Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1
BEFORE THE MADHYA PRADESH ELECTRICITY REGULATORY
COMMISSION AT BHOPAL
PETITION NO. 57 OF 2018
IN THE MATTER OF: Petition under Section 62 and Section 86(1)(a) of the Electricity Act,
2003 read with Part VII of the Electricity Act, 2003 for True-up of
Tariff for Unit-2 (600 MW) of 2 x 600 MW coal based Anuppur
Thermal Power Project (Phase-I) comprising of Unit-1 & Unit-2
(of 600 MW each) at District Anuppur, Madhya Pradesh for the
period from 01st April 2017 to 31
st March 2019 under Madhya
Pradesh Electricity Regulatory Commission (Terms and Conditions
for determination of Generation Tariff) Regulations, 2015.
AND
IN THE MATTER OF:
MB Power (Madhya Pradesh) Ltd.,
Laharpur, Jaithari,
Anuppur, Madhya Pradesh - 484330 … PETITIONER
VERSUS
1. M.P Power Management Company Ltd.,
(Erstwhile Madhya Pradesh Power Trading Company Ltd.)
Shakti Bhawan, Vidyut Nagar, Rampur,
Jabalpur, Madhya Pradesh – 482008, India
2. Madhya Pradesh Poorv Kshetra Vidyut Vitaran Company Ltd.,
Shakti Bhawan, Vidyut Nagar, Rampur,
Jabalpur, Madhya Pradesh – 482008, India
3. Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Ltd.,
Bijli Nagar Colony, Nishtha Parisar,
Govindpura, Bhopal, Madhya Pradesh – 462023
4. Madhya Pradesh Paschim Kshetra Vidyut Vitaran Company Ltd.,
GPH Compound,
Polo Ground, Indore, Madhya Pradesh – 452003 …RESPONDENTS
2
The Petitioner, MB Power (Madhya Pradesh) Limited submits that:-
1. The Petitioner is a generating company defined under Section 2(28) of the Electricity Act,
2003, hereinafter referred as 'Act', and is filing the instant Petition for determination of
True-up tariff for supply of power from Unit-2 (600 MW) of its 1200 MW (2x600 MW)
sub-critical coal based Anuppur Thermal Power Project (Phase-I) at District Anuppur,
Madhya Pradesh, hereinafter referred as 'Project' (comprising of 2 Units of 600 MW each), for
the period commencing from 01st April 2017 till 31
st March 2019 under Madhya Pradesh
Electricity Regulatory Commission (Terms and Conditions for determination of Generation
Tariff) Regulations, 2015, hereinafter referred as 'Tariff Regulations, 2015'.
2. The Petitioner has entered into two separate Power Purchase Agreements, hereinafter referred
as 'PPAs', with Madhya Pradesh Power Management Company Ltd., formerly known as
Madhya Pradesh Power Trading Company Ltd., hereinafter referred as 'MPPMCL',
(Respondent No. 1) as follows:
(a) PPA dated 05.01.2011 as amended on 31.07.2013 with Respondent No. 1 being the lead
procurer for Madhya Pradesh Poorv Kshetra Vidyut Vitaran Company Ltd. (Respondent
No. 2), Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Ltd. (Respondent
No. 3) and Madhya Pradesh Pashchim Kshetra Vidyut Vitaran Nigam Limited
(Respondent No. 4) for supply of an aggregate of 30% of the installed capacity of the
Project for a period of 20 years at the regulated tariff to be determined by the Hon’ble
Commission, hereinafter referred as 'Non-Concessional PPA'; and
(b) PPA dated 04.05.2011 with Government of Madhya Pradesh, hereinafter referred as
'GoMP', (Respondent No. 1 being the nominated agency of GoMP) for supply of 5% of
the net power generated from the Project at the variable charges for the life of the
Project, hereinafter referred as 'Concessional PPA'.
3. This Hon’ble Commission by its Order dated 07.09.2012 passed in Petition No. 7 of 2012 and
Order dated 04.02.2013 passed in Petition No. 82 of 2012 has accorded approval to the
aforesaid Non-Concessional PPA.
4. The Unit-1 (600 MW) of the Project achieved Commercial Operation Date, hereinafter
referred as 'COD', w.e.f. 00.00 Hours of 20th
May 2015 and Unit-2 (600 MW) of the Project
achieved COD w.e.f. 00.00 Hours of 07th
April 2016.
3
Summary of Tariff Orders
A. Tariff Orders for Unit-1 of the Project
5. This Hon'ble Commission vide Order dated 01.12.2017 passed in Petition No. 68 of 2016,
determined the final tariff of the Unit-1 of the Project as under:
a) Tariff for the period from COD of Unit-1 (i.e. 20.05.2015) till 31.03.2016 based on
Annual Audited Accounts for FY 2015-16 in terms of Madhya Pradesh Electricity
Regulatory Commission (Terms and Conditions for determination of Generation Tariff)
Regulations, 2012 hereinafter referred as 'Tariff Regulations, 2012' and;
b) Tariff for the period from 01.04.2016 to 31.03.2019 (for the control period
FY 2016-2019) in terms of MPERC Tariff Regulations 2015 on provisional basis subject
to true up on annual basis by this Hon’ble Commission based on Annual Audited
Accounts for the respective years.
6. Subsequently, this Hon'ble Commission vide Order dated 06.09.2018 passed in
Petition No. 11 of 2018, determined the true-up tariff of Unit-1 of the Project for the period
from 01.04.2016 to 31.03.2017 based on Annual Audited Accounts for FY 2016-17, in terms
of MPERC Tariff Regulations 2015;
7. Further, the Petitioner has already filed the Petition No. 51 of 2018 before this Hon’ble
Commission for determination of True-up tariff for supply of power from Unit-1 (600 MW) of
its Project for the period from 01.04.2017 to 31.03.2019 (i.e remaining control period under
MPERC Tariff Regulations 2015) based on Annual Audited Accounts for FY 2017-18 and
projected Additional Capital Expenditure for FY 2018-19 in terms of MPERC Tariff
Regulations 2015. The said Petition was admitted by this Hon’ble Commission by its daily
Order dated 12.12.2018.
B. Tariff Orders for Unit-2 of the Project
8. This Hon'ble Commission vide Order dated 29.11.2018 passed in Petition No. 10 of 2018,
determined the final tariff of the Unit-2 of the Project as under:
a) Tariff for the period from COD of Unit-2 (i.e. 07.04.2016) till 31.03.2016 based on
Annual Audited Accounts for FY 2016-17 in terms of Tariff Regulations, 2015;
b) Tariff for the period from 01.04.2017 till 31.03.2019 in terms of MPERC Tariff
Regulations 2015 on provisional basis subject to true-up on annual basis by the Hon’ble
Commission based on the Annual Audited Accounts for the respective years.
9. In accordance with aforesaid Order dated 29.11.2018, the Petitioner is hereby filing the instant
Petition in terms of Regulations 8.4 of MPERC Tariff Regulations 2015 for true-up of tariff
for the supply of power from Unit-2 for the period 01.04.2017 to 31.03.2019 (i.e remaining
4
control period under MPERC Tariff Regulations 2015) based on Annual Audited Accounts
for FY 2017-18 and projected Additional Capital Expenditure for FY 2018-19.
10. The submissions made by the Petitioner in the aforesaid Petitions i.e Petition No. 10 of 2018
and Petition No. 51 of 2018 may kindly be considered as an integral part of the instant Petition
which have not been repeated in the instant Petition for the sake of brevity.
Capital Cost of the Project as per the Annual Audited Accounts for FY 2017-18
11. The Petitioner submits that the Annual Audited Accounts for FY 2017-18 of the Petitioner’s
Company have now been placed on record for the consideration of this Hon’ble Commission,
a copy of which is attached hereto and marked as ANNEXURE-1.
12. The Petitioner further submits that the Annual Audited Accounts for FY 2017-18 have been
prepared under IND AS Accounting Standards in compliance with the Gazette Notification
dated 16.02.2015 issued by Ministry of Corporate Affairs.
13. The Petitioner submits that the reconciliation of the Gross Fixed Assets as on 31.03.2018
based on transition from Indian GAAP to IND AS, duly certified by the Auditor is attached
hereto and marked as ANNEXURE-2.
14. The Capital Cost of the Project as filed in Petition No. 10 of 2018 was Rs 8350.47 Crore
which was estimated on the basis of capitalized assets/expenditures, capital work in progress
and balance commitments/provisions of expenditure outstanding as on COD of Unit-2
(07.04.2016) as reflected in the Annual Audited Accounts for FY 2016-17.
15. However, the Petitioner further submits that based on the Annual Audited Accounts for
FY 2017-18, the capital cost of the Project has been re-estimated and reconciled as follows:
(Rs. Crore)
Particulars (in I-GAAP accounting standards) Amount
Gross Fixed Assets as on 31.03.2018 8001.53
Capital Work in Progress as on 31.03.2018 18.38
Sub Total 8019.91
Less: Disallowance by this Hon’ble Commission in its Order 29.11.2018 passed in Petition
No. 10 of 2018
(88.77)
Net Capital Cost 7931.13
Add: FERV Losses charged to P&L as allowed by this Hon’ble Commission in Order dated
29.11.2018 passed in Petition No. 10 of 2018 as on COD of Unit-2 (07.04.2016)
(Unit-1: Rs 46.69 Crore; Unit-2: Rs 101.35 Crore)
148.04
Add:Unamortized Finance Cost to Borrowings (as on COD of Unit-2) 34.93
Add: Provision for Custom Duty/ Excise Duty 163.97
Add: Carrying Cost considered as a part of Project Cost by this Hon’ble Commisison in its
Order dated 29.11.2018 passed in Petition No. 10 of 2018
28.09
Total – Capital Cost of the Project 8306.16
5
16. The Petitioner humbly submits that in accordance with the Order dated 29.11.2018 passed in
the Petition No. 10 of 2018 by Hon’ble Commisisons, the estimated Capital Cost of the
Project has now been revised to Rs 8306.16 Crore from Rs 8350.47 Crore, as earlier submitted
in the Petition No. 10 of 2018.
17. The item wise reconciliation of the revised estimated Project Capital Cost vis-à-vis the earlier
submitted Project Capital Cost is as hereunder:
(Rs. Crore)
S.
No Particulars
Project
Capital Cost
(as filed
under
Petition No.
10 of 2018)
Reconciled
Project Capital
Cost with
Annual Audited
Accounts for
FY 2017-18
Capital Exp.
Allowed(+)/
Disallowed(-)
by this Hon’ble
Commission in
its Order dated
29.11.2018
Revised
Project
Capital
Cost
A B C D E F = D-E
1 Freehold Land 150.53 156.21 - 156.21
2 Leasehold Land 21.58 21.58 - 21.58
3 Plant & Machinery 4565.83 4586.97 - 4586.97
4 Building & Civil Works 895.11 895.11 - 895.11
5 Pre-operative Expenditure 437.99 437.99 (19.31) 418.68
6 IDC/Finance Charges 1893.29 1893.29 (69.46) 1823.83
7 Custom Duty/Excise Duty
(Paid and capitalized)
28.75 28.75 - 28.75
Sub Total 7993.08 8019.91 (88.77) 7931.13
8 Custom Duty/Excise Duty
(Provision)
163.97 163.97 - 163.97
9 Add: FERV Losses charged
to revenue till Unit-2 COD
158.49 158.49 (10.45) 148.04
10 Add: Unamortized Cost to
Borrowings till Unit-2 COD
34.93 34.93 - 34.93
11 Add: Carrying Cost
considered as a part of
Project Cost by this Hon’ble
Commisison in its Order
dated 29.11.2018 passed in
in Petition No. 10 of 2018
- - +28.09 28.09
Capital Cost of the Project 8350.47 8377.29 (71.13) 8306.16
Firmed-up Unit-wise Capital Cost of the Project
18. The Petitioner submits the Auditor’s Certificate dated 12.11.2018 for unit-wise cash
expenditure as on 31.03.2018 along with Auditor’s Certificate dated 06.02.2018 for unit-wise
cash expenditure as on 31.03.2017 attached hereto and marked as ANNEXURE-3 (Colly).
Accordingly, the Project cash expenditure has been summarized as under:
6
(Rs. Crore)
S.
N
o
Particulars
Project
Cash Exp.
As on
31.03.2017*
Project
Cash Exp.
As on
31.03.2018*
Project
Cash
Exp.
during
FY 17-18
Additional
Cash Exp.
for Unit-1
during
FY 2017-18
Additional
Cash Exp.
for Unit-2
during
FY 2017-18
1 Land & Site
Development 92.11 103.59 11.48 - 11.48
2 Plant & Machinery 4337.32 4559.50 222.19 95.30 126.89
3 Building & Civil
Works 854.19 890.63 36.44 32.49 3.95
4 Pre-operative
Expenditure 419.62 437.52 17.90 10.80 7.10
5 IDC/Finance
Charges 1887.97 1891.32 3.35 - 3.35
6
Custom Duty/
Excise Duty
(Paid &capitalized)
28.75 28.75 - - -
Sub Total 7619.96 7911.31 291.36 138.59 152.77
7
Custom Duty/
Excised Duty
(Provision)
- - - - -
8
Add: FERV Losses
charged to revenue
till COD of Unit-2
158.49# 197.12 38.63 - 38.63
#
9
Add: Unamortized
Cost to Borrowings
till COD of Unit-2
34.93 34.93 - - -
Total 7813.38 8143.36 329.99 138.59 191.40
*excluding cash expenditure pertaining to CWIP as on date
#: Against the claimed FERV of Rs. 158.49 Crore for the Project till FY 2016-17, this Hon’ble Commission
has allowed FERV of Rs 148.04 Crore (Unit-1: Rs 46.69 Crore + Unit-2: Rs 101.35 Crore) corresponding to
the Project contruction period. Further, FERV of another Rs 5.84 Crore has been allowed by this Hon’ble
Commisison for Unit-2 for FY 2016-17 (operating period of Unit-2). As such the balance of Rs 4.61 Crore
(Rs 158.49 Crore - Rs 148.04 - Rs 5.84 Crores) has been carried forward for Unit-2 for FY 2017-18 in
addition to FERV of Rs 38.63 Crores claimed for Unit-2 for FY 2017-18 as per Annual Audited Accounts for
FY 2017-18
19. As approved and allowed by this this Hon’ble Commision vide its Order(s) dated:
(i) 06.09.2018 passed in Petition No. 11 of 2018 (True-up Tariff for Unit-1 for FY 2016-17);
(ii) 29.11.2018 passed in Petition No. 10 of 2018 (Final Tariff of Unit-2), the Petition submits
that opening capital blocks for Unit-1 & Unit-2 and Unit wise Additional Capital Expenditure
hereinafter referred as 'ACE' for FY 2017-18 are as follows:
7
(Rs. Crore)
S.No Particulars (on cash basis) Project Unit-1 Unit-2
1 Opening Capital Block as on 01.04.2017 7713.50 4303.40 3410.12
2 Actual ACE during FY 2017-18* 291.36 138.59 152.77
3 Closing Capital Block as on 31.03.2018 8004.86 4441.99 3562.90
*excluding FERV losses of Rs 38.63 Crore and treated as part of Annual Fixed Charges as per this Hon’ble
Commission;s Order dated 29.11.2018 in Petition No.10 of 2018
20. Based on the revised estimates of the Project Capital Cost as detailed our in Paragraph 17 of
the instant Petition & estimated closing capital block till 31.03.2018, the outstanding liabilities
and Projected ACE for FY 2018-19 is as follows:
(Rs. Crore)
S.
No Particulars
Revised
Project
Capital
Cost
Projected
Capital
Block as on
31.03.2018
Outstanding
Liabilities/
Provisions as on
31.03.2018
Projected ACE
for FY 2018-19
1 Land & Site Development 177.79 103.59 74.20 12.00
2 Plant & Machinery 4586.97 4559.50 27.47 27.47
3 Building & Civil Works 895.11 890.64 4.47 4.47
4 Pre-operative Expenditure 418.68 418.21 0.47 0.47
5 IDC/Finance Charges 1823.83 1821.86 1.97 1.97
6 Custom Duty/ Excise Duty
(Paid & capitalized) 28.75 - - -
Sub Total 7931.13 7822.55 108.58 46.38
7 Add: Custom Duty/ Excise
Duty (Provision) 163.97 - 163.97 163.97
8
Add: FERV Losses charged
to P&L as allowed by this
Hon’ble Commission in
Order dated 29.11.2018
passed in Petition No. 10 of
2018 as on COD of Unit-2
(07.04.2016)
148.04 148.04 - -
9 Add: Unamortized Cost to
Borrowings till Unit-2 COD 34.93 34.93 - -
10
Add: Carrying Cost
considered as a part of
Project Cost by this Hon’ble
Commisison in its Order
dated 29.11.2018 passed in
in Petition No. 10 of 2018
28.09 28.09 - -
Total 8306.16 8004.86 272.55 210.35
8
21. The Unit wise projected ACE for FY 2018-19 is as follows:
(Rs. Crore)
S.
No Particulars
Projected ACE for
the Project for
FY 18-19
Projected ACE
for Unit-1 for
FY 18-19
Projected ACE
for Unit-2 for
FY 18-19
1 Land & Site Development 12.00 6.00 6.00
2 Plant & Machinery 27.47 - 27.47
3 Building & Civil Works 4.47 - 4.47
4
Pre-operative Expenditure incurred
prior to COD of Unit-2 but now
projected to capitalized.
0.47 - 0.47
5
IDC/ Finance Charges incurred prior
to COD of Unit-2 but now projected
to capitalized.
1.97 - 1.97
6 Customs Duty/ Excise Duty
(Provision) 163.97 - 163.97
Total 210.35 6.00 204.35
22. In view of above, Capital Cost for Unit-2 considered in the instant Petition for the purpose of
tariff for Unit-2 is as shown below:
(Rs. Crore)
Particulars FY 2017-18 FY 2018-19
Opening Capital Cost 3410.12 3562.89
ACE during FY 2017-18 152.77 204.35
Closing Capital Cost 3562.90 3767.24
Average Capital Cost 3486.51 3665.07
Debt Equity Ratio for truing up of Additional Expenditure
23. The Petitioner submits that the debt-equity ratio of (73.51) : (26.49) as approved by this
Hon’ble Commisison in its Order dated 29.11.2018 pased in Petition No. 10 of 2018 has been
retained for the purpose of tariff in the instant Petition.
9
Components of Annual Capacity (Fixed) Charges for Unit-2
A. Return on Equity
24. In terms of Regulation 30 of Tariff Regulations, 2015, the Petitioner submits that for the
FY 2017-18, it has neither paid any Normal Tax nor MAT, accordingly Return on Equity has
been computed considering base rate of 15.50%. The Return on Equity computation is as
shown below:
(Rs. Crore)
Particulars FY 2017-18 FY 2018-19
Opening Equity 903.34 943.81
Addition in Equity during the year/ period 40.47 54.13
Closing Equity 943.81 997.94
Average Equity 923.58 970.88
Base rate of Return on Equity 15.500% 15.500%
Effective Tax rate 0.000% 0.000%#
Rate of return on equity 15.500% 15.500%
Annual Return on Equity 143.15 150.49
# Petitioner craves leave to claim tax as applicable as a part of the true-up Petition for FY 2018-19.
B. Interest on Loan
25. Regulation 32.5 of Tariff Regulations, 2015 stipulates that the rate of interest shall be
weighted average rate of interest calculated on the basis of the actual loan portfolio after
providing appropriate adjustment for interest capitalized.
26. Accordingly, the Petitioner submits that the weighted average rate of interest (WAROI) of
13.34% (calculation detailed out under Form-13 of Tariff Forms enclosed with the instant
Petition) has been considered for computation of interest on loan for the period FY 2017-18
and FY 2018-19. The interest on loan claimed has been computed as shown below:
(Rs. Crore)
Particulars FY 2017-18 FY 2018-19
Gross Opening Normative Loan 2506.78 2619.08
Less: Cumulative repayment of Normative Loan 161.12 331.18
Opening Normative Loan 2345.66 2287.90
Add: Increase in Loan during the year / period 112.30 150.22
Less: Normative Repayment during the year / period 170.06 178.78
Closing Normative Loan 2287.90 2259.34
Average Normative Loan 2316.78 2273.62
Weighted Average Rate of Interest 13.34% 13.34%
Annual Interest & Finance Charges 309.09 303.33
10
C. Depreciation
27. The Petitioner in accordance with Regulation 33 of Tariff Regulations, 2015 submits that it
has accordingly computed weighted average rate of depreciation of 4.88% for FY 2017-18
and 4.88% for the period FY 2018-19 considering Fixed Asset Register based on “Previous
Indian GAAP” and the rates of depreciation as per Appendix-II to Tariff Regulations, 2015.
The working of weighted average rate of depreciation is placed at Form-11 of the Tariff
Forms enclosed with the instant Petition. The depreciation claimed has been computed as
shown below:
(Rs. Crore)
Particulars FY 2017-18 FY 2018-19
Opening Capital Cost 3410.12 3562.89
Closing Capital Cost 3562.89 3767.24
Average Capital Cost 3486.51 3665.07
Weighted Average rate of Depreciation 4.88% 4.88%
Depreciation (for the period) 170.06 178.78
D. Operation and Maintenance Expenses (O&M Expenses)
28. The Petitioner submits that O&M Expenses have been claimed considering the norms for the
tariff period 2017-19 as specified in Regulation 35.8 of Tariff Regulations, 2015. The
necessary computation of O&M Expenses claimed is as shown below:
(Rs. Crore)
Particular Unit FY 2017-18 FY 2018-19
Installed Capacity MW 600 600
O&M Exp. (as per norms) in Rs.Lakh/MW 17.30 18.38
Annual O&M Expenses In Rs. Crore 103.80 110.28
E. Interest on Working Capital
29. Regulation 34.3 of Tariff Regulations, 2015 prescribes that rate of interest on working capital
shall be considered as bank rate [defined under Regulation 4.1(e) of the MPERC Tariff
Regulaitons as base rate of interest as specified by the SBI plus 350 basis points] as on
01st April of the year in which the Project is declared under COD. The Petitioner’s Project
achieved COD in FY 2016-17. Further, SBI’s base rate of interst as on 01.04.2016 (i.e. the
year of Project COD) was 9.30%. Accordingly, in accordance with the above referred
regulations, the applicable rate of interest on working capital is 12.80% (i.e. 9.30% plus 350
basis points). A copy of yearwise base interest rates of SBI as published on its website
evidencing SBI’s base rate of interst as on 01.04.2016 as 9.30% in attached hereto and marked
as ANNEXURE-4. Accordingly, the Petitioner has claimed interest on working capital for
the period FY 2017-18 and FY 2018-19 as 12.80% and the calculation of Interest on
Working Capital is as shown below:
11
(Rs. Crore)
Particulars FY 2018-19
Cost of Coal towards Stock 67.29 67.29
Cost of Coal towards Generation 67.29 67.29
Cost of Main Secondary Fuel Oil 0.99 0.99
O & M Expenses 8.65 9.19
Maintenance Spares 20.76 22.06
Receivables 272.08 267.61
Total Working Capital 437.07 434.44
Rate of Interest 12.80% 12.80%
Interest on Working Capital 55.94 55.61
F. Non Tariff Income
30. The Petitioner submits that it has earned non-tariff income of Rs. 8.63 Crore at the Project
level (i.e. for both Unit-1 and Unit-2) during FY 2017-18 in accordance with Regulation 53.1
of Tariff Regulations, 2015.
31. The details of the non-tariff income for FY 2017-18 are as here under:
(Rs. Crore)
S.No. Particulars Amount
1 Interest Income
Bank Deposits 6.02
Others 0.79
2 Scrap Sales 1.04
3 Others 0.74
4 Gain on sale of investments 0.04
Total 8.63
32. Further, the Petitioner has apportioned the above non-tariff income of Rs.8.63 Crore on 50:50
basis between Unit-1 and Unit-2 of its Project. Accordingly, the non-tariff income considered
for Unit-2 for FY 2017-18 is Rs.4.32 Crore.
33. The Petitioner has considered projected non-tariff income of Rs. 2 Crore for Unit-2
(i.e. projected non-tariff income of Rs. 4 Crore for the Project) FY 2018-19 which is subject to
true-up based on the Annual Audited Accounts for FY 2018-19.
G. Foreign Exchange Rate Variation (FERV):
34. The Petitioner submits that during the period of FY 2017-18 petitioner has incurred a FERV
loss of Rs. 43.24 Crore for Unit-2 and accordingly the same has been claimed in Annual Fixed
Charges for Unit-2 for FY 2017-18. Following is the reconciliation of FERV claimed in the
instant Petition:
12
(Rs. Crore)
Particulars Amount
Total FERV Losses realized as on 31.03.2018 as per Auditor’s Certificate of
Expenditure dated 12.11.2018 197.12
FERV losses capitalized with Unit-1 on its COD (20.05.2015) as allowed by this
Hon’ble Commission in its Order dated 01.12.2017 passed in Petition No. 68 of 2016 46.69
FERV losses capitalized with Unit-2 on its COD (07.04.2016) as allowed by this
Hon’ble Commission in its Order dated 29.11.2018 passed in Petition No. 10 of 2018 101.35
FERV Losses allowed as part of AFC by by this Hon’ble Commission in its Order
dated 29.11.2018 passed in Petition No. 10 of 2018 5.84
Balance FERV Losses allocated to Unit 2 as part of AFC for FY 2017-18 43.24
Summary for Annual Capacity (Fixed) Charges for Unit-2
35. In view of above, the Annual Fixed (Capacity) Charges claimed for Unit-2 for FY 2017-18
and FY 2018-19 (i.e remaining control period under MPERC Tariff Regulations 2015) are as
under:
(Rs. Crore)
36. It is submitted that in line with Tariff Regulations, 2015 the Tariff Forms for FY 2017-18 and
FY 2018-19 (i.e remaining control period under MPERC Tariff Regulations 2015) are
attached hereto and marked as ANNEXURE-5
Norms of Operation
A. Normative Annual Plant Availability Factor (NAPAF)
37. In accordance with Regulation 39.3(A) of Tariff Regulations, 2015, NAPAF of 85% has been
considered in the present Petition. The same has also been allowed by the Hon’ble
Commisison in its Order dated 29.11.2018 passed in Petition No. 10 of 2018.
Particulars FY 2017-18 FY 2018-19
Return on Equity 143.15 150.49
Interest on Loan 309.09 303.33
Depreciation 170.06 178.78
Interest on Working Capital 55.94 55.61
O&M Expenses 103.80 110.28
FERV 43.24 -
Total 825.29 798.49
No. of Operational Days Applicable for the Period 365 365
Total Capacity Charges for applicable days 825.29 798.49
Less: Non Tariff Income 4.32 2.00
Net Capacity Charges for applicable days 820.98 796.49
Capacity Charges for contracted Capacity i.e. (30%) of installed
Capacity 246.29 238.95
13
B. Gross Station Heat Rate (SHR)
38. Regulation 39.3 (C) of Tariff Regulations, 2015 provides the following:
"(C) Gross Station Heat Rate
(a) Existing Coal based thermal generating stations having COD on or after 1.4.2012
till 31.03.2016, (other than those covered under clause 39.2) shall be the heat rate
norms approved during FY 2012-13 to FY 2015-16.
New thermal generating stations achieving COD on or after 1.4.2016:
(b) Coal-based Thermal Generating Stations = 1.045 X Design Heat Rate (kCal/kWh)
Where the Design Heat Rate of a Unit means the Unit heat rate guaranteed by the
supplier at conditions of 100% MCR, zero percent make up, design coal and design
cooling water temperature/back pressure:
Provided that the design heat rate shall not exceed the following maximum design
Unit heat rates depending upon the pressure and temperature ratings of the Units:
.
.
Provided further that in case pressure and temperature parameters of a Unit are
different from above ratings, the maximum design Unit heat rate of the nearest class
shall be taken:
Provided also that where Unit heat rate has not been guaranteed but turbine cycle
heat rate and boiler efficiency are guaranteed separately by the same supplier or
different suppliers, the Unit design heat rate shall be arrived at by using guaranteed
turbine cycle heat rate and boiler efficiency:
Provided also that if one or more Units were declared under commercial operation
prior to 1.4.2016, the heat rate norms for those Units as well as Units declared under
commercial operation on or after 1.4.2016 shall be lower of the heat rate norms
arrived at by above methodology.
Note: In respect of Units where the boiler feed pumps are electrically operated, the
maximum design Unit heat rate shall be 40 kCal/kWh lower than the maximum design
Unit heat rate specified above with turbine driven BFP."
39. The Petitioner submits that in accordance with provisions contained in Regulation 39.3 (C) of
Tariff Regulations, 2015, the SHR of 2361.51 kCal/kWh as considered by this Hon’ble
Commisison in its Order dated 29.11.2018 (at Paragraph 192), has been retained in the instant
Petition.
14
C. Specific Fuel Oil Consumption (SFOC)
40. The Petitioner submits that in accordance with the provisions of Regulation 39.3 (D) of Tariff
Regulations, 2015, it has considered SFOC of 0.50 ml/kWh for the purpose of tariff, which
has also been considered by this Hon’ble Commisison in its Order dated 29.11.2018 (at
Paragraph 196).
D. Auxiliary Energy Consumption (Aux)
41. The Petitioner submits that in accordance with the provisions of Regulation 39.3 (E) of Tariff
Regulations, 2015, it has considered Auxiliary Energy Consumption of 5.75% i.e. (5.25% +
0.5%) for the purpose of tariff, which has also been considered by this Hon’ble Commisison
in its Order dated 29.11.2018 (at Paragraph 195).
Energy Charges for Unit-2 for FY 2017-18 and FY 2018-19 (i.e remaining control period
under MPERC Tariff Regulations 2015)
42. Considering the norms of operations in terms of SHR, Aux etc. as stated above, the Petitioner
has estimated the Energy Charges of Rs.1.917 per kWh for Unit-2 of the Project for the period
FY 2017-18 and FY2018-19 . The same has been calculated based on the actual fuel price and
calorific values for the three months (Jan’ 2016, Feb’ 2016 and Mar’ 2016) preceding
01.04.2016 as stipulated under Regulation 34.2 of Tariff Regulations, 2015 and has also been
considered by this Hon’ble Commisison in its Order dated 29.11.2018 (at Paragraph 222).
43. Accordingly, the weighted average landed cost and GCV of fuel as shown below has been
considered in the Petition:
S.No Particulars Values
1 Weighted Avg. GCV of Coal 3587.09 kCal/Kg
2 Weighted Avg. Price of Coal Rs. 2707.61/MT
3 Weighted Avg. GCV of Secondary Oil 9920 kCal/Lt
4 Weighted Avg. Price of Oil Rs. 26663/KL
44. The Energy charges for Unit-2 claimed for FY 2017-18 and FY 2018-19 in the instant Petition
are tabulated below:
15
Particulars FY 2017-18 FY 2018-19
Capacity (MW) 600 600
Target Availability (%) 85% 85%
Hours in a Day 24 24
Days in the Year 365 365
Annual Hours of Operation 8760 8760
Energy Generated (MU) 4467.60 4467.60
Aux. Power Consumption 5.75% 5.75%
Aux. Power Consumption (MU) 256.887 256.887
Energy Sent Out (MU) 4210.713 4210.713
Gross Station Heat Rate (kCal/kwh) 2361.51 2361.51
Specific Fuel Oil Consumption (ml/kwh) 0.50 0.50
Oil Stock
Weighted Avg. GCV of Oil (kCal/Lit.) 9920 9920
Heat Contribution by Oil (kCal/kwh) 4.96 4.96
Annual Requirement of Oil (KL) 2233.8 2233.8
Oil Stock (2 months) (KL) 372.30 372.30
Weighted Avg. Price of Oil (Rs./KL) 26663.00 26663.00
Oil Stock- 2 months- (Rs. Crore) 0.99 0.99
Coal Stock
Weighted Avg. GCV of Coal (kCal/kg) 3587.09 3587.09
Heat Contribution by Coal (kCal/kwh) 2356.55 2356.55
Specific Coal Consumption (kg/kwh) including
transit loss @ 0.8% 0.662 0.662
Annual Requirement of Coal (MT) 2982342 2982342
Coal Stock (30 days) (MT) 248529 248529
Weighted Avg. Price of Coal (Rs./MT) 2707.61 2707.61
Coal Stock (30 days) (Rs.Crore) 67.29 67.29
Variable Charges (Ex Bus)
Coal (Rs/kwh) 1.902 1.902
Oil (Rs/kwh) 0.014 0.014
Rs./kwh 1.917 1.917
Variable Charges per Year (Rs. Crore) 807.19 807.19
Receivables
Variable Charges - 2 Months (Rs. Crore) 134.53 134.53
Fixed Charges - 2 Months (Rs. Crore) 137.55 133.08
Total Receivables -2 Months (Rs. Crore) 272.08 267.61
45. However, the actual billing of Energy Charges shall be as per the formula and other provision
detailed in Regulation 36 of Tariff Regulations, 2015.
16
46. In terms of MPERC (Fees, Fines and Charges) (Revision-I) (First Amendment) Regulations,
2010, the requisite filling fees for the Unit-2 (600 MW) amounting to Rs. 1.00 Lakh has
already been paid by the Petitioner vide Demand Draft No. 12200 dated 20.12.2018 effected
by AXIS BANK. The said Demand Draft is attached hereto and marked as ANNEXURE-6
Statutory Charges
47. The Petitioner prays that this Hon’ble Commission may be pleased to allow recovery of
statutory charges, duties, taxes and cess on pass through basis from the beneficiary. It is
submitted that the Tariff Regulations, 2015 allow the recovery of electricity duty, cess and
water charges in terms of Regulation 52. However, there are certain other statutory charges,
duties and taxes which are linked with the generation of a power station. Just as in the case of
other fuel related/variable charges, there are express provisions in several tariff orders and
regulations framed by other State Commissions which allow the recovery of statutory charges,
taxes and duties on pass through basis based on actuals.
(a) Chhattisgarh
Regulation 47(1) of the Chhattisgarh State Electricity Regulatory Commission (Terms
and Conditions for Determination of Tariff according to Multi-year Tariff Principles and
Methodology and Procedure for determination of Expected revenue and Tariff and
Charges) Regulations, 2012 provide:-
“3. The Statutory Taxes and Duties shall be recoverable on reimbursement basis,
as per actual.”
(b) Uttar Pradesh
Further, the Ld. Uttar Pradesh Electricity Regulatory Commission in the Multi Year
Tariff Order for FY 2009-10 to 2013-14 in respect of the state thermal generating
company namely Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited had allowed the
recovery of:
(A) Recovery of Water Cess and Tax on Income etc.
“In addition to the above tariff UPRVUNL is allowed to recover the payment of
statutory charges like water cess, cost of water, payment to Pollution Control
Board, rates and taxes, FBT and Regulatory Fee paid to the Commission, on
production of details of actual payments made and duly supported with the
certificate of the Statutory Auditors. The Petitioner has claimed certain
additional charges as variable charges towards other fuel related costs, station
supplies, lubricants and consumables critical to the generating stations as
separate pass through on actuals. The same is allowed for the consideration
17
period of MYT subject to verification of audited accounts at the time when true up
would be considered by the Commission.”
48. In view of the above, it is prayed that this Hon’ble Commission may permit recovery of other
Statutory Charges on actual incurred basis as they are variable in nature and directly
attributable to generation of electricity from the Project.
PRAYER
49. In view of the above, the Petitioner respectfully prays that this Hon’ble Commission may
kindly:
(a) Determine the Trued-up tariff for Unit-2 of the Project as required under the
Non-Concessional PPA dated 05.01.2011 for the period from 01.04.2017 till 31.03.2019;
(b) Allow the recovery of the application filing fees from the beneficiary as per
Paragraph 46 of the instant Petition;
(c) Allow the recovery of the publication expenses from the beneficiary as and when
incurred;
(d) Allow the recovery of other charges including but not limited to RLDC/ NLDC charges,
Electricity Duty, Cess, Water Charges, other Statutory Charges, Taxes, Duties & Cess,
re-imbursement of any fee and/or expenses etc. on pass through basis from the
beneficiary for the period from 01.04.2017 to 31.03.2019;
(e) Allow carrying cost / interest on the under-recovered amount in accordance with
Regulation 8.15 of Tariff Regulations, 2015.
(f) Permit recovery of expenses understated/ not considered/ missed in the instant Petition at
a later stage, if required;
(g) Condone any inadvertent omissions/errors/rounding off differences/ shortcomings and
permit the Petitioner to add/alter this filing and make further submissions as may be
required by this Hon’ble Commission; and
(h) Pass such further and other Orders, as this Hon’ble Commission may deem fit and proper,
keeping in view the facts and circumstances of the case.
MB Power (Madhya Pradesh) Limited
DATE: 20.12.2018
PLACE: NEW DELHI