Balchik Integrated Water Project in Bulgaria
ISPA Measure 2002 BG 17 P PE 017
WWTP BALCHIK
Works ContractWWTP Balchik
• Commencement Date: 28thJune 2006
• Completion Date: 10th March 2010
• Physical Execution: 100 %
• Contract Price: 3 868 061.09 Euro
• WWTP became operational on 10th March 2010
Taking –over of the Works and Sections ofWWTP Balchik
WWTP BALCHIK
Aeration tank Sludge tank
WWTP BALCHIK
Main Tanks
Scroober installation at
Chlorination Building
WWTP BALCHIK
Balchik Water Supply& Sewerage Network ConnectionsWorks Contract
ISPA Measure 2002 BG 17 P PE 017
• Commencement Date: 07th January 2008
• Completion Date: 23th December 2011
• Physical Execution: 100%
• Contract Price: 8 658 308.34 Euro
• The Water Supply and Sewerage networks became operational on 23th December 2011
Balchik Water Supply& Sewerage Network Connections
Information boards
Balchik Water Supply&Sewerage Network Connections
Main sewerage and house connections
Compaction as layer on sewer line , Part III, Section F
Backdrop Manhole, Part IV, Section A
Balchik Water Supply&Sewerage Network Connections
Excavation on water supply main pipe, Part IV, Section A
Balchik Water Supply& Sewerage Network Connections
Excavation on Water Main – G. Milev Street
Balchik Water Supply& Sewerage Network Connections
Covering pipe for pressure under the Kavarna motorway
Balchik Water Supply& Sewerage Network Connections
Main to Reservoir (Tsarichino) excavation
Balchik Water Supply& Sewerage Network Connections
Welding activities on Tsarichino main pressure conduit