www.tge-gas.com Page 124/10/2016
BASED ON EXPERIENCE
TGE GAS ENGINEERINGEPC EXECUTION OF BOREALIS ETHANE TANK PROJECT
www.tge-gas.com Page 224/10/2016
� Overview on the Services and Experience of TGE Gas Engineering GmbH
� Project Overview and Process Description
� Construction Phase
� Pre-Commissioning and Commissioning
� Time Schedule
CONTENT
www.tge-gas.com Page 324/10/2016
TGE Gas Engineering GmbH (TGE) is one of the
world‘s leading contractors for projects involving the
storage and handling of liquefied gases in the energy
and petrochemical/chemical industries.
TGE has over 30 years of experience in this field,
providing full range of services from concept
/feasibility studies through to Lump Sum Turn-Key
Project execution.
Our target is to provide to customers the added value
based on our experience and Know-How in delivering
“millions of m³” of Liquefied Gas Storages and
Handling Facilities.
TGE is a technology focused company that is active
worldwide with main operating units throughout
Europe and Asia.
0
1.000.000
2.000.000
3.000.000
4.000.000
5.000.000
6.000.000
Overallcapacity
LNG Ethylene /Ethane
Propylene,LPG, etc.
LIQUEFIED GAS STORAGE CAPACITY PERFORMED (m³)
Status Sep. 2016
COMPANY PROFILE
www.tge-gas.com Page 424/10/2016
� Consultancy
� Technical and Commercial Feasibility Studies
� Site Selection
� Conceptual Design
� Environmental Impact Assessment (EIA) and
HAZOP Studies
� Capital Cost (CAPEX) and Operating Cost
(OPEX) Estimation
� Business Plan for Capital Investments and Operations
� Basic Engineering and Front End Engineering Design
(FEED)
� Detailed Engineering
� Procurement/Procurement Services
� Construction/Construction Services
� Supervision Services
� Pre-Commissioning and Commissioning Services
� Start-Up/Shut Down Services
� Selection and Training of Operators
� Operation and Maintenance Services
� Life-Cycle Engineering Studies and Plant
Life-Cycle Optimisation
SCOPE OF SERVICES BOREALIS
www.tge-gas.com Page 524/10/2016
� Medium
� Liquid Ethane
� Storage Tank
� Full Containment Storage Tank
� Working Volume 52,000 m³
� Design Conditions
� -4.5 to 300 mbarg
� -115°C to Ambient
� Level / Temperature / Pressure Measurement & Control Systems
� Main equipment
� In-tank Pumps (3 x 50% capacity)
� Screw Compressor Package (2 x 50% Capacity)
� Ground Flare System
� Utilities
� Design Requirements
� Unloading Rate
� Sendout Rate
� DESIGN BASIS
�PROJECT OVERVIEW
www.tge-gas.com Page 624/10/2016
�PROJECT OVERVIEW – FLOW DIAGRAM
www.tge-gas.com Page 724/10/2016
� Tank Design
� Full Containment Design acc. EN14620
� Insulation Calculations
� Design of Equipment
� Type
� Data Sheets
� Noise Study Compressor Shelter
� Restriction of Noise
� Natural Ventilation
� Hazop Review Meeting
� Safety Discussions Client & Vendors
� 3D Model Review
� 30% 3D Model Review – Lines
� 60% 3D Model Review – Maintability and Operability
� 90% 3D Model Review – All Layout
� Safety Review by Inspecta
� Review of Project Design regarding Overall Safety
� e.g. Check of Safety Valve Sizing
� MAIN PROJECT STEPS
�PROJECT OVERVIEW
www.tge-gas.com Page 824/10/2016
� SPECIAL PROCESS DESIGN
�PROJECT OVERVIEW - PROCESS
� Screw Compressors
� Preheating of Cold Ethane Vapour
� Shell & Tube Heater
� Usage of Hot Compressor Discharge
� Preheating to -40°C� Compressor Inlet Temperature controlled via Bypass
� Safety System
� Stop Compressor at low Temperature
www.tge-gas.com Page 924/10/2016
PROJECT OVERVIEW - PLOTPLAN
www.tge-gas.com Page 1024/10/2016
� Duration 26 months (08.14. – 09.16)
� Number of Near Misses: 303
� Total Hours Worked: 292.506
� Accidents: 0
� Lost Working Hours: 0
� Daily Site Coordination Meetings
� Weekly Meetings with CLIENT and Subcontractors
� Weekly Safety Walks
� Toolbox Meetings
� Involvement of CLIENT and INSPECTA from the beginning
� STATISTICS � ORGANIZATION
�CONSTRUCTION
www.tge-gas.com Page 1124/10/2016
� WORKS
�CONSTRUCTION
www.tge-gas.com Page 1224/10/2016
� Deviation into Systems and Subsystems and Testpacks
� Inspections
� Line Cleaning
� System Drying & Inerting
� Instrument Loop
� Interlock / ESD Checks
� PID Checks
� Electrical Circuit / Motor / Equipment Checks
� Equipment Installation
� Mechanical Equipment Checks
� Vendor Checks
� Introduce IA and N2 – Flush & Test
� Service Test FW System – Flush & Test & Drain
� Follow Up Done by PIMS CMS System
� MECHANICAL COMPLETION / PRE-COMMISSIONING
�CONSTRUCTION
www.tge-gas.com Page 1324/10/2016
� PRE-COMMISSIONING / COMMISSIONING
� Start Half a Year in Advance with first Commissioning
Meetings (Scope, Interfaces, Organization)
� Operator Training Support
� Dedicated Commissioning Team Full Time on Site
� Tank Purging with Nitrogen
� Tank Gassing-up & Start-up Compressors
� Tank Cool Down
� Start of In-tank Pumps
� Start of Sendout
� Performance Tests
� Taking Over
�PRE-COMMISSIONING / COMMISSIONING
www.tge-gas.com Page 1424/10/2016
� CHALLENGES
� Integration of:
� New DCS / SM into old DCS / SM
� Equipment into old DCS / SM
� Manual Control for Preheaters during Cooldown
� Sensible Interaction between Components of System forAdjustment
� Observation of Behavior of the Control Systems duringManual Control
� Support
� DCS programming according TGE design
� Adjustment of Control for Preheater System
�COMMISSIONING
www.tge-gas.com Page 1524/10/2016
�IMPORTANT MILESTONES
www.tge-gas.com Page 1624/10/2016
THANK YOU FOR YOUR ATTENTION!
Vielen Dank
多谢
cпaсибо большое
Obrigado
www.tge-gas.com Page 1724/10/2016
TGE Gas Engineering GmbH
Mildred-Scheel-Str. 1
53175 Bonn
Germany
+49 228 60448 0
+49 228 60448 893
www.tge-gas.com
CONTACT
www.tge-gas.com Page 1824/10/2016
Storages and
Terminals
for LNG
Small-Mid Scale
Natural Gas LNG
Liquefaction Plants
Storage and
Terminals
for Petrochemical/
Chemical Gas
Other
� Package Plants for gas
treatment or elements
of storage product
lines
� LNG as Fuel
� Storage Tank
Design Services
PRODUCT LINES
www.tge-gas.com Page 1924/10/2016
� 17 Projects in Total (EPC & EP+CS)
� Import Terminals: 9
� Export Terminals: 7
� Import/Export Terminal: 1
� 72 LNG Truck/Container Loading Stations
� Total Regasification Capacity > 13 mio t/a
� Total Production Capacity
Small-Mid Scale LNG > 3 mio t/a
Reference for all relevant International Design Codes:
Tanks: EN 14620, EUROCODE
API 625, API 620, ACI 376
Facilities: EN 1473, NFPA 59a, S
STORAGE TANKS
Storage Tanks installed 30,000 - 160,000 m³
Storage Tanks designed 5,000 - 260,000 m³
Storage Tanks installed in Europe 940,000 m³
Storage Tanks installed in Asia 1,908,000 m³
STORAGES AND TERMINALS FOR LNG
INSTALLED CAPACITY
21 Full Containment Tanks 2,838,000 m³
5 Single Containment Tanks 170,000 m³
TOTAL INSTALLED CAPACITY 3,008,000 m³
FACTS & FIGURES
www.tge-gas.com Page 2024/10/2016
� 36 Projects in Total (EPC & EP+CS) for
Petrochemical Products: Ethylene, Ethane,
Propylene, Butane, LPG, Ammonia.
STORAGE TANKS
Tanks installed with capacities from
up to3,000 - 120,000 m³
Facilities installed in Europe 327,000 m³
Facilities installed in Asia 1,684,000 m³
STORAGES AND TERMINALS FOR
PETROCHEMICAL GASES
INSTALLED CAPACITY
20 Full Containment Tanks
with installed capacity1,205,000 m³
22 Single Containment Tanks
with installed capacity560,000 m³
TOTAL INSTALLED CAPACITY 1,765,000 m³
FACTS & FIGURES
LARGEST INSTALLED CAPACITY
LPG 120,000 m³ Full Containment
Ethylene 80,000 m³ Full Containment
Ethane 120,000 m³ Full Containment
Propylene 80,000 m³ Full Containment
Ammonia 25,000 ton Full Containment