20
Barber Dam FERC Relicensing – Joint Meeting March 21, 2019

Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

Barber Dam FERC Relicensing –

Joint Meeting

March 21, 2019

Page 2: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

Barber Dam FERC Relicensing – Joint Meeting

Agenda

• Welcome and Introductions

• Overview of Project Layout and Operations

• FERC Relicensing Process and Schedule

• Overview of the Pre-Application Document (PAD)

• Comments and Information/Study Requests

Page 3: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

Introductions

Barber Dam Project Co-Licensees

• Fulcrum, LLC

– A subsidiary of Enel Green Power North America

• Ada County, Idaho

Consultant Team

• McMillen Jacobs Associates

– FERC Process, Engineering and Studies

• Louis Berger

– Studies and Study Program Lead

Page 4: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

Project Overview

Project Location

• Boise River, river mile 58.9, 6 miles southeast of downtown Boise

• 4 miles downstream of Lucky Peak Dam (US Army Corps of

Engineers), 2 miles downstream of Diversion Dam (US Bureau of

Reclamation)

• Project lies within the 425-acre Barber Pool Conservation Area

Page 5: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

Diversion Dam

Lucky Peak Dam

Page 6: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

Project Overview

Project Layout• Powerhouse

– Originally constructed 1905, refurbished 1987

– 2 horizontal Kaplan units, 1,077 cfs each

• Dam/Spillway

– 400 feet long X 25 feet high

• Embankment Dam

– 1,100 feet long X 39 feet high

• Headpond

– 75 acres

• Other Features

– Tailrace, transmission, recreation trail/portage

Page 7: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license
Page 8: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

Project Overview

Project Operations

• Run of river operation

– Automated pond level controls the turbine-generator units

• Seasonal pond level setpoints

• Excess flows (> 2,154 cfs) pass over the spillway

• Local operator conducts daily inspections, remotely monitored 24/7

• Manually operated trash raking system to remove river debris

• Generates clean renewable energy that locally powers ~3,000 homes

Page 9: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license
Page 10: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license
Page 11: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

FERC Relicensing Process

Role of the Federal Energy Regulatory Commission (FERC)

• FERC regulation of non-federal dams

– Authority derived from Federal Power Act (FPA)

– Exclusive authority to issue licenses (30-50 years)

– Monitors license compliance

– Dam safety

• Licenses define what can be built, how a project can be operated, and

determine other conditions

• Other agencies have separate authorities that are independent of

FERC but coordinated by FERC

Page 12: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

FERC Relicensing Process

Traditional Licensing Process (TLP)• Requested the TLP with filing of the PAD on November 29, 2018; approved by

FERC February 5, 2019

• Stage 1 – Applicants present project setting to stakeholders; stakeholders identify information needs, submit comments/study requests

• Stage 2 – Completion of reasonable and necessary studies requested by stakeholders at end of Stage 1; applicants provide draft license application and study results for stakeholder review and comment

• Stage 3 – Applicant files final application with FERC and sends copies to agencies and tribes

Post-Filing: FERC conducts NEPA, consults with agencies and stakeholders, and issues new license

Page 13: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

Relicensing – What FERC looks for

• Is the Applicants’ proposal “best suited” for the waterway according to

the standards of the Federal Power Act?

• What changes are the Licensees proposing for the next license term?

• How do proposed changes relate to project baseline and existing

environment?

Page 14: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

Relicensing – License Application Contents

• Exhibit A – Description of the Project

• Exhibit B – Project Operation / Resource Utilization

• Exhibit C – History of the Project

• Exhibit D – Statement of Costs and Financing

• Exhibit E – Environmental Analysis

• Exhibit F – Facilities Drawings

• Exhibit G – Maps and Boundaries

• Exhibit H – Electric Consumers Protection Act (ECPA) Considerations

Page 15: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

FERC Relicensing Process – Public Info

Information Available to the Public

• Website (https://mcmjac.com/barberdamrelicensing/)

– Pre-Application Document, notifications to FERC, relicensing schedule,

announcements

• FERC Docket for P-4881

– eLibrary at https://www.ferc.gov/

• Distribution List, maintained by licensees

• Ada County Operations Department, 200 W. Front Street, Boise, ID

• Kevin Webb: [email protected] or 978-935-6039

Heidi Wahto: [email protected] or 208-342-4214

Page 16: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

FERC Relicensing Process – Schedule

Activity Responsibility Time Frame Deadline

File NOI, PAD, and Request to use TLP Applicants 5 to 5 ½ years before license expiration November 30, 2018

Comment on TLP Request Stakeholders Within 30 days of TLP Request submittal December 31, 2018

Issue Public Notice of NOI, PAD, and decision on

TLP Request

FERC Within 60 days of NOI, PAD, and TLP Request

submittal

February 6, 2019

Notify FERC of Joint Meeting and publish notice in

newspaper

Applicants At least 15 days in advance of Joint Meeting March 6, 2019

Joint Meeting for consultation with agencies, tribes

and interested public

Applicants Within 30-60 days of FERC’s approval of TLP

Request

March 21, 2019

Comment on PAD and submit study requests Stakeholders Within 60 days of Joint Meeting May 20, 2019

Develop Study Plans Applicants Following receipt of PAD comments and study

requests

June – August 2019*

Conduct Field Studies Applicants Following development of study plans August 2019 – October

2020*

Summarize Study Results, develop Draft License

Application (DLA), and distribute to Stakeholders

Applicants Following conclusion of studies April 2021*

Comment on Study Results and DLA Stakeholders 90-day comment period July 2021*

Develop Final License Application (FLA) and file

with FERC

Applicants No later than 2 years before current license

expires

November 30, 2021

Current license expires FERC 40 years after effective date of current license November 30, 2023

Page 17: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

Overview of the Pre-Application Document

PAD Contents• Introduction

• Process Plan and Schedule

• Project Location, Facilities and Operation

• Description of Existing Environment and Resource Impacts– River Basin, Geology, Water Use/Quality, Fish & Aquatics, Terrestrial,

Rare/Threatened/Endangered Species, Recreation & Land Use, Aesthetics, Cultural, Socioeconomics

• Preliminary Issues and Studies List

• Appendices– Consultation to date, other requirements

Page 18: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

Study Requests and Comments

May 20, 2019 – deadline for study requests and comments• Missing information from PAD or data gaps

• Study Requests

• Written comments/study requests – reference P-4881– Kevin Webb, Hydro Licensing Manager Copy: Heidi Wahto, Project Manager

Fulcrum, LLC McMillen Jacobs Associates100 Brickstone Square, Suite 300 1011 Western Ave, Suite 706Andover, MA 01810 Seattle, WA [email protected] [email protected]

– Optional eFile at www.ferc.gov, under Documents & Filings eFiling

• Verbal comments – today– Transcript will be produced and filed with FERC

Page 19: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

Study Requests and Comments

FERC Study Request “Guidelines”1. Goals and Objectives

2. Relevant Resource Management Goals

3. Relevant Public Interest Considerations

4. Existing Information and Need for Additional Information

5. Project Nexus

6. Proposed Study Methodology

7. Level of Effort and Cost

https://www.ferc.gov/industries/hydropower/gen-info/guidelines/guide-study-criteria.pdf

Due on or before May 20, 2019

Page 20: Barber Dam FERC Relicensing – Joint Meeting · 2019. 4. 24. · Develop Final License Application (FLA) and file with FERC Applicants No later than 2 years before current license

Questions, Study Requests and Comments?