Upload
lamnhi
View
219
Download
2
Embed Size (px)
Citation preview
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 1 of 17
Before the
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION
World Trade Centre, Centre No.1, 13th
Floor, Cuffe Parade, Mumbai 400005.
Tel. 022 22163964/65/69 Fax 22163976
Email: [email protected]
Website: www.merc.gov.in/www.mercindia.org.in
CASE No. 148 of 2017
Petition of Tata Power Co. Ltd. (Generation) seeking suspension of medium-term
competitive bidding for procurement of 750 MW by BEST Undertaking
And
CASE No. 150 of 2017
Petition of The Tata Power Co. Ltd. (Distribution) for clarity on certain matters relating
to medium-term competitive bidding for procurement of 750 MW power by BEST
Undertaking
Coram
Shri Anand B. Kulkarni, Chairperson
Shri Azeez M. Khan, Member
Shri Deepak Lad, Member
Tata Power Co. Ltd. (Generation) ....Petitioner (Case 148/2017)
Tata Power Co. Ltd. (Distribution) ...Petitioner (Case 150/2017)
Vs.
Brihanmumbai Electric Supply & Transport Undertaking ....Respondent 1
State Transmission Utility ....Respondent 2
Maharashtra State Electricity Distribution Co. Ltd. ....Respondent 3
Reliance Infrastructure Ltd ....Respondent 4
Appearance
For the Petitioners : Shri. Bhaskar Sarkar
Smt. Swati Mehendale
For Respondent No. 1 : Shri. Rajendra Patsute
For Respondent No. 3 : Shri. Paresh Bhagwat
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 2 of 17
ORDER
Date: 30 November, 2017
M/s. Tata Power Company Limited (Generation) (TPC-G) has filed a Petition on 18.10.2017
(in Case No. 148 of 2017) citing Sections 86 (1) (b) and (k) of the Electricity Act (EA), 2003
seeking suspension of medium-term competitive bidding for procurement of 750 MW by
Brihanmumbai Electric Supply & Transport Undertaking (BEST) in pursuance to the Order
of the Commission in Case No. 25 of 2017 dated 23.9.2017.
2. The prayers of TPC-G in Case No. 148 of 2017 are as follows:-
a) “Admit the instant Petition
b) Considering the urgency of the matter, hold an early hearing of the instant petition
before 25th October, 2017 (extended bid due date of BEST)
c) Direct suspension of medium-term competitive bidding process for procurement of
750 MW by Brihanmumbai Electric Supply & Transport Undertaking from 11th
September, 2017 (issuance of bidding documents by BEST), in view of the reasons
enunciated in the instant petition
d) Direct appointment of an independent agency to assess the realistic time-lines for
completion of the various transmission Lines projects with due reference to STU’s
report and CEA’s report on the Mumbai Transmission Corridor scenario and
conclusively decide the maximum Quantum of power in RTC, Peak 1 and Peak 2 time
slots that can be brought in to Mumbai over next 5 years and beyond
e) Direct STU to study the Transmission System of Mumbai to enable binging power
from Mumbai Periphery to BEST network; and
f) Direct the BEST to revise and re-issue the Power Procurement process as required
based on the outcome of prayer (c) above...”
3. M/s. Tata Power Company Limited (Distribution) (TPC-D) has filed a Petition on
25.10.2017 (Case No. 150 of 2017) citing Sections 86(1)(b) and (k) of the EA, 2003
seeking clarity on certain matters relating to the proposed procurement of 750 MW
power by BEST through medium-term competitive bidding in pursuance of the Order of
the Commission in Case No. 25 of 2017.
4. The prayers of TPC-D in Case No. 150 of 2017 are as follows:
“a) Admit the instant Petition;
b) Considering the urgency of the matter, hold an early hearing of the instant petition
before 31st October, 2017 (extended bid due date of BEST);
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 3 of 17
c) Provide clarity on the issues mentioned in paragraph 2 of the instant petition, in
the overall interest of the consumers, before conclusion of bidding process for
procurement of 750 MW by Brihanmumbai Electric Supply & Transport Undertaking;
d) Direct STU to ensure that adequate transmission corridor is available to the
Petitioner, as a long term transmission user, to procure power from outside
Mumbai.”
5. As both Petitions have been filed with reference to the Commission’s Order in Case No.
25 of 2017 relating to BEST’s medium-term power procurement plan, the Commission
has decided to address them through this common Order.
6. In its Petition in Case No. 148 of 2017, TPC-G has stated as follows:
6.1. Vide its Order in Case No. 25 of 2017, the Commission approved BEST’s proposal to
undertake medium-term competitive bidding for procurement of 750 MW power for 3
time slots for 5 years from FY 2018-19, in accordance with the Competitive Bidding
Guidelines, under Section 63 of the Electricity Act. However, the Commission has
also appreciated that the issue of transmission constraints remains inconclusive, and
the issuance of the Letters of Award (LoAs) to the successful bidders is dependent on
the transmission constraints scenario.
6.2. The entire process of carrying out the bidding process becomes rather otiose as the
Commission itself has recognised that the transmission constraint scenario is
questionable at this stage. In other words, if the Commission comes to the conclusion
that there are transmission constraints due to which power cannot be brought from
outside Mumbai, then the entire bidding process initiated by BEST would become
futile. Further, the State Transmission Utility (STU) also needs to carry out a study of
whether power can flow from the Mumbai periphery to the BEST network.
6.3. Due to the above, several bidders, including TPC-G, would remain in an
indeterminate state as regards their power sale tie-ups because, even after successfully
winning the bid, the bidder would not be in a position to conclusively tie-up its power
with BEST till the STU and the Maharashtra State Load Despatch Centre (MSLDC)
give their concurrence insofar as transmissions constraints are concerned.
6.4. The Power Purchase Agreement (PPA) between TPC-G and BEST is expiring on
31.3.2018. However, as the outcome of the process of power procurement of BEST
has not attained finality even at this belated stage, TPC-G is unable to make any
alternative power sale arrangements. Therefore, it is necessary for the Commission to
decide on the issue of existing transmission constraints before allowing BEST to
proceed with the bidding process because the future of the power sale arrangements of
TPC-G is solely dependent on its outcome.
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 4 of 17
6.5. Vide its letter dated 21.6.2017, TPC requested the Central Electricity Authority
(CEA) to carry out System Studies of the Mumbai Transmission System based on the
current and future transmission planning for the Mumbai Area. On 13.10.2017, the
CEA convened a meeting along with the other Distribution Licensees and the STU in
which the issues of transmission constraints were discussed in detail. Although it is
yet to issue its final report, a draft report has been handed over by CEA. The
Commission may consider the findings in the draft report for the purpose of
adjudication of this Petition.
6.6. A summary of the issues identified in the report and subsequently discussed in the
meeting held on 13.10.2017 is provided below:
a) CEA has carried out load flow studies corresponding to FY 2021-22 peak conditions
considering total load of Western Region of the order of 70713 MW as against 46184
MW. The Table below provides the loads of TPC-D, Reliance Infrastructure Ltd.
(Distribution) (RInfra-D) and the rest of Maharashtra considered by the STU, TPC
and CEA. It establishes that the Mumbai load considered by TPC and CEA are similar
as compared to that of the STU.
Loads considered by STU, TPC and CEA
Zone
2021-22
STU Tata
Power CEA
Rest of
Maharashtra
MW 17958 20330 22908
MVAR 4071 4671 4177
Tata Power MW 2573 2821 2710
MVAR 115 125 319
RInfra MW 1525 1631 1703
MVAR 60 64 68
Total
Maharashtra
MW 22056 24782 27321
MVAR 4245 4860 4564
Total Western
Region
MW 47178 55447 70713
MVAR 12117 14455 11328
b) CEA has observed that a few additional 400 kV elements have not been considered by
STU in its studies/reports. Some of these are:
i. Padghe (PGCIL) - Navi Mumbai with Quad Moose
ii. Padghe (PGCIL) - Kharghar with Quad Moose
iii. LILO of Padghe (MSETCL) – Kharghar 400 kV át Navi Mumbai
iv. Aurangabad (PGCIL) - Boisar D/C with Quad Moose.
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 5 of 17
These are all new Lines that would require approvals from multiple
statutory/regulatory authorities, in addition to Right of Way (RoW) issues till they are
commissioned.
c) As per the transmission augmentation planned to be implemented, power is expected
to be available at Mumbai periphery (Borivali). However, there is no study carried out
as regards the flow of power from Borivali to the BEST area. CEA indicated that the
STU should present the Mumbai plan comprehensively for internal flows.
d) CEA indicated overloading of many Lines under various conditions of tripping of
Lines. The STU needs to study and inform about the mitigation measures to maintain
N-1 and N-1-1 contingency requirements.
e) The time Lines are very important when the reliability of power supply to Mumbai is
dependent upon the schemes yet to be implemented.
f) CEA also indicated that the Western Region Power Committee (WRPC) view is
required on islanding and reliability for metro cities as per the Indian Electricity Grid
Code Regulations, 2010 (‘IEGC’). This view must necessarily be taken before
deciding on reducing the reliability of power supply.
g) Mega Volt Ampere Reactive (MVAR) study needs to be done and individual
Distribution Licensees must provide for necessary reactive compensation.
h) STU is yet to carry out voltage and transient stability studies to evaluate the impact of
fault levels and voltage drops.
6.7. Therefore, till the CEA provides its final report and the issue of transmission
constraints is conclusively decided, it would be prudent to suspend the bidding
process of BEST.
6.8. TPC has carried out revised studies with the same data used by CEA. They indicate
that a few Lines would be carrying power beyond their thermal carrying capacity in
the event of non-availability of these new Lines by the peak of FY 2021-22 (June,
2021) and phasing out of embedded generation. The Table below provides the
comparative flows on critically loaded Lines under various scenarios:
Comparative flows on critically loaded Lines under various scenarios
Line Section With New
proposed Lines*
Without New
proposed Lines*
Config. Cond. Size Thermal
Loading
Limit With
EG
W/O
EG
With
EG
W/O
EG
Kudus _ Padghe 250 300 919 1007 S/C Twin
Moose@
850
Padghe - Kalwa 452 x 2 492 x 2 833 892 D/C Twin Moose 850
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 6 of 17
Pune – Ghat Kopar 465 536 771 866 S/C Twin Moose 850
Kudus
Transformer
385 x 2 423 x 2 511 x 2 560 x 2 Two 500
* 400 kV Padghe (PGCIL) - Navi Mumbai and Padghe (PGCIL) – Kharghar S/C Lines with
quad moose.
@ STU has proposed to change conductor of this Line with high ampacity conductor without
giving definite time Lines.
The Table below gives the voltage at representative Buses of Ghatkopar and Dharavi with
and without embedded generation and new proposed Lines:
Voltage at representative Buses
Sub-Station With New proposed Lines* Without New proposed
Lines*
With EG W/O EG With EG W/O EG
Ghatkopar 400 kV 399 (0.9975) 389 (.9725) 387 (.9675) 366 (.9150)
Dharavi 220 kV 214 (.975) 207 (.940) 209 (.952) 195 (.888)
From the above Table, it can be seen that the voltage in and around Mumbai would
violate the statutory limits of +/-5% in the event of non-availability of the new
proposed Lines and embedded generation is phased out by FY 2021-22.
6.9. These new proposed Lines are essential before the embedded generation is taken out.
Further, the Padghe – Kalwa and Pune – Ghatkopar Lines would remain critically
loaded even with full embedded generation in operation and would get over-loaded in
case any one Unit is taken out permanently. Decommissioning of any Unit is an
irreversible process, and decommissioned Units cannot be brought on bar in the
contingency of non-availability of these two new proposed Lines during peak FY
2021-22 conditions.
6.10. The CEA has taken cognizance of the fact that the system identified by STU would be
inadequate to meet the loads of Mumbai in the event of decommissioning of
embedded generation, and additional transmission system with high carrying capacity
would be required. As a first step, the additional transmission system proposed by
CEA would require to be approved in the CEA’s Standing Committee for Western
Region. Once it is approved by the Standing Committee, further regulatory approvals
bidding/tendering etc. would be taken. The whole process is time taking and,
therefore, time-lines have to be specified for their implementation.
6.11. Apart from BEST, there are three Distribution Licensees in Mumbai who are Long
Term Transmission System Users of the available Transmission Capacity and pay
Long Term Transmission Charges. The available Transmission Capacity needs to be
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 7 of 17
allocated amongst the Distribution Licensees to meet their peak demands and also
optimise their cost of power purchase. Such power requirement by all Mumbai
Distribution Licensees in FY 2017-18 was around 772 MW.
6.12. Further, based on the time-lines of proposed augmentation projects given in the STU
report as well as the CEA study report, it is clear that there cannot be any substantial
addition of capacity / change in the present transmission corridor situation in the near
future before commencement of power supply to BEST from 1 April, 2018.
6.13. Therefore, the Commission must necessarily first decide on the Mumbai Transmission
constraints situation before commencement of the bidding process by BEST.
Ambiguity on the issue of Letters of Award (LoA) even after winning the bid would
keep all the Generators, including TPC-G, in an uncertain business scenario leading to
unwarranted loading on cost of power. Clarity on the transmission constraints issue is
a primary requirement to ensure real competitive discovery of price for the benefit of
Mumbai consumers.
6.14. Considering the above, the Commission may appoint an independent agency to assess
the realistic time-lines for completion of the various Transmission Line projects.
7. In its Petition in Case No. 150 of 2017, TPC-D has stated as follows:
Increase in Transmission Charges and Losses and impact of MVAr compensation
7.1. Vide Order dated 23.09.2017 in Case No. 25 of 2017, the Commission has directed
BEST to undertake a competitive bidding process for procurement of 750 MW in
accordance with the Competitive Bidding Guidelines under Section 63 of the EA,
2003. However, the Commission has not provided any conclusion/clarity on the
impact of increase in transmission charges and losses and the reactive compensation
in case the entire 750 MW power would be procured from generating sources outside
Mumbai and the embedded generation is consequently not generating power.
7.2. It is important to examine the cost implications of the increase in transmission losses
and transmission charges as well as the MVAr compensation as these would have an
impact on not only BEST but all the Distribution Licensees in Maharashtra. These
implications are detailed below:
(i) In case the embedded generation of Mumbai is not generating power, the system
would face ‘voltage instability’ and would collapse unless additional and
adequate reactive compensation of more than 700 MVAr is provided in the
Mumbai area to have same quality of supply.
(ii) As per the State Grid Code Regulations, the reactive compensation has to be
provided by the User, i.e. the Distribution Licensees. Most of the Distribution
Sub-stations of TPC-D are unmanned. Accordingly, provision of fixed static
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 8 of 17
capacitors would not serve the purpose as these would require to be put in on/off
mode according to requirements. Therefore, Static Synchronous Capacitors
(StatComs) with provision for automatic on/off switching would have to be
provided. This would require significant capex of around Rs. 750-1000 crore.
Further, this impact would not be on BEST alone but on TPC-D and RInfra-D as
well. Apart from the cost, this would have a significant space requirement which
is a severe constraint in Mumbai.
(iii) In the event that the entire 750 MW power is imported from outside Mumbai,
transmission losses in the Western Region (WR) will increase by around 418
MW (0.5% of Maharashtra loads). Assuming loss load factor of 0.7%, additional
losses would be around 2,563 MUs, causing an additional burden on consumers
of Maharashtra of around Rs. 1,025 crore.
(iv) The additional capex estimated as above would have a significant tariff impact
on consumers.
7.3. From the above, it is clear that there will be significant cost implications and,
therefore, the Commission ought to provide this clarity before the bidding procedure
of BEST is concluded, and accordingly hold that such charges/costs would have to be
borne by BEST and not by TPC-D and its consumers, on account of BEST procuring
power from outside Mumbai.
Allocation of Transmission Corridor
7.4. In its Order in Case No.25 of 2017, the Commission has not provided
conclusion/clarity on the issue of allocation of transmission corridor to the other
Distribution Licensees.
7.5. In Case No. 25 of 2017, BEST has suggested that the share of each Distribution
Licensee in the limited Transmission Capacity be determined on the same
methodology as for the sharing of Transmission Charges, and that all the remaining
power can be purchased by the Mumbai Licensees proportionately from out of the
embedded generation. In their respective submissions on the presentation made by the
STU on the removal of embedded generation, TPC-D and RInfra-D had also
suggested that the Available Transmission Capacity be allocated among the Mumbai
Distribution Licensees. TPC-D also suggested that the allocation be in the same ratio
as for sharing of Transmission Charges, viz., the respective shares of the Distribution
Licensees in the average of Coincident Peak Demand (CPD) and Non-Coincident
Peak Demand (NCPD) of the three Distribution Licensees.
7.6. In view of the above, the Commission may provide clarity on these issues before the
bidding procedure of BEST is concluded so that TPC-D is assured of a transmission
corridor to meet the power requirement of its consumers and would not face issues
into maintaining reliability of its distribution system and managing its cost of power
purchase.
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 9 of 17
Requirement of transmission corridor for procurement of short term power by TPC-D
7.7. TPC-D has proposed an optimal power purchase arrangement in its Petition in Case
No. 39 of 2017. It has submitted that, for the entire period of its PPA, there would be
a requirement of short term power which would require a transmission corridor for
bringing power from outside Mumbai. Additionally, whenever there is an outage of
the tied up generating capacities, the transmission corridor would be required to bring
power into Mumbai.
7.8. In addition, TPC-G has indicated that, in the event that BEST does not procure power
from the embedded generation, TPC-G would not be in a position to run its Unit 5 of
500 MW. In this scenario, TPC-D would have to tie up power from only from Units 7
and 8 of TPC-G.
7.9. In that event, the entire power requirement of TPC-D may not be met and it would be
compelled to procure power from outside Mumbai. In order to do so, the transmission
corridor would be required.
7.10. The demand of TPC-D is expected to increase in the future, which would further
increase the necessity of the Transmission Corridor in the absence of embedded
generation in Mumbai.
7.11. However, while arriving at the available Mumbai Transmission Capacity for BEST to
bring 750 MW power from outside Mumbai (vide Order in Case No. 25 of 2017), the
Commission has not given clarity as to how the other two Distribution Licensees of
Mumbai, namely TPC-D and RInfra-D, will be allocated the transmission corridor to
meet their demand.
7.12. Further, TPC-D is also a Long Term Transmission System User, like BEST, and pays
the Long Term Transmission Charges. Accordingly, the Available Transmission
Capacity needs to be allocated amongst the Distribution Licensees to meet their peak
demands and also optimise their cost of power purchase. Therefore, blocking of
corridor unilaterally by BEST for bringing 750 MW power from outside Mumbai
would not be in the interest of justice to TPC-D as well as its consumers.
7.13. In view of the above, the Commission may direct the STU to ensure that adequate
transmission corridor is available to TPC-D, as a long term Transmission System
User, to procure power from outside Mumbai if the need arises and the consumers of
TPC-D are not adversely impacted on account of the allocation of transmission
corridor to BEST.
7.14. The decision of the Commission on these aspects would have a direct impact on the
reliability of power supply as well as cost to all the consumers of Mumbai.
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 10 of 17
Accordingly, the Commission may provide clarity on these issues before the bidding
procedure of BEST is concluded.
8. BEST’s Reply dated 26.10.2017 to TPC-G’s Petition in Case No. 148 of 2017 is as
below:
8.1. In its Order dated 23.9.2017 in Case No. 25 of 2017, the Commission had held and
directed as follows: -
“42.14. BEST shall approach the STU and the MSLDC for their concurrence
upon conclusion of these three competitive bidding processes and before
issuing Letters of Award (LoAs) for the supply of power or signing PPAs with
the successful bidders.
42.15. The STU and MSLDC shall examine the location of the successful
bidders in the three competitive bidding processes, and jointly assess whether
BEST can avail power from them or if there are any issues in sourcing power
from one or more of them.
42.16. In case there is any issue due to which BEST is unable to procure the
entire 750 MW power through competitive bidding considering the assessment
of the STU and MSLDC, BEST may approach the Commission through a
Petition to address those issues considering the STU and MSLDC’s views. The
Commission would take an appropriate view in the matter at that stage.”
8.2. From these extracts, it is clear that the Commission has taken due care of the
eventualities of transmission constraints for bringing power from outside Mumbai to
cater to the requirements of BEST and other Licensees in Mumbai. The Commission
had also impleaded the present Petitioner (TPC-G) in the proceedings Case No. 25 of
2017 and all its submissions were heard before deciding the matter. Hence, a separate
Petition by TPC-G in the same context does not stand as far as the above decision of
the Commission is concerned and it would amount to re-opening of Case No. 25 of
2017.
8.3. Further, a remedy for any transmission constraints that may be faced in procuring
power from the successful bidders is already available to BEST. In all scenarios, the
contract will be entered into with the successful bidders and power will be procured
from them only after joint assessment of any constraints by BEST, STU and MSLDC.
Hence, all of the concerns of TPC-G with respect to transmission constraints and their
effect on sourcing/bringing power from one or more successful bidders will be taken
care of at the appropriate time as directed by the Commission.
8.4. The bidding process conducted by BEST is conducted in conformity with the Model
Bidding Documents issued by the Ministry of Power (MoP) and as per the directions
of the Commission. TPC-G does not have any locus standi to request suspension of
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 11 of 17
the bidding process of a Distribution Licensee in general, and BEST in particular.
However, it is open to TPC-G to participate in the competitive bidding process
undertaken by BEST. In case TPC-G emerges as one of the successful bidders, all
such concerns would not only be addressed but also its Plant would remain live as
embedded generation at least for the medium-term.
8.5. Any study with respect to realistic time-lines for completion of the various
Transmission Line projects and the CEA report on the Mumbai Transmission
Corridor Scenario is within the purview of the Commission for decision. BEST as
such does not have any objection to such assessments at the present time or before the
issuance of LoA to the successful bidder. However, it would be prudent to continue
with the bidding process being conducted by BEST, and the assessments of
transmission constraints may go on simultaneously. It is also important for BEST to
fulfil its obligation as a Distribution Licensee to arrange power by the expiry of the
existing PPA with TPC-G, i.e., 1.4.2018.
8.6. BEST refutes the claim of TPC-G that genuine bidders would be attracted only when
there is clarity on the quantum and duration of power that will be finally allowed to be
procured. BEST has seen interest of multiple bidders for the present bidding process,
with 26 prospective bidders having already attended the pre-bid conference and many
are in correspondence with BEST. Even TPC-G was one of the attendees at the pre-
bid conference conducted on 26.9.2017 by BEST in the present bidding process.
9. In its Reply to TPC-G’s Petition in Case No. 148 of 2017, Maharashtra State
Electricity Distribution Co. Ltd. (MSEDCL) has stated as follows:
9.1 MSEDCL had made its detailed submission regarding the power transmission position
in the last one year for the Mumbai Distribution Licensees in Case No. 25 of 2017.
MSEDCL has demonstrated that embedded generation in Mumbai region of around
1877 MW is tied up through Long Term PPAs by Mumbai Distribution Licensees and
is being run continuously, and Short Term Power up to 1000 MW is being purchased
from outside Mumbai region as and when required.
9.1. Accordingly, after analysis of the data and confirmation of STU and MSLDC, the
Commission in its Order in Case No. 25 of 2017 has also recognised the facts and has
confirmed the transmission capacity of Mumbai area as follows:
Summary of Transmission Capacity for Mumbai
A Total Transmission Capacity (TTC) MW 2786
B Reliability Margin MW 500
C Available Transmission Capacity (ATC) (B-A) MW 2286
D MSEDCL Demand MW 248
E Railways LTOA MW 120
F Balance Available for Mumbai Licensees (C-D-E) MW 1918
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 12 of 17
G. Already Tied up Capacity by Mumbai Distribution Licensees MW 959
H. Balance Capacity Available MW 959
9.2. According to the directives issued in Case No. 25 of 2017, BEST floated three tenders
for procurement of power on medium term basis for 5 years on the Discovery of
Efficient Electricity Price (DEEP) e-bidding portal as below:
Sr.
No
Tender No Period Quantum
(MW)
1 BEST/Medium/Lumpsum Tariff/17-18/ET/56 00:00 to 24:00 300
2 BEST/Medium/Lumpsum Tariff/17-18/ET/57 07:00 to 24:00 200
3 BEST/Medium/Lumpsum Tariff/17-18/ET/58 09:00 to 19:00 250
9.3. In the present Petition, TPC has provided the CEA’s brief report on Mumbai System
Studies in which it is mentioned that the net import to Mumbai Distribution Licensees
on 01.06.2017 has reached 2048 MW (which includes 1089 MW short term power,
i.e. 2048 MW - 959 MW).
9.4. Even in present conditions, as per the MSLDC’s SCADA Data for 13.10.2017, there
is net power flow of 1971 MW (excluding MSEDCL’s demand) to Mumbai
Distribution Licensees. Since the last one year, Mumbai Distribution Licensees are
procuring short term power to the tune of 1000-1200 MW continuously without any
transmission constraints.
9.5. BEST presently has a contracted capacity of 932 MW (effective contracted capacity
676 MW, excluding TPC–G Unit 6 which is based on mixed fuel and is under
economic shut down) with the embedded generation of TPC-G. The Unit-wise
contracted capacity is as follows:
Sr. No Source Capacity (MW) BEST’s Contracted
Capacity (MW)
1 TPC-G Hydro 447 228
2 TPC-G Unit-5 500 256
3 TPC-G Unit-6* 500 -*
4 TPC-G Unit-7 180 92
5 TPC-G Unit-8 250 100
Total 1877 676
*TPC-G Unit 6 is under economic shut down.
9.6. In the contracted quantum with BEST, 228 MW is Hydro power (cheapest source)
which can easily be accommodated in the absence of BEST contract. Hence, only the
remaining 448 MW is for consideration for transmission of power from outside to the
Mumbai area as far as transmission constraints are concerned.
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 13 of 17
9.7. Hence, MSEDCL reaffirms that there is no constraint in transmission of power from
outside to Mumbai Licensees’ area upto about 1000 - 1200 MW on the basis of the
above realistic data.
9.8. CEA has furnished System Studies of the Mumbai Transmission System based on
data provided by the Mumbai Transmission Utilities and STU with current and future
transmission planning for the Mumbai Area. In its report, CEA has studied four
scenarios on PSS software considering the peak demand conditions for FY 2021-22
projected, with 4.5% growth over the peak demand observed on 01.06.2017:
i. With all planned augmentation and with full embedded generation.
ii. With all planned augmentation and without embedded generation.
iii. Without Vikhroli Substation and with full embedded generation.
iv. Without Vikhroli Substation and without embedded generation.
9.9. All these four scenarios are completely hypothetical, and only the extreme worst case
scenario has been taken instead of the realistic scenario. In the study, scenarios 2 and
4 are for zero embedded thermal generation. However, the realistic scenario in
consideration of 750 MW or 448 MW power flow from outside the Mumbai
Licensees’ area is not at all considered. This does not give clear picture regarding the
transmission loadings in case of power procurement by BEST from outside Mumbai.
This is very preliminary study and not the final report. CEA has sought the comments
of the Maharashtra Distribution and Transmission Utilities for further study and
finalization, at the meeting on 13.10.2017.
9.10. On the basis of this preliminary study, TPC-G is trying to build a larger scenario by
linking the whole Western Region with the smaller quantum of power. It is trying to
take shelter of the unrealistic case study to highlight the transmission constraints and
flaws only with the motive to stall the BEST bidding process by creating fear
psychosis.
9.11. The contention of TPC-G is intended to take undue benefit for supply of its costly
power to the Mumbai Licensees, specifically to BEST, with the fear of non-
competitiveness in the bidding process.
9.12. If such supply to BEST through embedded generation (without competitive bidding)
is allowed, the consumers of BEST and thereby the State will be burdened unduly in
their tariffs due to the costly power of TPC-G. Hence, the Commission may not
entertain this in the interest of the consumers.
9.13. The study with regard to reactive power management and Islanding Scheme (upto
Navi Mumbai and other areas near Mumbai) of the transmission system and
transmission network planning is essential for the long term stability of the power
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 14 of 17
system, and MSEDCL agrees with the contention of TPC-G. However, this study has
no concern with the present medium term power procurement having an effective
quantum of 448 MW.
9.14. The Petition filed by TPC-G for suspending the competitive bidding process initiated
by BEST may be dismissed.
10. At the hearing held on 27.10.2017:
10.1. TPC-G and TPC-D stated that they had filed their respective Petitions to raise
concerns on various issues regarding transmission constraints and the withdrawal of
embedded generation arising from the proposed medium-term procurement of 750
MW power through competitive bidding by BEST, and their consequences for TPC-
G, TPC-D and other Mumbai Distribution Licensees. In their submissions during the
proceedings of Case No. 25 of 2017, the STU and MSLDC had also stated that
embedded generation can be removed only in phases, and that power procurement
from outside Mumbai is presently possible only to the extent of 300 and not 750 MW.
10.2. TPC-G stated that it had received a letter from BEST stating that the PPA period may
have to be extended in case of delay in finalising the competitive bidding process,
considering its first right of refusal. The Commission observed that the issue was not
before the Commission in these proceedings. To a query of the Commission, TPC-G
stated that it was not averse to participating in the competitive bidding process of
BEST.
10.3. TPC-D stated that it has concerns regarding the extent of its own allocation and
availability of Long-Term Open Access capacity, considering the transmission
constraints, if BEST brings the proposed power quantum from outside.
10.4. According to TPC-D, it would also have to bear certain additional costs from such
import of power. The Commission observed that, on this logic, nowhere should any
new load be connected because the back-end losses of TPC-D would increase.
10.5. The Commission observed that, in its Order in Case No. 25 of 2017, it had dealt
extensively with the issue of the transmission capacity available, on which it had also
considered the similar submissions that were made in those proceedings. The
Commission had also expressed its grave concern and dissatisfaction on the slow
progress of the key Mumbai transmission projects, with which TPC (Transmission) is
concerned.
10.6. The Commission pointed out that the Order provides that the final decision on the
outcome of the competitive bidding process would be taken considering, among other
things, the locations of the generation sources of the successful bidders in the context
of the transmission capacity available, after consultation by BEST with the STU and
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 15 of 17
MSLDC. That being the case, the Commission observed that it could not understand
the purpose of these Petitions. They appear, in effect, to be in the nature of appeals or
for review of the Order in Case No. 25 of 2017.
11. In its undated letter received on 30.10.2017 referring to the hearing, the Maharashtra
Chamber of Commerce, Industry & Agriculture (MCCIA), an authorised Consumer
Representative, while commending BEST for its initiative and the Commission for its
support, suggested that BEST be asked to first procure power from nearby Generating
Stations and thereafter from other sources for any shortfall, considering the optimal
utilisation of the existing transmission corridor and its capacity, and the transmission
losses from importing power.
Commission’s Analysis and Rulings
12. TPC-G (in Case No. 148 of 2017) and TPC-D (in Case No. 150 of 2017) seek the
suspension or postponement of the competitive bidding process being
undertaken by BEST in pursuance of the Commission’s Order in Case No. 25 of
2017 until the transmission constraints and the implications of importing power
into Mumbai are reconsidered. While TPC-G has also referred to the draft of the
preliminary report of the CEA received after the Order in that Case, the
Commission notes that the issues now raised by TPC-G and TPC-D in these
Petitions are substantively the same as had been raised in the proceedings of
Case No. 25 of 2017.
13. The issue of transmission constraints was deliberated at length during the
proceedings of Case No. 25 of 2017, and the STU and MSLDC assessments were
also discussed. Considering the submissions in that Case, the Commission ruled
as follows in its Order dated 23.9.2017:
“42.12 In the light of the above discussion, the Commission is of the view that,
at this stage, it would be premature to presume which of the various
eventualities might materialise and to restrict BEST on that basis from
proceeding with medium-term competitive bidding for procurement of 750
MW power, particularly when it is for the first time that any Distribution
Licensee in Mumbai has sought to procure substantial power for the medium-
term through competitive bidding. The Authorised Consumer Representatives,
Prayas and TBIA, who participated in these proceedings have also welcomed
BEST’s proposal to procure power through competitive bidding.
42.13 The Commission accordingly approves BEST’s proposal to undertake
medium-term competitive bidding for procurement of 750 MW power for 3
time slots for 5 years from FY 2018-19, in accordance with the Competitive
Bidding Guidelines, under Section 63 of the EA, 2003. However, as discussed
while analysing the load curves of BEST, the time slot for procurement of 250
MW power (Peak Load II) shall be from 0900 hours to 1900 hours instead of
upto 1700 hours proposed by BEST. BEST shall undertake this power
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 16 of 17
procurement through three separate but simultaneous bidding processes for
the following:
(i) 300 MW Round the Clock;
(ii) 200 MW from 0700 hours to 2400 hours, and
(iii) 250 MW from 0900 hours to 1900 hours.
42.14 BEST shall approach the STU and the MSLDC for their concurrence
upon conclusion of these three competitive bidding processes and before
issuing Letters of Award (LoAs) for the supply of power or signing PPAs with
the successful bidders.
42.15 The STU and MSLDC shall examine the location of the successful
bidders in the three competitive bidding processes, and jointly assess whether
BEST can avail power from them or if there are any issues in sourcing power
from one or more of them.
42.16 In case there is any issue due to which BEST is unable to procure the
entire 750 MW power through competitive bidding considering the assessment
of the STU and MSLDC, BEST may approach the Commission through a
Petition to address those issues considering the STU and MSLDC’s views. The
Commission would take an appropriate view in the matter at that stage.
42.17 BEST must ensure that the process of obtaining the concurrence of
the STU and MSLDC and the filing of its Petition on any issues arising is
undertaken expeditiously so that the process is completed and LoAs are
issued to the successful bidders well within the Bid Validity Period as per the
Model RfP set out in the Competitive Bidding Guidelines for medium-term
procurement.
42.18 BEST shall also file a separate Petition within the stipulated period for
adoption of the tariff discovered through the medium-term competitive
bidding process in accordance with Section 63 of the EA, 2003 and the
Competitive Bidding Guidelines, and for approval of the PPAs entered into
with the successful bidders.”
14. Thus, in its Order in Case No. 25 of 2017, the Commission had dealt extensively
with the issue of the transmission capacity available and its implications for the
procurement of power proposed by BEST. It had also considered the
submissions made in those proceedings, which were similar to those which are
being reiterated now. The Commission had made it clear that, in the context of
these and other considerations, a final decision would be taken depending on the
outcome of the competitive bidding process and the locations of the generation
sources of the successful bidders, after consultation by BEST with the STU and
MSLDC. At that stage, when the options available would be crystallised, TPC
and the other Distribution Licensees and the Consumer Representatives would
have the opportunity to raise their concerns and issues, if any.
Order – Case Nos. 148 of 2017 & 150 of 2017 Page 17 of 17
15. However, TPC-G and TPC-D have nevertheless filed these Petitions inspite of the
clear dispensation in the Order in Case No. 25 of 2017 and without waiting for
that stage to be reached. The competitive bidding process being undertaken by
BEST in pursuance of its Order cannot be allowed to be pre-empted in this
manner, and the present Petitions are premature.
16. In view of the foregoing, these Petitions are dismissed.
The Petitions of Tata Power Co. Ltd. (Generation) in Case No. 148 of 2017 and of Tata
Power Co. Ltd. (Distribution) in Case No. 150 of 2017 stand disposed of accordingly.
Sd/- Sd/- Sd/-
(Deepak Lad)
Member
(Azeez M. Khan)
Member
(Anand B. Kulkarni)
Chairperson