41
Filing of ARR & FPT for SLDC business for Third Control Period (FY 2014-15 to FY 2018-19) 1 BEFORE THE HONOURABLE ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION AT ITS OFFICE AT V th FLOOR, SINGARENI BHAVAN, RED HILLS, HYDERABAD FILING NO.______/2013 CASE NO. _______/2013 In the matter of: Filing of the Aggregate Revenue Requirement (ARR), Filing for Proposed Tariff (FPT) for the Third Control Period (FY 2014-15 to FY 2018-19) for its SLDC Activity under Section 26(5) of the Andhra Pradesh Electricity Reform Act, 1998 (hereinafter referred to as ‘the Act’) and under Part VII (Section 61 to Section 64) of the Electricity Act, 2003 read with the relevant APERC Guidelines and Regulations till date, by the Transmission Corporation of Andhra Pradesh Limited (‘APTransco’ or ‘the Licensee’) as the Transmission Licensee and SLDC operator. In the matter of: TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED Applicant AFFIDAVIT OF APPLICANT VERIFYING THE APPLICATION ACCOMPANYING FILING OF AGGREGATE REVENUE REQUIREMENTS I, Suresh Chanda , S/o Ramgopal Singh, working for the gain at the Transmission Corporation of Andhra Pradesh Limited do solemnly affirm and say as follows: 1. I am the Chairman and Managing Director of APTransco, the licensee company operating and controlling the Transmission & SLDC business of electricity in Andhra Pradesh pursuant to the license granted by the Hon’ble Commission and in terms of Government of Andhra Pradesh (GoAP) orders vide G.O.Ms.No.8 dated 17-01-2004. I am competent and duly authorised by APTransco to affirm, swear, execute and file this affidavit in the present proceedings. 2. I have read and understood the contents of the accompanying Filing of Aggregate Revenue Requirement for SLDC Business. The statements made in the paragraph 9 of the accompanying application now shown to me are true to my knowledge, derived from the official records made

BEFORE THE HONOURABLE ANDHRA PRADESH … MYT ARR.pdf · filing of arr & fpt for sldc business for ... before the honourable andhra pradesh electricity regulatory ... before the honourable

  • Upload
    lycong

  • View
    221

  • Download
    0

Embed Size (px)

Citation preview

Filing of ARR & FPT for SLDC business for Third Control Period (FY 2014-15 to FY 2018-19)

1

BEFORE THE HONOURABLE ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION

AT ITS OFFICE AT Vth FLOOR, SINGARENI BHAVAN, RED HILLS, HYDERABAD

FILING NO.______/2013

CASE NO. _______/2013

In the matter of:

Filing of the Aggregate Revenue Requirement (ARR), Filing for Proposed Tariff (FPT) for the Third

Control Period (FY 2014-15 to FY 2018-19) for its SLDC Activity under Section 26(5) of the Andhra

Pradesh Electricity Reform Act, 1998 (hereinafter referred to as ‘the Act’) and under Part VII (Section

61 to Section 64) of the Electricity Act, 2003 read with the relevant APERC Guidelines and

Regulations till date, by the Transmission Corporation of Andhra Pradesh Limited (‘APTransco’ or ‘the

Licensee’) as the Transmission Licensee and SLDC operator.

In the matter of:

TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED

… Applicant

AFFIDAVIT OF APPLICANT VERIFYING THE APPLICATION ACCOMPANYING FILING OF AGGREGATE REVENUE REQUIREMENTS I, Suresh Chanda , S/o Ramgopal Singh, working for the gain at the Transmission Corporation of

Andhra Pradesh Limited do solemnly affirm and say as follows:

1. I am the Chairman and Managing Director of APTransco, the licensee company operating and

controlling the Transmission & SLDC business of electricity in Andhra Pradesh pursuant to the

license granted by the Hon’ble Commission and in terms of Government of Andhra Pradesh

(GoAP) orders vide G.O.Ms.No.8 dated 17-01-2004. I am competent and duly authorised by

APTransco to affirm, swear, execute and file this affidavit in the present proceedings.

2. I have read and understood the contents of the accompanying Filing of Aggregate Revenue

Requirement for SLDC Business. The statements made in the paragraph 9 of the accompanying

application now shown to me are true to my knowledge, derived from the official records made

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

2

available to me and are based on information and advice received which I believe to be true and

correct.

DEPONENT

VERIFICATION:

I, the above named Deponent solemnly affirm at Hyderabad on this 30th November, 2013 that

the contents of the above affidavit are true to my knowledge, no part of it is false and nothing

material has been concealed there from.

DEPONENT

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

3

BEFORE THE HONOURABLE ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION

AT ITS OFFICE AT Vth FLOOR, SINGARENI BHAVAN, RED HILLS, HYDERABAD

FILING NO.______/2013

CASE NO. ______/2013

In the matter of:

Filing of the Aggregate Revenue Requirement (ARR), Filing for Proposed Tariff (FPT) for the Third

Control Period (FY 2014-15 to FY 2018-19) for its SLDC Business under Section 26(5) of the Andhra

Pradesh Electricity Reform Act, 1998 (hereinafter referred to as ‘the Act’) and under Part VII (Section

61 to Section 64) of the Electricity Act, 2003 read with the relevant APERC Guidelines and

Regulations till date, by the Transmission Corporation of Andhra Pradesh Limited (‘APTransco’ or ‘the

Licensee’) as the Transmission Licensee and SLDC operator.

In the matter of:

TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED

… Applicant

The Applicant respectfully submits as under: -

1. Pursuant to the applicable provisions of the Andhra Pradesh Electricity Reform Act, 1998, the

Government of Andhra Pradesh undertook the reform and restructuring of the erstwhile

Andhra Pradesh State Electricity Board (‘APSEB’). APTransco has been formed as a

successor entity of the erstwhile APSEB through the First statutory transfer scheme, which

was notified in the Official Gazette of the Government of Andhra Pradesh on February 1st

1999 to manage the Transmission and Distribution of erstwhile APSEB. Subsequently, the

State Government notified the Second Transfer Scheme on March 31st, 2000 wherein

APTRANSCO retained the Transmission, SLDC and Bulk Supply business of the State with

itself, while transferring the Distribution and Retail Supply of the State to the four Distribution

Companies formed in the State viz., (i) Eastern Power Distribution Company of Andhra

Pradesh Limited, (ii) Southern Power Distribution Company of Andhra Pradesh Limited, (iii)

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

4

Central Power Distribution Company of Andhra Pradesh Limited, and (iv) Northern Power

Distribution Company of Andhra Pradesh Limited (collectively referred to as ‘Discoms’).

2. Pursuant to obtaining independent licenses by the Discoms in December 2000, APTransco

has relinquished its Distribution & Retail Supply License.

3. Subsequently on June 7, 2005, the State Government notified the Third Transfer Scheme in

its official gazette wherein the Bulk Supply business and undertaking of APTRANSCO is

vested to the DISCOMs with effect from June 9, 2005. As a result, APTRANSCO is presently

carrying out solely the Transmission & SLDC business as the State Transmission Utility (STU)

in the State.

4. This filing for Levy of Annual fee and Operating charges for SLDC business is in accordance

with the provisions of the Reform Act, the Electricity Act 2003, the License granted by the

Hon’ble Commission to APTransco on January 31, 2000 and the Guidelines and Regulation

No.1 of 2006, issued by the Honorable Commission.

5. Sub-section (1) of section 31 of the Electricity Act, 2003, provides that the State Government

shall establish a State Load Dispatch Center (SLDC). Sub-section (2) of the Section 31

provides that the said SLDC shall be operated by a Government

company/authority/corporation constituted by or under any State Act and that until such

company /authority /corporation is notified by the State Government, the State Transmission

Utility (STU) shall operate the SLDC. The Government of AP notified in G.O.Ms.No.8 dated

17-01-2004 that the existing SLDC shall continue as SLDC and be operated by the

Transmission Corporation of AP Ltd., being the STU, until the State Government establishes a

Government Company or any authority or Corporation.

6. While filing the present petition for Annual fee and Operating charges for SLDC Business,

APTransco has endeavored to comply with the various applicable legal and regulatory

directions and stipulations including the directions of the Hon’ble Commission in the Business

Rules of the Commission, the Guidelines, prior ARR and Tariff Orders and the recent

Regulations on Levy and Collection of Fees and Charges by State Load Dispatch Centre

(Regulation No. 1 of 2006) dated July 27, 2006.

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

5

7. Based on the information available, the Applicant has made bonafide efforts to comply with

the directions of the Hon’ble Commission and discharge its obligations to the best of its

abilities. However, any further material become available in the near future, the Applicant

reserves the right to file such additional information and consequently amend /revise the

application.

8. The current petition for Annual fee and Operating charges for SLDC Business being filed has

been discussed and approved by the Board of Directors of APTransco and Sri. Suresh

Chanda, Chairman and Managing Director of APTransco has been authorized to execute and

file the said annual fee and operating charges Petition on behalf of APTransco. Accordingly,

the current petition for Annual fee and Operating Charges for SLDC Business is signed and

verified by, and backed by the affidavit of Sri. Suresh Chanda, Chairman and Managing

Director.

9. In the aforesaid facts and circumstances, the Applicant requests that the Hon’ble Commission:

a. Take the accompanying Annual fee and Operating charges for Petition of APTransco for

SLDC Business on record;

b. Grant suitable opportunity to APTransco within a reasonable time frame to file additional

material information if any;

c. Grant the waivers prayed for with respect to such filing requirements, as APTransco is

unable to comply with at this stage, as more specifically detailed and for the reasons set

out in the present Annual fee and Operating charges filing for SLDC Business.

d. Treat the filing as complete in view of substantial compliance as also the specific requests

for waivers with justification placed on record;

e. Consider and approve SLDC Annual fee and Operating charges including all requested

regulatory treatments in the filing;

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

6

f. Pass such order, as the Hon’ble Commission may deem fit and proper in the facts and

circumstances of the case.

TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED

(APPLICANT)

Through

Suresh Chanda

CHAIRMAN AND MANAGING DIRECTOR

Place: HYDERABAD

Dated: November 30th, 2013

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

7

Contents Page No.

1 INTRODUCTION 9

2 TRUE UP - ANALYSIS OF PERFORMANCE FROM FY 2008-09 TO FY 2012-13 10

2.1 OPERATING EXPENSES TRUE UP: 10

2.2 CAPITAL COST TRUE UP: 12

2.3 REVENUE TRUE UP: 13

2.4 SURPLUS/ (DEFICIT) DURING THE PERIOD FY 2008-09 TO FY 2012-13 14

3 DETERMINATION OF SLDC ANNUAL FEE FOR 3RD

CONTROL PERIOD 15

3.1 CAPITAL INVESTMENTS 15

3.2 CAPITAL COST PROJECTION 23

3.3 TOTAL GENERATION CAPACITY: 23

3.4 ANNUAL FEE FOR THE THIRD CONTROL PERIOD AND REVISED CAPITAL COST FOR FY 2013-14 24

4 DETERMINATION OF SLDC OPERATING FEE FOR THE 3RD

CONTROL PERIOD 25

4.1 EMPLOYEE COST: 25

4.2 ADMINISTRATION AND GENERAL CHARGES: 26

4.3 REPAIRS AND MAINTENANCE COSTS: 26

4.4 SURPLUS CLAWED BACK 27

4.5 OPERATING CHARGES FOR THIRD CONTROL PERIOD: 28

5 SUMMARY – SLDC CHARGES 29

6 ANNEXURE-A 30

7 ANNEXURE-B 32

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

8

LIST OF TABLES PAGE NO.

TABLE 1: OPERATION AND MAINTENANCE EXPENSES - APERC 10

TABLE 2: OPERATION AND MAINTENANCE EXPENSES - ACTUAL 11

TABLE 3: TRUE UP: OPERATION AND MAINTENANCE EXPENSES - VARIANCE 11

TABLE 1 : TRUE UP: INVESTMENT AND CAPITAL COST - VARIANCE 13

TABLE 5: TRUE UP: ACTUAL REVENUE 13

TABLE 6: TRUE UP: SURPLUS/(DEFICIT) FOR THE PERIOD FY 2008-09 TO FY 2012-13 14

TABLE 7: PROPOSED CAPITAL INVESTMENT FOR THE 3RD

CONTROL PERIOD 16

TABLE 8: CAPITAL COST FOR THE 3RD

CONTROL PERIOD 23

TABLE 9: ESTIMATED GENERATION CAPACITIES (MW) 24

TABLE 10: SLDC ANNUAL FEE FOR THE 3RD

CONTROL PERIOD 24

TABLE 11: PROJECION – OPERATION AND MAINTENANCE EXPENSES 245

TABLE 12: SLDC OPERATING FEE – 3RD

CONTROL PERIOD 28

TABLE 13: SUMMARY – FILING FOR SLDC FOR THE 3RD

CONTROL PERIOD 29

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

9

1 Introduction

Pursuant to the applicable provisions of the Electricity Act, 2003 the State Government shall

establish a State Load Dispatch Center (SLDC). Section 31 (2) of the Act, provides that the said

SLDC shall be operated by a Government Company / Authority / Corporation constituted by or

under any State Act and that until such Company / Authority / Corporation is notified by the State

Government, the State Transmission Utility (STU) shall operate the SLDC. The Government of

AP notified in G.O.Ms.No. 8, dated 17-01-2004 that the existing SLDC shall continue as SLDC

and be operated by the APTransco being the STU, until the State Government establishes a

Government Company / Authority / Corporation. As a result APTransco is presently carrying out

solely, the Transmission & SLDC business as the State Transmission Utility (STU) in the state.

The purpose of this filing is to propose for levy and collection of annual fee and operating

charges of SLDC business. Section 32 (3) of the Electricity Act, 2003 provides for levy and

collection of such fees and charges from the generating companies and licensees engaged in the

intra-state transmission of electricity as may be specified by the State Commission.

As per the clause 6 of Regulation (Regulation No. 1 of 2006 dated July 27, 2006), on levy and

collection of fees and charges by State Load Dispatch, APTransco has to file with the

Commission, an application / petition for the second control period with statements containing

details of the Fee and Charges under its currently – approved levels of fee and charges along

with the proposals for the Third Control Period of 5 years for FY 2014-15 to FY 18-19.

In compliance with the APERC Regulations and Guidelines, APTransco, the State Transmission

Utility & Transmission licensee managing the SLDC business (as per G.O.Ms.No. 8 dated

17.01.2004) herein submits the following in this Petition:

i. Analysis of Performance of FY 2008-09 and Second Control period from

FY2009-10 to FY2012-13.

ii. Revised Estimates for FY2013-14

iii. Annual Fee for the Third Control Period (FY 2014-15 to FY 2018-19)

iv. Operating Charges for the Third Control Period (FY 2014-15 to FY 2018-19)

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

10

2 True Up - Analysis of Performance from FY 2008-09 to FY 2012-13

APTRANSCO had filed for determination of ARR for SLDC for the 2nd control period (FY 2009-10

– FY 2013-14) and the Hon’ble commission had determined the ARR and charges based on

principles laid out in Regulation 1 of 2006.

The actual costs and revenue vary with the cost and revenue approved by APERC for the

2nd control period. Following is the variation w.r.t costs and revenue for the years FY 2008-09 to

FY 2012-13.

2.1 Operating Expenses True Up:

Operating Expenses consist of the following expenses:

Employee Expenses

Administration and General Expenses

Repair & Maintenance Expenses

Other Miscellaneous expenses

There is a significant variance in the actual employee expenses as compared to the expenses

approved by the Hon’ble commission. The salaries of employees of SLDC were revised in FY

2010-11. This contributed in an increase of employee expenses.

The details of the O&M expenses approved by the commission, actual O&M Expenses and

variation in expenses are as given below: in

Table 1: Operation and Maintenance Expenses - APERC

O&M Expenses - SLDC Tariff Order

Parameter Unit 2008-09 2009-10 2010-11 2011-12 2012-13 Total

Employee Cost INR Crs 19.19 19.36 21 22.85 24.85 107.25

Administration and

General Expenses INR Crs 2.77 2.89 3.14 3.42 3.71 15.93

Repair and

Maintenance

Expenses

INR Crs 2.92 3.66 3.96 4.24 4.46 19.24

Other Expenses INR Crs 0.04 - - - - 0.04

Cost Clawed back INR Crs - -1.58 - - - -1.58

Total Operating

Expenses INR Crs 24.92 24.33 28.10 30.51 33.02 140.88

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

11

Table 2: Operation and Maintenance Expenses - Actual

O&M Expenses - Actual

Parameter Unit 2008-09 2009-10 2010-11 2011-12 2012-13 Total

Employee Cost INR Crs 16.67 19.29 31.2 34.53 38.63 140.32

Administration and

General Expenses INR Crs 2.40 2.73 3.41 4.07 4.60 17.21

Repair and

Maintenance

Expenses

INR Crs 5.35 4.92 5.12 4.56 4.79 24.74

Other Expenses INR Crs (0.06) - - - - (0.06)

Cost Clawed back INR Crs

-

Total Operating

Expenses INR Crs 24.36 26.94 39.73 43.16 48.02 182.21

Table 3: True Up: Operation and Maintenance Expenses - Variance

Deviation Deviation Deviation Deviation Deviation APERC Actual Deviation

Employee Cost INR Crs (2.52) (0.07) 10.20 11.68 13.78 107.25 140.32 33.07

Administration and General

ExpensesINR Crs

(0.37) (0.16) 0.27 0.65 0.89 15.93 17.21 1.28

Repair and Maintenance

ExpensesINR Crs

2.43 1.26 1.16 0.32 0.33 19.24 24.74 5.50

Other Expenses INR Crs (0.10) - - - - 0.04 (0.06) (0.10)

Cost Clawed back INR Crs - 1.58 - - - (1.58) - 1.58

Total Operating Expenses INR Crs (0.56) 2.61 11.63 12.65 15.00 140.88 182.21 41.33

O&M Expenses - APERC vis-à-vis Actual

Parameter Unit2008-09 2009-10 2010-11 2011-12 2012-13 Total

As could be seen from the above table, from year FY 2008-09 to FY 2012-13, Rs.41.33 Crs

excess expenditure was incurred than the approved expenditure. The employee expenditure

increased by Rs.33.07Crs, A&G expenditure increased by Rs.1.28Crs and Repairs &

Maintenance expenditure increased by Rs.5.5 Crs than the approved expenditure in the Tariff

Orders.

Almost 85% of the variance in O&M expenses is due to an increase in the Employee Expenses

during the 2nd control period. The employee expenses increased only after FY 2010-11 due to

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

12

revision in pay for the employees of SLDC. This was already mentioned by APTRANSCO during

the filing of MYT for 2nd Control Period for SLDC activity.

The increase in repairs and maintenance cost is due to the AMC of EMS/ SCADA system as long

term service agreement has been entered with M/s Power Grid for AMC of EMS/ SCADA system

for three years from 01-01-07 to 31-12-09 with a provision for extension of the LTSA for a further

period of 2 years at the same prices, terms and conditions. The LTSA from 01-01-07 to 31-12-09

had offshore component which varied as per dollar exchange rate and hence, the charges for the

period varied. After completion of 01-01-07 to 31-12-09 period, Karnataka opted out of the LTSA

and as the supplier insisted on fixed amount for the southern region, Karnataka amount was

shared among rest of constituents and hence AMC charges increased. The LTSA payments are

made as per the MoU entered

Hence, the R&M expenses have increased during the control period. We would humbly request

the Hon’ble commission to consider the increase in expenses.

2.2 Capital Cost True Up:

Capital Cost approved in the Tarff Order would cover the repayment of principal and payment of

interest on investment in a year, plus any residual capital cost of past investment.

But, the actual Capital Cost varies from the Capital Cost approved by the Commission mainly

due to the following reasons:

The year on year actual investments made by SLDC do not match the investments envisaged by

the commission.

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

13

The details of the capital cost incurred vis-à-vis the Hon’ble Commissions approved capital cost

is shown below table:

Table 4: True Up: Investment and Capital Cost - Variance

Capital Cost as per–Tariff Order

Parameter Unit 2008-09 2009-10 2010-11 2011-12 2012-13 Total

Residual/Annual

Investment INR Crs 26.37 9.16 9.76 9.69 4.83 59.81

Total Capital Cost INR Crs 4.11 5.54 7.06 8.57 9.32 34.59

Capital Cost as per – Actuals

Residual/Annual

Investment INR Crs 16.59 1.19 0.55 1.66 0.43 20.42

Total Capital Cost INR Crs 2.59 1.88 2.26 2.08 1.92 10.73

Difference in

Capital Cost INR Crs (1.52) (3.66) (4.80) (6.49) (7.40) (23.86)

The actual residual value at the begging of FY 2008-09 was INR 16.59 Crs Vis-à-vis INR 26.37

Crs estimated by the commission. The actual investments made during 2nd Control period are

less than the approved investments in the Tariff Order.

2.3 Revenue True Up:

Table 5: True Up: Actual Revenue

Revenue

Parameter Unit 2008-09 2009-10 2010-11 2011-12 2012-13 Total

Tariff Order INR Crs 29.03 29.87 35.16 39.08 42.34 175.47

Actual INR Crs 31.24 31.15 35.66 40.79 54.78 193.62

Difference INR Crs 2.21 1.28 0.5 1.71 12.44 18.15

The revenue has increased by around 10%. This is mainly due to increase in the number of

Open Access consumers in FY 2012-13.

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

14

2.4 Surplus/ (Deficit) during the period FY 2008-09 to FY 2012-13

Table 6: True Up: Surplus/(Deficit) for the period FY 2008-09 to FY 2012-13

Surplus/(Deficit)

Parameter Unit 2008-09 2009-10 2010-11 2011-12 2012-13 Total

Actual Cost INR Crs

26.95

28.82

41.99

45.24

49.94

192.94

Actual Revenue INR Crs 31.24 31.15 35.66 40.79 54.78 193.62

Surplus/(Deficit) INR Crs 4.29 2.33 -6.33 -4.45 4.84 0.68

The total surplus estimated for the period FY 2008-09 to FY 2012-13 is INR 0.68 Crs. The

surplus would be passed on to consumers in the 3rd control period.

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

15

3 Determination of SLDC Annual Fee for 3rd Control Period

The Hon’ble Commission has notified the Regulation No.1 on “Levy and collection of Fees and

Charges by SLDC” (Regulation No. 1 of 2006) dated July 27th 2006. As per the above regulation,

the APTRANSCO has to file an application for Annual Fee and Operating Charges for the Third

Control period of 5 years from FY 2014-15 to FY 2018-19.

Filing for Annual Fee

In compliance with Clause of Regulation 1 of 2006, APTRANSCO has to determine the Capital

cost for the period FY 2014-15 to FY 2018-19 based on the methodology suggested by the

Hon’ble commission and then compute the Annual SLDC charges. The Capital Cost covers the

repayment of principal and payment of interest on the investments made in a year

Annual SLDC Fee (Rs /MW/Annum) = (Capital Cost (CC) (in Rs) / Total Generation Capacity

(MW) )

APTRANSCO has computed the Annual SLDC charges based on the following methodology:

Estimation of Year on Year Investments for the period FY 2014-15 to FY 2018-19

Computation of Capital Cost based on methodology suggested by the Hon’ble

Commission

Determination of Year on Year Generation Capacity

Computation of SLDC Annual Charges

3.1 Capital Investments

The plan of Capital Assets to be added for SLDC Activity for the Five Year of 3rd Control Period

(FY 2014-15 to FY 2018-19) and Revised Estimates for FY2013-14 is shown in Table 7.

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

16

Table 7: Proposed Capital Investment for the 3rd Control Period

Name of the

Wing

2013-14

(R.E) 2014-15 2015-16 2016-17 2017-138 2018-19

Grid Operation 12.03 0.89 0.77 0.73 0.78 0.69

Commercial/EBC - 0.16 0.23 0.12 0.13 0.15

Telecom 3.84 40.97 14.29 14.18 12.89 -

Power Systems - 0.01 0.34 0.21 1.34 0.05

Total 15.87 42.04 15.63 15.24 15.15 0.88

The new CapitalI Assets proposed to be added during the Third control period and the need for

such capital assets for SLDC business in each of the wings viz., Grid Operation,

Telecommunication, Power System and Commercial/Energy Billing Centre wings is detailed

below.

A. Grid Operation wing:

In the above investment plan, Grid Operation wing is proposed to upgrading the existing ULDC

SCADA system

The present ULDC SCADA system is over 10 years old and the hardware and software systems

are now getting obsolete. Hence, APSLDC is upgrading the existing ULDC SCADA system with

state of the art technology in consultation with Power Grid Corporation of India Limited along with

the other Southern Region constituents viz., Kerala, Pondicherry and SRLDC.

The project execution has commenced and it is scheduled to be commissioned by ending of FY

2013-14. Hence, the large capital investment proposed in FY 2013-14.

As per present security standards for critical infrastructure, redundancy of Control Centre is

essential. Hence, the Up gradation scheme seeks to implement a remotely located (in a different

seismic zone) fully functional replica Control Center, to which all the field locations report the

real-time data parallel, on a redundant communication path. The communication protocol is being

upgraded from the present serial communication link based IEC 60870-5-101 to the Ethernet

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

17

based IEC 60870-5-104 for enhancing the data rate. For this purpose, the APTRANSCO

communication system is also being augmented.

The new system has a provision for the acquisition of data from over 1500 field locations by

means of newer communication protocols and hardware, as compared to the 140 field stations

now being monitored. Data Concentrator Cum Protocol Converters (DCPCs) will be located at 16

identified broadband locations for collecting data from the existing and new RTU stations, which

will report to the DCPC over IEC 60870-5-101 protocol. The DCPCs will in turn report to both the

main and backup SLDC over redundant communication routes, over IEC 60870-5-104 protocol.

The planned lifetime of the new project is 7 years as per the CERC regulations.

The new system provides the operators with new tools such as Complex Event Processing

(CEP) engines for enormous data storage and it’s near instantaneous retrieval; common

information model (CIM) based modeling and data exchange, Dispatcher Training Simulator

(DTS) for training, tools for better visualization of the SCADA Displays, to aid them in better Grid

Control and Visualization.

The Control Center will have a 6x3 Unit video projection system with each unit of size 70”

diagonal. This provides the operator with an excellent visualization for the large grid network.

This is in addition to the individual two monitor workstation provided to each operator.

A new DTS is also envisaged for training the operators on the new system. It will also aid the

new operators in getting trained before being posted on the job.

In view of the requirement of having SLDC data on the Internet, a dedicated APSLDC website

with real-time and historical data is being developed. The upgraded SCADA system also will

integrate seamlessly to this website with recommended cyber security systems and email

systems in tow.

The cyber security systems will have dedicated firewalls for internal and external networks apart

from IPS and IDS apart from online automated patch management solutions, antivirus solutions,

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

18

file sharing mechanisms, and single point user authentication systems. A Network Management

System is also envisaged.

Historical Data of up to seven years will be available online in the new system. The backup of the

system software and data will also be automatically taken periodically at both local and remote

location on different media. The AMC of the new system will be done by the supplier for a period

of 6 Years after the mandatory 1 year warranty, post commissioning of the system. The AMC is

also part of the Project Tender itself.

In addition to that grid operation wing, also proposed to add the assets like computers, printers,

LCD Display units, up gradation of software for various PCs in the 3rd Control Period.

B. Telecom wing:

For strengthening and Modernization of Telecom equipment the following schemes are proposed

during the second control period.

a) Communication to Back up SLDC at Tirupathi :

The provision of communication system in Transmission network for Back up SLDC, at

Tirupathi is proposed in view of the Up-gradation of existing SCADA EMS system with

Main SLDC at Vidyut Soudha, Hyderabad and Back up SLDC, at Tirupathi.

The main thrust and emphasis is laid on:

i. Providing reliable real time data (of all 220KV and 400KV SS and Generators) to Grid

operators of SLDC.

ii. Providing of data connectivity to Back up SLDC which is a fully functional replica of

Main SLDC and which shall take over operation in case of any emergency.

iii. Providing high speed secured data route with redundancy for all RTU locations.

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

19

The backup SLDC shall be a functional replica of Main SLDC so that it can function as a

full-fledged SLDC in case of any disaster. In this scheme, the full functionality of the

backup SLDC as far as the infrastructure is concerned shall be similar to the Main SLDC.

As per new SCADA EMS Up-gradation scheme proposal, all the existing and upcoming

RTUs would report to both the control centers i.e., Main SLDC & Back up SLDC preferable

over IEC 60870-5-104 protocol. RTUs coming through 101 protocol will be converted to

104 protocol through protocol convertor. Both the control centers Main and Back up will be

integrated with Distribution companies control centers as well as SRLDC, Bangalore on

ICCP links.

To meet the high speed multi data channel requirement, Optic Fibre based broadband

communication system is proposed in certain areas and Digital PLCC based

communication is proposed in certain links where execution of OFC works is difficult and

to have redundant data paths also.

Investment approval was accorded for the above scheme vide CRN:APT/TS/ULDC-up

gradation of communication/F-INVST-26/2012 by Hon’ble APERC.

b) ULDC Project commissioned during the year 2000-2002.

Power Grid and all constituents in Southern Region have implemented the Unified Load Dispatch

and Communication project for a sophisticated, reliable and secured load dispatch operations

with ALDCs, SLDCs and RLDC at Bangalore during the year 2000-2002 for transfer of real time

data from RTU location to ALDCs, SLDC and RLDC in Southern Region.

As a part of the ULDC project, the following systems are proposed:

Fibre Optic Transmission system (FOT) consisting of Optical line terminal equipment

(OLTEs)

Digital Microwave and MUX communication system with Network Management system

(NMS).

Laying of ADSS cable

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

20

c) Up gradation of existing Marconi make OLTEs commissioned under ULDC:

M/s. Marconi make OLTEs were commissioned in ULDC project in Southern Region during 2000-

2002. The following difficulties were experienced during the maintenance of the equipment.

Up gradation / modification & rectification of software corruption to be carried out by OEM

only as the software is proprietary in nature.

There is no repairing facility in India, the faulty cards of these OLTEs shall be sent to M/s.

Marconi, Italy for repairs which involves customs duty assessment etc.

In view of the above, APTRANSCO has accorded approval for AMC of OLTEs with M/s.

Ericsson along with all other constituents of Southern Region up to 31-03-2009.

Due to change in technology, M/s. Ericsson had withdrawn the support of further

maintenance w.e.f. 01-04-2009 and advised for network modification or up-gradation with

new hardware and software.

In view of the above, PGCIL have conducted several meetings to arrive a solution and reached to

a conclusion along with all constituents and APTRANSCO opined to deliberate issue at SRPC.

CEA suggested for adoption of latest technology which will support to the PMU (Phasor

Measurement units) which would be a part of smart grid in near future. Hence along with other

constituents in Southern Region, APTRANSCO also agreed for up-gradation of existing SDH

fibre optic equipment (OLTE) commissioned under ULDC project for transfer of real time data

from RTU locations to 4 ALDCs, SLDC and thereon to RLDC.

Hence APTRANSCO proposed up gradation of OLTEs.

d) Up-gradation of existing MUX commissioned under ULDC:

Alcatel make MUX equipment and NMS installed in ULDC project in Southern Region were

maintained by the original OEM M/s. Alstom Transmission & Distribution system with separate

charges for repair/replacement of faulty cards with increase in the AMC charges @ 10% of

amount year by year up to 31.12.2012.

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

21

During the year 2013, M/s. Alstom have increased the AMC by 15% on the existing AMC charges

due to change of technology and non-availability of spares and PGCIL also imposed the

overhead charges @ 15% over and above the contract price of AMC charges and M/s. Alstom

have not covered the rectification of faulty modules. APTRANSCO did not accept for increase in

AMC and PGCIL overhead charged and withdrawn from AMC and are presently being

maintained by APTRANSCO engineers with the available spare prints.

The present MUX equipment served more than 10years and also due to vast technology change

in communication system, it is necessary to upgrade the existing system. Hence we propose this

up gradation.

e) Replacement of existing ADSS cable laid under ULDC scheme by OPGW:

As per CERC Regulation of Grid code (IEGC) clause no. 4.6.2 reliable and efficient speech and

data communication system shall be provided to facilitate necessary communication and data

exchange and supervision/control of grid.

Subsequent to the commissioning of ULDC, volume of data and no. of substations/generating

stations have increased considerably. Number of hops for data transmission is increasing with

expansion of network. In addition to the requirement of communication system for SCADA

system, Special Protection schemes (SPS) are to be implemented and installation of PMUs and

Grid Security Expert System (GSES) are also envisaged. Each PMU requires minimum 64kbps

bandwidth. SPS requires transfer of signals over no. of hops. These additional requirements of

communication for the existing and upcoming substations can’t be met unless provided with

OPGW based communication link.

The ADSS cable laid under ULDC project have served more than 10years life period and giving

frequent problems. Due to change in technology and introduction of OPGW cable (Optical fibre

with ground wire), it is proposed to lay OPGW cable in place of ADSS cable because of dual

functionality of grounding and communication and most preferred aerial cable considering fibre

security and long life for transfer of real time data from RTU locations to 4 ALDCs, SLDC and

thereon to RLDC.

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

22

C. Energy Billing Center wing:

EBC wing of SLDC, is receiving Boundary meters (Generation to Transmission and Transmission

to Discoms) MRI data, manual readings from the field and on processing the above data through

various Billing applications could able to generate Transco-Discom Energy certificate, Discom-

Discom Energy & cost settlements reports and also generating Transmission Losses data for

various purposes. EBC has also developed software for Open Access users within state as per

APERC Regulation No. 2 of 2005 & Regulation No. 2 of 2006 which is web based application. All

the Open Access users as per Regulation 2 of 2006 may have to send or receive the relevant

data through this application. Further Open Access users can also view /download various

settlement data through this application.

EBC proposes to procure new Furniture, H.P Proline server (2Nos) to replace existing old

servers ,Printers for HP Color Laser Jet and also proposed provide dedicated leased line

Internet Service to its center in the 3rd Control Period for smooth functioning of Energy Billing

Center. Presently limited open access users are existing the same is expected to increase in due

course of time, for which necessary software with applicable licenses are needed to improve the

accessibility of web application to open access users. As such the propose infrastructure shown

in the investment plan is very essential

D. Power Systems:

Proposed to upgrade the outdated software currently in use for System Software, Generation

Planning Software, Transmission Planning Software and Load Forecast software.

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

23

3.2 Capital Cost Projection

Based on the capital investments shown above and 12% interest rate, the capital cost computed

as per APERC methodology is shown below:

Table 8: Capital Cost for the 3rd Control Period

Parameter Unit 2014-15 2015-16 2016-17 2017-18 2018-19 Total

Capital Cost on new

investmentINR Crs 7.44 2.73 2.66 2.64 0.16 15.63

Capital Cost on Residual

investmentINR Crs 6.05 13.49 16.22 18.88 21.52 76.16

Total Capital Cost INR Crs 13.49 16.22 18.88 21.52 21.68 91.79

Capital Cost - 3rd Control Period

The capital cost based on the residual value of asset at the end of FY 2012-13 and the

investments made during FY 2013-14 is INR 5.3 Crs Vis-à-vis INR 10.09 Crs approved by the

commission.

The residual value of assets at the end of 2013-14 has been considered to be INR 34.2 Crs. The

asset value at the beginning of FY 2013-14 was INR 18.33 Crs and the investments expected to

be made during FY 2013-14 is INR 15.87 Crs

The capital cost of this residual value and the annual capital investments is INR 91.79 Crs over

the 3rd Control Period.

3.3 Total Generation Capacity:

The total generation capacity estimated, including the capacity related to Open Access

consumers over the next five years is as shown below:

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

24

Table 9: Estimated Generation Capacities (MW)

S.No Source of Power 2014-15 2015-16 2016-17 2017-18 2018-19

I APGENCO 11330 11449 11449 12050 12790

A Thermal 7252 7252 7252 7853 8593

B Hydro 4078 4197 4197 4197 4197

II Central Generating

Stations 3669 3669 4372 4477 4477

III Joint Setor 57 57 57 57 57

IV IPPS 2426 2426 2426 2426 2426

V Others (NCE, M PP’s

etc, wind, Mini Hydel) 3606 5859 6576 6993 7361

Total 21088 23460 24881 26003 27110

VI Open Acess Generators 672 672 672 672 672

Grand Total 21761 24132 25553 26675 27782

Note:- Generating Station-wise details are shown in Annexures –B 1 to 5

3.4 Annual Fee for the Third Control Period and Revised Capital Cost for FY 2013-14

Table 10: SLDC Annual Fee for the 3rd Control Period

Parameter 2014-15 2015-16 2016-17 2017-138 2018-19

Capital Cost (INR Crs) 13.49 16.22 18.88 21.52 21.68

Generation

Capacity(MW) 21761 24132 25553 26675 27782

SLDC Annual Fee

(INR/MW/Annum) 6199 6721 7389 8069 7804

The Annual fee for the Third control period has been calculated based on the total capital cost

for the Third control period on total generation capacity as per SLDC regulation.

The Annual fee for the year FY 2014-15 is Rs.6199 MW/p.a, for the FY 2015-16 is

Rs.6121MW/p.a, for the FY 2016-17 is Rs.7389 MW/p.a, for the year FY 2017-18 is

Rs.8069MW/p.a, for the year FY 2018-19 is Rs.7804 MW/p.a.

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

25

4 Determination of SLDC Operating Fee for the 3rd Control Period

As per the guidelines given by the Commission vide para 4.5 of the regulation (Regulation

No.1/2006) the basis for determination of the Operating Charges are based on the Employee

cost, Administration and General Charges, Repairs and Maintenance expenses and other

relevant costs.

The details of the Annual Operating charges i.e. Employee cost, Administration and General

charges, Repairs and Maintenance charges and other charges are shown in the table below:

Table 11: Projection – Operation and Maintenance Expenses

Parameter Unit Base Year/

2013-14(R.E) 2014-15 2015-16 2016-17 2017-18 2018-19

Employee Cost INR Crs 47.66

58.81

72.55

89.52

110.45 136.27

Administration and

General Expenses INR Crs 5.41

6.37

7.49

8.82

10.37 12.21

Repair and

Maintenance

Expenses

INR Crs 5.05 8.17 4.71 5.39 5.62 5.37

Other Expenses INR Crs - - -

- - -

Surplus in 2nd

Control

Period – Clawed back INR Crs -

(0.68)

Total Operating Expenses

INR Crs 58.12 72.66 84.76 103.73 126.44 153.85

4.1 Employee Cost:

The employee cost for the base year FY 2013-14 has been projected based on the actual growth

rate observed in the employee expenses observed during the period FY 2008-09 to FY 2012-13.

Employee Expenses for 13-14 = (Employee Expenses for 12-13) * (CAGR (Emp exp 12-13/ Emp

exp 08-09))

The same growth rate has also been considered for projecting the employee expenses for the

3rd control period.

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

26

The employee cost, other than the salaries of the personnel, also contain the following

components:

Surrender leave

Various medical allowances

Other Allowances and pension contribution

Next wage revision is due with effect from 1st April 20104. The financial commitment of wage

revision will be claimed based on actuals

4.2 Administration and General Charges:

The Administration and General(A&G) cost for the base year FY 2013-14 has been projected

based on the actual growth rate observed in the A&G expenses observed during the period FY

2008-09 to FY 2012-13.

A&G Expenses for 13-14 = (A&G Expenses for 12-13) * (CAGR (A&G exp 12-13/ A&G exp 08-

09))

The same growth rate has also been considered for projecting the A&G expenses for the 3rd

control period.

4.3 Repairs and Maintenance Costs:

As per the clause No. 7 of Regulation 2/2006, the Energy Billing Center is also considered as the

SLDC Business. Therefore the assets of SLDC Business are mainly in Grid Operation unit,

Energy Billing Center and Telecom units. At present the Telecom unit assets are shared by the

Transmission business as well as SLDC business.

However for the purposes of calculation of operating charges certain amount of Repairs and

Maintenance expenses have been considered in the SLDC business.

These costs are primarily for the RTU’s and the SCADA system. The repairs & Maintenance

expenditure is projected based on the requirements of each wing.

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

27

A. EBC:

For smooth operations of Open Access and data collection system the following are essentially

required for AMC viz: Servers, Workstations, HUBs, Switches and procurement of consumables

like Printer cartridges and data cartridges to take the database backup and other computer

consumables for use in EBC wing is included in R&M cost.

B. Grid Operation:

The R&M expenditure projections cover for Annual Maintenance Charges for the following

equipment available in Grid Operation wing.

AMC of EMS/SCADA system till the up gradation of EMS/SCADA system gets completed,

AMC of new EMS/SCADA .

AMC of UPS systems at SLDC, ALDCs and Backup SLDC.

AMC of Air Conditioning Units at SLDC, ALDCs and Backup SLDC.

AMC of DG sets at SLDC, ALDCs.

AMC of HP Servers, PCs and printers at SLDC & ALDCs.

AMC of networking equipment at SLDC, ALDCs and Backup SLDC.

Further for regular maintenance the consumables are required for computer systems, printers

and other equipment

C. Telecom:

The repairs and maintenance cost of Telecom wing is projected due to AMC contracts of OLTEs

and MUXS with different vendors and regular maintenance of Micro wave links.

4.4 Surplus clawed back

There was a surplus of INR 0.68 Crs during the 2nd control period. We propose to pass on this

surplus to the consumers in FY 2014-15.

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

28

4.5 Operating Charges for Third Control Period: As per the regulation no .1 of 2006 the Operating charges are calculated by following formula

prescribed in the regulation.

Operating Charges (Rs / MW /pm) =( Annual Operating charges/ Total Generating Capacity

(MW) * 12)

The details of the Operating charges as shown in Table 9

Table 22: SLDC Operating Charges – 3rd Control Period

Parameter 2014-15 2015-16 2016-17 2017-138 2018-19

Operating Expenses

(INR Crs) 72.66 84.76 103.73 126.44 153.85

Generation

Capacity(MW) 21761 24132 25553 26675 27782

SLDC Operating

Charges

(INR/MW/Month)

2783 2927 3383 3950 4615

The Monthly Operating Charges for the year 2014-15 is Rs. 2783 / MW / month, for the year

2015-16 is Rs. 2,927 /MW/month, for the year 2016-17 is Rs3,383 /MW/month, for the year 2017-

18 is Rs. 3950/ MW /month and for the year 2018-19 is Rs. 4615/MW/month.

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

29

5 Summary – SLDC Charges The summary of SLDC Annual Fee and SLDC Operating Charges computed:

Table 33: Summary – Filing for SLDC for the 3rd Control Period

Summary - SLDC MYT Filing

Parameter Unit 14-15 15-16 16-17 17-18 18-19 Total

Capital Cost INR Crs 13 16 19 22 22 92

Employee Expenses INR Crs 59 73 90 110 136 468

A&G Expenses INR Crs 6 7 9 10 12 45

R&M Expenses INR Crs 8 5 5 6 5 29

Other Expenses INR Crs (0.68) - - - - (1)

O&M Expenses INR Crs 73 85 104 126 154 541

Total Cost INR Crs 86 101 123 148 176 633

Generation Capacity MW 21760 24132 25553 26675 27782

Annual Fee INR/MW/Annum 6199 6721 7389 8069 7804

Operating Charge INR/MW/Month 2783 2927 3383 3950 4615

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

30

6 ANNEXURE-A

LIST OF DIRECTIVES FOR SECOND CONTROL PERIOD

Dir. No.

Description of Directive

Status

1 APTRANSCO shall segregate the SLDC accounts in full shape within

a year, i.e. by 31st March 2010 and also immediately start maintaining

separate asset registers on prospective basis. These asset registers

will be inspected by the Commission Staff, from time to time.

(Paragraph 28)

The directive is complied with

2 APTRANSCO shall file the details of completed capital works

pertaining to SLDC operations along with Project Completion

Certificate (PCC) and Financial Completion Certificate (FCC) as is

being done for transmission projects. APTRANSCO shall also file a

monthly report with the Commission on progress in capital works

pertaining to SLDC operations by 25th of every month for the previous

month.

(Paragraph 29)

The directive is complied with

3 APTRANSCO shall file with the Commission an approach paper on its

OFC network duly indicating a) existing capacities, b) planned future

capacities c) expected surplus capacity available and d) possible

ways and means to utilize the surplus capacity by November 30,

2009.

(Paragraph 30)

The directive is complied with

4. APTRANSCO to collect variable cost information including backing

down limitation from each generating station on daily basis along with

generation schedule for a complete period of three months. Using this

information, it should analyze the perceived merit order benefits on

expost basis for the three months period and make a presentation on

this issue to the Commission by December 31, 2009.

(Paragraph 35)

The directive is complied with

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

31

5. APTRANSCO shall file the actual costs and revenues by 25th of every

month for the previous month in the format prescribed for this purpose

by the Commission. APTRANSCO may also state its own

observations on cost, revenues and capacities along with the monthly

report.

(Paragraph 48)

The directive is complied with

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

32

7 ANNEXURE-B

Generating Capacities FY 2014-15

Source of Power Plant Capacity A.P.share A.P.share

A.P. share Excl. Aux. Consm.

(MW) (%) (MW) (MW)

I APGENCO

VTPS I 420 100.00% 420.00 383.25

VTPS II 420 100.00% 420.00 383.25

VTPS III 420 100.00% 420.00 383.25

VTPS IV 500 100.00% 500.00 462.50

RTPP I 420 100.00% 420.00 382.20

RTPP-II 420 100.00% 420.00 382.20

RTPP-III 210 100.00% 210.00 191.63

KTPS A 240 100.00% 240.00 216.72

KTPS B 240 100.00% 240.00 216.72

KTPS C 240 100.00% 240.00 216.72

KTPS D 500 100.00% 500.00 455.00

KTPS VI 500 100.00% 500.00 462.50

RTS B 62.5 100.00% 62.50 56.88

Kakatiya TPS Stage 1 500 100.00% 500.00 462.50

Kakatiya TPS Stage II 600 100.00% 600.00 555.00

Damodaram Sanjeevaiah Thermal Power Plant-I 800 100.00% 800.00 748.00

Damodaram Sanjeevaiah Thermal Power Plant-II 800 100.00% 800.00 748.00

RTPP-IV 600 100.00% 600.00 546.00

TOTAL THERMAL 7892.5

7892.5 7252.31

MACHKUND PH AP Share 120 70.00% 84.00 83.16

TUNGBHADRA PH AP Share 72 80.00% 57.60 57.02

USL 240 100.00% 240.00 237.60

LSR 460 100.00% 460.00 455.40

DONKARAYI 25 100.00% 25.00 24.75

SSLM 770 100.00% 770.00 762.30

SSLM LCPH 900 100.00% 900.00 891.00

NSPH 815.6 100.00% 815.60 807.44

NSRCPH 90 100.00% 90.00 89.10

NSLCPH 60 100.00% 60.00 59.40

POCHAMPAD PH 27 100.00% 27.00 26.73

NIZAMSAGAR PH 10 100.00% 10.00 9.90

PABM 20 100.00% 20.00 19.80

SINGUR 15 100.00% 15.00 14.85

MINI HYDRO&OTHERS 12.16 100.00% 12.16 12.04

Priyadarshini JURALA HES 234 100.00% 234.00 231.66

POCHAMPAD Stg II 9 100.00% 9.00 8.91

Nagarjuna Sagar Tail Pond 50 100.00% 50.00 49.50

Lower Jurala Hydro Electric (New Project) 240 100.00% 240.00 237.60

TOTAL HYDRO 4169.76

4119.36 4078.17

Total A.P. Genco 12062.26

12011.86 11330.48

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

33

II Central Generating Stations (CGS)

NTPC(SR) Ramagundam- U1-U6 2100 32.32% 678.72 629.78

NTPC (SR) Ramagundam -U7 500 33.92% 169.60 158.58

NLC TS-II Stage-I 630 18.33% 115.48 103.93

NLC TS-II Stage-II 840 24.33% 204.37 183.93

NPC-MAPS 440 9.90% 43.56 38.99

Talcher Stage 2 2000 20.00% 400.00 374.00

NTPC- Simhadri Stage I 1000 100.00% 1000.00 940.00

NTPC- Simhadri Stage II 1000 46.01% 460.10 432.49

Kaiga Nuclear power Plant I&II 440 30.82% 135.61 121.37

Kaiga Nuclear power Plant III&IV 440 32.64% 143.62 128.54

Vallur Thermal Power Plant 1500 14.75% 221.25 206.87

Kalpakkam 500 26.40% 132.00 116.16

Tutricorn 1000 25.46% 254.60 234.23

Total Central Sector 12390

3958.91 3668.87

III Joint sector

APGPCL-I 100 16.00% 16.00 15.60

APGPCL-I 172 24.88% 42.79 41.72

Total Joint Sector 272

58.79 57.32

IV IPPs

GVK 216 100.00% 216.00 209.52

Spectrum 205 100.00% 205.00 198.85

Kondapalli 361.92 100.00% 361.92 351.06

BSES 220 100.00% 220.00 213.40

GVK Extension 220 100.00% 220.00 213.40

Vemagiri 370 100.00% 370.00 358.90

Gowthami 464 100.00% 464.00 450.08

Konaseema 444.08 100.00% 444.08 430.76

Total IPPS 2501

2501.00 2425.97

V Non Conventional Sources

Total Non conventional sources 2114.33 100.00% 2114.33 2114.33

VI Mini Power Projects

1 Sri Vatsa power Projects Limited 17.2 100.00% 17.20 16.51

2 M/s LVS Power Limited 36.8 100.00% 36.80 35.33

Total MPPS 54

54 51.84

VII OTHERS

Hinduja 1040

1040.00 1040.00

KSK Mahanadi 400

400.00 400.00

Total Others 1440

1440 1440

VIII Open Access Generators

Total Open Access Generators 671.8

671.8 671.8

Grand Total 31505.39

22810.69 21760.61

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

34

2015-16

Source of Power Plant

Capacity A.P.share A.P.share

A.P. share Excl. Aux. Consm.

(MW) (%) (MW) (MW)

I APGENCO

VTPS I 420 100.00% 420.00 383.25

VTPS II 420 100.00% 420.00 383.25

VTPS III 420 100.00% 420.00 383.25

VTPS IV 500 100.00% 500.00 462.50

RTPP I 420 100.00% 420.00 382.20

RTPP-II 420 100.00% 420.00 382.20

RTPP-III 210 100.00% 210.00 191.63

KTPS A 240 100.00% 240.00 216.72

KTPS B 240 100.00% 240.00 216.72

KTPS C 240 100.00% 240.00 216.72

KTPS D 500 100.00% 500.00 455.00

KTPS VI 500 100.00% 500.00 462.50

RTS B 62.5 100.00% 62.50 56.88

Kakatiya TPS Stage 1 500 100.00% 500.00 462.50

Kakatiya TPS Stage II 600 100.00% 600.00 555.00

Damodaram Sanjeevaiah Thermal Power Plant-I 800 100.00% 800.00 748.00

Damodaram Sanjeevaiah Thermal Power Plant-II 800 100.00% 800.00 748.00

RTPP-IV 600 100.00% 600.00 546.00

TOTAL THERMAL 7892.5

7892.5 7252.31

MACHKUND PH AP Share 120 70.00% 84.00 83.16

TUNGBHADRA PH AP Share 72 80.00% 57.60 57.02

USL 240 100.00% 240.00 237.60

LSR 460 100.00% 460.00 455.40

DONKARAYI 25 100.00% 25.00 24.75

SSLM 770 100.00% 770.00 762.30

SSLM LCPH 900 100.00% 900.00 891.00

NSPH 815.6 100.00% 815.60 807.44

NSRCPH 90 100.00% 90.00 89.10

NSLCPH 60 100.00% 60.00 59.40

POCHAMPAD PH 27 100.00% 27.00 26.73

NIZAMSAGAR PH 10 100.00% 10.00 9.90

PABM 20 100.00% 20.00 19.80

SINGUR 15 100.00% 15.00 14.85

MINI HYDRO&OTHERS 12.16 100.00% 12.16 12.04

Priyadarshini JURALA HES 234 100.00% 234.00 231.66

POCHAMPAD Stg II 9 100.00% 9.00 8.91

Nagarjuna Sagar Tail Pond 50 100.00% 50.00 49.50

Lower Jurala Hydro Electric (New Project) 240 100.00% 240.00 237.60

Pulichintala 120 100.00% 120.00 118.80

TOTAL HYDRO 4289.76

4239.36 4196.97

Total A.P. Genco 12182.26

12131.86 11449.28

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

35

II Central Generating Stations (CGS) NTPC(SR) Ramagundam- U1-U6 2100 32.32% 678.72 629.78

NTPC (SR) Ramagundam -U7 500 33.92% 169.60 158.58

NLC TS-II Stage-I 630 18.33% 115.48 103.93

NLC TS-II Stage-II 840 24.33% 204.37 183.93

NPC-MAPS 440 9.90% 43.56 38.99

Talcher Stage 2 2000 20.00% 400.00 374.00

NTPC- Simhadri Stage I 1000 100.00% 1000.00 940.00

NTPC- Simhadri Stage II 1000 46.01% 460.10 432.49

Kaiga Nuclear power Plant I&II 440 30.82% 135.61 121.37

Kaiga Nuclear power Plant III&IV 440 32.64% 143.62 128.54

Vallur Thermal Power Plant 1500 14.75% 221.25 206.87

Kalpakkam 500 26.40% 132.00 116.16

Tutricorn 1000 25.46% 254.60 234.23

Total Central Sector 12390

3958.91 3668.87

III Joint sector APGPCL-I 100 16.00% 16.00 15.60

APGPCL-I 172 24.88% 42.79 41.72

Total Joint Sector 272

58.79 57.32

IV IPPs GVK 216 100.00% 216.00 209.52

Spectrum 205 100.00% 205.00 198.85

Kondapalli 361.92 100.00% 361.92 351.06

BSES 220 100.00% 220.00 213.40

GVK Extension 220 100.00% 220.00 213.40

Vemagiri 370 100.00% 370.00 358.90

Gowthami 464 100.00% 464.00 450.08

Konaseema 444.08 100.00% 444.08 430.76

Total IPPS 2501

2501 2425.97

V Non Conventional Sources Total Non conventional sources 2817.33 100.00% 2817.33 2817.33

VI Mini Power Projects 1 Sri Vatsa power Projects Limited 17.2 100.00% 17.20 16.51

2 M/s LVS Power Limited 36.8 100.00% 36.80 35.33

Total MPPS 54

54 51.84

VII OTHERS Hinduja 1040

1040.00 1040.00

KSK Mahanadi 400

400.00 400.00

Singareni 1050

1050.00 1050.00

Thermal Power Tech 500

500.00 500.00

Total Others 2990

2990.00 2990.00

VIII Open Access Generators Total Open Access Generators 671.8

671.8 671.8

Grand Total 36196.59

25183.69 24132.41

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

36

2016-17

Source of Power Plant Capacity A.P.share A.P.share

A.P. share Excl. Aux.

Consm.

(MW) (%) (MW) (MW)

I APGENCO

VTPS I 420 100.00% 420.00 383.25

VTPS II 420 100.00% 420.00 383.25

VTPS III 420 100.00% 420.00 383.25

VTPS IV 500 100.00% 500.00 462.50

RTPP I 420 100.00% 420.00 382.20

RTPP-II 420 100.00% 420.00 382.20

RTPP-III 210 100.00% 210.00 191.63

KTPS A 240 100.00% 240.00 216.72

KTPS B 240 100.00% 240.00 216.72

KTPS C 240 100.00% 240.00 216.72

KTPS D 500 100.00% 500.00 455.00

KTPS VI 500 100.00% 500.00 462.50

RTS B 62.5 100.00% 62.50 56.88

Kakatiya TPS Stage 1 500 100.00% 500.00 462.50

Kakatiya TPS Stage II 600 100.00% 600.00 555.00

Damodaram Sanjeevaiah Thermal Power Plant-I 800 100.00% 800.00 748.00

Damodaram Sanjeevaiah Thermal Power Plant-II 800 100.00% 800.00 748.00

RTPP-IV 600 100.00% 600.00 546.00

TOTAL THERMAL 7892.5

7892.5 7252.31

MACHKUND PH AP Share 120 70.00% 84.00 83.16

TUNGBHADRA PH AP Share 72 80.00% 57.60 57.02

USL 240 100.00% 240.00 237.60

LSR 460 100.00% 460.00 455.40

DONKARAYI 25 100.00% 25.00 24.75

SSLM 770 100.00% 770.00 762.30

SSLM LCPH 900 100.00% 900.00 891.00

NSPH 815.6 100.00% 815.60 807.44

NSRCPH 90 100.00% 90.00 89.10

NSLCPH 60 100.00% 60.00 59.40

POCHAMPAD PH 27 100.00% 27.00 26.73

NIZAMSAGAR PH 10 100.00% 10.00 9.90

PABM 20 100.00% 20.00 19.80

SINGUR 15 100.00% 15.00 14.85

MINI HYDRO&OTHERS 12.16 100.00% 12.16 12.04

Priyadarshini JURALA HES 234 100.00% 234.00 231.66

POCHAMPAD Stg II 9 100.00% 9.00 8.91

Nagarjuna Sagar Tail Pond 50 100.00% 50.00 49.50

Lower Jurala Hydro Electric (New Project) 240 100.00% 240.00 237.60

Pulichintala 120 100.00% 120.00 118.80

TOTAL HYDRO 4289.76

4239.36 4196.97

Total A.P. Genco 12182.26

12131.86 11449.28

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

37

II Central Generating Stations (CGS) NTPC(SR) Ramagundam- U1-U6 2100 32.32% 678.72 629.78

NTPC (SR) Ramagundam -U7 500 33.92% 169.60 158.58

NLC TS-II Stage-I 630 18.33% 115.48 103.93

NLC TS-II Stage-II 840 24.33% 204.37 183.93

NPC-MAPS 440 9.90% 43.56 38.99

Talcher Stage 2 2000 20.00% 400.00 374.00

NTPC- Simhadri Stage I 1000 100.00% 1000.00 940.00

NTPC- Simhadri Stage II 1000 46.01% 460.10 432.49

Kaiga Nuclear power Plant I&II 440 30.82% 135.61 121.37

Kaiga Nuclear power Plant III&IV 440 32.64% 143.62 128.54

Vallur Thermal Power Plant 1500 14.75% 221.25 206.87

Kalpakkam 500 26.40% 132.00 116.16

Tutricorn 1000 25.46% 254.60 234.23

Kudigi I & II 4000 18.70% 748.00 703.12

Total Central Sector 16390

4706.91 4371.99

III Joint sector APGPCL-I 100 16.00% 16.00 15.60

APGPCL-I 172 24.88% 42.79 41.72

Total Joint Sector 272

58.79 57.32

IV IPPs GVK 216 100.00% 216.00 209.52

Spectrum 205 100.00% 205.00 198.85

Kondapalli 361.92 100.00% 361.92 351.06

BSES 220 100.00% 220.00 213.40

GVK Extension 220 100.00% 220.00 213.40

Vemagiri 370 100.00% 370.00 358.90

Gowthami 464 100.00% 464.00 450.08

Konaseema 444.08 100.00% 444.08 430.76

Total IPPS 2501

2501 2425.97

V Non Conventional Sources Total Non conventional sources 3534.33 100.00% 3534.33 3534.33

VI Mini Power Projects 1 Sri Vatsa power Projects Limited 17.2 100.00% 17.20 16.51

2 M/s LVS Power Limited 36.8 100.00% 36.80 35.33

Total MPPS 54

54 51.84

VII OTHERS Hinduja 1040

1040.00 1040.00

KSK Mahanadi 400

400.00 400.00

Singareni 1050

1050.00 1050.00

Thermal Power Tech 500

500.00 500.00

Total Others 2990

2990 2990

VIII Open Access Generators Total Open Access Generators 671.8

671.8 671.8

Grand Total 38595.39

26648.69 25552.53

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

38

2017-18

Source of Power Plant Capacity A.P.share A.P.share A.P. share Excl. Aux Consm.

(MW) (%) (MW) (MW)

I APGENCO

VTPS I 420 100.00% 420.00 383.25

VTPS II 420 100.00% 420.00 383.25

VTPS III 420 100.00% 420.00 383.25

VTPS IV 500 100.00% 500.00 462.50

RTPP I 420 100.00% 420.00 382.20

RTPP-II 420 100.00% 420.00 382.20

RTPP-III 210 100.00% 210.00 191.63

KTPS A 240 100.00% 240.00 216.72

KTPS B 240 100.00% 240.00 216.72

KTPS C 240 100.00% 240.00 216.72

KTPS D 500 100.00% 500.00 455.00

KTPS VI 500 100.00% 500.00 462.50

RTS B 62.5 100.00% 62.50 56.88

Kakatiya TPS Stage 1 500 100.00% 500.00 462.50

Kakatiya TPS Stage II 600 100.00% 600.00 555.00

Damodaram Sanjeevaiah Thermal Power Plant-I 800 100.00% 800.00 748.00

Damodaram Sanjeevaiah Thermal Power Plant-II 800 100.00% 800.00 748.00

RTTP-IV 600 100.00% 600.00 546.00

Ramagundam-C 660 100.00% 660.00 600.60

TOTAL THERMAL 8552.5 8552.50 7852.91

MACHKUND PH AP Share 120 70.00% 84.00 83.16

TUNGBHADRA PH AP Share 72 80.00% 57.60 57.02

USL 240 100.00% 240.00 237.60

LSR 460 100.00% 460.00 455.40

DONKARAYI 25 100.00% 25.00 24.75

SSLM 770 100.00% 770.00 762.30

SSLM LCPH 900 100.00% 900.00 891.00

NSPH 815.6 100.00% 815.60 807.44

NSRCPH 90 100.00% 90.00 89.10

NSLCPH 60 100.00% 60.00 59.40

POCHAMPAD PH 27 100.00% 27.00 26.73

NIZAMSAGAR PH 10 100.00% 10.00 9.90

PABM 20 100.00% 20.00 19.80

SINGUR 15 100.00% 15.00 14.85

MINI HYDRO&OTHERS 12.16 100.00% 12.16 12.04

Priyadarshini JURALA HES 234 100.00% 234.00 231.66

POCHAMPAD Stg II 9 100.00% 9.00 8.91

Nagarjuna Sagar Tail Pond 50 100.00% 50.00 49.50

Lower Jurala Hydro Electric (New Project) 240 100.00% 240.00 237.60

Pulichintala 120 100.00% 120.00 118.80

TOTAL HYDRO 4289.76 4239.36 4196.97

Total A.P. Genco 12842.26 12791.86 12049.88

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

39

II Central Generating Stations (CGS)

NTPC(SR) Ramagundam- U1-U6 2100 32.32% 678.72 629.78

NTPC (SR) Ramagundam -U7 500 33.92% 169.60 158.58

NLC TS-II Stage-I 630 18.33% 115.48 103.93

NLC TS-II Stage-II 840 24.33% 204.37 183.93

NPC-MAPS 440 9.90% 43.56 38.99

Talcher Stage 2 2000 20.00% 400.00 374.00

NTPC- Simhadri Stage I 1000 100.00% 1000.00 940.00

NTPC- Simhadri Stage II 1000 46.01% 460.10 432.49

Kaiga Nuclear power Plant I&II 440 30.82% 135.61 121.37

Kaiga Nuclear power Plant III&IV 440 32.64% 143.62 128.54

Vallur Thermal Power Plant 1500 14.75% 221.25 206.87

Kalpakkam 500 26.40% 132.00 116.16

Tutricorn 1000 25.46% 254.60 234.23

Kudigi I & II 4000 18.70% 748.00 703.12

Neyveli 1000 11.37% 113.70 104.60

Total Central Sector 17390 4820.61 4476.60

III Joint sector

APGPCL-I 100 16.00% 16.00 15.60

APGPCL-I 172 24.88% 42.79 41.72

Total Joint Sector 272 58.79 57.32

IV IPPs

GVK 216 100.00% 216.00 209.52

Spectrum 205 100.00% 205.00 198.85

Kondapalli 361.92 100.00% 361.92 351.06

BSES 220 100.00% 220.00 213.40

GVK Extension 220 100.00% 220.00 213.40

Vemagiri 370 100.00% 370.00 358.90

Gowthami 464 100.00% 464.00 450.08

Konaseema 444.08 100.00% 444.08 430.76

Total IPPS 2501 2501 2425.97

V Non Conventional Sources

Total Non conventional sources 3951.33 100.00% 3951.33 3951.33

VI Mini Power Projects

1 Sri Vatsa power Projects Limited 17.2 100.00% 17.20 16.51

2 M/s LVS Power Limited 36.8 100.00% 36.80 35.33

Total MPPS 54 54 51.84

VII OTHERS

Hinduja 1040 1040.00 1040.00

KSK Mahanadi 400 400.00 400.00

Singareni 1050 1050.00 1050.00

Thermal Power Tech 500 500.00 500.00

Total Others 2990 2990 2990

VIII Open Access Generators

Total Open Access Generators 671.8 671.8 671.8

Grand Total 40672.39 27839.39 26674.74

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

40

2018-19

Source of Power Plant Capacity A.P.share A.P.share A.P. share Excl.

Aux Consm.

(MW) (%) (MW) (MW)

I APGENCO

VTPS I 420 100.00% 420.00 383.25

VTPS II 420 100.00% 420.00 383.25

VTPS III 420 100.00% 420.00 383.25

VTPS IV 500 100.00% 500.00 462.50

RTPP I 420 100.00% 420.00 382.20

RTPP-II 420 100.00% 420.00 382.20

RTPP-III 210 100.00% 210.00 191.63

KTPS A 240 100.00% 240.00 216.72

KTPS B 240 100.00% 240.00 216.72

KTPS C 240 100.00% 240.00 216.72

KTPS D 500 100.00% 500.00 455.00

KTPS VI 500 100.00% 500.00 462.50

RTS B 62.5 100.00% 62.50 56.88

Kakatiya TPS Stage 1 500 100.00% 500.00 462.50

Kakatiya TPS Stage II 600 100.00% 600.00 555.00

Damodaram Sanjeevaiah Thermal Power Plant-I 800 100.00% 800.00 748.00

Damodaram Sanjeevaiah Thermal Power Plant-II 800 100.00% 800.00 748.00

RTTP-IV 600 100.00% 600.00 546.00

Ramagundam-C 660 100.00% 660.00 600.60

Kakatiya TPS Stage III 800 100.00% 800.00 740.00

TOTAL THERMAL 9352.5 9352.50 8592.91

MACHKUND PH AP Share 120 70.00% 84.00 83.16

TUNGBHADRA PH AP Share 72 80.00% 57.60 57.02

USL 240 100.00% 240.00 237.60

LSR 460 100.00% 460.00 455.40

DONKARAYI 25 100.00% 25.00 24.75

SSLM 770 100.00% 770.00 762.30

SSLM LCPH 900 100.00% 900.00 891.00

NSPH 815.6 100.00% 815.60 807.44

NSRCPH 90 100.00% 90.00 89.10

NSLCPH 60 100.00% 60.00 59.40

POCHAMPAD PH 27 100.00% 27.00 26.73

NIZAMSAGAR PH 10 100.00% 10.00 9.90

PABM 20 100.00% 20.00 19.80

SINGUR 15 100.00% 15.00 14.85

MINI HYDRO&OTHERS 12.16 100.00% 12.16 12.04

Priyadarshini JURALA HES 234 100.00% 234.00 231.66

POCHAMPAD Stg II 9 100.00% 9.00 8.91

Nagarjuna Sagar Tail Pond 50 100.00% 50.00 49.50

Lower Jurala Hydro Electric (New Project) 240 100.00% 240.00 237.60

Pulichintala 120 100.00% 120.00 118.80

TOTAL HYDRO 4289.76 4239.36 4196.97

Total A.P. Genco 13642.26 13591.86 12789.88

II Central Generating Stations (CGS)

NTPC(SR) Ramagundam- U1-U6 2100 32.32% 678.72 629.78

NTPC (SR) Ramagundam -U7 500 33.92% 169.60 158.58

Filing of ARR & FPT of SLDC business for the Third Control Period (FY2014-15 to FY2018 –19)

41

NLC TS-II Stage-I 630 18.33% 115.48 103.93

NLC TS-II Stage-II 840 24.33% 204.37 183.93

NPC-MAPS 440 9.90% 43.56 38.99

Talcher Stage 2 2000 20.00% 400.00 374.00

NTPC- Simhadri Stage I 1000 100.00% 1000.00 940.00

NTPC- Simhadri Stage II 1000 46.01% 460.10 432.49

Kaiga Nuclear power Plant I&II 440 30.82% 135.61 121.37

Kaiga Nuclear power Plant III&IV 440 32.64% 143.62 128.54

Vallur Thermal Power Plant 1500 14.75% 221.25 206.87

Kalpakkam 500 26.40% 132.00 116.16

Tutricorn 1000 25.46% 254.60 234.23

Kudigi I & II 4000 18.70% 748.00 703.12

Neyveli 1000 11.37% 113.70 104.60

Total Central Sector 17390 3958.91 4476.60

III Joint sector

APGPCL-I 100 16.00% 16.00 15.60

APGPCL-I 172 24.88% 42.79 41.72

Total Joint Sector 272 58.79 57.32

IV IPPs

GVK 216 100.00% 216.00 209.52

Spectrum 205 100.00% 205.00 198.85

Kondapalli 361.92 100.00% 361.92 351.06

BSES 220 100.00% 220.00 213.40

GVK Extension 220 100.00% 220.00 213.40

Vemagiri 370 100.00% 370.00 358.90

Gowthami 464 100.00% 464.00 450.08

Konaseema 444.08 100.00% 444.08 430.76

Total IPPS 2501 2501 2425.97

V Non Conventional Sources

Total Non conventional sources 4318.33 100.00% 4318.33 4318.33

VI Mini Power Projects

1 Sri Vatsa power Projects Limited 17.2 100.00% 17.20 16.51

2 M/s LVS Power Limited 36.8 100.00% 36.80 35.33

Total MPPS 54 54 51.84

VII OTHERS

Hinduja 1040 1040.00 1040.00

KSK Mahanadi 400 400.00 400.00

Singareni 1050 1050.00 1050.00

Thermal Power Tech 500 500.00 500.00

Total Others 2990 2990 2990

VIII Open Access Generators

Total Open Access Generators 671.8 671.8 671.8

Grand Total 41839.39 28144.69 27781.74