48
L&T- Power Basics of Engineering Basics of Engineering Electrical Electrical

basics of engineering Electrical.ppt

Embed Size (px)

Citation preview

Page 1: basics of engineering Electrical.ppt

L&T- Power

Basics of Engineering Basics of Engineering ElectricalElectrical

Page 2: basics of engineering Electrical.ppt

L&T- Power

Electrical System for a Power Station can be broadly classified as:

Main Power SystemThe Main power system deals with Generation of Power and stepping it up to a Extra High Voltage (EHV) level. It also deals with Unit start-up power.

Plant Auxiliary Distribution SystemThe Auxiliary distribution system deals with supply and distribution of power to various auxiliaries (e.g. boiler feed pump, Cooling water pumps etc) within the station boundary, necessary for keeping the Unit up and running.

Power Evacuation SystemPower evacuation system deals with receipt of power from Station at EHV level, Export/Import of Power to the Grid and Deriving Unit start-up power.

Electrical System for Power Plants

Page 3: basics of engineering Electrical.ppt

L&T- Power Typical Main Power System for Large Thermal Power Plant

Unit AuxiliariesStation Auxiliaries

Main Power System

Page 4: basics of engineering Electrical.ppt

L&T- Power Overview – Main Power System

Main Power System deals with Generation of Power and stepping-up this generated power to the evacuation voltage

For a 800MW Unit, power generated at 24kV and transmitted to the Generator Transformer (GT) thru Isolated Phase Bus Duct (IPBD)

Main route of IPBD is provided with taps to feed the plant unit auxiliaries thru Unit transformers (UTs)

Main Power system also deals with Unit start-up

For this mainly two schemes exists, Station transformer scheme and Generator Circuit Breaker (GCB) Scheme.

Page 5: basics of engineering Electrical.ppt

L&T- Power

Start-up power derived from Grid thru Station transformer.

Unit is started by supplying power to the necessary Turbine & Boiler auxiliaries thru Station to Unit interconnector

After start-up, unit is synchronized to the grid at EHV breaker in switchyard. Synchronization achieved thru automatic synchronizing equipment – normally a part of turbine control equipment

After synchronization with grid, unit load are transferred to the UT by paralleling via 11 kV interconnector

Unit supplies power to unit auxiliaries through UTs. Power is evacuated through GT.

HV side of ST – 132 kV, 220 kV, 400 kV LV side of ST – 11 kV On load Tap Changer is required

Station Transformer (ST) scheme

Page 6: basics of engineering Electrical.ppt

L&T- Power Station Transformer scheme

Page 7: basics of engineering Electrical.ppt

L&T- Power Generator Circuit Breaker (GCB) scheme

Page 8: basics of engineering Electrical.ppt

L&T- Power

• A switching device (GCB) introduced between generator and GT

• Start-up power is derived from Grid by back charging GT and UT and keeping GCB open

• Unit is started by supplying power to the necessary Turbine & Boiler auxiliaries

• After start-up, generator is synchronized with the grid thru GCB

• Once synchronized, unit supplies power to auxiliaries through UTs. Power is evacuated through GT.

HV side of UT – 24 kV LV side of ST – 11 kV

This scheme is not widely used for large thermal power plants, However this scheme is very popular for Combined cycle plants

Generator Circuit Breaker (GCB) scheme

Page 9: basics of engineering Electrical.ppt

L&T- Power

Major Constituents of Main Power System are:

• Generator with Excitation System

• Station Transformer

• Generator Circuit Breaker (GCB) (As applicable)

• Isolated Phase Bus Duct

• Generator Transformer

Main Power System

Page 10: basics of engineering Electrical.ppt

L&T- Power

Mainly comprises of:

• Generator with Excitation System

• Generator Control Protection & Monitoring System

• Neutral Earthing Equipment

• Above are in scope of Original Equipment Manufacturer (OEM) for Turbine Generator Package

• Generator stator and rotor - some of the heaviest equipment to be transported and handled at site, with stator weighing approx. 370 MT and rotor 80 MT for 800MW generator

• Major domestic suppliers - BHEL• Major international suppliers - MELCO, GE, ALSTOM, SIEMENS, HITACHI,

ABB, Toshiba• Major Chinese suppliers are Don fang Electric (DEC), Sanghai Electric, Harbin

Generator

Page 11: basics of engineering Electrical.ppt

L&T- Power

ROTOR

COIL END SUPPORT STRUCTUREWITH RESIN CONE

STATOR COIL

TURBINE SIDE

EXCITER SIDE

GAS COOLER

LARGE DIAMETER ROTOR

BLOWER

H2 GAS

STATOR CORE

BEARINGBEARING

COOLING SYSTEMSTATOR COIL: WATER COOLEDROTOR COIL: HYDROGEN INNER COOLED

BUSHING

Major Parts of a Large Water Cooled Generator

Page 12: basics of engineering Electrical.ppt

L&T- Power Picture of a 990MVA 3000rpm MHI Generator

Static Excitation System

Turbine

Generator

Page 13: basics of engineering Electrical.ppt

L&T- Power Picture of a 1,310MVA 1,800rpm MHI Generator

Brushless type Excitation system

Page 14: basics of engineering Electrical.ppt

L&T- Power Picture of a 1,600MVA 1,800rpm MHI Generator

Page 15: basics of engineering Electrical.ppt

L&T- Power Generator Excitation System

Function:

1. SUPPLY AND CONTROL THE DIRECT CURRENT FOR THE FIELD WINDING (FIELD CURRENT) OF THE GENERATOR.

2. CONTROL THE VOLTAGE AND REACTIVE VOLT- AMPERE OF THE MAIN GENERATOR BY CONTROLLING ITS EXCITATION.

Types of Excitation System:

1. STATIC EXCITATION SYSTEM

POWER ELECTRONICS BASEDMORE ADVANCED TECHNOLOGY

2. BRUSHLESS EXCITATION SYSTEM

ROTATING ELECTRICAL MACHINECONVENTIONAL TECHNOLOGY

THYRISTOR EXCITER

BRUSHLESS EXCITER

Page 16: basics of engineering Electrical.ppt

L&T- Power

MAJOR COMPONENTS:

- EXCITER & AVR CUBICLES

- EXCITER TRANSFORMER

- AC BUS DUCT

- DC BUS DUCT

- SLIP RING & BRUSH GEAR

MAJOR COMPONENTS:

- EXCITER & AVR CUBICLES

- EXCITER TRANSFORMER

- AC BUS DUCT

- DC BUS DUCT

- SLIP RING & BRUSH GEAR

EX PMGG

CT

PT

AVR

Field Breaker

BRUSHLESS EXCITATION SYSTEM

BRUSHLESS EXCITATION SYSTEM

STATIC (THYRISTOR) EXCITATION SYSTEM

STATIC (THYRISTOR) EXCITATION SYSTEM

AVR

Exciter Transformer

PT

CT

G

Thyristor Rectifier

Field Breaker

AC Bus Duct

DC BusDuct

Slip Ring & Brush Gear

MAJOR COMPONENTS:

- BRUSHLESS EXCITER

- AVR CUBICLE

MAJOR COMPONENTS:

- BRUSHLESS EXCITER

- AVR CUBICLE

System Configuration of Excitation System

Page 17: basics of engineering Electrical.ppt

L&T- Power

• Special type of breaker, capable of withstanding the short circuit level at Generator terminal

• Requires breaking capability of a very large amount of short circuit current, being very close to Generator

• Enables power to unit auxiliaries by back charging of Generator Transformer (as explained earlier)

Suppliers - ABB, Areva and Hitachi

ABB HEC-7 & HEC-8 more suitable for large thermal power units

Generator Circuit Breaker (GCB)

Page 18: basics of engineering Electrical.ppt

L&T- Power

GeneratorTransformer sideGenerator

side

Generator Circuit Breaker

Page 19: basics of engineering Electrical.ppt

L&T- Power

• Also known as Isolated Phase type Bus Duct.

• Main run connects Generator to GCB and GCB to Generator Transformer.

• Tap-off run connects main run to Unit Transformers, Excitation transformer etc

• For a 800MW unit, continuous rating of the Main run is in the range of 25,000 A and short-circuit rating of around 165 kA

• Major domestic suppliers - C&S, Powergear• Major International suppliers – ALFA Standard, EGE, Simelectro

from Europe, Delta Unibus from USA, Hyosung from Korea• Major Chinese suppliers - DAQO, Beijing Power Electric

Isolated Phase Bus Duct

Page 20: basics of engineering Electrical.ppt

L&T- Power Typical IPBD Layout and connection scheme, and internal details

Tubular (hollow) conductor

Enclosure

Page 21: basics of engineering Electrical.ppt

L&T- Power GE 7FA Gas Turbines – Part of a 500 MW Combined Cycle Power Plant

IPBD

GCB

Generator Transformer

Page 22: basics of engineering Electrical.ppt

L&T- Power

• Step up the generation voltage to evacuation voltage

• Available in three phase bank (Single unit) up to 315 MVA rating

• Single Phase banks (One transformer per phase) employed in large thermal power plants for

a) 3-Phase transformer impose transport weight and height limitations beyond 315 MVAb) Failure in one bank does not affect others

• Typical rating: 3 x 333 MVA for a 800 MW Unit and 3 x 260 MVA for a 660 MW Unit

• One of the heaviest and largest equipment to be transported to site

• Major domestic suppliers are AREVA, ABB, CGL, BHEL• Major International suppliers are GE Prolec, Fortune Electric, SPECO

(Shandong Power Equipment Company)

Generator Transformer

Page 23: basics of engineering Electrical.ppt

L&T- Power

FirewallTo restrict fire to a limited area

IPBDTransformerCooler banks

View of a 290 MVA Generator Transformer

Connection with the overhead lines

Page 24: basics of engineering Electrical.ppt

L&T- Power

Plant Auxiliary Distribution is broadly divided in to following sub-systems :

• Normal AC System

• Emergency AC System

• DC System

• UPS System

Plant Auxiliary Distribution System

Page 25: basics of engineering Electrical.ppt

L&T- Power Typical Unit & Station System for a 660MW Generator

Motors <160 kW

1500kW > Motors > 160 kW

Motors > 1500 kW

BFP largest motor, rating around 19 MW typically for a 800 MW Unit

Page 26: basics of engineering Electrical.ppt

L&T- Power

• Medium Voltage levels generally used are - 3.3 kV, 6.6 kV and 11 kV

• MV switchgears comprises of SF6/VCB breakers & protective relays.

• MV switchgears are used to feed HT motors and auxiliary / service transformers.

• Major Manufacturers – ABB, Siemens, L&T has entered in this field with a joint venture with TAMCO, Malayasia.

• Low Voltage levels generally used are - 415 V, 240 V and 110 V

• LV switchgears comprises of Air Circuit Breakers & protective relays.

• LV switchgears are used to feed LV loads, MCC and DB.

• L&T make switchgears are used in L&T projects.

Medium Voltage (MV) and Low Voltage (LV) Switchgear

Page 27: basics of engineering Electrical.ppt

L&T- Power Diesel Generator backed Emergency Power Supply

• Diesel Generator provide start-up or shut-down power

• In the event of total power failure, DG set provides power required for safe shutdown of the plant like AC lube oil pumps, turning gear, cooling water pumps/fans (as required), back-up to UPS and DC system

• DG sets also provide start-up power for combined cycle power plants (CCPP).

• Rating in the range of 1500 KVA for a 250 to 500 MW CCPP. Normally provided at LV (415V) level.

• For large thermal power plants, DG not adequate for huge start-up power supply requirements. Hence Gas turbines may be provided.

Page 28: basics of engineering Electrical.ppt

L&T- Power Diesel Generator (DG) room pictures

Auto Mains Failure (AMF) Panel

DG Set inside acoustic enclosure

Page 29: basics of engineering Electrical.ppt

L&T- Power

DC system

Supply power DC Emergency Oil Pumps, Control Supply to Switchgears & Panels, Emergency Lighting

DC system mainly comprises of :

• Batteries (Lead acid tubular/plante, Ni Cd type)• Battery chargers (float and float cum boost chargers)• DC distribution boards

Major local suppliers for Batteries: Exide, HBLNIFEMajor local supplier for Battery Chargers: Chhabi, Caldyne

Plant DC Supply System

Page 30: basics of engineering Electrical.ppt

L&T- Power Battery Room Picture

Battery Rack

Operation & Maintenance Space

Cable Trays

Page 31: basics of engineering Electrical.ppt

L&T- Power

UPS System

Provides uninterrupted AC power to:

• DCS• Various control panels• Instrumentation System

• Mainly comprises of : Battery charger, Battery, Static Inverter, Static Switches, Isolation Transformer, UPS DB.

• Major local suppliers for UPS: DB power, HIREL, Emerson, Gutor, HiRel

Uninterrupted Power Supply (UPS) System

Page 32: basics of engineering Electrical.ppt

L&T- Power

• Large thermal power plants are generally located away from the load centers

• Generated power is stepped up to a suitable high voltage in step-up substation / switchyard at generating end to minimize the transmission losses.

• Evacuation system receives power from the generating station at high voltage level, interconnects generating station with the regional / National grid.

• Provides power to generating station to feed plant auxiliaries during start up, and to feed station-load during running condition.

Overview - Power Evacuation System

Page 33: basics of engineering Electrical.ppt

L&T- Power

Generator Transformer

IPBD

Connection with the Switchyard

Connection of Generating Station with a Switchyard

Page 34: basics of engineering Electrical.ppt

L&T- Power Outdoor (AIS) type Switchyard

Switchyard Control Building

Transmission Tower& Lines

Page 35: basics of engineering Electrical.ppt

L&T- Power

Current

Transformer (CT) Centre rotating

double break isolator

Circuit

Breaker (CB)

Major equipment of a Outdoor type Switchyard

Page 36: basics of engineering Electrical.ppt

L&T- Power

400 kV Circuit breaker &Lighting tower

Wave trap, Capacitive Voltage Transformer (CVT), Lightning Arrestor,Double circuit Transmission tower

LA

Wave Trap

Major equipment of a Outdoor type Switchyard

CVT

TransmissionTower

CB

LightingTower

Page 37: basics of engineering Electrical.ppt

L&T- Power

Front View

Rear View

33 kV Gas Insulated Switchgear (GIS)

Page 38: basics of engineering Electrical.ppt

L&T- Power 132 kV GIS

CB MODULE

BUS BAR MODULE

VT MODULE

CT MODULE

Page 39: basics of engineering Electrical.ppt

L&T- Power Comparison between Outdoor AIS and GIS type Switchyard

Parameters Outdoor AIS Indoor GIS

Layout Occupies large space.

Hence suitable for plants in remote areas.

Occupies less than 40% space as compared to AIS. Hence suitable for urban area where land is at premium.

Civil & Structural aspects

Involves construction of large number of small foundations over a vast area, and vast length of small cable trenches

Involves construction of a GIS building

Environmental Considerations

Noise and electromagnetic radiation emanating from EHV lines is a cause of concern

Not a concern, as all the EHV conductors are enclosed

Overall Economics Excluding land cost, Initial capital cost is substantially less as compared to GIS.

Approximately 2.5 to 3 times costlier than AIS of similar capacity, for 220kV and 400kV level

Page 40: basics of engineering Electrical.ppt

L&T- Power

Load flow for the study of voltage regulation

Motor Starting Analysis - for the study of voltage regulation during motor starting, constraints on motor starting current

Short Circuit / Fault Studies - for selection / verification of % impedance of transformers, fault rating for Switchgear / MCC, assigning short circuit rating for equipment / system

Relay co-ordination / Settings for protection co-ordination, designing primary protections, ensuring system safety and maximum availability

Power System Studies

Page 41: basics of engineering Electrical.ppt

L&T- Power Switchgear Room Picture – Showing HV Switchgear

Page 42: basics of engineering Electrical.ppt

L&T- Power Switchgear Room Picture – Showing LV Switchgear

Page 43: basics of engineering Electrical.ppt

L&T- Power Model View of Cable Trays on Pipe rack

Page 44: basics of engineering Electrical.ppt

L&T- Power Picture of Cable Trays on Pipe rack

Page 45: basics of engineering Electrical.ppt

L&T- Power Picture of Cable Trays on Pipe rack

Page 46: basics of engineering Electrical.ppt

L&T- Power Picture showing Under ground cable trench

Page 47: basics of engineering Electrical.ppt

L&T- Power Underground Duct bank pictures

Page 48: basics of engineering Electrical.ppt

L&T- Power