Upload
trankhuong
View
239
Download
1
Embed Size (px)
Citation preview
BASIC ASSESSMENT REPORT
105
F599/19 Morning Mushrooms cc [email protected]
PO Box 2307, Beacon Bay, 5205 (083)4507522
F600/20, F600/21, F305/0 Schwartz Family Trust [email protected]
Hillview, P O Box 42, Homeleigh, 5212 (082)6524330
F599/22 Government [email protected] (082)5698627
F602/9, F602/22, F305/1 Amatola Water
Private Bag X3, Vincent, 5217 (043)7073700
F599/23 Paul Jakobus van Heerden [email protected]
P O Box 251, Cradock, 5880 (048)8813112 (084)5803490
F599/24 Leo Philip Geyer [email protected]
P O Box 19722, Tecoma, 5214
(043)7210033 / (011)3951541 (083)2653360
F600/22 Peter Otto Wilhelm Vischer [email protected] (043)7307023
F600/7 Michael Wayne Anderson [email protected]
P O Box 2556, Beacon Bay, 5205 (043)7210273
(083)7723767 / f(043)7210273
F600/5 Desmond Patrick Mildenhall
P O Box 2180, Beacon Bay, 5205 (043)7307053 (082)9367303
F600/11 Janet Egelhof [email protected]
P O Box 13059, Vincent, 5217
(043)7261028 / (043)7363207 (082)7186991
F601/6 Thomas Arthur Kretzmann [email protected] P O Box 617, East London (043)7222246 (083)6418811
F601/9 Wag-All 92 cc [email protected] P O Box 617, East London (043)7222246 (083)6418811
F601/14 Anton Lotter [email protected]
P O Box 1127, East London, 5200 (043)7307120 (082)5551476
F601/15, F601/16, F816/15, F816/86 ESKOM Holdings LTD [email protected] (043)7032585
F816/91 ESKOM Holdings LTD [email protected]
(043)7032104
F601/22 Donovan Michael Kretzmann [email protected]
P O Box 3171, Cambridge, 5206
(043)7307123 / (043)7222246 (083)6297390
F601/23 TELKOM SA LTD [email protected] (082)8260004 F651/2, F651/3, F816/9, F816/5, F816/9, F816/68
Amatole District Municipality
[email protected]; [email protected]
(043)7832393/2394
BASIC ASSESSMENT REPORT
106
F651/4, F651/13, F651/16, F651/23
Maureen Yvonne Oberem [email protected]
P O Box 13167, Cambridge, 5206
(043)7307060 / (043)7307060 (083)6510422
F651/7 Harold Frank Hughes [email protected] P O Box 2164, Beacon Bay, 5205 (043)7307110 0825953926
F651/12 B & GVW Prop CC [email protected]
P O Box 11153, Southernwood
(043)7265505 / (043)7263356
(082)9254380 / (083)2641507
F651/15 Bernadene Rhona Sternberg [email protected]
P O Box 3256, Cambridge, 5200 (043)7307121 (084)2094817
F652/2 All Craze 1050 cc [email protected] P O Box 2538, Beacon Bay (082)3746444
F652/3 Elizabeth Ann Whitelaw Broughton-Clarke [email protected]
P O Box 17, Homeleigh Halt, 5212 (083)2810037
F652/4 Garry Reginald Rogers [email protected]
P O Box 2024, Beacon Bay, 5205 (043)7307555 (082)4141703
F652/8 East London Child and Youth Care Centre [email protected] P O Box 313, East London (043)7260733 (082)2006353
F816/38 Daniel Barnard [email protected]
P O Box 2301, Beacon Bay, 5205 (043)7481160 (083)4558149
F816/39 Eleanora Joyce Walsh P O Box 14, Homeleigh, East London, 5211 (084)8421215
F816/40 Barry Arthur Neville [email protected]
P O Box 14, Homeleigh, 5212 (043)7484818 (082)6402801
F816/87 Jacobus Gerhard Saayman [email protected]
P O Box 2862, Beacon Bay, 5200
(043)7481936 / (043)7481936 (073)2426297
F816/88 BCMM [email protected] (043) 7052115 / 2507
F817/6 Kenneth David Frazier Cartwright [email protected]
P O Box 19251,Tecoma, 5214 (043)7354335 (082)5533709
F817/7 Lynette Esmay Esterhuyse [email protected]
(043)7321577 / (043)7321577 (082)5290732
F817/28 Saddle Path Props 59 PTY LTD [email protected] P O Box 13018, Vincent
(046)6540162 / (043)7433407
(082)5782320 / 0828093409
F817/30, F821/1 Colin Keith Salzwedel [email protected]; [email protected]
P O Box 2089, Beacon Bay, 5205
(043)7321172 / (043)7321722 (073)2462500
BASIC ASSESSMENT REPORT
107
F817/61 Amatole District Council [email protected]; [email protected]
(043)7832393/2394
F817/62 Erroll Mark Schonknecht [email protected] P O Box 526, Gonubie, 5256
(083)2723069 f (043)7438855
F817/63 Jacobus Gerhard Saayman [email protected]
P O Box 2862, Beacon Bay, 5200
(043)7481936 / (043)7481936 (073)2426297
F817/64 Izak Stephanus Coetsee [email protected]
7 Garden Street, Southernwood, East London, 5201
(043)7211020 / (043)7434340 (082)3272471
F817/65 Trevor Len Fraunstein
P O Box 3363, Cambridge, 5206
(083)3653832 /f (043)7267467
F817/102, F817/103 Kenneth David Frazier Cartwright [email protected]
P O Box 19251,Tecoma, 5214 (043)7354335 (082)5533709
F817/104 Wag-All 53 cc [email protected] P O Box 19451, Tecoma (043)7211121 (083)2662184
F818/0 Michael Frank du Toit [email protected]
Postnet , Private Bag X, Beacon Bay, (043)7321209 (082)5609990
F819/0 Azalea Holdings PTY LTD
[email protected]; [email protected]
P O Box 821, Northlands, 2116
(011)4937921 / (011)4937921
(083)3797453
F821/4 Build Props No 3 cc [email protected] P O Box 15700, Beacon Bay, East London (043)7321772 (082)9582653
F821/5 Helius Prop cc 71 Kloof Road Bedfordview 2008
F821/6 Milada Yvonne Burger [email protected]
P O Box 15050, Beacon Bay, North Coast House, 5205
(043)7321877 / (043)7321732 (082)8143765
F821/9 Simon Andrew Barker [email protected] P O Box 67, Gonubie, 5256 (043)7321666 (072)6363310
F821/10 Peggy Sheila Beard P O Box 13007, Vincent, 5217 (043)7221743
F821/11 Sapling Trade & INV 35 PTY LTD [email protected]
P O Box 19544, Tecoma, 5214 (043)7016900
F821/12 Desmond Neville & Paulina Naude Box 91, Homeleigh, 5212 (043)7311533 (083)9870849
BASIC ASSESSMENT REPORT
108
F821/14 Schuleeta Ann Lottering [email protected] (078)2396307
F821/15 Violet Zanele Barlow 3 Sable Place, Beacon Bay, 5241 (043)7483409
F821/16 Tom van der Vyver [email protected]
P O Box 2, Homeleigh, East London, 5212 (043)7307086 (083)9481168
F821/17 Ecopolymers cc [email protected]
P O Box 12311, Amalinda, East London (043)7420644 (083)4471482
F821/18 Mcklein Prop cc [email protected] P O Box 12485, Amalinda (043)7307365 / (043)7211711
(072)1537514 / (072)7974532
F821/19 Mohamed Moosajee [email protected]
P O Box 22931, Port Elizabeth, 6000
(041)5854938 / (041)5854938 (082)7816458
F821/20 Ashton Brian Harris [email protected]
P O Box 8146, Nahoon, 5241 (043)7221349 (084)5007080
F821/21 Valerie Ann Wood [email protected]; [email protected]
(043)7307374 / (043)7374258 (073)3037080
F821/22 Joseph Moses Reddy [email protected] P OBox 52849, Umtata, 5099
(047)5341956 / (047)5341956 (083)4453788
F821/23 Lawrence Robert Pohlman
P O Box 136, Homeleigh, 5212 (043)7093332
F821/24 Cyril Errol Naude P O Box 53, Homeleigh, 5212 (043)7631143
(083)3109913 f(043)7264565
F821/25 Deon Richard Coetzer [email protected]
P O Box 78, Homeleigh, 5212 (043)7321343 (082)7730261
F821/26 John Leonard Davies [email protected]
P O Box 17, Logan Drive, Nahoon, 5241 (043)7052880 (083)3216647
F821/27 Eric Fabian Clarke P O Box 198, Gonubie, 5256 (043)7321843 (072)1946264
F821/28 Petrus Philip Diedericks [email protected]
P O Box 2563,Beacon Bay 5205 (043)7321169 (083)2738825
F821/29 Patina Christina Bennett 278 Voortrekker Road, Eikendal, Kraaifonein, 7570 (021)9887965
F821/37 Paul van Heerden [email protected]
P O Box5190, Greenfields, 5208
(043)7321164 (083)2828546
BASIC ASSESSMENT REPORT
109
F821/38 Shane Michael Roach [email protected]
P O Box 2412, East London, 5200
(043)7321123 / 0437321123 (082)4537419
F821/39 James Mitford Thomson [email protected]; [email protected]
P O Box 2347 Beacon Bay, 5205 (043)7433585
F821/40 Ipoma Traders cc [email protected]
P O Box 15345, Beacon Bay, 5205 (082)7578551
F821/41 Allen Brian Lennard [email protected]
P O Box 2191, Beacon Bay, 5205
(043)7307339 / (043)7421641 (083)2549618
F821/35, F821/36 Rogers Yellow Woods Prop Trust [email protected] (043)7321133
F600/9 Andrew Bernard Levey [email protected]; [email protected]
P O Box 114, Homeleigh, East London, 5212 (043)7307310
(072)1795392 / (083)4002886
F600/16 Anthony Clarence Enslin [email protected]
P O Box 118, Homeleigh, 5212
(043)7307379 / (043)7482423 (082)0573273
F650/11 Patricia Richter [email protected]
P O Box 106, Homeleigh, 5212 (043)7116433 (083)3573292
F651/5 Malcolm William Pottinger
P O Box 13187, Vincent, 5217 (043)7264961
F816/92, F816/72 Errol Bryan Sangerhaus [email protected]
P O Box 352, East London, 5200
(043)7403221 / (043)7486006 (083)4596639
F600/4, F600/12 Graham Laird King [email protected]
P O Box 84, Homeleigh, 5212 (043)7307559 (078)3387346
F600/3 Sandra Joan Spence [email protected]
P O Box 869, East London, 5200
(043)7039885 / (043)7401085 (083)3205392
F652/7 Jiri Stanislav Koloman Kaps [email protected]
P O Box 2313, Beacon Bay, 5205 (043)7483589 (079)3887502
F599/0 R Kretzmann Trust P O Box 7449, East London, 5200 (043)7307011
(082)3187883 / f (043)7307059
F601/2 Valerie Yvonne Robinson [email protected]
P O Box 1665, East London, 5200 (043)7002345 (083)2751488
F652/5 M W Johnson Prop Trust [email protected]
P O Box 108, Homeleigh, 5212 (043)7307161 (082)6936555
BASIC ASSESSMENT REPORT
110
F821/13 Anne-Marie Grobbelaar 1 Kew Road, Vincent, 5217 (071)0612387
F816/74
East London Independent School Educational Trust [email protected]
P O Box 66, Homeleigh, 5212 (043)7486094
F817/84 Gerald & Vyvan Muller Family Trust [email protected]
P O Box 2062, Beacon Bay, 5205 (043)7482420
F817/29, F817/85 Walsh Prop Trust [email protected]
P O Box 2062, Beacon Bay, 5205 (043)7482420
F821/3 Norma Shirley Webber [email protected]
PO Box 2037, Beacon Bay, 5205 (043)7321392
F600/8 Tracey Lynn Blewett [email protected] Private Bag X8, Elarduspark, 0047 (012)3453154 (083)5111846
F817/8, F820/0, F1237/0, F1237/1, F816/27,F816/93, F816/72 Edcot Trust [email protected]
P O Box 1968, East London, 5200 (043)7071775 (078)0199858
F599/3 Hazel Aletta & Aubrey Victor Lugte
P O Box 2312, Beacon Bay, 5205 (043)7307155
F820/1 Edison Ndwayiza Makeba [email protected] (043)7424762/8
F816/33 Annette Spies [email protected]
(043)7115215
F816/4 Ntombomzi Felemu
56935 Mqokolo Street, Nompumelelo, Beacon Bay, East London, 5245
F816/4 T.N. Mhlwana
56935 Mqokolo Street, Nompumelelo, Beacon Bay, East London, 5245 (083)8918865
F816/4 Evelyn Mali
56934 Mqokolo Street, Nompumelelo, Beacon Bay, East London, 5245 (073)8621042
F816/60 Ntombomzi Sityeba
56933 Mqokolo Street, Nompumelelo, Beacon Bay, East London, 5246 (071)8358948
F816/61 Akhona Mabengwana 56914 Darling Street, Nompumelelo, Beacon Bay, (083)5531819
BASIC ASSESSMENT REPORT
111
East London, 5247
F816/62 No-Ande Bango
56912 Darling Street, Nompumelelo, Beacon Bay, East London, 5248 (083)7704542
Registered I&APs
Debbie Reynhardt [email protected] P.O. Box 49, Homeleigh, 5212 (043)7351528 (083)5088977
René Cathro [email protected] (033)3431130
BASIC ASSESSMENT REPORT
112
APPENDIX E6 COPIES OF CORRESPONDENCE SENT
Initial Notification Letter and Background Information Document sent to all Stakeholders and IA&Ps
BASIC ASSESSMENT REPORT
113
Background Information Document
Page 1 of BID
BASIC ASSESSMENT REPORT
114
Page 2 of BID
BASIC ASSESSMENT REPORT
115
Page 3 of BID
BASIC ASSESSMENT REPORT
116
Registered mail
BASIC ASSESSMENT REPORT
117
BASIC ASSESSMENT REPORT
118
Fax
BASIC ASSESSMENT REPORT
119
BASIC ASSESSMENT REPORT
120
BASIC ASSESSMENT REPORT
121
Proof of Notification sent: Emails
BASIC ASSESSMENT REPORT
122
BASIC ASSESSMENT REPORT
123
BASIC ASSESSMENT REPORT
124
BASIC ASSESSMENT REPORT
125
BASIC ASSESSMENT REPORT
126
RELEASE OF DRAFT BAR Letter sent to Registered I&APs concerning release of Draft BAR
BASIC ASSESSMENT REPORT
127
Email sent to all Stakeholders and IA&Ps concerning release of Draft BAR
BASIC ASSESSMENT REPORT
128
BASIC ASSESSMENT REPORT
129
BASIC ASSESSMENT REPORT
130
BASIC ASSESSMENT REPORT
131
Registered mail
BASIC ASSESSMENT REPORT
132
Fax
BASIC ASSESSMENT REPORT
133
BASIC ASSESSMENT REPORT
134
BASIC ASSESSMENT REPORT
135
BASIC ASSESSMENT REPORT
136
BASIC ASSESSMENT REPORT
137
BASIC ASSESSMENT REPORT
138
APPENDIX F
Impact Assessment
Impacts and mitigation of the Planning and Design phase of the Preferred Alternatives.
PLANNING AND DESIGN PHASE NATURE OF IMPACT
IMPACT DESCRIPTION
SPATIAL SCALE
TEMPORAL SCALE/ DURATION
CERTAINTY SCALE/ LIKELIHOOD
SEVERITY/ BENFICIAL SCALE
SIGNIFICANCE PRE-MITIGATION
MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION
GENERAL PLANNING AND DESIGN ISSUES
ALL ALTERNATIVES POLICY COMPLIANCE
Direct The pipeline route may not be consistent with relevant environmental policy and/or spatial guideline documents, (e.g. the alternative routes for the pipeline falls within CBA 2 in terms of ECBCP and within 32m of wetland).
Localised Permanent Possible Severe MODERATE NEGATIVE
The development must comply with relevant legislation and/or policy, e.g. ECBCP, Municipal By-laws, SDFs, etc.
LOW NEGATIVE
LAND OWNERSHIP AND SERVITUDE CONSTRAINTS
Direct The pipeline construction will inconvenience landowners.
Localised Permanent Possible Severe HIGH NEGATIVE
Prior to the start of the construction, servitude agreements must be in place and the areas to be directly impacted must be appropriately demarcated so that no undue impact is made on the surrounding environment.
LOW NEGATIVE
CONSIDERATION OF THE ENVIRONMENT
Direct/Indirect/Cumulative
Lack of environmental consideration in the route planning and inappropriate placement of the pipeline within sensitive systems along the length of the route.
Project level Permanent Possible Moderately severe
MODERATE NEGATIVE
Where feasible, the routing of the pipeline must be planned to avoid sensitive environments.
An independent Environmental Control Officer (ECO) must be appointed and must give input to the final layout.
Micro-siting of the final pipeline layout must be approved by the ECO.
LOW NEGATIVE
SOCIO-ECONOMIC
Direct Temporary job creation and skills development. Surrounding areas
Short Term Probable
Beneficial VERY BENEFICIAL
No mitigation. VERY BENEFICIAL
Direct
The local community will be provided with potable water.
Project Level Long Term Probable Beneficial VERY BENEFICIAL
No mitigation. VERY BENEFICIAL
PIPELINE MATERIALS
Direct/Indirect The use of inappropriate corrodible material for the pipeline could result in leakages and result in loss of the water resource.
Localised Long term Possible Severe MODERATE NEGATIVE
High quality design specifications (i.e. appointing a suitably qualified engineer) and materials (e.g. SABS approved) must be adopted for all elements of infrastructure design and installation.
LOW NEGATIVE
ACCESS ROADS
Direct/Indirect Access roads for construction and maintenance that are on steep slopes will lead to loss of vegetation and potential soil erosion.
Project level Short term Possible Moderately severe
MODERATE NEGATIVE
Where possible, all construction access roads and tracks must avoid steep slopes or sensitive environments.
LOW NEGATIVE
LANDSCAPE & VISUAL
Direct/Indirect/Cumulative
Aesthetic impacts of the pipeline on the currently open landscape.
Localised Long term Probable Moderate to slight
LOW The area must be re-vegetated with indigenous grasses.
Topsoil excavated on site must be retained and protected for use in landscaping of the area post-construction.
LOW
GEOLOGY & SOILS
Direct Installation of pipeline without taking into account the geology and soil structure along the proposed
Localised Long term Possible Moderately severe
MODERATE NEGATIVE
Unsuitable and unstable geological or soil structure must be avoided as far as possible.
LOW NEGATIVE
BASIC ASSESSMENT REPORT
139
PLANNING AND DESIGN PHASE NATURE OF IMPACT
IMPACT DESCRIPTION
SPATIAL SCALE
TEMPORAL SCALE/ DURATION
CERTAINTY SCALE/ LIKELIHOOD
SEVERITY/ BENFICIAL SCALE
SIGNIFICANCE PRE-MITIGATION
MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION
line may result in unnecessary soil erosion and/or damage to geological formations.
ECOLOGY
Direct Permanent loss of thicket vegetation due to pipeline routing.
Localised Permanent Definite Moderately severe
MODERATE NEGATIVE
Construction activities must be limited to the pipeline route.
LOW NEGATIVE
Direct/Indirect The pipeline could result in permanent physical loss of wetlands in the area without proper planning.
Localised Long term Possible Moderately severe
HIGH The project layout must be planned to ensure that a buffer zone of 32 metres is maintained and that no development activities occur within watercourses.
Authorisation from DWA must be obtained if any construction footprint takes place inside or within 32 meters of any water body.
LOW
HERITAGE AND PALEONTOLOGY
Direct The heritage and paleontological heritage of the area may be impacted by the pipeline routing.
Localised Long term Possible Moderately severe
MODERATE NEGATIVE
The recommended management measures from the Phase 1 Heritage assessment must be incorporated in the final planning and design for the pipeline construction (See Appendix D1 for Heritage Impact Assessment Report).
LOW NEGATIVE
SOIL EROSION
Direct/Indirect The placement of the pipeline on steep slopes may require vegetation clearing and result in significant soil erosion.
Project level Long term Possible Severe MODERATE NEGATIVE
Construction activities must not be located on slopes steeper than 1:6.
Appropriate stormwater routing and attenuation must be implemented to avoid onsite erosion and downstream sedimentation.
LOW NEGATIVE
OPTION A1 (River crossing, north route) Same as the General PLANNING AND DESIGN impacts above; IN ADDITION:
RIVER CROSSING
Direct/Indirect Without proper planning, the pipeline could result in damage to the Nahoon River.
Localised Medium to long term
Possible Severe HIGH The pipeline layout must be planned to ensure that watercourses are not disturbed or damaged.
Water courses within 32 meters of the route must be demarcated and must not be accessible during construction.
All trenches dug within 32 meters of any water courses must be rehabilitated in full.
No work camp or any other temporary construction infrastructure shall be erected within 32 meters of any water body.
Where necessary, water use licenses should be obtained from the Department of Water Affairs for impeding/diverting flow of water.
LOW
OPTION B2 (south of N6) TRAFFIC
Direct/Indirect The N6 is the most direct route between Stutterheim/Queenstown and East London. Construction along this route with cause increased traffic congestion.
Project level Short to medium term
Possible Slight LOW Project planning with BCMM must include adequate measures to avoid traffic congestion during construction phase of the pipeline.
LOW
OPTION C1 (along N6) Same as B2.
OPTION C2 (east of N6) STREAM CROSSING
BASIC ASSESSMENT REPORT
140
PLANNING AND DESIGN PHASE NATURE OF IMPACT
IMPACT DESCRIPTION
SPATIAL SCALE
TEMPORAL SCALE/ DURATION
CERTAINTY SCALE/ LIKELIHOOD
SEVERITY/ BENFICIAL SCALE
SIGNIFICANCE PRE-MITIGATION
MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION
Direct/Indirect Inappropriate disturbance and modification to streams during construction may lead to hydrological changes.
Localised Medium term Possible Severe HIGH NEGATIVE
Construction on any crossings must comply with the EMPr approved by Department of Water Affairs and Department of Environmental Affairs.
Construction on stream crossings must be done under the supervision of the ECO.
MODERATE NEGATIVE
OPTION C3 (far east of N6) Same as C2.
Impacts and mitigation of the Construction phase of the Preferred Alternative.
CONSTRUCTION PHASE NATURE OF IMPACT
IMPACT DESCRIPTION
SPATIAL SCALE
TEMPORAL SCALE/ DURATION
CERTAINTY SCALE/ LIKELIHOOD
SEVERITY/ BENFICIAL SCALE
SIGNIFICANCE PRE-MITIGATION
MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION
GENERAL CONSTRUCTION ISSUES
ALL ALTERNATIVES NOISE POLLUTION
Direct Noise pollution caused during construction could potentially be a nuisance to neighbouring residential areas and businesses along the pipeline route.
Localised Short term Possible Moderately Severe
MODERATE NEGATIVE
Construction activities and movement of construction vehicles must be limited to the hours 08:00am – 17:00pm.
LOW NEGATIVE
DUST
Direct Dust (air) pollution caused by digging and levelling of exposed soil can cause a nuisance to neighbouring areas and businesses along the pipeline route.
Localised Short term Probable Severe MODERATE NEGATIVE
Cleared surfaces must be dampened whenever possible and especially in dry and windy conditions to avoid excessive dust generation.
Any soil excavated, and not utilised for rehabilitation, must be removed from site or covered and no large mounds of soil should be left behind after construction.
LOW NEGATIVE
HAZARDOUS SUBSTANCE USAGE
Direct Cement, tar and bitumen mixing techniques and diesel/oil spillage occurring as a result of poorly maintained machinery can contaminate the surrounding environment (soil, surface/groundwater).
Localised Long term Possible Severe MODERATE NEGATIVE
Hazardous Chemical Substances Regulations promulgated in terms of the Occupational Health & Safety Act 85 of 199. And the SABS Code of Practice must be adhered to. This applies to solvents and other chemicals possibly used in the construction process.
Oil trays must be placed under the machinery to avoid soil contamination. All areas affected during the Construction Phase should be rehabilitated.
CONCRETE BATCHING
Concrete should not be mixed directly on the ground, or during rainfall events when the potential for transport to the stormwater system is the greatest (as per the EMPr).
Concrete must be mixed only in the area demarcated for this purpose and on an impermeable substratum.
All areas affected during the Construction Phase must be rehabilitated.
HAZARDOUS CHEMICAL STORAGE
All hazardous chemicals must be properly stored in a
LOW NEGATIVE
BASIC ASSESSMENT REPORT
141
CONSTRUCTION PHASE NATURE OF IMPACT
IMPACT DESCRIPTION
SPATIAL SCALE
TEMPORAL SCALE/ DURATION
CERTAINTY SCALE/ LIKELIHOOD
SEVERITY/ BENFICIAL SCALE
SIGNIFICANCE PRE-MITIGATION
MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION
secure bunded and contained area.
Staff that will be handling hazardous materials must be trained.
WORKER HEALTH AND SAFETY
Direct Destruction of sensitive vegetation due to uncontrolled wood collection.
Localised
Long term Possible
Severe
MODERATE NEGATIVE
No illegal firewood collection shall be allowed and must be monitored by the Environmental Site Officer.
LOW NEGATIVE
Direct Inadequate attention to fire safety awareness and fire safety equipment could result in unsafe working environment and wider ecological and social damage (loss of crops and property).
Localised
Short term Possible Severe HIGH NEGATIVE
The Contractor must have operational fire-fighting equipment available onsite at all times.
All construction foremen must be trained in fire hazard control and fire fighting techniques.
All flammable substances must be stored in dry areas which do not pose an ignition risk to the said substances.
No open fires must be allowed onsite unless in a demarcated area identified by the ECO.
No smoking must be allowed near flammable substances.
Cooking must be done in demarcated areas that are safe and would not cause runaway or uncontrolled fires.
Construction waste or debris must not be burnt onsite.
MODERATE NEGATIVE
Direct Failure to provide adequate onsite sanitation may result in runoff transferring contaminants into the surrounding environment.
Localised
Short term Possible
Moderately severe
MODERATE NEGATIVE
Onsite sanitation facilities must be provided and construction workers must be informed not to use the surrounding environment.
The facilities must be regularly serviced to reduce the risk of surface or groundwater pollution.
Contaminated wastewater must be managed by the Contractor to ensure existing water resources on the site are not contaminated. All wastewater from general activities in the camp must be collected and removed from the site for appropriate disposal at a licensed commercial facility.
LOW NEGATIVE
WASTE MANAGEMENT
Direct Littering on site may detract from the visual appeal of the area, and pollute the surrounding areas.
Localised
Short term
Possible
Moderately severe
MODERATE NEGATIVE
All rubble and refuse must be collected and disposed of at Roundhill licenced landfill site.
Littering by the employees of the Contractor must not be allowed under any circumstances. The ECO shall monitor the neatness of the work sites as well as the Contractor campsite.
An environmental management programme incorporating waste management issues during the construction phase of the project has been developed and must be implemented.
LOW NEGATIVE
Direct Increased risk of inadequate waste disposal resulting in pollution of environment
Localised
Long term Possible Severe MODERATE NEGATIVE
All excess waste must be disposed of at Roundhill licensed landfill site.
LOW NEGATIVE
SOCIO-ECONOMIC
Direct/Indirect Increase in job creation during the construction phase
Surrounding area
Medium term Probable Beneficial HIGH POSITIVE Surrounding communities must be hired for construction to provide a beneficial impact on the local economy.
HIGH POSITIVE
TRAFFIC
Direct/Indirect Construction vehicles could cause traffic congestion especially if temporary road closures
Localised Short term Possible Moderately severe
MODERATE During construction, adequate measures to limit traffic congestion must be implemented.
LOW
BASIC ASSESSMENT REPORT
142
CONSTRUCTION PHASE NATURE OF IMPACT
IMPACT DESCRIPTION
SPATIAL SCALE
TEMPORAL SCALE/ DURATION
CERTAINTY SCALE/ LIKELIHOOD
SEVERITY/ BENFICIAL SCALE
SIGNIFICANCE PRE-MITIGATION
MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION
are required.
LOSS OF BIODIVERSITY
Direct Excessive damage to surrounding biodiversity due to vehicular movement and unrestricted construction activities.
Localised Short term Definite Moderately severe
MODERATE NEGATIVE
Construction activities must be restricted within the proposed pipeline route.
And ECO must be on site at least twice a week during construction to monitor construction activities.
LOW NEGATIVE
STORM WATER MANAGEMENT
Direct Uncontrolled stormwater during construction can disperse spillage or leaking of diesel, lubricant and cement and sediment from excavated ground material contaminating the surrounding environment.
Localised Long term Probable Severe HIGH NEGATIVE
Adequate provision must be made to manage stormwater during construction.
LOW NEGATIVE
SOIL EROSION
Indirect Soil erosion on steep slopes due to disturbance of highly erosive soils and poor rehabilitation
Project level Medium to long term
Possible Severe HIGH Construction sites must be stabilised and soil must be prevented from unnecessary exposure.
Vegetation re-establishment must be implemented as part of a detailed Rehabilitation Plan.
MODERATE
OPTION A1 (River crossing, north route) RIVER CROSSING
Direct Construction activities (e.g. bulldozers, rubble) of a pipeline across the Nahoon River increase the risk of damage to sensitive river ecosystems.
Project level Medium term Definite Moderately severe
MODERATE NEGATIVE
All construction rubble must be removed from all rivers and streams after completion of work.
The river/stream must be returned to its natural state after construction.
LOW NEGATIVE
OPTION B2 Same as the General CONSTRUCTION impacts above.
OPTION C1 Same as the General CONSTRUCTION impacts above.
OPTION C2 STREAM CROSSING
Direct Damage and loss of streams due to construction activities close to or in the streams.
Localised Short term Possible Moderately severe
MODERATE A buffer zone of 32 metres must be maintained. No development activities may occur without prior approval by the DWA.
LOW
OPTION C3 Same as C2.
Impacts and mitigation of the Operational phase of the Preferred Alternative.
OPERATIONAL PHASE NATURE OF IMPACT
IMPACT DESCRIPTION
SPATIAL SCALE
TEMPORAL SCALE/ DURATION
CERTAINTY SCALE/ LIKELIHOOD
SEVERITY/ BENFICIAL SCALE
SIGNIFICANCE PRE-MITIGATION
MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION
GENERAL OPERATIONAL ISSUES
ALL ALTERNATIVES MAINTENANCE
Direct Non-compliance with a pipeline maintenance schedule could result in leaks going undetected.
Surrounding areas
Medium term Possible Moderately severe
MODERATE NEGATIVE
Pipelines must be regularly monitored for leaks. If these are identified or reported by the public, immediate actions must be taken to remedy the situation.
LOW NEGATIVE
BASIC ASSESSMENT REPORT
143
OPERATIONAL PHASE NATURE OF IMPACT
IMPACT DESCRIPTION
SPATIAL SCALE
TEMPORAL SCALE/ DURATION
CERTAINTY SCALE/ LIKELIHOOD
SEVERITY/ BENFICIAL SCALE
SIGNIFICANCE PRE-MITIGATION
MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION
Direct/Indirect Disturbance of vegetation due to on-going utilisation of service roads could initiate erosion events.
Localised Short term Possible Moderately severe
HIGH NEGATIVE
Service roads must avoid creating permanent tracks. Monitor for erosion and rehabilitate if necessary.
MODERATE NEGATIVE
INCREASED STORM WATER RUNOFF
Direct Failure to maintain the storm water system could increase the risk of surface water damage to the landscape and vegetation due to increased runoff.
Surrounding areas
Long term Possible Moderately severe
HIGH NEGATIVE
A Storm Water Management Plan must be implemented.
Vegetation must be retained where possible to avoid soil erosion.
MODERATE NEGATIVE
SOCIO-ECONOMIC
Direct/Indirect/Cumulative
Water availability will result in increased housing development.
Surrounding areas
Long term Definite Highly beneficial
BENEFICIAL No mitigation provided. BENEFICIAL
NO-GO
NATURE OF IMPACT
IMPACT DESCRIPTION
SPATIAL SCALE
TEMPORAL SCALE/ DURATION
CERTAINTY SCALE/ LIKELIHOOD
SEVERITY/ BENFICIAL SCALE
SIGNIFICANCE PRE-MITIGATION
MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION
Direct/ Indirect
The no-go option for development entails that the proposed pipeline will not go ahead. There would be a lost opportunity for socio-economic benefits in terms of an improved water supply, job creation, and the provision of housing units.
Localised Long term Probable Moderately severe
MODERATE No mitigation required. MODERATE
BASIC ASSESSMENT REPORT
144
APPENDIX G Environmental Management Programme (EMPr)
BASIC ASSESSMENT REPORT
145
APPENDIX H Details of EAP and expertise
Environmental Consulting Company: Coastal & Environmental Services 16 Tyrell Road, Berea, East London PO Box 8145, Nahoon, East London, 5210 Tel: 043 726 7809/8313 Fax: (043) 726 8352 e-mail: [email protected] www.cesnet.co.za Environmental Assessment Practitioners working on this project:
Dr Alan Carter
Dr Greer Hawley
Mr Roy de Kock
Ms Daisy Kotsedi In fulfilment of this requirement Coastal and Environmental Services (CES) wishes to point to the following expertise of the study team, which includes Dr Alan Carter (Director), , Dr Greer Hawley (Principal Environmental Consultant), Mr Roy de Kock (Senior Environmental Consultant), Ms Daisy Kotsedi (Environmental Consultant) and CES as a consulting firm: Coastal & Environmental Services (CES), established in 1990, is a specialist environmental consulting company based in Grahamstown (Eastern Cape Province). We believe that a balance between development and environmental protection can be achieved by skilful, considerate and careful planning. CES has considerable experience in terrestrial, marine and freshwater ecology, the Social Impact Assessment (SIA) process, and state of environment reporting (SOER), Integrated Waste Management Plans (IWMP), Spatial Development Frameworks (SDF), public participation, as well as the management and co-ordination of all aspects of the Environmental Impact Assessment (EIA) and Strategic Environmental Assessment (SEA) processes. CES has been active in all of the above fields, and in so doing have made a positive contribution to towards environmental management and sustainable development in the Eastern Cape, South Africa and many other African countries. Dr Alan Carter is a Director at CES, holds a PhD in Marine Biology and is a certified Public Accountant, with extensive training and experience in both financial accounting and environmental science disciplines with international accounting firms in South Africa and the USA. He has 15 years’ experience in environmental management and has specialist skills in sanitation, coastal environments and industrial waste. Dr Carter is registered as a Professional Natural Scientist under the South African Council for Natural Scientific Professions (SACNASP).
BASIC ASSESSMENT REPORT
146
Dr Greer Hawley (Principal Environmental Consultant) has a BSc degree in Botany and Zoology and a BSc Honours in Botany from the University of Cape Town. She completed her PhD thesis (Microbiology) at Rhodes University. Greer has been involved in a number of diverse activities. The core academic focus has been directed in the field of taxonomy both in the plant and fungal kingdom. Greer’s research ranges from studying fresh and marine algae, estuarine diatoms, Restio species classification in the fynbos and forest vegetation and fungal species identification and ecology. Greer’s study of fungi have also contributed towards an understanding of soil ecology and “below ground” ecology. She is currently working on numerous impact assessments at the East London branch. Registration: South African Society for Microbiology, South African Association of Botany.
BASIC ASSESSMENT REPORT
147
Mr Roy de Kock (Senior Environmental Consultant) holds a BSc Honours in Geology and an MSc in Botany from the Nelson Mandela Metropolitan University in Port Elizabeth. His MSc thesis focussed on Rehabilitation Ecology with the focus on Mine Rehabilitation. He has been working for CES since 2010, and is based at the East London branch where he focuses on ecological impact assessments, geological and hydro geological analysis, environmental management plans and various environmental impact studies. Roy is registered as a Candidate Natural Scientist under SACNASP. Ms Daisy Kotsedi (Environmental Consultant) has a BSc. Honours and MSc degree in Botany both from Nelson Mandela Metropolitan University in Port Elizabeth. Her MSc thesis focused on the effects of environmental factors on microalgal biomass and community composition in the Sundays River Estuary. Daisy’s research interests include a broad range of environmental conservation and estuarine ecology with the main focus on microalgae. Daisy worked as an intern at WWF-SA in the freshwater unit in 2011. She is currently employed in the East London office of CES. Daisy is registered as a Candidate Natural Scientist under SACNASP.
BASIC ASSESSMENT REPORT
148
APPENDIX I Specialist’s declaration of interest
BASIC ASSESSMENT REPORT
149
APPENDIX J Additional Information
GPS co-ordinates taken every 250 meters along the route for each alternative pipeline
Section A (Option A1)
km Longitude Latitude
0 32°54'13.57"S 27°48'34.71"E
0.25 32°54'6.66"S 27°48'38.64"E
0.5 32°54'12.28"S 27°48'45.58"E
0.75 32°54'17.58"S 27°48'52.85"E
1 32°54'21.34"S 27°48'58.42"E
1.25 32°54'21.54"S 27°49'8.07"E
1.5 32°54'16.55"S 27°49'12.64"E
1.75 32°54'8.68"S 27°49'14.67"E
2 32°54'10.69"S 27°49'23.67"E
2.25 32°54'6.32"S 27°49'30.54"E
2.5 32°54'8.87"S 27°49'37.33"E
2.75 32°54'8.39"S 27°49'44.24"E
3 32°54'7.23"S 27°49'53.58"E
3.25 32°54'5.35"S 27°50'2.90"E
3.5 32°54'6.04"S 27°50'11.87"E
3.75 32°54'13.37"S 27°50'15.34"E
4 32°54'11.85"S 27°50'22.52"E
4.25 32°54'5.61"S 27°50'28.61"E
4.5 32°54'4.89"S 27°50'39.12"E
4.75 32°54'1.26"S 27°50'47.23"E
5 32°53'55.42"S 27°50'53.93"E
5.25 32°53'51.51"S 27°51'1.91"E
5.5 32°53'46.11"S 27°51'9.01"E
5.75 32°53'42.05"S 27°51'16.69"E
6 32°53'43.45"S 27°51'22.66"E
Section A (Option A2)
km Longitude Latitude
0 32°54'13.57"S 27°48'34.71"E
0.25 32°54'6.66"S 27°48'38.64"E
0.5 32°54'12.28"S 27°48'45.58"E
0.75 32°54'17.58"S 27°48'52.85"E
1 32°54'21.34"S 27°48'58.42"E
1.25 32°54'21.54"S 27°49'8.07"E
1.5 32°54'21.74"S 27°49'17.53"E
1.75 32°54'21.93"S 27°49'27.14"E
2 32°54'20.60"S 27°49'34.75"E
2.25 32°54'12.92"S 27°49'36.06"E
2.5 32°54'8.58"S 27°49'43.63"E
2.75 32°54'7.27"S 27°49'52.94"E
BASIC ASSESSMENT REPORT
150
3 32°54'5.54"S 27°50'2.25"E
3.25 32°54'5.66"S 27°50'11.29"E
3.5 32°54'12.79"S 27°50'15.28"E
3.75 32°54'12.28"S 27°50'22.07"E
4 32°54'5.91"S 27°50'28.08"E
4.25 32°54'4.81"S 27°50'37.40"E
4.5 32°54'2.29"S 27°50'45.98"E
4.75 32°53'56.63"S 27°50'52.81"E
5 32°53'52.00"S 27°51'0.23"E
5.25 32°53'47.17"S 27°51'7.82"E
5.5 32°53'41.97"S 27°51'15.04"E
5.75 32°53'43.45"S 27°51'22.66"E
Section B (Option B1)
km Longitude Latitude
0 32°53'43.45"S 27°51'22.66"E
0.25 32°53'35.91"S 27°51'22.85"E
0.5 32°53'40.31"S 27°51'27.55"E
0.75 32°53'47.38"S 27°51'32.38"E
1 32°53'54.49"S 27°51'37.10"E
1.25 32°54'1.30"S 27°51'42.10"E
1.5 32°54'0.94"S 27°51'51.75"E
1.75 32°54'0.64"S 27°52'1.50"E
2 32°54'0.36"S 27°52'11.20"E
2.25 32°53'59.98"S 27°52'20.82"E
2.5 32°53'59.46"S 27°52'30.51"E
2.75 32°53'58.27"S 27°52'40.04"E
3 32°53'57.17"S 27°52'49.62"E
3.25 32°53'55.97"S 27°52'59.20"E
3.5 32°53'57.01"S 27°53'7.95"E
3.75 32°54'3.78"S 27°53'13.27"E
4 32°54'10.38"S 27°53'18.95"E
4.25 32°54'16.75"S 27°53'25.01"E
4.5 32°54'22.92"S 27°53'31.33"E
4.75 32°54'29.20"S 27°53'37.42"E
5 32°54'35.19"S 27°53'43.93"E
5.25 32°54'40.78"S 27°53'50.97"E
5.5 32°54'46.72"S 27°53'57.62"E
5.75 32°54'52.00"S 27°54'4.98"E
6 32°54'56.28"S 27°54'13.28"E
6.25 32°55'2.72"S 27°54'19.00"E
6.5 32°55'5.29"S 27°54'20.90"E
Section B (Option B2)
km Longitude Latitude
0 32°53'43.45"S 27°51'22.66"E
0.25 32°53'51.02"S 27°51'25.82"E
BASIC ASSESSMENT REPORT
151
0.5 32°53'58.09"S 27°51'30.55"E
0.75 32°54'3.92"S 27°51'36.94"E
1 32°54'8.63"S 27°51'44.79"E
1.25 32°54'13.24"S 27°51'52.62"E
1.5 32°54'18.97"S 27°51'59.11"E
1.75 32°54'19.20"S 27°52'8.74"E
2 32°54'19.52"S 27°52'18.38"E
2.25 32°54'19.92"S 27°52'28.03"E
2.5 32°54'15.33"S 27°52'34.09"E
2.75 32°54'15.39"S 27°52'43.73"E
3 32°54'15.38"S 27°52'53.37"E
3.25 32°54'15.41"S 27°53'3.01"E
3.5 32°54'15.81"S 27°53'12.66"E
3.75 32°54'18.85"S 27°53'21.52"E
4 32°54'24.15"S 27°53'28.77"E
4.25 32°54'31.20"S 27°53'33.49"E
4.5 32°54'38.95"S 27°53'36.39"E
4.75 32°54'46.26"S 27°53'40.41"E
5 32°54'51.54"S 27°53'47.61"E
5.25 32°54'54.24"S 27°53'56.69"E
5.5 32°54'54.72"S 27°54'6.33"E
5.75 32°54'59.26"S 27°54'14.07"E
6 32°55'5.62"S 27°54'16.98"E
Section C (Option C1)
km Longitude Latitude
0 32°55'5.62"S 27°54'16.98"E
0.25 32°55'13.46"S 27°54'19.82"E
0.5 32°55'21.13"S 27°54'22.95"E
0.75 32°55'28.85"S 27°54'26.09"E
1 32°55'36.48"S 27°54'29.37"E
1.25 32°55'44.13"S 27°54'32.41"E
1.5 32°55'52.20"S 27°54'33.51"E
1.75 32°56'0.33"S 27°54'33.05"E
2 32°56'8.28"S 27°54'31.60"E
2.25 32°56'16.23"S 27°54'31.90"E
2.5 32°56'22.29"S 27°54'38.05"E
2.75 32°56'26.24"S 27°54'46.49"E
3 32°56'32.38"S 27°54'52.20"E
3.25 32°56'40.30"S 27°54'54.60"E
3.5 32°56'45.85"S 27°55'1.46"E
3.75 32°56'50.24"S 27°55'9.45"E
4 32°56'57.84"S 27°55'11.35"E
4.25 32°56'56.56"S 27°55'20.45"E
4.5 32°56'57.95"S 27°55'27.28"E
Section C (Option C2)
km Longitude Latitude
BASIC ASSESSMENT REPORT
152
0 32°55'5.29"S 27°54'20.90"E
0.25 32°55'12.99"S 27°54'24.24"E
0.5 32°55'20.71"S 27°54'27.34"E
0.75 32°55'28.48"S 27°54'30.34"E
1 32°55'36.21"S 27°54'33.25"E
1.25 32°55'44.10"S 27°54'35.98"E
1.5 32°55'51.93"S 27°54'38.70"E
1.75 32°55'59.76"S 27°54'41.43"E
2 32°56'7.48"S 27°54'44.70"E
2.25 32°56'15.12"S 27°54'48.23"E
2.5 32°56'22.74"S 27°54'51.74"E
2.75 32°56'30.36"S 27°54'55.28"E
3 32°56'37.98"S 27°54'58.76"E
3.25 32°56'43.58"S 27°55'5.70"E
3.5 32°56'48.86"S 27°55'9.74"E
3.75 32°56'56.27"S 27°55'12.87"E
4 32°56'56.60"S 27°55'20.16"E
4.25 32°56'57.98"S 27°55'27.29"E
Section C (Option C3)
km Longitude Latitude
0 32°55'5.29"S 27°54'20.90"E
0.25 32°55'4.56"S 27°54'30.64"E
0.5 32°55'3.79"S 27°54'40.28"E
0.75 32°55'7.63"S 27°54'48.61"E
1 32°55'14.57"S 27°54'52.49"E
1.25 32°55'21.80"S 27°54'54.64"E
1.5 32°55'29.55"S 27°54'56.99"E
1.75 32°55'34.69"S 27°55'3.38"E
2 32°55'38.23"S 27°55'12.06"E
2.25 32°55'41.71"S 27°55'20.83"E
2.5 32°55'45.17"S 27°55'29.58"E
2.75 32°55'45.99"S 27°55'39.13"E
3 32°55'45.77"S 27°55'48.88"E
3.25 32°55'45.96"S 27°55'58.44"E
3.5 32°55'50.60"S 27°56'5.77"E
3.75 32°55'47.13"S 27°56'13.52"E
4 32°55'51.08"S 27°56'18.61"E
4.25 32°55'58.90"S 27°56'20.64"E
4.5 32°56'7.01"S 27°56'20.88"E
4.75 32°56'15.12"S 27°56'20.94"E
5 32°56'22.73"S 27°56'20.68"E
5.25 32°56'29.45"S 27°56'15.25"E
5.5 32°56'32.83"S 27°56'7.12"E
5.75 32°56'31.71"S 27°55'57.69"E
6 32°56'32.69"S 27°55'48.27"E
6.25 32°56'38.97"S 27°55'43.86"E
6.5 32°56'46.63"S 27°55'42.09"E
BASIC ASSESSMENT REPORT
153
6.75 32°56'53.11"S 27°55'36.67"E
7 32°56'57.46"S 27°55'28.97"E
7.1 32°56'57.98"S 27°55'27.35"E
BASIC ASSESSMENT REPORT
154
Surveyor-General Codes Farm number Surveyor-general codes
F561/2 C02300000000056100002
F599/2 C02300000000059900002
F599/6 C02300000000059900006
F599/16 C02300000000059900016
F599/19 C02300000000059900019
F600/20 C02300000000060000020
F600/21 C02300000000060000021
F305/0 C02300000000030500000
F599/22 C02300000000059900022
F602/9 C02300000000060200009
F602/22 C02300000000060200022
F305/1 C02300000000030500001
F599/23 C02300000000059900023
F599/24 C02300000000059900024
F600/22 C02300000000060000022
F600/7 C02300000000060000007
F600/5 C02300000000060000005
F600/11 C02300000000060000011
F601/6 C02300000000060100006
F601/9 C02300000000060100009
F601/14 C02300000000060100014
F601/15 C02300000000060100015
F601/16 C02300000000060100016
F601/23 C02300000000060100023
F651/2 C02300000000065100002
F651/3 C02300000000065100003
F651/4 C02300000000065100004
F651/7 C02300000000065100007
F651/15 C02300000000065100015
F652/2 C02300000000065200002
F652/3 C02300000000065200003
F652/4 C02300000000065200004
F652/8 C02300000000065200008
F816/5 C02300000000081600005
F816/15 C02300000000081600015
F816/86 C02300000000081600086
F816/38 C02300000000081600038
F816/39 C02300000000081600039
F816/40 C02300000000081600040
F816/68 C02300000000081600068
F816/87 C02300000000081600087
F816/88 C02300000000081600088
F817/6 C02300000000081700006
F817/7 C02300000000081700007
F817/28 C02300000000081700028
F817/30 C02300000000081700030
F817/61 C02300000000081700061
F817/62 C02300000000081700062
F817/63 C02300000000081700063
BASIC ASSESSMENT REPORT
155
F817/64 C02300000000081700064
F817/65 C02300000000081700065
F817/102 C02300000000081700102
F817/103 C02300000000081700103
F817/104 C02300000000081700104
F818/0 C02300000000081800000
F819/0 C02300000000081900000
F821/1 C02300000000082100001
F821/4 C02300000000082100004
F821/5 C02300000000082100005
F821/6 C02300000000082100006
F821/9 C02300000000082100009
F821/10 C02300000000082100010
F821/11 C02300000000082100011
F821/12 C02300000000082100012
F821/14 C02300000000082100014
F821/15 C02300000000082100015
F821/16 C02300000000082100016
F821/17 C02300000000082100017
F821/18 C02300000000082100018
F821/19 C02300000000082100019
F821/20 C02300000000082100020
F821/21 C02300000000082100021
F821/22 C02300000000082100022
F821/23 C02300000000082100023
F821/24 C02300000000082100024
F821/25 C02300000000082100025
F821/26 C02300000000082100026
F821/27 C02300000000082100027
F821/28 C02300000000082100028
F821/29 C02300000000082100029
F821/37 C02300000000082100037
F821/38 C02300000000082100038
F821/39 C02300000000082100039
F821/40 C02300000000082100040
F821/41 C02300000000082100041
F821/35 C02300000000082100035
F821/36 C02300000000082100036
F600/9 C02300000000060000009
F600/16 C02300000000060000016
F651/5 C02300000000065100002
F816/92 C02300000000081600092
F600/4 C02300000000060000004
F600/3 C02300000000060000003
F652/7 C02300000000065200007
F599/0 C02300000000059900000
F601/2 C02300000000060100002
F652/5 C02300000000065200005
F821/13 C02300000000082100013
F816/74 C02300000000082100074
F817/84 C02300000000081700084
F817/29 C02300000000081700029
BASIC ASSESSMENT REPORT
156
F817/85 C02300000000081700085
F821/3 C02300000000082100003
F600/8 C02300000000060000008
F817/8 C02300000000081700008
F820/0 C02300000000082000000
F1237/0 C02300000000123700000
F1237/1 C02300000000123700001
F816/27 C02300000000081600027
F816/93 C02300000000081600093
F599/3 C02300000000059900003
F816/33 C02300000000081600033
F601/1 C02300000000060100001
F602/21 C02300000000060200021
F816/1 C02300000000081600001
F816/4 C02300000000081600004
F816/60 C02300000000081600060
F817/1 C02300000000081700001
F817/57 C02300000000081700057
F817/82 C02300000000081700082
F821/0 C02300000000082100000
F820/1 C02300000000082000001
F821/52 C02300000000082100052
F821/53 C02300000000082100053
F821/54 C02300000000082100054
F821/61 C02300000000082100061
F821/62 C02300000000082100062
F821/64 C02300000000082100064
F0/0 or F821/50 C02300000000082100050
F821/51 C02300000000082100051
F821/65 C02300000000082100065
F821/63 C02300000000082100063
F306/0 C02300000000030600000
F816/91 C02300000000081600091
F816/72 C02300000000081600072