Beaufort County 1% Sales TaxBeaufort County 1% Sales TaxRoad Improvement ProgramRoad Improvement Program
Monday, September 22, 2008Monday, September 22, 2008
Presented by:Presented by:
2
Project LocationsProject Locations01 –
Bluffton Parkway
2a –
US 278 (William Hilton Pkwy.) Resurfacing
2b –
US 278 Intersection Realignment
2c –
US 278 (Fording Island Rd.) Widening
2d –
US 278 (Fording Island Rd.) Frontage Roads
2e –
US 278 Street Lighting at Traffic Signals
03 –
SC 170 (Okatie Hwy.) Widening
04 –
US 17 (Charleston Hwy.) Widening
05 –
US 21 (Boundary St.) Improvements
06 –
US 21 (Boundary St.) Parallel Road
07 –
SC 802 (Ribaut Rd.) Intersection Improvements
08 –
SC 802/US 21 (Lady’s Island Dr.) Widening
09 –
Northern Beaufort Bypass
10 –
SC 802 (Savannah Hwy.) Widening
01
2a
2b
2e03
04
5/6
0708
09
10
2c/d
Northern Beaufort County
Southern Beaufort County
3
Actual vs. Forecasted Sales Tax RevenueActual vs. Forecasted Sales Tax Revenue
Fiscal Year DateReceivedForecasted
ReceiptsActual Receipts
(Including Interest)
2008, 1st Quarter2008, 1st Quarter 9/30/20079/30/2007 $6,333,333 $7,838,127
2008, 2nd Quarter2008, 2nd Quarter 12/31/200712/31/2007 $6,333,333 $7,275,319
2008, 3rd Quarter2008, 3rd Quarter 3/31/20083/31/2008 $6,333,333 $7,549,882
2008, 4th Quarter2008, 4th Quarter 6/30/20086/30/2008 $6,333,333 $7,783,702
$25,333,332 $30,447,030
4
Project Cost SummaryProject Cost SummaryOriginal Budget
Expenditures
to DateCounty
Obligations
01 Bluffton Parkway
-
Phases 5A & 5B $60,000,000 $1,981,945 $9,479,067
2a US 278 (William Hilton Parkway) Resurfacing
-
Gum Tree Road to Sea Pines Circle $4,700,000 $0 $0
2b US 278 Intersection Realignment -
Squire Pope Road $2,400,000 $886,120 $739,041
2c US 278 (Fording Island Road) Widening
-
SC 170 (Okatie Highway) to Simmonsville Road $39,630,000 $0 $0
2d US 278 (Fording Island Road) Frontage Roads
-
Six Sections $13,100,000 $43,170 $154,784
2e US 278 Street Lighting at Traffic Signals
-
SC 170 (Okatie Highway) to Hilton Head Island $100,000 $0 $6,000
03 SC 170 (Okatie Hwy.) Widening
-
SC 46 (May River Rd.) to Tide Watch Dr. $26,000,000 $405,653 $1,037,402
04 US 17 (Charleston Highway) Widening
-
US 21 (Garden’s Corner) to Lightsey Plantation Road (Colleton County) $100,471,305 $24,816,909 $3,377,193
05 US 21 (Boundary Street) Improvements
-
Neil Road to Palmetto Street $13,250,000 $431,955 $330,545
06 US 21 ( Boundary Street) Parallel Road
-
SC 170 (Robert Small Parkway to Sycamore Street $8,750,000 $351,381 $286,119
07 SC 802 (Ribaut Road) Intersection Improvements
-
3 between Lenora Drive and Lady’s Island Drive $600,000 $96,120 $2,030
08 SC 802/US 21 (Lady’s Island Dr.) Widening
-
Ribaut Rd. to Sea Island Pkwy. $35,500,000 $1,764,039 $318,637
09 Northern Beaufort Bypass
-
US 21 (Grays Hill) to Brickyard Point Road $6,000,000 $1,801 $1,103,199
10 SC 802 (Savannah Highway) Widening
-
SC 170 to Parris Island Gateway $7,200,000 $738,326 $235,378
$317,701,305 $31,517,419 $17,069,394
5
1. Bluffton Parkway Phase 5A1. Bluffton Parkway Phase 5A
Location:Burnt Church Road toUS 278 –
Mackays CreekDescription:
3 miles, 4-lane dividedroad, 8’
multi-usepathways
Design Consultant:Florence & Hutcheson, Inc.
Project Status:•
Road design 75% complete•
Santee-Cooper continues design plans for relocating transmission line towers•
Bridge/ ramp design reduces wetland impacts from 3 acres of fill
to 0.5 acresProject Funding:
County Roadway Sales TaxCounty Road Impact Fee
Total Expenditures to Date
$50,000,000$10,000,000
$60,000,000$1,981,945
6
1. Bluffton Parkway Phase 5B1. Bluffton Parkway Phase 5B
Location:
Buckwalter Parkway to Buck Island RoadDescription:
2.5 miles, 4-lane divided road, 8’multi-use pathwaysDesign Consultant:
Florence & Hutcheson, Inc.Project Status:•
Working in conjunction with 5A•
Final Right-of-Way plans to be complete inOctober, 2008
7
2A.2A.
US 278 (William Hilton Pkwy.) ResurfacingUS 278 (William Hilton Pkwy.) Resurfacing
Location:Gumtree Road to Sea Pines Circle
Description:7.5 miles of resurfacing
Design Consultant:SCDOT
Project Status:•
Phase 1, Whooping Crane Way toShelter Cove Lane
•
Construction bids for Phase 1 tobe advertised in October, 2008
•
Phase 1 construction to begin inearly 2009
•
Phase 1 construction to be completed prior to the Heritage Golf Tournament by April, 2009•
Phase 2, Shelter Cove Lane to Park Lane, construction planned to
begin in 2009•
Phase 3 (Two parts) Gumtree Road to Whooping Crane Way and Park Lane to Sea Pines Circle, construction planned for 2010
Project Funding:County Roadway Sales Tax
TotalExpenditures to Date
$4,700,000
$4,700,000$0
8
2A. US 278 Resurfacing2A. US 278 Resurfacing
(Problem Areas)(Problem Areas)
Dillon Road and William Hilton Parkway Intersection
Mathews Drive and William Hilton Parkway Intersection
Gardner Drive and William Hilton Parkway Intersection
9
2B. US 278 Intersection Realignment2B. US 278 Intersection Realignment
Location:Squire Pope Road
Description:Intersection improvement
Design Consultant:Wilbur Smith Associates
Construction Firm:U.S. Group
Project Status:•
Substantially complete•
Final punch list underwayProject Funding:
County Roadway Sales Tax
TotalExpenditures to Date
$2,400,000
$2,400,000$886,120
10
2B.2B.
US 278 Intersection RealignmentUS 278 Intersection Realignment
(Construction Photos)(Construction Photos)
Crosswalk for Pedestrian Access Across Highway 278
Re-alignment of US 278 and Squire Pope Road Intersection Completed and Fully Operational
Sidewalk and Crosswalks Complete
11
2C. US 278 (Fording Island Road) Widening2C. US 278 (Fording Island Road) Widening
Location:SC 170 (Okatie Highway)to Simmonsville Road
Description:5.3 miles, 6-lane dividedhighway
Design Consultant:SCDOT
Project Status:•
Surveys are completed•
Preliminary plans to beready in Sept., 2008
•
Construction letting is planned for January, 2010•
IGA/ Participation Agreement between SCDOT and Beaufort County has been signedProject Funding:
County Roadway Sales TaxState and Federal FundingCounty Road Impact Fee
TotalExpenditures to Date
$17,600,000$15,530,000
$7,000,000
$40,130,000$0
12
2D. US 278 Frontage Roads2D. US 278 Frontage Roads
Description:Frontage roads at six locationson US 278:
1.
Buckwalter Commercial2.
St. Gregory3.
Rose Hill4.
Plantation Business Park5.
Tanger Outlet6.
The GatheringsDesign Consultant:
Florence & Hutcheson, Inc.Project Funding:
County Roadway Sales TaxTown and City FundingCounty Road Impact Fee
TotalExpenditures to Date
$3,600,000$3,500,000$6,000,000
$13,100,000$43,170
*pending from other sources
*
13
2D. 2D. US 278 Frontage Roads US 278 Frontage Roads ––
Buckwalter CommercialBuckwalter Commercial
Location:Buckwalter Commercial, west of Buckwalter Parkway
Description:Frontage road design
Project Status:•
Surveying began in late June•
August 1st
conceptual plans completed
14
2D. 2D. US 278 Frontage Roads US 278 Frontage Roads ––
St. GregorySt. Gregory
Location:St. Gregory by Berkeley Hall, north of US 278, east of Buckwalter Parkway
Description:Design and build frontage road from Berkeley Hall to the fire station
Project Status:•
Ward Edwards to complete survey and design•
Survey completed on August 24•
Road design is underway
15
2D. 2D. US 278 Frontage Roads US 278 Frontage Roads ––
Rose HillRose Hill
Location:Rose Hill, west of Buck Island Road
Description:Frontage road design and construction
Project Status:•
Surveying began in July, 2008•
August 22 conceptual plans completed•
Right-of-Way designs to be complete at the end of September, 2008
16
2D. 2D. US 278 Frontage Roads US 278 Frontage Roads ––
Plantation Business ParkPlantation Business Park
Location:Plantation Business Park, from WestburyPark Way to Simmonsville Road
Description:Frontage road design and construction
Project Status:•
Surveying completed July 18, 2008•
August 1st
preliminary plans and environmental screening completed•
Required permits application submitted to US Army Corps of Engineers and SCDHEC•
Right-of-Way plans to be completed at the end of September, 2008
17
2D. 2D. US 278 Frontage Roads US 278 Frontage Roads ––
Tanger 1 OutletTanger 1 Outlet
Location:Tanger Outlet, east ofBurnt Church Road
Description:Frontage road designand construction
Project Status:•
Survey complete•
Preliminary plans and environmental screenings completed August 1st
•
Right-of-Way plans to be completed at the end of September, 2008
18
2D. 2D. US 278 Frontage Roads US 278 Frontage Roads ––
The GatheringsThe Gatherings
Location:The Gatherings at Salt Marsh Lane
Description:Frontage road design and construction
Project Status:Negotiating with Andrews & Burgessfor survey and preliminary designs
19
2E.2E.
US 278 (Fording Island Rd.) Street LightingUS 278 (Fording Island Rd.) Street Lighting
Location:SC 170 (Okatie Highway) to HiltonHead Island
Description:Streetlights at signalizedintersections along US 278
1.
Buckwalter Parkway2.
Rose Hill Way3.
Buck Island Road4.
Simmonsville Road5.
Bluffton Road6.
Gateway Village Road (New Target)7.
Burnt Church Road8.
Sawmill Creek Road9.
Malphrus Road10.
Tanger 211.
Buckingham Plantation Drive
Project Status:•
Consultant Joe Scruggs completed lighting design June, 2008
Project Funding:County Roadway Sales Tax
Total
Expenditures to Date
$100,000
$100,000
$0
20
3. SC 170 (Okatie Highway) Widening3. SC 170 (Okatie Highway) Widening
Location:SC 46 (May River Road) toTide Watch Drive (RiversBend)
Description:6 miles, 4 and 6-lane divided roadway, context-sensitive design based on existing trees, pathways/paved shoulders
Design Consultant:Thomas & Hutton Engineering Company
Project Status:•
Public meeting held on May 27, 2008•
Traffic study submitted to SCDOT•
Noise study underway•
30% Design Plans submitted to SCDOTProject Funding:
County Roadway Sales TaxCounty Road Impact Fee
TotalExpenditures to Date
$6,000,000$20,000,000
$26,000,000$405,653
21
4. US 17 (Charleston Highway) Widening4. US 17 (Charleston Highway) Widening
Location:US 21 (Garden’s Corner) to Lightsey Plantation Road (Colleton County)
Description:6 miles, 4-lane divided roadway, multi-
use pathways
Design/Build Contractor:Phillips & Jordan, Inc.
Project Status:•
Bridge construction continuing•
Construction of multi-purpose path started
•
Public hearing planned for early October, 2008
Project Funding:County Roadway Sales TaxState and Federal FundingCounty Road Impact Fee
TotalExpenditures to Date
$5,000,000$93,471,305
$2,000,000
$100,471,305$24,816,909
22
4. US 17 (Charleston Highway) Widening4. US 17 (Charleston Highway) WideningCombahee River Bridge Construction Photos
Pre-Cast Concrete Pile Driven
New Deck Poured, Parapet Rebar Tied in Place
Overhang Forms Constructed
End Bent/ Wingwall Poured
23
5. US 21 (Boundary Street) Improvements5. US 21 (Boundary Street) Improvements
Location:Neil Road to PalmettoStreet
Description:2 miles, improving capacity,intersections, safety,streetscaping, addingroundabout, multi-usepathways, providingredevelopment opportunity
Design Consultant:Kimley-Horn andAssociates, Inc.
Project Status:•
Informational website developed and on-line•
Public meeting planned for October 2, 2008Project Funding:
County Roadway Sales TaxCounty Road Impact Fee
TotalExpenditures to Date
$9,500,000 $3,750,000
$13,250,000$431,955
24
6. New Parallel Road to Boundary Street6. New Parallel Road to Boundary Street
Location:Robert SmallsParkway (SC 170)to Sycamore Street
Description:Partial new constructionon north side of USRoute 21
Design Consultant:Kimley-Horn andAssociates, Inc.
Project Status:•
Informational websitedeveloped and on-line
•
Public meeting planned for October 2, 2008Project Funding:
County Roadway Sales TaxCounty Road Impact Fee
TotalExpenditures to Date
$4,200,000$4,550,000
$8,750,000$351,381
25
7.7.
SC 802 (Ribaut Road) Intersection ImprovementsSC 802 (Ribaut Road) Intersection Improvements
Location:West of Edinburgh Avenue to north of Old Shell Road
Description:Improvements at three intersections:
•
Vaigneur Road/ Edinburgh Road/ West Paris Avenue•
East Paris Avenue•
Old Shell Road
Design Consultant:Dennis Corporation
Project Status:•
SCDOT comments addressed and final encroachment permit submitted
•
Cost and quantity estimates compiled•
Utility companies notified•
Draft bid documents preparedProject Funding:
County Roadway Sales TaxCounty Road Impact Fee
TotalExpenditures to Date
$600,000$1,001,000
$1,601,000$96,120
26
8. US 21/SC 802 (Lady8. US 21/SC 802 (Lady’’s Island Dr.) Widenings Island Dr.) Widening
Location:SC 802 (Ribaut Road) to US 21 (SeaIsland Parkway)
Description:2.8 miles, 4-lane divided roadwaywith new bridge, sidewalks,pathways and bike lanes
Design Consultant:Collins Engineers, Inc.
Project Status:•
Right-of-Way acquisition approximately 80% complete
•
Submitted final roadway plans for SCDOT review
•
Advertise for road construction in 2008Project Funding:
County Roadway Sales Tax
TotalExpenditures to Date
$35,500,000
$35,500,000$1,764,039
27
8. US 21/SC 802 (Lady8. US 21/SC 802 (Lady’’s Island Dr.) Widenings Island Dr.) Widening
Proposed Renderings of the SC 802 Bridge
28
9. Northern Beaufort Bypass9. Northern Beaufort Bypass
Location:US 21 (Grays Hill) to BrickyardPoint Rd. (Tentative)
Description:Environmental study for bypass
Design Consultant:Thomas & Hutton Engineering Co.
Project Status:•
New traffic data will be applied to the traffic model to continue development of alignment alternatives
•
GIS data and property/ stakeholder list will be created to ensure public involvement
•
Environmental screening will begin this month as alignment alternatives are developed
Project Funding:County Roadway Sales Tax
TotalExpenditures to Date
$6,000,000
$6,000,000$1,801
29
10. SC 802 (Savannah Hwy) Widening10. SC 802 (Savannah Hwy) Widening
Location:SC 170 (Robert SmallsParkway) to Parris IslandGateway
Description:2.1 miles, 5-lane roadway,planted median, sidewalksand bike lanes
Design Consultant:Collins Engineers, Inc.
Project Status:•
Right-of-Way acquisitionApproximately 75% complete
•
Submitted final roadway plans for SCDOT review•
Advertise for road construction in 2008Project Funding:
County Roadway Sales Tax
TotalExpenditures to Date
$7,200,000
$7,200,000$738,326
30
Program Management UpdateProgram Management Update
•
All Projects in Design
•
Developed Cost Tracking System
•
Compiled Draft Master Program Schedule
•
Presentation to State Infrastructure Bank (SIB) on October 16, 2008
•
Generating Cash Flow Projections
•
Providing Monthly Project Status Reports to County Council
Slide Number 1Slide Number 2Actual vs. Forecasted Sales Tax RevenueProject Cost SummarySlide Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 11Slide Number 12Slide Number 13Slide Number 14Slide Number 15Slide Number 16Slide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24Slide Number 25Slide Number 26Slide Number 27Slide Number 28Slide Number 29Slide Number 30
/ColorImageDict > /JPEG2000ColorACSImageDict > /JPEG2000ColorImageDict > /AntiAliasGrayImages false /CropGrayImages true /GrayImageMinResolution 300 /GrayImageMinResolutionPolicy /OK /DownsampleGrayImages true /GrayImageDownsampleType /Bicubic /GrayImageResolution 96 /GrayImageDepth -1 /GrayImageMinDownsampleDepth 2 /GrayImageDownsampleThreshold 1.00000 /EncodeGrayImages true /GrayImageFilter /DCTEncode /AutoFilterGrayImages true /GrayImageAutoFilterStrategy /JPEG /GrayACSImageDict > /GrayImageDict > /JPEG2000GrayACSImageDict > /JPEG2000GrayImageDict > /AntiAliasMonoImages false /CropMonoImages true /MonoImageMinResolution 1200 /MonoImageMinResolutionPolicy /OK /DownsampleMonoImages true /MonoImageDownsampleType /Bicubic /MonoImageResolution 96 /MonoImageDepth -1 /MonoImageDownsampleThreshold 1.00000 /EncodeMonoImages true /MonoImageFilter /CCITTFaxEncode /MonoImageDict > /AllowPSXObjects false /CheckCompliance [ /None ] /PDFX1aCheck false /PDFX3Check false /PDFXCompliantPDFOnly false /PDFXNoTrimBoxError true /PDFXTrimBoxToMediaBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXSetBleedBoxToMediaBox true /PDFXBleedBoxToTrimBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXOutputIntentProfile () /PDFXOutputConditionIdentifier () /PDFXOutputCondition () /PDFXRegistryName () /PDFXTrapped /False
/CreateJDFFile false /Description > /Namespace [ (Adobe) (Common) (1.0) ] /OtherNamespaces [ > /FormElements false /GenerateStructure false /IncludeBookmarks false /IncludeHyperlinks false /IncludeInteractive false /IncludeLayers false /IncludeProfiles false /MultimediaHandling /UseObjectSettings /Namespace [ (Adobe) (CreativeSuite) (2.0) ] /PDFXOutputIntentProfileSelector /DocumentCMYK /PreserveEditing true /UntaggedCMYKHandling /LeaveUntagged /UntaggedRGBHandling /UseDocumentProfile /UseDocumentBleed false >> ]>> setdistillerparams> setpagedevice