Baseline Reconsultation Timeline
17-08-07
Timeline (1)
Aug Sep Oct Nov Dec
14/8 Workshop 1: History & Timeline
17/8 Workshop 2: Methodology Brainstorm
12/9 Workshop 3: Review Options (baselines & substitutions)• high level interaction with charging / IECR / T&T
19/9 Summary report on workshop outputs
25/10 Workshop 1: Enduring T&T
1/11 Workshop 2: Enduring T&T
8/11 Workshop 3: Enduring T&T
29/11 Enduring T&T Mod raised
[16/11] Ofgem consultation
[if appropriate with indicative charges]
23/11 Mod raised to delay AMSEC
13/12 T&T MS Consultation
Timeline (2)
Nov Dec Jan Feb Mar
[16/11] Ofgem consultation
23/11 Mod raised to delay AMSEC
13/12 T&T MS Consultation
[21/12] Mod approved to delay AMSEC
10/1 T&T MS Consultation closes
[28/12] Ofgem consultation closes
[23/01] T&T Mod approved
29/11 Enduring T&T Mod raised
23/01 T&T MS Sent to Ofgem
14/02 IECR / Sub MS / [pricing] workshop 1
[07/02] Section 23 issued
[28/02] T&T MS approved
21/02 IECR / Sub MS / [pricing] workshop 2
28/02 IECR / Sub MS / [pricing] consultation
[06/03] Section 23 consultation closes
14/02 GCM01 Conditional Prices Published
Timeline (3)
Mar Apr May Jun Jul
[06/03] Section 23 consultation closes[13/03] Section 23 consented to and directed
27/03 IECR / Sub MS / [pricing] consultation closes
10/04 Revised IECR / Sub MS / [charging proposal] sent to Ofgem
[17/04] AMSEC auction
[1/05] New GCM01 prices effective
[10/06] IECR / Sub MS / [Charging Proposal] approved by Ofgem
[1/07] September QSEC prices issued