BCPS Original Race to the Top budget (DSW) June 15 2011

Embed Size (px)

Citation preview

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    1/33

    Baseline

    2009-10 2010-11

    1. Student Achievement % of All Students Proficient - Grade 4 Reading State 71.6% 74.6%

    (EOG; a proxy for NAEP Grade 4 Reading) LEA/Charter 77.8% 79.0%

    % of All Students Proficient - Grade 4 Math State 83.0% 85.0%

    (EOG; a proxy for NAEP Grade 4 Math) LEA/Charter 83.3% 89.0%

    % of All Students Proficient - Grade 8 Reading State 69.5% 72.5%

    (EOG; a proxy for NAEP Grade 8 Reading) LEA/Charter 77.8% 79.0%

    % of All Students Proficient - Grade 8 Math State 83.9% 86.9%

    (EOG; a proxy for NAEP Grade 8 Math) LEA/Charter 93.1% 93.5%

    2. Graduation Rates 4-Year Cohort Rate State 74.2% 76%

    LEA/Charter 80.5% 81.5%

    3. College Readiness Average SAT Composite (% students taking) State 1,008 (63%) 1,009 (65%) 1

    LEA/Charter 1005(40%) 1009 (65%)

    % of AP exams taken on which students scored 3or above (% of students taking AP exams) State 57.6% (10.4%) 60% (11%)

    LEA/Charter 50.1% 51.0%

    *Note that in the 2012-13 school year,

    new assessments aligned to new

    standards (including the Common

    Core) will be implemented in NC which

    may require the adjustment of these

    targets to ensure ambitiousness and

    feasiblility.

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW)

    State & Local Priority Goals

    State RttT Goal

    120 Burke County

    Measure

    NC RttT LEA/Ch t D t il d S f W k P i it G l P 1 f 33

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    2/33

    4. College Enrollment

    % of high school graduates who enroll in post-secondary education programs State 65.6%Note:LEAs/Charters do not need to fill this in for Nov. 8, 2010. Further

    information will be provided to LEAs/Charters in the future. LEA/Charter N/A

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    3/33

    2013-14

    83.6%*

    85.0%

    91.0%*

    92.0%

    81.5%*

    85.0%

    95.9%*

    95.0%

    85%

    86.0%

    1,025 (72%)

    1025(72%

    66% (17%)

    52.5%

    NC RttT: LEA/Charter Detailed Scope of Work - Priority Goals Page 3 of 33

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    4/33

    72%

    N/A

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    5/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Required Activ

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    (A)(2)Cloud

    Obj. 1.1,2.1, 3.1

    1,584,042$

    Plan/Timeline for Implementation

    Objective (A)(2) 1.1: Incorporate the state

    infrastructure blueprint into technology

    plans (see NC Cloud Attachment 2).

    Objective (A)(2) 2.1: Implement the

    infrastructure blueprint.

    Objective (A)(2) 3.1: Provide and support

    student, teacher, administrator access to

    Learner Management System, Learning

    Object Repository, and web collaboration

    tools.

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW)

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    Performa

    Measu

    (Targe

    Objective (A)(2) EVAL 1.1: Participate in the

    evaluation of the RttT initiatives and use the

    resulting evaluation data and conclusions to

    improve effectiveness.

    (A)(2)Eval

    Obj. 1.1

    ***See State Detailed Scope of Work***

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    6/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Requ

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    1DSSF Plan isin progress

    Professional development will be providedfor teachers, instructional coaches,instructional technology specialists andother staff for the new standard course ofstudy and the adoption of the Common Coreand Essential Standards. Teachers andstaff will attend professional developmentoffered by DPI and local professional

    development. Stipends, subsititute costsand travel costs will support these activitiesover a 4-year period.

    Teachers,Instructional

    Coaches,

    InstructionalTechnologySpecialists

    Objective (B)(3) 1.1: Ensure teachers and

    staff understand the new Standard Course

    of Study, including the Common Core and

    Essential Standards, and related

    assessments.

    (B)(3)Obj. 1.1

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    7/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Required A

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    Perfo

    Me

    (Ta

    (C)(3)Obj. 1.1

    (C)(3)Obj. 1.2

    Objective (C)(3) 1.1: Create a transition plan

    for schools and LEAs to begin using the

    online IIS for the 2012-2013 school year.

    Objective (C)(3) 1.2: Utilize LEA/Charter and

    school technology funds to enhance school

    and LEA/Charter technology infrastructure

    to facilitate online real-time assessments at

    each school.

    Objective (C)(2) 1.1: Complete a unified

    strategic plan for the LEA/Charter that

    utilizes data to determine priority goals and

    activities, and set targets for performance.

    (C)(2)Obj. 1.1

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    8/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Required A

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    Perfo

    Me

    (Ta

    (C)(3)Obj. 1.3

    Objective (D)(1) 1.2: Use alternative routes

    Objective (C)(3) 1.4: Work as partners with

    DPI staff to incorporate the IIS into the daily

    operational aspects of school.

    Objective (C)(3) 1.3: Designate current staff

    to help educators utilize EVAAS and

    assessment data for instructional and

    program decision-making.

    Objective (D)(1) 1.1: Recruit individuals toteach in high-need schools in rural and

    urban areas utilizing school/university

    partnerships.

    (C)(3)Obj. 1.4

    (D)(1)Obj. 1.1

    (D)(1)

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    9/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Required A

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    Perfo

    Me

    (Ta

    (D)(2)Obj. 1.1

    Objective (D)(1) 2.1: Address areas of

    teacher shortage.

    (D)(1)Obj. 2.1

    Objective (D)(2) 2.1: Integrate student

    growth data into teacher and principal(D)(2)

    Objective (D)(2) 1.2: Provide evaluation

    results to the State by submitting summary

    ratings.

    (D)(2)Obj. 1.2

    Objective (D)(2) 1.1: Utilize the evaluationtool and process as a primary factor in

    teacher and principal development plans

    and decisions related to promotion,

    retention and removal.

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    10/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Required A

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters wil l")

    Aligned with

    Key Personnel

    Perfo

    Me

    (Ta

    Objective (D)(3) 2.2: Forecast hiring needsand use succession planning to identify

    candidates for school leadership positions.

    Objective D(4) 2.1: Provide feedback for

    preparation certification and alternative(D)(4)

    (D)(3)Obj. 2.2

    Objective (D)(3) 1.1: Identify and select

    highly-qualified candidates to participate in

    regional leadership academies.

    (D)(3)Obj. 1.1

    Objective (D)(3) 2.1: Recruit and increase

    the concentration of highly-effective

    teachers and leaders in high need schools.

    (D)(3)Obj. 2.1

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    11/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Required Ac

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    Perfor

    Mea

    (Ta

    Objective D(4) 2.2 : Establish

    communication process with regional

    preparation programs to strengthen

    programs and increase success of first-year

    educators.

    (D)(4)Obj. 2.2

    (D)(4)Obj. 2.3

    Objective D(4).2.3: Establish or extend

    existing partnerships with North Carolina

    colleges and universities.

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    12/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Requi

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (D

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    1DSSF Plan isin progress

    1. Professional development on use oftechnology, end of course courses, studentgrowth. A train the trainer model will be

    used as appropriate. Stipends, substitutecosts and funds for travel costs will supportthese activities over a 4-year period.

    Teachers,Instructional

    Coaches,

    InstructionalTechnologySpecialists.

    dN

    loo

    c

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    13/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Requi

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (D

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    1DSSF Plan isin progress

    2. All principals, assistant principals, centraloffice administrators, instructional coaches,instructional technology specialists will usea laptop for online assessments,professional development, and other RttTefforts. Laptops will be purchased for thesestaff.

    Principals,Assistant

    Principals. CentralOffice

    Administrators,InstructionalCoaches,

    InstructionalTechnologySpecialists

    B

    p

    su

    (D)(5)Obj. 1.1

    Objective D(5) 1.1: Provide access to

    effective, high-quality, job-embedded, data-

    informed professional development and

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    14/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Requir

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (D

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    P

    1

    DSSF Plan is

    in progress

    3. Professional development on data

    literacy will be provided. Stipends,

    substitute costs and funds for travel costswill support these activities over a 4-year

    period.

    Data

    Managers/DataCoaches,

    Teachers

    asta

    at

    s

    as

    a

    dis

    b

    d

    da

    aligned to the Race to the Top Initiatives.

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    15/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Require

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DS

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    P

    1

    DSSF Plan is

    in progress

    4. Professional develoment for DataManagers, Teachers, Instructional Coaches,

    Instructional Technology Facilitators in datause. Training will occur over a 4 year period

    ($50,000 per year).

    Data Managers,Teachers,

    InstructionalCoaches,

    InstructionalTechnology

    Facilitators

    Da

    I

    I

    TFac

    traus

    Objective (E)(2) 1.1: Implement one of the

    U.S. Department of Education's four models

    in each of their lowest-achieving schools:

    turnaround restart closure or

    (E)(2)Obj. 1.1

    Objective D(5) 1.2: Measure, evaluate and

    improve professional development andsupport.

    (D)(5)

    Obj. 1.2

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    16/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Required Ac

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW)

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    Perfor

    Mea

    (Tar

    ,

    implementation map.

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    17/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Required A

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    Perfo

    Mea

    (Ta

    Objective (E)(2) 1.4: Only if a school has

    made less than a 5-point increase on its

    performance composite after two years, the

    district will relinquish to the State Board

    oversight and control of curriculum andinstruction, personnel, and budget and final

    decisions regarding school management and

    governance and/or districts recognize that

    the State Board will require more aggressive

    intervention in lowest-achieving districts

    and schools if the district administration

    does not provide sufficient leadership for

    (E)(2)Obj. 1.4

    Objective (E)(2) 1.3: Only if a principal has

    led a lowest-achieving school for two years

    before Transformation division intervention

    without adequate progress in improving

    student achievement, the Districts will

    replace leadership, involving the

    Transformation division in the process.

    (E)(2)

    Obj. 1.3

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    18/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Required A

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    Perfo

    Me

    (Ta

    (E)(2)Obj. 2.3

    Objective (E)(2) 2.3: Only if a principal has

    led a lowest-achieving school for two yearsbefore Transformation division intervention

    without adequate progress in improving

    student achievement, the Districts will

    replace leadership, involving the

    Transformation division in the process.

    (E)(2)Obj. 2.1

    (E)(2)Obj. 2.2

    Objective (E)(2) 2.1: Implement one of the

    U.S. Department of Education's four models

    in each of their lowest-achieving schools:

    turnaround, restart, closure, or

    transformation.

    Objective (E)(2) 2.2: Engage in NC

    Comprehensive Needs Assessment,

    Leadership and Instructional Coaching,

    Professional Development, change plan and

    implementation map.

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    19/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Required A

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    Perfo

    Me

    (Ta

    Objective (E)(2) 2.4: Only if a school has

    made less than a 5-point increase on its

    performance composite after two years, the

    district will relinquish to the State Boardoversight and control of curriculum and

    instruction, personnel, and budget and final

    decisions regarding school management and

    governance and/or districts recognize that

    the State Board will require more aggressive

    intervention in lowest-achieving districts

    and schools if the district administration

    does not provide sufficient leadership for

    and cooperation with the turnaround

    process.

    (E)(2)Obj. 2.4

    Objective (E)(2) 3.1: Accept placement of a

    district transformation coach and other

    coaches as mutually identified.

    (E)(3)Obj. 3.1

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    20/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Required Ac

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW)

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    Perfor

    Mea

    (Tar

    map.

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    21/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Required A

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    Perfo

    Mea

    (Ta

    (E)(3)Obj. 3.3

    Objective (E)(2) 3.4: Only if a school has

    made less than a 5-point increase on its

    performance composite after two years:

    The district will relinquish to the State Board

    oversight and control of curriculum and

    instruction, personnel, and budget and final

    decisions regarding school management and

    governance

    and/or

    (E)(3)Obj. 3.4

    Objective (E)(2) 3.3: Only if a principal has

    led a lowest-achieving school for two years

    before Transformation division intervention

    without adequate progress in improving

    student achievement:

    Districts agree to replace school leadership,

    involving the Transformation division in the

    process.

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    22/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Required Ac

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    Perfo

    Mea

    (Ta

    sufficient leadership for and cooperation

    with the turnaround process.

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    23/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Req

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    1DSSF Plan isin progress

    1. Offer large set of professionaldevelopment activities in STEM, AP andhybrid courses for teachers, instructionalcoaches, instructional technologyspecialists. Stipends, substitute costs,travel expenses will support these activitiesover a 4-year period.

    Teachers,Instructional

    Coaches,InstructionalTechnologySpecialists.

    1DSSF Plan isin progress

    2. Professional development provided totrain teachers to be on-line, hybrid teachers.Professional development provided by NCLEARN. Stipends, substitute costs, travelexpenses will support these activities over a4-year period.

    Teachers,Instructional

    Coaches,InstructionalTechnologySpecialists.

    Objective (P)(2) 1.1: Provide curriculum

    support in new standards and use available

    data to place students in the most

    appropriate and rigorous science and math

    courses.

    (P)(2)Obj. 1.1

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    24/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted for Required A

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    1,584,042$

    Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW

    Required Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

    Required RttT Activity

    ("Participating LEAs/Charters will")

    Aligned with

    Key Personnel

    Perfo

    Mea

    (Ta

    Total Budget for Required RttT A

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    25/33

    Total RttT Funding Allotted (over four years): Total RttT Funding Budgeted

    LEA/Charter

    Goal

    DSSF Plan

    Strategy

    C(3) Obj.1.2

    Utilize RttT funds for technology infrastructureto facilitate and support online assessments 2

    DSSF Plan isin progress

    Technology infrastructure for wirelesscapability for online assessments with priorityon (1) middle schools, (2) two high schoolswith very limited capability.

    Chief TechnOfficer

    TechnoloEnginee

    C(3) Obj.

    1.3

    Hire/repurpose staff to serve as instructionalfacilitators or embedded instructional supportat each school 1

    DSSF Plan isin progress

    Hire/repurpose Assistant Director of Student

    Information, Data Management, and OnlineLearning, and Instructional TechnologyFacilitator to provide embedded support atschools. Positions will be paid over a 4 yearperiod.

    Director SecondaEducation

    Chief TechnOfficer

    Key Perso

    1,584,042$

    Aligned with...Optional RttT Activity

    ("Participating LEAs/Charters may")Plan/Timeline for Implementation

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of W

    Optional Activities

    120 Burke County

    NC RttT

    Initiative

    (Section)

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    26/33

    C(3) Obj.1.3

    Hire/repurpose staff to serve as instructionalfacilitators or embedded instructional support

    at each school to assist with using data fromformative and benchmark assessments,

    implementation of the ISS and ongoingsupport of teachers using IIS 1

    DSSF Plan isin progress

    Purchase SuccessMaker educational

    software for middle school level todifferentiate and personalize reading and

    math instruction and provide information forformative assessments.

    Inst

    FacilTe

    Total Budget for Op

    Total Budg

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    27/33

    2011-12 N

    2010-11 R

    R/N?Fiscal

    Year

    NC RttT LEA/Charter Detailed Scope of Work - Optional Activities Page 27 of 33

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    28/33

    2010-11 N

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    29/33

    Total RttT Funding Allotted (over four years): 1,584,042$

    2010-11 2011-12 2012-13 2013-14 Totals

    Total Budget for Required RttT Activities $ 574,351 $ 69,000 $ - $ - $ 643,351

    Total Budget for Optional RttT Activities $ 701,750 238,941$ -$ -$ $ 940,691

    Total Budget for RttT Activities 1,276,101$ 307,941$ -$ -$ $ 1,584,042

    Total RttT Funds Budgeted $ 1,584,042 OK

    Total Non-RttT Funds Budgeted $ -

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW)

    Budget Summary

    120 Burke County

    NC RttT LEA/Charter Detailed Scope of Work - Budget Summary Page 29 of 33

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    30/33

    NC RttT LEA/Charter Detailed Scope of Work - Budget Summary Page 30 of 33

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    31/33

    NC RttT Initiative (Section) Contact Contact Name Phone Number Email Address

    Primary Contact for Local Implementation Team Wendy Jodry 828-432-2892 [email protected]

    Technology Infrastructure & Resources (A) Angie Blalock 828-439-2900 [email protected]

    Standards & Assessments (B) David McGee 828-437-4482 [email protected]

    Data Systems to Support Instruction (C) Debbie Kincaid 828-438-2930 [email protected]

    Great Teachers & Leaders (D) Kim Rudisill 828-430-4100 [email protected]

    Turning Around the Lowest-Achieving Schools (E) N/A N/A N/A

    STEM (Priority 2) Rexanna Lowman 828-439-4337 [email protected]

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW)

    LEA/Charter Implementation Team Contacts

    120 Burke County

    NC RttT LEA/Charter Detailed Scope of Work - Implementation Team Page 31 of 33

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    32/33

    Planning & Advisory Team

    MembersTitle/Organization Phone Number Email Address

    Sandra Hatley Local Teacher Association Leader 828-437-5906 [email protected]

    Dr. Art Stellar Superintendent, BCPS 828-439-4310 [email protected]

    David McGee Director of Testing, BCPS 828-437-4482 [email protected]

    Dr. Angie Blalock Chief Technology Officer, BCPS 828-438-2900 [email protected]

    Rexanna Lowman Director of Secondary Education, BCPS 828-439-4337 [email protected]

    Kim Rudisill Director of Elementary Education, BCPS 828-430-4100 [email protected]

    Blair Propst Executive Director of Human Resources 828-439-4302 [email protected]

    Debbie Kincaid Assistant Director of Student Information 828-438-2930 [email protected]

    Wendy Jodry Grants Program Manager 828-432-2892 [email protected]

    120 Burke County

    NC Race to the Top (RttT) LEA/Charter Detailed Scope of Work (DSW)

    LEA/Charter Planning & Advisory Team Contacts

    NC RttT LEA/Charter Detailed Scope of Work - Planning Advisory Team Page 32 of 33

  • 8/3/2019 BCPS Original Race to the Top budget (DSW) June 15 2011

    33/33

    Signature

    NC RttT LEA/Charter Detailed Scope of Work - Planning Advisory Team Page 33 of 33