Upload
leonard-weaver
View
229
Download
0
Embed Size (px)
Citation preview
Barr-Milton Watershed Barr-Milton Watershed Modeling Project - Workshop #4Modeling Project - Workshop #4
David Pillard, Ph.D. – Project Manager, Ft. David Pillard, Ph.D. – Project Manager, Ft. Collins, COCollins, CO
Ken Heim, Ph.D. – Lead Modeler, Westford, MAKen Heim, Ph.D. – Lead Modeler, Westford, MA
Ken Wagner, Ph.D. – Solutions Support – Ken Wagner, Ph.D. – Solutions Support – Willington, CTWillington, CT
Key Project PremisesKey Project Premises
• Barr Reservoir and Milton Lake experience periodic high pH (>9.0) that violate state standard (<9 for 85% of time)
• High pH is believed to be a consequence of algal productivity (removal of CO2 during photosynthesis)
• Algal productivity is controlled mainly by nutrients, light and temperature
• Nitrogen affects the types of algae present, but phosphorus tends to control the quantity of algae and is the most practical nutrient to control
• Available phosphorus levels are very high in both waterbodies
Derivation of Potentially Protective P LoadsDerivation of Potentially Protective P LoadsFeature or Scenario Units Barr Milton Notes
Chlorophyll (ug/L) target based on regressions using Chl and Temp - Summer (constructed from 2002-2007 data) ug/L 14 1.5
Accounts for only about half the variation in pH
Chlorophyll (ug/L) target based on regressions using Chl and Temp - Winter (constructed from 2002-2007 data) ug/L 127 5.0
Accounts for only about half the variation in pH; lower temp allows greater Chl
Chlorophyll (ug/L) target based on calculated mean that yields a Chl corresponding to pH=9.0 SU for 15% of the time from all 2002-2007 data ug/L 77 77
Depends on Chl-pH relationship that is very weak in Barr and Milton; Barr data applied to both
Chlorophyll (ug/L) target based on calculated mean that yields a Chl corresponding to pH=9.0 SU for 15% of the time from summer 2002-2007 data ug/L 47 47
Depends on Chl-pH relationship that is very weak in Barr and Milton; Barr data applied to both
Chlorophyll (ug/L) target based 15th percentile of pH data >9.0 SU from 2002-2007 data ug/L 21 6.8
Reflects actual occurrence of high pH over 6 years
Chlorophyll (ug/L) target based 15th percentile of pH data >9.0 SU from summer 2002-2007 data ug/L 18 8.2
Lower Chl from subset of data, most likely results from influence of higher temperature
Chlorophyll (ug/L) target based 15th percentile of pH data >9.0 SU from 2002-2007 data for other Denver area reservoirs ug/L 25 25
Mostly summer data from 15 area reservoirs with some wastewater influence but no major benthic algae or rooted plants
mg/L
mg/L
mg/L
mg/L
mg/L
kg/yr 20500 19600
kg/yr 12400 11900
kg/yr 6230 5950
Applies to Barr
Derivation of Potentially Protective P LoadsDerivation of Potentially Protective P Loads
ug/L 14 1.5
ug/L 127 5.0
ug/L 77 77
ug/L 47 47
ug/L 21 6.8
ug/L 18 8.2
Chlorophyll (ug/L) target based 15th percentile of pH data >9.0 SU from 2002-2007 data for other Denver area reservoirs ug/L 25 25
Mostly summer data from 15 area reservoirs with some wastewater influence but no major benthic algae or rooted plants
Total Phosphorus (mg/L) target to achieve Chl=25 ug/L based on projections from 2002-2007 data mg/L Relies on weak relationshipTotal Phosphorus (mg/L) target to achieve Chl=25 ug/L based on projections from 2002-2007 data from other Denver area reservoirs mg/L
Relies on weak relationship, but consistent with findings for Barr-Milton
Total Phosphorus (mg/L) target to achieve Chl=25 ug/L based on projections from empirical models for temperate North America mg/L
Uses mean of 5 models constructed from different groups of temperate zone lakes
Total Phosphorus (mg/L) target to achieve Chl=25 ug/L based on empirical models as interpreted for Denver area reservoirs mg/L
Doubles empirical model result based on research on plains lakes
Total Phosphorus (mg/L) target to achieve Chl=25 ug/L based on hypothetical trajectory and actual variation in TP-pH relationship from 2002-2007 data mg/L
Hypothetical but theoretically sound constructed curve applied; available data do not cover lower range
Average Total Phosphorus - all 2002-2007 data mg/L 0.68 0.57Average Total Phosphorus - summer data only mg/L 0.56 0.59
Current TP Load kg/yr 85000 67800Converts concentration to load via empirical models
TP load that leads to meeting 0.165 mg/L TP target intended to lead to a 25 ug/L Chl level kg/yr 20500 19600
Converts concentration to load via empirical models
TP load that leads to meeting 0.10 mg/L TP target intended to lead to a 25 ug/L Chl level kg/yr 12400 11900
Converts concentration to load via empirical models
TP load that leads to meeting 0.05 mg/L TP target intended to lead to a 25 ug/L Chl level kg/yr 6230 5950
Converts concentration to load via empirical models
0.09
Applies to Barr
0.17
0.16
0.05
0.10
Limitations of Empirical ModelingLimitations of Empirical ModelingMilton Reservoir Summer Avg pH (WC) vs. TP mg/L
7.00
7.50
8.00
8.50
9.00
9.50
10.00
0.00 0.20 0.40 0.60 0.80 1.00
TP (mg/L)
pH
(S
U)
Barr Lake Summer Avg pH (WC) vs. TP mg/L
7.00
7.50
8.00
8.50
9.00
9.50
10.00
0 0.2 0.4 0.6 0.8 1
TP (mg/L)
pH
(S
U)
• We don’t have site specific data for the low end of the scale• We have a reasonable idea of “background” pH• We can project how background would be approached with
declining TP and the level of associated variability • A TP value somewhere near 0.1 mg/L appears most appropriate,
but is not a hard threshold
Important Things to Remember When Important Things to Remember When Considering ModelingConsidering Modeling
• Biological factors are less amenable to modeling and induce variability/uncertainty in predictions
• Types of algae may matter almost as much as quantity of algae, especially diatom vs. bluegreen dominance
• Historical and current loads are high; predicting responses at lower loads requires reliance on other systems (prediction outside range of site data)
• Internal load is likely to compensate for reduced external load
• Water in Milton appears to be “pre-conditioned” – arrives with higher pH and less margin for compliance
• Actual data is “spotty” – exercise caution when comparing predictions and observations
Watershed InfluencesWatershed Influences
• Major tributary InletsMajor tributary Inlets
• Sub-watershed inletsSub-watershed inlets
• Point SourcesPoint Sources
• ReservoirsReservoirs
• Withdrawals/TransfersWithdrawals/Transfers
(not shown, very (not shown, very complicated pattern)complicated pattern)
Gather all Relevant Watershed and Water Withdrawal/Discharge/Transfer Information
and Comparative Data
Import into Enhanced SWAT Model, Run, and Calibrate
Prepare Required Files using Visual Basic Macros
Prepare SWAT Output for WASP Model
Link WASP to Prepared Files, Run, and Calibrate.
Prepare and Execute Alternative Simulations
Develop TMDL
SchematicSchematic Showing Steps Showing Steps
Taken to Taken to Complete Complete
Watershed-Lake Watershed-Lake ModelingModeling
SWAT = Soil and Water Assessment Tool
WASP = Water Analysis Simulation Program
O'Brian Canal Inlet to Barr - Total Phosphorus
0.0
0.5
1.0
1.5
2.0
2.5
3.0
Jan-03 Apr-03 Jul-03 Oct-03 Jan-04 Apr-04 Jul-04 Oct-04
Co
nce
ntr
atio
n (
mg
/L)
Measured Predicted
Results of Watershed Model
Barr LakePredicted Volume
Barr LakePredicted P Concentration
Barr Lake: 2003-04Measured and Predicted Volumes
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
Jan-03 Apr-03 Jul-03 Oct-03 Jan-04 Apr-04 Jul-04 Oct-04
Vo
lum
e (a
cre-
ft)
Measured Predicted
Barr Lake Total Phosphorus Barr Lake Total Phosphorus Calibration ResultsCalibration Results
0.0
0.5
1.0
1.5
2.0
Jan
2003
Apr
200
3
Jul 2
003
Oct
200
3
Jan
2004
Apr
200
4
Jul 2
004
Oct
200
4
To
tal P
(p
pm
)
WASP PredictedMeasured
Barr Lake Total Chlorophyll Barr Lake Total Chlorophyll Calibration ResultsCalibration Results
0
50
100
150
200
250
Jan
2003
Apr
200
3
Jul 2
003
Oct
200
3
Jan
2004
Apr
200
4
Jul 2
004
Oct
200
4
To
tal C
hlo
rop
hyl
l (p
pb
)
WASP PredictedMeasured
Barr Lake Total Chlorophyll Barr Lake Total Chlorophyll Calibration ResultsCalibration Results
Quantify the effects of several management options on Barr Lake/Milton Reservoir water quality.
1. Wastewater – Reduced phosphorus loads from three major dischargers.
2. Refill – Alter the timing and sources of water for Barr Lake infill.
3. Land Use – Alter the effects of agriculture and urbanization.
4. Reservoir Treatment – Reduced internal phosphorus loading.
Model Scenarios
Total Total Phosphorus Phosphorus PredictionsPredictions
for Barr Lakefor Barr Lake
Total Total Chlorophyll Chlorophyll PredictionsPredictions
for Barr Lakefor Barr Lake
Total Total Phosphorus Phosphorus PredictionsPredictionsfor Milton for Milton ReservoirReservoir
Total Total Chlorophyll Chlorophyll PredictionsPredictionsfor Milton for Milton ReservoirReservoir
Total Total Phosphorus Phosphorus PredictionsPredictions
for Barr Lakefor Barr Lake
Total Total Chlorophyll Chlorophyll PredictionsPredictions
for Barr Lakefor Barr Lake
Total Total Phosphorus Phosphorus PredictionsPredictionsfor Milton for Milton ReservoirReservoir
Total Total Chlorophyll Chlorophyll PredictionsPredictionsfor Milton for Milton ReservoirReservoir
Modeling Implications for Modeling Implications for Compliance StrategiesCompliance Strategies
• The lower the WWTP output P level, the better for the reservoirs, but not necessarily proportionally
• Addressing P from Metro and Littleton/Englewood WWTP is essential
• Internal loading must be addressed• Unless WWTP and internally loaded P are both
addressed, compliance is unlikely to be achieved through P control
• There is enough loading from other sources to prevent achievement of “pristine” conditions
• Have to think in terms of distribution of values; not just mean/median, but shape of upper “tail”
In-Lake Strategies for Lowering pHIn-Lake Strategies for Lowering pH
• P inactivation – reducing available P with aluminum sulfate additions to lakes (also directly lowers pH)
• Mixing/aeration – would avoid localized high pH with algal blooms, may disrupt blooms (esp. blue-greens), encourages CO2 transfer
• Biomanipulation – fosters zooplankton that minimize algal biomass; usually involves altering the fish community
• Algaecides – directly kills algae when too abundant, could limit maximum pH
Towards a TMDL and Towards a TMDL and Management PlanManagement Plan
• A few more combination scenarios might be worthwhile (e.g., WWTP @ 1.0 ppm and 70+% internal load reduction, or other water management options)
• Pilot testing of mixing or reduced P in limnocorrals in the reservoirs might be useful to define direct pH response
• Defining goals in terms of use attainability would be appropriate, with comparison to WQ standards (e.g., when and why should the pH standard be met, based on water uses?)
Questions and CommentsQuestions and Comments