23
BART Weir / Rubber Dam 1 Fish Ladder Workshop March 12, 2009 Hanson Environmental, Inc.

BART Weir / Rubber Dam 1 Fish Ladder Workshop

Embed Size (px)

Citation preview

Page 1: BART Weir / Rubber Dam 1 Fish Ladder Workshop

BART Weir / Rubber Dam 1 Fish Ladder Workshop

March 12, 2009

Hanson Environmental, Inc.

Page 2: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Agenda

• Project Goals

• Introduction of Project Team

• Background

• Schedule

• Environmental Process

• Fish Ladder Design Criteria

Page 3: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Goals

• Provide fish passage for adult steelhead and salmon to migrate through the flood control channel to Alameda Creek

• Provide fish passage for smolts and kelts to migrate to the bay

• Maintain the beneficial uses of the flood control channel (flood protection, water supply, groundwater percolation, recreation)

• Be mindful of the economic impacts to our customers

Page 4: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Project Team

Winzler & Kelly • Project Management•Structural Design •Civil Design 

Kosmo• Fish passage design, hydraulics 

Mike Love & Associates • Fish passage design, hydraulics, hydrology

Kleinfelder• Geotechnical

Hanson Environment• CEQA• Biological Assessment

Page 5: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Status and Schedule

Page 6: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Bunting Pond Fish Screen

Page 7: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Rubber Dam 2 Decommissioning and Foundation Modification

Page 8: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Rubber Dam 2 Decommissioning and Foundation Modification

Page 9: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Status and Schedule:Facility Current Status Project 

CompletionGrant Funding / Cost Sharing

Total Project Cost

Screens at Upper Rubber Dam

Complete March 2008 $500,000 NFWF $3,641,300

Lower Rubber Dam Removal and Notch

Advertising for Construction

2009 $500,000 NFWF $1,547,800*

Bunting Pond Fish Screen

Advertising for Construction

2009 $600,000 Prop 50 Grant (on hold)

$1,698,300*

BART Weir/Middle Rubber Dam Fish Ladder

Geotech complete

Prelim Design – in progress

CEQA/BA – Start March 2009

2010 $500,000 NFWF 

ACWD/ACFC sharing project cost

$5,400,000*

Upper Rubber Dam Fish Ladder

Geotech complete

CEQA / BA – Start March 2009

2011 or 2012 $500,000 NFWF $2,500,000*

Kaiser and Shinn Fish Screen 

Preliminary design –begin mid‐2009

2012 or 2013 $6,238,000*

*Estimated Cost

Page 10: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Alameda Creek Fisheries Restoration Workgroup

Presenter
Presentation Notes
Largely as a result of community organizing and public pressure, there are now 15 local, state, and federal agencies pursuing fish passage projects in the watershed, including dam removals, construction of fish ladders at instream barriers, and installation of fish screens at water diversions. The Alameda Creek Fisheries Restoration Workgroup, which formed in 1999, is now conducting 2 years of studies to determine appropriate stream flows necessary to sustain a restored steelhead population.
Page 11: BART Weir / Rubber Dam 1 Fish Ladder Workshop
Page 12: BART Weir / Rubber Dam 1 Fish Ladder Workshop
Page 13: BART Weir / Rubber Dam 1 Fish Ladder Workshop
Page 14: BART Weir / Rubber Dam 1 Fish Ladder Workshop
Page 15: BART Weir / Rubber Dam 1 Fish Ladder Workshop
Page 16: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Reduced Vertical Slot

Page 17: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Pool and Chute

Page 18: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Roughened Channel

Page 19: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Flood Control Channel Hydrologic Conditions

• Summer – Flows off the watershed are approximately 10‐15 cfs, ACWD imports are 10‐35 cfs

• Winter– Flows are flashy  (rise and recede quickly, within hours)

Page 20: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Rubber Dam / Diversion Operations

• Storm Event– Critical stream flow Qc is determined; typically between 700 cfs and 1200 cfs

– Monitor flows at Arroyo de la Laguna at Verona and Alameda Creek at the Welch Gage

– Diversions are closed

– Dams are deflated 

– Dams remain down for a minimum of 24 hours

Page 21: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Vertical Slot Fish Ladder

• Accommodates targeted life stage – in migrant adult steelhead and salmon

• Passable at a range of flows

• Self‐Controlling 

• Better suited to accommodate multiple entrances needed for water supply operations

Page 22: BART Weir / Rubber Dam 1 Fish Ladder Workshop

BART Weir/Rubber Dam 1 ScheduleMilestones to date

• ACFC&WCD and ACWD Agreement – July 2007• Winzler & Kelly contract for Preliminary Design –September 2008

• Geotechnical work for fish ladders – November 2008• Fish ladder alternatives analysis – December 2008 and January 2009

• Hanson contract for Environmental Work – March 2009

• Pre‐workshop meeting with NOAA – March 6, 2009• Workshop with Workgroup – March 12, 2009

Page 23: BART Weir / Rubber Dam 1 Fish Ladder Workshop

Moving Forward

• Complete Preliminary Design – August 2009

• Complete CEQA – June 2009

• Complete Biological Assessment – July 2009

• Permit Applications – September 2009

• Complete Final Design – January 2010

• Construction – Summer / Fall ‐ 2010