40

being implemented at Mulanur, Tamil Nadu which is to be connected to 400/230 kV , PGCIL substation, Pugalur (ISTS). TheCommercial Sub-Committeemay approve the metering schemes. 11

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 2/23

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU

Agenda for the 41stMeeting of Commercial Sub Committee

of SRPC to be held at SRPC, Bengaluru on 20.06.2019.

1. Introduction

2. Confirmation of the Minutes of 40thCommercial Committee meeting Minutes of the 40thMeeting of the Commercial Sub-Committee of SRPC held on

25thFebruary 2019 were issued vide letter No. SRPC/SE-I/40CC/2019/1434-67dated

19thMarch 2019.Amendment to the minutes (Item No. 6.1.7) was issued vide letter No.

SRPC/SE-I/40 CC/2019/1434-67 dated 17.5.2019.

The Minutes of the meeting, incorporating the amendment issued, may please be confirmed.

3. Audit of SR Deviation& Reactive Energy ChargePool Accounts In line with Para15 of Annexure-I to the CERC (IEGC) Regulations, 2010

(Complementary Commercial Mechanism), RLDC shall table the complete statement of

the Regional UI account and the Regional Reactive Energy pool account in the RPC’s

Commercial Committee Meeting on a quarterly basis, for audit by the latter.

SRLDC vide letter SRLDC/MO/CCM dated 17-05-2019 (ANNEXUREA) have

furnished details of payment and disbursement of weekly Deviation and Reactive

Energy charges for the period from 14.01.2019 to 21.04.2019.

The Accounts may be audited.

4. Items proposed by SRLDC SRLDC vide letter dated 17.05.2019 (refer ANNEXURE A) have proposed the

following items for discussion:

(i). Audit of SR DSM& Reactive energy Accounts.

(ii). Reconciliation of DSM, RRAS, Reactive and Congestion charges.

(iii). Status of outstanding charges to the pool accounts.

(iv). Reconciliation of Short Term Open Access (STOA) disbursements.

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 3/23

5. SEM issue at Ananthapuramu(NP KUNTA) ULTRA MEGA SOLAR PARK It was noted during the 39th and 40thCCM that SEM reading i.r.onight drawal values of

all ACME SPDs were mostly zero.

In the 40th CCM SE (O), SRPC requested SR-I, PGCIL to take up testing and

calibration of the above SEMs (on payment basis) so that the problem is fixed and

APSPCL was requested to coordinate for the calibration.

SR-I, PGCIL agreed to take up the calibration works, however, they would discuss

thematter internally with the officials concerned and revert.

It was also suggested to swap the non-recording SEMs with the SEMs

presentlyrecording drawal,so as to ascertain the reason of malfunction.APSPCL and

ACME SPDs were requested to mitigate the problem so that preciseenergy accounting

of all SPDs of the park could be carried out.

In spite of the above, the SEM values continued to have the same discrepancy and hence

the average drawals are being computed to assign drawal values to these SPDs to assess

deviation.

APSPCL may clarify. It is also requested that a representative from ACME may attend the

meeting to present the factual position.

6. NNTPP power to be scheduled to Tamil Nadu through ISTS In the 40th CCM,SRPC Secretariat presented the computation of percentage of NNTPP

power to be scheduled to Tamil Nadu through ISTS, for which losses are applicable, out

of total share of allocation and informed that in case of any major changes in the

allocation, the scheduling percentages could be recomputed then.

Subsequently, it was noted that 53 MW of unallocated power from Neyveli New

Thermal Power Station (NNTPS) has been allocated by MoP to U.T of Puducherry over

and above the firm allocation of 4.24 MW.Accordingly, the revised computation of

percentage of NNTPP power to be scheduled to Tamil Nadu through ISTS is given

below:

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 4/23

State MW allocated

Percentage of sharing

Revisedex-bus MW allocation

Revised MW allocation after considering the

Unallocated Power of 6.56 MW

TN 53.07 15.88922156 49.75 50.81 AP 52.46 15.70658683 49.18 50.23 TS 61.31 18.35628743 57.48 58.71

KAR 70.54 21.11976048 66.13 67.55 KL 32.38 9.694610778 30.36 31.01 Pud 57.24 17.13772455 53.66 54.81

Unallocated 7 2.095808383 6.56 Total 334 100 313.12 313.12

MW %

Percentage share based on total TN Schedule

Total Ex Bus NNTPP generation:

875.625 MW

Total TN Schedule (State Network) 562.51 91.7

Total TN Schedule (ISTS network) 50.81 8.3

Note: Considering Auxiliary Consumption as 6.25% based on Tariff Regulation 2019-2024 (applicable period). • The above modification was incorporated in the amendment to the minutes issued vide

letter No. SRPC/SE-I/40 CC/2019/1434-67 dated 17.5.2019.

• Further, NNTPP was requested to update the LTA quantum based on the updated

auxiliary consumption of 6.25%, based on Tariff Regulation 2019-2024.

Placed for the information of the forum. NNTPP may update on the status.

7. Certified NaturalInterstate lines

• APTRANSCO vide their letter dated 13-03-2019 had requested for the certification of

certain interstate lines owned by STU of AP, that have been modified/added recently, so

that these lines can be considered for inclusion in POC charges.

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 5/23

• Subsequently, SRLDC vide letter dated 22-03-2019 had confirmed the above lines as

interstate lines.Based on the above input from SRLDC,lines with the configurational

changes and also the new lines that have been commissionedhas been certified. The

details are shown below:

• New ISTS lines are commissioned between Andhra Pradesh and Telangana:

Sl. No. AP SS Line (new) Voltage level (kV) Connected to 1 K V Kota K V Kota - Suryapeta - I 400 Telangana 2 K V Kota K V Kota - Suryapeta - II 400 Telangana

• Lines which have been LILOed at new locations in Telangana:

Sl. No AP SS Line before alteration

(Considered in PoC) Voltage

level (kV) LILOed in TS

at Line after alteration

Connected to

1 Kalpaka Kalpaka - Khammam - II 400 Asupaka Kalpaka - Asupaka - I Telangana

2 Srisailam Srisailam RB - Dindi - II 220 Domalapenta Srisailam RB –Domalapenta#

Telangana

3 Chillakallu Chillakallu - Narketpalli - I 220 Suryapeta Chillakallu - Suryapeta Telangana

4 Chillakallu Chillakallu - Narketpalli - II 220 Pulichintala Chillakallu - Pulichintala Telangana

5 AP Carbides AP Carbides - Gadwal 132 Alampur AP Carbides - Alampur - II Telangana

6 VTPS VTPS-Malkaram 400 Suryapet VTPS-Suryapet-II Telangana

Note: #: The Substation at Domalapenta is yet to be charged.

Placed for the information of the forum.

8. Mismatch of Declared Capacity and Schedule subsequent to the implementation of SCED.

• Frequent instances have been observed from the schedule data files received from

SRLDC, subsequent to the implementation of SCED, that the total schedules of

generating stations are much higher than the DC (sample instances at ANNEXURE B).

• This has ramification on various account statements.

SRLDC/NLDC may clarify the factual position and measures being taken to obviate the discrepancy.

9. Technical Specification of Special Energy Meters

• It became apparent from draft amendments to Metering Regulations published by CEA

that AMR scheme would be mandated. The need of AMR is also being felt in view of

high RE ingress, amendments in DSM Regulations, SCADA related issues etc.

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 6/23

• The matter was deliberated in the SRPC meetings. In the 35thSRPC meeting it has been

decided to finalise the Technical Specifications required for the Interface Energy

Meters (IEM) /SEM (with AMR, configurable recording intervals, SCADA integration

etc.).

• Accordingly, a video conference to deliberate on the finalsation of technical

specifications required for the Interface Energy Meters (IEM) /SEM (with AMR,

configurable recording intervals etc.) was held on 7.3.2019. A presentation on features

of SEM, issues faced and technical feasibilities were made during the VC.

• Subsequently, a meeting of utilities, to finalise the technical specifications was held on

22ndMarch 2019. In the meeting some manufactures presented the state-of-the-art

features in the metering.

• Based on the inputs from the meeting adraft technical specifications for SEM/IEM

along with the scope of the scheme and technical specifications for AMR and draft

technical details of Meter Data Processing (MDP), Historian, ICCP Associations with

the SCADA systems of utilities, User Interface(UI) etc. within Interface Meter Data

Centre (IMDC)to be implemented for SR along with details of existing

meters(ANNEXURE C) has been prepared by PGCIL and circulated for

suggestions/comments/observation of all concerned.

• KSEBL had furnished comments/suggestions on the draft specifications, which is

enclosed at ANNEXURED.

• To finalize the Technical Specification document a meeting is being convened on 19th

June, 2019 (Wednesday) at 10:30 hr.at SRPC, Bengaluru.All concerned are

requested to furnish views/suggestions before the special meeting proposed as above.

Placed for the information of the forum.

10. Metering Scheme of M/S. Betam Wind Energy Pvt Ltd. and M/S Sprng Renewable Energy Private Ltd.

• M/s. Betam Wind Energy Pvt Ltd., vide letter dated 18-04-2019

(ANNEXUREE),submitted metering scheme i.r.o of the Wind Energy Project being

implemented at Tuticorin, with a request for approval of the scheme.

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 7/23

• M/s Sprng Renewable Energy Private Limited, vide letter dated 16.5.2019

(ANNEXUREF),submitted metering scheme i.r.o of 300 MW Wind Power Project

being implemented at Mulanur, Tamil Nadu, which is to be connected to 400/230 kV

PGCIL substation, Pugalur (ISTS).

TheCommercial Sub-Committeemay approve the metering schemes.

11. Scheduling and Despatch of Pavagada Solar Power Park

• Meeting to discuss the modalities and compliance of various provisions of Regulation

vis-à-vis scheduling and despatch of Pavagada Solar Power Park. Karnataka by

SRLDC was held on 4.10.2018.

• Further, a review meeting was held to discuss and resolve various issues to enable

SPDs for compliance of requirements under the regulations, on 02.11.2018.

• The matter was further deliberated in the 34th TCC/35thSRPC meetings.

• In the 40th CCM:

KSPDCL was requested to complete all the pending works as per the assured time frame (May 2019) so as to commence scheduling by SRLDC expeditiously.

All registered SPDs, who were yet to furnish PPA rates on notarized affidavit supported by copy of PPA, were requested to furnish the same.

Actual metered data to be communicated to SRLDC by all SPDs for mock account preparation.

KSPDCL may presentthe update.

12. Compensation Computation for SCED

• Security Constrained Economic Despatch (SCED) for Inter State Generating Stations

pan India wasoperationalized from 1stApril, 2019.

• The detailed procedure on SCED for ISGS Pan-India defines the role of RPC to issue

Weekly SCED accounts based on the data provided by RLDCs and monthly

“Statement of Compensation due to Part Load Operation on Account of SCED”

separately for all SCED generators.

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 8/23

• In this regard, Compensation due to Part Load Operation on Account of SCED as

well as beneficiaries are defined as shown below:

• Compensation for degradation of Heat Rate (SHR) and Auxiliary

EnergyConsumption (AEC) Computation remain unaltered as defined in the

approved detailedprocedure issued vide the CERC Order dated 5th May, 2017.

It is mentioned in the Tariff Regulation, 2019-2024, that

CVPF = Weighted Average GrossCalorific value of coal as received, in

Kcal/Kg for coal based stationsless85 Kcal/Kg on account of variation during

storage at generating station.

All concernedare requested to furnish CVPF value aftersubtractingthe

quantum of 85 kCal/kg for Coal based Stations.

The following procedure would be adopted for Computation of compensation:

• For computation of compensation SCED will be considered as an entity along with

the Beneficiaries.

• Final Compensation payable by kth beneficiary and SCED for the calculation period

ending nth month is as below:

No compensation shall be payable by a beneficiaries if it has requisitioned at

least 85% of its entitlement during the calculation period.

No compensation shall be payable to SCED Generatorif it hasnet increment

in schedule during the calculation period. If the SCED Generator has net

decrement schedule, then the net decrement schedule shall be considered for

sharing of compensation by SCED.

The compensation amongst allbeneficiaries and SCED shall be shared in the

ratio of un-requisitioned energy below 85% of their entitlement for

beneficiary and net decrement schedule for SCED, i.e., compensation payable

by kth beneficiary and SCED for the calculation period ending on nth month

FCBkn = Compn(F) ∗UEkn

∑UEkn

Where UEkn is un-requisitioned energy of kthbeneficiary below 85% of its

entitlement and net decrement schedule for SCED during the calculation

period ending nth month.

• RPCs issues monthly "Statement of Compensation due to PartLoad Operation on

Account of SCED” (as per Format SCED4 specified in the detailed procedure). An

illustrative example is given below:

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 9/23

Compensation Calculated for the ISGS Station =Rs.X.

If there are 4 beneficiaries for the ISGS Station, and the ratio of Un-

requisitioned energy of beneficiaryand SCED below 85% of its

entitlement from ISGSStationsare as shown below:

A1 A2 A3 A4 SCED Total

15% 0 20% 15% 50% 100

The compensation amount payablewould be:

A1 A2 A3 A4 SCED Total

15%*X 0 20%*X 15%*X 50%*X X

• This will be carried out on Cumulative basis in line with the Compensation

Procedure.

Placed for the deliberation/concurrence of the sub-committee.

13. Compensation Calculation for Secondary Fuel Oil consumption

• The approved detailed procedure for taking unit(s) under Reserve Shut Down and

Mechanism for Compensation for Degradation of Heat Rate, Aux Compensation and

Secondary Fuel Consumption, due to Part Load Operation and Multiple Start/Stop of

Units, stipulates that Calculation of Compensation for degradation of Secondary Fuel

Oil consumption for the year shall be done iftotal number of start-ups exceed 7 x no.

of units in the generating station. Compensation for degradation of Secondary Fuel

Oil Consumption (in terms of KL of Secondary Oil)shall be calculatedby multiplying

number of start-ups exceeding 7 per unit,which are solely attributable to reserve shut-

downs, with the appropriate value of additional secondary oil consumption specified

in Regulation and shall be restricted such that Oil Consumption based on Norms plus

Compensation calculated as above does not exceed actual Secondary Fuel oil

consumption for the year.

• For example, if the station consists of 3 Units and there are total 28 outages

(Forced/Planned/RSD) for a year, out of which 9 are attributable to RSD, then

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 10/23

Compensation shall be calculated for number of stat-ups exceeding 7 X 3 =21, which

are solely attributable to reserve shut-downs.,i.e., 28-21=7 outages would be

considered for compensation of degradation of SFC.

• Among the above reserve shut-downs, if there are 4 Cold, 3Warm and 2Hot RSD

category, then oil compensationwill be computed as(COLD*4+ WARM*3+

HOT*2)*7/Total start-ups attributable RSD (9); i.e. for example, compensation

calculated be 770 KL.

• Compensation payable to CGS/ISGS shall be restricted such that OilConsumption

based on Norms plus Compensation calculated above does not exceed actual

Secondary Fuel oil consumption for the year.

• Illustration:

Actual Gross Generation for the year,G: 5000 MU

Compensation Calculated be = 770 KL Norm

SFC (A)

Actual

SFC (B)

Norm Oil

(A’=A*G)

Actual

Oil

(B’=B*G)

Compensation

calculated (C)

A’+C

(D)

Restricted

to B’ if

D>B’

Final

Compensation

after

restricting

ml/kWh ml/kWh KL KL KL KL KL KL

Scenario

No.1

0.5 0.65 2500 3250 770 3270 3250 770-(3270-

3250)=750

Scenario

No.2

0.5 0.65 2500 3250 700 3200 3250 700

• Compensation in terms of Rupees shall be calculated by multiplying compensation in

terms of KL as calculated and average landed price of Secondary fuel oil for the year.

• Each start-up due to reserve shutdown shall be attributed to the beneficiaries, who had

requisitioned below 55% of their entitlement.SRLDC is requested to furnish the relevant

requisition data of the beneficiariespertaining to Generating Station(s) for the

period,blocks, based on which decision to take generator(s) under RSD is taken.

• Compensation (in terms of Rupees) shall be shared amongst the beneficiaries in the

following manner:

𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶 𝐶𝐶𝐶𝐶𝑝𝑝𝐶𝐶𝑝𝑝𝑝𝑝𝐶𝐶 𝑝𝑝𝑝𝑝 𝑝𝑝𝐶𝐶𝐶𝐶𝐶𝐶𝑏𝑏𝐶𝐶𝑏𝑏𝐶𝐶𝐶𝐶𝑏𝑏𝑝𝑝 𝐶𝐶

= �𝑁𝑁𝐶𝐶 ∗𝐴𝐴𝐶𝐶

∑(𝑁𝑁𝐶𝐶 ∗ 𝐴𝐴𝐶𝐶 )� ∗ 𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶 𝐶𝐶𝐶𝐶𝑝𝑝𝐶𝐶𝑝𝑝𝑝𝑝𝐶𝐶 𝐶𝐶𝐶𝐶 𝐶𝐶𝐶𝐶𝐶𝐶/𝐼𝐼𝐶𝐶𝐶𝐶𝐶𝐶

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 11/23

• Where𝐴𝐴𝐶𝐶= Number of start-ups attributable to the beneficiary i.

Ni = Weightage Average Percentage share of the beneficiary in the generating station.

• Illustrative example:

Compensation Calculated for the ISGS Station Y = Rs.(750*LPSFi).

If there are 4 beneficiaries for the ISGS Station, the payment details

would be as shown below: Beneficiary A1 A2 A3 A4 Total

Weighted Average percentage share (MoP)

15% 20% 40% 25% 100

Number of start-ups attributable to RSDs (of beneficiary who had requisitioned below 55% of their entitlement during RSD)

4 9 4 1

Payable amount (𝟒𝟒 ∗ 𝟎𝟎.𝟏𝟏𝟏𝟏)

𝑫𝑫∗ 𝒀𝒀

(𝟗𝟗 ∗ 𝟎𝟎.𝟐𝟐)𝑫𝑫

∗ 𝒀𝒀 (𝟒𝟒 ∗ 𝟎𝟎.𝟒𝟒)

𝑫𝑫∗ 𝒀𝒀

(𝟏𝟏 ∗ 𝟎𝟎.𝟐𝟐𝟏𝟏)𝑫𝑫

∗ 𝒀𝒀 Y

Denominator, D= (4*0.15 + 9*0.2 +4*0.4 + 1*0.25)

Placed for the deliberation/concurrence of the committee.

14. NLCIL and NTPL Agenda

• NLC India Ltd.,vide letter dated 18.05.2019 (ANNEXUREG), forwarded the

following agenda for discussion in the meeting:

• The Power Bill Dues from DISCOMs to NLCIL & NTPL as on 15-05-2019

In spite of regular letters to the senior officials of the DISCOMs and frequent

visits to the DISCOM Offices by NLCIL' s officials to pursue the payment of

huge dues from them, payments commensurate with the outstanding dues are

not being made by DISCOMs which results in the accumulation of dues. The

huge outstanding makes it difficult for NLCIL in the financial management of

ongoing projects and for NTPL in making payments for coal purchases.

NLC India Limited

SEBs POWER BILL Dues (Rs.Cr.)

>60 days Total TANGEDCO 2780.06 3228.11

HESCOM 208.41 256.59

CESC 42.65 68.55

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 12/23

GESCOM 70.69 103.09

APDISCOMS 253.91 333.36

TELANGANADISCOMS 296.36 381.02

PED 99.25 172.35

NTPL

SEBs POWER BILL Dues (Rs.Cr.)

>60 days Total TANGEDCO 417.69 542.04

HESCOM 181.10 194.00

CESC 17.89 24.66

GESCOM 37.16 45.61

APDISCOMS 268.83 310.27

TELANGANA DISCOMS 322.58 375.75

TANGEDCO, HESCOM, CESCOM, GESCOM, AP, Telangana and

PED are requested to update the status.

15. KKNPP Agenda

• KKNPP, vide letter dated 20.5.2019 (ANNEXURE H), proposed the following

agenda regarding nonpayment of energy dues and DPC dues & non

submission/revision of LC by beneficiaries, for discussion in the meeting:

i. Non Payment of Energy Dues & DPC dues byState Electricity Boards

(SEB's).

ii. Non Submission of Letter of Credit by M/s. HESCOM.

iii. Non Revision of Letter of Credit value by M/s. TNEB, M/s KSEB,

M/s.CESCORP and M/s GESCOM.

The outstanding due furnished by KKNPP as per their letter dated 22-05-2019

(ANNEXURE I)is given below:

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 13/23

Details of Dues - MAY 2019 (18.05.2019)

S.N

Name of the SEBs

Energy Bill Outstanding DPC Outstanding

Grand Total

Outstanding

(Energy Bill & DPC)

Less than 60 days

More than 60 days Total Less than

60 days More than

60 days Total

1 M/s. Tamil Nadu Electricity Board 1817857368 3346670774 5164528142 107756357 1384455505 1492211862 6,65,67,40,004

2

M/s. Hubli Electricity Supply Company, Karnataka

133231978 968410065 1101642043 196300360 252207838 448508198 1,55,01,50,241

3 M/s. Transmission Corporation of Telanaana

161587263 403473776 565061039 3050966 16845511 19896477 58,49,57,516

4 M/s. Pondicherry Electricity Board 108262814 112585404 220848218 15218955 18855137 34074092 25,49,22,310

5

M/s .Gulbarga Electric Supply Company, Karnataka

87300920 110083987 197384907 35416466 44843579 80260045 27,76,44,952

6

M/s Chamundeswari Electric Supply Corporation, Karnataka

71632073 95010722 166642795 24330846 32863598 57194444 22,38,37,239

7

M/s. Andhra Pradesh Power Coordination Committee

11978393 11978393 1243347 6773764 8017111 1,99,95,504

TOTAL 2,37,98,72,416 5048213121 7428085537 383317297 1756844932 2140162229 9,568,247,769

• M/s. KKNPP states that in spite of assurance given in the Commercial meetings of

SRPC held, the outstanding dues have not been cleared as on date. KKNPP also

requests that SEB's shall commit exact date for payment of such long outstanding

dues. Further, non-receipt of energy dues from SEB's is hampering KKNPP day to

day activities along with working capital management and are unable to clear off

liabilities in timely manner.

• Additionally, M/s. KKNPP vide the letter dated 21-05-2019 (ANNEXURE J)had

also intimated to Additional Chief Secretary to Government of Karnataka regarding

the non-payment of Energy dues and LC related non-compliance by M/s HESCOM,

M/s CESCORP and M/s GESCOM.

• Subsequently, M/s. KKNPP vide the letters dated 23-05-2019 (ANNEXURE K)

had again requested TANGEDCO, HESCOM, GESCOM and CESCOM to clear the

Overdue Energy bills and DPC as early as possible.

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 14/23

The agenda point would be discussed in the meeting and the above

beneficiaries are requested to present reply.

16. NTECL agenda Points

• NTECLvide their letter dated07-05-2019 and29-05-2019 (ANNEXURE L) had

intimated regarding the outstanding payment against energy billsraised on the

beneficiaries such asAPPCC,HESCOM,CESCORP,GESCOM, TSPCC and

TANGEDCO.

• In this regard, it may be mentioned that in addition to fund requirements for other

operational needs, NTECL also needs to make advance payment to the coal

companies against the coal supplies. In case regulation of coal supplies takes place,

it will result in reduction in DC from NTECL Vallur Station, which in turn will

cause reduction in Power availability for the beneficiaries.

• Moreover, with the introduction of SCED, NTECL needs to make payment to

POSOCO SCED pool account to the tune of 10-15 Crores every week and due to

huge outstanding from beneficiaries, release of payment to SCED pool account from

NTECL is also adversely affected. It is pertinent to mention that in the event of

default in payment to SCED pool account; it shall attract huge interest liability.

The issue would be discussed in the meeting.

All the Constituentsconcerned are requested to update the status of

payment.

17. Transmission Charges Pertaining to Kudgi STPS 1. Regarding Additional LTA Quantum

• The matter was discussed in the earlier CCM meeting and in 34th SRPC meeting

held on 11-08-2018, all beneficiaries had concluded that the additional quantum

needs to be relinquished immediately to avoid future liabilities.

• In this regard, CTU clarified that till the quantum is relinquished or some Order is

received from CERC, full LTA quantum would continue to be billed.

• NTPC vide their letter dated 26-03-2019 had requested CTU for the revision of LTA

granted to NTPC for Kudgi TPS from 2392.49 MW to 2250 MW on account of

auxiliary consumption and overload capacity.

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 15/23

• Subsequently, CTU letter dated 16-05-2019 had intimated that 142.49 MW is

relinquished from 2392.49 MW to 2250 MW on account of auxiliary consumption

and overload capacity. It was requested to facilitate the signing of necessary

amendments to agreements as per provisions of CERC Regulations 2009 as

amended from time to time.

• In this regard, NTPC vide the letter dated 22-05-2019 (ANNEXURE M) requested

all beneficiaries to take up with CTU for signing of the requisite agreements to make

the revision of LTA effective.

NTPC/Constituents may furnish the update.

2. Regarding CERC Order No. 261/MP/2017 dated 06-11-2018 • CERC vide order dated 06.11.2018 had asserted and directed the following:

a) The liability to pay charges towards Long term Access under Central Electricity

Regulatory Commission (Sharing of inter-State Transmission charges and losses), Regulations, 2010 as amended from time to time shall be that of beneficiaries in view of Agreements entered into by them.

b) The LTA needs to be operationalized from the date of declaration of COD of the transmission system irrespective of the CoD of the generator.

c) Annual transmission charges of the associated transmission system (i.e. in this case -Kudgi-Narendra, Narendra-Madhugiri and MadhugiriBidadi and associated bays/ substation) as determined or adopted by the Commission shall be considered in PoC mechanism corresponding only to the units declared under commercial operation and the balance transmission charges shall be recovered from NTPC till the respective COD of remaining units.

• SRPC has already revised RTA on 22.11.2018 corresponding to transmission charges

recoverable from NTPC till COD of the respective units, as per data furnished by

CTU/NLDC.

• In this regard, SRPC, vide letter dated 06-02-2019, had requested data for

compliance of the CERC directions at Para 44(a), (b) and part of (c) of the Order and

also to furnish revised Slab rates and LTA quantum for the applicable period.

• Further, KSEBL, vide letter dated 20.12.2018, referring to CERC Order dated

06.11.2018 in Petition No. 261/MP/2017 had pointed out the following:

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 16/23

Charges recoverable (Rs. 304.10 Cr) from NTPC for the periods August 2016

to September 2018 are to be reimbursed to the beneficiaries who had paid

this amount originally.

PoC slab excluding rates revision for the period August 2016 to September

2018 excluding the charges of Kudgi ATS needs to be carried by NLDC. The

benefit of this revision needs to be passed on to the SR beneficiaries as they

had borne these charges.

• In the 40th CCM, PGCIL had informed that the LTA operationalizing details were

received from CTU internally. In the petition filed by NTPC against the billing of

LTA charges, CERC had directed that the LTA be operationalized from the COD of

associated transmission system and the proportionate YTC of the ATS be collected

from NTPC till commissioning of their pending generation.

• SRPC had issued the revision to the RTA for NTPC revising the billing amount to

Rs. 304.10 Crores. On relevant billing by CTU; the amount has been paid by NTPC.

• PGCIL also stated that there is still a shortfall of Rs. 59 Crores (with respect to RTA

issued) in recovery in the POC Pool, which needs to be collected from other DICs in

the POC Pool through adjustment in the POC bills upon revision of POC slab rates /

SR-RTA for the period Aug’16 to Sep’18.The YTC details of ATS for Kudgi

evacuation and LTA details have been furnished to NLDC.

• Further, PGCIL requested KSEBL to immediately release the withheld amount of

Rs.3.87 Crores in respect of Kudgi Transmission limited charges disallowed in

Bill-3.

• CC requested CTU/PGCIL to furnish element wise details of LTA operationalization

with dates, as mentioned in the CERC order. POSOCO was requested to expedite the

revision of POC slab rates as noted in 35thSRPC/34thTCC meetings.

NLDC may furnish the update.

KSEBL may update the release the status of withheld amount.

18. Certification of Non-ISTS Transmission Lines for the Period 2019-20

• SRPC vide their letter dated 7th March, 2019 (ANNEXURE N) had communicated the

list of Non- ISTS Lines carrying interstate power for the period 2019-20, which were

having more than 50% utilization for interstate power transmission during the year

2018-19.

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 17/23

• In compliance with CERC regulation, 65 non- ISTS lines were certified, in consultation

with SRLDC, as lines carrying interstate power. The data used for the study was taken

from Quarter-1 to Quarter-4 of 2018-19, which was considered for POC computation.

• TNEB vide mail dated 15th March, 2019 had intimated that one of the line got LILOed

on 31-01-2019. Based on the same, a Corrigendum to the above letter dated 27th

March, 2019 was issued intimating the line details as shown below:

As per letter dated 7.3.2019:

Sl.No. Line Certified by SRPC Voltage Level

(KV) State

57 MYVADY42-PUGALR42:1 230 TN

Modified as:

Sl.No. Line Certified by SRPC Voltage Level

(KV) State 57a MYVADY42-KURKATHI:1 230 TN

57b KURKATHI-PUGALR42:1 230 TN

• APSLDC vide their letter dated 25-04-2019 had requested to furnish SRPC certification

for non-ISTS lines carrying interstate power having more than 50 % utilization during

the years FY 2014-15, FY 2015-16 and FY 2016-17 for filling the petition before

Honorable CERC/APERC. Accordingly, SRPC vide their letter dated 13-05-2019

(ANNEXUREO) informed that the certification could be processed only for the

subsequent period from the date of adoption of procedure by the RPC. The procedure as

recommended by the Commercial Committee had been approved by the 31st meeting of

SRPC held on 25-02-2017.

Placed for the information of the committee.

19. CERC, Deviation Settlement Mechanism and related matters (5th Amendment), Regulations, 2019

• CERC, Deviation Settlement Mechanism and related matters

(5thAmendment),Regulations, 2019 were notified on 28.05.2019 and to be

implemented w.e.f 03.06.2019.

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 18/23

• It is mentioned under Clause (10) of Regulation 7 of the Principal Regulations that :

“…….

Provided also that payment of additional charge for failure to adhere to sign

change requirement as specified under clauses (a) & (b) of this regulation shall

not be applicable to:

…..

…..

Forced outage of a generating station in case of collective transactions

on Power Exchanges. “

• The details of forced outage fulfilling the above criteria in a specific format would be

communicated to RPC by RLDC in order to exempt the sign change clause for the

Generating Station from such period /blocks.

The agenda points would be discussed in the meeting.

20. Outstanding dues between Southern & Western Regional Constituents • Pending payments between WR& SR Constituents as on 30.4.2019are as follows:

ANDHRAPRADESH/TELENGANA

RECEIVABLE FROM (₹) PAYABLE TO (₹)

MPPMCL 1,21,76,270* NIL

KARNATAKA

RECEIVABLE FROM (₹) PAYABLE TO (₹)

MPPMCL 13,27,208 NIL

KERALA

RECEIVABLE FROM (₹) PAYABLE TO (₹)

MPPMCL 1,21,47,260

CSPDCL 7,05,279

TAMIL NADU

RECEIVABLE FROM (₹) PAYABLE TO (₹)

MPPMCL 1,17,17,268 CSPDCL 92,77,878

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 19/23

• In the 37th CCM, MS, SRPC had suggested that the matter may be taken up with

WRPC once again. Accordingly, the matter was further discussed in the CCM (77th)

of WRPC held on 20.4.2018. Representatives from TANTRANSCO and SRPC

attended the meeting. As decided in the 77th CCM of WRPC, one to one meeting with

MPPMCL and SR constituents (Andhra Pradesh, Karnataka and Tamil Nadu) was

held on 9.5.2018 at Jabalpur, to reconcile the figures.

In the 38thCCM the committee noted the following:

a. Subsequent to the 38thCCM, MPPTCL vide letter dated 13.7.2018 requested

MS, WRPC to again arrange and convene a meeting amongst WR and SR

beneficiaries, EREB, OPTCL and SREB so that all matter could be resolved and

settled in totality.

b. In the 39th CCM KSEBL intimated that MPPMCL had requested WRPC for

conducting a joint meeting of SR-WR constituents and OPTCL for settling the

issue.

c. In the 40th CCM, SE, SRPC informed the forum that the matter was taken up

again by SRPC with WRPC. One more meeting would be arranged shortly to

discuss the issue.

• Subsequently, SRPC mail dated 30-05-2019 had requested MS, WRPC to arrange a

meeting among WR and SR Constituents to reconcile the figures and resolve the

matter totally.

The constituents may furnish the update if any.

21. Pending recommendations of the 3rdmeeting of Nodal Officers Nodal Officers for SEM Data Coordination

• The 3rd meeting of Nodal Officers for SEM data coordination was held on 5th August

2016 and the Record notes of the meeting was issued vide SRPC/SE-I/2016/5711-40

dated 19.08.2016.

• The updated status on the pending recommendations are as follows:

i. Pending Installation of SEMs by KPTCL:

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 20/23

• In the 40thCCM KPTCL informed the forum that tender for the meter was

opened and SEM would be installed by KPCL by April 2019

KPTCL/KPCL may furnish the status.

ii. Pending Installation of SEMs by Telangana -Bonakaalu- Chillakallu lines 1&2

• In the 39th CCM TSTRANSCO informed tender to procure SEM was floated

and by December, 2018 SEMs would be installed.

TSTRANSCO may furnish the status.

22. Agenda Points of TANGEDCO deliberated in the 36thto 38thCCM:

Deviation to be computed based on the Schedule revision carried out from 01-05-2015

• As decided in the 37thCCM the DSM for the period 2ndOctober to 8thOctober, 2017and

9thOctober to 15thOctober, 2017 were revised. The draft revised account hadbeen

circulated to all concerned and requested to verify the revised account to finalise the

same.

• In the 40th CCM;

o Tamil Nadu confirmed the account statements.

o KSEBL also stated that the accounts had been verified; and observed that IPPs

had not been included in the lesser of two principle computation. SRPC

clarified that this was done as decided in the previous meeting and KSEBL

confirmed the account.

o Andhra Pradesh and Karnataka sought a weeks’ time to verify and confirm.

o Telangana and Puducherry, who were not represented in the meeting, were also

requested to verify the revised account within a period of one week.

• The Summary of the Account statements are furnished below:

Total Amount based on Revised Account(₹)

Total Amount based on original Account(₹)

Final Transaction details (₹)

Final Status of Payment

Andhra Pradesh -1,50,70,94,051 -1,50,46,51,988 24,42,062 Payable

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 21/23

AP, Karnataka, Telangana and Puducherry may confirm the account

settlement.

23. Settling of Wheeling Charges paid mutually with effect from July 2011.

• The CERC Orders (in KPTCL- Petition No.225/TT/2013, KSEB- Petition No.

232/TT/2013 and TNEB- Petition No.212/TT/2013), mention that the YTC for the

interstate lines have been taken in line with Sharing of Inter-State Transmission Charges

and Losses Regulations, 2010 and the charges reimbursable had been calculated from

1.7.2011. The Wheeling charges indicated at 3(b) of the REA statements issued from

the month of July, 2011 were provisional and issued as inputs from NLDC were

pending. As these lines are to be covered under PoC Mechanism from 1.7.2011, the

Wheeling charges indicated at 3(b) of the REA statements issued from the month of

July, 2011 ceased to have any commercial implications. Accordingly, item No. 3(b) was

not included in REA statement from February 2017. Constituents were requested to

mutually settle Wheeling Charge payment effected from July, 2011, vide SRPC letter

dated 17.3.2017.

• The relevant extract from REAs with effect from July, 2011 in respect of wheeling

charges was circulated.

• In the 38thCCM requested all States to verify and confirm the figures in

theStatement of Wheeling charges for the period from July, 2011 to 31-03- 2018

in order to issue the mutual settlement from July, 2011and in the 39thCCM the

same was confirmed.

Karnataka -2,49,93,33,616 -2,48,79,73,498 1,13,60,118 Payable

Kerala -2,39,30,20,289 -2,39,17,10,279 13,10,010 Payable

Puducherry 23,33,84,963 23,47,87,735 14,02,772 Payable

Telangana 115,53,08,578 116,04,52,871 51,44,293 Payable

Tamil Nadu 67,97,33,127 59,21,40,999 8,75,92,128 Receivable

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 22/23

• SRPC vide letter No: SRPC/SE-I/2018/7126-36 dated 06-11-2018 had circulated

the final statements.

• In the 40th CCM:

Karnataka informed that Telangana reconciled the figures and the

payments were being processed. PCKL requested for a meeting with

KSEBL to resolve certain disputed figures.

Andhra Pradesh was to reconcile.

TN had also requested AP, Karnataka and Kerala for one to one meeting

to reconcile the amount. The forum then requested all concerned to settle

the charges before next CCM.

All entities concerned may update the status of reconciliation and settlement of the account.

24. PXSOLD quantum data for the period 01.05.2017 to 10.12.2017

• The issue of data pertaining to PXSOLD Consent given by states, to compute the

Entitlement values for each state from 01-05-2017 was deliberated in the 38th CCM to

40th CCM.

• Subsequently, NLC, vide email dated 1-10-2018 and NTPC vide email dated

22-10-2018, furnished Traded Quantity for the days of transaction for NLC TPS II

Stage-1, NLC TPS II Stage-2 , NLC TPS 1 Expansion, NTPC Kudgi and SimhadriStage

II. The same had been processed to compatible format.

• However, some discrepancy of data was found (intimated via email dated 25-02-2019)

and it has been observed that the total Beneficiary PX SOLD quantum is not matching

with total Station PX quantum. For some sheets furnished by NTPC, it does not mention

the Beneficiary it has been booked.

• Subsequently, NLC had furnished their details.

NTPC may update the status.

25. Outstanding dues of MEPL to the Regional Pool

• It has been observed that there are large outstanding paymentsto the regional pool due

from MEPL.

• SRLDC may furnish the factual position with update.

Agenda Notes for 41st CCM to be held on 20.6.2019 at SRPC, Bangalore 23/23

MEPL is requested to attend the meeting and update the status.

26. Procedure to Prepare Merit Order Despatch List

• The matter of adoption of uniform procedure to prepare Merit Order Despatch List was

discussed during earlier Commercial Committee Meetings and also during 33rdTCC

and 34thSRPC meetings, and it was decided that the issue would be deliberated in a

separate meeting. Accordingly, SRPC, vide letter dated 20-9-2018, requested all

beneficiaries and regional entities to furnish comments/ suggestions/ factors to be

considered in finalizing a uniform procedure for preparing Merit Order Despatch list,

along with the methodology being followed at present.

• During the 39th CCM, Member Secretary, SRPC clarified that the matter was taken up

only to facilitate the beneficiaries to have a better MOD and requested all beneficiaries

to share views,and requested all SR Constituents, except KSEB, Vallur, and NLC, to

share the details to prepare a draft uniform procedure to frame MOD.

• In the 40th CCM, all the utilities were requested to share the details within a month.

• Subsequently, Andhra Pradesh had furnished the methodology adopted

(ANNEXURE P).

The agenda points would be discussed in the meeting.

27. Commercial Operation Declarationof ISTS Elements&ISGS (CGS) During the Financial Year 2019-20.

The details of approval of each scheme/element accorded by the competent

committee/forum may be mentioned.

ISTS and ISGS are requested to furnish the details, if any.

28. Any other item with the permission of the Chair

29. Date and Venue of 42ndMeeting of CC

The date and Venue of the 42nd Meeting of Commercial Committee may bedecided.

*****

SOUTHERN REGIONAL POWER COMMITTEE

BENGALURU

Additional Agenda for the 41st Meeting of Commercial Sub

Committee of SRPC to be held at SRPC, Bengaluru on

20.06.2019. The following agenda items would be discussed in the meeting:

1. AP Agenda Points

AP vide mail dated 03.06.2019 (ANNEXURE Q) had requested to consider plant

wise dispatch instead of Unit wise dispatch from NTPC Kudgi (3×800 MW) power.

Due to Frequent & prolonged RSDs of the Plant, AP had to confront hurdles to meet

the daily AP Grid Demand.

It has been observed that, while operating, scheduling / dispatching of the Capacity /

Energy generated from Kudgi plant by SRLDC, allocation has been reckoned on Unit

basis rather than on Plant basis. That means unit wise declared capacity is being

allocated to all beneficiaries on the basis of their entitlement. For instance, Karnataka

which is having an allocation of around 54% in the plant, during light load (Grid

Demand) condition prevailing in the State, backs down the generation from Kudgi

Station and thus the unit is forced into Reserve Shut Down mode, since, technical

minimum condition is not fulfilled. This deprives the other beneficiaries of their share

of power.

In such circumstances the States with lesser allocation are unduly got affected due to

Reserve Shut Down instructions (RSD) issued by the major stakeholders depending

on the Load Generation Balance in their grid.

The agenda item would be discussed in the CCM.

2. TANGEDCO Agenda Points

TANGEDCO had requested to include the following agenda points (vide letter dated

06.06.2019, ANNEXURE R) as shown below:

I. Issues related to implementation of the Hon’ble CERC’s order dated

08.03.2019 in Petition No. 92/MP/2015.

a. Based on the above referred CERC Order, CTU has been directed to

calculate the stranded capacity and the compensation (relinquishment

charges) payable by each relinquishing long term customer as per

methodology within one month of date of issue of the Order and

publish the same on its website. CTU has not yet published the same.

b. Further, it was also stated that M/s NLDC, the Implementing Agency

has to ensure that no LTA quantum of generators is socialized in the

PoC pool for the sake of relieving the generators.

II. Delay in Commissioning of the NNTPP Plant

III. Prolonged rerated capacity declaration and inefficient plant management of

NLC TPS-II Expansion

IV. Delay in commissioning of Kalpakkam PFBR by Bhavini.

CTU/NLDC may update on this agenda item.

The matter may be further deliberated in the meeting.

3. Inclusion of all Bilateral Billing including RE Generators

As per CERC Order in Petition No.155/MP/2016 dated 04-01-2017, NLDC/CTU has

been requested to furnish all bilateral billing; including RE Generators to RPC along

with the submission of monthly LTA/MTOA details.

Further, it is also requested that the LTA operationalizion details corresponding to

Renewable Generators may be furnished along with the above said monthly details.

CTU/NLDC may elucidate.

****

APPCC---- Agenda Point for the 41st Commercial Sub-Committee Meeting /SRPC Sub:- Considering Plant wise dispatch instead of Unit wise dispatch from NTPC Kudgi (3×800 MW) power – Frequent & prolonged RSDs to the Plant-hurdles to meet daily Grid Demand by AP

***************

a) The NTPC has developed Kudgi Super Thermal Power Station -Stage 1 with 3×800 MW

configuration in the state of Karnataka. AP DISCOMs in the erstwhile combined AP

State have entered into PPA with M/s NTPC Limited for purchase of power from this

plant on 23/09/2010, subject to the allocation as decided by Govt. of India.

b) Power Purchase Agreement has been entered into by the beneficiary States/Entities for

the entire capacity (3X800=2400 MW) of the Stage-I project.

c) As per the PPA Clause 2.1.1. “Allocation of Capacity from the Station to the State of

Andhra Pradesh shall be as decided by GoI, based on the existing GoI policy.

d) As per Clause 2.2.3, “the allocation made from the Station by GoI or any other

competent authority in favour of APPEDCL shall be the contracted capacity....”

e) The state of Karnataka is having a major share of around 54% in the project and

bifurcated Andhra Pradesh state has a share of 16.03% as per the latest allocation of

Ministry of Power Govt of India. The present share of Andhra Pradesh is 384.72 MW

from NTPC (Kudgi) power plant as per the following breakup.

Firm Share 215.04MW

Bundled power against

NVVNL coal power

14.4MW

Bundled power against

National Solar Mission

phase-II Batch-II Tranch-I

155.28MW

Total 384.72MW.

f) As per Clause 4.1 of the PPA with regard to Scheduling, ..... NTPC shall make

declaration of the capacity at the busbars of the Station after taking into account the

capability of the station to deliver EX-Bus, which shall be considered while calculating

declared capacity.

g) It is observed that, while operating, scheduling / dispatching of the Capacity / Energy

generated from Kudgi plant by SRLDC, allocation has been reckoned on Unit basis

khan
Typewritten Text
Annexure Q (Page1/3)

rather than on Plant basis. That means unit wise declared capacity is being allocated to

all beneficiaries on the basis of their entitlement. Consequent to the implementation of

RSD procedures, in the instant case Karnataka which is having an allocation of around

54% in the plant, and any light load (Grid Demand) condition prevailing in Karnataka

forces that state to back down the generation from Kudgi Station, thus depriving the

other beneficiaries of their share of power since, technical minimum condition is not

fulfilled. Thus the unit is forced into Reserve Shut Down mode.

h) Even though the PPA has been entered into on Plant basis and Fixed Cost is payable

for the entire project as per the monthly REA, the entitlement of the target generation

schedules on Unit basis is hampering the prospects of other states. .

i) In these kind of circumstances the States with lesser allocation are unduly got affected

due to Reserve Shut Down instructions (RSD) issued by the major stakeholders

depending on the Load Generation Balance in their native States. The technical

minimum of operation of each unit is 55%. The major stakeholder has the

allocation almost equivalent to the technical minimum. Once the load in the State which

is having major share, drops below a certain level and Merit order stack doesn't support

the dispatch from Kudgi, the plant is forced to RSD state, there by depriving other

beneficiaries the much needed power, even though the States are feeling under power

shortages.

j) The monthly “Regional Energy Account (REA)” is settled on the basis of entire plant and

not based on individual unit. The fixed costs are also payable based on the overall plant

availability during the month and not segregated Unit wise.

k) During this calendar year 2019 so far, the Kudgi plant was under RSD for several days.

AP has to purchase power from costly sources to substitute the expected allocation from

Kudgi plant, and thus the APDISCOMs have incurred huge mounts. During the period of

1st January to June15th, the Load on the AP system is more and has to be supported by

matching generation from all entitled sources. Had there been generation from Kudgi

station as per the PPA entitlement, the state could have reduced exposure to the open

market.

l) AP is also a RE rich State having combined installed capacity of Wind & Solar at around

7000 MW and further in the interests of grid security and addressing intermittency of RE

generation, hot reserve in terms of base thermal generation is essential in Grid

operation.

khan
Typewritten Text
Annexure Q (Page2/3)

m) Commercial Sub-Committee is requested to deliberate on the issue, and resolve to

recommend to NTPC & SRLDC to carry out Plant wise dispatch instead of Unit wise

dispatch.

*********************************

khan
Typewritten Text
Annexure Q (Page3/3)

Scanned with CamScanner

khan
Typewritten Text
Annexure R (Page1/5)

Scanned with CamScanner

khan
Typewritten Text
Annexure R (Page2/5)

Scanned with CamScanner

khan
Typewritten Text
Annexure R (Page3/5)

Scanned with CamScanner

khan
Typewritten Text
Annexure R (Page4/5)

Scanned with CamScanner

khan
Typewritten Text
Annexure R (Page5/5)