BASIC INSTALLATION GUIDE For full technical guidance call Scotdeck on 01501 750840 Typical End Detail on Steel Typical Side Detail on Brick/Block Typical Side Detail on Steel Typical End Detail on Brick/Block Beam centres Edge trim Stud on centreline of beam ComFlor®51 + Floor Decking to extend to edge trim Universal beam Restraint strap at 600mm centres X ComFlor®80 Floor Decking 20 mm min Universal beam X Steel Stud Edge trim Restraint strap at 600mm centres Typical wall side detail Wall outer dimensions ComFlor®80 Floor Decking with 50 mm (minimum) bearing Masonry fixing to wall at 500 mm c/c 100 mm wall illustrated Overall outer dimensions Typical wall side detail 100 mm wall illustrated ComFlor®80 Floor Decking with 75 mm (minimum) bearing onto wall www.scotdeck.com E. [email protected] T. 01501 750840 Shona’s Way, Sibbald Park, Blackridge, West Lothian EH48 3BN

BASIC INSTALLATION GUIDE - Scotdeck Ltd

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: BASIC INSTALLATION GUIDE - Scotdeck Ltd

BASIC INSTALLATION GUIDEFor full technical guidance call Scotdeck on 01501 750840

Typical End Detail on Steel

Typical Side Detail on Brick/Block

Typical Side Detail on Steel

Typical End Detail on Brick/Block

Beam centres

Edge trim

Stud on centreline of beam

ComFlor®51 + Floor Deckingto extend to edge trim

Universal beam

Restraintstrap at

600mmcentres

X

ComFlor®80Floor Decking

20 mm min

Universal beam

X

Steel Stud

Edge trim

Restraint strap at 600mm centres

Typical wall side

detail

Wall outer dimensions

ComFlor®80 Floor Deckingwith 50 mm (minimum) bearing

Masonry fi xing to wall at 500 mm c/c

100 mm wall illustrated

Overall outer dimensions

Typical wall side

detail

100 mm wall illustrated

ComFlor®80 Floor Deckingwith 75 mm (minimum) bearing onto wall

www.scotdeck.com E. [email protected]. 01501 750840

Shona’s Way, Sibbald Park, Blackridge, West Lothian EH48 3BN

Page 2: BASIC INSTALLATION GUIDE - Scotdeck Ltd

www.scotdeck.com E. [email protected]. 01501 750840

Shona’s Way, Sibbald Park, Blackridge, West Lothian EH48 3BN

DECK FIXINGImmediately after laying, the deck must be fi xed through its trough to the top of the supporting structure. Powder actuated pins or self-drilling screws are used. Side lap fi xings are required at 1000mm centres for all profi les.

Casting concreteBefore the concrete is poured, the decking must be cleared of all dirt and grease, which could adversely infl uence the performance of the hardened slab. The oil left on the decking from the roll forming process does not have to be removed. Concrete should be poured evenly, working in the direction of span. Care should be taken to avoid heaping of concrete in any area during the casting sequence. Construction and day joint should occur over a support beam, preferably also at a deck joint.

Temporary supportsThe safe design and installation of temporary props is the responsibility of the main contractor or designated sub contractor. Where temporary supports are required by the design, these must provide continuous support to the profi led sheeting. Spreader beams (timbers) are used, supported by temporary props at one metre centres.

Edge trimThis is used to retain the wet concrete to the correct level at the decking perimeters. It is fi xed to the supports in the same manner as the deck and the top is restrained by straps at 600mm centres, which are fi xed to the top of the deck profi le by steel pop rivets or self drilling screws,

To steel

Heavy duty powder actuated fi xingsHilti X ENP 19 L15 nail/Split SBR14 or equivalent.

For temporary fi xing (i.e. where weld through shear studs are to be used) Hilti DAK16.

Self-drilling screws. To steel up to 11mm thick - SFS SD145.5 x 32/EJOT HS 38 or equivalent.

To steel up to 17mm thickSFS TDC - T - 6.3 x 38 or equivalent.

To masonryor concrete

Pre-drill hole - use self tapping fi xing suitable for masonry/concrete - SFS TB-T range/EJOT 4H32 or equivalent

To side laps or closures

etc.

Self drilling stitching screw typically SFS SL range/EJOT SF25 or equivalent

Comfl or® 46 & ComFlor® 100Comfl or® 51+ & ComFlor® 60 & ComFlor® 80

End fi xing3 per sheet(2 per sheet when using sheer studs)

2 per sheet

Intermediate supports

2 per sheet(1 per sheet when using shear studs)

1 per sheet

Side laps (for all profi les)

1 fi xing at 1000 mm c/c

Side fi xing onto support (for all

profi les)1 fi xing at 600 mm c/c

0.9 1.2 1.6 2.0

130 100 125 160 195

150 50 115 150 185

200 x 100 130 160

250 x 50 100 135

300 x x 50 100

350 x x x 50

Fixing information for shallow decking

Fixing spacings

Edge trim selectorEdge trim

depth

x = not recommended

Maximum cantilever (mm)Galv. steel edge trim thickness (mm)

Temporary support using an Acrow type prop