
shall be once a year with reference to the last
annual audited financial statements.
(i) Current Ratio of 1.33 (never below 1.20) ;
(ii) Total Outstanding Liabilities* / Tangible Net
Worth** of 3.20 (never above 3.50);
(iii) Security Margin*** of 20% (never below
18%);
(iv) DSCR of 1.15
* Total Outstanding Liabilities = (Secured
Loans + Unsecured Loans + Current Liabilities
& Provisions + Advance Against Depreciation)
** Tangible Net Worth = (Paid up capital +
Reserves and Surplus (excluding Revaluation
reserve) + Net Deferred Tax Liability –
Intangible Assets)
*** Security Margin = (1- Outstanding Rupee
Term Loan/ Net Fixed Assets)
Strictly Private & Confidential 93
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
32. Pre-Commitment
conditions
The Borrower agrees as under:
1) The Borrower shall have received sanctions
for the entire Rupee Term Loan;
2) To finalise the exact shareholding/equity
contribution pattern by the Sponsor in the
Borrower;
3) The Borrower/BHL shall have received
Letter of Assurance from Ministry of Coal for
the coal required for the Project.
4) Undertake to bring in the entire equity
requirement for the Project in a timely
manner;
5) Provide an undertaking that the completion
cost of the Project shall not exceed the
Project Cost indicated above and in case of
any cost over-run, the same shall be met by
BHL through additional equity contribution /
subordinated debt from BHL or loans
arranged by BHL without recourse to Project
assets, in a manner and to the satisfaction
of the Lenders;
6) Agree for appointment of Lenders’
Independent Engineer (LIE), Lenders’ Legal
Counsel (LLC) and Lenders’ Insurance
Advisor (LIA) and any other agencies as
may be necessary for review and
monitoring of the Project. The Borrower
shall also agree to bear the expenditure
incurred for availing the services of these
agencies;
7) Agree to prepare a schedule for award of
Project contracts adhering to or improving
upon the envisaged implementation
Strictly Private & Confidential 94
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
schedule for the Project ;
8) That the Lenders reserves the right to
withhold disbursement of the amount of
loan equivalent to the provision against
margin money for working capital in the
cost of the Project till such time as the
Project is near completion and the build up
of the working capital commences;
9) That the Lenders shall reserve the right to
review the cost of the Project and means of
finance anytime during construction period
of the Project and stipulate relevant
conditions, as deemed necessary;
10) That the preliminary and preoperative
expenses shall be allowed as part of the
Project cost only to the extent they are
certified by the LIE / LLC/ Statutory
Auditor/Other agency as relating to the
Project and as accepted by the Lenders;
11) Agree to make suitable arrangements
for project management/ O&M during
implementation and operation of the
Project;
12) Agree to modify its Memorandum of
Association and Articles of Association, for
enhancement of the authorized share
capital and borrowing power as per the
envisaged financing plan, if required, and
incorporate any other changes as may be
required by the Lenders;
13) Ensure that the expenditure on the
Project is as per schedule and in case of any
savings in the expenditure on account of
Strictly Private & Confidential 95
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
change in duties/other taxes and / or price
negotiations, the Lenders shall have the
right to cancel their Rupee Term Loan in the
proportion mentioned under Financing plan;
14) That the Lenders shall be entitled to
appoint one (1) nominee on behalf of all the
Lenders on the Board of the Borrower on
occurrence of an Event of Default;
15) Undertake to open a Trust and Retention
Account (TRA) to the satisfaction of the
Lenders through which all the Project cash
flows (including during construction period)
would flow and maintain a Debt Service
Reserve Account (DSRA) in the TRA for the
ensuing 3 months principal and interest
payment due to the Lenders from the cash
flows available after meeting debt service
obligations during the operational phase.
DSRA should be topped-up to the required
level within 6 months from CoD. The
Borrower will have one-time option to
provide a letter of credit/ bank guarantee
without recourse to project assets and as
acceptable to Lenders, for an amount
equivalent to ensuing 3 months principal
and interest payment to the Lenders, in lieu
of cash funded DSRA. No grace period will
be allowed for build-up of requisite amount
in DSRA if letter of credit/bank guarantee is
provided in lieu of cash funded DSRA.
The amounts accumulated in the DSRA
would be utilized only in case of a shortfall
in cash flows for meeting debt service
Strictly Private & Confidential 96
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
requirements from time to time. The
Borrower shall invest the funds in DSRA only
in permitted investments and securities as
approved by Lenders. No dividend
distribution will be permitted until the DSRA
requirement is fulfilled.
16) To obtain rating by an external credit
rating agency for the Facility with-in three
(3) months from Financial Closure Date.
33. Conditions
Precedent to First
Disbursement
Prior to first disbursement under the Facility,
the Borrower/BHL, as the case may be, shall, to
the satisfaction of the Lenders, have complied
with the following:
1) 60% of the total equity required for the
Project shall have been spent on the
Project;
2) The Borrower/BHL shall have firmed up
power sale arrangements for at least 90%
of the Project capacity by entering into a
long term Power Purchase Agreement with
UPPCL with suitable payment security
mechanism;
3) Acquire/lease the requisite land for the
Project to the satisfaction of the Lenders.
4) Execute contract for BTG and major civil
contracts and display readiness to award
other major contracts;
5) Initiate steps to make necessary
arrangements for transportation of
requisite quantity of coal to the Project
site;
6) Obtain critical statutory clearances
required for implementation of the Project,
Strictly Private & Confidential 97
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
as certified by Lenders Independent
Engineer (LIE), including NOC from State
Pollution Control Board and Environmental
Clearance from State Level Expert
Appraisal Committee and agree to comply
with all the conditions of these clearances.
7) To appoint Lenders Independent Engineer
(LIE) on the terms which would include
review of project cost, review of project
agreements/contracts/clearances, and pre-
construction due-diligence, monitoring of
construction and performance, testing, CoD
and monitoring of operations post CoD.
8) Arrange to review the water availability,
sourcing plans, etc. by LIE and accordingly
have a firm allocation from concerned state
government department for the same;
9) To demonstrate that actions have been
initiated for arrangement of evacuation
facilities for entire power generated from
the Project;;
10) Appoint Lenders’ Legal Counsel (LLC)
and Lenders’ Insurance Advisor (LIA) and
any other agencies as may be deemed
necessary for review and monitoring of the
Project. The Borrower shall also agree to
bear the expenditure incurred for availing
the services of these agencies;
11) To ensure that the concerns raised by
LIE/LLC in regard to key contracts required
for the implementation of the Project are
adequately addressed to satisfaction of the
lenders.
Strictly Private & Confidential 98
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
12) Make a plan for obtaining necessary
right of way and/or acquisition of land, if
any, for laying of water pipeline, if
required, and power transmission line to
inter-connection point in line with the
commissioning schedule of the project (to
be reviewed by the LIE);
13) Prepare a schedule for award of Project
contracts adhering to or improving upon
the envisaged; implementation schedule
for the Project (to be reviewed by LIE);
14) Open a Trust & Retention Account (TRA)
into which the Borrower shall deposit all its
cash inflows from the Project to be utilized/
applied in a manner and priority to be
stipulated in the TRA Agreement. For this
purpose, the Borrower shall have to
appoint an acceptable bank/institution as a
Trust and Retention Agent and enter into a
Trust and Retention Agreement;
15) To appoint Owner’s Engineer for
monitoring of project implementation to
the satisfaction of Lenders / LIE;
16) Undertake that all the inter-group
transactions relating to the Project are not
prejudicial to the interest of BEPL and
appropriately disclosed;
17) Fully insure the Borrower’s assets,
offered as security for the Facility, against
fire and all such other risks as may be
required by the Lenders/ LIA and the
policies retained by the Borrower. Ensure
that requisite insurance policies have been
Strictly Private & Confidential 99
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
suitable endorsed in favour of the Lenders
which should contain the Lenders’ Security
Stipulation and name the Lenders as loss
payees. A copy of this policy should be
submitted to the Lenders/ LIA for review. A
list of the current insurance policies should
be submitted to the Lenders detailing
therein the names and addresses of the
insurer, brief particulars of goods covered,
type of cover, amount of cover and date of
expiry of each policy.
18) To ensure that Lenders shall have
received the final copies of the
construction schedule, organization chart,
copies and related contracts, the
construction budget and disbursement
schedule, in accordance with the Base case
business plan as agreed between Borrower
and the relevant contractors and duly
certified by LIE.
19) Furnish an undertaking that Borrower
and other contracted parties have
complied with the conditions precedent in
major project documents and in critical
statutory clearances/approvals of the
Project.
20) To ensure that all representations and
warranties which are made till the date of
first drawdown are true in all material
respects.
34. Conditions
Subsequent to First
Disbursement
1) Within 6 months of the date of First
Disbursement, the Borrower shall submit to
the Facility Agent/Security Trustee ‘No
Strictly Private & Confidential 100
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Objection Certificates’ from the existing
lenders of BHL/Bajaj Hindusthan Sugar and
Industries Ltd. (BHSIL) for the following:
a. Use of Land, transmission network
and other assets transferred/leased
by BHL/BHSIL to the Borrower;
b. Infusion of Equity by BHL in the
Borrower.
2) The Borrower shall execute the Fuel Supply
Agreement and Fuel Transportation
Agreement 6 months prior to the CoD and
the same shall be vetted by the LE/LLC and
the Borrower shall comply with their
observations, if any.
35. Negative
Covenants
During the currency of the Rupee Term Loan,
the Borrower shall not without prior approval of
the Lenders, which would not be withheld
unreasonably:
1) Effect any change in the capital structure
which results in the Long Term Debt to
Equity ratio exceeding 75:25;
2) Formulate and effect any scheme of
amalgamation or restructuring or
reconstruction;
3) Create any Security Interest over the
Project assets/ properties and contracts
other than those required to be created
under the Facility Agreement;
4) Undertake any new project either itself or
through any of its subsidiary(ies).
5) Augment, modernize, expand or otherwise
make material change in the scope of the
Strictly Private & Confidential 101
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Project;
6) Make any material modifications to Project
Contracts/ Agreements;
7) Enter into borrowing arrangements, either
secured or unsecured, with any other bank
or financial institution or undertake any
guarantee obligation on behalf of any other
borrower (including group companies). The
Borrower may however enter into
borrowing arrangements for refinancing
and for meeting its working capital
requirements and such additional financing
arranged to meet any cost overruns as
discussed in this Term Sheet.
8) Allow the following:
a. Dilution of equity holding of the
Sponsor in BEPL below 51%, and
b. Dilution of equity holding of Bajaj
Hindusthan Limited in BEPL below
26%.
36. Event of Default The Lenders may reserve the right to call up
the Facility by giving a notice of 30 days upon
the happening of any of the following events of
Default (each an “Event of Default”): –
1) Any instalment of principal amount or
interest on the Facility remaining unpaid
for a period exceeding thirty (30) days on
their respective due dates.
2) The Borrower committing any breach or
default in the performance or observance
of the material covenants of the Facility
Agreement and such breach or default
continues for a period of ninety (90) days
Strictly Private & Confidential 102
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
after receipt of a notice from the Lenders.
3) Execution or distress being enforced or
levied against the whole or any part of the
Borrower’s property and any order relating
thereto is not discharged or stayed within a
period of ninety (90) days from the date of
enforcement or levy.
4) The Borrower ceasing or threatening to
cease to carry on its business for a period
exceeding ninety (90) days.
5) A receiver being appointed in respect of
the whole or any part of the property of the
Borrower and such appointment is not
stayed, quashed or dismissed within a
period of ninety (90) days.
6) The occurrence of any event or
circumstance which is prejudicial to or
imperils or depreciates the security given
to the Lenders and such event or
circumstance continues to have an effect
for a period in excess of ninety (90) days.
37. Other Terms &
Conditions
1) In case of default in repayment of the
principal amount or payment of interest or
any other dues on due dates, the Lenders /
RBI / CIBIL shall have right to disclose
details of the default and/or other
information and the name of the Borrower
and of its directors as defaulters;
2) The Lenders acting through the Lead Bank
will have the right to examine the books of
accounts of the Borrower and to have the
Project site inspected from time to time by
officers of the Lenders and/or outside
Strictly Private & Confidential 103
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
auditors. Expenses incurred by the Bank in
this regard will be borne by the Borrower;
3) The Borrower shall ensure that, as required
by the Lenders, approvals and clearances
received in the name of Bajaj Hindusthan
Limited/Bajaj Hindusthan Sugar and
Industries Limited/any other entity shall be
transferred in the name of BEPL;
4) Rupee Term Loan will be disbursed after
each drawdown request is certified by the
LIE as being in consonance with the project
implementation schedule/status and by a
chartered accountant as being in
consonance with the expenditure incurred
on the Project.
5) The Borrower shall to the satisfaction of the
Lenders:
a. Obtain prior approval of the
Lenders for incurring and utilizing amount
of the loans equivalent to the contingency
provision in the Project cost. The
disbursement of the contingency provision
shall be based on LIE certification.
b. Maintain a Debt Service Reserve
Account (DSRA) in the TRA for the ensuing
3 months principal and interest payment
due to the Lenders from the cash flows
available after meeting debt service
obligations during the operational phase.
DSRA should be topped-up to the required
level within 6 months from CoD. The
Borrower will have one-time option to
provide a letter of credit/ bank guarantee
Strictly Private & Confidential 104
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
without recourse to project assets and as
acceptable to Lenders, for an amount
equivalent to ensuing 3 months principal
and interest payment to the Lenders, in
lieu of cash funded DSRA. No grace period
will be allowed for build-up of requisite
amount in DSRA if letter of credit/bank
guarantee is provided in lieu of cash
funded DSRA.
The amounts accumulated in the DSRA
would be utilized only in case of a shortfall
in cash flows for meeting debt service
requirements from time to time. The
Borrower shall invest the funds in DSRA
only in permitted investments and
securities as approved by Lenders. No
dividend distribution will be permitted
until the DSRA requirement is fulfilled.
c. Make satisfactory arrangements
for tie-up of the required working capital
facilities prior to start of commercial
operations;
d. Appoint technical, financial and
executive personnel of proper qualification
and experience for the key posts and
ensure that the organization set up is
adequate enough for smooth
implementation and operation of the
Project;
e. Undertake not to declare any
dividend during construction/ moratorium
period and that during the repayment
period of Rupee Term Loan, it shall not,
Strictly Private & Confidential 105
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
without obtaining prior consent of the
lenders declare any dividend on its share
capital in case; (i) During the Continuance
of an Event of Default, or (ii) if the DSRA is
not funded and /or arranged as required by
the Lenders;
f.Constitute a Project Management
Committee of Directors/Senior Executives
for the purpose of supervising and
monitoring the progress of implementation
of the Project. The committee shall be
responsible for the management of the
Project during construction period and
monitoring of the implementation of the
Project.
g. Constitute an Audit Sub-
committee of its Directors to the
satisfaction of Lenders for monitoring of
the company’s operations;
h. Furnish to the Lenders every year
a copy of audited annual accounts of the
Borrower immediately on finalisation of the
same but in any case not later than 180
days from the end of each relevant
accounting period;
i. Submit to the Lenders such financial
statements as may be required by the
Lenders from time to time, apart from the
set of such statements to be furnished by
the Borrower to the Lenders as on date of
publication of the company’s annual
accounts.
j. Provide regular progress reports on the
Strictly Private & Confidential 106
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Project both during construction and during
operation to the Lenders as may be
required by the Lenders;
k. Agree to broad-base its Board of
Directors with professional nominees and
strengthen its management set up to the
satisfaction of Lenders;
l. Permit the Lenders and their authorized
officers or employees to carry out
technical, financial and legal inspections of
the assets created out of the Facility and to
visit any facilities and construction sites
included in the Project and to examine any
plants, installations, sites, works, buildings,
properties, equipment, records and
documents relevant to the performance of
the obligations of Borrower under the
Facility agreement. Any such
representative of the Lenders shall have
access to Borrower’s properties upon
suitable prior notice and shall receive full
cooperation and assistance from the
employees of Borrower provided no
material disturbance will be caused to the
business and operations of Borrower.
m. Maintain adequate books of
accounts which should correctly reflect its
financial position and scale of operations
and should not radically change its
accounting system without prior notice to
the Lenders.
n. Keep the Lenders informed of the
happening of any event likely to have
Strictly Private & Confidential 107
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
substantial effect on its profit and business
with explanations and the remedial steps
proposed to be taken.
o. Keep the Lenders advised of any
circumstances adversely affecting the
financial position of their subsidiaries/group
companies or companies or in which it has
large investments, including any action
taken by the creditor against the said
companies legally or otherwise.
p. Increase its authorized share
capital in line with the envisaged means of
finance, if required.
38. Documentation
In addition to the terms and conditions
contained in this Term Sheet, the final
documentation will contain other customary
clauses such as Financial covenants,
Representation & Warranties from the
Borrower, Conditions Precedent to the
effectiveness of the loan and Condition
Precedent to each disbursement, Affirmative
Covenants by Borrower, Negative Covenants,
Additional Covenants, Information Covenants,
Events of Defaults by the Borrower and the
Consequences of the Event of Default, RBI
disclosure norms, as applicable etc.
Strictly Private & Confidential 108
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
12 Annexure
12.1 Annexure I: Historical Financials of BHL
Profit & Loss Statement
(Rs.Crore)
Year ending September 30, 2006 2007 2008 2009 INCOME
Sales1526.9
2 1841.2
2 1879.4
9 1655.75
Less: Excise Duty 79.68 128.21 123.21 72.02
Net Sales1,447.
24 1,713.
01 1,756.
28 1,583.7
4
Total Income (A)1,447.
24 1,713.
01 1,756.
28 1,583.7
4 EXPENDITURE
Raw Material Consumed951.45
1,283.42
1,390.33
816.76
Stores Consumed 53.34 108.81 75.99 35.46 Power & Fuel 9.88 12.79 18.23 14.98 Repairs & Maintenance 32.73 42.61 46.22 19.89 Manpower Cost 56.60 112.52 116.29 120.83 Rent 1.49 2.44 3.55 3.81
Strictly Private & Confidential 109
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
(Rs.Crore)
Year ending September 30, 2006 2007 2008 2009 Other Expenses 25.71 42.05 141.52 51.11 Selling & Distribution expenses
12.12 22.98 16.90 13.04
(Increase)/ Decrease in Stocks
(6.98)(132.4
1)(224.69
)143.73
Total Expenses (B)1,136.
33 1,495.
20 1,584.
33 1,219.6
0
EBITDA (A-B)310.9
1 217.8
1 171.95 364.13
Less: Interest on Term Loans, Debentures, Fixed Deposits
27.71 46.18 102.99 85.57
Interest Income 52.20 73.35
100.09
107.98
Less: Interest on Others9.29 38.52
47.27
115.84
Less: Interest on Working Capital Loans
11.81 47.24 65.97 81.34
Finance Charges 1.23 5.09 23.31 12.31
PBDT313.0
5 154.1
2 32.50 177.06
Less: Depreciation 72.39
146.88
187.22 202.21
Operating Profit240.6
6 7.24
(154.72)
(25.16)
Add: Other Income 39.51 30.65 46.59 231.16
PBT 280.
17 37.89
(108.13)
206.00
Less: Income Tax89.34
(7.81)
(60.44)
49.77
PAT190.8
3 45.70
(47.69)
156.23
Balance Sheet
(Rs.Crore)
As on September 30, 2006 2007 2008 2009 ASSETSFixed Assets Land & Building 261.71 550.04 643.13 724.94
Strictly Private & Confidential 110
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
(Rs.Crore)
As on September 30, 2006 2007 2008 2009
Plant & Machinery866.17
1895.26
2237.22 2507.8
9 Other Fixed Assets 157.46 193.96 176.03 174.65
Gross Block1,285.
34 2,639.
26 3,056.3
8 3,407.
48 Less: Depreciation 271.86 418.62 577.56 774.98
Net Fixed Assets 1,013
.48 2,220
.64 2,478.8
3 2,632.
50
Capital work in progress1,223.
08 562.97 138.69 131.28
Total Fixed Assets & CWIP (A) 2,236
.56 2,783.
61 2,617.5
2 2,763.
77
Investments (B)205.8
1 437.4
7 488.26 549.11
Current Assets Inventories
Raw Materials0.05
-
- 305.66
Work in progress -
-
- 0.40
Finished Goods 70.83 308.71 584.06 395.37 Stores & Spares 42.29 59.81 44.90 59.00 By products 9.21 26.31 8.28 40.02
Total Inventories122.3
9 394.8
3 637.24 800.45
Receivables Outstanding for more than six months (Net)
0.50 1.56 2.05 0.87
Other debts 61.36 108.44 40.25 27.70
Total Receivables61.86
110.00
42.30 28.57
Loans & Advances Advance Tax 59.47 80.10 99.45 110.21 Loans to Subsidiaries & Joint Venture
200.76 828.19 900.73 956.21
Others loans & advances274.06 586.99 806.03
1,026.63
Total Loans & Advances534.2
8 1,495.
28 1,806.2
1 2,093.
05 Cash & Bank Balance 223.31 108.95 39.73 112.36 Total Current Assets © 941.8 2,109. 2,525. 3,034.
Strictly Private & Confidential 111
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
(Rs.Crore)
As on September 30, 2006 2007 2008 2009 3 05 47 42
Total Assets (A+B+C)3,384.
21 5,330.
13 5,631.2
5 6,347.
30 LIABILITIESShare Capital Share Capital (Equity) 14.14 14.14 14.14 17.69 Equity Warrants - - - 18.90
General Reserve 276.
60 281.60 281.407 379.97
Other Reserves1,077.
93 1,138.
59 1,049.56
1,877.11
Total (D)1,368.
67 1,434.
33 1,345.1
1 2,293.
67 Current Liabilities & Provisions
Sundry Creditors 172.87 602.04 562.75 657.35 Bank Borrowings (Working Capital) 95.96 984.84 858.54 539.51
Other current liabilities9.168 22.5
47.74
25.68
Provisions197.46 259.49
207.64
187.42
Total Current Liabilities (E) 475
.45 1,868
.87 1,676.
67 1,409.
96 Long Term Liabilities Secured Loans
- From Fis/ Banks 330
.90 800
.54 1,377
.50 1345.8
7 - From others 13.31 0.50 7.05 56.35
- Debentures -
250.00
565.00
15.00
Unsecured Loans - From promoters - - - -
- From others 1,065
.92 855.0
1 600.
99 1,118.
42 Total Long Term Liabilities (F) 1,410 1,906 2,550. 2,535.
Strictly Private & Confidential 112
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
(Rs.Crore)
As on September 30, 2006 2007 2008 2009 .13 .05 53 64
Deferred Tax Liability/(Asset) (G)129.9
6 120.8
8 58.
94 108.04
Total Liabilities (D+E+F+G)3,384.
21 5,330.
13 5,631.2
5 6,347.
31
12.2 Annexure II: Detailed Banking Arrangement of BHL
S.NoFinancial Institutions/ Banks from which borrowed.
Loan Amount (Rs crore)
Sanctioned
Outstanding as on 31.12.2009
(A) Secured LoanNon Convertible Debentures
1. GIC 15.00 15.00Total Non Convertible Debentures (Total a) 15.00 15.00
Working Capital Loans 2. State Bank of India 750.00 400.66 3. State Bank of Patiala 100.00 90.43 4. Punjab National Bank 300.00 (30.55)5. HDFC 10.00 1.99 6. Oriental Bank of Commerce 150.00 50.70 7. IDBI 170.00 - 8. YES bank 50.00 - 9. Allahabad Bank 25.00 1.29
Total Working Capital Loan(Total b) 1,555.00 514.52
Term Loans from Banks 10. ECB Loan from BNP/ABN 309.64 479.3611. State Bank of Patiala Term Loans 150.88 17.9712. State Bank of India 390.25 90.2513. Punjab National Bank 37.87 37.8714. Oriental Bank of Commerce 20.00 20.0015. Yes bank 30.00 30.0016. IDBI 15.19 15.19
Term loans From Banks(Total c) 953.83 690.64
Strictly Private & Confidential 113
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
S.NoFinancial Institutions/ Banks from which borrowed.
Loan Amount (Rs crore)
Sanctioned
Outstanding as on 31.12.2009
Corporate Loans 17. Punjab National Bank 550.00 466.6718. Bank of Rajasthan 170.00 110.0019. Allahabad Bank 100.00 83.3420. Bank Of India 200.00 200.0021. Corporation Bank 200.00 200.0022. State Bank of Mysore 50.00 50.0023. State Bank of Hyderabad 50.00 50.0024. State Bank of India 300.00 300.00
Total Corporate Loans(Total d) 1,620.00 1,460.01
Term Loans from Others 25. Sugar Development Fund 123.77 70.04
Total Other Loans Others(Total e) 123.77 70.04Total Secured Loans (Total a to e) 4,267.59 2,750.21
(B) Unsecured Loan Deposits
26. Public Deposits 0.08 0.08Total Deposits (Total a) 0.08 0.08
Short Term Loan (STL)27. Central Bank of India 100.00 100.00
Total STL (Total b) 100.00 100.00
Mutual Funds & Others28. LIC Mutual Funds 400.00 400.0029. JP Morgan Assets Management 150.00 0.00
(Total c) 550.00 400.0030. FCCB 549.22 464.80
Total FCCB(Total d) 549.22 464.80Total Unsecured (Total a to d) 1,199.30 964.88Total Loan & Funds (Total A+ B) 5,466.89 3,715.09
Notes The sanctioned amount of FCCB is representing the FCCB of 119.50
million. Out of outstanding Foreign Currency Convertible Bonds (FCCBs) aggregating to US$ 119.50 million, FCCBs of the aggregate
Strictly Private & Confidential 114
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
face value of US$ 19.93 million were repurchased at discount and cancelled during the year 2008-2009.
The outstanding amount of FCCB is representing the FCCB of 99.57 million USD (119.50-19.93)
The difference in the sanctioned and outstanding amount of ECB is only due to the exchange fluctuation.
Strictly Private & Confidential 115
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
12.3 Annexure III: Project Implementation Schedule
Strictly Private & Confidential 116
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
12.4 Annexure IV: Key Assumptions
Particulars DetailsGeneral AssumptionsTotal Capacity of the
Project
450 MW (5 x 2 x 45 MW)
Schedule of
Implementation
CoD of the Project – 1st November, 2011
Phasing AssumptionsQuarterly Phasing of
ExpenditureQuarte
r Ending
%age of total
Expenditure
Mar-10 18.9%
Jun-10 11.0%
Sep-10 8.7%
Dec-10 18.3%
Mar-11 13.6%
Jun-11 8.3%
Sep-11 9.7%
Dec-11 11.5%
Total 100.0%
Operational & Technical DetailsCoal (Primary Fuel) GCV: 3865 Kcal/Kg
Price: Rs. 1880 per tonne as on 1st April, 2010
Escalated: @ 2.5% p.a. thereafter.
LDO (Secondary Fuel) Price: Rs. 24000 per kL as on 1st April, 2010.
Escalated: @ 3.0% p.a. thereafter
Consumption: 1 ml per KWh (UPERC)
Consumption: 0.3 ml per KWh (Actual)
Power Block Actual:
Station Heat Rate: 2675 kcal/KWh
Auxiliary Consumption: 10%
PLF: 80% in the first part-year of Operations
Strictly Private & Confidential 117
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Particulars Detailsand 85% thereafter for Plant Life.
UPERC Norms:
Station Heat Rate: 2675 kcal/KWh
Auxiliary Consumption: 10%
PLF: 80% in the first part-year of Operations
and 85% thereafter for Plant Life
O&M Expenses Actual: Rs. 12.0 Lacs per MW p.a. (for FY
2009-10) escalated at 5.72%
UPERC Norms: Rs. 18.2 Lacs per MW p.a. (for
FY 2009-10) escalated at 5.72%.
Working Capital Actual:
Margin Money: 25%
Interest on Working Capital: 11.75% p.a.
Coal Stock: 1.5 Months
Fuel Oil Stock: 1.5 Months
O&M Expenses: 1 Month
Spares: 20% of O&M Expenses
Receivables: 1.5 Months
For UPERC Tariff Calculation;
Coal Stock:2 Months
Fuel Oil Stock: 2 Months
O&M Expenses: 1 Month
Maintenance Spares: 20% of O&M Expenses
Receivables: 2 Months
Financing Related Assumption:
Debt : Equity Ratio 75:25
Upfront Equity 60%
Debt Related
Assumptions
Moratorium from CoD 6 Months
Strictly Private & Confidential 118
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Particulars Detailsof Project
Rate of Interest on
Rupee Term Loan (for
Projections purpose)
11.50% p.a.
Tariff Assumptions
Power Sale 405 MW (90% of Net Saleable Power) to
UPPCL at Regulated Tariff as per UPERC Tariff
Norms. Levelized tariff for 25 years works out
to Rs. 3.54/kwh.
45 MW (10% of Net Saleable Power) on
Merchant basis at Rs. 3.54/kwh in line with the
tariff for long-term PPA with UPPCL.
12.5 Annexure V: Award of Coal Linkage for the Project
Strictly Private & Confidential 119
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
12.6 Annexure VI: Brief profile of Contractors
Thermax (india) Limited
Thermax is an India based solution provider in energy and
engineering services for over 30 years. It has teamed up with
Babcock & Wilcox Power Generation Group, Inc. (B&W PGG), USA
Strictly Private & Confidential 120
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
under a technology license agreement for offering B&W’s Radiant
line of boilers for power utilities. These radiant boilers are the most
thoroughly field-tested and proven sub-critical power utility boiler in
the world.
Some contracts already contracted by Thermax includes Welspun
(43 MW), DCW (50 MW), Maral Overseas (10 MW), J K Laxmi Cements
(36 MW), CESC-RPG enterprise (40 MW), etc. Projects like Meenakshi
Energy Private Limited (270 MW), Brahmani Industries (60 MW),
Chemplast Sanmar – 50 MW, Jay Kay Cements – 50 MW, Madras
Cement Limited – 40 MW are still under execution.
Siemens India Limited
The Siemens Group in India is a unique player in the field of
electrical and electronics engineering with a business volume
aggregating about Rs 11,800 crores. The group’s business is
represented by various companies that span across three major
business segments of Industry, Energy and Healthcare. Siemens
Group in India comprises of 20 companies, providing direct
employment to over 17,200 persons. Currently, the group has 19
manufacturing plants, a wide network up of Sales and Service offices
across the country as well as over 500 channel partners.
Thyssenkrupp Industires India Pvt. Limited
ThyssenKrupp Industries India Pvt. Ltd. (TKII) in the last five decades
has grown to become one of the most trusted names in the fields of
Sugar Plants & Machinery, Open Cast Mining & Bulk Material
Handling Systems, Cement Plants & Machinery and Steam & Power
Generation Plants. The company's nationwide branch network along
with the support of ThyssenKrupp’s global establishments enables it
to meet the needs of customers on time. Few of the projects
Strictly Private & Confidential 121
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
executed by TKII in power generation are as follows:
Aditya Cement Limited: 2x25 MW Thermal power plant at
Chittorgarh Rajasthan
Ultratech Cement Limited: 2x25 MW Thermal power plant at
Tadipatri Andhra Pradesh
Tata Chemicals Limited (TCL): 1x50 MW Thermal Power plant
for TCL at Mithapur, Gujarat.
The India Cements Limited: 1x50 MW power plant for The India
Cement Limited at Sankarnagar, Tamil Nadu is under
execution
ANRAK Aluminium Limited: 2x75 MW thermal power plant at
Vishakapatnam, Andhra Pradesh is under execution
Mantech Technical Services Private Limited (MTSPL)
MTSPL is an engineering consultancy services and specializes in
project development and engineering services for the following
projects.
Coal based Thermal Power Projects,
Gas based Power Projects,
Renewable Energy Projects,
Waste to Energy Projects,
Desalination Projects.
Few of the projects completed by MTSPL are as under:
Construction Services for 46 MW Coal Fired CPP Project for
L&T Awarpur, Maharashtra
105 MW Diesel Based Power Project of Balaji Power
Corporation, Tamil Nadu
Lender Engineering Services for Vishnuprayag Hydro Power
Project, Uttar Pradesh - Electrical & Balance of plant
equipments and substation
Strictly Private & Confidential 122
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Installation of 2 X 210 MW steam turbine and auxiliaries at
Raichur Thermal Power Project, Karnataka.
Powertech Engineering Pvt. Limited (PEPL)
PEPL is a reputed engineering organizations with well established
credentials in the Indian Power Sector. PEPL has an Engineering
Consultancy practice as well as an Infrastructure and Management
Consultancy practice. The firm has so far executed more than 130
assignments under different categories of services such as Project
development (PD), Owners Engineer (OE), Detailed Engineering (DE),
etc. Few of the executed assignments by PEPL are as follows:
105.66 MW DG Based Project for Balaji Power Co. Pvt. Ltd in
Tamil Nadu
330 MW Combined Cycle IPP of PPN Power Generating Co. Pvt.
Ltd., in Tamil Nadu
330 MW Gas Based Combined Cycle Power Project for RRVUNL
at Dholpur, Rajasthan.
Petron Civil Engineering Pvt Limited (Petron)
Petron Civil Engineering Pvt. Ltd. is a privately held organization which
was formed in 1980. It is mainly involved in the civil construction works
in Industrial and Infrastructure Sector including Heavy Industrial
Construction in steel and concrete.
Few of the projects undertaken by Petron are as follows:
Thermal Power Plant, BHEL, Harduaganj, Uttar Pradesh
Thermal Power Plant, BHEL, Bhatinda, Punjab
Construction of Cement Plant for Madras Cement Ltd.,
Ariyalur, Tamil Nadu
Construction of Preheater, Gujarat Ambuja Cement Ltd.,
Darlaghat, Himachal Pradesh
Strictly Private & Confidential 123
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
ERA Building Systems Ltd (Era)
Era Building Systems Ltd. is an engineering, construction and services
conglomerate with operations across the entire spectrum of
infrastructure development including power transmission &
distribution. ERA has successfully completed projects across various
sector i.e Power, Highways, Railways, Airports, Urban Infrastructure,
Refineries, Industrial Complexes, Commercial and Office buildings, etc.
Few of the projects undertaken by Era are as follows:
For Thermax, 3 projects at Savali, Vadodara
Bajaj Ecotech, Sugar Mills at Paliakalan (U.P.)
Civil works, L & T, Hazira
Civil Works, Videocon, Kashipur
K.K Construction Builders (KKCB)
KKCB started its operations in 1991. The company’s core competency
is in civil structures interiors, plumbing, electrical working, housing
complexes, institutional projects, development work including
infrastructure with road and bridges and heavy steel fabrication.
Few of the projects executed by KKCB are as follows:
Development of 440 KVA sub-station, Uttar Pradesh Elecricity
Board, Gorakhpur, Uttar Pradesh
Construction of cooling towers, switch yard, control room and
township for 4x300 MW Rosa Thermal Power Project (Reliance
Energy Limited), Shahjahanpur, Uttar Pradesh
Civil works of 27 MW co-generation plant (BHL), at Budhana,
Uttar Pradesh
Strictly Private & Confidential 124
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Toshiba Plant Systems & Services Corporation India Private
Limited (TPSCI)
Toshiba Plant Systems & Services Corporation India Private Limited
(TPSCI) is Engineering, Procurement and Construction company under
the flagship of Toshiba Corporation, Japan which has been active in the
development of power projects for the last sixty six years. The
company’s focus and core competence has been on the power
projects.
TPSCI was registered in India in December, 1998 and is wholly owned
by Toshiba Plant Systems & Services Corporation (TPSC) to further
strengthen the business interest of Toshiba Corporation in the thermal,
combined cycle, diesel based, hydro-electric and non-conventional
energy power plants, in India, Middle East and the South East Asia.
TPSCI has full-fledged technical support and access to the database of
TPSC developed through the principal company’s long and rich
experience from projects executed across the globe.
Few of the projects executed by TPSCI are as follows:
2 x 500 MW Anpara ‘B’ Thermal Power Plant at Sonebhadra,
Uttar Pradesh
2 x 125 MW Hydel Power Station, Ghatghar, Maharashtra
3 x 170 MW Teesta Stage-V, Hydro Power Project, Sikkim
4 x 225 MW Hydro Electric Project, Purulia, West Bengal
172 Combined Cycle Power Project, Vijjesswaram, Andhra
Pradesh
4 x 10.5 MW Hydro Electric Project (Modernization and
Renovation), Umiam, Meghalaya
Strictly Private & Confidential 125
Bajaj Energy Private Ltd Project Information Memorandum 450
MW Power Project
Strictly Private & Confidential 126
Bajaj Energy Private Ltd Project Information Memorandum 450 MW Power Project
12.7 Annexure VII: Projected Financials of Project
DSCR Calculations
(Rs. Crores)
ParticularsMar-
12Mar-
13Mar-
14Mar-
15Mar-
16Mar-
17Mar-
18Mar-
19Mar-
20Mar-
21Mar-
22Interest Payments 81.5 190.1 170.1 150.1 130.1 110.1 90.0 70.0 50.0 30.0 10.0Loan Repayments - 174.0 174.0 174.0 174.0 174.0 174.0 174.0 174.0 174.0 174.0Total Debt Servicing Liability 81.5 364.1 344.1 324.1 304.1 284.1 264.0 244.0 224.0 204.0 184.0
PBDIT + AAD 190.7 536.3 519.2 502.2 485.3 468.5 451.7 435.0 418.5 402.0 357.1
Less: WC Interest 6.4 17.2 17.3 17.5 17.6 17.8 18.0 18.2 18.4 18.6 18.5
Less: Current Tax 11.4 27.5 28.0 28.6 29.2 29.8 30.4 31.0 31.7 32.3 33.3Amount available for Debt servicing 172.9 491.6 473.9 456.2 438.5 420.9 403.3 385.9 368.4 351.1 305.3
DSCR 2.12 1.35 1.38 1.41 1.44 1.48 1.53 1.58 1.64 1.72 1.66
Minimum DSCR 1.35
Average DSCR 1.51
Strictly Private & Confidential 127
Bajaj Energy Private Ltd Project Information Memorandum 450 MW Power Project
Profit & Loss Account
(Rs.
Crores)
Profit and Loss Statement
Mar-12
Mar-13
Mar-14
Mar-15
Mar-16
Mar-17
Mar-18
Mar-19
Mar-20
Mar-21
Mar-22
Revenue Sale of Power 393.5 982.5 980.7 979.5 978.8 978.8 979.5 980.8 982.8 985.5 990.2ExpenditureCoal Cost 176.7 461.7 473.3 485.1 497.3 509.7 522.4 535.5 548.9 562.6 576.7
Oil Cost 1.0 2.6 2.7 2.8 2.9 3.0 3.1 3.1 3.2 3.3 3.4
O& M Cost 25.1 63.8 67.5 71.3 75.4 79.7 84.3 89.1 94.2 99.6 105.3Total Expenditure 202.8 528.2 543.5 559.2 575.5 592.4 609.7 627.7 646.3 665.5 685.4PBDIT 190.7 454.3 437.2 420.2 403.3 386.5 369.7 353.1 336.5 320.0 304.8
InterestInterest on Loan 81.5 190.1 170.1 150.1 130.1 110.1 90.0 70.0 50.0 30.0 10.0Interest on Working Capital 6.4 17.2 17.3 17.5 17.6 17.8 18.0 18.2 18.4 18.6 18.5Total Interest 87.9 207.3 187.4 167.5 147.7 127.8 108.0 88.2 68.4 48.6 28.5PBDT 102.8 247.0 249.8 252.7 255.6 258.6 261.7 264.9 268.1 271.4 276.3
Depreciation 45.5 109.2 109.2 109.2 109.2 109.2 109.2 109.2 109.2 109.2 109.2PBT 57.3 137.8 140.6 143.5 146.4 149.4 152.5 155.6 158.8 162.2 167.1
Tax
Income Tax 11.4 27.5 28.0 28.6 29.2 29.8 30.4 31.0 31.7 32.3 33.3
Deferred Tax 7.6 18.3 18.7 19.1 19.5 19.8 20.3 20.7 21.1 21.5 22.2
Total Tax 19.0 45.8 46.7 47.7 48.6 49.6 50.6 51.7 52.8 53.9 55.5PAT 38.3 92.0 93.9 95.8 97.8 99.8 101.8 103.9 106.1 108.3 111.6
Strictly Private & Confidential 128
Bajaj Energy Private Ltd Project Information Memorandum 450 MW Power Project
Balance Sheet
ParticularsMar-
10Mar-
11Mar-
12Mar-
13Mar-
14Mar-
15Mar-
16Mar-
17Mar-
18Mar-
19Mar-
20Mar-
21Mar-
22Liabilities Shareholders Funds
Equity 438.6 439.5 580.0 580.0 580.0 580.0 580.0 580.0 580.0 580.0 580.0 580.0 580.0Reserves & Surplus - - 38.3 130.3 224.2 320.0 417.7 517.5 619.3 723.2 829.3 937.6
1,049.2
Net worth 438.6 439.5 618.3 710.3 804.2 900.0 997.71,097
.51,199
.31,303
.21,409
.31,517
.61,629
.2Loan FundsLong term borrowings -
1,195.7
1,740.0
1,566.0
1,392.0
1,218.0
1,044.0 870.0 696.0 522.0 348.0 174.0 (0.0)
Working Capital Borrowings - - 54.7 146.1 147.3 148.5 149.9 151.4 153.0 154.7 156.5 158.4 157.8
Sub Total -1,195
.71,794
.71,712
.11,539
.31,366
.51,193
.91,021
.4 849.0 676.7 504.5 332.4 157.8Deferred Tax Liability - - 7.6 25.9 44.6 63.7 83.1 103.0 123.2 143.9 165.0 186.5 208.7Deferred Revenue - - - 82.0 163.9 245.9 327.9 409.9 491.8 573.8 655.8 737.8 790.0Total Liabilities 438.6
1,635.3
2,420.5
2,530.3
2,552.0
2,576.1
2,602.7
2,631.7
2,663.4
2,697.6
2,734.6
2,774.4
2,785.8
AssetsFixed Assets
Strictly Private & Confidential 129
Bajaj Energy Private Ltd Project Information Memorandum 450 MW Power Project
ParticularsMar-
10Mar-
11Mar-
12Mar-
13Mar-
14Mar-
15Mar-
16Mar-
17Mar-
18Mar-
19Mar-
20Mar-
21Mar-
22
Gross Block - -2,271.
32,271.
32,271.
32,271.
32,271.
32,271.
32,271.
32,271.
32,271.
32,271.
32,271.
3Less:Depreciation - - 45.5 154.8 264.0 373.3 482.5 591.8 701.0 810.2 919.5
1,028.7
1,138.0
Net Block - -2,225
.82,116
.52,007
.31,898
.01,788
.81,679
.51,570
.31,461
.11,351
.81,242
.61,133
.3
CWIP 438.61,635.
3 - - - - - - - - - - -
Sub Total 438.61,635
.32,225
.82,116
.52,007
.31,898
.01,788
.81,679
.51,570
.31,461
.11,351
.81,242
.61,133
.3Currents Assets, Loans & Advances
Inventories - - 21.9 57.3 58.7 60.2 61.7 63.2 64.8 66.4 68.1 69.8 71.5
Debtors - - 48.5 131.2 131.0 130.9 130.8 130.8 130.9 131.0 131.3 131.6 128.5Maintenance & Spares - - 0.4 1.0 1.1 1.2 1.2 1.3 1.4 1.5 1.5 1.6 1.7Cash & Bank Balances (including cash in DSRA) - - 123.9 224.2 353.9 485.9 620.2 756.9 896.0
1,037.7
1,181.9
1,328.8
1,450.7
Current LiabilitiesNet Current Assets - - 70.8 189.5 190.8 192.2 193.7 195.3 197.0 198.9 200.9 203.0 201.8Total Assets 438.6
1,635.3
2,420.5
2,530.3
2,552.0
2,576.1
2,602.7
2,631.7
2,663.4
2,697.6
2,734.6
2,774.4
2,785.8
Strictly Private & Confidential 130
Bajaj Energy Private Ltd Project Information Memorandum 450 MW Power Project
Cash flow Statement
FY Ending March 31,
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Cash Flow from Operating Activities
PBT - - 57.3 137.8 140.6 143.5 146.4 149.4 152.5 155.6 158.8 162.2 167.1Add:Depreciation - - 45.5 109.2 109.2 109.2 109.2 109.2 109.2 109.2 109.2 109.2 109.2
Add: AAD - - - 82.0 82.0 82.0 82.0 82.0 82.0 82.0 82.0 82.0 52.3Add:Interest Paid - - 87.9 207.3 187.4 167.5 147.7 127.8 108.0 88.2 68.4 48.6 28.5Operating Profit before Working Capital Changes - - 190.7 536.3 519.2 502.2 485.3 468.5 451.7 435.0 418.5 402.0 357.1Adjustment for Working Capital
Add/(Less)Change in Inventory - - (21.9) (35.3) (1.4) (1.5) (1.5) (1.5) (1.6) (1.6) (1.7) (1.7) (1.7)Change in Maintenance & Spares - - (0.4) (0.6) (0.1) (0.1) (0.1) (0.1) (0.1) (0.1) (0.1) (0.1) (0.1)Change in Receivables - - (48.5) (82.7) 0.2 0.2 0.1 0.0 (0.1) (0.2) (0.2) (0.3) 3.1
Sub Total - - (70.8) (118.7) (1.3) (1.4) (1.5) (1.6) (1.7) (1.9) (2.0) (2.1) 1.2Less: Income Tax Paid - - 11.4 27.5 28.0 28.6 29.2 29.8 30.4 31.0 31.7 32.3 33.3Net Cash from Operating
- - 108.4 390.1 489.9 472.2 454.6 437.1 419.6 402.2 384.8 367.6 325.1
Strictly Private & Confidential 131
Bajaj Energy Private Ltd Project Information Memorandum 450 MW Power Project
FY Ending March 31,
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Activities
Cash Flow from Investing ActivitiesPurchase of Fixed Assets (438.6)(1,196.7)(636.0) - - - - - - - - - -Net Cash from Investing Activities (438.6)(1,196.7)(636.0) - - - - - - - - - -Cash Flow from Financing Activities
Infusion of Equity 438.6 0.9 140.5 - - - - - - - - - -Add:Proceeds from Long term borrowings - 1,195.7 544.3 - - - - - - - - - -Add:working Capital Borrowing - - 54.7 91.4 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 (0.6)
Transfer to DSRA - - 91.0 (5.0) (5.0) (5.0) (5.0) (5.0) (5.0) (5.0) (5.0) (5.0) (46.0)Less:Repayment of Loan - - - 174.0 174.0 174.0 174.0 174.0 174.0 174.0 174.0 174.0 174.0Less:Interest Paid - - 87.9 207.3 187.4 167.5 147.7 127.8 108.0 88.2 68.4 48.6 28.5Net Cash from Financing Activities 438.6 1,196.7 560.5 (284.8) (355.2) (335.3) (315.3) (295.4) (275.4) (255.5) (235.6) (215.7) (157.1)Increase/ - - 32.9 105.3 134.7 137.0 139.3 141.7 144.1 146.7 149.2 151.9 167.9
Strictly Private & Confidential 132
Bajaj Energy Private Ltd Project Information Memorandum 450 MW Power Project
FY Ending March 31,
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Decrease in cash balanceOpening Cash Balance - - - 32.9 138.2 272.9 409.9 549.2 690.9 835.0 981.7 1,130.9 1,282.8Closing Cash Balance - - 32.9 138.2 272.9 409.9 549.2 690.9 835.0 981.7 1,130.9 1,282.8 1,450.7Cash Balance in DSRA - - 91.0 86.0 81.0 76.0 71.0 66.0 61.0 56.0 51.0 46.0 -Closing Cash Balance including DSRA - - 123.9 224.2 353.9 485.9 620.2 756.9 896.0 1,037.7 1,181.9 1,328.8 1,450.7
Strictly Private & Confidential 133