Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
1 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
BEFORE THE NATIONAL GREEN TRIBUNAL
(WESTERN ZONE) BENCH, PUNE
M.ANo. 46/2013
M.ANo.09/2014
IN
APPEAL NO.7/2013
Along with Appeal No.2/2014
CORAM:
Hon’ble Shri Justice V.R. Kingaonkar
(Judicial Member)
Hon’ble Dr. Ajay A.Deshpande
(Expert Member)
B E T W E E N:
1. Dr.(Sau.) Nandini Sushrut Babhulkar, M.D. Age -42 years, Occ: Doctor, R/ at At-Plot,Kanadewadi, Taluka Gadhingalj, Dist: Kolhapur.
2. Shri Narayan Saturam Patil Age-60 years, Occ: Agriculturist, Residing at Navin Vashati, Chandgad, Taluka, CHandgad, Dist: Kolhapur.
3. Shri Umesh Bharamaji Patil Age 40 years, Occ: Service, At Post-Dholgarwadi, Taluka Chandgad, Dist. Kolhapur.
….APPLICANTS
A N D
1. Maharashtra Industrial Development Corporation, Regional office, Kolhapur Udyog Bhavan Nagala Park,
2 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
Near Collector Office, Kolhapur.
2. The Maharashtra Pollution Control Board Through Secretary,
Kalptaru Point,2nd ,4th Floor, Opp Cine planet Cinema,
Near Sion Circle, Sion(E), Mumbai-400022.
3. Government Maharashtra,
Through The Secretary, Environment Department
Room No. 217, 2nd Floor, Mantralaya Annex, Mumbai-400032.
4. M/s. AVII Chemicals Pvt. Ltd,
2nd Floor, Raj Mahal, 84 Veer Nariman Road,
Churchgate, Mumbai-400020.
5. The Ministry of Environment & Forests,
Through its Principal Secretary, Government Of India,
CGO Complex, Lodi Road, New Delhi-110003.
6. The District Collector,
Kolhapur, District Kolhapur.
………Respondents
Counsel for Applicant(s) Mr.Hemant V. Chavan, Sangramsingh R.Bhonsale, Mr. A.B.Bhonsale, Aarti .D.Bhonsale.
Counsel for Respondent(s):
Ms Shamali Gadre, Mr. Deepak Pawar, i/by Little & Co. for Respondent No.1,
Mr. Karl Tamboly w/Ms Sneha Jaisingh Adv i/b Bharucha &
Partners, for Respondent No.4.
…….
3 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
Appeal No.2/2014
B E T W E E N:
Mr. Narsing Patil, Age: 80 Yers, Occ: Social Work (Ex MLA) R/at Plot No.8, ‘Gurukunj, Maratha Colony’ Tilakwadi, Belgaum (Karnataka State) ….APPLICANT
A N D
1. M/s AVH Chemicals P. Ltd & Ors,
2nd Floor, Raj Mahal,
84 Veer Nariman Road,
Churchgate, Mumbai-400020.
2. The Ministry of Environment & Forests,
Through its Principal Secretary,
Government Of India,
CGO Complex, Lodi Road,
New Delhi-110003.
3. State of Maharashtra,
Through The Secretary, Environment Department Room No. 217, 2nd Floor, Mantralaya Annex, Mumbai-400032.
4. The Maharashtra Pollution Control Board
Through Secretary, Kalptaru Point,2nd ,4th Floor, Opp Cine planet Cinema, Near Sion Circle, Sion(E), Mumbai-400022.
5. Maharashtra Industrial Development Corporation, Regional office, Kolhapur Udyog Bhavan Nagala Park, Near Collector Office, Kolhapur.
6. The District Collector, Kolhapur, District Kolhapur ...Respondents
Counsel for Applicant(s) Mr Asim Sarode, Mr. Vikas Shinde, Ms. Pallavi Talware.
4 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
Counsel for Respondent(s)
Mr. Karl Tamboly w/ Ms Sneha Jaisingh Adv i/b Bharucha & Parners
For Respondent No.1.
Mr.Krishna D. Ratnaparkhi, Mr. Amol Nehru, for Respondent No.2.
Mr. D.M.Gupte w/ Supriya Dangare for Respondent Nos.3,4. Shamali Gadre, Deepak Pawar i/by Little & Co. for Respondent No.5.
Date: May 16th, 2014
C O M M O N - J U D G M E N T
1. By this common Judgment, all the above matters, are being
disposed of together, inasmuch as identical question is required to
be determined in both the Appeals and the Misc. Applications.
2. For the sake of convenience, the Appeal No.7 of 2013, will
be treated as leading matter and the relevant averments and
documents filed therein, will be referred for the purpose of
discussion.
3. Original Appellants in Appeal No.7 of 2013, Dr.(Sau)
Nandini Sushrut Babhulkar and Ors, have preferred Appeal against
the Environment Clearance (EC) certificate dated March 28th, 2012,
granted by the Respondent No.3 –SEIAA, i.e. competent authority of
the Environment Ministry of the State of Maharashtra, in favour of
Respondent No.4 M/s AVH Chemicals P Ltd. (For short, hereinafter
referred to as “Chemical Industry”).
4. The same the Environment Clearance (EC) certificate dated
March 28th, 2012, is the subject matter of challenge in Appeal No.2
of 2014, filed by the Appellant – Narsing Patil. Needless to say, both
the matters are clubbed together, in order to avoid over lapping
consideration of the same issues.
5 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
5. Miscellaneous Application No.46 of 2013, is filed in Appeal
No.7 of 2013, by the Appellants for condonation of delay of five (5)
days. It is stated that there is delay of only five (5) days in filing of
the Appeal, which occurred due to time consumed in collecting of
various documents, travelling to Pune, engaging of a Counsel and
preparing the Appeal, along with voluminous record.
6. The Chemical Industry, has filed M.A.No.9/2014, seeking
framing of preliminary issue in respect of bar of limitation, prior to
proceeding with hearing of the appeals and deciding of the same.
On behalf of the Chemical Industry, it is submitted that the Appeal
is hopelessly barred by limitation and therefore, it should not be
taken up for hearing.
7. We have heard learned Counsel, appearing for contesting
parties. We have gone through the relevant record. It is important
to note that in both the Appeals, a categorical statement is made
that the Appellants had preferred Writ Petition (PIL) No.184 of 2013
in the Hon’ble High Court of Bombay, raising identical issues and
challenging the Environment Clearance (EC) certificate dated March
28th, 2012, issued in favour of the Chemical Industry by the State
Environment Ministry (SEIAA). They allege that by Judgment dated
11.10.2013, they were directed by the Hon’ble High Court of
Bombay, to withdraw that Writ Petition with liberty to file
proceedings on the same cause of action in this Tribunal. This
Tribunal has jurisdiction to decide on merits substantial issue
relating to environment. They claim, therefore, that in pursuance of
such Judgment/Order of the Hon’ble High Court of Bombay they
6 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
have withdrawn earlier Writ Petition (PIL) No.184 of 2013 and have
preferred the Appeal.
8. According to the Appellants, limitation period has to be
computed from 11.10.2013, when they were directed to withdraw
the Writ Petition (PIL) No.184 of 2013, with liberty to file the
Proceedings in the NGT. The case of Appellants Dr.(Sau) Nandini
Sushrut Babhulkar and others, is that on the date of filing of the
Appeal, which was filed on 19.11.2013, there was delay of only six
(6) days, if the period is counted from the date of withdrawal of Writ
Petition (PIL) No.184 of 2013. They would submit that the Appeal is
filed six (6) days after the initial period of thirty (30) days, but falls
within period of sixty (60)days as permissible under the proviso
appended to Section 16 of the NGT Act, 2010, and as such, the
delay of six (6) days can be condoned, when the same is
satisfactorily explained. They submit that delay is marginal, duly
explained and condonable under the circumstances.
9. In case of Appeal No.2 of 2014, the Appellant Narsing Patil, states
that there is no delay caused in filing of the Appeal. It is stated in
the Appeal Memo that the Appeal is filed within limitation,
inasmuch as the appellant Narsing Patil, got knowledge about
withdrawal of Writ Petition (PIL) No.184 of 2013 at later date and
therefore, the Appeal is preferred after such knowledge was
received.
10. The questions which emerge for consideration are as
follows:
7 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
1. Whether there is only delay of six (6) days, as contended by
Appellants Dr. (Sau) Nandini Sushrut Babhulkar and
others and it is liable to be condoned?
2. Whether the Appeals are barred by limitation under Section
16 of the NGT Act,2010?
11. Before we proceed to deal with the above questions on
merits, it would be appropriate to consider import of the order
dated October 11th, 2013, passed by the Hon’ble High Court of
Bombay. The copy of said order (P-104) annexed with the Appeal
No.7 of 2013, reveals that withdrawal of Writ Petition was allowed
with liberty to file proceedings on the “same cause of action” before
the NGT. The order itself may be reproduced for the purpose of
clarity:
IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION
PUBLIC INTEREST LITIGATION NO.184 OF 2013
Dr, (Sau) Nandini Shushrut
Babhulkar £ Ors. .. Petitioners
vs.
Maharashtra Industrial Development Corporation & Ors. .. Respondents
Mr. A. S. Desai for Petitioners, Mr. Samir Patil - AGP for Respondent - State, Mr. D. D. Madon - Senior Advocate i/b. Bharucha & Partners for Respondent No. 4. Mr. Y. R. Mishra with N. R. Prajapati for. Respondent No. 6.
AM : DR. D.Y. CHANDRACHUD. AND M.S. SONAK, JJ.
11 October 2013
In view of the judgment of the Supreme Court in Bhopal Gas Peedith
Mahila Sangathan & Ors. vs. Union of India & Ors. we allow the Petitioners'
Counsel to withdraw the petition with liberty to file proceedings on
the same cause of action before the National Green Tribunal. The petition is
8 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
accordingly disposed of.
(Dr. D. Y. Chandrachud, J.)
(M. S. Sonak, J.)
A plain reading of above order, goes to show that Hon’ble
Bench did not by itself direct the Appellants to withdraw the Writ
Petition (PIL) No.184 of 2013. There is no affidavit of concerned
Counsel that the Hon’ble Bench directed him to withdraw the Writ
Petition and as such, it was withdrawn. What appears from the
order is that withdrawal of the Writ Petition was allowed with liberty
to file proceedings in the NGT, ‘on the same cause of action’. In any
case, the Writ Petition itself was not transferred by the Hon’ble High
Court of Bombay for determination of the issues raised therein. Had
it been transfer order passed by the Hon’ble High Court of Bombay,
then all the issues raised in the Writ Petition, could be deemed as
open for consideration.
12. In such a case, there could perhaps be leverage available to
this Tribunal to go into the merits of the matter, particularly in
respect of the issues raised in the Application.
13. As stated before, the order of the Hon’ble High Court
categorically states that the withdrawal of Writ Petition, was
permitted with liberty to file the proceedings in this Tribunal on the
“same cause of action.” This conditional permission for withdrawal
has significance and utmost bearing on the question of limitation
raised as a preliminary objection, on behalf of the contesting
Respondents as well as in regard to condonation of the delay sought
9 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
by the Applicants – Dr. (Sau.) Nandini Sushrut Babhulkar and
others. The very fact that the Writ Petition (PIL) No.184 of 2013 was
filed in the Hon’ble High Court of Bombay, based upon the very
same cause of action, challenging the Environment Clearance (EC)
Certificate dated March 28th, 2012, reveals that the Appeal period
was over as on October 11th, 2013, when the Writ Petition was
withdrawn by the Applicants. The averments in paragraph 11,
where under objections raised by the Applicants are set out, go
show that in October, 2012, the brother of Applicant No.3, namely
Sh. Ramesh Patil, who is working at London, informed him about
information gathered from Internet that the Respondent No.4, is
going to set up Coal Powered Distillery plant at MIDC Halkarni. It
was thereafter that Applicant No.3, Ramesh, gave information to
other Applicants and a meeting was convened on 11.11.2012. The
villagers formed ‘Janhit Andolan Samiti’ to oppose setting of the Coal
Powered Distillery plant by the Respondent No.4, (Chemical
Industry) in MIDC area. Applicant No.3, Ramesh and other people
of the village visited the project site on 16.12.2013, to collect
further information. It is also stated that they came to know that
the Coal Powered Distillery plant is hazardous and obnoxious to
environment and therefore it was necessary to oppose the plant by
issuing circulars, pamphlets etc. The Applicants gathered
knowledge about the impugned Environment Clearance Certificate,
granted to the Chemical Industry, in view of aforesaid facts, after
collecting necessary information and it was more than clear that
they did not file Appeal against such Environment Clearance (EC)
Certificate within prescribed period of limitation, as provided under
10 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
Section 16 of the National Green Tribunal Act, 2010. According to
the Appellants, the E.C. was granted in violation of the
Environment (Protection) Act, 1986, and illegality has continued
‘cause of action’ also has continued. They further submit that after
coming to know about the EC, they immediately started agitation
and therefore the Respondent No.3, granted stay to commissioning
of the project vide an order passed by the Respondent No.3, which
is the subject matter of challenge in the Writ Petition filed by the
Respondent No.4, (Project Proponent) and also that the
Environment Clearance Certificate granted by the Respondent No.3,
- SEIAA, is without jurisdiction and as such the Appeal is within
limitation.
14. The settled legal position is that once limitation has started
running then it cannot be halted in the midst. The Appellants were
required to challenge the Environment Clearance Certificate, dated
March 28th, 2012, within period of thirty (30) days, as
contemplated under Section 16( ) of the NGT Act,2010. Assuming
that for some tangible reason, there was delay on the part of the
Appellants to file the Appeal, yet the delay could not be condoned
beyond period of sixty (60) days. The commencement of period of
limitation has to be computed from the date of ‘communication’ of
impugned Environment Clearance Certificate. The expression
‘communication’ includes placement of such Environment
Clearance Certificate on the website of Environment Ministry of the
State or publication thereof in the newspaper at the behest of the
Project Proponent. As demonstrated earlier, the Appellants have
stated that the information was received by them from the relative
11 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
of the Appellant No.3 that the Environment Clearance Certificate
was granted to the Chemical Industry, as per the Internet
information and news. They had also visited the site of the project.
They had also challenged the Environment Clearance Certificate by
filing the Writ Petition before the Hon’ble High Court. Not only that
but on their own showing they took up the issue by starting
agitations and therefore, the Respondent No.3, (Environment
ministry) granted suspension to the project activities, which
apparently is the subject matter of challenge in Writ Petition filed by
the Project Proponent (Respondent No.4). These are events much
prior to October, 2013 and therefore, it will have to be said that
there was communication of the Environment Clearance Certificate
dated March 28th, 2012, granted in favour of the Chemical Industry
i.e. Respondent No.4, to the Appellants, much earlier than October,
2013. It is pertinent to note that in the present case, the expression
‘communication’ will not be necessarily restricted to mean
communication by way of full-fledged publication of the Notices in
the newspapers, as published by the Project Proponent, or that
putting the said Environment Clearance Certificate in public
domain by the Competent Authority. As a matter of fact, the
averments in the Application, go to show that it was put in the
public domain by the Respondent No.3, and therefore, was available
for perusal of the Appellants, which gave them cause for protest
and to make demand for withholding of the EC granted to the
Chemical Industry (Respondent No.4). The Competent Authority
thereafter granted Suspension/Status Quo. The Respondent No.4,
12 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
filed the Writ Petition against such order of the Competent
Authority. The Appellants too filed writ Petition (IL) No.184 of 2013.
15. The consequence of events indicated above, leave no
manner of doubt, that the Appellants can be imputed with due
knowledge of the Environment Clearance Certificate much prior to
October, 2013. The averments in the Application, would make it
manifestly clear that on 17th December, 2013, the Appellants had
filed Application under RTI Act, in order to obtain information
regarding the setting up of the industrial plant. The relevant
averments made by the Appellants in paragraph 11 (h) may be
reproduced for ready reference :
“11. Objections raised by the Appellants:
(h) the Applicant made Application under RTI to get
the information and various orders issued by the
Respondent Nos. 2 and 3 on 17.12.2012.”
16. They have further alleged in paragraph (i) as below:
“11. Objections raised by the Appellants:
(i) On 28.12.2012 there was a gathering
organized by Applicant No.3 of residents of
Chandgad Taluka at Patne Phata which was
also attended by is Lordship Justice (retired)
Shri. B.G.Kolse Patil and other political leaders
and workers of all political parties and there
were about more than 20000 attended by said
gathering and in the said meeting it was
decided to take strong action to oppose setting
up Coal Tar Distillation Plant by the
Respondent No.4.”
13 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
17. It can be gathered without difficulty, from the averments
shown above that the Appellants received information regarding the
Environment Clearance Certificate at least before the end of
December 2012. The very fact that one of the retired High Court
Judge, namely Sh. B.G.Kolse-Patil, was amongst leading members
who attended gathering of 20,000 people, is indication of the fact
that there was knowledge of Environment Clearance Certificate in
question granted by the Respondent No.3, in favour of the
Respondent No.4.
18. It does not stand to reason that inspite of Application
presented by the Appellants under the RTI Act, they did not receive
any copy of Environment Clearance Certificate dated 28th March,
2012, within reasonable period, nor is it their case that they did not
receive copy of the said EC within a reasonable period. A bare
perusal of the Environment Clearance Certificate, reveals that the
Applicants could be imputed with knowledge that they were
required to file Appeal within period of thirty (30) days in the NGT,
if they wanted to challenge the Environment Clearance Certificate.
This categorical information is stated at the end of the certificate
itself, as shown at serial No.9. i.e. Clause-9, of the Environment
Clearance letter dated 28th March, 2012, which reads as below:
“Any Appeal against this EC shall lie with NGT, Van-
Vigyan Bhawan, Sec-v, R.K.Puram, New Delhi-1100 22,
if preferred within thirty (30) days, as prescribed under
Section 16 of the NGT Act, 2010 ”.
14 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
Obviously, when copy of this Environment Clearance
Certificate was obtained by the Appellants in exercise of the right
under the RTI Act, somewhere at the end of January, 2013, the
Appeal ought to have been preferred by the end of January, 2013.
Admittedly, It was not so done. This Appeal is filed on 19th
November, 2013, which is clearly barred by limitation, even if
maximum stretching of limitation period is permitted in favour of
the Appellants.
19. On behalf of the Appellants, learned Counsel Mr.
Sangramsingh R.Bhonsale, contended that the Environment
Clearance Certificate dated 28th March, 2012, itself is null, void and
must be overlooked because of the fact that it is outcome of fraud,
inasmuch as instead of appraisal of the project under category 5(c)
of the Schedule appended to the EIA Notification dated 14th
September, 1986, it has been purposefully and erroneously
appraised under category 5(f). It is argued that the project ought to
have been assessed for clearance of the MoEF and not for clearance
by SEIAA. In our opinion, this is a disputed question. For
consideration of the Appeal, the question whether impugned
Environment Clearance Certificate is granted by the Competent
Authority, or that the Authority itself is incompetent, is required to
be gone into if the Appeal has to be considered on merits. However,
if the Appeal itself is barred by limitation, then such a question
cannot be considered by this Tribunal, otherwise there will be
hardly any relevance to the preliminary objection pertaining to the
question of limitation and provision made in respect of special
15 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
limitation under Section 16 of the NGT Act, 2010, may become
otiose. Under these circumstances, we do not think it proper to
consider the contention of learned Counsel for the Appellants by
examining merits of the issues involved in the Appeal.
20. At this juncture, we may point out that the learned Counsel
for the Respondent No.4, also invited our attention to certain
observations of the Hon’ble Principal Bench in Application No.1373
of 2013 (MA No.686 of 2013 and MA No.96). The MoEF filed
affidavit of Aditya Naryan Singh, Deputy Director in that matter,
which shows that category of “Coal Tar manufacturing industry”
does not fall under any project or activity of the Schedule appended
to the EIA Notification 2006. It also appears from order dated
January 10th,2014, passed by the Co-ordinate Bench of this
Tribunal at Principal Bench, New Delhi, that on basis of such
affidavit, it is observed that under Sub-clause 5(f) of the Schedule
appended to MoEF Notification dated 14th September 2006, only
“Synthetic organic chemicals industry (dyes & dye intermediates;
bulk drugs and intermediates excluding drug formulations;
synthetic rubbers; basic organic chemicals, other synthetic organic
chemicals and chemical intermediates” is covered. We do not wish
to express any opinion in this behalf. We have pointed out the
contentions of both sides, in order to highlight the issue and show
that such issue is debatable and rather a disputed question. So, it
cannot be perse said that the Environment Clearance Certificate
dated March 28th, 2012, is outcome of fraud and as such stands
vitiated for all the purposes. Resultantly, the Appeal cannot be
entertained without considering the question of limitation for so
16 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
called reason that the Environment Clearance Certificate dated
March 28th, 2012, itself is non-est in the eye of Law.
21. The chronology of the events go to show that after the
agitations, the Respondent No.3 directed that the Environment
Clearance Certificate shall be kept in abeyance. Thereafter, the
Respondent No.4, (Chemical Industry) preferred Writ Petition
No.7098 of 2013, in the Hon’ble High Court of Bombay. By its order
dated August 6th, 2013, the Hon’ble High Court of Bombay granted
interim relief in favour of the Respondent No.4, (M/s AHV
Chemicals P. Ltd). Obviously, the order of Respondent No.3, to keep
the Environment Clearance Certificate in abeyance was stayed and
as such, there was no legal impediment for the Respondent No.4, to
go ahead with the project activity. The affidavit is filed by Shri. J.S.
Thakur, Scientist-II, of the Environment department, shows that in
a meeting dated 23/24 December, 2013, both the parties were
heard and after hearing them, it was decided that since the issue
was subjudiced before the Hon’ble High Court in Writ Petition
No.7098 of 2013, further action should not be taken till outcome of
the Writ Petition No.7098 of 2013, pending before the Hon’ble High
Court of Bombay, is decided and also till the present Appeal is
decided by this Tribunal.
22. There is no dispute about the fact that the Appellants filed
Intervention Application in the Writ Petition No.7098 of 2013, which
is pending before the Hon’ble High Court of Bombay. Admittedly,
their Intervention Application is allowed. The very same issue is
being agitated by them befor the Hon’ble High Court.
17 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
23. Relying upon certain observations, in case of Municipal
Corporatonl, Indore, vs Niyamatullah (dead) by his L.Rs, AIR
1971, SC 97, it is contended that the plea of limitation under the
special statute, may not be considered when an action is without
jurisdiction. In given case, a Govt. servant was dismissed by
Incompetent Authority. The dismissal could be ordered only by the
Competent Authority. Therefore, it was held that “action did not fall
within mischief of Section 135(2) of Indore Municipal Council Act,
and it was governed by Article 120 of the Limitation Act”. As stated
before, we cannot presuppose that the Environment Clearance
Certificate dated March 28th, 2012, is by itself issued by an
Authority, having no jurisdiction to do so and is issued without
jurisdiction available to SEIAA. The competency of the Authority is
the subject matter of the dispute, which is not yet determined on
merits.
24. It need not be reiterated that the Writ Petition No. 7098 of
2013, is pending before the Hon’ble High Court of Bombay. The
Appellants have the legal forum available to ventilate their grievance
before the Hon’ble High Court of Bombay. So far as the question of
limitation is concerned, we are not satisfied with the contention of
the Appellants that the Appeal is filed within period of limitation,
because the Environment Clearance Certificate, is issued by
Incompetent Authority. In Rauf Ahmed Vs State of Chhattisgarh and
others (Appeal No.1 of 2003), a Coordinate Bench of this Tribunal
(Central Zone Bench, Bhopal) held that “the period of limitation
cannot be extended by the Tribunal, in view of the language used in
Section 16 of the NGT Act,2010.” The Hon’ble Bench of Central
18 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
Zone, further observed that the order of transfer of Writ Petition in
view of Bhopal Gas Peedith Mahila Sangathan & Ors. vs. Union of
India & Ors. NGT by itself would not cover up the issue of
limitation, inasmuch as such issue had been kept open for decision
of the Tribunal. In present case too, withdrawal of the Writ Petition
was permitted by the Hon’ble High Court of Bombay with liberty to
approach this Tribunal on the ‘same cause of action’ which would
indicate that whatever cause of action had triggered at the time of
filing of the said Writ Petition, was the same and was the starting
point for the purpose of limitation in respect of present Appeal or
any other remedy which the Appellants could have availed of.
Considering this aspect of the matter, we find that the Appeal is
filed beyond period of limitation, as envisaged under Section 16 of
the NGT Act, 2010. Learned Counsel for the Respondent No.4, has
referred to observations in Ms. Medha Patkar Vs MoEF and Ors in the
Judgment of Hon’ble Principal Bench, passed in Appeal No. 1 of
2013. The Hon’ble Principal Bench elaborately considered the
issue of limitation by referring to the expression “communicaton”
and the other expressions in the context of cause of action. Similar
issue is considered in
1. Janhit Seva Samiti& Anr. V. Union of India & Ors. [Misc Application
No.59 of 2011].
2. Consumer Federation Tamil Nadu v. Union of India [Appeal No.33 of
2011 (PB.NGT)]
3. State Level Environment Impact Assessment Agency v. Tamil Nadu &
Ors [Appeal No.5 of 2012 (PB, NGT)]
4. Grampanchayat Tiroda & Anr V. MoEF & Ors [Appeal No. 2 of 2013
(WZ)]
19 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
5. Aradhana Bhargav & Ors. V. MoEF & Ors [Application No.11 of 2013
(P.B 46/2013 THC)]
25. It is not necessary to elaborate the discussion on the ratio
laid down in each of the above referred Judgments. Suffice to say
that the period of limitation is circumscribed by the specific
provision of the special enactment, namely, the National Green
Tribunal Act, 2010. Obviously, this Tribunal has no discretion to
extend the period by taking aid from the general provisions of the
Limitation Act. The negative expression used in the language of
Section 16 of NGT Act, creates embargo on flexibility in the context
of the limitation available for filing of the Appeal. Having regard to
legal position enumerated hereinabove, we have no hesitation in
holding that the Appeal is barred by limitation.
26. For the reasons discussed in the foregoing paragraphs, we
are inclined to allow the Misc Application No.46/2013, and hold
that the Appeals are barred by limitation. Consequently, MA
No.46/2013, is allowed. The Appeals are dismissed, as being barred
by limitation. However, it is made clear that we have not considered
any issue raised in the Appeal on merits. We are of the opinion that
the Appellants have raised certain important issues, which need
consideration and have already been allowed to intervene in the
Writ Petition No.7098 of 2013, and they are at liberty to agitate the
said issues. The Misc. Application No. 46 of 2013, and both the
Appeals are accordingly disposed of. No costs.
..……………………………………………, JM (Justice V. R. Kingaonkar)
20 (J) M.A. No.46/2013, MA No.9/2014, In Appeal No.7/2013 with Appeal No.2/2014
….…………………………………………, EM (Dr.Ajay A. Deshpande)