Unit Rate for 2010-2011
Sr. No. DESCRIPTION OF ITEMS (in Rs.)
Completed Labour
25 Providing and laying in situ, cement concrete M-15 /1:2:4 Cu.M. 2,924.00 287.00of trap/granite/quartzite/gneiss metal for foundation and
bedding including bailing-out water manually, formwork,
compacting, covering newly laid concrete by gunny bag,
plastic or tarpaulin, curing etc. complete. (Wooden planks/
shuttering will not be allowed)
Spec.No. : Bd.E.1 Page No. 287 /IS 456:2000
26 Providing and laying in situ cement concreteM-10 /1:3:6 Cu.M. 2,181.00 327.00
of trap/granite/quartzite/gneiss metal for foundation and
bedding including bailing-out water manually formwork,
compacting, covering newly laid concrete by gunny bag,
plastic or tarpaulin, curing etc. complete. (Wooden planks/
shuttering will not be allowed)
Spec.No. : Bd.E.1 Page No. 287 /IS 456:2000
27 Providing and laying is situ, cement concrete in 1:4:8 Cu.M. 1,920.00 334.00
of trap/granite/quartzite/gneiss metal for foundation and
bedding including bailing-out water manually, formwork,
compacting, covering newly laid concrete by gunny bag,
plastic or tarpaulin, curing etc. complete. (Wooden planks/
shuttering will not be allowed)Spec.No. : Bd.E.1 Page No. 287
28 Providing and laying in situ cement concrete in 1:5:10 Cu.M. 1,685.00 327.00
of trap/granite/quartzite/gneiss metal for foundation and
bedding including bailing-out water manually, formwork,
compacting, covering newly laid concrete by gunny bag,
plastic or tarpaulin, curing etc. complete. (Wooden planks/
shuttering will not be allowed)
Spec.No. : Bd.E.1 Page No. 287
29 Providing and casting in si tu cement concrete Cu.M. 2,976.00 341.00
M15 /1:2:4 of trap/ granite/ quartzite/ gneiss metal for
steps including centering, form work, compacting, covering
newly laid concrete by gunny bag, plastic or tarpaulin,
roughening them if special finish is to be provided and
curing and finishing if required etc. complete. (The cement
mortar 1:3 plaster is considered for rendering uneven and
honey- combed surface only. Wooden planks/shuttering
will not be allowed)
Spec.No. : Bd.E.2 Page No. 288 /IS 456:2000
Bd E : PLAIN CEMENT CONCRETE 17
7/31/2019 BDE Plain+Cement+Concrete
2/3
Unit Rate for 2010-2011
Sr. No. DESCRIPTION OF ITEMS (in Rs.)
Completed Labour
30 Providing and casting in situ cement concrete M-20 of Cu.M. 3,643.00 341.00trap/ granite/ quartzite/ gneiss metal for steps including
centering, form work, compacting, covering newly laid
concrete by gunny bag, plastic or tarpaulin, roughening
them if special finish is to be provided and curing and
finishing if required etc. complete. (The cement mortar 1:3
plaster is considered for rendering uneven and honey-
combed surface only. Wooden planks/shuttering will not
be allowed)
Spec.No. : Bd.E.2 Page No. 288 /IS 456:2000
31 Providing and casting in situ cement concrete M-15/1:2:4
of trap/ granite/ quartzite/ gneiss metal, moulded or
chamfered as per drawing or as directed including
centering, form work, compacting, covering newly laid
concrete by gunny bag, plastic or tarpaulin, roughening
them if special finish is to be provided and curing and
finishing if required etc. complete. (The cement mortar 1:3
plaster is considered for rendering uneven and honey-
combed surface only. Wooden planks/shuttering will not
be allowed)
(i) for coping to plinth or parapet Cu.M. 3,290.00 327.00
32 (ii) for bed blocks Cu.M. 3,133.00 334.00
33 (iii) for plain or moulded sills, cornice, jambs, Cu.M. 3,400.00 375.00
architraves
Spec.No. : Bd.E.3 Page No. 288 /IS 456:2000
34 Providing and casting in situ cement concrete M-20 of
trap/ granite/ quartzite/ gneiss metal, moulded or
chamfered as per drawing or as directed including
centering, form work, compacting, covering newly laid
concrete by gunny bag, plastic or tarpaulin, roughening
them if special finish is to be provided and curing and
finishing if required etc. complete. (The cement mortar 1:3
plaster is considered for rendering uneven and
honeycombed surface only. Wooden planks/ shuttering
will not be allowed)
18 Bd E : PLAIN CEMENT CONCRETE
7/31/2019 BDE Plain+Cement+Concrete
3/3
Unit Rate for 2010-2011
Sr. No. DESCRIPTION OF ITEMS (in Rs.)
Completed Labour
i) for bed blocks, foundation blocks Cu.M. 3,629.00 314.00
35 ii) for plain or moulded sills, cornice, jambs, Cu.M. 4,021.00 355.00
architraves
Spec.No. : Bd.E.4 Page No. 289 /IS 456:2000
36 Providing and laying in situ cement concreteM-15/1:2:4 Cu.M. 2,742.00 287.00
grade by using cement 75% and fly Ash 25% of trap /
granite / quartzite / gneiss metal for foundation and bedding
including bailing out water manually, formwork,
compacting, covering newly laid concrete by gunny bag,
plastic or tarpulin, curing etc. complete. (Wooden planks/
shuttering will not be allowed)
37 Providing and laying in situ cement concreteM-10/1:3:6 Cu.M. 2,050.00 327.00
grade by using cement 75% and fly Ash 25% of trap /
granite / quartzite / gneiss metal for foundation and bedding
including bailing out water manually, formwork,
compacting, covering newly laid concrete by gunny bag,
plastic or tarpulin, curing etc. complete. (Wooden planks/
shuttering will not be allowed)
38 Providing and laying in situ cement concrete 1:4:8 Cu.M. 1,828.00 334.00
grade by using cement 75% and fly Ash 25% of trap /
granite / quartzite / gneiss metal for foundation and bedding
including bailing out water manually, formwork,
compacting, covering newly laid concrete by gunny bag,
plastic or tarpulin, curing etc. complete. (Wooden planks/
shuttering will not be allowed)
39 Providing and laying in situ cement concrete 1:5:10 Cu.M. 1,607.00 327.00
grade by using cement 75% and fly Ash 25% of trap /
granite / quartzite / gneiss metal for foundation and bedding
including bailing out water manually, formwork,
compacting, covering newly laid concrete by gunny bag,
plastic or tarpulin, curing etc. complete. (Wooden planks/
shuttering will not be allowed)