Upload
ngohanh
View
213
Download
0
Embed Size (px)
Citation preview
Order _ Case No 290 of 2018 Page 1
Before the
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION
World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005
Tel. 022 22163964/65/69 Fax 22163976
Email: [email protected]
Website: www.mercindia.org.in/www.merc.gov.in
Case No. 290 of 2018
Case of M/s Adani Power Maharashtra Limited for approval of relief under Change in
Law for shortfall in domestic coal under SHAKTI Policy.
Coram
Anand B. Kulkarni, Chairperson
Mukesh Khullar, Member
M/s Adani Power Maharashtra Limited … Petitioner
V/s
Maharashtra State Electricity Distribution Co. Ltd. … Respondent
Appearance
For APML : Shri. Saurabh Roy (Adv.)
For MSEDCL : Shri. Ashish Singh (Adv.)
ORDER
Dated: 07 February, 2019
1. M/s Adani Power Maharashtra Limited (APML), “ Adani House”, Near Mithakali Six
Road, Navrangpura, Ahmedabad- 380 009, has filed a Petition under Section 86 read
with Section 63 of the Electricity Act, 2003(EA, 2003) and Article 13 of the Power
Purchase Agreement (PPA) dated 8 September, 2008 (1320 MW), and Article 10 of the
PPAs dated 31 March, 2010 (1200 MW), 9 August, 2010 (125 MW) and 16 February,
2013(440 MW) for approval of relief under Change in Law for shortfall in domestic coal
under Scheme for Harnessing and Allocating Koyala (Coal) Transparently in India
(SHAKTI) policy after 31 March, 2017 along with Carrying Cost.
2. APML’s main prayers are as follows:
a) Hold and declare that introduction of SHAKTI Policy is change in law event.
b) Hold and declare that the Petitioner is entitled to get relief under Change in Law
provision of PPAs for any shortfall/ non-availability of domestic coal after 31.03.2017
vis-à-vis the quantity assured under NCDP 2007.
Order _ Case No 290 of 2018 Page 2
c) Allow recovery of compensation for the period after 31.03.2017 as per the same
methodology as approved in Order dated 7.3.2018 in Case no. 189 of 2013 and 140 of
2014 until the supply of the domestic coal is restored to 100% as assured in the NCDP
2007.
d) Grant carrying cost along with relief for domestic coal shortfall as prayed herein in
respect of the PPAs dated 08.09.2008, 31.03.2010, 09.08.2010 and 16.02.2013; and
e) Approve the interim relief at 75% of the compensation payable based on the
methodology approved in Order dated 07.03.2018 in Case no. 189 of 2013 and 140 of
2014, subject to adjustment based on final order in the present case.
3. APML in its Petition has stated that:
3.1. It owns and operates a generating station of 3300 MW (660 MW X 5) at Tiroda in
Maharashtra. APML and MSEDCL have entered into four PPAs being (a) PPA dated
08 September, 2008 for 1320 MW, (b) PPA dated 31 March, 2010 for 1200 MW, (c)
PPA dated 09 August, 2010 for 125 MW and (d) PPA dated 16 February, 2013 for 440
MW. PPAs provide for relief under Change in Law qua any events subsequent to Cut-
off Date (i.e. 7 days prior to Bid Deadline) under the respective PPAs. Cut-off Date is
14 February, 2008 and 31 July, 2009 under the 1320 MW and under other PPAs
respectively.
3.2. The Ministry of Coal (MoC), Government of India (GoI) on 22 May,2017, notified
SHAKTI Policy whereby:
a. The supply of coal for period after 31 March, 2017 was continued to be restricted to
75% of Annual Contracted Quantity (ACQ) as against 100% of normative quantity
as was assured under NCDP 2007.
b. All the pending applications for LoA were closed and this resulted in taking away
the entire assurance which was there under NCDP, 2007.
3.3. While issuing the Order dated 1 October, 2018 in Case No. 167 of 2018, the
Commission has granted liberty to file fresh Petition in respect of Change in Law for
SHAKTI Policy and carrying cost on the relief granted through the Order dated 07
March,2018 in Case No. 189 of 2013 and 140 of 2014 till 31 March, 2017.
3.4. APML is therefore seeking relief in respect of Change in Law under respective PPAs
for non-availability/ short supply of domestic coal under SHAKTI Policy after 31
March, 2017 along with carrying cost.
3.5. The Commission vide Order dated 07 March, 2018 has held that the impact of the
Change in Law shall be available until the end of FY 2016-17, i.e., till the last year of
Order _ Case No 290 of 2018 Page 3
the 12th
plan period referred to in the CCEA decision and the NCDP 2013. Further, in
its Order dated 01 October, 2018 in Case No. 167 of 2018, the Commission has also
noted that SHAKTI scheme has stipulated continuation of shortfall in domestic coal.
3.6. In terms of the SHAKTI Policy, coal supply beyond the period of 31 March, 2017 is
continued to be restricted to 75% of the ACQ as against the 100% assurance given
under NCDP 2007. Also, the Applications pending for LOA under NCDP 2007 were
closed. Further, in the said Policy, while introducing the scheme for linkage auction,
GOI has stipulated that the old regime of LoA-FSA would come to finality and fade
away. It means that with the introduction of SHAKTI Policy, there is no grant of coal
linkages as assured under NCDP 2007.
3.7. Thus, even after the end of the 12th
Plan Period (i.e., March 31, 2017), the availability
of domestic linkage coal under the extant policy of the GOI continues to be restricted to
75% of ACQ. Also, all the pending applications for LoA have been closed and hence
there shall be no coal linkage against such pending applications contrary to the
assurance given to supply 100% coal in NCDP, 2007 prevailing at the time of Cut-off
dates for respective PPAs.
3.8. Further, as stipulated at Para B(ii) of the SHAKTI Policy, the Power producers/IPPs
having concluded PPAs based on domestic coal with Distribution Companies are
eligible to participate in bidding process for grant of coal linkages on notified price
through auction by offering discount in the PPA tariff (in paisa/unit). The Policy
stipulates for amending / supplementing the concluded PPA to pass on such discount to
the consumers with the approval of Appropriate Commission. As per the requirement
stipulated in the process for grant of coal linkage under the said Policy, CEA sought
details of the PPAs signed by the developers against coal based thermal power project
for which coal linkage is sought in the specific format, duly authenticated from the
concerned DISCOMs / Lead procurer. APML therefore furnished the PPA details duly
endorsed by the MSEDCL to the CEA. CEA confirmed that APML is eligible for
participation in the process since the PPA is based on Domestic coal as endorsed by the
MSEDCL.
3.9. Accordingly, APML participated in the auction process and became Successful Bidder
for the allocation of 5.84 MMT coal linkages from MCL, SECL and WCL by way of
giving discount (in the range of 1 to 3 paise /unit).
3.10. Under SHAKTI Policy FSA, ACQ was only 5.84 MMT. Therefore, as against the
assurance of 100% coal availability under NCDP, 2007, APML is getting substantially
reduced quantum in terms of SHAKTI Policy. This is in addition to the shortfall as
stipulated in Para (A) of the SHAKTI Policy to restrict coal supply at maximum 75%
even after March 2017.
3.11. As per Judgment of the Supreme Court in Energy Watchdog v. CERC & Ors. dated
11April, 2017 read with provisions of the PPA, introduction of SHAKTI Policy would
Order _ Case No 290 of 2018 Page 4
qualify for Change in Law since SHAKTI is a policy notified by GoI which is at par
with NCDP and therefore has force of Law. The same is also acknowledged by the
Commission in its Order dated 01 October, 2018 in Case No. 167 of 2018.
3.12. The SHAKTI policy envisages the short supply or non-availability of coal beyond the
12th
Plan i.e. beyond 31 March, 2017, therefore the impact of Change in Law would
commence from the date the policy is affecting the supply of coal i.e. 01 April, 2017.
This is in line with the judgment of the Supreme Court in Energy Watchdog which has
held that insofar as procurement of Indian coal is concerned, to the extent the supply
from Coal India or other Indian sources are cut down, relief is to be granted to the
affected party under Change in Law provisions of the PPA from the date the policy
affects or impacts the supply of coal. It is pertinent to note that the Supreme Court has
not restricted the principle of granting relief under Change in Law to any date rather it
has stated that relief is to be granted as long as there is cut down in coal supply by CIL
or other Indian sources.
3.13. Change in Law provisions of the respective PPAs mandate that the affected party is to
be restored to the same economic position as if Change in Law did not take place. Since
actual coal materialization as a consequence of the SHAKTI Scheme is still much
below the 100% normative quantity assured under the NCDP, 2007, the relief for
Change in Law ought to continue beyond 31 March, 2017 till such time 100% assured
coal under NCDP 2007 is supplied by Coal India Ltd.
3.14. The Commission has already approved a mechanism for claiming relief under Change
in Law for domestic coal shortfall through the Order dated 7 March, 2018 in Case No.
189 of 2013 and 140 of 2014 for the period upto 31 March, 2017. Since the basis of
domestic coal shortfall remains the same albeit through successor SHAKTI Policy in
place of NCDP, APML is entitled for relief on similar basis.
3.15. Therefore, it is requested to approve the shortage/ non-availability of coal vis-à-vis the
quantity assured under NCDP as Change in Law and allow APML to claim
compensation as per the methodology approved by the Commission in the Order dated
07 March, 2018 in Case No. 189 of 2013 and 140 of 2014 for the Period from 1 April
2017.
3.16. As per Article 13.2 and 10.2 of the 1320 MW and 1200/125/440 MW PPAs
respectively, Change in Law relief is based on the Restitution Principle and requires the
affected party to be restored to the same economic position as if the Change in Law
event had not occurred. One of the key ingredients for such restitution as contemplated
under the PPAs would be payment of 'carrying cost'. Thus, payment of carrying cost is
imperative to achieve the true objective of restitution. This aspect was also recognized
by the Supreme Court of India in the Energy Watchdog v. CERC & Ors. Judgment.
3.17. Payment towards Change in Law events results in additional burden to APML and if
not reimbursed immediately by the procurer, results in increase in working capital
Order _ Case No 290 of 2018 Page 5
interest. Grant of carrying cost is in line with Section 61(b), (c) and (d) of the EA, 2003
to conduct generation, transmission and distribution on commercial principles. Carrying
cost is also a well-established concept which has been re-emphasized by the GoI in
Clause 8.2.2 of the Tariff Policy, 2016.
3.18. ATE in its Order dated 13 April, 2018 in the matter of Adani Power Ltd Vs CERC &
Others (Appeal No. 210 of 2017) has held that the impact of Change in Law is to be
done in the form of adjustment to the tariff which is nothing less then re-determination
of the existing tariff and that interest (i.e. carrying cost) is payable till re-determination
of tariff.
3.19. ATE in its Judgment dated 20 December, 2012 in Appeal No. 150 of 2012 had
recognized the principle of carrying cost. ATE Judgment in Appeal No. 210 of 2017 as
decided on 13 April, 2018 would reveal that the said judgment is merely upholding the
Law as laid down in the SLS Case. Recently, based on the above ATE judgment, this
Commission vide Order dated 19 April, 2018 has allowed carrying cost while approving
Change in Law compensation under Case No. 102 of 2016 at the rate applicable for
working capital interest calculation as per MYT Regulations, 2015.
3.20. Therefore, it is requested to grant carrying cost from the date the Change in Law events
have affected APML to the date of Order by the Commission in the present case in
respect of relief granted under (i) the Order dated 189 of 2013 & 140 of 2014 dated 07
March, 2018 and (ii) Order under the present Petition in order to achieve the objective
of restitution.
3.21. The Commission’s Order in Case No. 102 of 2016 relates to one of the PPAs under
consideration in the present Petition and therefore the Commission may consider the
rate applicable for working capital interest calculation as per MYT Regulations, 2015
for carrying cost claimed under the present Petition.
3.22. The Commission has already held that shortage/non-availability of domestic coal
supply is Change in Law and allowed compensation to APML for the same PPAs for
the period up to March 2017 keeping in view the applicability of CCEA decision up to
31 March, 2017. As the coal supply post March 2017 is also restricted by the GoI
through a policy decision, APML has a very strong prima facie case for succeeding in
the case and getting relief from the Commission. Further, admittedly APML had to
procure imported coal to the extent of shortfall by incurring higher cost. APML is under
severe financial stress due to non-recovery of the relief for domestic coal shortfall and
unable to continue operations. Shutdown of power plant due to non-availability of
sufficient funds for working capital needs would cause irreparable loss to it. Therefore,
it is requested to grant interim relief and direct MSEDCL to pay 75% of the
compensation subject to adjustment based on final decision in the Case. Such interim
payment also benefits the MSEDCL/End Consumer since the burden of carrying cost
will get reduced to that extent. It is pertinent to note that CERC, in IA No. 57 of 2017 in
Order _ Case No 290 of 2018 Page 6
Case No. 97/MP/2017 vide Order dated 28 September, 2017, has approved interim
relief at 75% of the amount claimed in similar matter.
4. MSEDCL in its submission dated 3 December, 2018 has stated that:
4.1. SHAKTI policy is framed with the broad perspective to provide the coal, to the utilities
having either no linkages or to provide the linkages to utilities having imported coal
based power plants, for reduction in power generation cost. As a part of this policy,
CIL/SCCL is to grant coal linkages on notified price on auction basis for Independent
Power Producers (IPPs) having already concluded domestic coal based Power Purchase
Agreement (PPAs), with the bidding parameter being levellised discount on existing
tariff that the IPP is willing to provide. This was expected to result in a win-win
situation for IPPs having a long term supply security of coal from a source of their
choice while consumers will benefit from a lower tariff.
4.2. SHAKTI policy also assures to provide additional coal quantum in future. As provided
in the policy, coal supply to the LOA/FSA holders continue to get 75% of ACQ and the
coal supply to these capacities may be increased in future based on coal availability.
Further, there are no directives specified by MoC for any pass through of coal cost
similar to NCDP 2013. SHAKTI policy has given the coal linkage for the IPPs
contracted under Section 63 PPAs with an assurance that the coal linkage may be
increased in future on basis of availability. MoC is taking the efforts to make the
incremental coal supply as committed in the policy. Instead of following up with coal
supplier for additional supply of coal, APML by wrong interpretation of SHAKTI
Policy is seeking compensation under Change in Law.
4.3. Hence the contention of APML, that SHAKTI policy envisages the short supply or non
availability beyond 12th
Plan i.e. beyond 31 March, 2017, and therefore the change of
law event has occurred, is no correct. NCDP 2013 has a specific provision of cost pass
through for alternate source of coal supply on account of shortage of linkage coal.
Contrary to this, there is no specific provision of any directive for similar pass-through
in the SHAKTI policy.
4.4. As per PPA provisions, to make the claims under Change in Law, the seller shall have
to provide to procurer and the Commission, the documentary proof of such increase /
decrease in cost for establishing the impact of change in Law. Hence the contention of
APML that the SHAKTI policy is continuation of NCDP 2013 is completely deceptive.
In fact there is assurance of coal to FSA/LOA under the old regime and the new coal
linkage is granted for those IPPs who had signed PPAs with Discoms.
4.5. APML has reproduced only the selective portion of the policy and is creating the false
impression that SHAKLTI policy will lead to shortfall in coal supply. In fact, SHAKTI
policy is the assurance of coal linkage to the IPPs who have already signed PPAs and is
also assuring them an increase in coal supply in future. Policy should be read
harmoniously with next statement in totality and not in part i.e. ….would continue to get
Order _ Case No 290 of 2018 Page 7
coal at 75% of ACQ even beyond 31.03.2017. The coal supply to these capacities may
be increased in future based on coal availability. APML has composed the relevant
suitable portions of the policy to co-relate it with NCDP 2013 and to get relief under
Change in Law.
4.6. APML has wrongly interpreted the efforts of MoC about the assurance and future Coal
supply. APML accepted that it was allocated the 5.8475 MTPA of coal for 2120 MW
capacities (balance capacity of the plant after considering already signed FSA of
1180MW). Hence it is clear that APML has got coal linkage for 3300MW capacity.
Hence there is no shortfall of coal linkage for Tiroda Power Plant after getting
allocation from SHAKTI policy.
4.7. APML’s contention that due to the SHAKTI policy the availability of coal is restricted
up to 75% of ACQ is wrong and misleading. As per CIL web site data and the data
available with the MSEDCL, the availability of domestic coal is increased by 11% and
APML and Adani Power Rajasthan Ltd is to be supplied with 9.9MT of coal during the
year 2018-2019 from various coal mines of SECL like Korba , Raigarh, korea rewa
mines, Mahanadi coal field, Basundhara and Talcher mine. Thus, instead of following
up with the coal suppliers, APML has filed petition for compensation due to Change in
Law.
4.8. The carrying cost sought by APML is not justifiable in as much as the Parties had never
specifically agreed to compensate towards carrying cost on account of the impact of the
Change in Law, more particularly not contemplating the inclusion of the same in Clause
10.3 of the PPA.
4.9. The ATE in the case of SLS Power Ltd. Vs. APERC & Ors., Appeal No. 150 of 2011
has specifically rejected the similar relief, as sought by the Applicant/Petitioner herein
qua claim of carrying cost de hors the terms of the PPA.
4.10. Further as per Clause 10.3.4 of the PPA, The Commission is the final authority for
determination of the compensation and unless and until such compensation is not being
determined by the Commission, MSEDCL cannot be compelled to make any payment
towards the alleged demand of compensation, which otherwise has been rejected by the
Commission.
4.11. The carrying cost is recognized normally in cases of monies being denied at the
appropriate time. There is no dispute on the fact that the amount payable gets
determined and becomes payable only after such determination, and thus there is no
liability to make payment until the decision of the Appropriate Commission on Change
in Law. Therefore, amounts do not become legally due and payable until the decision of
the Appropriate Commission. In view of the above MSEDCL requests the Commission
not to allow any carrying cost. Further the Commission may not grant the relief to
APML for Change in Law under SHAKTI policy.
Order _ Case No 290 of 2018 Page 8
5. During the hearing held on 4 December, 2018 APML reiterated its submissions as made
in its Petition. MSEDCL raised a preliminary issue against APML that it has not
followed the mandatory/obligatory clauses of the PPAs which were essential
requirement for any claim to be sought under Change in Law. MSEDCL stated that
APML has not followed due procedure as provided under the provisions of the PPA and
had not notified MSEDCL about the effect of Change in Law. In reply, APML stated
that since the Petition was filed before the Commission seeking only declaratory relief,
the Notice to MSEDCL was not served. APML further stated that it will serve notice to
MSEDCL as required under the relevant clauses of PPA. The Commission granted a
week to APML to file its submissions and reserved the matter for final Orders.
6. APML in its additional submission dated 10 December, 2018 has stated that:
6.1. The present Petition has been filed in pursuance of this Commission’s Order dated 1
October, 2018 in Case No. 167 of 2018 which was filed seeking review of Orders of
this Commission in Case No. 189 of 2013 and 140 of 2014. Vide Order dated 01
October, 2018, the Commission was pleased to dismiss the said Review Petition but, in
its wisdom, had granted liberty to file fresh petition in respect of Change in Law for
SHAKTI Policy and carrying cost.
6.2. SHAKTI Policy has replaced the earlier policy i.e. NCDP by stipulating the treatment to
be given to the applications for coal linkage, LoA and FSAs under the NCDP. The
SHAKTI Policy has resulted in short supply/ non-availability of coal even after the end
of the 12th
Plan Period (i.e., 31 March, 2017). In terms of the Supreme Court’s order
and judgment in Energy Watchdog v. CERC & Ors. dated 11 April, 2017, shortfall in
the domestic coal supply after 31 March, 2017 is Change in Law. As a natural corollary
and extension of the same principle, the shortfall in domestic coal supply under the
SHAKTI Policy, is Change in Law.
6.3. The effect of relief under Change in Law has to be from the date the Change in Law
occurred and not from date of Order of the Commission. (clause 13.4.1 of the 1320 MW
PPA and clause 10.5 of the 1200 MW, 440 MW and 125 MW PPA).
6.4. APML disagrees with the contention of MSEDCL that there has to be a direction for
pass through. There need not be any mention of pass through in the SHAKTI Policy to
enable APML to get Change in Law relief. The principle of restitution in the PPA itself
is enough to enable APML to get relief. Even NCDP 2013 didn’t specifically mention
pass through, yet relief was given. Hence, if any event qualifies for Change in Law, the
relief to be provided under principle of restitution under PPA needs to be followed and
no further direction is required for pass through.
6.5. Contention of MSEDCL that no notice of Change in Law event was served for the
shortfall under SHAKTI policy is misleading. There was no occasion for a fresh notice
for coal shortfall under SHAKTI Policy as the shortfall in coal supply was already
Order _ Case No 290 of 2018 Page 9
under consideration in Case Nos. 189 of 2013 and 140 of 2014 decided on 7 March,
2018 and in Case No. 167 of 2018 decided on 1 August, 2018.
6.6. As the Petition for Change in Law for shortfall in coal (including SHAKTI) was
pending before this Commission there was no occasion for APML to privately deal with
MSEDCL on the said issue.
6.7. Through FSAs entered under Shakti Policy, APML got combined quantum of 5.84
MTPA for Gross PPA capacity of 2120 MW from SECL, WCL & MCL. Hence, there
is shortfall in coal supply with reference to normative coal requirement assured under
NCDP 2007. Further, in view of the restriction of coal supply to 75%, there is further
increase in curtailment of coal supply.
6.8. It has claimed Carrying Cost based on the principle of restitution as enumerated in the
Change in Law provisions of the PPAs. Further, decision of ATE granting carrying cost
dated 20 December, 2012 in Appeal No. 150 of 2012 in the matter of SLS Power had
recognized the principle of carrying cost (SLS Decision). The said decision is binding
and applicable in full force upon this Commission. The SLS decision was upheld by the
ATE again in Appeal No. 210 of 2017 as decided on 13 April, 2018. Even this
Commission has upheld Carrying Cost in its judgement dated 19 April, 2018 in Case
No. 102 of 2016.
6.9. Carrying cost is also a well-established concept which has been re-emphasized by the
GoI in Clause 8.2.2 of the Tariff Policy, 2016. The Tribunal in its Order dated 13 April,
2018 in the matter of Adani Power Ltd Vs CERC & Others (Appeal No. 210 of 2017)
has held that the impact of Change in Law is to be done in the form of re-determination
of the existing tariff and interest (i.e. carrying cost) is payable till re-determination of
tariff.
6.10. Delay in grant of the relief would not only aggravate the financial situation of APML
but also place additional burden of avoidable carrying cost on the end consumers
Therefore, considering the consumer interest as of paramount importance, the prayers in
the present Petition ought to be allowed.
6.11. MSEDCL in its reply to the Petition has referred to the ATE Judgment dated 20
December, 2012 in Appeal No. 150 of 2011 (SLS Power Ltd. Vs APERC & Ors.) and
has submitted that the ATE has rejected the similar relief as sought by APML herein.
However, it is observed that ATE in the said judgment has allowed carrying cost. The
relevant para is extracted hereunder:
“35.5 The principle of carrying cost has been well established in the various
judgments of the Tribunal. The carrying cost is the compensation for time value
of money or the monies denied at the appropriate time and paid after a lapse of
time. Therefore, the developers are entitled to interest on the differential amount
due to them as a consequence of re- determination of tariff by the State
Order _ Case No 290 of 2018 Page 10
Commission on the principles laid down in this judgment. We do not accept the
contention of the licensees that they should not be penalized with interest. The
carrying cost is not a penal charge if the interest rate is fixed according to
commercial principles. It is only a compensation for the money denied at the
appropriate time.”
6.12. Therefore, it is prayed to grant carrying cost from 01 April, 2017 to the date of Order at
rate applicable for working capital interest calculation as per MYT Regulations, 2015.
7. APML in its further additional submission dated 18 December, 2018 has stated
that:
7.1. The contention by MSEDCL that notice is not served for SHAKTI Policy is incorrect as
many letters were written to MSEDCL (i) in relation to SHAKTI Policy and amendment/
approval of PPA as required under the SHAKTI Policy and (ii) in relation to
continuation of restriction of coal supply to 75% and its consequences on APML as well
as MSEDCL/ end Consumers before filing the present Petition.
7.2. On 2 August, 2017, APML informed MSEDCL about SHAKTI Policy and requested to
authenticate the PPA details to be submitted to CEA. In response vide letter dated 9
August, 2017, MSEDCL has certified the details to be submitted to the CEA for
participation under SHAKTI option. Subsequently, Supplementary PPA was signed on
24 January, 2018 and approved by the Commission on 20 March, 2018.
7.3. APML through number of letters intimated to MSEDCL that the coal supply restriction
of 75% of ACQ continued even under SHAKTI Policy and as a result, APML is forced
to utilize costlier imported coal to mitigate such shortage in coal supply which resulted
in severe financial hardship on APML. Letters dated 8 September, 2018, 1 and 19
October, 2018, 1, 13 and 27 November, 2018 have indicated the shortfall in coal supply.
Therefore it is clear that APML has filed the Petition before the Commission on 10
October, 2018 after giving ample notices to MSEDCL regarding SHAKTI Policy and the
shortage in coal supply there under.
7.4. In the submission filed by APML on 3 June, 2017 (in Case No. 189 of 2013) i.e. after
remand by the ATE based on the Supreme Court Judgment dated 11 April, 2017 in
Energy Watchdog case, APML prayed for grant of relief for past period as well as for the
future period. Subsequently, APML in the affidavit filed on 9 November, 2017,
specifically made submission regarding continuation of restriction of coal supply to
75%.
7.5. MSEDCL in its Written Submission dated 27 November, 2017 (in Case No. 189 of
2013), while replying to the submission of APML in affidavit dated 9 November, 2017,
stated that issues relating to SHAKTI Policy are irrelevant for the purpose of relief in the
Case No. 189 of 2013. The same is recorded at Para 19.13 of the Commission’s Order
dated 7 March, 2018 in Case No.189 of 2013. The above fact makes it evident that the
Order _ Case No 290 of 2018 Page 11
issue related to relief for coal shortages under SHAKTI Policy was already pleaded
before the Commission and both APML as well as MSEDCL have made submissions in
that regard.
7.6. Therefore, MSEDCL now cannot take a stand that APML has not given notice under
SHAKTI Policy. It is pertinent to note that, no objection was raised by MSEDCL with
regard to notice, any time earlier including its recent Reply dated 3 December, 2018 filed
in present Petition. This is because SHAKTI is continuation of earlier Change in Law.
Therefore, the contention of MSEDCL is only an afterthought and raised during the
hearing on 4 December, 2018. In view of the above, the contention of MSEDCL that
APML has not given notice about SHAKTI Policy does not sustain.
8. MSEDCL in its additional submission dated 26 December, 2018 (Reply to APML’s
Rejoinder dated 10 December, 2018) has stated that:
8.1 The Clause No. 13.3 of 1320 MW PPA and Clause 10.4 of 1200 MW/125 MW /440
MW PPA clearly provides that for any Change in Law under Article 13/Article 10 for
the respective PPAs a seller (APML) should give notice to the procurer (MSEDCL) of
such Change in Law as soon as reasonably practicable after becoming aware of the same
or should reasonably have known of the Change in Law. Further this Notice shall
provide , precise details of ;
(a) The Change in Law and
(b) The effects on the Seller of the matters referred
8.2 In accordance with above PPA clauses, APML has not served a Notice on it regarding
SHAKTI policy as a Change in Law mentioning precise details of the Change in Law
and the effects on the Seller (APML).
8.3 Ministry of Coal has issued Notification dated 22 May, 2017 regarding introduction of
SHAKTI Policy and has given certain guidelines for allocation of coal linkages to power
sector. Under SHAKTI policy there are different options to get the coal allocations for
power plants as;
Coal Linkage on auction basis for IPPs:
A. Having PPA based on Domestic Coal
(a) Bid for discount in existing tariff (paise/unit)
(b) A minimum discount in tariff to be determined
(c) Discount to be adjusted from Gross amount at time of billing
B. Without PPA
(a) Bid for linkages over CIL notified price
(b) PPA to be submitted within 2 years
C. Having PPA based on Imported Coal
(a) Transparent Bidding process of linkages
Order _ Case No 290 of 2018 Page 12
8.4 As per Coal allocation under B(ii) option of SHAKTI policy APML had applied for
obtaining the coal linkage from CIL. One of the pre-requisites for this was to furnish the
details of Power station and relevant information in prescribed format to CEA. APML
vide letter dated 2 August, 2017 requested MSEDCL for providing the details of PPA for
furnishing in Bid document of SHAKTI policy under B(ii) option for receiving the coal
linkage for Tiroda Power plant. However, in additional submission APML has
contended that this request letter is the Notice of Change in Law for SHAKTI Policy.
This is completely misleading and should not be considered as notice of Change in Law.
8.5 Further APML has contended that various letters were written to MSEDCL mentioning
the present coal scenario. These letters are not Notice as per the provisions under PPA
and should not be considered as Notice of Change in Law.
8.6 Hence, MSEDCL request the Commission to reject APML’s instant Petition as the
letters given to MSEDCL are not precise Notice with Change in Law details as per the
provisions of PPA signed between APML and MSEDCL and also not to grant the relief
to APML for Change in Law under SHAKTI policy.
Commission’s Analysis and Ruling
9. The Commission notes that APML has filed the present Petition under Section 86 read
with Section 63 of the EA, 2003 and Article 13 of the PPA dated 08 September, 2008
(1320 MW), and Article 10 of the PPA dated 31 March, 2010 (1200 MW), 09 August,
2010 (125 MW) and 16 February, 2013(440 MW) entered into with MSEDCL. APML is
seeking approval for relief under Change in Law for shortfall in domestic coal under
SHAKTI policy from 1 April, 2017 along with Carrying Cost.
10. The Commission also notes that MSEDCL has raised preliminary objection that APML
has not complied with mandatory requirement of notifying Change in Law event to
procurer under the PPA before filing this Petition. In this regard, relevant provisions of
PPAs are reproduced below:
PPA Dated 8 September, 2008
13.3 Notification for Change in law:
13.3.1 If the seller is affected by a Change in Law in accordance with Article
13.2 and wishes to claim a Change in Law under this Article, it shall give
notice to the Procurer of such Change in Law as soon as reasonably
practicable after becoming aware of the same or should reasonably have
known of the Change in Law.
13.3.2 Notwithstanding Article 13.3.1, the seller shall be obliged to serve a
notice to the procurer under this Article 13.3.2 if it is beneficially affected by
Order _ Case No 290 of 2018 Page 13
a Change in Law. Without prejudice to the factor of materiality or other
provisions contained in this Agreement, the obligation to inform the
Procurer contained herein shall be material. Provided that in case the Seller
has not provided such notice, the Procurer shall have the right to issue such
notice to the Seller.
13.3.3 Any notice served pursuant to this Article 13.3.2 shall provide,
amongst other things, precise details of:
(a) the Change in Law; and
(b) the effects on the Seller of the matters referred to in Article 13.2.
PPA dated 31 March, 2010, 9 August, 2010 and 16 February, 2013
10.4 Notification of Change in law:
10.4.1 If the seller is affected by a Change in Law in accordance with Article
10.1 and the Seller wishes to claim relief for such a Change in Law under
this Article 10, it shall give notice to the Procurer of such Change in Law as
soon as reasonably practicable after becoming aware of the same or should
reasonably have known of the Change in Law.
10.4.2 Notwithstanding Article 10.4.1, the seller shall be obliged to serve a
notice to the Procurer under this Article 10.4.2, even if it is beneficially
affected by a Change in Law. Without prejudice to the factor of materiality
or other provisions contained in this Agreement, the obligation to inform the
Procurer contained herein shall be material.
Provided that in case the Seller has not provided such notice, the Procurer
shall have the right to issue such notice to the Seller.
10.4.3 Any notice served pursuant to this Article 10.4.2 shall provide,
amongst other things, precise details of:
(a) the Change in Law; and
(b) the effects on the Seller.
11. Thus, as per Articles of the PPA, it is mandatory for the Seller (APML) to serve the
Notice to the procurer (MSEDCL), if it wishes to claim relief under Change in Law.
Such notice should include details of Change in Law and effect of it on the Seller.
Subsequent to such Notice, both parties may agree or disagree on such claim of Change
in Law. Decision of the Commission on compensation for event of Change in Law is
final and binding on both the parties subject to right of appeal provided in the applicable
Law.
Order _ Case No 290 of 2018 Page 14
12. Admittedly, APML has not served Notice to MSEDCL notifying Change in Law on
account of SHAKTI Policy. In reply, APML has stated that it was not able to do that as
matter of Change in Law on account of shortage in Coal supply was pending before this
Commission. In this regard, the Commission notes that in Case No. 189 of 2013 and 140
of 2014 which was decided on 7 March, 2018, the issue of Coal Shortage was related to
NCDP 2013 and not with SHAKTI Policy. Relevant part of Order is reproduced below:
“15. The Commission notes that Impugned Order dated 7 March, 2018 was issued in the
matter remanded back by APTEL vide its Judgment dated 4 May, 2017. Original matter
in Case No. 189 of 2013 and 140 of 2014, which was remanded back by APTEL for fresh
consideration of the Commission, was filed for Change in Law relief on account of
shortage of coal as per NCDP, 2013. Since, the scope of original matters was limited to
NCDP, 2013 which covers time period upto 31 March, 2017, the Commission has
restricted Change in Law relief upto 31 March, 2017. The Commission also notes that
during remand back proceedings, APML has never pleaded / prayed /emphasized on
SHAKTI Policy for continuing Change in Law relief beyond 31 March, 2017. Reference
of SHAKTI policy in affidavit dated 9 November, 2017 was limited to the Competitive
bidding process in which APML has participated and not in terms of Change in Law
effect to be admissible for Original Petition. Therefore, the issue which was never
pleaded in the original matter cannot be ground for review of the Order in that matter.
The issue raised by APML in this review Petition, seeking extension of Change in Law
relief beyond March 2017 not being part of original Petition is clearly outside the scope
of review of the order thereon. Accordingly the issue raised by APML to give Change in
Law relief as per SHAKTI Policy is rejected.[Underline added]
Thus, APML’s claim that issue of coal shortage on account of SHAKTI Policy was
pending before the Commission is not correct. However, in the same Order, the
Commission allowed APML to file separate Petition for seeking compensation on
account of SHAKTI Policy.
13. Accordingly, APML has filed this Petition seeking compensation under Change in Law
on account of SHAKTI Policy. The Commission notes that requirement of serving notice
under the PPA for claiming compensation under Change in Law is a mandatory
provision under the PPA. APML has contended that it has informed the MSEDCL about
coal shortage even after notification of SHAKTI Policy at several times which fulfills
the requirement of notice under the PPA. Whereas, MSEDCL contended that PPA
stipulate details to be provided along with such notice, and hence letters informing coal
shortage situations cannot be treated as notice under the PPA. In this regard, the
Commission notes that MSEDCL is relying on technical requirement of serving notice
for rejecting APML’s claim. It is a matter of fact that issue of Coal Shortage on account
of NCDP Change was sub-judice before the Commission and was decided on 7 March,
2018. Further, subsequent to SHAKTI Policy, APML has written several letters to
MSEDCL providing Coal Shortage situation. One of such letter dated 8 September, 2018
reads as follows:
Order _ Case No 290 of 2018 Page 15
“ As you are aware, APML had secured linkage coal of 5.8475 MTPA under SHAKTI
policy of Ministry of Coal. But as the coal supply restriction under NCDP 2013 is
continued at 75% of ACQ even under SHAKTI policy, the position has not improved
as expected. We are therefore forced to utilize costlier imported coal to mitigate the
shortage in coal supply from Coal India Ltd. This has been resulting in severe
financial hardship to us due to under recovery of energy charges and consequential
burden on end consumer. Hence due to non-availability of funds for procurement of
coal, presently, Tiroda Plant is operating at super-critical coal stock position.”
(Underline added)
From the above letter, it is observed that APML has communicated adverse impact of
coal shortage after notification of SHAKTI Policy to MSEDCL. Thus, even though
APML has not served a notice which it usually serves for other incidences of Change in
Law, it cannot be denied that APML has not apprised MSEDCL about adverse financial
implication of SHAKTI Policy. In 25 year long PPA, it is expected that both the parties
work in the spirit of the PPA provisions. Hence, in the opinion of the Commission, it
would not be proper to reject the claim of Change in Law merely on technical ground of
not serving proper notice when broad implications of such event have already been
communicated in writing in other forms and energy generated from such alternate coal
source has actually been consumed by MSEDCL. Hence, the Commission decides to
address the issues in this Petition on its merits.
14. The Commission notes that in its Order dated 7 March, 2018 in Case No. 189 of 2013, it
has dealt with issue of Coal shortage in terms of New Coal Distribution Policy (NCDP),
2013. APML has contended that SHAKTI Policy has extended the dispensation of
NCDP, 2013. Hence, it is pertinent to refer Order dated 7 March, 2018. Relevant part of
the Order is reproduced below:
“
21. APML and MSEDCL have entered into various PPAs for supply of power from
Units 1 to 5 of the Tiroda TPP, as follows:-
Table 1: PPAs between APML and MSEDCL
Particulars Unit 2 Unit 3 Unit 1 Unit 4 Unit 5
Installed Capacity 660 MW 660 MW 660 MW 660 MW 660 MW
Contracted in the
PPA(s) dated 8 September, 2008
*1200 MW in PPA dated 31 March, 2010
*125 MW in PPA dated 9 August, 2010
*440 MW in PPA dated 16 February, 2013
Total PPA
Contracted Capacity 1320 MW from Units 2 & 3 1765 MW from Units 1,4 and 5
Originally envisaged
coal
source as per
Definition in PPAs
Coal from Captive Mine, Linka
ge Coal and Imported Coal
Domestic Coal
Originally envisaged
coal
Source as per
No Schedule relating to Coal
Source
Schedule 5 A of PPA: Details of Generation
Source as submitted in the RfP Bid
Order _ Case No 290 of 2018 Page 16
Particulars Unit 2 Unit 3 Unit 1 Unit 4 Unit 5
Schedule of PPA Primary Fuel – Domestic Coal
FSA for all 5 Units
Captive Coal Block (800 MW)
Linkage with SECL/WCL (1180MW)
Imported Coal Supply for Five Years and Long-
Term Coal Linkage (1320 MW)
Schedule 5 B of PPA: Details of Primary Fuel
as submitted in the RFP Bid
Primary Fuel – Domestic/Imported Coal
Fuel Source for all 5 Units
Captive Coal Block (800 MW)
Linkage with SECL/WCL (1180MW)
Imported Coal Supply for Five Years and Long-
Term Coal Linkage (1320 MW
Current coal supply
arrangement
Linkage Coal
through FSA:
520 MW;
Tapering
Linkage (for
Captive Coal
Block): 140
MW
Tapering
Linkage (for
Captive Coal
Block)
Linkage Coal
through FSA
MoU with CIL
subsidiaries
MoU with CIL
subsidiaries
Note: * Units 1, 4 & 5 have been contracted in a combined manner with MSEDCL
through 3 different PPAs.
22. As will be seen from the above Table, the generation capacity having FSA is 520
MW of Unit 2 and 660 MW of Unit 1, i.e., 1180 MW. The generation capacity
having MoU is 660 MW of Unit 4 and 660 MW of Unit 5, i.e., 1320 MW.
……………….
29. The Supreme Court has, thus, identified the events of Change in Law, and the PPA
provides for consequent relief to the extent that the assured supply from CIL and its
subsidiaries is reduced due to such Change in Law, including the CCEA decision of
21 June, 2013 and the subsequent NCDP Amendment of 2013.
30. GoI notified the NCDP 2007 on 18 October, 2007 assuring supply of 100% of the
normative coal requirement to the IPPs at the price notified by CIL….
………..
31. It is evident from a plain reading of the NCDP 2007 that GoI had given an
unequivocal commitment to meet the coal requirement of all IPPs/ Generators
through linkage/FSA for domestic coal up to 100% of their normative requirement.
Further, the commitment to supply domestic coal through linkage/FSA was also
applied to all future capacity addition. The NCDP 2007 also provided that, in case
Order _ Case No 290 of 2018 Page 17
of shortfall in domestic coal, CIL may even import coal to meet the full
requirements under FSAs, which reflects GoI’s commitment to supply coal through
linkage/FSA to all existing and future Power Projects.
…..
32. Thus, the CCEA decision of 21 June, 2013 effectively approved amendment of the
NCDP 2007 so as to curtail the supply of domestic coal through linkage/FSA at the
CIL-notified price, as against the assured 100% normative quantity, to 65-75% of
the ACQ in the 12th
Plan Period. The balance coal requirements were to be met
through imports on a cost-plus basis, with the higher cost of imported coal to be
considered for pass through. Further, as per the mechanism approved by CCEA,
FSAs were to be executed only for the generation capacity covered under 78000
MW (with approved coal linkages), and a separate mechanism was to be explored
for supply of coal to the generation capacity of 4660 MW and other similar cases
which did not have any coal linkage.
…..
36. The revised Tariff Policy of 28 January, 2016 also refers to and reiterates the MoP
Advisory (which was itself in pursuance of the CCEA decision) to pass-through the
cost of meeting the shortfall through imports or e-auction coal against the quantum
of domestic coal from CIL which was earlier assured:
……….
37. In terms of the ratio laid down by the Supreme Court in the Energy Watchdog
Judgment, it is clear that the change in the coal supply assurance contained in the
NCDP 2007 brought in through various directives and culminating in the NCDP
2013 notified by the MoC constitutes a Change in Law event. Therefore, Generators
relying on domestic coal supply from CIL and whose bids were based on such
supply, having been adversely affected by the curtailment in the supply of coal and
non-issuance of domestic coal linkage/ LoA/FSA, are entitled to relief on account of
such Change in Law in terms of their PPAs
……..
42. ..............In the present Petition, APML has not sought any relief on account of
Change in Law for this 800 MW capacity, and the Change in Law event discussed in
this Order is not applicable to this capacity.............
...............
43. In view of the foregoing, the Commission concludes that the Change in Law
provisions are applicable to the generation capacity tied up under PPAs from both
Units 1 & 2 (1180 MW) as well as Units 4 & 5 (1320 MW) to the extent discussed
above.
.........
C. QUANTUM OF DOMESTIC COAL AND BASE PRICE FOR COMPENSATION
FOR CAPACITY TIED UP UNDER PPAs FROM 1180 MW CAPACITY HAVING
FSAs (Units 1 & 2)
...........
72. From the CCEA decision and the consequent NCDP 2013 and MoP Advisory
quoted earlier, it is clear that the shortfall in domestic coal supply by CIL for Units
Order _ Case No 290 of 2018 Page 18
1 & 2 having FSA has to be determined with reference to the minimum assured
supply of 65%, 65%, 67% and 75% for the corresponding year of the 12th Plan
Period. The Change in Law for these Units having FSA is to the extent that the
assured quantity of coal supply has been curtailed from 100% of the normative
requirement under NCDP 2007 to 65%-75% of the requirement under NCDP 2013.
Hence, if in any year the actual coal supply by CIL is, say, only 50% and the
minimum assured quantum for the relevant year was 75%, the shortfall in CIL
supply for the purpose of Change in Law relief would be 25 % (100% earlier
assured minus 75% now assured), and not 50% (100% earlier assured minus 50%
actually supplied). The shortfall in actual coal supply against the revised assured
quantum is a contractual matter between APML and CIL in the background of the
NCDP 2013, and not on account of Change in Law. The Commission also finds
merit in MSEDCL’s contention that the quantum of coal offered by CIL should be
considered for determining the shortfall rather than the actual off-take out of it by
APML. Hence, the shortfall in domestic coal supply by CIL should be assessed with
reference to the maximum of (1) actual quantum of coal offered for offtake by CIL,
and (2) the minimum assured quantum as per the NCDP 2013 for the respective
year.
………
D. QUANTUM OF DOMESTIC COAL AND BASE PRICE FOR COMPENSATION
FOR CAPACITY TIED UP UNDER PPAs FROM 1320 MW CAPACITY HAVING
MOU (Units 4 & 5)
……….
78. As discussed earlier, this 1320 MW capacity was included in the additional capacity
of 4660 MW referred to in the CCEA decision and the NCDP 2013. Had there been
no shortage of coal, this generation capacity would also have got linkage coal
under the earlier NCDP 2007 dispensation. The basic principle of compensation for
Change in Law is that the economic position of APML as on 7 days prior to the cut-
off date is to be restored to the extent that it is affected by the Change in Law. Had
the NCDP 2007 continued to be operative, APML was assured of being supplied
100% of its normative coal requirement at the CIL notified price. If, however, due to
the Change in Law in terms of NCDP 2013, either the quantity or the price has been
changed to APML’s disadvantage, the entire differential in quantity and price
would have to be allowed to restore APML to the same economic position as it was
on the cut-off date.
……….
84. In view of the foregoing, the effective date for compensation for the impact of
Change in Law as approved in this Order shall be the later of (1) SDD, (2) NCDP
2013 (26 July, 2013), and (3) the actual date of commencement of power supply
under the respective PPAs. The impact of the Change in Law shall be considered till
the end of FY 2016- 17, i.e. the last year of the 12th
Plan referred to in the CCEA
decision and the NCDP 2013.”
Order _ Case No 290 of 2018 Page 19
15. Thus, in terms of Order dated 7 March, 2018 in Case No. 189 of 2013, the Commission
has concluded as follows:
(a) Seven days prior to cut-off date, NCDP 2007 was applicable which assured supply of
100% normative coal requirement at the CIL notified price.
(b) Shortfall in coal supply with reference to assured normative quantity under
NCDP, 2007, needs to be compensated under Change in Law provisions of PPA.
(c) APML had not sought any relief on account of Change in Law for 800 MW capacity
relating to Lohara Coal Block, and this Order is not applicable to 800 MW capacity
(d) Shortfall in domestic coal supply for 1180 MW capacity of Units 1 & 2 having
FSA has to be determined with reference to the minimum assured supply of 65%,
65%, 67% and 75% (as per NCDP, 2013) for the corresponding year of the 12th Plan
Period. Hence, if in any year the actual coal supply by CIL is, say, only 50% and the
minimum assured quantum for the relevant year was 75%, the shortfall in CIL supply
for the purpose of Change in Law relief would be 25 % (100% earlier assured minus
75% now assured), and not 50% (100% earlier assured minus 50% actually supplied).
(e) As against, 100 % assured normative supply under NCDP, 2007, there is no FSA for
1320 MW capacity of Units 4 & 5. Hence, entire differential in quantity and price is
allowed to restore APML to the same economic position with respect to 1320 MW.
(f) The impact of the Change in Law under this Order is applicable till the end of FY
2016- 17, i.e. the last year of the 12th
five year Plan referred to in the CCEA decision
and the NCDP 2013.
16. Against the above background, the Commission now deals with APML’s claim of
Change in Law relating to SHAKTI Policy. This policy has been notified by the Ministry
of Coal (MoC), Government of India (GoI) on 22 May, 2017. Under the provisions of
PPAs, an event arising from the actions of an authority covered within the definition of
‘Indian Governmental Instrumentality’ would be covered within the definition of
“Change in Law”. “Indian Government Instrumentality’ as defined under the PPA
includes any Ministry of the Government of India. The Ministry of Coal being Ministry
under the Government of India is satisfying the requirement of ‘an Indian Government
Instrumentality’ under the PPAs. Further as per Energy Watchdog Judgment of the
Supreme Court, if there is a change in any consent, approval or licence available or
obtained for the Generation Project, which results in a change in the cost of generation
and supply of the contracted power, it would be governed by the Change in Law
provisions of the PPAs. Accordingly, any change in the assurance of supply of coal by
amendment to the NCDP 2007 is a Change in Law for which relief can be claimed by
the Seller. Relevant part of Supreme Court Judgment is reproduced below:
Order _ Case No 290 of 2018 Page 20
...53. However, in so far as the applicability of clause 13 to a change in Indian
law is concerned, the respondents are on firm ground. It will be seen that under
clause 13.1.1 if there is a change in any consent, approval or licence available or
obtained for the project, otherwise than for the default of the seller, which results
in any change in any cost of the business of selling electricity, then the said seller
will be governed under clause 13.1.1. It is clear from a reading of the Resolution
dated 21st June, 2013, which resulted in the letter of 31st July, 2013, issued by
the Ministry of Power, that the earlier coal distribution policy contained in the
letter dated 18th March, 2007 stands modified as the Government has now
approved a revised arrangement for supply of coal. It has been decided that,
seeing the overall domestic availability and the likely requirement of power
projects, the power projects will only be entitled to a certain percentage of what
was earlier allowable. Both the letter dated 31stJuly, 2013 and the revised tariff
policy are statutory documents being issued under Section 3 of the Act and have
the force of law. This being so, it is clear that so far as the procurement of Indian
coal is concerned, to the extent that the supply from Coal India and other Indian
sources is cut down, the PPA read with these documents provides in clause 13.2
that while determining the consequences of change in law, parties shall have due
regard to the principle that the purpose of compensating the party affected by
such change in law is to restore, through monthly tariff payments, the affected
party to the economic position as if such change in law has not occurred.
Further, for the operation period of the PPA, compensation for any
increase/decrease in cost to the seller shall be determined and be effective from
such date as decided by the Central Electricity Regulation Commission. This
being the case, we are of the view that though change in Indonesian law would
not qualify as a change in law under the guidelines read with the PPA, change in
Indian law certainly would.
54. However, Shri Ramachandran, learned senior counsel for the appellants,
argued that the policy dated 18th October, 2007 was announced even before the
effective date of the PPAs, and made it clear to all generators that coal may not
be given to the extent of the entire quantity allocated. We are afraid that we
cannot accede to this argument for the reason that the change in law has only
taken place only in 2013, which modifies the 2007 policy and to the extent that it
does so, relief is available under the PPA itself to persons who source supply of
coal from indigenous sources. It is to this limited extent that change in law is held
in favour of the respondents. Certain other minor contentions that are raised on
behalf of both sides are not being addressed by us for the reason that we find it
unnecessary to go into the same. The Appellate Tribunal’s judgment and the
Commission’s orders following the said judgment are set aside. The Central
Electricity Regulatory Commission will, as a result of this judgment, go into the
matter afresh and determine what relief should be granted to those power
generators who fall within clause 13 of the PPA as has been held by us in this
judgment.”
17. As SHAKTI Policy has been notified by an Indian Government Instrumentality i.e. the
Ministry of Coal and it is notified on 22 May, 2017 which is after the cut off date under
the PPAs, the Commission holds that notification of ‘SHAKTI Policy’ is an event of
Change in Law under the PPAs signed between APML and MSEDCL.
Order _ Case No 290 of 2018 Page 21
18. Now to analyze impact of SHAKTI Policy on APML, relevant clauses of Policy are
reproduced below:
“ The proposal of Coal linkages Allocation Policy for Power Sector has been
under examination in this Ministry. With the approval of Cabinet Committee on
Economic Affairs (CCEA), the following policy guidelines for allocation of Coal
linkages to Power Sector have been decided:
(A) Under the old regime of LoA-FSA:
………..
iii. The capacities totaling about 68,000 MW as per the decision of CCEA dated
21.06.2013 would continue to get coal at 75% of ACQ even beyond 31.03.2017.
The coal supply to these capacities may be increased in future based on coal
availability.
…………
(B) The following shall be considered under a New More Transparent Coal
Allocation Policy for Power Sector, 2017 – SHAKTI (Scheme for Harnessing and
Allocating Koyala (Coal) Transparently in India):
.........
(ii) CIL/SCCL may grant coal linkages on notified price on auction basis for
power producers / IPPs having already concluded long term PPAs (both under
section 62 and section 63 of The Electricity Act, 2003) based on domestic coal.
Power producers/IPPs, participating in auction will bid for discount on the tariff
(in paise/unit). Bid Evaluation Criteria shall be the non-zero Levellised Value of
the discount (applying a pre-notified discount rate) quoted by the bidders on the
existing tariff for each year of the balance period of the PPA. Ministry of Coal
may, in consultation with Ministry of Power, work out a methodology on
normative basis to be used in the bidding process for allocation of coal linkages to
IPPs with PPAs.
…….”
19. Thus, as per SHAKTI Policy, Coal supply to APML’s plant will be governed by the
following:
(a) Generating capacities whose coal supply was curtailed as per CCEA decision dated
21 June, 2013 for the remaining period of 12th
five year plan i.e. up to 31 March,
2017, will continue to get coal at 75% of ACQ even beyond 31 March, 2017. The
coal supply to these Generating capacities may be increased in future based on coal
availability.
(b) IPP having already concluded PPA under Section 63 of the Electricity Act, 2003
may get Coal allocation after participating in auction process by quoting discount in
tariff.
Order _ Case No 290 of 2018 Page 22
20. MSEDCL in its submission has rightly stated that SHAKTI Policy does not deal with
only shortage of Coal but has also provided methodology for allocating new coal FSA
through various auction routes. Accordingly, by exercising option under clause (B) (ii)
of the SHAKTI Policy, APML has successfully participated in auction conducted under
SHAKTI Scheme for 5.8475 MTPA coal for 2120 MW capacity of its Tiroda plant with
tariff rebate of 1 to 3 paise/kWh. The Commission in its Order dated 20 March, 2018 in
Case No. 70 of 2018 has allowed modification in PPA for allowing such rebate against
5.8475 MTPA of coal allocated under SHAKTI Scheme. Thus, subsequent to coal
allocation under SHAKTI scheme, APML has FSA for 1180 MW under old regime and
for 2120 MW under new regime, thereby having FSA for total capacity of 3300 MW i.e.
installed capacity of APML’s plant at Tiroda (5 x 660 MW).
21. However, as mentioned in clause A(iii) of the SHAKTI Policy, APML will continue to
get only 75% of ACQ for its FSA of 1180 MW signed under old regime, till
improvement happens in coal availability. Further, as per model FSA for auction under
SHAKTI scheme, compensation for short supply of coal is triggered only when the
allocation was below 75% of ACQ. Hence, the Commission notes that even though
APML has now got FSA for its full generating capacity at Tiroda, coal supply under
these FSAs is restricted to 75% of ACQ. Such shortage of Coal linkage allocation needs
to be seen with respect to assurance of 100% normative coal requirement for its power
station under NCDP, 2007 which was prevailing at the time of cut-off date.
22. While opposing claim of compensation under SHAKTI Scheme, MSEDCL has
contended that as against CCEA decision in the year 2013 and NCDP, 2013, there is no
mention about pass through of cost of alternate coal in SHAKTI Policy. In this regard,
the Commission notes that compensation for short supply of coal under NCDP, 2013
was given as per principle of ‘restitution to same economic position’ as stipulated under
the Change in Law provisions in PPA, in accordance with the order of Supreme Court in
Energy Watchdog Judgment, and not just because CCEA/NCDP, 2013 states so. Hence,
in the opinion of the Commission, if event is qualified as Change in Law under the PPA,
then compensation has to be given so as to restitute the affected party to the same
economic position as if such Change in Law has not occurred.
23. As observed earlier, notification of SHAKTI Policy constitutes Change in Law event
under the PPAs. Hence, the Commission rules that APML needs to be compensated for
shortfall of coal on account of reduction in coal supply allocation (not below 75% of
ACQ) under SHAKTI Policy as against 100% normative requirement assured under
NCDP, 2007. Further, till the time new FSA was signed under SHAKTI Policy, the coal
supply had already commenced in the year 2018 without any FSA for corresponding
generating capacity. Thus for that period, as ruled under its Order dated 7 March, 2018
in Case No. 189 of 2013, entire differential in quantity and price is allowed as Change in
Law compensation to restore APML to the same economic position with respect to 1320
MW capacity of Unit 4 and 5.
Order _ Case No 290 of 2018 Page 23
24. Methodology and parameters to be used for computing relief under the Change in Law
for capacity having FSA and not having FSA has already been mentioned in Order dated
7 March, 2018 in Case No. 189 of 2013. Same methodology and parameters should be
adopted for computing relief under Change in Law for the period beyond 31 March,
2017 till availability of coal improves and APML gets assurance of coal supply
equivalent to 100% of its normative requirement as assured under NCDP, 2007.
25. Notwithstanding the dispensation ruled above, the Commission is of the opinion that in
case of Change in Law event which has a continuing impact, intent of the notice needs to
be understood in broader prospective.
25.1. Such notice should be treated as intimation from the seller to the buyer that cost
of power will become higher on account of higher cost of fuel procured from
alternate source so as to supply the full contracted power as per PPA. Under such
circumstances, before scheduling such power which is generated from the costly
alternate coal/fuel, buyer i.e. the Distribution Licensee who is mandated to keep its
power procurement costs at lowest possible level, could look for the other
alternate cheaper sources of power supply, if available. For a Distribution
Licensee to undertake such measures so as to reduce its cost of power procurement
it is important that it gets proper intimation from the Seller of such possibility of
increase in cost of power from contracted sources well in advance.
25.2. If Distribution Licensee finds such higher rate not competitive in comparison with
other available sources for procurement of power, then it can ask the Generator
not to generate such power using coal from alternate sources. Based on such
inputs, if the Distribution Licensee decides not to schedule energy generated from
costly coal and intimates such decision to Maharashtra State Load Despatch
Center (MSLDC), then for the purpose of approving Daily Schedule, even though
Generator could declare higher availability on account of adequate coal stock
procured from alternate source, SLDC should consider capacity intimated by the
Distribution Licensee as schedulable capacity of such Generator.
25.3. In the past, in order to optimize its power procurement cost, MSEDCL has given
zero schedules/Reserved Shutdowns to Generators which are placed at higher
level in Merit Order Stack. Methodology stipulated in this Order is on those
similar principles. Although such advance intimation of the rate would be an
estimated value only and not the final rate, the methodology will strengthen the
existing MoD mechanism wherein generators are placed in MoD stack based on
its variable rate for previous period.
25.4. With advance intimation of rate, Distribution Licensee will be in better position to
optimize its power procurement cost while the sanctity of giving a notice
containing full details about any incidence of change in law would also be
Order _ Case No 290 of 2018 Page 24
maintained. It is certainly not a perfunctory exercise, but a choice to the buyer to
evaluate its options while dealing with the cost impact.
26. Accordingly, in line with the above mentioned analysis, in future, APML needs to
intimate to MSEDCL about estimated impact on energy charge for using costly alternate
source of coal whenever it falls short of the allocation under the linkage coal. The
Commission expects that this methodology would be implemented with effect from 1
March, 2019. Meanwhile, MSEDCL and APML should work out modalities including
frequency and time of communicating such advance intimation of estimated impact of
Change in Law within the provisions/principles of the PPAs. Further, APML should
continue its efforts to get maximum possible coal under FSA and wherever possible,
MSEDCL should support such efforts so that cheaper coal is available to APML and
thereby use of costly coal is avoided.
27. As far as issue of carrying cost is concerned, vide Order dated 3 August, 2018 in Case
No 124 of 2018 the Commission has allowed M/s Adani Power Maharashtra Ltd.
(APML) to levy the carrying cost from the effective dates from which it was affected and
incurred expenditure on account of the approved Change in Law events till the date of
that Order. Moreover the Commission finds that in the Judgment dated 20 December,
2012 in Appeal No. 151 of 2011, the ATE has in fact upheld the principle of time value
of money and carrying cost as follows:
“35.5 The principle of carrying cost has been well established in the various judgments
of the Tribunal. The carrying cost is the compensation for time value of money or the
monies denied at the appropriate time and paid after a lapse of time. Therefore, the
developers are entitled to interest on the differential amount due to them as a
consequence of re- determination of tariff by the State Commission on the principles laid
down in this judgment. We do not accept the contention of the licensees that they should
not be penalized with interest. The carrying cost is not a penal charge if the interest rate
is fixed according to commercial principles. It is only a compensation for the money
denied at the appropriate time.”
28. In view of above and considering settled position of Law regarding carrying cost, the
Commission allows APML to claim carrying cost from the date the Change in Law events
have affected it to the date of the present Order. Further the rate of interest for the
payment of carrying cost shall be as specified for the interest on working capital in the
MYT Regulations applicable to the relevant periods.
29. Hence, the following Order:
Order _ Case No 290 of 2018 Page 25
ORDER
1) Case No. 290 of 2018 is allowed.
2) Shortage of Coal allocation subsequent to 31 March, 2017 qualifies as Change in
Law event.
3) The impact of Change in Law event should be computed from the date it affects
APML. Such payment of compensation is subject to the conditions stipulated in
para 24 above.
4) The Commission allows APML to levy the carrying cost from the effective dates
from which it was affected and incurred expenditure on account of the approved
Change in Law event till the date of this Order.
5) As shortage in linkage coal allocation is likely to continue, before scheduling
power generated from alternate costly coal, methodology stipulated in para 25
and 26 needs to be complied with by both the parties to PPA.
Sd/- Sd/-
(Mukesh Khullar) (Anand B. Kulkarni)
Member Chairperson