Upload
montymilky
View
217
Download
0
Embed Size (px)
Citation preview
8/14/2019 Banerejee_Energy Policy (in press).pdf
1/11
Energy Policy ] (]]]]) ]]]]]]
Comparison of options for distributed generation in India
Rangan Banerjee,1
Department of Engineering and Public Policy, Carnegie Mellon University, Pittsburgh, PA 15217, USA
Abstract
There is renewed interest in distributed generation (DG). This paper reviews the different technological options available for DG,
their current status and evaluates them based on the cost of generation and future potential in India. The non-renewable options
considered are internal combustion engines fuelled by diesel, natural gas and microturbines and fuel cells fired by natural gas. Therenewable technologies considered are wind, solar photovoltaic, biomass gasification and bagasse cogeneration. The cost of
generation is dependent on the load factor and the discount rate. Gas engines and Bagasse based cogeneration are found to be the
most cost effective DG options while wind and biomass gasifier fired engines are viable under certain conditions. PEM Fuel cells and
micro turbines based on natural gas need a few demonstrations projects and cost reductions before becoming viable. A strategy
involving pilot projects, tracking of costs and dissemination of information is likely to result in DG meeting 10% of Indias power
needs by 2012.
r 2004 Elsevier Ltd. All rights reserved.
Keywords: Distributed generation; Annualized life cycle cost; Load factor
1. Introduction
The earliest electric power systems were distributed
generation (DG) systems intended to cater to the
requirements of local areas. Subsequent technology
developments driven by economies of scale resulted in
the development of large centralized grids connecting up
entire regions and countries. The design and operating
philosophies of power systems have emerged with a
focus on centralized generation. During the last decade,
there has been renewed interest in DG. This paper
reviews the different technological options available for
DG, their current status and evaluates them based on
the cost of generation and future potential. Therelevance of these options for a developing country
context is examined using data for India.
Different definitions of DG have been proposed.
Some have linked this to the size of the plant, suggesting
that DG should be from a few kW to sizes less than 10
or 50 MW.Ackerman et al. (2001) provides a review of
alternative definitions of DG and suggests that DG be
defined as the installation and operation of electric power
generation units connected directly to the distribution
network or connected to the network on the customer site
of the meter. DG is also referred to as dispersed
generation or embedded generation. DG options can
be classified based on the prime movers usedengines,
turbines, fuel cells or based on the fuel source as
renewable or non-renewable. There are a large number
of possible system configurations.In this review the comparison is limited to the
following options:
(A) Non-Renewable
1. Internal combustion engine fuelled by diesel
2. Internal combustion engine fuelled by natural gas
3. Micro-turbine fuelled by natural gas
4. Proton exchange membrane (PEM) fuel cell with
reformer fuelled by natural gas
ARTICLE IN PRESS
www.elsevier.com/locate/enpol
0301-4215/$- see front matter r 2004 Elsevier Ltd. All rights reserved.
doi:10.1016/j.enpol.2004.06.006
Corresponding author. IIT Bombay, Energy Systems Engineering,
Powai, Mumbai 400076, India. Tel.: +91-22-2576-7883; fax: +91-22-
2572-6875.
E-mail address: [email protected] (R. Banerjee).1On leave from Indian Institute of Technology Bombay.
http://www.elsevier.com/locate/enpolhttp://www.elsevier.com/locate/enpol8/14/2019 Banerejee_Energy Policy (in press).pdf
2/11
(B) Renewable
5. Wind turbine
6. Solar photovoltaic (PV)
7. Biomass gasifier connected to a spark ignition engine
(dedicated gas engine)
8. Bagasse cogeneration in sugar factories
Other options that have not been considered here are
small hydropower, geothermal, ocean thermal, tidal and
solar thermal power generation options. In order to
place DG in the context of the Indian power sector, a
brief background of the Indian power scenario is
provided before comparing the DG options.
2. Indian power sector
India had an installed capacity of 105,000 MW
(Ministry of Power, 2003a, b) in the centralized power
utilities on 31st March 2003. Of this 74,400 MW is
accounted for by thermal power plants, 26,300 MW of
large hydro plants and 2700 MW of nuclear. The focus
of power planning has been to extend the centralized
grid throughout the country. However the capacity
addition has not been able to keep pace with the
increasing demand for electricity. This is reflected by the
persistent energy and peak shortages in the country. The
transmission and distribution losses are extremely high
(estimated to be more than 25%, this includes theft).
India has a plan to add 100000MW of additional
power generation capacity by 2012 (MOP, 2001). This
requires an average capacity addition of more than10,000 MW per year. Centralized generation alone is
unlikely to meet this target. In this context DG is likely
to be important. DG also has the advantage of
improving tail-end voltages, reducing distribution losses
and improving system reliability.
The present installed capacity of DG is about
13,000 MW (10,000 MW diesel, 3000 MW renewables).
The majority of this is accounted for by diesel engines
that are used for back-up power (in the event of grid
failure) and operate at very low load factors. The share
of the energy generation from DG is marginal (about
23% of the total generation). Apart from the dieselengines, the DG options that have been promoted in
India are modern renewables.
India is probably the only country with a separate
Ministry of Non-conventional Energy Sources (MNES).
The renewable energy installed capacity was 205.5MW
in 1993 (104.6 MW small hydro, 39.9 MW Wind). This
increased to 2978 MW in 2001 (as on 31st March 2001)
and accounted for almost 3% of Indias installed power
capacity (MNES, 2001; Annual Reports MNES, 2000,
2001, 2002). The growth rate of installed renewable
power capacity during the period 19932001 was 39%
per year. During the period January 2000April 2001
the installed capacity increased from 1600 MW to
2978 MW (an annual growth rate of 49%).
Fig. 1 shows the installed capacity of different
renewable energy technologies (Annual Report MNES,
2002). The major contributors are small hydro
o25 MW which accounts for 1341 MW (45%) and
wind which accounts for 1267 MW (42%). The installedcapacity in Biomass based power generation is 308 MW
(10.3%), with most of it coming from bagasse based
cogeneration. Most of the installed capacity available
from renewables is accounted for by grid connected
systems (wind, small hydro and biomass cogeneration).
This accounts for about 3% of Indias installed capacity
contribute to about 12% of the total generation (due to
low capacity factors on renewables). The growth rate
has been significant (above 30% per year). This has been
facilitated by an enabling policy environment and a
supportive government.
Despite the emphasis on extending the centralized
grid to the rural areas, 78 million rural households
(Ministry of Power, 2003b) or 56.5% of rural house-
holds are still unelectrified. The recently passed Elec-
tricity Act (2003) has made it a statutory obligation to
supply electricity to all areas including villages and
hamlets. The act suggests a two pronged approach
encompassing grid extension and through standalone
systems. The act provides for enabling mechanisms for
service providers in rural areas and exempts them from
licensing obligations. MNES has been given the
responsibility of electrification of 18,000 remote villages
through renewables. The ministry has set up an
ambitious target of meeting 10% of the power require-ments of India from renewables by 2012 . In most cases,
the areas to be electrified do not have sufficient paying
capacity. Most systems are subsidized by the Govern-
ment or the utility. The power sector has significant
losses and needs to ensure that the DG systems selected
are likely to be cost-effective. This paper examines the
cost effectiveness of the different DG options selected.
ARTICLE IN PRESS
1267 1341
63 35 15 47
210
0
200
400
600
800
1000
1200
1400
1600
Wind
SmallHydro
BioCombn
BioCogen
Gasifiers
Waste-
Energy
SolarPV
InstalledCapacity(M
W) Total Renewable Installed capacity 2978 MW
31/3/2001 MNES
Fig. 1. Installed capacity of renewables in India.
R. Banerjee / Energy Policy ] (]]]]) ] ]]]]]2
8/14/2019 Banerejee_Energy Policy (in press).pdf
3/11
3. Comparison methodology
In order to compare the costs of generation of
electricity from each of these options, the annualized
life cycle cost (ALCC) is used. The annualized life cycle
cost represents the annual cost of purchase and
operation of the system. The cost of generated electricity
is obtained by dividing the ALCC by the annual
generation.
The ALCC is computed as
ALCC C0 CRFd; n ACfACO&M; 1
whereC0 is the initial capital cost for the option, ACf is
the annual fuel cost for the option and ACO&M is the
annual operating and maintenance cost for the option.
The capital recovery factor (CRF) is computed based on
the discount ratedand the life of the option n using the
equation
CRFd; n d1dn=1dn 1: 2
The annual generation is dependent on the load factor.
The cost of generation is dependent on the size and the
application load factor. In this paper a 100 kW peak
rating is used as the basis except for wind and biomass
cogeneration that are considered to be in the range of a
few MW. The calculations are done with existing Indian
fuel and equipment prices. In the case of technologies
not commercially available in India the existing inter-
national prices in US $ have been converted to Indian
rupees at the prevalent exchange rates (1 US $ 47 Rs.
in 2003). An idea of the comparative costs of options
and impact of the load factor will provide an idea of the
viability of the DG option. The status of each option in
India is discussed along with some of the issues relevant
for its adoption.
4. Non-renewable cost of generation
Table 1 shows the input data used for the economic
calculations.
Fig. 2 shows the annualized life cycle costs of the
diesel, gas engine and micro-turbine options, as a
function of the load factor. It is clear that except at
very low load factors, the gas engine and microturbine
option seem cheaper than the diesel engine. One of the
main reasons for this is the availability of relatively
cheaper natural gas (Rs. 0.144/MJ of energy) in India as
compared to diesel (Rs. 0.464/MJ of energy). The ratio
of the diesel price to the natural gas price on a per unit
of delivered energy is 3.2. In the US the price of natural
gas in January 2003 (USDOE, 2003) was 4.47$/1000ft3
(Rs. 0.167/MJ) and the price of diesel oil to industrial
consumers was 82.5 c/gal (Rs. 0.297/MJ) resulting in aratio of 1.8 of diesel price to natural gas price. It is likely
that the differential between diesel and natural gas
prices in India would reduce in the future.
This comparison is done with a societal discount rate
of 10%. The price of power from diesel engine
generators is Rs. 4.8/kWh (10 c/kW h) at 80% load
factor with fuel cost accounting for 86% of the cost of
generation. Fig. 3 shows the cost of generation from
diesel engine-generators as a function of the load factor.
The industrial tariff prevalent in Maharashtra is shown
for comparison. It is seen that electricity from the grid
is cheaper for load factors greater than 15%. (Tariff
ARTICLE IN PRESS
Table 1
Input cost data used for calculations
Option Capital cost (Rs./kW) Life ZEfficiency O&M cost Rs./kW h
Diesel engine 25000 20 40% 0.25
Gas engine 33000 20 35% 0.25
Micro turbine 45000 20 28% 0.25
Fuel cell 141000 10 45% 0.25
Discount rated= 0.1; natural gas price = Rs. 5200/1000sm3; diesel price = Rs.16/l, density = 850kg/m3; LHV = 9700kcal/kg.
Sources:ICRA, 2003; Borbely and Kreider, 2001;Resources Dynamics Corporation, 2001.
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
50000
0 0.2 0.4 0.6 0.8 1
Load Factor
AnnualisedLifeCycleC
ost(Rs/kW/year) Diesel
Gas Engine
MicroTurbine
Fuel Cell
Fig. 2. Comparison of annualized life cycle costs for non-renewables
(Discount rate = 10%).
R. Banerjee / Energy Policy ] (]]]]) ] ]]]]] 3
8/14/2019 Banerejee_Energy Policy (in press).pdf
4/11
for large industrial consumers receiving high tension
supply.)
For private sector companies that have a higher
discount rate1 d30%, the comparison is shown in
Fig. 4. It is seen that diesel engines are preferred at load
factors of 20% or less (less than 5 h per day). This is
probably the reason for the large base of diesel engine-
generators for back up power in India that provide
uninterrupted power supply in the event of grid failure.
Diesel engines are manufactured indigenously (major
companies include Cummins, Wartsila, Kirloskar and
Greaves) and there is significant experience in India in
the operation, maintenance and repair of diesel engine-
generators. About 10,000 MW of diesel engine capacity
exists in India. Only a small portion of this is connected
to the grid. Most of these operate with very low loadfactors. From the national viewpoint there is an attempt
to discourage diesel based power plants since India has a
middle distillate bulge (scarcity of middle distillates like
diesel) that is constrained by the refinery mix and
necessitates the import of petroleum products.
Natural Gas engines are not as common, probably
because natural gas was not available around the
country and the higher initial capital cost. The
improvement in natural gas availability and the presence
of gas distribution companies is likely to see an increase
in gas engines. Microturbines are not indigenously
available. A joint venture between Allied Signal andThermax was announced, but was subsequently discon-
tinued.
For fuel cells, the technology considered here is the
PEM fuel cells (USDOE, 1998) that operates at low
temperatures 80 C. The disadvantage is that it can
only withstand a small proportion of impurities (carbon
monoxide). Fuel cells are not indigenously available
commercially though there are prototype PEM cells
developed by SPIC Foundation in Chennai and BHEL.
Even considering an optimistic estimate of $3000/kW
for the fuel cell and the reformer, the cost of generation
is still high. At a discount rate of 10% the PEM fuel cell
competes with diesel engines at load factors of 70% and
higher. At a 80% load factor the price of electricity from
a PEM fuel cell is Rs. 4.7/kW h with the capital cost
accounting for 70% of the cost of generation. In case of
a discount rate of 30%, fuel cells do not compete at any
load factor.
5. Cost of generation from renewables
5.1. Wind turbines
Most of the installed wind capacity is grid-connected.
The total installed capacity in September 2002 was
1702MW (MNES, October 2002). Most of this
(1639 MW) is from commercial projects. Individual
machines range from 55 to 1250kW. There are a
number of Indian companies with foreign collaborators
(Suzlon, Enercon, Vestas, REPL, BHEL) who aremanufacturing and marketing wind turbines and gen-
erators. The wind resources of India have been mapped
(data from 1000 monitoring stations throughout the
country). A potential site is considered viable in case the
average winds speeds at a height of 50m is above
200W=m2. Wind speeds are high during the monsoonmonths (June to August) with relatively weak winds
during the rest of the year. The viability of wind is
critically dependent on the capacity factor that is site
specific. The average capacity factor for wind installa-
tions in India can be computed by dividing the average
power generation by the sum of the rated capacities of
ARTICLE IN PRESS
Fig. 3. Cost of generation from diesel engine-generator.0
5000
10000
15000
20000
25000
30000
35000
40000
45000
0 0.2 0.4 0.6 0.8 1
Load Factor
AnnualisedLifeC
ycleCosts
Rs/kWi
nstalled
Diesel
Gas Engine
Micro Turbine
Fig. 4. Comparison of non-renewable options (d= 0.3).
1Private companies in the manufacturing sector India perceive a
scarcity of capital and have high discount rates. The bank interest rate
in India has recently been reduced and it is expected that this would
result in a lowering of company discount rates.
R. Banerjee / Energy Policy ] (]]]]) ] ]]]]]4
8/14/2019 Banerejee_Energy Policy (in press).pdf
5/11
all the installations. The annual generation in 20012002
was 1966 GW h resulting in an average capacity factor of
only 13.3%. Table 2 shows the input data, the ALCC
and costs of generation for wind.
The average cost of generation (at the average load
factor of 13.3%) is Rs. 5.14/kW h. This implies that
several unviable wind turbines have been installed. Thiswas due to the intial incentives based on capital
subsidies and tax benefits due to 100% depreciation.
Incentives were not linked to generation. Profit making
companies set up wind farms to avail of the tax benefits.
In many cases due to improper siting, the actual
generation and capacity factors were low. There have
been policy correlations. This resulted in a slow down of
capacity additions during 19961998 followed by a more
sustainable wind capacity addition. The initial experi-
ence had many unviable wind machines being installed
in a hurry to avail tax benefits without considering wind
siting issues. Many of the machines were designed for
European wind regimes that are different from the
Indian wind regime (more seasonal and monsoon
driven). The MNES has tried to improve the capacity
utilization through technology development and em-
phasis on micro-siting. The MNES has established a
dedicated research center for wind energy technology
(CWET).
India has a large wind resource assessment effort with
more than 1000 wind monitoring stations. The wind
energy programme operates commercially and is facili-
tated by the availability of innovative financing schemes
from the Indian Renewable Energy Development
Agency (IREDA).In order to promote wind, the government has
provided several incentives like 100% accelerated
depreciation. Many state governments have provided
capital subsidies (Andhra Pradesh, Maharashtra, Kar-
nataka upto 20%), sales tax exemption. Most utilities
permit wheeling, banking and buy-back (purchase price
of Rs. 2.25/kW h in 19941995 with an escalation of 5%
per year). Often wind farms are permitted to carry out
third party sale. In states that have energy shortages, a
company could install a wind farm to shield itself from
mandatory power cuts. A chemical company in Gujarat
(Excel Industries) invested in a wind farm in Dhag thathad a low capacity factor of 10%. This was still
considered to be a viable investment by the industry
since the Bhavnagar plant was exempt from power cuts
by the Gujarat Electricity Board during periods of
shortage because of its wind generation.
A wind turbine is different from the non-renewable
options for DG discussed earlier since its output
fluctuates during the day and over the year. Figs. 5a
and b show the hourly variation and the monthlyvariation in the wind for a site on the west coast of
India. This implies that wind needs to have a grid
backup to meet the requirements for DG. The potential
for wind power has been estimated to be 45,000 MW
with 15,000 MW being the technical potential (assuming
a low grid penetration).
Though most state regulatory commissions are
allowing a preferential tariff for wind power, the state
electricity boards feel that large wind farms (e.g. more
than 300 MW at Vankasuwde in Satara district of
Maharashtra) supply the maximum output to the grid in
the monsoon months when the system demand is at its
lowest. An additional 5000 MW from wind is being
targeted by 2012. For isolated systems wind diesel and
WindDieselPV hybrids have a significant potential.
The wind energy programme in India has made the
transition from demonstration to commercialization
and can be further strengthened by indigenous technol-
ogy development (especially for wind turbines of smaller
rating in the kW range and controllers). It is expected
that for the new installations optimal equipment
selection and siting will result in higher capacity factors.
ARTICLE IN PRESS
Table 2
Cost of generation from wind
0.1 0.2 0.3 0.4
d 0:1 ALCC Rs. 5960 6048 6136 6223Rs./kW h 6.80 3.45 2.33 1.78
d 0:3 ALCC Rs. 15 167 15 255 15 342 15 430Rs./kW h 17.31 8.71 5.84 4.40
Capital cost Rs. 50,000/kW, O&M cost Rs. 0.1/kWh, Life 20 years.
0
1
2
3
4
5
6
7
8
9
Time of day (hours)
Avgwindspeedm/s
0
20
40
60
80
100
January
February
March
AprilMay
JuneJuly
August
September
October
Novem
ber
Decem
ber
Month
NormalizedPowerOutput(%)
0 4 8 12 16 20 24
(a)
(b)
Fig. 5. (a) Daily variation of wind (Sanodar, West Coast); (b)
Monthly variation of wind power (Sanodar, West coast India).
R. Banerjee / Energy Policy ] (]]]]) ] ]]]]] 5
8/14/2019 Banerejee_Energy Policy (in press).pdf
6/11
Annual capacity factors of 38% have been reached at
some of the Indian sites.
5.2. Solar photovoltaic
The daily average solar insolation incident over India
varies from 4 to 7kWh=m2 depending on the location.Most regions in the country get about 300 clear sunny
days a year. Figs. 6a and b show the variation in the
solar insolation for a typical day and for different
months during the year for Mumbai. A solar PV system
converts the incident solar radiation directly into
electricity using silicon based solar cells. For the
modules available, the efficiencies range between
1015%. In PV systems the capacity factor is decided
by the insolation characteristics at the site with a
maximum capacity factor of 25%. The advantage of
PV is ease of operation and negligible operating cost.India has both monocrystalline silicon and polycrys-
talline silicon cells. Manufacturers include Tata-BP,
Shell, BHEL, and Central Electronics limited. The total
installed capacity of solar PV in India was 65 MW in
2002. This includes home lighting, street lighting, water
pumping and stand-alone power systems. The grid
connected systems account for only about 2.5 MW (31
systems average about 80 kW and largest about 240 kW
peak). The annual production of PV cells in 19992000
was 9.6 MW and 11MW of PV modules (Annual
ReportsMNES, 2000, 2001, 2002).
The economics is computed for a grid connected
system with no requirement for storage. For isolated
systems there is an additional cost of storage batteries.
Table 3shows the cost of generation from solar PV. PV
is expected to have niche markets in remote areas,
islands etc. The main advantage is the maintenance free
operation. For the PV systems installed for village
electrification (Sunderbans in West Bengal) almost the
entire capital cost has been provided as a capital
subsidy. If subsidies are continued, there may be a
number of remote villages electrified through PV since
systems are modular and can be quickly installed.
However the costs are significantly higher than the
other renewable options.
5.3. Biomass gasifiers operating gas engines
Fuelwood, agricultural residues (rice husk, sugarcane
trash, coconut shells...) and animal waste are the main
biomass fuels available in India. The advantage of
biomass fuels is that they are available throughout the
country. Different biomass sources are available indifferent regions. Biomass (fuelwood, crop residues and
cattle dung) accounts for about 40% of Indias primary
energy use (TERI, 2000). At present biomass is mainly
used for cooking in chulhas (cookstoves) with poor
efficiency.
Aggregate estimates of biomass availability can be
made from the crop production data and the residue to
product ratio. Using this approach, Mukunda (1999)
estimated the biomass produced in India in 19971998
to be 545 million tons. Of this, about 150 million tons is
expected to be available for power generation. This is
estimated to be made up of 23% rice straw, 18% wheatstraw, 16% other straw, 15% bagasse and 12% plant
stalks. These residues are estimated to have a generation
capacity of 16,000 to 18,000 MW with a plant load
factor of 68.5% (6000 h per year). MNES estimates a
potential of 3500MW from Bagasse based power
generation and an additional 16,000 MW from other
biomass that is already available (Annual Report
MNES, 2002).
In addition to residues that are available, it is possible
to have dedicated plantations on waste land or degraded
lands that are not normally used for agriculture. In
social forestry programmes sustainable yields of
ARTICLE IN PRESS
0
0.2
0.4
0.6
0.8
1
1.2
0 2 4 6 8 10
Time in hrs.
SolarradiationkW/m2
0
1
2
3
4
5
6
7
8
Month
AvgDailySolarRadiation(kW
h/m2/day)
12 14 16 18 20 22 24
1 2 3 4 5 6 7 8 9 10 11 12
(a)
(b)
Fig. 6. (a) Daily solar radiation (Mumbai, May); (b) Variation in
monthly solar radiation (Mumbai).
Table 3
Cost of generation from solar PV
Capital cost Rs./kW 200 000 250 000 300 000
LF 0:2 ALCC Rs. 23,930 29,803 35,676Rs./kW h 13.66 17.01 20.36
LF 0:25 ALCC Rs. 24,039 29,912 35,785
Rs./kW h 10.98 13.66 16.34
O&M Rs. 0.25/kWh, Life 20 years, discount rate = 10%.
R. Banerjee / Energy Policy ] (]]]]) ] ]]]]]6
8/14/2019 Banerejee_Energy Policy (in press).pdf
7/11
78 tons/hectare/year have been achieved (Ravindranath
and Hall, 1995). The waste land available in the country
has been estimated to be between 66130 million
hectares (Mukunda, 1999). Using an average productiv-
ity of 5 tons/hectare/year and 100 million hectares of
waste land the total biomass available annually is 500
million tons which can fuel power generation of60,000 MW at a plant load factor of 68.5% (6000 h/
year).
The options for conversion of biomass into electricity
are combustion, gasification, IGCC, pyrolysis (Ganesh
and Banerjee, 2001). The biomass can be converted into
producer gas by gasification (partial combustion).
Thermochemical gasification involves burning the bio-
mass with insufficient air so that complete combustion
does not occur and producer gas is formed. Producer
gas is a mixture of carbon monoxide and hydrogen.
Gasifiers are classified as updraft or downdraft depend-
ing on the direction of flow of the biomass and the
producer gas. In a downdraft gasifier the biomass and
the gases flow in the same direction (downwards).
In a typical downdraft gasifier the biomass is fed from
the top. It passes through the gasifier and undergoes the
following sequence of processesdrying, pyrolysis,
oxidation and reduction (Parikh, 1984). The gas formed
is passed through a cooling and cleaning sub-system that
usually consists of a cyclone for particulate removal and
a scrubber for cooling and cleaning the gas (removing
the tar). Some ash is formed from the oxidation
reactions. The ash moves through the reduction zone
and gets removed from the ash disposal system (grate
and ash collection system). The typical composition ofproducer gas is 2022% CO, 1518% H2, 24% CH4,
911% CO2 and 5053% N2 (by volume). This is a low
calorific value fuel with a calorific value of
10001200 kcal=Nm3.India has significant experience in atmospheric fixed
bed gasifiers. About 1700 gasifiers have been installed
with a total installed capacity of 34 MW. The average
gasifier size is 20 kW. Biomass gasifiers were initially
developed for diesel replacement in agricultural pump-
sets. Gasifier models were indigenously developed
around 1986. During the initial years of the National
Demonstration Programme (19861994) the emphasiswas on agricultural pumpsets of 5 and 10 hp rating. A
feature of this programme was heavy subsidies on
gasifiers, pump-sets and diesel engines. It is estimated
that the majority of installations (80%) during this
phase become inoperative within one to three years of
the system installation (ASCENT, 1998). Target bene-
ficiaries took little interest in the programme and
reverted back to full diesel operation, after the initial
few hundred hours of operation. Subsidies were misused
to obtain a diesel engine pump-set at a cheaper rate.
Despite this, there was important technology demon-
stration experience obtained in the installations that
continued to operate with gasifiers. Since 1994 subsidies
were reduced and were only available for the gasifier.
This initially resulted in a drop in the number of annual
installations, but the programme is now more market
oriented.
Biomass gasifiers have been developed either for wood
or for rice-husk. Other fuels that have been used arecotton stalks, coconut shells, saw dust, palm shells, corn
cobs. Installations range from 3 to 500 kW capacity. The
biomass input required ranges from 5 to 500 kg/h for
electrical outputs ranging from 5 to 500 kW. The largest
installation size is 500 kW in Gujarat that is being
connected to the grid. A 500 kW 5100 kW rural
electrification system has been installed at Gosaba in
Sunderbans (West Bengal). A 100 kW rice husk based
gasifier has been installed in a rice mill in Andhra
Pradesh. Almost all gasifier systems installed are stand
alone. Most installations use diesel engines in the dual
fuel mode. There are a number of manufacturers
Ankur Scientific (Ascent, Baroda), Netpro, Cosmos
(Raipur), AEW and Tanaku. Decentralized Energy
Systems India (DESI Power, 2003) has set up six
projects as independent rural power producers (IRPP)
in various parts of the country. The first installation was
at Orchcha in Madhya Pradesh (100 kW rating2 units
of 50 kW each). DESI power estimates that a 100 kW
IRPP will directly employ 11 persons and another 56
downstream jobs in new small scale industries (because
of the availability of electricity). Instead of a diesel
engine being operated in the dual-fuel mode that has a
high operating cost and emissions because of the diesel
fuel, it is preferable to opt for a dedicated spark ignitionengine operated on producer gas. There are a few
installations in the countryIISc Bangalore has set up a
100 kW dedicated engine in a milk chilling plant in
Arnekal near Bangalore. Ankur has set up 100 kW gas
engines in an industry near Baroda.Table 4shows the
input data for the calculation.
Fig. 7shows the cost of generation from this option.
It is clear that this is preferable to diesel engines at load
factors of 20% or higher. In case biomass is available,
this can operate like a dispatchable power plant.
Biomass gasifier-engines appear to be a potentially
cost effective DG solution. This has a potential forwidespread diffusion since biomass can be obtained
from waste lands using dedicated plantations. It is
ARTICLE IN PRESS
Table 4
Input data for the biomass gasifier-engine
Gasifier Engine-generator
Capital cost (Rs./kW) 20 000 33 000
Life 10 years 20 years
Efficiency 70% 35%
Biomass NCV = 3400kcal/kg; Price Rs. 1/kg; Discount rate = 10%;
O&M cost = Rs. 0.5/kWh.
R. Banerjee / Energy Policy ] (]]]]) ] ]]]]] 7
8/14/2019 Banerejee_Energy Policy (in press).pdf
8/11
necessary to have assured biomass supply as the viability
would depend locally on the biomass price. It is expected
that the optimal ratings would be between 50500 kW. It
is seen that the dedicated biomass fired engine has a cost
of generation comparable to the gas engine. The main
advantage for this option is that it would operate on
locally available resources, unlike the gas engine that
would require natural gas transport and supply to the
rural areas (this might increase the cost of energy from
the gas engine). The viability of the biomass option is
critically dependent on the availability and price ofbiomass. (The present value is Rs. 0.07/MJ or half the
price of natural gas on an equivalent energy basis.) The
main usage of biomass in the rural areas of India is for
cooking. This is often collected from local wood lots or
from areas near forests. There is no well developed
market for biomass in most rural areas. Hence a
dedicated biomass based power plant should ensure
that it has a dedicated plantation attached to it. In case
of isolated gasifierengine systems it is essential that
the system is coupled with an industrial load (cold
storage, rice mill, oil mill etc.) so that the demand load
factor can be improved and the revenue can be ensured.The operation of the gasifier requires operator training.
The institutional mechanism for cost recovery and plant
operation needs a number of policy experiments. Most
of the installations have been subsidized and operated
by the technology supplier. Independent assessment of
actual costs incurred and operating experiences need to
be documented and disseminated before launching a
large biomass gasifier engine programme. The present
manufacturer base and number of energy service
companies (ESCOs) is sub-critical for a large scale
programme. One possible solution is a setting up of a
public-sector (on joint sector) national company the
National Bio Power Corporation (modelled on the lines
of the National Thermal Power Corporation).
5.4. Bagasse cogeneration in sugar factories
All sugar factories use bagasse as a fuel in their boilers
to generate process steam and also to generate theelectricity and shaft work required by the plant.
Cogeneration is the simultaneous generation of power
(electricity or motive power/shaft work) and process
heat (steam). The process steam required in sugar
factories is at low pressuresmost of the steam is
required at 2 atm absolute (ata,) a small portion is
required at 6 ata. Traditionally sugar factories have been
designed to meet most of their power requirements
during the crushing season from the bagasse itself. All
sugar factories already have cogeneration of steam and
power. However the steam generation pressures are low
(usually 21 atm absolute (ata)). The mill turbines and
power turbines are old and inefficient.
If the steam generation pressures are increased by
using a high pressure boiler, the sugar factories can
export surplus power to the grid. A large number of
options are possible. The options proposed have been to
replace the milling turbines by efficient electric motors
and the power turbine by an efficient backpressure
turbine, increasing the generation pressure, using a
condensing extraction turbine. An improved configura-
tion that uses steam at 65 ata and passes through a
condensing extraction turbine provides surplus power
for export of 9.5 MW for a 2500 tons of cane crushed
per day (tcd) plant (Smouse et al., 1998). For a givenconfiguration, it is possible to select an optimal steam
generation pressure (Raghu Ram and Banerjee, 2003).
MNES estimates indicate a potential of 3500 MW net
(additional) exportable capacity from the Indian sugar
factories. Thirty four bagassebased cogeneration
projects aggregating 210 MW have been commissioned
till March 2001. The average export capacity of these
plants is 6 MW per plant. The projects implemented
have been with steam conditions of 60 ata (some are
lower). New cogeneration projects designed with steam
conditions of 87 ata and 515 C are being implemented
(Annual reportMNES, 2002. Bagasse based cogenera-tion has the problem that the mill operates only during
the crushing season, 79 months a year.) Bagasse can be
supplemented using other biomass fuels such as cane
trash and rice hulls so that there is power export
throughout the year.
There are about 430 sugar mills in India. In terms of
equivalent 2500 tpd mills, about 360 were in operation
during 19961997 (Smouse et al., 1998). Based on the
option discussed earlier, this would result in an
exportable power output of about 3500 MW. Sugarcane
production has been increasing at 35% per year. Hence
the cogeneration potential can be expected to increase at
ARTICLE IN PRESS
0
2
4
6
8
10
12
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Load Factor
CostofGeneration
Rs/kWh
Gas Engine
Bioengine
Diesel
Fig. 7. Cost of generation from bio-engine.
R. Banerjee / Energy Policy ] (]]]]) ] ]]]]]8
8/14/2019 Banerejee_Energy Policy (in press).pdf
9/11
this rate. The capital cost of the plant is around $450/
kW of output or $650/kW of exportable surplus. This
works out to around Rs. 30,000 per kW of surplus
power which is cheaper than setting up a new fossil fuel
power plant.
MNES provides an interest subsidy on term loans for
cogeneration in sugar. The interest rate reduction is 3%for 80 ata and above, 2% for 6080 ata and 1% for
4060 ata. Most state governments have announced
policies that fix buy back rates, permit wheeling and
banking Tata Energy Data Directory (1999). To
encourage co-generation in co-operative and public
sector mills a joint venture/ Independent Power Produ-
cer model has been proposed by MNES in the major
sugar producing states. Capital subsidies are available
for the first projects of these types in each state.
Many of the sugar factories are in the co-operative
sector. They are traditional industries with limited
technical capability. Often the sugar factory does not
have the confidence to operate high pressure steam
based power plants. The capital investments are
significant, about Rs. 300 million for a 2500 tcd plant,
and the sugar factories are hesitant to make these
investments. At present boilers and turbines are avail-
able in India from suppliers like BHEL, Thermax,
ISGEC, Triveni. Grid interconnection and recovery of
dues from the State Electricity Board is perceived as a
problem. Some states have announced a special tariff for
Biomass Cogeneration (e.g the Maharashtra Electricity
Regulatory Commissions recent tariff order). This tariff
makes it viable for the sugar factory, even if it operates
during the crushing season only. The bagasse basedcogeneration option is only viable for large plants
2500 tcd or higher. Hence this option is suitable for
510 MW or more. This is the cheapest of the options
considered, since only the incremental cost is charged to
power generation.
The efforts to promote bagasse based cogeneration
seem to be providing the desired results. Access to soft
loans for the capital investment and the development of
a number of energy service companies (ESCOs) that
could prepare detailed project reports and build, own
and operate the plants may accelerate the installation of
Bagasse based cogeneration (Table 5).
6. Conclusions
The summary of the different options evaluated is
presented inTable 6. The cost of generation of different
DG options depends on the load factor. For some of the
renewable options the system load factor is constrained
by the supply availability.Among the non-renewable DG options considered,
diesel engines are prevalent in India. This is because of
the scarcity of capital and low load factors (use as
backup power). In view of the government liquid
fuel policy gas engines are likely to be the preferred
option for DG. Gas engines are cost competitive in
view of the relatively low natural gas price. These are
likely to be the preferred option for DG in areas
where natural gas is available. The existing engine
manufacturers need to promote their gas engines in
India. For PEM fuel cells and micro-turbines based
on natural gas, there is a need to have a few
demonstration projects and obtain experience with these
technologies. Technology development and cost reduc-
tions could make either of these technologies
cost-competitive.
Among the renewable technologies considered wind
energy is growing significantly because of the supportive
policy environment. For sites where the capacity factor
is 30% or more, wind is competitive at present prices.
Even though the comparison shows a price of Rs. 5.84/
kW h, the accelerated depreciation and tax benefits
provided make it a viable investment even at a selling
price of Rs. 3/kW h.
Biomass gasifiers operating dedicated gas engines is aDG option that is almost cost effective and seems suited
for rural areas. At present engine availability is a
constraint. Engine manufacturers are not keen to
develop producer gas engines as they are unsure of the
volumes. Biomass availability, system standardization
and institutional issues need to be addressed before this
option can achieve widespread diffusion. A national
level Bio-power corporation to provide technology
solutions and operation and maintenance support may
help this option reach its potential. Bagasse based
cogeneration is cost-effective at present prices and is
likely to provide about 3000 MW of surplus power tothe grid.
Solar PV does not seem to be a viable option for grid
connected systems, at present prices. However, the
technology is mature and requires low maintenance.
This is the preferred option for small remote systems.
For isolated systems hybrid systems of PV-Wind diesel
are likely to be cost-effective (IIT Bombay, 2002).
Accordingly to estimates of the Ministry of Power
(MOP, 2003a, b) there are about 18,000 villages that are
remote and difficult to connect to the grid. These
villages can be electrified by DG systems. This would
result in a potential of about 500 MW of small isolated
ARTICLE IN PRESS
Table 5
Data and calculations for Bagasse cogeneration
Incremental capital cost (Rs./kW) 30 0 00
Life 20 years
Boiler efficiency 70%
Load factor 0.4 0.5 0.6
Rs./kW h 2.60 2.40 2.27
Bagasse NCV = 3400 kcal/kg (dry basis); Price Rs. 1.50/kg; Discount
rate = 10%; O&M cost = Rs. 0.5/kWh; 2500 tcd plant 9.5 MW
export; 0.93 kg extra/kWh.
R. Banerjee / Energy Policy ] (]]]]) ] ]]]]] 9
8/14/2019 Banerejee_Energy Policy (in press).pdf
10/11
systems. The difficulty for these systems is the need to
match the supply with the load profile. For this
constraint hybrids of two renewables or renewable-fossil
can be shown to perform better than power plants
based on a single technology. The isolated systems are
likely to be costlier than the grid connected systems. In
isolated systems, the DG system viability increasesby the inclusion of an industry load (cold storage,
rice mill...).
Different institutional models adopted for DG in
India have been reviewed in the Gokak Committee
report (Gokak, 2003). The Sunderbans model
involves a village committee that manages the project
and collects bills from members, the local enterprise
that operates and maintains the plant and the nodal
agency (West Bengal Renewable Energy Development
Agency). The Uttam Urja project in Rajasthan
is an example of private Energy Supply Companies
operating a DG project in collaboration with TERIand manufacturers. A large number of DG projects
have to be initiated through different institutional
mechanisms and the results tracked. The national
strategy should involve demonstrations and pilot
projects with some of the new technologies (PEM
fuel cells, micro turbines), dissemination of successful
implementation mechanisms, tracking of actual
costs of generation from different DG options and
promotion of the cost-effective options. This
strategy could result in increasing the share of DG to
10% of the total electricity by 2012, as envisaged by
the Government.
Acknowledgements
The author is grateful for financial support from the
Carnegie Mellon Electricity Industry Center for the
duration of this work.
References
Ackerman, T., Andersson, G., Sodder, L., 2001. Distributed genera-
tion: a definition. Electric Power Systems Research 57, 195204.
ASCENT, 1998. Status of Biomass Gasification Technology, India,
October 1998; http://www.bgtechnologies.net/ankur.htm.
Borbely, A.M., Kreider, J.F., 2001. Distributed Generation, The
Power Paradigm for the New Millennium. CRC Press, Boca
Raton, USA.
DESI Power, 2003. www.desipower.com.
Ganesh, A., Banerjee, R., 2001. Biomass pyrolysis for power
generationa potential technology. Renewable Energy 22, 914.
Gokak Committee Report on Distributed Generation, 2003. Sub-
mitted to the Ministry of Power, Government of India, 2003;available at powermin.nic.in.
ICRA, 2003. Indian Credit Rating Agency New Delhi, Rating Feature,
The Indian Natural Gas Industry, January; available on the web at
//www.icraindia.com/biz-arch/naturalgasindustry-changes.pdf .
Ministry of Non Conventional Energy Sources, 2001. Renewable
Energy in India, Business Opportunities, Government of India,
March 2001.
Ministry of Non Conventional Energy Sources, 2002. Wind power
development in India: Towards global leadership; New Delhi,
October 2002.
Ministry of Non Conventional Energy Sources, Annual Reports, New
Delhi, 1993, 2000, 2001, 2002.
Ministry of Power, 2001. Blueprint for Power Sector Development,
Government of India, New Delhi; available at powermin.nic.in.
ARTICLE IN PRESS
Table 6
Summary of DG options
Type Technology
status
Capacity factor Cost of generated
electricityd 0:1Comments
Diesel NR C, I N LF 0:5 Rs: 5:10=kW h
LF 0:8 Rs: 4:85=kWh
Existing base of more than 10,000 MW
as backup.
Gas engine NR C N LF 0:5 Rs: 2:62=kW h
LF 0:8 Rs: 2:29=kW h
Relative price of Natural gas low
Micro turbine fuelled
by natural gas
NR D N LF 0:5 Rs: 3:24=kW h
LF 0:8 Rs: 2:82=kW h
Technology not proven in India
Fuel cell fuelled by
natural gas
NR D N LF 0:5 Rs: 6:64=kW h
LF 0:8 Rs: 4:68=kW h
Technology demonstration required
Wind turbines R C, I 13% Avg Max
3038%
LF 0:2 Rs: 8:71=kW h
LF 0:3 Rs: 5:84=kW h
2000 MW already installed
PV R C, I Max 25% LF 0.25 Rs.17/kW h Niche applications Grid connected
systems 2.5 MW installed (80240kW)
BiomassGasifier R C N LF 0:5 Rs: 3:16=kW hGasEngine Gasifier-I LF 0:8 Rs: 2:59=kW hBiomass Cogen R C, I 50% Higher if aux
fuel is used
LF 0:5 2:40=kW h
LF 0:6 2:27=kW h
About 300 MW installed export
capacity in 2002
NRNon Renewable; IIndigenous; RRenewable; DDemonstration; CCommercially available technology; NNot constrained by the
supply.
R. Banerjee / Energy Policy ] (]]]]) ] ]]]]]10
http://www.bgtechnologies.net/ankur.htmhttp://www.bgtechnologies.net/ankur.htmhttp://www.desipower.com/http://www.icraindia.com/biz-arch/naturalgasindustry-changes.pdfhttp://www.icraindia.com/biz-arch/naturalgasindustry-changes.pdfhttp://www.icraindia.com/biz-arch/naturalgasindustry-changes.pdfhttp://www.desipower.com/http://www.bgtechnologies.net/ankur.htm8/14/2019 Banerejee_Energy Policy (in press).pdf
11/11
Ministry of Power, 2003a. Annual Report 20022003, Government of
India, New Delhi.
Ministry of Power, 2003b. Discussion Paper on Rural Electrification
Policies, November 2003, Government of India, New Delhi.
Mukunda, H. S., 1999. A biomass option for enhancing energy
security. NIAS Report R4-99, National Institute of Advanced
Studies, IISc Bangalore.
Parikh, P.P., 1984. State of the Art Report on Gasification of Biomass,Report submitted to DNES, Government of India.
Raghu Ram, J., Banerjee, R., 2003. Energy and cogeneration targeting
for a sugar factory. Applied Thermal Engineering 23, 15671575.
Ravindranath, N.H., Hall, D.O., 1995. Biomass Energy, and
Environment, A Developing Country Perspective From India.
Oxford University Press, New York.
Resource Dynamics Corporation, 2001. Assessment of Distributed
Generation Technology Applications, Prepared for Maine Public
Utilities Commission by Resource Dynamics Corporation, Vienna,
VA, USA; available on the web at //www.distributed-generation.-
com.
Smouse, S.M., Staats, G.E., Rao, S.N., Golman, R., Hess, D.,
1998. Promotion of biomass cogeneration with power export
in the Indian sugar industry. Fuel Processing Technology 54,
227247.
Tata Energy Data Directory, 1999. Tata Energy Research Institute,New Delhi, 2000.
USDOE, Department of Energy, 1998. Fuel Cell Handbook, Fourth
Edition, November 1998, Office of Fossil Energy, Federal Energy
Technology Centre, Pittsburgh, USA; available on the web at //
www.fetc.doe.gov/publications .
USDOE, 2003. Energy Prices from the Energy Information Admin-
istration, US Department of Energy; available on the web athttp://
www.eia.doe.gov/price.html .
ARTICLE IN PRESS
R. Banerjee / Energy Policy ] (]]]]) ] ]]]]] 11
http://www.distributed-generation.com/http://www.distributed-generation.com/http://www.distributed-generation.com/http://www.fetc.doe.gov/publicationshttp://www.fetc.doe.gov/publicationshttp://www.eia.doe.gov/price.htmlhttp://www.eia.doe.gov/price.htmlhttp://www.eia.doe.gov/price.htmlhttp://www.eia.doe.gov/price.htmlhttp://www.fetc.doe.gov/publicationshttp://www.fetc.doe.gov/publicationshttp://www.distributed-generation.com/http://www.distributed-generation.com/