52
BASIC ASSESSMENT REPORT 105 F599/19 Morning Mushrooms cc [email protected] PO Box 2307, Beacon Bay, 5205 (083)4507522 F600/20, F600/21, F305/0 Schwartz Family Trust [email protected] Hillview, P O Box 42, Homeleigh, 5212 (082)6524330 F599/22 Government [email protected] (082)5698627 F602/9, F602/22, F305/1 Amatola Water Private Bag X3, Vincent, 5217 (043)7073700 F599/23 Paul Jakobus van Heerden [email protected] P O Box 251, Cradock, 5880 (048)8813112 (084)5803490 F599/24 Leo Philip Geyer [email protected] P O Box 19722, Tecoma, 5214 (043)7210033 / (011)3951541 (083)2653360 F600/22 Peter Otto Wilhelm Vischer [email protected] (043)7307023 F600/7 Michael Wayne Anderson [email protected] P O Box 2556, Beacon Bay, 5205 (043)7210273 (083)7723767 / f(043)7210273 F600/5 Desmond Patrick Mildenhall P O Box 2180, Beacon Bay, 5205 (043)7307053 (082)9367303 F600/11 Janet Egelhof [email protected] P O Box 13059, Vincent, 5217 (043)7261028 / (043)7363207 (082)7186991 F601/6 Thomas Arthur Kretzmann [email protected] P O Box 617, East London (043)7222246 (083)6418811 F601/9 Wag-All 92 cc [email protected] P O Box 617, East London (043)7222246 (083)6418811 F601/14 Anton Lotter [email protected] P O Box 1127, East London, 5200 (043)7307120 (082)5551476 F601/15, F601/16, F816/15, F816/86 ESKOM Holdings LTD [email protected] (043)7032585 F816/91 ESKOM Holdings LTD [email protected] (043)7032104 F601/22 Donovan Michael Kretzmann [email protected] P O Box 3171, Cambridge, 5206 (043)7307123 / (043)7222246 (083)6297390 F601/23 TELKOM SA LTD [email protected] (082)8260004 F651/2, F651/3, F816/9, F816/5, F816/9, F816/68 Amatole District Municipality [email protected]; [email protected] (043)7832393/2 394

BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof [email protected] 5217 (043)7261028 / (043)7363207 (082)7186991

Embed Size (px)

Citation preview

Page 1: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

105

F599/19 Morning Mushrooms cc [email protected]

PO Box 2307, Beacon Bay, 5205 (083)4507522

F600/20, F600/21, F305/0 Schwartz Family Trust [email protected]

Hillview, P O Box 42, Homeleigh, 5212 (082)6524330

F599/22 Government [email protected] (082)5698627

F602/9, F602/22, F305/1 Amatola Water

Private Bag X3, Vincent, 5217 (043)7073700

F599/23 Paul Jakobus van Heerden [email protected]

P O Box 251, Cradock, 5880 (048)8813112 (084)5803490

F599/24 Leo Philip Geyer [email protected]

P O Box 19722, Tecoma, 5214

(043)7210033 / (011)3951541 (083)2653360

F600/22 Peter Otto Wilhelm Vischer [email protected] (043)7307023

F600/7 Michael Wayne Anderson [email protected]

P O Box 2556, Beacon Bay, 5205 (043)7210273

(083)7723767 / f(043)7210273

F600/5 Desmond Patrick Mildenhall

P O Box 2180, Beacon Bay, 5205 (043)7307053 (082)9367303

F600/11 Janet Egelhof [email protected]

P O Box 13059, Vincent, 5217

(043)7261028 / (043)7363207 (082)7186991

F601/6 Thomas Arthur Kretzmann [email protected] P O Box 617, East London (043)7222246 (083)6418811

F601/9 Wag-All 92 cc [email protected] P O Box 617, East London (043)7222246 (083)6418811

F601/14 Anton Lotter [email protected]

P O Box 1127, East London, 5200 (043)7307120 (082)5551476

F601/15, F601/16, F816/15, F816/86 ESKOM Holdings LTD [email protected] (043)7032585

F816/91 ESKOM Holdings LTD [email protected]

(043)7032104

F601/22 Donovan Michael Kretzmann [email protected]

P O Box 3171, Cambridge, 5206

(043)7307123 / (043)7222246 (083)6297390

F601/23 TELKOM SA LTD [email protected] (082)8260004 F651/2, F651/3, F816/9, F816/5, F816/9, F816/68

Amatole District Municipality

[email protected]; [email protected]

(043)7832393/2394

Page 2: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

106

F651/4, F651/13, F651/16, F651/23

Maureen Yvonne Oberem [email protected]

P O Box 13167, Cambridge, 5206

(043)7307060 / (043)7307060 (083)6510422

F651/7 Harold Frank Hughes [email protected] P O Box 2164, Beacon Bay, 5205 (043)7307110 0825953926

F651/12 B & GVW Prop CC [email protected]

P O Box 11153, Southernwood

(043)7265505 / (043)7263356

(082)9254380 / (083)2641507

F651/15 Bernadene Rhona Sternberg [email protected]

P O Box 3256, Cambridge, 5200 (043)7307121 (084)2094817

F652/2 All Craze 1050 cc [email protected] P O Box 2538, Beacon Bay (082)3746444

F652/3 Elizabeth Ann Whitelaw Broughton-Clarke [email protected]

P O Box 17, Homeleigh Halt, 5212 (083)2810037

F652/4 Garry Reginald Rogers [email protected]

P O Box 2024, Beacon Bay, 5205 (043)7307555 (082)4141703

F652/8 East London Child and Youth Care Centre [email protected] P O Box 313, East London (043)7260733 (082)2006353

F816/38 Daniel Barnard [email protected]

P O Box 2301, Beacon Bay, 5205 (043)7481160 (083)4558149

F816/39 Eleanora Joyce Walsh P O Box 14, Homeleigh, East London, 5211 (084)8421215

F816/40 Barry Arthur Neville [email protected]

P O Box 14, Homeleigh, 5212 (043)7484818 (082)6402801

F816/87 Jacobus Gerhard Saayman [email protected]

P O Box 2862, Beacon Bay, 5200

(043)7481936 / (043)7481936 (073)2426297

F816/88 BCMM [email protected] (043) 7052115 / 2507

F817/6 Kenneth David Frazier Cartwright [email protected]

P O Box 19251,Tecoma, 5214 (043)7354335 (082)5533709

F817/7 Lynette Esmay Esterhuyse [email protected]

(043)7321577 / (043)7321577 (082)5290732

F817/28 Saddle Path Props 59 PTY LTD [email protected] P O Box 13018, Vincent

(046)6540162 / (043)7433407

(082)5782320 / 0828093409

F817/30, F821/1 Colin Keith Salzwedel [email protected]; [email protected]

P O Box 2089, Beacon Bay, 5205

(043)7321172 / (043)7321722 (073)2462500

Page 3: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

107

F817/61 Amatole District Council [email protected]; [email protected]

(043)7832393/2394

F817/62 Erroll Mark Schonknecht [email protected] P O Box 526, Gonubie, 5256

(083)2723069 f (043)7438855

F817/63 Jacobus Gerhard Saayman [email protected]

P O Box 2862, Beacon Bay, 5200

(043)7481936 / (043)7481936 (073)2426297

F817/64 Izak Stephanus Coetsee [email protected]

7 Garden Street, Southernwood, East London, 5201

(043)7211020 / (043)7434340 (082)3272471

F817/65 Trevor Len Fraunstein

P O Box 3363, Cambridge, 5206

(083)3653832 /f (043)7267467

F817/102, F817/103 Kenneth David Frazier Cartwright [email protected]

P O Box 19251,Tecoma, 5214 (043)7354335 (082)5533709

F817/104 Wag-All 53 cc [email protected] P O Box 19451, Tecoma (043)7211121 (083)2662184

F818/0 Michael Frank du Toit [email protected]

Postnet , Private Bag X, Beacon Bay, (043)7321209 (082)5609990

F819/0 Azalea Holdings PTY LTD

[email protected]; [email protected]

P O Box 821, Northlands, 2116

(011)4937921 / (011)4937921

(083)3797453

F821/4 Build Props No 3 cc [email protected] P O Box 15700, Beacon Bay, East London (043)7321772 (082)9582653

F821/5 Helius Prop cc 71 Kloof Road Bedfordview 2008

F821/6 Milada Yvonne Burger [email protected]

P O Box 15050, Beacon Bay, North Coast House, 5205

(043)7321877 / (043)7321732 (082)8143765

F821/9 Simon Andrew Barker [email protected] P O Box 67, Gonubie, 5256 (043)7321666 (072)6363310

F821/10 Peggy Sheila Beard P O Box 13007, Vincent, 5217 (043)7221743

F821/11 Sapling Trade & INV 35 PTY LTD [email protected]

P O Box 19544, Tecoma, 5214 (043)7016900

F821/12 Desmond Neville & Paulina Naude Box 91, Homeleigh, 5212 (043)7311533 (083)9870849

Page 4: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

108

F821/14 Schuleeta Ann Lottering [email protected] (078)2396307

F821/15 Violet Zanele Barlow 3 Sable Place, Beacon Bay, 5241 (043)7483409

F821/16 Tom van der Vyver [email protected]

P O Box 2, Homeleigh, East London, 5212 (043)7307086 (083)9481168

F821/17 Ecopolymers cc [email protected]

P O Box 12311, Amalinda, East London (043)7420644 (083)4471482

F821/18 Mcklein Prop cc [email protected] P O Box 12485, Amalinda (043)7307365 / (043)7211711

(072)1537514 / (072)7974532

F821/19 Mohamed Moosajee [email protected]

P O Box 22931, Port Elizabeth, 6000

(041)5854938 / (041)5854938 (082)7816458

F821/20 Ashton Brian Harris [email protected]

P O Box 8146, Nahoon, 5241 (043)7221349 (084)5007080

F821/21 Valerie Ann Wood [email protected]; [email protected]

(043)7307374 / (043)7374258 (073)3037080

F821/22 Joseph Moses Reddy [email protected] P OBox 52849, Umtata, 5099

(047)5341956 / (047)5341956 (083)4453788

F821/23 Lawrence Robert Pohlman

P O Box 136, Homeleigh, 5212 (043)7093332

F821/24 Cyril Errol Naude P O Box 53, Homeleigh, 5212 (043)7631143

(083)3109913 f(043)7264565

F821/25 Deon Richard Coetzer [email protected]

P O Box 78, Homeleigh, 5212 (043)7321343 (082)7730261

F821/26 John Leonard Davies [email protected]

P O Box 17, Logan Drive, Nahoon, 5241 (043)7052880 (083)3216647

F821/27 Eric Fabian Clarke P O Box 198, Gonubie, 5256 (043)7321843 (072)1946264

F821/28 Petrus Philip Diedericks [email protected]

P O Box 2563,Beacon Bay 5205 (043)7321169 (083)2738825

F821/29 Patina Christina Bennett 278 Voortrekker Road, Eikendal, Kraaifonein, 7570 (021)9887965

F821/37 Paul van Heerden [email protected]

P O Box5190, Greenfields, 5208

(043)7321164 (083)2828546

Page 5: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

109

F821/38 Shane Michael Roach [email protected]

P O Box 2412, East London, 5200

(043)7321123 / 0437321123 (082)4537419

F821/39 James Mitford Thomson [email protected]; [email protected]

P O Box 2347 Beacon Bay, 5205 (043)7433585

F821/40 Ipoma Traders cc [email protected]

P O Box 15345, Beacon Bay, 5205 (082)7578551

F821/41 Allen Brian Lennard [email protected]

P O Box 2191, Beacon Bay, 5205

(043)7307339 / (043)7421641 (083)2549618

F821/35, F821/36 Rogers Yellow Woods Prop Trust [email protected] (043)7321133

F600/9 Andrew Bernard Levey [email protected]; [email protected]

P O Box 114, Homeleigh, East London, 5212 (043)7307310

(072)1795392 / (083)4002886

F600/16 Anthony Clarence Enslin [email protected]

P O Box 118, Homeleigh, 5212

(043)7307379 / (043)7482423 (082)0573273

F650/11 Patricia Richter [email protected]

P O Box 106, Homeleigh, 5212 (043)7116433 (083)3573292

F651/5 Malcolm William Pottinger

P O Box 13187, Vincent, 5217 (043)7264961

F816/92, F816/72 Errol Bryan Sangerhaus [email protected]

P O Box 352, East London, 5200

(043)7403221 / (043)7486006 (083)4596639

F600/4, F600/12 Graham Laird King [email protected]

P O Box 84, Homeleigh, 5212 (043)7307559 (078)3387346

F600/3 Sandra Joan Spence [email protected]

P O Box 869, East London, 5200

(043)7039885 / (043)7401085 (083)3205392

F652/7 Jiri Stanislav Koloman Kaps [email protected]

P O Box 2313, Beacon Bay, 5205 (043)7483589 (079)3887502

F599/0 R Kretzmann Trust P O Box 7449, East London, 5200 (043)7307011

(082)3187883 / f (043)7307059

F601/2 Valerie Yvonne Robinson [email protected]

P O Box 1665, East London, 5200 (043)7002345 (083)2751488

F652/5 M W Johnson Prop Trust [email protected]

P O Box 108, Homeleigh, 5212 (043)7307161 (082)6936555

Page 6: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

110

F821/13 Anne-Marie Grobbelaar 1 Kew Road, Vincent, 5217 (071)0612387

F816/74

East London Independent School Educational Trust [email protected]

P O Box 66, Homeleigh, 5212 (043)7486094

F817/84 Gerald & Vyvan Muller Family Trust [email protected]

P O Box 2062, Beacon Bay, 5205 (043)7482420

F817/29, F817/85 Walsh Prop Trust [email protected]

P O Box 2062, Beacon Bay, 5205 (043)7482420

F821/3 Norma Shirley Webber [email protected]

PO Box 2037, Beacon Bay, 5205 (043)7321392

F600/8 Tracey Lynn Blewett [email protected] Private Bag X8, Elarduspark, 0047 (012)3453154 (083)5111846

F817/8, F820/0, F1237/0, F1237/1, F816/27,F816/93, F816/72 Edcot Trust [email protected]

P O Box 1968, East London, 5200 (043)7071775 (078)0199858

F599/3 Hazel Aletta & Aubrey Victor Lugte

P O Box 2312, Beacon Bay, 5205 (043)7307155

F820/1 Edison Ndwayiza Makeba [email protected] (043)7424762/8

F816/33 Annette Spies [email protected]

(043)7115215

F816/4 Ntombomzi Felemu

56935 Mqokolo Street, Nompumelelo, Beacon Bay, East London, 5245

F816/4 T.N. Mhlwana

56935 Mqokolo Street, Nompumelelo, Beacon Bay, East London, 5245 (083)8918865

F816/4 Evelyn Mali

56934 Mqokolo Street, Nompumelelo, Beacon Bay, East London, 5245 (073)8621042

F816/60 Ntombomzi Sityeba

56933 Mqokolo Street, Nompumelelo, Beacon Bay, East London, 5246 (071)8358948

F816/61 Akhona Mabengwana 56914 Darling Street, Nompumelelo, Beacon Bay, (083)5531819

Page 7: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

111

East London, 5247

F816/62 No-Ande Bango

56912 Darling Street, Nompumelelo, Beacon Bay, East London, 5248 (083)7704542

Registered I&APs

Debbie Reynhardt [email protected] P.O. Box 49, Homeleigh, 5212 (043)7351528 (083)5088977

René Cathro [email protected] (033)3431130

Page 8: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

112

APPENDIX E6 COPIES OF CORRESPONDENCE SENT

Initial Notification Letter and Background Information Document sent to all Stakeholders and IA&Ps

Page 9: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

113

Background Information Document

Page 1 of BID

Page 10: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

114

Page 2 of BID

Page 11: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

115

Page 3 of BID

Page 12: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

116

Registered mail

Page 13: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

117

Page 14: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

118

Fax

Page 15: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

119

Page 16: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

120

Page 17: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

121

Proof of Notification sent: Emails

Page 18: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

122

Page 19: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

123

Page 20: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

124

Page 21: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

125

Page 22: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

126

RELEASE OF DRAFT BAR Letter sent to Registered I&APs concerning release of Draft BAR

Page 23: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

127

Email sent to all Stakeholders and IA&Ps concerning release of Draft BAR

Page 24: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

128

Page 25: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

129

Page 26: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

130

Page 27: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

131

Registered mail

Page 28: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

132

Fax

Page 29: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

133

Page 30: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

134

Page 31: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

135

Page 32: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

136

Page 33: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

137

Page 34: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

138

APPENDIX F

Impact Assessment

Impacts and mitigation of the Planning and Design phase of the Preferred Alternatives.

PLANNING AND DESIGN PHASE NATURE OF IMPACT

IMPACT DESCRIPTION

SPATIAL SCALE

TEMPORAL SCALE/ DURATION

CERTAINTY SCALE/ LIKELIHOOD

SEVERITY/ BENFICIAL SCALE

SIGNIFICANCE PRE-MITIGATION

MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION

GENERAL PLANNING AND DESIGN ISSUES

ALL ALTERNATIVES POLICY COMPLIANCE

Direct The pipeline route may not be consistent with relevant environmental policy and/or spatial guideline documents, (e.g. the alternative routes for the pipeline falls within CBA 2 in terms of ECBCP and within 32m of wetland).

Localised Permanent Possible Severe MODERATE NEGATIVE

The development must comply with relevant legislation and/or policy, e.g. ECBCP, Municipal By-laws, SDFs, etc.

LOW NEGATIVE

LAND OWNERSHIP AND SERVITUDE CONSTRAINTS

Direct The pipeline construction will inconvenience landowners.

Localised Permanent Possible Severe HIGH NEGATIVE

Prior to the start of the construction, servitude agreements must be in place and the areas to be directly impacted must be appropriately demarcated so that no undue impact is made on the surrounding environment.

LOW NEGATIVE

CONSIDERATION OF THE ENVIRONMENT

Direct/Indirect/Cumulative

Lack of environmental consideration in the route planning and inappropriate placement of the pipeline within sensitive systems along the length of the route.

Project level Permanent Possible Moderately severe

MODERATE NEGATIVE

Where feasible, the routing of the pipeline must be planned to avoid sensitive environments.

An independent Environmental Control Officer (ECO) must be appointed and must give input to the final layout.

Micro-siting of the final pipeline layout must be approved by the ECO.

LOW NEGATIVE

SOCIO-ECONOMIC

Direct Temporary job creation and skills development. Surrounding areas

Short Term Probable

Beneficial VERY BENEFICIAL

No mitigation. VERY BENEFICIAL

Direct

The local community will be provided with potable water.

Project Level Long Term Probable Beneficial VERY BENEFICIAL

No mitigation. VERY BENEFICIAL

PIPELINE MATERIALS

Direct/Indirect The use of inappropriate corrodible material for the pipeline could result in leakages and result in loss of the water resource.

Localised Long term Possible Severe MODERATE NEGATIVE

High quality design specifications (i.e. appointing a suitably qualified engineer) and materials (e.g. SABS approved) must be adopted for all elements of infrastructure design and installation.

LOW NEGATIVE

ACCESS ROADS

Direct/Indirect Access roads for construction and maintenance that are on steep slopes will lead to loss of vegetation and potential soil erosion.

Project level Short term Possible Moderately severe

MODERATE NEGATIVE

Where possible, all construction access roads and tracks must avoid steep slopes or sensitive environments.

LOW NEGATIVE

LANDSCAPE & VISUAL

Direct/Indirect/Cumulative

Aesthetic impacts of the pipeline on the currently open landscape.

Localised Long term Probable Moderate to slight

LOW The area must be re-vegetated with indigenous grasses.

Topsoil excavated on site must be retained and protected for use in landscaping of the area post-construction.

LOW

GEOLOGY & SOILS

Direct Installation of pipeline without taking into account the geology and soil structure along the proposed

Localised Long term Possible Moderately severe

MODERATE NEGATIVE

Unsuitable and unstable geological or soil structure must be avoided as far as possible.

LOW NEGATIVE

Page 35: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

139

PLANNING AND DESIGN PHASE NATURE OF IMPACT

IMPACT DESCRIPTION

SPATIAL SCALE

TEMPORAL SCALE/ DURATION

CERTAINTY SCALE/ LIKELIHOOD

SEVERITY/ BENFICIAL SCALE

SIGNIFICANCE PRE-MITIGATION

MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION

line may result in unnecessary soil erosion and/or damage to geological formations.

ECOLOGY

Direct Permanent loss of thicket vegetation due to pipeline routing.

Localised Permanent Definite Moderately severe

MODERATE NEGATIVE

Construction activities must be limited to the pipeline route.

LOW NEGATIVE

Direct/Indirect The pipeline could result in permanent physical loss of wetlands in the area without proper planning.

Localised Long term Possible Moderately severe

HIGH The project layout must be planned to ensure that a buffer zone of 32 metres is maintained and that no development activities occur within watercourses.

Authorisation from DWA must be obtained if any construction footprint takes place inside or within 32 meters of any water body.

LOW

HERITAGE AND PALEONTOLOGY

Direct The heritage and paleontological heritage of the area may be impacted by the pipeline routing.

Localised Long term Possible Moderately severe

MODERATE NEGATIVE

The recommended management measures from the Phase 1 Heritage assessment must be incorporated in the final planning and design for the pipeline construction (See Appendix D1 for Heritage Impact Assessment Report).

LOW NEGATIVE

SOIL EROSION

Direct/Indirect The placement of the pipeline on steep slopes may require vegetation clearing and result in significant soil erosion.

Project level Long term Possible Severe MODERATE NEGATIVE

Construction activities must not be located on slopes steeper than 1:6.

Appropriate stormwater routing and attenuation must be implemented to avoid onsite erosion and downstream sedimentation.

LOW NEGATIVE

OPTION A1 (River crossing, north route) Same as the General PLANNING AND DESIGN impacts above; IN ADDITION:

RIVER CROSSING

Direct/Indirect Without proper planning, the pipeline could result in damage to the Nahoon River.

Localised Medium to long term

Possible Severe HIGH The pipeline layout must be planned to ensure that watercourses are not disturbed or damaged.

Water courses within 32 meters of the route must be demarcated and must not be accessible during construction.

All trenches dug within 32 meters of any water courses must be rehabilitated in full.

No work camp or any other temporary construction infrastructure shall be erected within 32 meters of any water body.

Where necessary, water use licenses should be obtained from the Department of Water Affairs for impeding/diverting flow of water.

LOW

OPTION B2 (south of N6) TRAFFIC

Direct/Indirect The N6 is the most direct route between Stutterheim/Queenstown and East London. Construction along this route with cause increased traffic congestion.

Project level Short to medium term

Possible Slight LOW Project planning with BCMM must include adequate measures to avoid traffic congestion during construction phase of the pipeline.

LOW

OPTION C1 (along N6) Same as B2.

OPTION C2 (east of N6) STREAM CROSSING

Page 36: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

140

PLANNING AND DESIGN PHASE NATURE OF IMPACT

IMPACT DESCRIPTION

SPATIAL SCALE

TEMPORAL SCALE/ DURATION

CERTAINTY SCALE/ LIKELIHOOD

SEVERITY/ BENFICIAL SCALE

SIGNIFICANCE PRE-MITIGATION

MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION

Direct/Indirect Inappropriate disturbance and modification to streams during construction may lead to hydrological changes.

Localised Medium term Possible Severe HIGH NEGATIVE

Construction on any crossings must comply with the EMPr approved by Department of Water Affairs and Department of Environmental Affairs.

Construction on stream crossings must be done under the supervision of the ECO.

MODERATE NEGATIVE

OPTION C3 (far east of N6) Same as C2.

Impacts and mitigation of the Construction phase of the Preferred Alternative.

CONSTRUCTION PHASE NATURE OF IMPACT

IMPACT DESCRIPTION

SPATIAL SCALE

TEMPORAL SCALE/ DURATION

CERTAINTY SCALE/ LIKELIHOOD

SEVERITY/ BENFICIAL SCALE

SIGNIFICANCE PRE-MITIGATION

MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION

GENERAL CONSTRUCTION ISSUES

ALL ALTERNATIVES NOISE POLLUTION

Direct Noise pollution caused during construction could potentially be a nuisance to neighbouring residential areas and businesses along the pipeline route.

Localised Short term Possible Moderately Severe

MODERATE NEGATIVE

Construction activities and movement of construction vehicles must be limited to the hours 08:00am – 17:00pm.

LOW NEGATIVE

DUST

Direct Dust (air) pollution caused by digging and levelling of exposed soil can cause a nuisance to neighbouring areas and businesses along the pipeline route.

Localised Short term Probable Severe MODERATE NEGATIVE

Cleared surfaces must be dampened whenever possible and especially in dry and windy conditions to avoid excessive dust generation.

Any soil excavated, and not utilised for rehabilitation, must be removed from site or covered and no large mounds of soil should be left behind after construction.

LOW NEGATIVE

HAZARDOUS SUBSTANCE USAGE

Direct Cement, tar and bitumen mixing techniques and diesel/oil spillage occurring as a result of poorly maintained machinery can contaminate the surrounding environment (soil, surface/groundwater).

Localised Long term Possible Severe MODERATE NEGATIVE

Hazardous Chemical Substances Regulations promulgated in terms of the Occupational Health & Safety Act 85 of 199. And the SABS Code of Practice must be adhered to. This applies to solvents and other chemicals possibly used in the construction process.

Oil trays must be placed under the machinery to avoid soil contamination. All areas affected during the Construction Phase should be rehabilitated.

CONCRETE BATCHING

Concrete should not be mixed directly on the ground, or during rainfall events when the potential for transport to the stormwater system is the greatest (as per the EMPr).

Concrete must be mixed only in the area demarcated for this purpose and on an impermeable substratum.

All areas affected during the Construction Phase must be rehabilitated.

HAZARDOUS CHEMICAL STORAGE

All hazardous chemicals must be properly stored in a

LOW NEGATIVE

Page 37: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

141

CONSTRUCTION PHASE NATURE OF IMPACT

IMPACT DESCRIPTION

SPATIAL SCALE

TEMPORAL SCALE/ DURATION

CERTAINTY SCALE/ LIKELIHOOD

SEVERITY/ BENFICIAL SCALE

SIGNIFICANCE PRE-MITIGATION

MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION

secure bunded and contained area.

Staff that will be handling hazardous materials must be trained.

WORKER HEALTH AND SAFETY

Direct Destruction of sensitive vegetation due to uncontrolled wood collection.

Localised

Long term Possible

Severe

MODERATE NEGATIVE

No illegal firewood collection shall be allowed and must be monitored by the Environmental Site Officer.

LOW NEGATIVE

Direct Inadequate attention to fire safety awareness and fire safety equipment could result in unsafe working environment and wider ecological and social damage (loss of crops and property).

Localised

Short term Possible Severe HIGH NEGATIVE

The Contractor must have operational fire-fighting equipment available onsite at all times.

All construction foremen must be trained in fire hazard control and fire fighting techniques.

All flammable substances must be stored in dry areas which do not pose an ignition risk to the said substances.

No open fires must be allowed onsite unless in a demarcated area identified by the ECO.

No smoking must be allowed near flammable substances.

Cooking must be done in demarcated areas that are safe and would not cause runaway or uncontrolled fires.

Construction waste or debris must not be burnt onsite.

MODERATE NEGATIVE

Direct Failure to provide adequate onsite sanitation may result in runoff transferring contaminants into the surrounding environment.

Localised

Short term Possible

Moderately severe

MODERATE NEGATIVE

Onsite sanitation facilities must be provided and construction workers must be informed not to use the surrounding environment.

The facilities must be regularly serviced to reduce the risk of surface or groundwater pollution.

Contaminated wastewater must be managed by the Contractor to ensure existing water resources on the site are not contaminated. All wastewater from general activities in the camp must be collected and removed from the site for appropriate disposal at a licensed commercial facility.

LOW NEGATIVE

WASTE MANAGEMENT

Direct Littering on site may detract from the visual appeal of the area, and pollute the surrounding areas.

Localised

Short term

Possible

Moderately severe

MODERATE NEGATIVE

All rubble and refuse must be collected and disposed of at Roundhill licenced landfill site.

Littering by the employees of the Contractor must not be allowed under any circumstances. The ECO shall monitor the neatness of the work sites as well as the Contractor campsite.

An environmental management programme incorporating waste management issues during the construction phase of the project has been developed and must be implemented.

LOW NEGATIVE

Direct Increased risk of inadequate waste disposal resulting in pollution of environment

Localised

Long term Possible Severe MODERATE NEGATIVE

All excess waste must be disposed of at Roundhill licensed landfill site.

LOW NEGATIVE

SOCIO-ECONOMIC

Direct/Indirect Increase in job creation during the construction phase

Surrounding area

Medium term Probable Beneficial HIGH POSITIVE Surrounding communities must be hired for construction to provide a beneficial impact on the local economy.

HIGH POSITIVE

TRAFFIC

Direct/Indirect Construction vehicles could cause traffic congestion especially if temporary road closures

Localised Short term Possible Moderately severe

MODERATE During construction, adequate measures to limit traffic congestion must be implemented.

LOW

Page 38: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

142

CONSTRUCTION PHASE NATURE OF IMPACT

IMPACT DESCRIPTION

SPATIAL SCALE

TEMPORAL SCALE/ DURATION

CERTAINTY SCALE/ LIKELIHOOD

SEVERITY/ BENFICIAL SCALE

SIGNIFICANCE PRE-MITIGATION

MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION

are required.

LOSS OF BIODIVERSITY

Direct Excessive damage to surrounding biodiversity due to vehicular movement and unrestricted construction activities.

Localised Short term Definite Moderately severe

MODERATE NEGATIVE

Construction activities must be restricted within the proposed pipeline route.

And ECO must be on site at least twice a week during construction to monitor construction activities.

LOW NEGATIVE

STORM WATER MANAGEMENT

Direct Uncontrolled stormwater during construction can disperse spillage or leaking of diesel, lubricant and cement and sediment from excavated ground material contaminating the surrounding environment.

Localised Long term Probable Severe HIGH NEGATIVE

Adequate provision must be made to manage stormwater during construction.

LOW NEGATIVE

SOIL EROSION

Indirect Soil erosion on steep slopes due to disturbance of highly erosive soils and poor rehabilitation

Project level Medium to long term

Possible Severe HIGH Construction sites must be stabilised and soil must be prevented from unnecessary exposure.

Vegetation re-establishment must be implemented as part of a detailed Rehabilitation Plan.

MODERATE

OPTION A1 (River crossing, north route) RIVER CROSSING

Direct Construction activities (e.g. bulldozers, rubble) of a pipeline across the Nahoon River increase the risk of damage to sensitive river ecosystems.

Project level Medium term Definite Moderately severe

MODERATE NEGATIVE

All construction rubble must be removed from all rivers and streams after completion of work.

The river/stream must be returned to its natural state after construction.

LOW NEGATIVE

OPTION B2 Same as the General CONSTRUCTION impacts above.

OPTION C1 Same as the General CONSTRUCTION impacts above.

OPTION C2 STREAM CROSSING

Direct Damage and loss of streams due to construction activities close to or in the streams.

Localised Short term Possible Moderately severe

MODERATE A buffer zone of 32 metres must be maintained. No development activities may occur without prior approval by the DWA.

LOW

OPTION C3 Same as C2.

Impacts and mitigation of the Operational phase of the Preferred Alternative.

OPERATIONAL PHASE NATURE OF IMPACT

IMPACT DESCRIPTION

SPATIAL SCALE

TEMPORAL SCALE/ DURATION

CERTAINTY SCALE/ LIKELIHOOD

SEVERITY/ BENFICIAL SCALE

SIGNIFICANCE PRE-MITIGATION

MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION

GENERAL OPERATIONAL ISSUES

ALL ALTERNATIVES MAINTENANCE

Direct Non-compliance with a pipeline maintenance schedule could result in leaks going undetected.

Surrounding areas

Medium term Possible Moderately severe

MODERATE NEGATIVE

Pipelines must be regularly monitored for leaks. If these are identified or reported by the public, immediate actions must be taken to remedy the situation.

LOW NEGATIVE

Page 39: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

143

OPERATIONAL PHASE NATURE OF IMPACT

IMPACT DESCRIPTION

SPATIAL SCALE

TEMPORAL SCALE/ DURATION

CERTAINTY SCALE/ LIKELIHOOD

SEVERITY/ BENFICIAL SCALE

SIGNIFICANCE PRE-MITIGATION

MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION

Direct/Indirect Disturbance of vegetation due to on-going utilisation of service roads could initiate erosion events.

Localised Short term Possible Moderately severe

HIGH NEGATIVE

Service roads must avoid creating permanent tracks. Monitor for erosion and rehabilitate if necessary.

MODERATE NEGATIVE

INCREASED STORM WATER RUNOFF

Direct Failure to maintain the storm water system could increase the risk of surface water damage to the landscape and vegetation due to increased runoff.

Surrounding areas

Long term Possible Moderately severe

HIGH NEGATIVE

A Storm Water Management Plan must be implemented.

Vegetation must be retained where possible to avoid soil erosion.

MODERATE NEGATIVE

SOCIO-ECONOMIC

Direct/Indirect/Cumulative

Water availability will result in increased housing development.

Surrounding areas

Long term Definite Highly beneficial

BENEFICIAL No mitigation provided. BENEFICIAL

NO-GO

NATURE OF IMPACT

IMPACT DESCRIPTION

SPATIAL SCALE

TEMPORAL SCALE/ DURATION

CERTAINTY SCALE/ LIKELIHOOD

SEVERITY/ BENFICIAL SCALE

SIGNIFICANCE PRE-MITIGATION

MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION

Direct/ Indirect

The no-go option for development entails that the proposed pipeline will not go ahead. There would be a lost opportunity for socio-economic benefits in terms of an improved water supply, job creation, and the provision of housing units.

Localised Long term Probable Moderately severe

MODERATE No mitigation required. MODERATE

Page 40: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

144

APPENDIX G Environmental Management Programme (EMPr)

Page 41: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

145

APPENDIX H Details of EAP and expertise

Environmental Consulting Company: Coastal & Environmental Services 16 Tyrell Road, Berea, East London PO Box 8145, Nahoon, East London, 5210 Tel: 043 726 7809/8313 Fax: (043) 726 8352 e-mail: [email protected] www.cesnet.co.za Environmental Assessment Practitioners working on this project:

Dr Alan Carter

Dr Greer Hawley

Mr Roy de Kock

Ms Daisy Kotsedi In fulfilment of this requirement Coastal and Environmental Services (CES) wishes to point to the following expertise of the study team, which includes Dr Alan Carter (Director), , Dr Greer Hawley (Principal Environmental Consultant), Mr Roy de Kock (Senior Environmental Consultant), Ms Daisy Kotsedi (Environmental Consultant) and CES as a consulting firm: Coastal & Environmental Services (CES), established in 1990, is a specialist environmental consulting company based in Grahamstown (Eastern Cape Province). We believe that a balance between development and environmental protection can be achieved by skilful, considerate and careful planning. CES has considerable experience in terrestrial, marine and freshwater ecology, the Social Impact Assessment (SIA) process, and state of environment reporting (SOER), Integrated Waste Management Plans (IWMP), Spatial Development Frameworks (SDF), public participation, as well as the management and co-ordination of all aspects of the Environmental Impact Assessment (EIA) and Strategic Environmental Assessment (SEA) processes. CES has been active in all of the above fields, and in so doing have made a positive contribution to towards environmental management and sustainable development in the Eastern Cape, South Africa and many other African countries. Dr Alan Carter is a Director at CES, holds a PhD in Marine Biology and is a certified Public Accountant, with extensive training and experience in both financial accounting and environmental science disciplines with international accounting firms in South Africa and the USA. He has 15 years’ experience in environmental management and has specialist skills in sanitation, coastal environments and industrial waste. Dr Carter is registered as a Professional Natural Scientist under the South African Council for Natural Scientific Professions (SACNASP).

Page 42: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

146

Dr Greer Hawley (Principal Environmental Consultant) has a BSc degree in Botany and Zoology and a BSc Honours in Botany from the University of Cape Town. She completed her PhD thesis (Microbiology) at Rhodes University. Greer has been involved in a number of diverse activities. The core academic focus has been directed in the field of taxonomy both in the plant and fungal kingdom. Greer’s research ranges from studying fresh and marine algae, estuarine diatoms, Restio species classification in the fynbos and forest vegetation and fungal species identification and ecology. Greer’s study of fungi have also contributed towards an understanding of soil ecology and “below ground” ecology. She is currently working on numerous impact assessments at the East London branch. Registration: South African Society for Microbiology, South African Association of Botany.

Page 43: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

147

Mr Roy de Kock (Senior Environmental Consultant) holds a BSc Honours in Geology and an MSc in Botany from the Nelson Mandela Metropolitan University in Port Elizabeth. His MSc thesis focussed on Rehabilitation Ecology with the focus on Mine Rehabilitation. He has been working for CES since 2010, and is based at the East London branch where he focuses on ecological impact assessments, geological and hydro geological analysis, environmental management plans and various environmental impact studies. Roy is registered as a Candidate Natural Scientist under SACNASP. Ms Daisy Kotsedi (Environmental Consultant) has a BSc. Honours and MSc degree in Botany both from Nelson Mandela Metropolitan University in Port Elizabeth. Her MSc thesis focused on the effects of environmental factors on microalgal biomass and community composition in the Sundays River Estuary. Daisy’s research interests include a broad range of environmental conservation and estuarine ecology with the main focus on microalgae. Daisy worked as an intern at WWF-SA in the freshwater unit in 2011. She is currently employed in the East London office of CES. Daisy is registered as a Candidate Natural Scientist under SACNASP.

Page 44: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

148

APPENDIX I Specialist’s declaration of interest

Page 45: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

149

APPENDIX J Additional Information

GPS co-ordinates taken every 250 meters along the route for each alternative pipeline

Section A (Option A1)

km Longitude Latitude

0 32°54'13.57"S 27°48'34.71"E

0.25 32°54'6.66"S 27°48'38.64"E

0.5 32°54'12.28"S 27°48'45.58"E

0.75 32°54'17.58"S 27°48'52.85"E

1 32°54'21.34"S 27°48'58.42"E

1.25 32°54'21.54"S 27°49'8.07"E

1.5 32°54'16.55"S 27°49'12.64"E

1.75 32°54'8.68"S 27°49'14.67"E

2 32°54'10.69"S 27°49'23.67"E

2.25 32°54'6.32"S 27°49'30.54"E

2.5 32°54'8.87"S 27°49'37.33"E

2.75 32°54'8.39"S 27°49'44.24"E

3 32°54'7.23"S 27°49'53.58"E

3.25 32°54'5.35"S 27°50'2.90"E

3.5 32°54'6.04"S 27°50'11.87"E

3.75 32°54'13.37"S 27°50'15.34"E

4 32°54'11.85"S 27°50'22.52"E

4.25 32°54'5.61"S 27°50'28.61"E

4.5 32°54'4.89"S 27°50'39.12"E

4.75 32°54'1.26"S 27°50'47.23"E

5 32°53'55.42"S 27°50'53.93"E

5.25 32°53'51.51"S 27°51'1.91"E

5.5 32°53'46.11"S 27°51'9.01"E

5.75 32°53'42.05"S 27°51'16.69"E

6 32°53'43.45"S 27°51'22.66"E

Section A (Option A2)

km Longitude Latitude

0 32°54'13.57"S 27°48'34.71"E

0.25 32°54'6.66"S 27°48'38.64"E

0.5 32°54'12.28"S 27°48'45.58"E

0.75 32°54'17.58"S 27°48'52.85"E

1 32°54'21.34"S 27°48'58.42"E

1.25 32°54'21.54"S 27°49'8.07"E

1.5 32°54'21.74"S 27°49'17.53"E

1.75 32°54'21.93"S 27°49'27.14"E

2 32°54'20.60"S 27°49'34.75"E

2.25 32°54'12.92"S 27°49'36.06"E

2.5 32°54'8.58"S 27°49'43.63"E

2.75 32°54'7.27"S 27°49'52.94"E

Page 46: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

150

3 32°54'5.54"S 27°50'2.25"E

3.25 32°54'5.66"S 27°50'11.29"E

3.5 32°54'12.79"S 27°50'15.28"E

3.75 32°54'12.28"S 27°50'22.07"E

4 32°54'5.91"S 27°50'28.08"E

4.25 32°54'4.81"S 27°50'37.40"E

4.5 32°54'2.29"S 27°50'45.98"E

4.75 32°53'56.63"S 27°50'52.81"E

5 32°53'52.00"S 27°51'0.23"E

5.25 32°53'47.17"S 27°51'7.82"E

5.5 32°53'41.97"S 27°51'15.04"E

5.75 32°53'43.45"S 27°51'22.66"E

Section B (Option B1)

km Longitude Latitude

0 32°53'43.45"S 27°51'22.66"E

0.25 32°53'35.91"S 27°51'22.85"E

0.5 32°53'40.31"S 27°51'27.55"E

0.75 32°53'47.38"S 27°51'32.38"E

1 32°53'54.49"S 27°51'37.10"E

1.25 32°54'1.30"S 27°51'42.10"E

1.5 32°54'0.94"S 27°51'51.75"E

1.75 32°54'0.64"S 27°52'1.50"E

2 32°54'0.36"S 27°52'11.20"E

2.25 32°53'59.98"S 27°52'20.82"E

2.5 32°53'59.46"S 27°52'30.51"E

2.75 32°53'58.27"S 27°52'40.04"E

3 32°53'57.17"S 27°52'49.62"E

3.25 32°53'55.97"S 27°52'59.20"E

3.5 32°53'57.01"S 27°53'7.95"E

3.75 32°54'3.78"S 27°53'13.27"E

4 32°54'10.38"S 27°53'18.95"E

4.25 32°54'16.75"S 27°53'25.01"E

4.5 32°54'22.92"S 27°53'31.33"E

4.75 32°54'29.20"S 27°53'37.42"E

5 32°54'35.19"S 27°53'43.93"E

5.25 32°54'40.78"S 27°53'50.97"E

5.5 32°54'46.72"S 27°53'57.62"E

5.75 32°54'52.00"S 27°54'4.98"E

6 32°54'56.28"S 27°54'13.28"E

6.25 32°55'2.72"S 27°54'19.00"E

6.5 32°55'5.29"S 27°54'20.90"E

Section B (Option B2)

km Longitude Latitude

0 32°53'43.45"S 27°51'22.66"E

0.25 32°53'51.02"S 27°51'25.82"E

Page 47: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

151

0.5 32°53'58.09"S 27°51'30.55"E

0.75 32°54'3.92"S 27°51'36.94"E

1 32°54'8.63"S 27°51'44.79"E

1.25 32°54'13.24"S 27°51'52.62"E

1.5 32°54'18.97"S 27°51'59.11"E

1.75 32°54'19.20"S 27°52'8.74"E

2 32°54'19.52"S 27°52'18.38"E

2.25 32°54'19.92"S 27°52'28.03"E

2.5 32°54'15.33"S 27°52'34.09"E

2.75 32°54'15.39"S 27°52'43.73"E

3 32°54'15.38"S 27°52'53.37"E

3.25 32°54'15.41"S 27°53'3.01"E

3.5 32°54'15.81"S 27°53'12.66"E

3.75 32°54'18.85"S 27°53'21.52"E

4 32°54'24.15"S 27°53'28.77"E

4.25 32°54'31.20"S 27°53'33.49"E

4.5 32°54'38.95"S 27°53'36.39"E

4.75 32°54'46.26"S 27°53'40.41"E

5 32°54'51.54"S 27°53'47.61"E

5.25 32°54'54.24"S 27°53'56.69"E

5.5 32°54'54.72"S 27°54'6.33"E

5.75 32°54'59.26"S 27°54'14.07"E

6 32°55'5.62"S 27°54'16.98"E

Section C (Option C1)

km Longitude Latitude

0 32°55'5.62"S 27°54'16.98"E

0.25 32°55'13.46"S 27°54'19.82"E

0.5 32°55'21.13"S 27°54'22.95"E

0.75 32°55'28.85"S 27°54'26.09"E

1 32°55'36.48"S 27°54'29.37"E

1.25 32°55'44.13"S 27°54'32.41"E

1.5 32°55'52.20"S 27°54'33.51"E

1.75 32°56'0.33"S 27°54'33.05"E

2 32°56'8.28"S 27°54'31.60"E

2.25 32°56'16.23"S 27°54'31.90"E

2.5 32°56'22.29"S 27°54'38.05"E

2.75 32°56'26.24"S 27°54'46.49"E

3 32°56'32.38"S 27°54'52.20"E

3.25 32°56'40.30"S 27°54'54.60"E

3.5 32°56'45.85"S 27°55'1.46"E

3.75 32°56'50.24"S 27°55'9.45"E

4 32°56'57.84"S 27°55'11.35"E

4.25 32°56'56.56"S 27°55'20.45"E

4.5 32°56'57.95"S 27°55'27.28"E

Section C (Option C2)

km Longitude Latitude

Page 48: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

152

0 32°55'5.29"S 27°54'20.90"E

0.25 32°55'12.99"S 27°54'24.24"E

0.5 32°55'20.71"S 27°54'27.34"E

0.75 32°55'28.48"S 27°54'30.34"E

1 32°55'36.21"S 27°54'33.25"E

1.25 32°55'44.10"S 27°54'35.98"E

1.5 32°55'51.93"S 27°54'38.70"E

1.75 32°55'59.76"S 27°54'41.43"E

2 32°56'7.48"S 27°54'44.70"E

2.25 32°56'15.12"S 27°54'48.23"E

2.5 32°56'22.74"S 27°54'51.74"E

2.75 32°56'30.36"S 27°54'55.28"E

3 32°56'37.98"S 27°54'58.76"E

3.25 32°56'43.58"S 27°55'5.70"E

3.5 32°56'48.86"S 27°55'9.74"E

3.75 32°56'56.27"S 27°55'12.87"E

4 32°56'56.60"S 27°55'20.16"E

4.25 32°56'57.98"S 27°55'27.29"E

Section C (Option C3)

km Longitude Latitude

0 32°55'5.29"S 27°54'20.90"E

0.25 32°55'4.56"S 27°54'30.64"E

0.5 32°55'3.79"S 27°54'40.28"E

0.75 32°55'7.63"S 27°54'48.61"E

1 32°55'14.57"S 27°54'52.49"E

1.25 32°55'21.80"S 27°54'54.64"E

1.5 32°55'29.55"S 27°54'56.99"E

1.75 32°55'34.69"S 27°55'3.38"E

2 32°55'38.23"S 27°55'12.06"E

2.25 32°55'41.71"S 27°55'20.83"E

2.5 32°55'45.17"S 27°55'29.58"E

2.75 32°55'45.99"S 27°55'39.13"E

3 32°55'45.77"S 27°55'48.88"E

3.25 32°55'45.96"S 27°55'58.44"E

3.5 32°55'50.60"S 27°56'5.77"E

3.75 32°55'47.13"S 27°56'13.52"E

4 32°55'51.08"S 27°56'18.61"E

4.25 32°55'58.90"S 27°56'20.64"E

4.5 32°56'7.01"S 27°56'20.88"E

4.75 32°56'15.12"S 27°56'20.94"E

5 32°56'22.73"S 27°56'20.68"E

5.25 32°56'29.45"S 27°56'15.25"E

5.5 32°56'32.83"S 27°56'7.12"E

5.75 32°56'31.71"S 27°55'57.69"E

6 32°56'32.69"S 27°55'48.27"E

6.25 32°56'38.97"S 27°55'43.86"E

6.5 32°56'46.63"S 27°55'42.09"E

Page 49: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

153

6.75 32°56'53.11"S 27°55'36.67"E

7 32°56'57.46"S 27°55'28.97"E

7.1 32°56'57.98"S 27°55'27.35"E

Page 50: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

154

Surveyor-General Codes Farm number Surveyor-general codes

F561/2 C02300000000056100002

F599/2 C02300000000059900002

F599/6 C02300000000059900006

F599/16 C02300000000059900016

F599/19 C02300000000059900019

F600/20 C02300000000060000020

F600/21 C02300000000060000021

F305/0 C02300000000030500000

F599/22 C02300000000059900022

F602/9 C02300000000060200009

F602/22 C02300000000060200022

F305/1 C02300000000030500001

F599/23 C02300000000059900023

F599/24 C02300000000059900024

F600/22 C02300000000060000022

F600/7 C02300000000060000007

F600/5 C02300000000060000005

F600/11 C02300000000060000011

F601/6 C02300000000060100006

F601/9 C02300000000060100009

F601/14 C02300000000060100014

F601/15 C02300000000060100015

F601/16 C02300000000060100016

F601/23 C02300000000060100023

F651/2 C02300000000065100002

F651/3 C02300000000065100003

F651/4 C02300000000065100004

F651/7 C02300000000065100007

F651/15 C02300000000065100015

F652/2 C02300000000065200002

F652/3 C02300000000065200003

F652/4 C02300000000065200004

F652/8 C02300000000065200008

F816/5 C02300000000081600005

F816/15 C02300000000081600015

F816/86 C02300000000081600086

F816/38 C02300000000081600038

F816/39 C02300000000081600039

F816/40 C02300000000081600040

F816/68 C02300000000081600068

F816/87 C02300000000081600087

F816/88 C02300000000081600088

F817/6 C02300000000081700006

F817/7 C02300000000081700007

F817/28 C02300000000081700028

F817/30 C02300000000081700030

F817/61 C02300000000081700061

F817/62 C02300000000081700062

F817/63 C02300000000081700063

Page 51: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

155

F817/64 C02300000000081700064

F817/65 C02300000000081700065

F817/102 C02300000000081700102

F817/103 C02300000000081700103

F817/104 C02300000000081700104

F818/0 C02300000000081800000

F819/0 C02300000000081900000

F821/1 C02300000000082100001

F821/4 C02300000000082100004

F821/5 C02300000000082100005

F821/6 C02300000000082100006

F821/9 C02300000000082100009

F821/10 C02300000000082100010

F821/11 C02300000000082100011

F821/12 C02300000000082100012

F821/14 C02300000000082100014

F821/15 C02300000000082100015

F821/16 C02300000000082100016

F821/17 C02300000000082100017

F821/18 C02300000000082100018

F821/19 C02300000000082100019

F821/20 C02300000000082100020

F821/21 C02300000000082100021

F821/22 C02300000000082100022

F821/23 C02300000000082100023

F821/24 C02300000000082100024

F821/25 C02300000000082100025

F821/26 C02300000000082100026

F821/27 C02300000000082100027

F821/28 C02300000000082100028

F821/29 C02300000000082100029

F821/37 C02300000000082100037

F821/38 C02300000000082100038

F821/39 C02300000000082100039

F821/40 C02300000000082100040

F821/41 C02300000000082100041

F821/35 C02300000000082100035

F821/36 C02300000000082100036

F600/9 C02300000000060000009

F600/16 C02300000000060000016

F651/5 C02300000000065100002

F816/92 C02300000000081600092

F600/4 C02300000000060000004

F600/3 C02300000000060000003

F652/7 C02300000000065200007

F599/0 C02300000000059900000

F601/2 C02300000000060100002

F652/5 C02300000000065200005

F821/13 C02300000000082100013

F816/74 C02300000000082100074

F817/84 C02300000000081700084

F817/29 C02300000000081700029

Page 52: BASIC ASSESSMENT REPORT - EOH Coastal and … Dam East Coast Bulk Water... · 2017-06-13 · F600/11 Janet Egelhof janet.egelhof@defy.co.za 5217 (043)7261028 / (043)7363207 (082)7186991

BASIC ASSESSMENT REPORT

156

F817/85 C02300000000081700085

F821/3 C02300000000082100003

F600/8 C02300000000060000008

F817/8 C02300000000081700008

F820/0 C02300000000082000000

F1237/0 C02300000000123700000

F1237/1 C02300000000123700001

F816/27 C02300000000081600027

F816/93 C02300000000081600093

F599/3 C02300000000059900003

F816/33 C02300000000081600033

F601/1 C02300000000060100001

F602/21 C02300000000060200021

F816/1 C02300000000081600001

F816/4 C02300000000081600004

F816/60 C02300000000081600060

F817/1 C02300000000081700001

F817/57 C02300000000081700057

F817/82 C02300000000081700082

F821/0 C02300000000082100000

F820/1 C02300000000082000001

F821/52 C02300000000082100052

F821/53 C02300000000082100053

F821/54 C02300000000082100054

F821/61 C02300000000082100061

F821/62 C02300000000082100062

F821/64 C02300000000082100064

F0/0 or F821/50 C02300000000082100050

F821/51 C02300000000082100051

F821/65 C02300000000082100065

F821/63 C02300000000082100063

F306/0 C02300000000030600000

F816/91 C02300000000081600091

F816/72 C02300000000081600072