Drive Test EventsDestination out of order (3)
Network Release (2)
Dropped calls (5)
1) Kitintale2) Busega3) Kisugu4) Muyenga5) Munyonyo
ACTIONS ON THE DROPS:1) Kitintale: Optimisation done , DT to be repeated2) Busega: Optimisation Ongoing. Time plan: End June 20143) Kisugu/Muyenga: Infill Site integration in progress. Time plan: August 20144) Munyonyo: Infill Site integration in progress. Time plan: August 2014