Benacre & Kessingland Flood Risk Management Project Karen Thomas Project Manager Water Management Alliance On behalf of Waveney, Lower Yare and Lothingland Internal Drainage Board

Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Benacre & Kessingland Flood Risk Management Project

Karen Thomas Project Manager

Water Management Alliance

On behalf of Waveney, Lower Yare and Lothingland

Internal Drainage Board

Page 2: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Lowestoft N

Page 3: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland
Page 4: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Courtesy of Mike Page

Page 5: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Courtesy of Mike Page

2016

Page 6: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Courtesy of Mike Page and Benacre Estates

2017

Page 7: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Breach Risk to Kessingland Levels

Page 8: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Alternative Flood Risk Management Options

Page 9: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

What’s at Tidal Risk?

Circa 44 Homes Commercial businesses 600 acres + Agriculture Abstraction Tourism Recreation and Access Transport links (A12) Utilities (water, electric) Landscape Wildlife

Page 10: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

SOUTH AREA 08/01/2019

Page 11: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

SOUTH AREA 08/01/2019

Page 12: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

NORTH AREA 08/01/2019

Page 13: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

NORTH AREA 08/01/2019

Page 14: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Fluvial Flood Risk

Page 15: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Surface water flooding in Kessingland

Page 16: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Preferred alignments of potential new defences

Benacre flood defence options

Page 17: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Parkdean Resorts Alignment Options

Page 18: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Benacre Estates- Lothingland Valley set-back option

Page 19: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Economics studies

• Wider economic study from Mott MacDonalds

• Identifies £130M of wider economic benefits arising from an adaptive approach

• SCC Highways report estimated present value losses (PV Losses), accrued over a 50 years (2018 –2068), are £253,717,000 for the Do Nothing plus climate change scenario.

• Both reports will feed into economic appraisal in OBC

• Form basis of wider partnership funding ask for a scheme

Page 20: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Stakeholder Engagement

• Partnership approach

• Project Board supported by local Councillors and MP Peter Aldous

• Multi-agency project team

• Local leadership from Kessingland Parish Council

• 150 stakeholders attended initial drop-in Nov 2017

• Autumn 2019- update on latest information and likely preferred options

• Spring 2020- final rounds of engagement and OBC submission

Page 21: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Recent progress

From October 2018 • RFCC decision on Levy funding • WMA & Jacobs programme for 18 months OBC • Includes Parkdean Resorts costed options in the appraisal • Developing our stakeholder engagement approach and share evidence • Identify potential funding routes (funding framework) for the capital scheme

including private elements • Technical work to be developed over next 12 months- coastal change, ground

conditions, outline designs for defences and pump capacity • Develop a preferred option and engage local people Autumn 2019 and Spring 2020 • Submit Business Case June 2020

Page 22: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Opportunities & challenges

• Outside of the FDGIA Business Case- the project aims to deliver wider benefits and attract broader funding streams

• Opportunities for landscape scale adaptation

• Freshwater capture and storage for habitat enhancement and agriculture

• Fisheries, tourism and access can be enhanced

• Need to attract investors • £10-15M scheme

Page 23: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland
Page 24: Benacre & Kessingland Flood Risk Management Project · •Project Board supported by local Councillors and MP Peter Aldous •Multi-agency project team •Local leadership from Kessingland

Questions