Banerejee_Energy Policy (in press).pdf

Embed Size (px)

Citation preview

  • 8/14/2019 Banerejee_Energy Policy (in press).pdf

    1/11

    Energy Policy ] (]]]]) ]]]]]]

    Comparison of options for distributed generation in India

    Rangan Banerjee,1

    Department of Engineering and Public Policy, Carnegie Mellon University, Pittsburgh, PA 15217, USA

    Abstract

    There is renewed interest in distributed generation (DG). This paper reviews the different technological options available for DG,

    their current status and evaluates them based on the cost of generation and future potential in India. The non-renewable options

    considered are internal combustion engines fuelled by diesel, natural gas and microturbines and fuel cells fired by natural gas. Therenewable technologies considered are wind, solar photovoltaic, biomass gasification and bagasse cogeneration. The cost of

    generation is dependent on the load factor and the discount rate. Gas engines and Bagasse based cogeneration are found to be the

    most cost effective DG options while wind and biomass gasifier fired engines are viable under certain conditions. PEM Fuel cells and

    micro turbines based on natural gas need a few demonstrations projects and cost reductions before becoming viable. A strategy

    involving pilot projects, tracking of costs and dissemination of information is likely to result in DG meeting 10% of Indias power

    needs by 2012.

    r 2004 Elsevier Ltd. All rights reserved.

    Keywords: Distributed generation; Annualized life cycle cost; Load factor

    1. Introduction

    The earliest electric power systems were distributed

    generation (DG) systems intended to cater to the

    requirements of local areas. Subsequent technology

    developments driven by economies of scale resulted in

    the development of large centralized grids connecting up

    entire regions and countries. The design and operating

    philosophies of power systems have emerged with a

    focus on centralized generation. During the last decade,

    there has been renewed interest in DG. This paper

    reviews the different technological options available for

    DG, their current status and evaluates them based on

    the cost of generation and future potential. Therelevance of these options for a developing country

    context is examined using data for India.

    Different definitions of DG have been proposed.

    Some have linked this to the size of the plant, suggesting

    that DG should be from a few kW to sizes less than 10

    or 50 MW.Ackerman et al. (2001) provides a review of

    alternative definitions of DG and suggests that DG be

    defined as the installation and operation of electric power

    generation units connected directly to the distribution

    network or connected to the network on the customer site

    of the meter. DG is also referred to as dispersed

    generation or embedded generation. DG options can

    be classified based on the prime movers usedengines,

    turbines, fuel cells or based on the fuel source as

    renewable or non-renewable. There are a large number

    of possible system configurations.In this review the comparison is limited to the

    following options:

    (A) Non-Renewable

    1. Internal combustion engine fuelled by diesel

    2. Internal combustion engine fuelled by natural gas

    3. Micro-turbine fuelled by natural gas

    4. Proton exchange membrane (PEM) fuel cell with

    reformer fuelled by natural gas

    ARTICLE IN PRESS

    www.elsevier.com/locate/enpol

    0301-4215/$- see front matter r 2004 Elsevier Ltd. All rights reserved.

    doi:10.1016/j.enpol.2004.06.006

    Corresponding author. IIT Bombay, Energy Systems Engineering,

    Powai, Mumbai 400076, India. Tel.: +91-22-2576-7883; fax: +91-22-

    2572-6875.

    E-mail address: [email protected] (R. Banerjee).1On leave from Indian Institute of Technology Bombay.

    http://www.elsevier.com/locate/enpolhttp://www.elsevier.com/locate/enpol
  • 8/14/2019 Banerejee_Energy Policy (in press).pdf

    2/11

    (B) Renewable

    5. Wind turbine

    6. Solar photovoltaic (PV)

    7. Biomass gasifier connected to a spark ignition engine

    (dedicated gas engine)

    8. Bagasse cogeneration in sugar factories

    Other options that have not been considered here are

    small hydropower, geothermal, ocean thermal, tidal and

    solar thermal power generation options. In order to

    place DG in the context of the Indian power sector, a

    brief background of the Indian power scenario is

    provided before comparing the DG options.

    2. Indian power sector

    India had an installed capacity of 105,000 MW

    (Ministry of Power, 2003a, b) in the centralized power

    utilities on 31st March 2003. Of this 74,400 MW is

    accounted for by thermal power plants, 26,300 MW of

    large hydro plants and 2700 MW of nuclear. The focus

    of power planning has been to extend the centralized

    grid throughout the country. However the capacity

    addition has not been able to keep pace with the

    increasing demand for electricity. This is reflected by the

    persistent energy and peak shortages in the country. The

    transmission and distribution losses are extremely high

    (estimated to be more than 25%, this includes theft).

    India has a plan to add 100000MW of additional

    power generation capacity by 2012 (MOP, 2001). This

    requires an average capacity addition of more than10,000 MW per year. Centralized generation alone is

    unlikely to meet this target. In this context DG is likely

    to be important. DG also has the advantage of

    improving tail-end voltages, reducing distribution losses

    and improving system reliability.

    The present installed capacity of DG is about

    13,000 MW (10,000 MW diesel, 3000 MW renewables).

    The majority of this is accounted for by diesel engines

    that are used for back-up power (in the event of grid

    failure) and operate at very low load factors. The share

    of the energy generation from DG is marginal (about

    23% of the total generation). Apart from the dieselengines, the DG options that have been promoted in

    India are modern renewables.

    India is probably the only country with a separate

    Ministry of Non-conventional Energy Sources (MNES).

    The renewable energy installed capacity was 205.5MW

    in 1993 (104.6 MW small hydro, 39.9 MW Wind). This

    increased to 2978 MW in 2001 (as on 31st March 2001)

    and accounted for almost 3% of Indias installed power

    capacity (MNES, 2001; Annual Reports MNES, 2000,

    2001, 2002). The growth rate of installed renewable

    power capacity during the period 19932001 was 39%

    per year. During the period January 2000April 2001

    the installed capacity increased from 1600 MW to

    2978 MW (an annual growth rate of 49%).

    Fig. 1 shows the installed capacity of different

    renewable energy technologies (Annual Report MNES,

    2002). The major contributors are small hydro

    o25 MW which accounts for 1341 MW (45%) and

    wind which accounts for 1267 MW (42%). The installedcapacity in Biomass based power generation is 308 MW

    (10.3%), with most of it coming from bagasse based

    cogeneration. Most of the installed capacity available

    from renewables is accounted for by grid connected

    systems (wind, small hydro and biomass cogeneration).

    This accounts for about 3% of Indias installed capacity

    contribute to about 12% of the total generation (due to

    low capacity factors on renewables). The growth rate

    has been significant (above 30% per year). This has been

    facilitated by an enabling policy environment and a

    supportive government.

    Despite the emphasis on extending the centralized

    grid to the rural areas, 78 million rural households

    (Ministry of Power, 2003b) or 56.5% of rural house-

    holds are still unelectrified. The recently passed Elec-

    tricity Act (2003) has made it a statutory obligation to

    supply electricity to all areas including villages and

    hamlets. The act suggests a two pronged approach

    encompassing grid extension and through standalone

    systems. The act provides for enabling mechanisms for

    service providers in rural areas and exempts them from

    licensing obligations. MNES has been given the

    responsibility of electrification of 18,000 remote villages

    through renewables. The ministry has set up an

    ambitious target of meeting 10% of the power require-ments of India from renewables by 2012 . In most cases,

    the areas to be electrified do not have sufficient paying

    capacity. Most systems are subsidized by the Govern-

    ment or the utility. The power sector has significant

    losses and needs to ensure that the DG systems selected

    are likely to be cost-effective. This paper examines the

    cost effectiveness of the different DG options selected.

    ARTICLE IN PRESS

    1267 1341

    63 35 15 47

    210

    0

    200

    400

    600

    800

    1000

    1200

    1400

    1600

    Wind

    SmallHydro

    BioCombn

    BioCogen

    Gasifiers

    Waste-

    Energy

    SolarPV

    InstalledCapacity(M

    W) Total Renewable Installed capacity 2978 MW

    31/3/2001 MNES

    Fig. 1. Installed capacity of renewables in India.

    R. Banerjee / Energy Policy ] (]]]]) ] ]]]]]2

  • 8/14/2019 Banerejee_Energy Policy (in press).pdf

    3/11

    3. Comparison methodology

    In order to compare the costs of generation of

    electricity from each of these options, the annualized

    life cycle cost (ALCC) is used. The annualized life cycle

    cost represents the annual cost of purchase and

    operation of the system. The cost of generated electricity

    is obtained by dividing the ALCC by the annual

    generation.

    The ALCC is computed as

    ALCC C0 CRFd; n ACfACO&M; 1

    whereC0 is the initial capital cost for the option, ACf is

    the annual fuel cost for the option and ACO&M is the

    annual operating and maintenance cost for the option.

    The capital recovery factor (CRF) is computed based on

    the discount ratedand the life of the option n using the

    equation

    CRFd; n d1dn=1dn 1: 2

    The annual generation is dependent on the load factor.

    The cost of generation is dependent on the size and the

    application load factor. In this paper a 100 kW peak

    rating is used as the basis except for wind and biomass

    cogeneration that are considered to be in the range of a

    few MW. The calculations are done with existing Indian

    fuel and equipment prices. In the case of technologies

    not commercially available in India the existing inter-

    national prices in US $ have been converted to Indian

    rupees at the prevalent exchange rates (1 US $ 47 Rs.

    in 2003). An idea of the comparative costs of options

    and impact of the load factor will provide an idea of the

    viability of the DG option. The status of each option in

    India is discussed along with some of the issues relevant

    for its adoption.

    4. Non-renewable cost of generation

    Table 1 shows the input data used for the economic

    calculations.

    Fig. 2 shows the annualized life cycle costs of the

    diesel, gas engine and micro-turbine options, as a

    function of the load factor. It is clear that except at

    very low load factors, the gas engine and microturbine

    option seem cheaper than the diesel engine. One of the

    main reasons for this is the availability of relatively

    cheaper natural gas (Rs. 0.144/MJ of energy) in India as

    compared to diesel (Rs. 0.464/MJ of energy). The ratio

    of the diesel price to the natural gas price on a per unit

    of delivered energy is 3.2. In the US the price of natural

    gas in January 2003 (USDOE, 2003) was 4.47$/1000ft3

    (Rs. 0.167/MJ) and the price of diesel oil to industrial

    consumers was 82.5 c/gal (Rs. 0.297/MJ) resulting in aratio of 1.8 of diesel price to natural gas price. It is likely

    that the differential between diesel and natural gas

    prices in India would reduce in the future.

    This comparison is done with a societal discount rate

    of 10%. The price of power from diesel engine

    generators is Rs. 4.8/kWh (10 c/kW h) at 80% load

    factor with fuel cost accounting for 86% of the cost of

    generation. Fig. 3 shows the cost of generation from

    diesel engine-generators as a function of the load factor.

    The industrial tariff prevalent in Maharashtra is shown

    for comparison. It is seen that electricity from the grid

    is cheaper for load factors greater than 15%. (Tariff

    ARTICLE IN PRESS

    Table 1

    Input cost data used for calculations

    Option Capital cost (Rs./kW) Life ZEfficiency O&M cost Rs./kW h

    Diesel engine 25000 20 40% 0.25

    Gas engine 33000 20 35% 0.25

    Micro turbine 45000 20 28% 0.25

    Fuel cell 141000 10 45% 0.25

    Discount rated= 0.1; natural gas price = Rs. 5200/1000sm3; diesel price = Rs.16/l, density = 850kg/m3; LHV = 9700kcal/kg.

    Sources:ICRA, 2003; Borbely and Kreider, 2001;Resources Dynamics Corporation, 2001.

    0

    5000

    10000

    15000

    20000

    25000

    30000

    35000

    40000

    45000

    50000

    0 0.2 0.4 0.6 0.8 1

    Load Factor

    AnnualisedLifeCycleC

    ost(Rs/kW/year) Diesel

    Gas Engine

    MicroTurbine

    Fuel Cell

    Fig. 2. Comparison of annualized life cycle costs for non-renewables

    (Discount rate = 10%).

    R. Banerjee / Energy Policy ] (]]]]) ] ]]]]] 3

  • 8/14/2019 Banerejee_Energy Policy (in press).pdf

    4/11

    for large industrial consumers receiving high tension

    supply.)

    For private sector companies that have a higher

    discount rate1 d30%, the comparison is shown in

    Fig. 4. It is seen that diesel engines are preferred at load

    factors of 20% or less (less than 5 h per day). This is

    probably the reason for the large base of diesel engine-

    generators for back up power in India that provide

    uninterrupted power supply in the event of grid failure.

    Diesel engines are manufactured indigenously (major

    companies include Cummins, Wartsila, Kirloskar and

    Greaves) and there is significant experience in India in

    the operation, maintenance and repair of diesel engine-

    generators. About 10,000 MW of diesel engine capacity

    exists in India. Only a small portion of this is connected

    to the grid. Most of these operate with very low loadfactors. From the national viewpoint there is an attempt

    to discourage diesel based power plants since India has a

    middle distillate bulge (scarcity of middle distillates like

    diesel) that is constrained by the refinery mix and

    necessitates the import of petroleum products.

    Natural Gas engines are not as common, probably

    because natural gas was not available around the

    country and the higher initial capital cost. The

    improvement in natural gas availability and the presence

    of gas distribution companies is likely to see an increase

    in gas engines. Microturbines are not indigenously

    available. A joint venture between Allied Signal andThermax was announced, but was subsequently discon-

    tinued.

    For fuel cells, the technology considered here is the

    PEM fuel cells (USDOE, 1998) that operates at low

    temperatures 80 C. The disadvantage is that it can

    only withstand a small proportion of impurities (carbon

    monoxide). Fuel cells are not indigenously available

    commercially though there are prototype PEM cells

    developed by SPIC Foundation in Chennai and BHEL.

    Even considering an optimistic estimate of $3000/kW

    for the fuel cell and the reformer, the cost of generation

    is still high. At a discount rate of 10% the PEM fuel cell

    competes with diesel engines at load factors of 70% and

    higher. At a 80% load factor the price of electricity from

    a PEM fuel cell is Rs. 4.7/kW h with the capital cost

    accounting for 70% of the cost of generation. In case of

    a discount rate of 30%, fuel cells do not compete at any

    load factor.

    5. Cost of generation from renewables

    5.1. Wind turbines

    Most of the installed wind capacity is grid-connected.

    The total installed capacity in September 2002 was

    1702MW (MNES, October 2002). Most of this

    (1639 MW) is from commercial projects. Individual

    machines range from 55 to 1250kW. There are a

    number of Indian companies with foreign collaborators

    (Suzlon, Enercon, Vestas, REPL, BHEL) who aremanufacturing and marketing wind turbines and gen-

    erators. The wind resources of India have been mapped

    (data from 1000 monitoring stations throughout the

    country). A potential site is considered viable in case the

    average winds speeds at a height of 50m is above

    200W=m2. Wind speeds are high during the monsoonmonths (June to August) with relatively weak winds

    during the rest of the year. The viability of wind is

    critically dependent on the capacity factor that is site

    specific. The average capacity factor for wind installa-

    tions in India can be computed by dividing the average

    power generation by the sum of the rated capacities of

    ARTICLE IN PRESS

    Fig. 3. Cost of generation from diesel engine-generator.0

    5000

    10000

    15000

    20000

    25000

    30000

    35000

    40000

    45000

    0 0.2 0.4 0.6 0.8 1

    Load Factor

    AnnualisedLifeC

    ycleCosts

    Rs/kWi

    nstalled

    Diesel

    Gas Engine

    Micro Turbine

    Fig. 4. Comparison of non-renewable options (d= 0.3).

    1Private companies in the manufacturing sector India perceive a

    scarcity of capital and have high discount rates. The bank interest rate

    in India has recently been reduced and it is expected that this would

    result in a lowering of company discount rates.

    R. Banerjee / Energy Policy ] (]]]]) ] ]]]]]4

  • 8/14/2019 Banerejee_Energy Policy (in press).pdf

    5/11

    all the installations. The annual generation in 20012002

    was 1966 GW h resulting in an average capacity factor of

    only 13.3%. Table 2 shows the input data, the ALCC

    and costs of generation for wind.

    The average cost of generation (at the average load

    factor of 13.3%) is Rs. 5.14/kW h. This implies that

    several unviable wind turbines have been installed. Thiswas due to the intial incentives based on capital

    subsidies and tax benefits due to 100% depreciation.

    Incentives were not linked to generation. Profit making

    companies set up wind farms to avail of the tax benefits.

    In many cases due to improper siting, the actual

    generation and capacity factors were low. There have

    been policy correlations. This resulted in a slow down of

    capacity additions during 19961998 followed by a more

    sustainable wind capacity addition. The initial experi-

    ence had many unviable wind machines being installed

    in a hurry to avail tax benefits without considering wind

    siting issues. Many of the machines were designed for

    European wind regimes that are different from the

    Indian wind regime (more seasonal and monsoon

    driven). The MNES has tried to improve the capacity

    utilization through technology development and em-

    phasis on micro-siting. The MNES has established a

    dedicated research center for wind energy technology

    (CWET).

    India has a large wind resource assessment effort with

    more than 1000 wind monitoring stations. The wind

    energy programme operates commercially and is facili-

    tated by the availability of innovative financing schemes

    from the Indian Renewable Energy Development

    Agency (IREDA).In order to promote wind, the government has

    provided several incentives like 100% accelerated

    depreciation. Many state governments have provided

    capital subsidies (Andhra Pradesh, Maharashtra, Kar-

    nataka upto 20%), sales tax exemption. Most utilities

    permit wheeling, banking and buy-back (purchase price

    of Rs. 2.25/kW h in 19941995 with an escalation of 5%

    per year). Often wind farms are permitted to carry out

    third party sale. In states that have energy shortages, a

    company could install a wind farm to shield itself from

    mandatory power cuts. A chemical company in Gujarat

    (Excel Industries) invested in a wind farm in Dhag thathad a low capacity factor of 10%. This was still

    considered to be a viable investment by the industry

    since the Bhavnagar plant was exempt from power cuts

    by the Gujarat Electricity Board during periods of

    shortage because of its wind generation.

    A wind turbine is different from the non-renewable

    options for DG discussed earlier since its output

    fluctuates during the day and over the year. Figs. 5a

    and b show the hourly variation and the monthlyvariation in the wind for a site on the west coast of

    India. This implies that wind needs to have a grid

    backup to meet the requirements for DG. The potential

    for wind power has been estimated to be 45,000 MW

    with 15,000 MW being the technical potential (assuming

    a low grid penetration).

    Though most state regulatory commissions are

    allowing a preferential tariff for wind power, the state

    electricity boards feel that large wind farms (e.g. more

    than 300 MW at Vankasuwde in Satara district of

    Maharashtra) supply the maximum output to the grid in

    the monsoon months when the system demand is at its

    lowest. An additional 5000 MW from wind is being

    targeted by 2012. For isolated systems wind diesel and

    WindDieselPV hybrids have a significant potential.

    The wind energy programme in India has made the

    transition from demonstration to commercialization

    and can be further strengthened by indigenous technol-

    ogy development (especially for wind turbines of smaller

    rating in the kW range and controllers). It is expected

    that for the new installations optimal equipment

    selection and siting will result in higher capacity factors.

    ARTICLE IN PRESS

    Table 2

    Cost of generation from wind

    0.1 0.2 0.3 0.4

    d 0:1 ALCC Rs. 5960 6048 6136 6223Rs./kW h 6.80 3.45 2.33 1.78

    d 0:3 ALCC Rs. 15 167 15 255 15 342 15 430Rs./kW h 17.31 8.71 5.84 4.40

    Capital cost Rs. 50,000/kW, O&M cost Rs. 0.1/kWh, Life 20 years.

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    Time of day (hours)

    Avgwindspeedm/s

    0

    20

    40

    60

    80

    100

    January

    February

    March

    AprilMay

    JuneJuly

    August

    September

    October

    Novem

    ber

    Decem

    ber

    Month

    NormalizedPowerOutput(%)

    0 4 8 12 16 20 24

    (a)

    (b)

    Fig. 5. (a) Daily variation of wind (Sanodar, West Coast); (b)

    Monthly variation of wind power (Sanodar, West coast India).

    R. Banerjee / Energy Policy ] (]]]]) ] ]]]]] 5

  • 8/14/2019 Banerejee_Energy Policy (in press).pdf

    6/11

    Annual capacity factors of 38% have been reached at

    some of the Indian sites.

    5.2. Solar photovoltaic

    The daily average solar insolation incident over India

    varies from 4 to 7kWh=m2 depending on the location.Most regions in the country get about 300 clear sunny

    days a year. Figs. 6a and b show the variation in the

    solar insolation for a typical day and for different

    months during the year for Mumbai. A solar PV system

    converts the incident solar radiation directly into

    electricity using silicon based solar cells. For the

    modules available, the efficiencies range between

    1015%. In PV systems the capacity factor is decided

    by the insolation characteristics at the site with a

    maximum capacity factor of 25%. The advantage of

    PV is ease of operation and negligible operating cost.India has both monocrystalline silicon and polycrys-

    talline silicon cells. Manufacturers include Tata-BP,

    Shell, BHEL, and Central Electronics limited. The total

    installed capacity of solar PV in India was 65 MW in

    2002. This includes home lighting, street lighting, water

    pumping and stand-alone power systems. The grid

    connected systems account for only about 2.5 MW (31

    systems average about 80 kW and largest about 240 kW

    peak). The annual production of PV cells in 19992000

    was 9.6 MW and 11MW of PV modules (Annual

    ReportsMNES, 2000, 2001, 2002).

    The economics is computed for a grid connected

    system with no requirement for storage. For isolated

    systems there is an additional cost of storage batteries.

    Table 3shows the cost of generation from solar PV. PV

    is expected to have niche markets in remote areas,

    islands etc. The main advantage is the maintenance free

    operation. For the PV systems installed for village

    electrification (Sunderbans in West Bengal) almost the

    entire capital cost has been provided as a capital

    subsidy. If subsidies are continued, there may be a

    number of remote villages electrified through PV since

    systems are modular and can be quickly installed.

    However the costs are significantly higher than the

    other renewable options.

    5.3. Biomass gasifiers operating gas engines

    Fuelwood, agricultural residues (rice husk, sugarcane

    trash, coconut shells...) and animal waste are the main

    biomass fuels available in India. The advantage of

    biomass fuels is that they are available throughout the

    country. Different biomass sources are available indifferent regions. Biomass (fuelwood, crop residues and

    cattle dung) accounts for about 40% of Indias primary

    energy use (TERI, 2000). At present biomass is mainly

    used for cooking in chulhas (cookstoves) with poor

    efficiency.

    Aggregate estimates of biomass availability can be

    made from the crop production data and the residue to

    product ratio. Using this approach, Mukunda (1999)

    estimated the biomass produced in India in 19971998

    to be 545 million tons. Of this, about 150 million tons is

    expected to be available for power generation. This is

    estimated to be made up of 23% rice straw, 18% wheatstraw, 16% other straw, 15% bagasse and 12% plant

    stalks. These residues are estimated to have a generation

    capacity of 16,000 to 18,000 MW with a plant load

    factor of 68.5% (6000 h per year). MNES estimates a

    potential of 3500MW from Bagasse based power

    generation and an additional 16,000 MW from other

    biomass that is already available (Annual Report

    MNES, 2002).

    In addition to residues that are available, it is possible

    to have dedicated plantations on waste land or degraded

    lands that are not normally used for agriculture. In

    social forestry programmes sustainable yields of

    ARTICLE IN PRESS

    0

    0.2

    0.4

    0.6

    0.8

    1

    1.2

    0 2 4 6 8 10

    Time in hrs.

    SolarradiationkW/m2

    0

    1

    2

    3

    4

    5

    6

    7

    8

    Month

    AvgDailySolarRadiation(kW

    h/m2/day)

    12 14 16 18 20 22 24

    1 2 3 4 5 6 7 8 9 10 11 12

    (a)

    (b)

    Fig. 6. (a) Daily solar radiation (Mumbai, May); (b) Variation in

    monthly solar radiation (Mumbai).

    Table 3

    Cost of generation from solar PV

    Capital cost Rs./kW 200 000 250 000 300 000

    LF 0:2 ALCC Rs. 23,930 29,803 35,676Rs./kW h 13.66 17.01 20.36

    LF 0:25 ALCC Rs. 24,039 29,912 35,785

    Rs./kW h 10.98 13.66 16.34

    O&M Rs. 0.25/kWh, Life 20 years, discount rate = 10%.

    R. Banerjee / Energy Policy ] (]]]]) ] ]]]]]6

  • 8/14/2019 Banerejee_Energy Policy (in press).pdf

    7/11

    78 tons/hectare/year have been achieved (Ravindranath

    and Hall, 1995). The waste land available in the country

    has been estimated to be between 66130 million

    hectares (Mukunda, 1999). Using an average productiv-

    ity of 5 tons/hectare/year and 100 million hectares of

    waste land the total biomass available annually is 500

    million tons which can fuel power generation of60,000 MW at a plant load factor of 68.5% (6000 h/

    year).

    The options for conversion of biomass into electricity

    are combustion, gasification, IGCC, pyrolysis (Ganesh

    and Banerjee, 2001). The biomass can be converted into

    producer gas by gasification (partial combustion).

    Thermochemical gasification involves burning the bio-

    mass with insufficient air so that complete combustion

    does not occur and producer gas is formed. Producer

    gas is a mixture of carbon monoxide and hydrogen.

    Gasifiers are classified as updraft or downdraft depend-

    ing on the direction of flow of the biomass and the

    producer gas. In a downdraft gasifier the biomass and

    the gases flow in the same direction (downwards).

    In a typical downdraft gasifier the biomass is fed from

    the top. It passes through the gasifier and undergoes the

    following sequence of processesdrying, pyrolysis,

    oxidation and reduction (Parikh, 1984). The gas formed

    is passed through a cooling and cleaning sub-system that

    usually consists of a cyclone for particulate removal and

    a scrubber for cooling and cleaning the gas (removing

    the tar). Some ash is formed from the oxidation

    reactions. The ash moves through the reduction zone

    and gets removed from the ash disposal system (grate

    and ash collection system). The typical composition ofproducer gas is 2022% CO, 1518% H2, 24% CH4,

    911% CO2 and 5053% N2 (by volume). This is a low

    calorific value fuel with a calorific value of

    10001200 kcal=Nm3.India has significant experience in atmospheric fixed

    bed gasifiers. About 1700 gasifiers have been installed

    with a total installed capacity of 34 MW. The average

    gasifier size is 20 kW. Biomass gasifiers were initially

    developed for diesel replacement in agricultural pump-

    sets. Gasifier models were indigenously developed

    around 1986. During the initial years of the National

    Demonstration Programme (19861994) the emphasiswas on agricultural pumpsets of 5 and 10 hp rating. A

    feature of this programme was heavy subsidies on

    gasifiers, pump-sets and diesel engines. It is estimated

    that the majority of installations (80%) during this

    phase become inoperative within one to three years of

    the system installation (ASCENT, 1998). Target bene-

    ficiaries took little interest in the programme and

    reverted back to full diesel operation, after the initial

    few hundred hours of operation. Subsidies were misused

    to obtain a diesel engine pump-set at a cheaper rate.

    Despite this, there was important technology demon-

    stration experience obtained in the installations that

    continued to operate with gasifiers. Since 1994 subsidies

    were reduced and were only available for the gasifier.

    This initially resulted in a drop in the number of annual

    installations, but the programme is now more market

    oriented.

    Biomass gasifiers have been developed either for wood

    or for rice-husk. Other fuels that have been used arecotton stalks, coconut shells, saw dust, palm shells, corn

    cobs. Installations range from 3 to 500 kW capacity. The

    biomass input required ranges from 5 to 500 kg/h for

    electrical outputs ranging from 5 to 500 kW. The largest

    installation size is 500 kW in Gujarat that is being

    connected to the grid. A 500 kW 5100 kW rural

    electrification system has been installed at Gosaba in

    Sunderbans (West Bengal). A 100 kW rice husk based

    gasifier has been installed in a rice mill in Andhra

    Pradesh. Almost all gasifier systems installed are stand

    alone. Most installations use diesel engines in the dual

    fuel mode. There are a number of manufacturers

    Ankur Scientific (Ascent, Baroda), Netpro, Cosmos

    (Raipur), AEW and Tanaku. Decentralized Energy

    Systems India (DESI Power, 2003) has set up six

    projects as independent rural power producers (IRPP)

    in various parts of the country. The first installation was

    at Orchcha in Madhya Pradesh (100 kW rating2 units

    of 50 kW each). DESI power estimates that a 100 kW

    IRPP will directly employ 11 persons and another 56

    downstream jobs in new small scale industries (because

    of the availability of electricity). Instead of a diesel

    engine being operated in the dual-fuel mode that has a

    high operating cost and emissions because of the diesel

    fuel, it is preferable to opt for a dedicated spark ignitionengine operated on producer gas. There are a few

    installations in the countryIISc Bangalore has set up a

    100 kW dedicated engine in a milk chilling plant in

    Arnekal near Bangalore. Ankur has set up 100 kW gas

    engines in an industry near Baroda.Table 4shows the

    input data for the calculation.

    Fig. 7shows the cost of generation from this option.

    It is clear that this is preferable to diesel engines at load

    factors of 20% or higher. In case biomass is available,

    this can operate like a dispatchable power plant.

    Biomass gasifier-engines appear to be a potentially

    cost effective DG solution. This has a potential forwidespread diffusion since biomass can be obtained

    from waste lands using dedicated plantations. It is

    ARTICLE IN PRESS

    Table 4

    Input data for the biomass gasifier-engine

    Gasifier Engine-generator

    Capital cost (Rs./kW) 20 000 33 000

    Life 10 years 20 years

    Efficiency 70% 35%

    Biomass NCV = 3400kcal/kg; Price Rs. 1/kg; Discount rate = 10%;

    O&M cost = Rs. 0.5/kWh.

    R. Banerjee / Energy Policy ] (]]]]) ] ]]]]] 7

  • 8/14/2019 Banerejee_Energy Policy (in press).pdf

    8/11

    necessary to have assured biomass supply as the viability

    would depend locally on the biomass price. It is expected

    that the optimal ratings would be between 50500 kW. It

    is seen that the dedicated biomass fired engine has a cost

    of generation comparable to the gas engine. The main

    advantage for this option is that it would operate on

    locally available resources, unlike the gas engine that

    would require natural gas transport and supply to the

    rural areas (this might increase the cost of energy from

    the gas engine). The viability of the biomass option is

    critically dependent on the availability and price ofbiomass. (The present value is Rs. 0.07/MJ or half the

    price of natural gas on an equivalent energy basis.) The

    main usage of biomass in the rural areas of India is for

    cooking. This is often collected from local wood lots or

    from areas near forests. There is no well developed

    market for biomass in most rural areas. Hence a

    dedicated biomass based power plant should ensure

    that it has a dedicated plantation attached to it. In case

    of isolated gasifierengine systems it is essential that

    the system is coupled with an industrial load (cold

    storage, rice mill, oil mill etc.) so that the demand load

    factor can be improved and the revenue can be ensured.The operation of the gasifier requires operator training.

    The institutional mechanism for cost recovery and plant

    operation needs a number of policy experiments. Most

    of the installations have been subsidized and operated

    by the technology supplier. Independent assessment of

    actual costs incurred and operating experiences need to

    be documented and disseminated before launching a

    large biomass gasifier engine programme. The present

    manufacturer base and number of energy service

    companies (ESCOs) is sub-critical for a large scale

    programme. One possible solution is a setting up of a

    public-sector (on joint sector) national company the

    National Bio Power Corporation (modelled on the lines

    of the National Thermal Power Corporation).

    5.4. Bagasse cogeneration in sugar factories

    All sugar factories use bagasse as a fuel in their boilers

    to generate process steam and also to generate theelectricity and shaft work required by the plant.

    Cogeneration is the simultaneous generation of power

    (electricity or motive power/shaft work) and process

    heat (steam). The process steam required in sugar

    factories is at low pressuresmost of the steam is

    required at 2 atm absolute (ata,) a small portion is

    required at 6 ata. Traditionally sugar factories have been

    designed to meet most of their power requirements

    during the crushing season from the bagasse itself. All

    sugar factories already have cogeneration of steam and

    power. However the steam generation pressures are low

    (usually 21 atm absolute (ata)). The mill turbines and

    power turbines are old and inefficient.

    If the steam generation pressures are increased by

    using a high pressure boiler, the sugar factories can

    export surplus power to the grid. A large number of

    options are possible. The options proposed have been to

    replace the milling turbines by efficient electric motors

    and the power turbine by an efficient backpressure

    turbine, increasing the generation pressure, using a

    condensing extraction turbine. An improved configura-

    tion that uses steam at 65 ata and passes through a

    condensing extraction turbine provides surplus power

    for export of 9.5 MW for a 2500 tons of cane crushed

    per day (tcd) plant (Smouse et al., 1998). For a givenconfiguration, it is possible to select an optimal steam

    generation pressure (Raghu Ram and Banerjee, 2003).

    MNES estimates indicate a potential of 3500 MW net

    (additional) exportable capacity from the Indian sugar

    factories. Thirty four bagassebased cogeneration

    projects aggregating 210 MW have been commissioned

    till March 2001. The average export capacity of these

    plants is 6 MW per plant. The projects implemented

    have been with steam conditions of 60 ata (some are

    lower). New cogeneration projects designed with steam

    conditions of 87 ata and 515 C are being implemented

    (Annual reportMNES, 2002. Bagasse based cogenera-tion has the problem that the mill operates only during

    the crushing season, 79 months a year.) Bagasse can be

    supplemented using other biomass fuels such as cane

    trash and rice hulls so that there is power export

    throughout the year.

    There are about 430 sugar mills in India. In terms of

    equivalent 2500 tpd mills, about 360 were in operation

    during 19961997 (Smouse et al., 1998). Based on the

    option discussed earlier, this would result in an

    exportable power output of about 3500 MW. Sugarcane

    production has been increasing at 35% per year. Hence

    the cogeneration potential can be expected to increase at

    ARTICLE IN PRESS

    0

    2

    4

    6

    8

    10

    12

    0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1

    Load Factor

    CostofGeneration

    Rs/kWh

    Gas Engine

    Bioengine

    Diesel

    Fig. 7. Cost of generation from bio-engine.

    R. Banerjee / Energy Policy ] (]]]]) ] ]]]]]8

  • 8/14/2019 Banerejee_Energy Policy (in press).pdf

    9/11

    this rate. The capital cost of the plant is around $450/

    kW of output or $650/kW of exportable surplus. This

    works out to around Rs. 30,000 per kW of surplus

    power which is cheaper than setting up a new fossil fuel

    power plant.

    MNES provides an interest subsidy on term loans for

    cogeneration in sugar. The interest rate reduction is 3%for 80 ata and above, 2% for 6080 ata and 1% for

    4060 ata. Most state governments have announced

    policies that fix buy back rates, permit wheeling and

    banking Tata Energy Data Directory (1999). To

    encourage co-generation in co-operative and public

    sector mills a joint venture/ Independent Power Produ-

    cer model has been proposed by MNES in the major

    sugar producing states. Capital subsidies are available

    for the first projects of these types in each state.

    Many of the sugar factories are in the co-operative

    sector. They are traditional industries with limited

    technical capability. Often the sugar factory does not

    have the confidence to operate high pressure steam

    based power plants. The capital investments are

    significant, about Rs. 300 million for a 2500 tcd plant,

    and the sugar factories are hesitant to make these

    investments. At present boilers and turbines are avail-

    able in India from suppliers like BHEL, Thermax,

    ISGEC, Triveni. Grid interconnection and recovery of

    dues from the State Electricity Board is perceived as a

    problem. Some states have announced a special tariff for

    Biomass Cogeneration (e.g the Maharashtra Electricity

    Regulatory Commissions recent tariff order). This tariff

    makes it viable for the sugar factory, even if it operates

    during the crushing season only. The bagasse basedcogeneration option is only viable for large plants

    2500 tcd or higher. Hence this option is suitable for

    510 MW or more. This is the cheapest of the options

    considered, since only the incremental cost is charged to

    power generation.

    The efforts to promote bagasse based cogeneration

    seem to be providing the desired results. Access to soft

    loans for the capital investment and the development of

    a number of energy service companies (ESCOs) that

    could prepare detailed project reports and build, own

    and operate the plants may accelerate the installation of

    Bagasse based cogeneration (Table 5).

    6. Conclusions

    The summary of the different options evaluated is

    presented inTable 6. The cost of generation of different

    DG options depends on the load factor. For some of the

    renewable options the system load factor is constrained

    by the supply availability.Among the non-renewable DG options considered,

    diesel engines are prevalent in India. This is because of

    the scarcity of capital and low load factors (use as

    backup power). In view of the government liquid

    fuel policy gas engines are likely to be the preferred

    option for DG. Gas engines are cost competitive in

    view of the relatively low natural gas price. These are

    likely to be the preferred option for DG in areas

    where natural gas is available. The existing engine

    manufacturers need to promote their gas engines in

    India. For PEM fuel cells and micro-turbines based

    on natural gas, there is a need to have a few

    demonstration projects and obtain experience with these

    technologies. Technology development and cost reduc-

    tions could make either of these technologies

    cost-competitive.

    Among the renewable technologies considered wind

    energy is growing significantly because of the supportive

    policy environment. For sites where the capacity factor

    is 30% or more, wind is competitive at present prices.

    Even though the comparison shows a price of Rs. 5.84/

    kW h, the accelerated depreciation and tax benefits

    provided make it a viable investment even at a selling

    price of Rs. 3/kW h.

    Biomass gasifiers operating dedicated gas engines is aDG option that is almost cost effective and seems suited

    for rural areas. At present engine availability is a

    constraint. Engine manufacturers are not keen to

    develop producer gas engines as they are unsure of the

    volumes. Biomass availability, system standardization

    and institutional issues need to be addressed before this

    option can achieve widespread diffusion. A national

    level Bio-power corporation to provide technology

    solutions and operation and maintenance support may

    help this option reach its potential. Bagasse based

    cogeneration is cost-effective at present prices and is

    likely to provide about 3000 MW of surplus power tothe grid.

    Solar PV does not seem to be a viable option for grid

    connected systems, at present prices. However, the

    technology is mature and requires low maintenance.

    This is the preferred option for small remote systems.

    For isolated systems hybrid systems of PV-Wind diesel

    are likely to be cost-effective (IIT Bombay, 2002).

    Accordingly to estimates of the Ministry of Power

    (MOP, 2003a, b) there are about 18,000 villages that are

    remote and difficult to connect to the grid. These

    villages can be electrified by DG systems. This would

    result in a potential of about 500 MW of small isolated

    ARTICLE IN PRESS

    Table 5

    Data and calculations for Bagasse cogeneration

    Incremental capital cost (Rs./kW) 30 0 00

    Life 20 years

    Boiler efficiency 70%

    Load factor 0.4 0.5 0.6

    Rs./kW h 2.60 2.40 2.27

    Bagasse NCV = 3400 kcal/kg (dry basis); Price Rs. 1.50/kg; Discount

    rate = 10%; O&M cost = Rs. 0.5/kWh; 2500 tcd plant 9.5 MW

    export; 0.93 kg extra/kWh.

    R. Banerjee / Energy Policy ] (]]]]) ] ]]]]] 9

  • 8/14/2019 Banerejee_Energy Policy (in press).pdf

    10/11

    systems. The difficulty for these systems is the need to

    match the supply with the load profile. For this

    constraint hybrids of two renewables or renewable-fossil

    can be shown to perform better than power plants

    based on a single technology. The isolated systems are

    likely to be costlier than the grid connected systems. In

    isolated systems, the DG system viability increasesby the inclusion of an industry load (cold storage,

    rice mill...).

    Different institutional models adopted for DG in

    India have been reviewed in the Gokak Committee

    report (Gokak, 2003). The Sunderbans model

    involves a village committee that manages the project

    and collects bills from members, the local enterprise

    that operates and maintains the plant and the nodal

    agency (West Bengal Renewable Energy Development

    Agency). The Uttam Urja project in Rajasthan

    is an example of private Energy Supply Companies

    operating a DG project in collaboration with TERIand manufacturers. A large number of DG projects

    have to be initiated through different institutional

    mechanisms and the results tracked. The national

    strategy should involve demonstrations and pilot

    projects with some of the new technologies (PEM

    fuel cells, micro turbines), dissemination of successful

    implementation mechanisms, tracking of actual

    costs of generation from different DG options and

    promotion of the cost-effective options. This

    strategy could result in increasing the share of DG to

    10% of the total electricity by 2012, as envisaged by

    the Government.

    Acknowledgements

    The author is grateful for financial support from the

    Carnegie Mellon Electricity Industry Center for the

    duration of this work.

    References

    Ackerman, T., Andersson, G., Sodder, L., 2001. Distributed genera-

    tion: a definition. Electric Power Systems Research 57, 195204.

    ASCENT, 1998. Status of Biomass Gasification Technology, India,

    October 1998; http://www.bgtechnologies.net/ankur.htm.

    Borbely, A.M., Kreider, J.F., 2001. Distributed Generation, The

    Power Paradigm for the New Millennium. CRC Press, Boca

    Raton, USA.

    DESI Power, 2003. www.desipower.com.

    Ganesh, A., Banerjee, R., 2001. Biomass pyrolysis for power

    generationa potential technology. Renewable Energy 22, 914.

    Gokak Committee Report on Distributed Generation, 2003. Sub-

    mitted to the Ministry of Power, Government of India, 2003;available at powermin.nic.in.

    ICRA, 2003. Indian Credit Rating Agency New Delhi, Rating Feature,

    The Indian Natural Gas Industry, January; available on the web at

    //www.icraindia.com/biz-arch/naturalgasindustry-changes.pdf .

    Ministry of Non Conventional Energy Sources, 2001. Renewable

    Energy in India, Business Opportunities, Government of India,

    March 2001.

    Ministry of Non Conventional Energy Sources, 2002. Wind power

    development in India: Towards global leadership; New Delhi,

    October 2002.

    Ministry of Non Conventional Energy Sources, Annual Reports, New

    Delhi, 1993, 2000, 2001, 2002.

    Ministry of Power, 2001. Blueprint for Power Sector Development,

    Government of India, New Delhi; available at powermin.nic.in.

    ARTICLE IN PRESS

    Table 6

    Summary of DG options

    Type Technology

    status

    Capacity factor Cost of generated

    electricityd 0:1Comments

    Diesel NR C, I N LF 0:5 Rs: 5:10=kW h

    LF 0:8 Rs: 4:85=kWh

    Existing base of more than 10,000 MW

    as backup.

    Gas engine NR C N LF 0:5 Rs: 2:62=kW h

    LF 0:8 Rs: 2:29=kW h

    Relative price of Natural gas low

    Micro turbine fuelled

    by natural gas

    NR D N LF 0:5 Rs: 3:24=kW h

    LF 0:8 Rs: 2:82=kW h

    Technology not proven in India

    Fuel cell fuelled by

    natural gas

    NR D N LF 0:5 Rs: 6:64=kW h

    LF 0:8 Rs: 4:68=kW h

    Technology demonstration required

    Wind turbines R C, I 13% Avg Max

    3038%

    LF 0:2 Rs: 8:71=kW h

    LF 0:3 Rs: 5:84=kW h

    2000 MW already installed

    PV R C, I Max 25% LF 0.25 Rs.17/kW h Niche applications Grid connected

    systems 2.5 MW installed (80240kW)

    BiomassGasifier R C N LF 0:5 Rs: 3:16=kW hGasEngine Gasifier-I LF 0:8 Rs: 2:59=kW hBiomass Cogen R C, I 50% Higher if aux

    fuel is used

    LF 0:5 2:40=kW h

    LF 0:6 2:27=kW h

    About 300 MW installed export

    capacity in 2002

    NRNon Renewable; IIndigenous; RRenewable; DDemonstration; CCommercially available technology; NNot constrained by the

    supply.

    R. Banerjee / Energy Policy ] (]]]]) ] ]]]]]10

    http://www.bgtechnologies.net/ankur.htmhttp://www.bgtechnologies.net/ankur.htmhttp://www.desipower.com/http://www.icraindia.com/biz-arch/naturalgasindustry-changes.pdfhttp://www.icraindia.com/biz-arch/naturalgasindustry-changes.pdfhttp://www.icraindia.com/biz-arch/naturalgasindustry-changes.pdfhttp://www.desipower.com/http://www.bgtechnologies.net/ankur.htm
  • 8/14/2019 Banerejee_Energy Policy (in press).pdf

    11/11

    Ministry of Power, 2003a. Annual Report 20022003, Government of

    India, New Delhi.

    Ministry of Power, 2003b. Discussion Paper on Rural Electrification

    Policies, November 2003, Government of India, New Delhi.

    Mukunda, H. S., 1999. A biomass option for enhancing energy

    security. NIAS Report R4-99, National Institute of Advanced

    Studies, IISc Bangalore.

    Parikh, P.P., 1984. State of the Art Report on Gasification of Biomass,Report submitted to DNES, Government of India.

    Raghu Ram, J., Banerjee, R., 2003. Energy and cogeneration targeting

    for a sugar factory. Applied Thermal Engineering 23, 15671575.

    Ravindranath, N.H., Hall, D.O., 1995. Biomass Energy, and

    Environment, A Developing Country Perspective From India.

    Oxford University Press, New York.

    Resource Dynamics Corporation, 2001. Assessment of Distributed

    Generation Technology Applications, Prepared for Maine Public

    Utilities Commission by Resource Dynamics Corporation, Vienna,

    VA, USA; available on the web at //www.distributed-generation.-

    com.

    Smouse, S.M., Staats, G.E., Rao, S.N., Golman, R., Hess, D.,

    1998. Promotion of biomass cogeneration with power export

    in the Indian sugar industry. Fuel Processing Technology 54,

    227247.

    Tata Energy Data Directory, 1999. Tata Energy Research Institute,New Delhi, 2000.

    USDOE, Department of Energy, 1998. Fuel Cell Handbook, Fourth

    Edition, November 1998, Office of Fossil Energy, Federal Energy

    Technology Centre, Pittsburgh, USA; available on the web at //

    www.fetc.doe.gov/publications .

    USDOE, 2003. Energy Prices from the Energy Information Admin-

    istration, US Department of Energy; available on the web athttp://

    www.eia.doe.gov/price.html .

    ARTICLE IN PRESS

    R. Banerjee / Energy Policy ] (]]]]) ] ]]]]] 11

    http://www.distributed-generation.com/http://www.distributed-generation.com/http://www.distributed-generation.com/http://www.fetc.doe.gov/publicationshttp://www.fetc.doe.gov/publicationshttp://www.eia.doe.gov/price.htmlhttp://www.eia.doe.gov/price.htmlhttp://www.eia.doe.gov/price.htmlhttp://www.eia.doe.gov/price.htmlhttp://www.fetc.doe.gov/publicationshttp://www.fetc.doe.gov/publicationshttp://www.distributed-generation.com/http://www.distributed-generation.com/