193
50 000 MW HYDROELECTRIC INITIATIVE Government of India Ministry of Power Central Electricity Authority 180 MW BAJOLI-HOLI HYDRO-ELECTRIC PROJECT HIMACHAL PRADESH Preliminary Feasibility Report (DRAFT COPY) JUNE, 2004 Consultant: Himachal Pradesh State Electricity Board ( H.P.Government Undertaking )

Bajoli Holi

Embed Size (px)

DESCRIPTION

s

Citation preview

Page 1: Bajoli Holi

50 000 MW HYDROELECTRIC INITIATIVE

Government of India

Ministry of Power Central Electricity Authority

180 MW BAJOLI-HOLI HYDRO-ELECTRIC PROJECT HIMACHAL PRADESH

Preliminary Feasibility Report

(DRAFT COPY)

JUNE, 2004

Consultant: Himachal Pradesh State Electricity Board ( H.P.Government Undertaking )

Page 2: Bajoli Holi

INDEX

SR.NO. DESCRIPTION PAGE

CHAPTER-I SUMMARY I-1 TO I-8

CHAPTER-II BACKGROUND INFORMATION II-1 TO II-3

CHAPTER-III PROJECT AREA III-1 TO III-2

CHAPTER-IV TOPOGRAPHIC AND GEO-TECHNICAL

ASPECTS IV-1 TO IV-8

CHAPTER-V HYDROLOGY V-1 TO V-38

CHAPTER-VI CONCEPTUAL LAYOUT & PLANNING VI-1 TO VI-10

CHAPTER-VII POWER POTENTIAL STUDIES VII-1 TO VII-28

CHAPTER-VIII POWER EVACUATION VIII-1 TO VIII-9

CHAPTER-IX ENVIRONMENTAL ASPECTS IX-1 TO IX-35

CHAPTER-X INFRASTRUCTURE X-1 TO X-6

CHAPTER-XI CONSTRUCTION PLANNING &

SCHEDULE XI-1 TO XI-6

CHAPTER-XII COST ESTIMATE XII-1 TO XII-36

CHAPTER-XIII ECONOMIC EVALUATION XIII-1 TO XIII-14

Page 3: Bajoli Holi

CHAPTER–I SUMMARY

1.0 SUMMARY

The Bajoli-Holi Hydro-electric Project has been contemplated as a run of

river scheme on river Ravi in Chamba District of H.P. It is an upstream

development of Kutehr Hydro-electric Project (260 MW). This project

comprises a diversion barrage near village Bajoli, intake structure, one no

feeder tunnel, an under ground desilting arrangement to divert 71.74

cumecs of water through a 5 m dia, 14600 m long modified horse shoe

shaped head race tunnel, a surge shaft 12m dia. and ± 96m heigh, a

pressure shaft 4 m dia trifurcating near power house to 2.30 m dia each and

a underground power house near village Barola on the right bank of river

Ravi to accommodate three vertical axis Francis turbines to generate 180

MW (3 x 60 MW) of power.

1.1 GENERAL PROJECT FEATURES

LOCATION

State Himachal Pradesh

District Chamba

River Ravi

Diversion barrage Near village Bajoli

Power house site Near village Barola

HYDROLOGY

Catchment Area at intake site 760 Sq. km.

Snow catchment 372 Sq. km. above El. 4000m

Page 4: Bajoli Holi

I - 2

Mean annual rainfall at Bharmour 899 mm

Design flood 3050 cumecs

DIVERSION STRUCTURE

Type Gated Barrage

Length of Barrage at top ±100.00 m

Max. height from R.B.L 33.00 m

Top El. of Barrage 2018.00 m

Average River Bed level. 1985.00 m

FRL 2015.00 m

MDDL 1993.00 m

SPILLWAY

Design flood 3050 cumecs

Type Gated spillways with radial gates

Nos. of spillways, Crest elevation 6 Nos , El 1987.00

Size of gated spillway 6m x 8m, each.

Energy dissipation Stilling basin

Down stream bed level El. 1975m

INTAKE STRUCTURE

Type Semi circular

Crest level El. 1990.00 m

No. & size of opening 8 No., 5.50 mx3.0 m

FEEDER TUNNEL

No. 1

Size and type 6.00m dia, Circular concrete lined

Page 5: Bajoli Holi

I - 3

Velocity 3.17m/sec

Length ± 300m

Design discharge from intake 89.67 cumecs

DESANDING BASIN

Type Underground.

No. of basins 2 nos.

Length of each basin 380m

Size of basins Width 13.00m, Depth 19.60 m

Minimum particle size to be removed 0.2mm

Flushing tunnel, size 4.00m, D-Shaped

Flushing tunnel, length ± 1000 m

HEAD RACE TUNNEL

No. One

Size & Shape 5m diameter, modified

Horse shoe concrete lined

Length ±14600 m

Design discharge 71.74 cumecs

Slope 1 in 409 m

Velocity 3.65m/sec

SURGE SHAFT

Type Open to sky, Restricted orifice type

Size 12.00 m dia cricular

Orifice 2.15 m dia

Maximum upsurge level El.± 2043 m

Minimum down surge level El.± 1960 m

Bottom level El±.1954 m

Page 6: Bajoli Holi

I - 4

Top level El.± 2050 m

PRESSURE SHAFT

Type Underground

Size:

Main 1 No., 4m dia, ± 440 m long

Branches 3 Nos., 2.30 m dia, ± 20 m long each

Velocity 5.74 m/sec.

POWER HOUSE

Type Underground

Installed capacity 180 MW

No. and capacity of unit 3 Nos. 60 MW

Size of machine hall 50 m x 17 m x 35 m

Type of turbine Francis turbine

Speed of turbine 500 RPM

Gross Head 308 m

Normal tail water level 1700 m

Net operating head for design discharge 278 m

Peaking duration 3 hrs .

TAIL RACE TUNNEL

Shape D-Shaped

Dia 5.00 m

Length ± 450 m

SWITCH YARD

Type Surface

Page 7: Bajoli Holi

I - 5

Size 170 (L) x 35 m (W)

TRANSMISSION LINE

No. of circuits S/C Line

Length of each 35 km.

Voltage 220 KV

POWER GENERATION

Installed capacity 3x60 MW

Annual energy generation

90% dep. Year 762.98 GWH

50% mean year 861.37 GWH

1.2 STUDIES UNDERTAKEN

The Layout of the Bajoli-Holi HEP has been finalized keeping in view

various studies undertaken by HPSEB from time to time to conceive a most

economical and viable scheme on Ravi river.

Proposal-I

This proposal-I envisages diversion structure near village Bajoli water

conductor system comprising 12200 m long HRT on right bank of river

Ravi and power house site near Kala nallah with tail race tunnel of 3500 m

length and losing the head approximate 20 m therefore resultant losing the

capacity of power house. Hence this proposal has been rulled out due to

constraints of high inverse gradient of access tunnel to power house and its

construction difficulties.

Page 8: Bajoli Holi

I - 6

Proposal-II

Present proposal of Bajoli Holi HEP (180 MW) is based on head available

between village Bajoli and Barola. The proposed scheme envisages

diversion of in flows of river Ravi near village Bajoli and 14600 m water

conductor system proposed at right bank and underground power house

near Barola village (opposite of village Holi). This proposal will generate

762.98 Gwh in 90% dependable year.

The alternative proposals are shown in Plate 1.1.

Page 9: Bajoli Holi

I - 7

1.3 COST ESTIMATE & FINANCIAL ASPECTS

COST ESTIMATE

Capital cost of the project (At Price level June. 2004):

Civil works Rs. 415.01 Crore

Electrical works

(P-Production) Rs. 165.61Crore

T-Transmission Rs. 36.03 Crore

Total Rs 616.64

Capital cost of Generation Rs. 649.22 Crore

(Including IDC Rs. 68.60Crore)

Loan 70% Rs. 454.45Crore

Equity 30% Rs. 194.76Crore

Capital cost at purchase center Rs. 688.35 Crore

(Including IDC Rs. 71.70Crore)

Loan 70% Rs. 481.84Crore

Equity 30% Rs. 206.50Crore

FINANCIAL ASPECTS

Cost of generation per MW of

Installed capacity Rs. 3.23Crore

Levelized tariff at PH Rs. 1.60/Kwh

Bus bars in 90% dep. Year

Page 10: Bajoli Holi

I - 8

Levelized tariff at purchase center Rs. 1.93/Kwh

in 90% dep. Year

Energy available for sale in 90% dep. Year 753.82 GWH

(Auxiliary consumption @ 0 .7% &

Transformation losses @ 0.5%).

at power house bus bars

Page 11: Bajoli Holi

I - 9

PARA DESCRIPTION PAGE

1.0 SUMMARY I-1

1.1 GENERAL PROJECT FEATURES I-1 TO I-5

1.2 STUDIES UNDERTAKEN I-5 TO I-6

1.3 COST ESTIMATE & FINANCIAL ASPECTS I-7 TO I-8

PLATE 1.1 ALTERNATIVE PROPOSAL

Page 12: Bajoli Holi

I - 10

SALIENT FEATURES LOCATION State Himachal Pradesh District Chamba River Ravi

Diversion barrage Bajoli Power house site Barola (Opposite village Holi) HYDROLOGY Catchment Area at intake site 760 Sq. km. Snow catchment 372 Sq. km. above El. 4000m Mean annual rainfall at Bharmour 899 mm

Design flood 3050 cumecs DIVERSION STRUCTURE

Type Gated Barrage Length of Barrage at top ±100.00 m

Max. height from R.B.L 33.00 m Top El. of Barrage 2018.00 m Average River Bed level. 1985.00 m

FRL 2015.00 m MDDL 1993.00 m

SPILLWAY Design flood 3050 cumecs Type Gated spillways with radial gates Nos. of spillways, Crest elevation 6 Nos , to 1987.00 Size of gated spillway 6m x 8m, each. Energy dissipation Stilling basin Down stream bed level El. 1975m INTAKE STRUCTURE

Type Semi circular Crest level El. 1990.00 m No. & size of opening 8 No., 5.50 mx3.0 m FEEDER TUNNEL No. 1 Size and type 6.00m dia, Circular concrete lined Velocity 3.17m/sec Length ± 300m Design discharge from intake 89.67 cumec DESANDING BASIN Type Underground.

No. of basins 2 nos. Length of each basin 380m Size of basins Width 13.00m, Depth 19.60 m Minimum particle size to be removed 0.2mm Flushing tunnel, size 4.00m, D-Shaped Flushing tunnel, length ± 1000 m

HEAD RACE TUNNEL No. One Size & Shape 5m diameter, modified

Horse shoe concrete lined Length ±14600 m Design discharge 71.74 cumecs

Slope 1 in 409 m Velocity 3.65m/sec SURGE SHAFT Type Open to sky Restricted orifice type Size 12.00 m dia cricular Orifice 2.15 m dia Maximum upsurge level El.± 2043 m Minimum down surge level El.± 1960 m Bottom level El±.1954 m Top level El.± 2050 m PRESSURE SHAFT/PENSTOCK Type Underground/ Surface Size: Main 1 No., 4m dia, ± 440 m long Branches 3 Nos., 2.30 m dia, ± 20 m long each Velocity 5.74 m/sec. POWER HOUSE Type Underground Installed capacity 180 MW No. and capacity of unit 3 Nos. 60 MW Size of machine hall 50 m x 17 m x 35 m Type of turbine Francis turbine

Page 13: Bajoli Holi

I - 11

Speed of turbine 500 RPM Gross Head 308 m Normal tail water level 1700 m Net operating head for design discharge 278 m Peaking duration 3 hrs . TAIL RACE TUNNEL Shape D-Shaped Dia 5.00 m Length ± 450 m SWITCH YARD Type Surface Size 170 (L) x 35 m (W) TRANSMISSION LINE No. of circuits S/C Line Length of each 35 km. Voltage 220 KV POWER GENERATION Installed capacity 3x60 MW Annual energy generation 90% dep. Year 762.98 GWH 50% mean year 861.37 GWH

Page 14: Bajoli Holi

CHAPTER – II BACKGROUND INFORMATION

2.0 BACKGROUND INFORMTION

2.1 GENERAL INFORMATION

Hydel potential of Ravi basin in H.P. has been identified as 2323.02 MW as

indicated in Plate-I for this basin. Bhuri Singh (450 Kw), Bharmour (20

Kw), Gharola (50 Kw), Baira Suil HEP (198 MW), Chamera Stage-I (540

MW) & Sal Stage-II ( 2 MW), Chamera Stage-II (300 MW) are under

operation at present. The construction works on Hibra (231 MW) renamed

as Chamera Stage-III have also been taken up by Govt. of India through

NHPC. Construction work of Holi HEP (3 MW) has been got completed by

the HPSEB on turn key basis & commissioning of the project is expected

shortly.

MOU’s have been signed with IPP/Central Agency for the projects like Sai-

Kothi, Hibra HEP renamed Chamera HEP Stage-III. Presently, two projects

namely Chamba HEP 126 MW and Bajoli Holi HEP (180 MW) are under

investigation in Ravi basin. The project like Harsar, Kugti, Bharmour,

Budhil, Sal Stage-I, Suil and Kutehr, Bara Bhangahal (170 MW), Chanju

Stage-I (25 MW), Chanju Stage-II (17 MW) & Baira Bihali (15 MW) are

yet to be taken up for investigation. Presently, two projects namely

Chamba HEP 126 MW and Bajoli Holi HEP (180 MW) are under

investigation in Ravi basin.

Bajoli Holi HEP (180 MW) is a upstream development of Kutehr HEP on

right bank of river Ravi to generate 180 MW of power by constructing a

diversion structure near village Bajoli and underground power house near

village Barola..

Page 15: Bajoli Holi

II - 2

2.2 POWER SCENARIOS & EXISTING INSTALLATIONS

2.2.1 POWER ABSORPTION IN NORTHERN REGION

2.2.2 POWER LOAD DEVELOPMENT

The Northern Region comprises the states of Himachal, Haryana, Punjab,

Rajashtan, Jammu & Kashmir, Uttar Pradesh, Uttranchal and Union

territories of Delhi and Chandigarh. The Northern Regional Power Grid

comprises the power system controlled by the Electricity Boards of above

states/Union territories and Bhakhra Beas Management Board.

The Power system in this region is now operating in an inter-connected and

co-ordinated manner. Even in co-ordinated operation of existing hydro,

nuclear and thermal power stations, including benefits from the ongoing

projects and as well from the new schemes cleared by CEA, the Northern

region is expected to face severe power deficits in the 10th Five Year Plan.

The CEA schemes for preparation of PFR under “50,000 MW Hydro-

electric Initiative” schemes launched by the Hob’ble Prime Minister of

India are as under:-

Sr.No. Name of scheme River/Basin

1 Gharopa (114 MW) Beas

2 Gondhala (144 MW) Chenab

3 Bardang (114 MW) -do-

4 Chhatru (108 MW) -do-

5 Khoksar (90 MW) -do-

6 Chamba (126 MW) Ravi

7 Jangi-Thopan (480 MW) Satluj

8 Luhri (465 MW) -do-

9 Tidong-I (90 MW) -do-

10 Tidong-II (90 MW) -do-

11 Yangthang Khab (261 MW) -do-

12 Thopan Powari (402 MW) -do-

13 Bajoli-Holi (180 MW) Ravi

Page 16: Bajoli Holi

II - 3

2.3 NECESSITY OF THE PROJECT AND RELATED ASPECTS

From the growth of peak demand and anticipated installed generation

capacity on the basis of schemes proposed for benefits under

construction/consideration during 10th and early 11th Five Year Plan period,

it is observed that power supply position in the Northern region would

become all the more acute from the start of 10th Five Year Plan and power

region shortages would have to be faced unless additional schemes are

taken up immediately and implemented to derive timely benefits. The most

important source of power development in the Northern region is its

abundant hydro resources located in Himachal Pradesh, Uttar Pradesh,

Uttranchal and Jammu & Kashmir. Priority would have to be given to the

development of these untapped resources because of the following

distinguishing features of the hydro stations.

i) They estimate the most economic source of power development.

ii) They provide the cheapest source of peaking capacity.

iii) They enable improvement in the utilization of thermal/nuclear

power stations in the region.

iv) They provide much needed operation & flexibility to the system.

Thus, there is an urgent need of rapid hydro potential exploitation for

providing additional generation capacity in the Northern region. Among the

various sites, available for hydro development, Bajoli Holi Hydro-electric

Project is considered very attractive from point of view of deriving benefits

during 11th Five Year Plan. The diversion site is located on Chamba-Holi

road and 7 Km from village Naya Gaon. Power house site is to be

connected by providing RCC bridge on river Ravi near village Barola. The

existing communication facilities will be of considerable utility in cutting

down the pre-construction time and costs.

Page 17: Bajoli Holi

II - 4

Page 18: Bajoli Holi

II - 5

PARA DESCRIPTION PAGE

2.0 BACK GROUND INFORMATION II-1

2.1 GENERAL INFORMATION II-1

2.2 POWER SCENARIOS & EXISTING

INSTALLATIONS

II-2

2.2.1 POWER ABSORPTION IN NORTH REGION II-2

2.2.2 POWER LOAD DEVELOPMENT II-2

2.3 NECESSITY OF THE PROJECTS AND

RELATED ASPECTS

II-3

PLATE - 1 MASTER PLAN OF RAVI BASIN

Page 19: Bajoli Holi

CHAPTER - III PROJECT AREA

3.0 PROJECT AREA

3.1 DESCRIPTION OF PROJECT INCLUDING RIVER SYSTEM

Himachal Pradesh has the unique distinction of providing water both to the

Indus and Ganges basins. The major river systems of the region are

Chandra- Bhaga or Chenab the Ravi,the Beas the Satluj and the Yamuna.

These perennial rivers are both snowfed and rain fed and are protected by

fairly extensive cover of natural vegetation.

Bajoli-Holi hydroelectric project is located in Distt. Chamba of Himachal

Pradesh and the project involves the construction of diversion barrage at

latitude 32°16'53’’ & longitude 76°40'45’’ and power house at latitude

32°20'31’’ & longitude 76°32'37’’. This project has been contemplated as

upstream development of Kutehr HEP (260 MW). Max. gross head of 308

m is available for generation of 180 MW power in an underground power

house near village Barola. This project comprises a diversion barrage near

village Bajoli, intake structure one No. feeder tunnel, an under ground

desilting arrangement to divert 71.74 cumecs of water through a 5 m dia,

14600 m long horse shoe head race tunnel, a surge shaft dia 12m and ±

96m height, a pressure shaft 4 m dia trifurcating near power house to 2.30

m dia each and a underground power house near village Barola on the right

bank of river Ravi to accommodate three vertical axis Francis turbines to

generate 180 MW (3 x 60 MW) of power.

The annual power generation from the project in 90% dependable year and

50% mean year will be 762.98 Gwh and 861.37 Gwh respectively.

Page 20: Bajoli Holi

III -

2

3.2 SOCIO-ECONOMIC AND OTHER ASPECTS

The economy of the Himachal Pradesh is predominantly dependent on

agricultural and allied sectors. The per capita income of Himachal Pradesh

in 2000-01 was Rs. 10,942.00 as compared to Rs. 16487.00 at the national

level. The electric power being a vital and essential infrastructure has a

significant role to play in economic upliftment of the state. The

construction of project will provide employment to the local people. When

completed, it will be another step towards realization of the dreams of the

state and exploiting its power potential for heralding an era of progress and

prosperity for not only of Himachal Pradesh but for the entire northern

region.

Page 21: Bajoli Holi

III -

3

Page 22: Bajoli Holi

III -

4

PARA DESCRIPTION PAGE

3.0 PROJECT AREA III-1

3.1 DESCRIPTION OF PROJECT INCLUDING RIVER

SYSTEM

III-1

3.2 SOCIO-ECONOMIC & OTHER ASPECTS III-2

Page 23: Bajoli Holi

CHAPTER-IV TOPOGRAPHIC & GEO-TECHNICAL ASPECTS

4.0 GENERAL

The preliminary geotechnical studies of Bajoli Holi HEP have been got carried

out from GSI and a detailed appraisal note sent by Sh. S. Chopra, Director, DPR

Unit, Geological Survey of India, New Delhi is as under:-

4.1 INTRODUCTION

The Central Electricity Authority (CEA), with a view to fill the gap between

supply and demand in the field of power have embarked on an exercise to assess

the balance hydroelectric potential in the country and rank the schemes thus

identified in various parts of the country in different river basins. As a part of this

exercise, 162 schemes with probable installed capacity of 50,600 MW and located

in various river basins spread over 16 states have to be taken up for preparation of

Pre Feasibility Reports (PFRs) in the first phase. The schemes found feasible are

proposed to be taken up for further development in X and XI Five Year Plans.

The proposed Bajoli Holi Hydroelectric Project is one such scheme identified in

Ravi Basin in Chamba district of Himachal Pradesh State. Bajoli Holi

Hydroelectric Project is a run of the river scheme that envisages the construction

of a 30 m high diversion barrage across the river Ravi, 200 m downstream of its

confluence with Channi nallah (32o16’53”N:76o40’45”E; 52 D/11), about 14.6

km long water conductor system and an underground power house on the right

bank of Ravi, near village Barola (32o20’31”N:76o32’37”E; 52 D/11). The

proposed power house would have installed capacity of 180 MW.

Page 24: Bajoli Holi

IV -

2

4.2 REGIONAL GEOLOGY

The area around the proposed projects is located in Lesser Himalaya in Ravi

Basin and is characterised by sharp crested ridges and deeply dissected valleys.

The main drainage in the area is provided by the river Ravi which originates in

Bara Bhangal area. The river initial reaches up to Khada Mukh between Tipri –

Chamba and Raj Nagar Khas flows along the regional strike of rocks and cuts

across the strike between Khada Mukh and Tipri. The influence of lithology and

structure is clearly evident an drainage by its semidenritic and rectangular pattern

Geologically the region exposes rocks ranging in age from early Proterozoic to

Mesozoic. The rocks of the area are extensively covered by slope debris, fluvial

terraces and fan the deposits of Quaternary recent origin. The statigraphic

succession in the area is given by the officers of GSI and Malviya et al (1991) is

given below:

Age Group Formation Lithology

Triassic -- Khalel Limestone with calcareous

shale and ferruginous clay

Upper Permian -- Salooni Calcareous sandstone

arenaceous shaly limestone,

slate.

Lower Permian -- Panjal Traps Green massive amygdaloidal

basic lava flows

Late Proterozoic Vaikrita Katari Gali Dark grey slate micaceous

sandstone, quartzite, calcareous

siltstone limestone

Manjir Dimictite shale slate sandstone,

limestone

Chamba Slate, phyllite, carbonaceous

slate subordinate quartzite

Page 25: Bajoli Holi

IV -

3

In the area around the proposed projects, the rocks belonging to Varikrita Group

are exposed in the valley of Ravi river. The rock belonging to Chamba Formation

of Vaikrita Group include an assemblage of slates phyllite, carbonaceous slate and

subordinate quartzites. The rocks of Chamba Formation are succeeded by an

assemblage comprising pebbly slate/dimictite, phyllite, shale, sandstone and

limestone belonging to Manjir Formation. The rocks of Manjir Formation are in

turn succeeded by the rocks belonging to Katari Gali Formation which include an

interbedded sequence of the slate, quartzite with limestone and magnesite. The

bands of limestone, calcareous shale and ferruginous chart belonging to Khalel

Formation of Triassic age have been reported to be occurring in east and north of

the arc of proposed projects.

4.3 STRUCTURE AND TECTONICS

Tectonically, the Chamba area is located in Main Himalayan Tectonic Belt

bounded by Indus Suture Zone(ISZ) in north and MBF-I in south (Kumareta

1989). This belt exposes the lithostratigraphic units ranging in age from

Proterozoic to Quaternary. The most important tectonic plane in this belt is Main

Centre Thrust. However, its position between the rivers Beas and Chenab is not

well defined. The other important tectonic feature in this belt is Vaikrita

Thrust(VT). In addition to these tectonic planes following the Himalays trend, a

number of transverse fault dissect the rocks in the area, the prominent ones being

Sundernary Fault, Kishtwar Fault, Ravi Tear and a few other transverse

lineaments which have been picked up with the help of satellite imageries. The

tectonic zone south of Main Himalayan Belt is the Frontal Fold Belt demarcated

by HFB-I in the north and Foot Hill Thrust in south. The structure elements

recorded in the area are both primary and secondary. The primary structures

include bedding and current bedding. The secondary structures include cleavage

and foliation, joints, folds, faults and lineation developed during metamorphic and

tectonic phases. The bedding is marked by colour bands and contacts between

arenaceous and argillaceous beds. The strike of bedding of the rock formations

Page 26: Bajoli Holi

IV -

4

generally various from N200W-S200E to N80O W – S80O E with moderate to low

dips towards NE or SW. There are two sets of cleavages recorded in the rocks i.e.

slaty cleavage fracture cleavage. The trend of these varies between NNE-SSW

and WNW – ESE. The slaty cleavage showing NW-SW Himalayan trend in the

metasedimentary rocks of the area represents axial plane cleavage of folds F1

(Datta & Singh, 1973). In general it is parallel to the bedding of the formations.

The pebbles of Manjir Formation are deformed and their shape indicates these

have been flattened on cleavage plane. The fracture cleavage is parallel F2 folds

that have folded bedding and slaty cleavage. The rocks of the area are jointed and

many of the joint sets are common to all the rocks formations. Prominent joint

sets trend NW-SE, NE-SW and E-W and have moderate to steep dips in general

4.4 SEISMOTECTONIC AND SEISMICITY

From seismotectonic point of view, the area under reference is located on the

western fringe of Kangra Seismic Block (Narula,1991) which is bound by Ravi

Tear in west and Sundernagar fault in east. The litho tectonic packets of the

Himalayan Orogenic Belt are poorly metamorphosed lithol-units of the Tethyan

sequence , high and low grade assemblages of the Central crystalline and other

crystallines and Lesser Himalayan belt respectively along with granitoids and

basic volcanics (Narula et al., 2000). The southern fringe of the Himalayan belt is

occupied by cover rocks of the Frontal Belt. Further south, the Quaternary cover

is represented by alluvial fill along the foredeep and peri-cratonic fills on

attenuated continental crust on northern and southern sides, respectively of Delhi-

Sargoda Ridge.

Within the Himalayan belt, the northernmost conspicuous structural element is the

Main Central Thrust (MCT). From Manali towards east throughout the entire

Himalaya almost up to the eastern syntaxis this is considered as one of the most

important tectonic surfaces. However, NW of Manali, it is not clearly discernible.

Further south, within the lesser Himalayan package, the other important tectonic

Page 27: Bajoli Holi

IV -

5

surface is Vaikrita Thrust (VT). This Lesser Himalayan Belt is separated from the

Frontal belt by the Main Boundary Thrust (MBT). The southern limit of the

Frontal Belt is marked by the Main Frontal Thrust (MFT). Within MBT and

MFT, the belt is traversed by several subsidiary thrusts viz Jawalamukhi Thrust

and Drang Thrust. Evidences of neotectonic activity have been documented at

several places along MBT and in western parts of Jawalamukhi Thrust. The

Frontal Belt package is affected by several regional scale folds, of which

Mastgarh and Paror anticlines are prominent.

In addition to the structural discontinuities sub parallel to Himalayan trend, there

are a number of faults lineaments transverse to this fold-thrust belt. The

Sundarnagar Fault (also known as Manali Fault) is a dextral transverse structures

which extends from Higher Himalayas to Frontal Belt. The Ropar Tear is

considered to be continuation of the Sunder Nagar fault.

A total of 99 seismic events of magnitude > 4.0 have been recorded in the area.

Out of these 20 events have magnitude >5.0 and are mostly confined to depths

less than 40Km. Event having magnitude between 4.0 and 5.0 are prevalent in the

area. Seismic activity in mainly concentrated along the Himalayan Belt

particularly around Chamba. This sector with maximum clustering of seismic

events represent part of Kangra Seismic Zone that continues towards N. Out of 20

events of magnitude >5 about 18 events define this zone. In this part of the

Himalaya, 4 events having magnitude > 6 have been recorded. Out of these, 3

events lie on MBT, which include the famous Kangra Earthquake of 1905. Six

earthquakes in this area have caused considerable damage. The earliest is the

Kangra Earthquake of 4th April, 1905 having Ms = 8.0, Chamba Earthquake of

22nd June 1945 also caused considerable damage to the property. Dharamshala

Earthquake of 14th June, 1978, Dharamshala of Earthquake 26th April, 1986 and

Chamba Earthquake of 24th March 1995 are other major earthquakes that caused

considerable damage in the area. Keeping in view the seismotectonic set up and

seismic status of the area, it has been kept in Zone-V as per. Map of India

Page 28: Bajoli Holi

IV -

6

showing Seismic zones (IS: 1893 (Part-I)-2002). Therefore, it is recommended

that suitable seismic coefficient be determined for site and incorporated in the

design of appurtenant structure of the projects.

4.5 GEOTECHNICAL APPRAISAL

The geological map of the area indicates that almost all the appurtenant structures

of the proposed Bajoli Holi Hydroelectric Project are likely to be located on the

rocks belonging to Katari Gali Formation which could be good foundation as well

as excavation media except for reaches where weathering is deep, carbonaceous

slates are en countered and rocks are fractured or sheared. The exploration at the

site of Kutehr Project located downstream of this scheme indicates that thick

overburden can be expected in the riverbed. Therefore it is suggested that the site

for dam and type of structure be selected after assessing the depth of overburden

in the river bed and on abutments.

The 14.6 km long HRT of the proposed Bajoli Holi Hydroelectric Project is likely

to encounter slates, micaceous sandstone, quartzite and limestone belonging to the

Katari Gali Formation in the initial reaches and dimictite, shale, sandstone and

limestone belonging to Manjir Formation in the final reaches. These rocks are

expected to be fair to good tunnelling media in general except in the reaches

where slate/phyllite are encountered. The problem may be more acute where

these are water charged. Poor rock conditions may also be expected in the reaches

where local faults/shears are encountered. It is suggested that adequate rock

cover over HRT may be provided, especially in the reaches where it negotiates

cross drainages. The perusal of preliminary layout of the scheme indicates that no

provision of intermediate construction adit has been kept along this 14.6 km long

HRT. It may lead to difficult construction conditions. It is suggested that efforts

may be made to provide at least one intermediate construction adit to facilitate

construction.

Page 29: Bajoli Holi

IV -

7

The powerhouse location exposes dimictite, shale, slate and sandstone belonging

to Manjir Formation. It is suggested that the final selection of powerhouse site be

made depending on availability of bed rock in the foundation and adequate space

to host structure and its appurtenants without disturbing the hill slopes. If such a

site is not available on the surface, the structure may be designed as underground

one. The area is located in Zone V as per Map of India Showing Seismic Zone

[IS – 1893(Part – I) 2002]. Therefore suitable seismic coefficient be in corporate

in design of apppurtenants of the project. This geotechnical appraisal is based on

regional geological set up without field visit to the project site.

REFERENCES

1. Datta, R.K. and Singh, Surinder (1975). Report on geological mapping in parts of

Chamba, District Himachal Pradesh, unpubl, GSI Report, FS 1971-72.

2. Kumar, G., Sinha, Roy, S. and Ray, K.K. (1989). Structure and Tectonics in

Himalayan, GSI, spl Publ. 26 pp 85-118

3. Malviya, A.K. Jamwal, J.S. Kachker, A.K. and Pande A.C. (1991) Report on

lithostratigraphy, standardisation and regional correlation of the rocks of Tethyan

Realm of NW Himalaya, Unpublished GSI compilation for F.S. 1982-83 to 1988-

89.

4. Narula, PL (1991). Seismotectonic Evaluation of NW Himalayan, Unpublished

GSI Report.

5. Narula, P.L., Acharayya, S.K. and Banerjee, J. (2000) Seismotectonic Atlas of

India and its Environs. Pub. Geol. Surv. Ind..

Page 30: Bajoli Holi

IV -

8

Page 31: Bajoli Holi

IV -

9

PARA DESCRIPTION PAGE

4.0 GENERAL IV-1

4.1 INTRODUCTION IV-1

4.2 REGIONAL GEOLOGY IV-2 TO IV-3

4.3 STRUCTURE & TECTONICS IV-3 TO IV-4

4.4 SEISMO TECTONICS AND SEISMICITY IV-4 TO IV-6

4.5 GEO-TECHNICAL APPPRAISAL IV-6 TO V-7

REFERENCES IV-7

PLATE-4.1 GEOLOGICAL MAP OF PROJECT IV-8

Page 32: Bajoli Holi

CHAPTER – V

HYDROLOGY

5.1 LOCATION

The Ravi is a major river of the Indus Basin originating in the Himalayas

from the Bara Bangahal branch of the Dhaula-Dhar range. Bara-Bangahal

branch comprises of snow covered peaks at heights ranging from 3050 m

to 5800 m, above mean sea level.

Bajoli-Holi Hydro-electric Project is located on the river Ravi, between

the longitudes 76°40′45" to 76°32′37" and latitudes 32°16′53" to

32°20′31" in the Chamba Distt. of Himachal Pradesh.

5.2 TOPOGRAPHY AND CATCHMENT

5.2.1 TOPOGRAPHY

Lying mostly astride the main Himalayas and touching the Shiwaliks on

the southern fringe, the Ravi catchment area is rugged and covered with

the spurs of the high ranges. The Dhauladhar range separating the basin of

the Beas from that of the Ravi, the Pangi or Pir Panjal range dividing the

water shed between the river Ravi and river Chenab and Zaskar range

bifurcating the basins of the Chenab and the Indus, are the three well

defined snowy ranges, constituting the main topographical features of the

area.

The Dhauladhar range running in North-West direction, forms the

boundary between Mandi and Kullu Districts, at the point where it gives

off Bara Bangahal branch to join the mid Himalayas. It makes a sudden

bend west-ward and for the first time touches Chamba District, on the

Page 33: Bajoli Holi

southern border. From this point, it continues for about 50 Kms. forming

the boundary between Kangra and the Chamba Districts.

The Zaskar range is the direct continuation of the main Himalayan axis. It

runs in north west direction, divding Ladakh from Lahaul- Spiti and then

touches Chamba District, for a short distance along its northern border,

separating Chamba and Lahaul-Spiti from Zaskar.

The Pir Panjal range known as the Pangi range within the Chamba District

after separating Kullu from Lahaul-Spiti, enters Chamba district on the

western border of the Bara Bangahal and traverses the district from South-

East to North-West for more than 100 kms. On the North-Western border,

where the Pangi range leaves the territory, it gives off a branch to the

South-West called the Daganidhar which forms the boundary between

Chamba and Bhadrawah of Jammu and Kashmir. At its western extremity,

this branch is connected by a short ridge, in which the Padri and the

Chatardhar passes. Topographically, the Dagnidhar and the Chatardhar are

different sections of one continuous offshoot, forming with the Pangi

Range, the water shed between the Ravi and the Chander-Bhaga

(Chenab).

5.2.2 RIVER RAVI AND ITS TRIBUTARIES

It originates from Bara-Bangahal at an elevation of 4229 m above mean

sea level, approximately 150 Kms North-East of historical Chamba town.

The Ravi flows in steep gradient with series of loops & bends. In between,

main tributaries like Kalihan, Budhil, Tundah, Suil & Sewa contribute lot

of run-off to the Ravi. Bara-Bangahal comprises of snow covered peaks at

heights ranging from 3050 mtrs to 5800 mtrs above mean sea level.

Page 34: Bajoli Holi

The basin represents some remarkable physical features. The river flows

in a North-West direction for most of its course, rises in Baira-Balsio and

continues through Traila and Chanota to Ulans, where it is joined by two

of its major tributaries in the head reaches Viz. Budhil and Tundah.

Beyond this, upto Chhatrari, river flows through a narrow gorge where

after it opens out. After passing through Churi, Bagga, Mehla, Chamba

and Udaipur, the river approaches Rajnagar, then flows in narrow gorge to

Sherpur. The Suil river, the largest tributary, joins the Ravi upstream of

Chamera Stage-I Dam. The Sewa river flowing from the north joins the

Ravi near Khairi. It then bends to the South-West and striking the terminal

spurs of the Dhauladhar range, separates Chamba from Jammu and

Kashmir and finally leaves the territory of Himachal Pradesh up stream of

Ranjit Sagar Dam (Punjab).

Budhil nallah has its origin on the slopes of the mid Himalays near Kugti

pass. At Harsar, it receives on its left bank the small stream from sacred

lake of Mani-Mahesh, situated beneath the peak called the Mani-Mahesh,

Kailash at an elevation of 3952 m. It passes Village Bharmour at 15 Kms

downstream and soon afterwards meets the Ravi near Village Kharamukh.

Tundah nallah rises at Kalichtop pass, flows through Tundah valley and

joins the Ravi near Kharamukh. The right bank tributaries are bigger and

have more discharge as campared to the left bank tributaries except

Kalihan, which originates in Dhauladhar range on the left bank and

contributes a good discharge. Both Budhil & Tundah are about 54 Kms

long each .

5.2.3 CATCHMENT

The catchment area at Bajoli-Holi diversion site measures 760 Sq.Km. out

of which 372 Sq.Km is above 4000 m and is snowfed catchment. The

Page 35: Bajoli Holi

entire catchment comprises of mountaineous terrain with steep hill slopes

and is very thinly populated. The Ravi river after its origin from Bara-

Bangahal branch of Dhaula Dhar range, is mainly formed by the combined

waters of the three tributaries namely; Kalihan, Budhil & Tundah in the

head reaches. The Catchment areas of these three are:

1. Kalihan Nallah 158.75 Sq.Km

2. Budhil Nallah 555 Sq.Km

3. Tundah Nallah 305 Sq. Km.

The river bed slope is comparatively steeper in its upper reaches. The

equivalent slope of the Ravi upto Bajoli-Holi diversion site is 47.01

mtrs/Km.

5.3 METEOROLOGICAL CHARACTERISTICS

5.3.1 RAINFALL

There are, in all, thirteen non recording type rain gauge stations in the

catchment area of the river Ravi.

The normal annual rainfall & annual rainfall has been recorded in

millimeters at all these stations for the period 1960-2000 by the office of

Director, Land Records, Revenue Department (HP).

5.3.2 TEMPERATURE

There is no temperature record available at the proposed diversion site

while some record is available at Bharmour, which is ±15 Kms opposite

to proposed diversion site.

Page 36: Bajoli Holi

The relative humidity is generally high in the monsoon season, being over

90%. In the post monsoon and winter seasons, the humidity is less. The

summer is generally the driest part of the year.

5.4 HYDROLOGICAL CHARACTERISTICS

The Catchment area of the Ravi, above the proposed diversion site is 760

Sq. Kms, and is elongated leaf shaped as shown in drawing No. Bajoli

Holi-PR-2. In this reach, a good part of the catchment i.e. about 372

Sq.Km lies above the snow line i.e. 4000 m above M.S.L., which receives

moderate to heavy snowfall during winter.

The discharge of the Ravi and its major snowfed tributaries dwindles

down to lowest during winter months, from December to February and

starts increasing from February end due to the melting of snow. The bulk

contribution is in form of rainfall in the monsoon months. A few discharge

measuring stations namely; Bagga, Durgathi, Banthu, Tiyari, Bajoli and

Kutehr were set-up by HPSEB and a good data bank is available for these

sites.

5.5 HYDROLOGICAL STUDIES

5.5.1 DISCHARGE DATA AND WATER AVAILABILITY

The Discharge data of river Ravi at diversion site of Kutehr HEP (series

already approved by CWC) shown in Table 5.1 has been used to derive the

discharge data at diversion site of Bajoli-Holi HEP shown in Table 5.2.

The data w.e.f. June 1972 to May 1997 is the derived data whereas it is

actually observed data w.e.f. June 1997 to May 2003.

Based upon the daily discharge data, overall flow duration curve has been

developed (Plate 5.1). From this curve, it is seen that flow corresponding

Page 37: Bajoli Holi

to 90% and 50% availability works out to 12.50 cumecs and 29.17 cumecs

respectively. The design discharge of 71.74 cumecs is available for 25%

of the period. Flow duration curve for lean season (Dec. to Feb.) has also

been developed (Plate 5.2) and it is seen that flow corresponding to 90%

& 50% availability works out to 10.94 cumecs & 12.50 cumecs

respectively.

5.5.2 METHOD OF DISCHARGE OBSERVATION

i) GENERAL

Discharges of the Ravi at Durgathi, Banthu, Tiyari & Kutehr stream

gauging sites are measured by surface float method. Surface floats are

made up of well seasoned heavier type wood available locally. Heavier

floats are generally preferred so that its greater part would be submerged

in water thus reducing influence of the wind.

Cableways are installed across the river for the purpose of taking

observations. Two wire ropes are stretched across the river section, one at

the beginning and other at the end of the selected river reach for

conducting observations. The distance between two ropes known as float

race, is kept as 30 meters at discharge sites. The ropes are marked at 5 m

intervals to divide the river cross-section into different segments. The

centre line of the segment defines the path or track of the float. A third

rope is stretched 10 m upstream of test reach. A person taking

measurements rides in a small jhulla beneath the cable and drops floats in

different segments 10m upstream of the float race so that floats acquire

uniform velocity by the time they reach float race. Three floats are

dropped in each segment and mean of the time taken to traverse the float

race is recorded. The time of travel of test reach of only those floats which

follow their correct track is, recorded.

Page 38: Bajoli Holi

ii) CROSS SECTIONAL AREA OF FLOW

The cross-sectional area is divided into segments, each of 5 m width.

Cross-section is checked before and after monsoon period and after every

major flood in the river.

iii) MEASUREMENT OF VELOCITY

Measurement of Velocity =

Float Race

Time taken by float to cover the float race distance.

Mean velocity is generally determined by taking average of the velocities

measured at depths, 0.2 times and 0.8 times the total depth from the

surface. Float measurements represent surface velocity, as such, velocities

measured by float are multiplied by 0.89 to determine the mean velocity of

flow.

Mean velocity of flow = 0.89 x Surface velocity.

iv) COMPUTATIONS OF DISCHARGE

Mean velocities V1,V2,V3…………………………in each segment are

obtained after multiplying the surface velocities by 0.89. The velocities are

multiplied by area of cross-section of the corresponding segment to obtain

discharges in each segment. Summation of discharges in each segment

gives discharges in the river.

Q = ∑A1V1+A2V2+A3V3+………………….

= ∑Q1+Q2+Q3+……………………………

Page 39: Bajoli Holi

5.5.2 CO-RELATION STUDY

W.B. Langbein’s log deviation method has been used to obtain the co-

efficient of co-relation between discharges of river Ravi at Kutehr and at

Bajoli. The co-relation factors are as follows:

Monsoon period (June-Sept.) = 0.8665

Non-monsoon period = 1.0093

The computations have been shown in Table 5.3 & 5.4 respectively

From the above co-relation factors, it is evident that the discharges of river

Ravi at Kutehr & at Bajoli are consistent. The series for Kutehr HEP has

already been approved by your good office and the same has been used for

this period.

5.6 DESIGN FLOOD Design flood has been computed on the basis of flood estimation report for

western Himalaya Zone-7 and accordingly Hydrographs have been

prepared. The maximum flow due to rain contribution comes out to be

3029.99 cumecs which has return period of 1 in 50 years. Thus total

design flood has been adopted to be 3050 cumecs. The computations have

been shown as Annexure-V-1.

5.7 SEDIMENTATION ASPECTS

Detailed studies shall be carried out at the DPR stage.

Page 40: Bajoli Holi

5.8 90% DEPENDABLE YEAR As per the latest guidelines of CEA, the year wise unrestricted energy

generation has been computed for the period June-1972 to May,2003. The

energy so generated has been arranged in descending order. According to

Weibull’s relationship p=i/(n+1) where p= percentage exceeding of

occurrence, i=event number in descending order and n is the total number

of events, 90% dependable year and 50% mean year, have been computed.

The computations of power and energy generation have been shown in the

Table 7.1.

Page 41: Bajoli Holi
Page 42: Bajoli Holi

PARA DESCRIPTION PAGE 5.1 LOCATION V-1 5.2 TOPOGRAPHY AND CATCHMENT V-1 TO V-4 5.3 METEOROLOGICAL CHARACTERISTICS V-4 TO V-5 5.3.1 RAINFALL V-4 5.3.2 TEMPERATURE V-4 TO V-5 5.4 HYDROLOGICAL CHARACTERISTICS V-5 5.5 HYDROLOGICAL STUDIES V-5 TO V-8 5.5.1 DISCHARGE DATA AND WTER AVAILABILITY V-5 TO V-6 5.5.2 METHOD OF DISCHARGE OBSERVATION V-6 TO V-7 5.5.3 CO-RELATION STUDIES V-8 5.6 DESIGN FLOOD V-8 5.7 SEDIMENTATION ASPECTS V-8 5.8 90% DEPENDABLE YEAR V-9 TABLE-5.1 TEN DAILY AVERAGE DISCHARGE DATA OF RIVER

RAVI AT KUTEHR DIVERSION SITE V-10 TO V-13

TABLE-5.2 TEN DAILY AVERAGE DISCHARGE DATA AT BAJOLI HOLI DIVERSION SITE

V-14 TO V-17

TABLE-5.3 INFLOWS OF RIVER RAVI AT KUTEHR V-18 TABLE-5.4 INFLOWS OF RIVER RAVI AT BAJOLI V-19 TABLE-5.5 REGRESSION ANALYSIS BETWEEN DISCHARGES OF

KUTEHR AND BAJOLI (MONSOON PERIOD ) V-20

TABLE-5.6 REGRESSION ANALYSIS BETWEEN DISCHARGES OF KUTEHR AND BAJOLI( NON- MONSOON PERIOD )

V-21

ANNEXURE-V-1 DESIGN FLOOD COMPUTATION (UNIT HYDROGRAPH METHOD)

V-22 TO V-26

ANNEXURE-V-2 COMMENTS OF CWC ON DRAFT PFR AND REPLY THEREOF

V-27 TO V-32

PLATE-5.1 FLOW DURATION CURVE (OVERALL) V-33 PLATE-5.2 FLOW DURATION CURVE (LEAN PERIOD) V-34 PLATE-5.3 AREA CAPACITY CURVE V-35 PLATE-5.4 SYNTHETIC UNIT HYDROGRAPH V-36 PLATE 5.5 DESIGN FLOOD HYDROGRAPH V-37 PLATE 5.6 PLAN SHOWING RAIN GAUGE STATIONS, G&D SITES

AND SNOW GAUGE STATIONS V-38

Page 43: Bajoli Holi

CHAPTER – VI

CONCEPTUAL LAYOUT

AND PLANNING

6.0 CONCEPTUAL LAYOUT OF PROJECT COMPONENTS

6.1 FINALIZATION OF CONCEPTUAL LAYOUT

The proposed Civil Engineering Structures have been planned and designed

to divert and conduct 71.74 lacs of water, from river Ravi for generating

180MW of power in an underground power house by utilizing a gross head

of 308.00 m. The main works of the project comprise a diversion barrage,

intake, underground desanding basins for removing all particles down to

0.20mm size, 14600m long head race tunnel, a restricted orifice type surge

shaft and an underground power house to accommodate 3 vertical axis,

Francis turbines driven generating units each of 60 MW. After diversion,

all the civil engineering components have been kept underground keeping

in view the topography of the area. A brief geological site specific

feasibility note titled “Geo-technical appraisal” founded on preliminary site

inspection about each component is appended as Para 4.5 in chapter-IV

titled “Geo-technical Aspects”.

6.2 PRELIMINARY DESIGN FEATURES

6.2.1 BARRAGE

6.2.1.1 GENERAL

The slope of river at the diversion site u/s of Bajoli village is of the order of

1 in 55. Peak annual flood of river Ravi at diversion site has been adopted

as 3050 cumecs for design of spillways/barrage bays. Barrage 100m long

including abutments with crest level of barrage bays at El. 1987m & non

Page 44: Bajoli Holi

VI - 2

over flow section has been proposed to pass the estimated design flood at

FRL El. 2015.00m. The proposed barrage comprises 6 bays of 6.00m each

with 3.00m thick piers and is capable of passing the estimated design flood

even when one bay is considered inoperative during period of high floods.

The max. pond level/ FRL (El. 2015.00m) attained during winter months

shall also cater to peaking requirement . During high flood max. water level

to be attained has been proposed as 2016.00m. Radial gates in the barrage

bays shall be provided from top of crest El. 1987m to the bottom of RCC

breast wall El. 1995.00m spanning between the piers. The breast wall is

supported on the piers and is provided between El. 1995.00m and El.

2018.00m.

6.2.1.2 RESERVOIR

The full reservoir level (FRL) is fixed at El. 2015.00. The minimum draw

down level (MDDL) has been fixed at El. 1994.00m. The reservoir so

formed has a gross storage capacity of 89.95 ha-m at FRL and 10.00 ha-m

at MDDL. Available diurnal storage of 79.9500 ha-m is sufficient for

running the power station as a peaking station at full installed capacity for

3.00 hrs. The discharge availability in lean period(Nov. to Feb) in 90% dep.

year is 10.94 cumecs. The reservoir spreads over an area of about 7.50

hectares and is about 1.00 km long.

6.2.1.3 BARRAGE BAYS

6 barrage bays 6.00m wide each have been provided to pass the design

flood discharge i.e. 3050 cumecs. Total floor of 136m length has been

proposed comprising u/s floor, sloping glacis u/s & d/s (4:1) and d/s floor

of 50m including end still. A 4 m deep cut off extending up to El. 1981m

at u/s side of the floor and 5.00m deep cut off at the end of d/s floor

extending up to El. 1970m have been provided to protect the u/s and d/s

floor from scour/ piping action. Cement concrete blocks extending 10m

each beyond u/s and d/s floors have been provided. Protection to cement

concrete blocks have been provided with stone filled wire crates extending

Page 45: Bajoli Holi

VI - 3

10m beyond u/s & d/s floors. Consolidation grouting has not been proposed

in the river bed, keeping in view the fact that rock is not available upto

reasonable depth in the river bed.

6.2.1.4 ENERGY DISSIPATION

Dissipation of energy is proposed to be done by providing a horizontal

stilling basin depressed below the river bed level (El.1975m) with solid end

sill to facilitate formation of hydraulic jump. Layout & details of barrage

have been shown in drawing No. Bajoli-Holi-PR-4.

6.2.2 RIVER DIVERSION WORKS

The river diversion works have been designed for a discharge of 800

cumecs. The construction of diversion works i.e. half of barrage, intake

structure from inlet have been proposed to be taken up by making Ist Stage

coffer dam of length 300m allowing flow of water along the left bank of

river. After the completion of diversion barrage upto El. 1987m & Power

intake upto El. 1990m the Ist stage coffer dam shall be removed and

water shall be diverted on right bank of river through barrage constructed,

by making 2nd stage coffer dam. Thereafter, the construction of remaining

half of the barrage shall be completed. The construction of diversion works

has been proposed to be completed within three months period.

Construction of coffer dam is proposed to be modified as per site

conditions after each monsoon season.. The provision for construction of

coffer dam has been made accordingly, adding 50% quantum of work

being involved due to repetition of job after each season in the cost estimate

of the project. The provision of plain cement concrete of grade M-10 has

been made on the top and side slopes of coffer dam to prevent the seepage

of water towards working area.

Page 46: Bajoli Holi

VI - 4

6.2.2.1 INTAKE STRUCTURE

The intake structure comprising single intake with eight no. openings,has

been proposed on the right bank of river, to handle a discharge of 89.68

cumecs. A semi circular trash rack structure with reinforced concrete

columns has been proposed for intake. Crest elevation of intake is

proposed as 1990m. Stop logs has been proposed for controlling flow

through intake bays 8 nos.(5.50mx3m) each during repairs. A suitable

transition is provided to convert the rectangular opening into a 6.00m dia

circular approach tunnel. Approach tunnel is 200m long and shall lead the

water into two desanding basins. Details are shown in drawing No. Bajoli-

Holi- -PR-4.

6.2.3 DESANDING ARRANGEMENT

An underground desanding arrangement to exclude all silt particles down to

0.20mm has been proposed d/s of barrage axis on the right bank of river

Ravi. A lateral rock cover more than 3 time width has been ensured for

locating chamber No. 1. Rock cover of the order of twice the width of

excavated cavity of the chamber has been ensured in between the two

chambers. Stop logs will be provided at the inlet and outlet of all the

chambers to facilitate closing of any chamber for maintenance/repairs,

while the others will enable continuous operation of the power station.

Layout and details of desilting arrangement are given in drawing No.

Banjoli-Holi-PR-5.

6.2.4 HEAD RACE TUNNEL

6.2.4.1 GENERAL

The head race tunnel 5.00m dia, 14600m modified horse shoe type has

been proposed to carry a design discharge of 71.74cumecs from the

junction point of feeder tunnels of desilting chamber with HRT to the surge

shaft. The tunnel is located along right bank of river Ravi. Layout of the

tunnel has been fixed keeping in view the topography of the area and

Page 47: Bajoli Holi

VI - 5

location of construction adit from Ravi river for completing the tunnel

excavation work on schedule. Adequate rock cover has been ensured in

entire reach of the tunnel. The invert level of tunnel at RD-0 is at El.

1984.75 m and at outlet end at El. 1949.00m resulting in a slope of 1 in

409.

Six adits each 5m D-shaped at inlet, outlet and at intermediate locations

have been provided to facilitate construction of HRT from eight faces. The

inlet and outlet adits are so provided that they shall separate the

construction activity of the head race tunnel from that of desilting chambers

and surge shaft. The layout of the tunnel and other details are indicated in

Drawing. No. BAJOLI-HOLI-PR-6.

6.2.4.2 CROSS SECTION

Based on geological, hydraulic, structural and functional considerations,

modified horse shoe shaped cross section, 5.0m dia has been adopted. The

tunnel is proposed to be lined with concrete M:20.

6.2.5 SURGE SHAFT

6.2.5.1 GENERAL

The underground restricted orifice type surge shaft of 12m dia and 96.00m

height has been proposed at the outlet end of Head race tunnel at RD

14600. Top level of surge shaft is proposed at El. 2050.00m. One adit 5m

D-shaped, at the bottom at El. 1954.00m have been proposed. The bottom

adit will also be utilized to facilitate excavation of surge shaft and

horizontal portions of pressure shaft. After execution of the project this adit

will be plugged near junction of pressure shaft and rest of it will be used as

a drainage gallery. General layout and details of surge shaft are shown in

drawing No. Bajoli-Holi-PR-7.

Page 48: Bajoli Holi

VI - 6

6.2.5.2 HYDRAULIC PARAMETERS

Surge shaft area has been worked out by using Thomas’s criteria for

incipient stability with factor of safety as 1.6m conforming to IS:7396

(Part-I) 1979. Maximum upsurge and minimum down surge levels have

been computed by computer analysis as per above mentioned IS code.

Maximum upsurge level works out to be 2043.00m and minimum down

surge level as 1960.00m. For calculating maximum upsurge and minimum

down surge levels the friction co-efficient have been taken as 0.012 and

0.015 respectively.

6.2.5.2 CONCRETE LINING

It is proposed to provide reinforced concrete lining for surge shaft. Lateral

cover around surge shaft at all heights has been kept more than three times

the excavated diameter of the surge shaft. It is assumed that upsurge being

of very short duration will not cause any saturation in the surrounding rock

mass.

6.2.6 PRESSURE SHAFT

6.2.6.1 GENERAL

A 4.00m dia pressure shaft with centre line at El. 1951.50m will take off

from surge shaft for leading the water in to turbines. In the initial 20m

horizontal reach, a valve gallery has been proposed to accommodate

butterfly valve. The inclined length of main pressure shaft is 440m. Three

nos. branch pressure shaft of 2.30m dia 20m each in length, takes off from

the main pressure shaft to feed three units in the power house. The entire

length of the pressure shaft will be steel lined. The excavation of inclined

portion will be carried out from surge shaft bottom adit and from power

house cavity. The space between liner and excavated rock will be back

filled with M-20 conc. Adequate contact grouting will be done at contact

points of concrete with liner and rock. Consolidation grouting has also been

Page 49: Bajoli Holi

VI - 7

proposed in the reach, where the pressure shaft will pass through poor rock.

Details of pressure shaft are shown in Drawing No. BAJOLI HOLI-PR-7.

6.2.6.2 ECONOMIC DIAMETER

Economical dia of the pressure shaft has been worked out by cost

optimization studies for various diameters. Accordingly, a diameter of

4.00m has been adopted to carry the design discharge of 71.74cumecs with

velocity of flow as 5.74m/sec. The diameters of branches has been kept as

2.30m.

6.2.7 POWER HOUSE

6.2.7.1 GENERAL

The proposed underground power house is located about 2.0km. d/s of Holi

village on right bank of Ravi river. This site has been considered suitable

for underground power house. The tail race tunnel from power house will

discharge in to river Ravi. The erection bay and transformer hall floor

levels, are proposed at El. 1720m. The approach to power house and

transformer hall cavern is through 7m D-shaped main excess tunnel. The

machine hall and transformer hall are proposed in underground parallel

cavities at suitable spacing. The control room is proposed in power house

cavity while the SF6 switchgear is proposed in transformer hall cavity. A

cable cum ventilation gallery/tunnel is proposed, which will initially be

used for carrying out excavation and providing support system in the crown

portion of power house and transformers hall cavities. Vertical and lateral

cover each of ±200m approx. respectively has been provided in machine

cavity and transformer hall cavity. The safety of power house complex

from flooding, from tail water end during construction stage will be

adequately ensured.

Page 50: Bajoli Holi

VI - 8

6.2.7.2 TYPE

Reconnaissance surveys for location of underground or surface power

house are yet to be taken up. Surface power house has been ruled out due

to the reason that the entire area remains under snow cover for maximum

period in the year.

Keeping in view the above fact, an underground power house with

underground transformer hall has been proposed on right bank of Ravi

river. Also the GIS unnderground 220 KV Switchyard has been proposed

keeping in view the terrain and reliability of the system.

6.2.7.3 MACHINE HALL

The internal dimensions of power house cavity has been proposed as length

50m, width 17m and height 35m. For support system in crown portion of

cavity 6m long mechanically anchored , tensioned and grouted rock bolts

1.50m spacing, staggered has been proposed. 100mm thick shotcreting

reinforced with welded mesh has been proposed in crown portion and sides

of cavity. The spacing of rock bolts in sides has been kept at 2m c/c

staggered. The columns in unit bay and erection bay have been kept 1.60m

x 0.80m. For columns a nich in the side measuring 0.80mx0.80m has been

proposed which will be supported by grouted anchors 25mm dia at 1m

spacing. All rock bolts will be tensioned to 12 tonnes immediately after

installation and pull out tests will be carried out on 2% rock bolts.

The control bay is proposed on opposite side of erection bay in the end of

power house. Cavern for housing control room and various

auxiliaries/offices, 5 nos. floor have been proposed at El. 1716m, El.

1720m, El. 1724m, El. 1727.5m and El. 1730.5m respectively. The main

inlet valve is proposed to be housed in power house cavity just u/s of

turbine. EOT crane of 130/30 tonnes capacity has been proposed in erection

bay and unit bay to facilitate erection and repair of heavy equipment

including main inlet valves.

Page 51: Bajoli Holi

VI - 9

6.2.7.4 TRANSFORMER HALL

The size of transformer hall cavity has been proposed as 80m long, 16m

wide. The clear spacing between these two cavities has been kept at 30m.

In addition to main generator transformers, space for spare transformers

and station transformer has also been provided in the cavern. The

transformer hall cavern will be connected to erection bay by 5mx7m D-

shaped gallery for carriage of transformers at erection stage and for repairs.

NG rail track is proposed between transformer hall and erection bay for

transportation of transformers. The transformer hall will be connected by 3

nos. bus duct galleries 3m D-shaped.

The detail of power house has been shown in Drg. No. BAJOLI-HOLI-PR-

8&9.

6.2.8 AUXILLIARY SURGE SHAFT AND TAIL RACE TUNNEL

The outflow from the end of draft tube will be taken through 3 nos. separate

branch tail race tunnels. Vertical lift gates have been proposed in these

branch tail race tunnels to prevent entry of silt etc. into draft tube and for

facilitating repair in turbines. Downstream of this, all the branch tail race

tunnels will be joined to one main tail race tunnel 5m D-shaped, 450 m

long.

Page 52: Bajoli Holi

VI - 10

6.3 PRELIMINARY DRAWINGS

DRG. NO.BAJOLI-HOLI-PR-1 LOCATION & VICINITY MAP

DRG. NO.BAJOLI-HOLI-PR-2 CATCHMENT AREA PLAN

DRG. NO.BAJOLI-HOLI-PR-3 GENERAL LAYOUT PLAN

DRG. NO.BAJOLI-HOLI-PR-4 DIVERSION BARRAGE, INTAKE, PLAN &

SECTIONS

DRG. NO.BAJOLI-HOLI-PR-5 DESANDING BASIN PLAN & SECTIONS

DRG. NO.BAJOLI-HOLI-PR-6 HEAD RACE TUNNEL, PLAN & SECTION

DRG. NO.BAJOLI-HOLI-PR-7 SURGE SHAFT & PRESSURE SHAFT – PLAN &

SECTION

DRG. NO.BAJOLI-HOLI-PR-8 POWER HOUSE - PLAN

DRG. NO.BAJOLI-HOLI-PR-9 POWER HOUSE – SECTION

DRG. NO.BAJOLI-HOLI-PR-9(A) POWER HOUSE X–SECTION

DRG. NO.BAJOLI-HOLI-PR-10 SINGLE LINE DIAGRAM

DRG. NO.BAJOLI-HOLI-PR-11 CONSTRUCTION PROGRAMME

DRG. NO.BAJOLI-HOLI-PR-12 CONSTRUCTION FACILITIES

Page 53: Bajoli Holi

VI - 11

Page 54: Bajoli Holi

VI - 12

PARA DESCRIPTION PAGE

6.0 CONCEPTUAL LAYOUT OF PROJECT COMPONENTS VI-1

6.1 FINALIZATION OF CONCEPTUAL LAYOUT VI-1

6.2 PRELIMINARY DESIGN FEATURES VI-1

6.2.1 BARRAGE VI-1

6.2.1.1 GENERAL VI-1 TO VI-2

6.2.1.2 RESERVOIR VI-2

6.2.1.3 BARRAGE BAYS VI-2 TO VI-3

6.2.1.4 ENERGY DISSIPATION VI-3

6.2.2 RIVER DIVERSION WORKS VI-3

6.2.2.1 INTAKE STRUCTURE VI-4

6.2.3 DESANDING ARRANGEMENT VI-4

6.2.4 HEAD RACE TUNNEL VI-4

6.2.4.1 GENERAL VI-4 TO VI-5

6.2.4.2 CROSS SECTION VI-5

6.2.5 SURGE SHAFT VI-5

6.2.5.1 GENERAL VI-5

6.2.5.2 HYDRAULIC PARAMETERS VI-6

6.2.5.3 CONCRETE LINING VI- 6

6.2.6 PRESSURE SHAFT VI-6

6.2.6.1 GENERAL VI-6 TO VI-7

6.2.6.2 ECONOMIC DIAMETER VI- 7

6.2.7 POWER HOUSE VI-7

6.2.7.1 GENERAL VI-7

6.2.7.2. TYPE VI- 8

6.2.7.3 MACHINE HALL VI-8

6.2.7.4 TRANSFORMER HALL VI-9

Page 55: Bajoli Holi

VI - 13

6.2.8 AUXILIARY SURGE SHAFT AND TAIL RACE TUNNEL VI-9

6.3 PRELIMINARY DRAWINGS VI-10

Page 56: Bajoli Holi

CHAPTER – VI

CONCEPTUAL LAYOUT

AND PLANNING

6.0 CONCEPTUAL LAYOUT OF PROJECT COMPONENTS

6.1 FINALIZATION OF CONCEPTUAL LAYOUT

The proposed Civil Engineering Structures have been planned and designed

to divert and conduct 71.74 lacs of water, from river Ravi for generating

180MW of power in an underground power house by utilizing a gross head

of 308.00 m. The main works of the project comprise a diversion barrage,

intake, underground desanding basins for removing all particles down to

0.20mm size, 14600m long head race tunnel, a restricted orifice type surge

shaft and an underground power house to accommodate 3 vertical axis,

Francis turbines driven generating units each of 60 MW. After diversion,

all the civil engineering components have been kept underground keeping

in view the topography of the area. A brief geological site specific

feasibility note titled “Geo-technical appraisal” founded on preliminary site

inspection about each component is appended as Para 4.5 in chapter-IV

titled “Geo-technical Aspects”.

6.2 PRELIMINARY DESIGN FEATURES

6.2.1 BARRAGE

6.2.1.1 GENERAL

The slope of river at the diversion site u/s of Bajoli village is of the order of

1 in 55. Peak annual flood of river Ravi at diversion site has been adopted

as 3050 cumecs for design of spillways/barrage bays. Barrage 100m long

including abutments with crest level of barrage bays at El. 1987m & non

Page 57: Bajoli Holi

over flow section has been proposed to pass the estimated design flood at

FRL El. 2015.00m. The proposed barrage comprises 6 bays of 6.00m each

with 3.00m thick piers and is capable of passing the estimated design flood

even when one bay is considered inoperative during period of high floods.

The max. pond level/ FRL (El. 2015.00m) attained during winter months

shall also cater to peaking requirement . During high flood max. water level

to be attained has been proposed as 2016.00m. Radial gates in the barrage

bays shall be provided from top of crest El. 1987m to the bottom of RCC

breast wall El. 1995.00m spanning between the piers. The breast wall is

supported on the piers and is provided between El. 1995.00m and El.

2018.00m.

6.2.1.2 RESERVOIR

The full reservoir level (FRL) is fixed at El. 2015.00. The minimum draw

down level (MDDL) has been fixed at El. 1994.00m. The reservoir so

formed has a gross storage capacity of 36.00 ha-m at FRL and 7.60 ha-m at

MDDL. Available diurnal storage of 22.72 ha-m ( 85.00-20% reserved for

silt deposits) is sufficient for running the power station as a peaking station

at full installed capacity for 3.00 hrs. The discharge availability in lean

period(Nov. to Feb) in 90% dep. year is 10.94 cumecs. The reservoir

spreads over an area of about 12.00 hectares and is about 1.00 km long.

6.2.1.3 BARRAGE BAYS

6 barrage bays 6.00m wide each have been provided to pass the design

flood discharge i.e. 3050 cumecs. Total floor of 136m length has been

proposed comprising u/s floor, sloping glacis u/s & d/s (4:1) and d/s floor

of 50m including end still. A 4 m deep cut off extending up to El. 1981m

at u/s side of the floor and 5.00m deep cut off at the end of d/s floor

extending up to El. 1970m have been provided to protect the u/s and d/s

floor from scour/ piping action. Cement concrete blocks extending 10m

each beyond u/s and d/s floors have been provided. Protection to cement

Page 58: Bajoli Holi

concrete blocks have been provided with stone filled wire crates extending

10m beyond u/s & d/s floors. Consolidation grouting has not been proposed

in the river bed, keeping in view the fact that rock is not available upto

reasonable depth in the river bed.

6.2.1.4 ENERGY DISSIPATION

Dissipation of energy is proposed to be done by providing a horizontal

stilling basin depressed below the river bed level (El.1975m) with solid end

sill to facilitate formation of hydraulic jump. Layout & details of barrage

have been shown in drawing No. Bajoli-Holi-PR-4.

6.2.2 RIVER DIVERSION WORKS

The river diversion works have been designed for a discharge of 800

cumecs. The construction of diversion works i.e. half of barrage, intake

structure from inlet have been proposed to be taken up by making Ist Stage

coffer dam of length 300m allowing flow of water along the left bank of

river. After the completion of diversion barrage upto El. 1987m & Power

intake upto El. 1990m the Ist stage coffer dam shall be removed and

water shall be diverted on right bank of river through barrage constructed,

by making 2nd stage coffer dam. Thereafter, the construction of remaining

half of the barrage shall be completed. The construction of diversion works

has been proposed to be completed within three months period.

Construction of coffer dam is proposed to be modified as per site

conditions after each monsoon season.. The provision for construction of

coffer dam has been made accordingly, adding 50% quantum of work

being involved due to repetition of job after each season in the cost estimate

of the project. The provision of plain cement concrete of grade M-10 has

been made on the top and side slopes of coffer dam to prevent the seepage

of water towards working area.

6.2.2.1 INTAKE STRUCTURE

Page 59: Bajoli Holi

The intake structure comprising single intake with eight no. openings,has

been proposed on the right bank of river, to handle a discharge of 89.68

cumecs. A semi circular trash rack structure with reinforced concrete

columns has been proposed for intake. Crest elevation of intake is

proposed as 1990m. Stop logs has been proposed for controlling flow

through intake bays 8 nos.(5.50mx3m) each during repairs. A suitable

transition is provided to convert the rectangular opening into a 6.00m dia

circular approach tunnel. Approach tunnel is 200m long and shall lead the

water into two desanding basins. Details are shown in drawing No. Bajoli-

Holi-PR-4.

6.2.3 DESANDING ARRANGEMENT

An underground desanding arrangement to exclude all silt particles down to

0.20mm has been proposed d/s of barrage axis on the right bank of river

Ravi. A lateral rock cover more than 3 time width has been ensured for

locating chamber No. 1. Rock cover of the order of twice the width of

excavated cavity of the chamber has been ensured in between the two

chambers. Stop logs will be provided at the inlet and outlet of all the

chambers to facilitate closing of any chamber for maintenance/repairs,

while the others will enable continuous operation of the power station.

Layout and details of desilting arrangement are given in drawing No.

Banjoli-Holi-PR-5.

6.2.4 HEAD RACE TUNNEL

6.2.4.1 GENERAL

The head race tunnel 5.00m dia, 14600m modified horse shoe type has

been proposed to carry a design discharge of 71.74cumecs from the

junction point of feeder tunnels of desilting chamber with HRT to the surge

shaft. The tunnel is located along right bank of river Ravi. Layout of the

tunnel has been fixed keeping in view the topography of the area and

Page 60: Bajoli Holi

location of construction adit from Ravi river for completing the tunnel

excavation work on schedule. Adequate rock cover has been ensured in

entire reach of the tunnel. The invert level of tunnel at RD-0 is at El.

1984.73 m and at outlet end at El. 1949.00m resulting in a slope of 1 in

409.

Six adits each 5m D-shaped at inlet, outlet and at intermediate locations

have been provided to facilitate construction of HRT from eight faces. The

inlet and outlet adits are so provided that they shall separate the

construction activity of the head race tunnel from that of desilting chambers

and surge shaft. The layout of the tunnel and other details are indicated in

Drawing. No. BAJOLI-HOLI-PR-6.

6.2.4.2 CROSS SECTION

Based on geological, hydraulic, structural and functional considerations,

modified horse shoe shaped cross section, 5.0m dia has been adopted. The

tunnel is proposed to be lined with concrete M:20.

6.2.5 SURGE SHAFT

6.2.5.1 GENERAL

The underground restricted orifice type surge shaft of 12m dia and 96.00m

height has been proposed at the outlet end of Head race tunnel at RD

14600. Top level of surge shaft is proposed at El. 2050.00m. One adit 5m

D-shaped, at the bottom at El. 1954.00m have been proposed. The bottom

adit will also be utilized to facilitate excavation of surge shaft and

horizontal portions of pressure shaft. After execution of the project this adit

will be plugged near junction of pressure shaft and rest of it will be used as

a drainage gallery. General layout and details of surge shaft are shown in

drawing No. Bajoli-Holi-PR-7.

6.2.5.2 HYDRAULIC PARAMETERS

Page 61: Bajoli Holi

Surge shaft area has been worked out by using Thomas’s criteria for

incipient stability with factor of safety as 1.6m conforming to IS:7396

(Part-I) 1979. Maximum upsurge and minimum down surge levels have

been computed by computer analysis as per above mentioned IS code.

Maximum upsurge level works out to be 2043.00m and minimum down

surge level as 1960.00m. For calculating maximum upsurge and minimum

down surge levels the friction co-efficient have been taken as 0.012 and

0.015 respectively.

6.2.5.2 CONCRETE LINING

It is proposed to provide reinforced concrete lining for surge shaft. Lateral

cover around surge shaft at all heights has been kept more than three times

the excavated diameter of the surge shaft. It is assumed that upsurge being

of very short duration will not cause any saturation in the surrounding rock

mass.

6.2.6 PRESSURE SHAFT

6.2.6.1 GENERAL

A 4.00m dia pressure shaft with centre line at El. 1951.50m will take off

from surge shaft for leading the water in to turbines. In the initial 20m

horizontal reach, a valve gallery has been proposed to accommodate

butterfly valve.The inclined length of main pressure shaft is 440m. Three

nos. branch pressure shaft of 2.30m dia 20m each in length, takes off from

the main pressure shaft to feed three units in the power house. The entire

length of the pressure shaft will be steel lined. The excavation of inclined

portion will be carried out from surge shaft bottom adit and from power

house cavity. The space between liner and excavated rock will be back

filled with M-20 conc. Adequate contact grouting will be done at contact

points of concrete with liner and rock. Consolidation grouting has also been

Page 62: Bajoli Holi

proposed in the reach, where the pressure shaft will pass through poor rock.

Details of pressure shaft are shown in Drawing No. BAJOLI HOLI-PR-7.

6.2.6.2 ECONOMIC DIAMETER

Economical dia of the pressure shaft has been worked out by cost

optimization studies for various diameters. Accordingly, a diameter of

4.00m has been adopted to carry the design discharge of 71.74cumecs with

velocity of flow as 5.74m/sec. The diameters of branches has been kept as

2.30m.

6.2.7 POWER HOUSE

6.2.7.1 GENERAL

The proposed underground power house is located about 2.0km. d/s of Holi

village on right bank of Ravi river. This site has been considered suitable

for underground power house. The tail race tunnel from power house will

discharge in to river Ravi. The erection bay and transformer hall floor

levels, are proposed at El. 1720m. The approach to power house and

transformer hall cavern is through 7m D-shaped main excess tunnel. The

machine hall and transformer hall are proposed in underground parallel

cavities at suitable spacing. The control room is proposed in power house

cavity while the SF6 switchgear is proposed in transformer hall cavity. A

cable cum ventilation gallery/tunnel is proposed, which will initially be

used for carrying out excavation and providing support system in the crown

portion of power house and transformers hall cavities. Vertical and lateral

cover each of ±200m approx. respectively has been provided in machine

cavity and transformer hall cavity. The safety of power house complex

from flooding, from tail water end during construction stage will be

adequately ensured.

6.2.7.2 TYPE

Page 63: Bajoli Holi

Reconnaissance surveys for location of underground or surface power

house are yet to be taken up. Surface power house has been ruled out due

to the reason that the entire area remains under snow cover for maximum

period in the year.

Keeping in view the above fact, an underground power house with

underground transformer hall has been proposed on right bank of Ravi

river. Also the GIS underground 220 KV Switchyard has been proposed

keeping in view the terrain and reliability of the system.

6.2.7.3 MACHINE HALL

The internal dimensions of power house cavity has been proposed as length

50m, width 17m and height 35m. For support system in crown portion of

cavity 6m long mechanically anchored , tensioned and grouted rock bolts

1.50m spacing, staggered has been proposed. 100mm thick shotcreting

reinforced with welded mesh has been proposed in crown portion and sides

of cavity. The spacing of rock bolts in sides has been kept at 2m c/c

staggered. The columns in unit bay and erection bay have been kept 1.60m

x 0.80m. For columns a nich in the side measuring 0.80mx0.80m has been

proposed which will be supported by grouted anchors 25mm dia at 1m

spacing. All rock bolts will be tensioned to 12 tonnes immediately after

installation and pull out tests will be carried out on 2% rock bolts.

The control bay is proposed on opposite side of erection bay in the end of

power house. Cavern for housing control room and various

auxiliaries/offices, 5 nos. floor have been proposed at El. 1716m, El.

1720m, El. 1724m, El. 1727.5m and El. 1730.5m respectively. The main

inlet valve is proposed to be housed in power house cavity just u/s of

turbine. EOT crane of 130/30 tonnes capacity has been proposed in erection

bay and unit bay to facilitate erection and repair of heavy equipment

including main inlet valves.

6.2.7.4 TRANSFORMER HALL

Page 64: Bajoli Holi

The size of transformer hall cavity has been proposed as 80m long, 16m

wide. The clear spacing between these two cavities has been kept at 30m.

In addition to main generator transformers, space for spare transformers

and station transformer has also been provided in the cavern. The

transformer hall cavern will be connected to erection bay by 5mx7m D-

shaped gallery for carriage of transformers at erection stage and for repairs.

NG rail track is proposed between transformer hall and erection bay for

transportation of transformers. The transformer hall will be connected by 3

nos. bus duct galleries 3m D-shaped.

The detail of power house has been shown in Drg. No. BAJOLI-HOLI-PR-

8 & 9.

6.2.8 AUXILLIARY SURGE SHAFT AND TAIL RACE TUNNEL

The outflow from the end of draft tube will be taken through 3 nos. separate

branch tail race tunnels. Vertical lift gates have been proposed in these

branch tail race tunnels to prevent entry of silt etc. into draft tube and for

facilitating repair in turbines. Downstream of this, all the branch tail race

tunnels will be joined to one main tail race tunnel 5m D-shaped, 450 m

long.

6.3 PRELIMINARY DRAWINGS

Page 65: Bajoli Holi

DRG. NO.BAJOLI-HOLI-PR-1 LOCATION & VICINITY MAP

DRG. NO.BAJOLI-HOLI-PR-2 CATCHMENT AREA PLAN

DRG. NO.BAJOLI-HOLI-PR-3 GENERAL LAYOUT PLAN

DRG. NO.BAJOLI-HOLI-PR-4 DIVERSION BARRAGE, INTAKE, PLAN &

SECTIONS

DRG. NO.BAJOLI-HOLI-PR-5 DESANDING BASIN PLAN & SECTIONS

DRG. NO.BAJOLI-HOLI-PR-6 HEAD RACE TUNNEL, PLAN & SECTION

DRG. NO.BAJOLI-HOLI-PR-7 SURGE SHAFT & PRESSURE SHAFT – PLAN &

SECTION

DRG. NO.BAJOLI-HOLI-PR-8 POWER HOUSE - PLAN

DRG. NO.BAJOLI-HOLI-PR-9 POWER HOUSE – SECTION

DRG. NO.BAJOLI-HOLI-PR-10 SINGLE LINE DIAGRAM

DRG. NO.BAJOLI-HOLI-PR-11 CONSTRUCTION PROGRAMME

Page 66: Bajoli Holi
Page 67: Bajoli Holi

PARA DESCRIPTION PAGE

6.0 CONCEPTUAL LAYOUT OF PROJECT COMPONENTS VI-1

6.1 FINALIZATION OF CONCEPTUAL LAYOUT VI-1

6.2 PRELIMINARY DESIGN FEATURES VI-1

6.2.1 BARRAGE VI-1

6.2.1.1 GENERAL VI-1 TO VI-2

6.2.1.2 RESERVOIR VI-2

6.2.1.3 BARRAGE BAYS VI-2 TO VI-3

6.2.1.4 ENERGY DISSIPATION VI-3

6.2.2 RIVER DIVERSION WORKS VI-3

6.2.2.1 INTAKE STRUCTURE VI-4

6.2.3 DESANDING ARRANGEMENT VI-4

6.2.4 HEAD RACE TUNNEL VI-4 TO VI-5

6.2.4.2 CROSS SECTION VI-5

6.2.5 SURGE SHAFT VI-5

6.2.5.1 GENERAL VI-5

6.2.5.2 HYDRAULIC PARAMETERS VI-6

6.2.5.3 CONCRETE LINING VI- 6

6.2.6 PRESSURE SHAFT VI-6

6.2.6.1 GENERAL VI-6 TO VI-7

6.2.6.2 ECONOMIC DIAMETER VI- 7

6.2.7 POWER HOUSE VI-7

6.2.7.1 GENERAL VI-7

6.2.7.2. TYPE VI- 8

6.2.7.3 MACHINE HALL VI-8

6.2.7.4 TRANSFORMER HALL VI-9

6.2.8 AUXILIARY SURGE SHAFT AND TAIL RACE TUNNEL VI-9

6.3 PRELIMINARY DRAWINGS VI-10

Page 68: Bajoli Holi

6.4 DESIGN COMPUTATIONS A. Diversion Barrage ( REF. DRG. NO. BAJOLI - HOLI-PR-4)

i) Design Parameters Design flood discharge = 3050 cum/sec. Average bed level of the river = ± 1985m

Safe exit gradient of Nallah material (assumed) = 1 in 4 The water bays of the barrage has been so proposed that design flood discharge i.e. 3050 cum/sec passes through all the bays of barrage.

However, stilling basin has been designed corresponding to max. observed discharge in Chenab river i.e. 379.46 cumecs Say 1000 cumecs.

Hence design flood discharge for stilling basin = 1000 cumecs ii) Fixation of crest level and water bay

Average bed level of river = ± 1985m The crest level of barrage bays has been kept 2m higher than the average bed level at El. ±1985m . Six No. bays each 5.00m wide with 3m thick pier has been provided. The total water bay of overflow portion works out to be 54.00m[(6x6)+(3.00x6)] . Two meter wide fish ladder Originating from reservoir, left bank at M.D.D.L. El. ± 1994m joining river bed d/s has been provided.

iii) Storage capacity

The live storage available in barrage reservoir between M.D.D.L. El. 1994m and F.R.L. El. 2015m is 85 Hect. m. This storage capacity will run the power station at full installed capacity for 3 hrs. a day. CHECKING OF LEVELS AND CALCULATIONS FOR SIZE OF GATES Design discharge for power generation = 71.74 cumecs Total discharge i/c flushing discharge @ 20% = 71.74/(1-0.20) =71.74/80 = 89.67 cumecs Fixing crest level of intake = ± 1990m M.D.D.L. = ± 1994m F.R.L. = ± 2015 m

Page 69: Bajoli Holi

Providing one no. power intake, having 8 no. bays each of size

= 5.50 m(b)x3m(h) a) F.R.L. Condition Intake crest behaves as a rectangular large orifice

H1 = 25.00m H2 = 21m

Discharge Passed Q1 = 2/3xCdxLx√ 2g (H1

3/2-H2 3/2 ) = 2/3x0.61x44√2x9.81 (253/2 –213/2 )

= 2279 cumecs >89.67 cumecs Hence O.K.

b) M.D.D.L CONDITION

H1 = 4.00m H2 = 0.50m Q = 2/3xCdxLx√2g (H1

3/2-H23/2)

Page 70: Bajoli Holi

= 2/3x0.61x44x√2x9.81 (43/2-0.503/2) =605.00 cumecs > 89.67 cumecs Hence O.K. CHECK FOR VELOCITY THROUGH TRASH RACK Aligning trash rack at 75° Design discharge through intake/trash rack = 89.67 cumecs F.R.L. Condition Length of trash rack = xm

25/x = Sin75° x = 25/Sin75° = 25.88m Area = 25.88x44 = 1139 Sqm.

Less 25% area for trash rack bars = 1139-1139x0.25= 854 Sqm. Considering 50% clogging of trash rack bars Net area available during floods = 854/2 = 427 Sqm. Velocity through trash rack = 89.67/427 = 0.21m/sec.

M.D.D.L. condition

Length of trash rack = 4.0/x = Sin75° x = 4.00/Sin75 x = 4.14 m

Page 71: Bajoli Holi

Area available = 4.14x44 = 182.2 Sqm. Less 25% area of rack bars Net area = 182.20-182.20x0.25 =136.65 Sqm. Considering 50% area of trash rack bars Net area = 136.65-136.65x0.50 = 68.32 Sqm. Velocity through trash rack = 89.67/68.32 = 1.31m/sec. Hence size of intake provided and levels fixed are O.K.

Gated barrage is to be provided

Parameters will be as under; R.B.L. = 1985m Crest level = 1987m of barrage bays (fixed) M.D.D.L. = 1994m F.R.L. = 2015m M.R.L. = 2016m Top of barrage = 2018m Height of structure = 3424-3405 =19m Design flood = 3050 cum/sec. Size of gate = 6mx8m No. of gate = 6 No. Storage available between El. MDDL 1994m and F.R.L. 2015m It is assumed that Live storage= 85.00 Hac. m Less 20% for sedimentation Net = 85-17.00 = 68 hect .m. Time in hr = 68x104/(71.74-12.50)x3600 = 3.19 hours For Base Load Station 90% available discharge = 12.50 cumecs Design discharge = 71.74 cumecs Power = 9.81x71.74x278x0.92/1000 = 180 MW

Page 72: Bajoli Holi

Hydraulic design of free flowing/ungated structure Design discharge for power generation = 71.74 cumecs Modified discharge including 20% flushing Discharge in desanding basin = 71.74/(1-0.20)= 89.67 cum If it is the head over intake crest to pass 89.67 cumecs discharge Q = CLH3/2 89.67 = 1.70x44xH3/2 H3/2 = 89.687/1.70x44 H = 1.20m R.B.L. = 1985m Crest level of over flow bay = 1987m Crest level of intake crest = 1990m

Head over crest to pass 89.67 cumecs discharge = 1.20m Water level = 1990+1.20 = 1991.20m Hence if ungated barrage is to be provided the level of Ungated crest will have to be kept as 1991.20m Height of structure =1991.20-1985 = 6.20m Live storage (Between El. 1990& 1991.20m)= = 6.00 hacm.(Assumed) Time in hours = 6.00x104/(71.74-12.50)x3600 = 0.28 hrs. If height of structure is kept upto El. 1995m Height of structure = 1995-1985 = 10m Live storage (Between El. 1990 & El. 2000) = 30.00hacm.(Assumed) Time in hrs = 30.00x104/(71.74-12.5)x3600 = 1.41 hrs. Time to filling up of this storage = 8 months.

CALCULATIONS FOR SIZE OF GATES IN BARRAGE BAYS

As per I.S. recommendations, 10% gates are considered to be inoperative during floods(with min. one gate)

R.B.L. = 1985m

Crest level = 1987m M.D.D.L. = 1994m F.R.L. = 2015.00m M.R.L. = 2016.00m No. of barrage bays= 6 nos.

Page 73: Bajoli Holi

Width of each barrage bay =6m Providing radial gate from El. 1987m to El. 1995.00m & breast wall Thereafter upto El. 2018m Size of gate = 6mx8m Discharge through breast wall spillway is estimated by the equation Q = Cb.L.D. [2g(He+Vo2/2g]0.50 Where L = Total width of water bays available = 6x6 =36m D = Height of opening = 8.00m He = Head from C/L of spillway He =[(1995.00-1987)/2]+[2015-1994] = 4.00+21 =25.00m Vo = Vel. of approach of flood water = 3050/100x 25 = 0.68m/sec. Vel. head = Vo2/2g = 0.682/2x9.81 = 0.023 For calculating discharge co-efficient Head H = 2015-1987 = 28.00m Considering that design head may be exceeded by 25% H/Hd = 1.25 Design head Hd = H/1.25 = 28/1.25 = 22.40m Choosing Hd = 22.50m H/Hd = 1.4/11.50 = 1.244 Corresponding value of Cb = 0.811 When all the bays are open Discharge passed =Q = Cb.L.D. [2g(He+Vo2/2g) ] 0.50

Q = 0.809x36x8.00 [2x9.81(25+0.023) ]0.50

Page 74: Bajoli Holi

= 5169 cumecs When one barrage bay is inoperative Q = Cb.L.D. [2g(He+Vo2/2g) ] 0.50

= 0.809x30x8.00 [2x9.81(25+.023) ]0.50 = 4307 cumecs which is more than 3050 cumecs Hence O. K. HYDRAULIC DESIGN OF STILLING BASIN Fixation of pre-jump velocity and depth of flow The theoretical velocity at the start of the jump is calculated by the following relation: VT = √ 2g (H-0.50 Hd) Where VT = Theoretical velocity in m/sec. H = Difference in u/s reservoir El. and stilling basin invert in meters H = 2016-1975 = 41m H = Head over crest of barrage bays in meters

= 2016-1987 = 28m g = Acceleration due to gravity in m/sec = 9.81 m/sec. VT = √ 2x9.81 (41-0.50x28.00) VT = 23.02m/sec. Due to surface friction, the actual velocity is less than VT Considering VA= VT = 23.02m/sec

Discharge equation Q = A1xV1

Where

1000 = A1x23.02 VA=V1 23.02m/sec. A1 = 1000/23.02 = 43.44 Sqm. Q = Design flood discharge of Stilling basin =1000 cum L.D1 = 43.44 45.00xD1 = 43.44 ∴ D1 = 43.44/45.00 =0.965m

Page 75: Bajoli Holi

Froude No. (F) = V1/√ gd1 = 23.02/√9.81x0.965m

= 7.48 For Froude no. 7.48>4.50, U.S.B.R. type-III stilling basin is recommended. D2 = Depth Conjugate to D1 D2 = D1/2+√2q2/D1g +D1

2/4 Here q = 1000/45.00 =22.22 cum/sec D2 = -0.965/2+√2x22.222/0.965x9.81+0.965^2/4 = -0.48+10.08 = 9.60 m Length of basin = 5xD2 = 5*9.60 = 48.40 Say 50m

The floor of the basin is set at such a level at to provide 5% more water depth than Y2

Hence depth of basin = 9.60x1.05 = 10.08 m

Cistern level = 1985-10 = 1975 m Hence provided cistern level = 1975m is O.K.

SIZE OF APPROACH TUNNEL

Design discharge Q = 71.74/0.80 = 89.67 cum/sec. No. of main tunnels = 1 no. Discharge through each tunnel = 89.67 cum/sec. Vel. in the tunnel = 3.30m/sec Dia of tunnel = √(93.75/3.30)/4/Π = 5.88m

After bifurcation

Q through each tunnel = 44.84 V = 3.30 cum/sec.

Dia of each tunnel √ 44.84x4/3.30xΠ = 4.159 m say 4.25 m After Desilting

Total design discharge, Q = 71.74 cum/sec.

Page 76: Bajoli Holi

No. of tunnels = 2 nos.

Discharge through each tunnel = 71.74/2 =35.87 cum/sec Dia = 4.25m V = 35.87/Π/4(4.25)² = 2.52m/sec.

DESIGN OF APPROACH TUNNEL & INTAKE STRUCTURE A. APPROACH TUNNELS ( Ref. Drawing No. Bajoli-Holi-PR-6)

Design discharge to be drawn i/c flushing discharge = 89.67 cum/sec.

No. of tunnels = 1 nos.

Discharge through each tunnel = 89.67 cum/sec.

Provide size of tunnel = 6m, circular concrete lined

Area of each tunnel = Π/4(d²) = Π/4(6)² = 28.27 Sqm.

Vel. through each tunnel = 89.67/28.27 = 3.17 m/sec. Length of tunnel = 300m B. INTAKE STRUCTURE

Considering bell mouth intake with bottom flat

Width of opening = 1.42857 D D = Size of conduit i.e. tunnel = 1.42857x6.00 = 8.57m

Height of opening h = h1+h2 h1 [(1.21 tan2φ +0.0847)1/2+1/2 cosφ -1.1 tanφ )]D Where φ is the angle of inclination with Horizontal = 0° h1 = [(1.21 tan20+0.0847)1/2+(1/2cos 0-1.1 tan0 )] xD = [(0+0.0847)1/2 + ½]x6 = (0.291+0.50) 6 = 4.75m h2 = [0.791/ +0.077 tan0]xD = (0.791+0) x 6 = 4.75m

Page 77: Bajoli Holi

h = h1+h2 =4.75+4.75 = 9.50m Provide clear opening for intake = 8.60x9.50m

The opening is rectangular and depress it to circular from starting of intake face to a distance of 1.1 D = 1.1x6 = 6.60m

Here

a = 6.60m b = 3.50m Hence size of bell mouth entrance 8.60m(b)x9.50m(d) from 6m circular section Min. water cushion provided above the opening of intake = 0.3 he = 0.3x9.50 = 2.85m El. at top of intake = 1994-2.85 = 1990.15m C/L of intake = 1990-4.75/2 = 1987.625m C/L of approach tunnel = 1987.625 m Hence invert level of approach tunnel at RD 0 =1987.625-6/2 =1984.63m And C/L of approach tunnel at inlet = 1984.63m

Invert level as invert = 1984.63m At inlet of desanding basin Invert level = 1984.23m Overt level = 1984.23+4.25m = 1988.48m

HYDRAULIC DESIGN OF DESANDING BASIN (Underground ) (Ref. Drawing No. Chhatru-FR-5 sheet 2 of 2) Design criteria = All particles down to 0.20mm shall be removed Parameters Design discharge for power generation = 71.74 cumecs Design discharge i/c 20% for deflushing in desanding basin=71.74/0.80 = 89.67 cumecs

Page 78: Bajoli Holi

HYDRAULIC DESIGN Particle size to be removed = 0.020mm and above Permissible flow through vel. as per camp’s formula

V = 44√d for 1mm>d>0.10mm V = 44√0.020 = 19.67 cm/sec

Provide v = 19.50 cm/sec Effective area of flow = 93.75/0.1950 = 459.90 Sqm. Provide 2 No. chambers in the desanding basin Width of each basin = 13.00m Total width = 13x2 = 26m Effective area of flow of each chamber = 459.90/2 = 229.75 Sqm. CHECK FOR CROSS SECTIONAL AREA Arch Portion r = (C²+4h²)/8h = (13²+4x3.50²)/8x3.50 = 7.78m Sin α/2 = C/2/2 = 6.50/7.78 = 0.835 α/2 = 56.66° α = 113.33° Length of arch =Π/180xαxr L =Π/180x113.33x7.78

Page 79: Bajoli Holi

= 15.38m A Area of Arch Portion A1 = ½[r.L-C(r-h)] A1 = ½[(7.78x15.38)-13(7.78-3.50)] = ½(119.65-55.64) = 32 Sqm. A2 = Area of rectangular Portion = 13x16.10 = 208 Sqm. Total area = A1 + A2 =32+208 =240 Sqm.>2229.75 Sqm.

Hence O.K. 0.20mx0.20m openings are proposed to be provided at the bottom of each pit 10m c/c to carry the silt to gallery 1.50x1.80m rectangular shaped, from where silted water will be flushed back to Beas river. Settling vel. = 2.35cm/sec corresponding to 0.20mm particle size Vel. correction W1 = 0.132xv/√h = 0.132x0.195/√19.50 W1 = 0.00581 Corrected settling vel. = W-W1 = 0.02350-0.00581 = 0.017685 Length of desanding basin L = hxV/W-W1 = 19.60x0.195/0.017685 L = 216.11m Provide L = 380m Hence size of each chamber = 380m(L)x13m(b)x19.60m(h) No. of chambers = 2 nos. CHECK FOR THE SIZE Settling time t is given by t = h/W-W1 = 19.60/0.017685 = 1108.28 sec. Water conveyed during this period Qxt = Discharge per chamber x settling time = (93.75/2) x 1108.28 = 51950.80 cum Capacity of one chamber = 241.30x380= 91935 cum>51950.80 cum Hence O.K.

Page 80: Bajoli Holi

Removal efficiency of particle size of 0.20mm ηt = 1-(e) –WxL/vxh = 1-e –2.35x380/19.50x19.60 = 1-0.0960 = 90.40% Design of transitions Inlet transition length = B-b/2tan 12.5º = 13-4.25/2tan 12.5º = 19.73m Say 20.00m Outlet transition length = 13-4.25/2tan 12.5º = 19.73m Say 20.00m HEAD RACE TUNNEL(REF. DRAWING NO. CHHATRU-FR-6) Parameters Design discharge = 75 cumecs Shape of the tunnel (adopted) = Modified horse shoe shaped Length of head race tunnel = 6500m M.D.D.L. = 3413.50m Min. down surge level (as per computer analysis) = 3396.96m Co-efficient of friction = 0.014 HYDRAULIC DESIGN Calculation for economic diameter

The most economical dia of tunnel would be such as to result in a minimum total value of the sum of the following.

a) Recurring annual expenditure According to Manning formula’s V = 1/nx R2/3 S1/2

Where V = Average vel. X = Rugosity co-efficient = 0.014 R = Hydraulic mean radius = 0.506287 r

Page 81: Bajoli Holi

D = Diameter S = Slope Now V = 1/n R2/3 S1/2= 1/n (D/4)2/3 S1/2

S = 6.40 V²n²/D1.33 -(i) In this equation S gives value of head loss in meter or hydraulic gradient If η is the overall efficiency of generation Then Power lost Pe = 9./80xQxSxη KW -(ii) Where Q = VxΠ/4 (D²) Or V = 1.275Q/D² -(iii) From equation (i) & (iii) we got S = 6.40n²/D5.33x[1.275Q/D²]² - (iv) Substituting the value of S in (ii) we get revenue lost per year Pe = 9.80Q [6.40n²/D5.33 (1.275Q/D²)²]x η KW (A) Pe = 101.96 Q3/D1.33xn²xη KW Revenue lost per year Re = Pex24x365x C0 (B) From equation A&B Re = [ 101.96 Q3/D5.33xn²xη]x24x365xC0 Re = 8.95x105

x Qª/D5.33xn2xηxC0 Re = 8.95x105

x Qª/D5.33xηxn2xC0 C0 = Selling rate of power per unit = Rs. 2.50 η = Overall efficiency = 0.92 Q = Equivalent discharge =Design discharge x Load factor

Page 82: Bajoli Holi

= 75x0.50 = 37.50 cum/sec. ∴ Re = [8.95x105x(37.50)3 x0.92x(0.014)²x2.50] /D5.33 Re = 2.127x107/D5.33

Annual expenditure/Cost per year (Ae) Assuming lining thickness = D/16 (Including OB) Qty. of excavation per meter length = Π/4 (D+2xD/16)² = Π/4x81/64 D² = 0.994 D² Rate of Excavation Good rock = 903x0.60 = Rs. 541.80 Moderately jointed rock = 1499x0.20 = Rs. 299.80 Poor rock = 1906x0.20 = Rs. 381.20 Total = Rs. 541.80+299.80+381.20 = Rs. 1222.80 Rate of over break per cum = 2.3x1222.80 = Rs. 815.20/ cum

Cost of excavation including over break = 1222.80+81.52 (10% of Rs.815.20) = Rs. 1304.32 Rate of excavation per cum = Rs. 1304.32 Say Rs. 1305.00 Rate of lining M:20 = Rs. 3177 per cum Qty. of steel for ribs @ 18 kg.per cum = 0.018x56037 = Rs. 1008.66 Say Rs. 1009.00 Total cost of lining = 3177+1009 = Rs. 4186.00 Area of lining = Π(D+D/16)D/16 = 0.2086 D² Cost of excavation = 0.994 D²x1305 = 1297.17 D² Cost of lining = 0.2086D²x4186 = 873.19D² Total cost = 1297.17 D²+873.19 D²= 2170.36D² Total cost including over head charges @ 15% on total cost = 2495.91D² Ae = Annual expenditure @ 15.50% of above cost =

Page 83: Bajoli Holi

= 2495.91D²x0.155 = 386.87 D2

Now T Re+Ae T = 2.13x107/D5.33+386.87D² For mix. value DT/Dd = 0 T = 2.13x107/D5.33+386.87 D² =2.13x107xD-5.33+386.87D² For min. value DT/Dd = -5.33 D-6.33x2.13x107+2D(386.87) = 0 -1.135x108 D-6.33 = -773.74D D 7.33 = 1.135x108/773.74 = 146690.10 D = 5.07m Say 5.10m Hence dia of H.R.T. (fixed) = 5.10m Vel. in the H.R.T. = 75/20.63 = 3.63m/sec. D = 5.10m R = 5.00/2 = 2.55m r = 0.987580 R =0.987580x2.55 = 2.52m R = RARIUS OF HYDRAULICALLY EQUIVALENT CIRCLE AREA OF SECTION = 3.253 572 r2 = 20.63 Sqm. PERIMETRE OF SECTION = 6.426 334r = 16.19m

Page 84: Bajoli Holi

HYDRAULIC RADIUS = 0.506 287 r = 1.27m A = 0.780 776 r = 1.97m B = 1.561 553 r = 3.93m θ = 31º-22’-01” SURGE SHAFT (REF. DRAWING NO. CHHATRU-FR-6)

Hydraulic Design

Design discharge = 75 cumecs Size & shape of head race tunnel = 5.10m, Modified horse shoe shaped Length of head race tunnel = 6500m Value of rugosity co-efficient (assumed) = 0.012 to 0.016 Computations As per IS: code 7396 Part-I

Thoma area of surge tank is given by the formula Ath L.At/B V1

2H0 V12/2g

Sectional area of H.R.T. 5.10m modified horse shoe shaped At = 20.63 Sqm Vel. in H.R.T. = 3.63 m/sec. BV1

2 = Friction losses in the tunnel & other losses = 6.4x3.632x0.0142x6500/(5.10)1.33 = 12.30m

For computation of Thoma area using min. value of rugosity co-fficient Head losses with n=0.014, = 12.30m Head losses with n=0.012, = 9.04m Say 9m Other losses in trash rack approach tunnel & desilting tank = 0.30m

Page 85: Bajoli Holi

BV1

2 = 12.30+0.30 = 12.60m For n=0.014 And 9.00+0.30=9.30m With n=0.012 Now, Ho = Net head on turbines Ho = Net head - losses in the system Total losses = Losses upto surge shaft + penstock losses Penstock losses, hf = 0.0085x350x4.32²/2x9.81x4.80 D= 4.80m = 0.589m Say 0.60m L= 465m Q= 75 cumecs V= 4.32m/sec. F = 0.0085 Total losses = 12.60+0.60 = 13.20m Say 11m with n=.014 And = 9.30+0.60 = 9.90m with n=0.012 Say 10m H0= (3418.50-3247.00)-10 = 161.50m Ath = 6500x20.63x3.63²/161.50x10x2x9.81 = 55.76m2 Factor for safety = 1.60 Ath = Area required 55.76x1.60 = 89.22m2 Provide 15m φ surge shaft Area of surge shaft = Π/4(15)² = 176.71 Sqm. CALCULATIONS FOR AREA OF ORIFICE

Orifice area is so provided as to satisfy Calame and Gaden condition for max. flow as given below 2*/√2 + ¼ hf ≤ hor ≤ Z*/√2+¾ hf

Here Z* = Vo √L/gxAt/As =3.63 √ 6500/9.81*20.63/176.71 = 31.92m

Page 86: Bajoli Holi

For N = 0.016 Hf in tunnel system = 16.06m = 31.92/√2+16.06/4 ≤ hor ≤ 31.92/√2+3/4x16.06 = 22.57+4.01≤ hor ≤ 22.57+12.04 = 26.58 ≤ hor ≤ 34.61 For n=0.012 Then 31.92/ √2+9.00/4 ≤ hor 31.92/√2+3/4x9.00 22.57+2.25 ≤ hor 22.57+6.75 24.82 ≤ hor 29.32 Adopt Head loss across orifice = 30m Now hor = Q0

2/Cd2xA0

2x2g A0 = Q/Cd √2g hor = 75/0.62x√19.62x30 A0 = 4.98 Sqm. D = √4.98x4/Π D = 2.52m Provide orifice dia = 2.50m Max. up surge = 13.10m As per surge analysis on computer Min. Down surge = 11.90m Max. upsurge level FRL= 3421+14.96 =3435.96m Say 3436.00m Min. downsurge level MDDL = 3413.50-16.86 =3396.64m Say 3396.60m CALCULATIONS FOR SLOPE OF TUNNEL Invert level of tunnel at RD 0 of tunnel = 3402.50m

Page 87: Bajoli Holi

C/L of the tunnel at RD 0 = 3402.50+5.10/2 = 3402.50+2.55 = 3405.05m

C/L of tunnel at outlet = MDDL-Losses in HRT- 1.5x orifices losses- depth of orifice-radius of HRT = 3413.50-12.30-1.5(30)-2.50-2.55

= 3413.50-12.30-45-2.50-2.55 = 3351.01m Say 3351.00m Difference in levels = (3402.50-2.55)-3351 = 54.05m (RD 0 & RD 6500) Length of tunnel = 6500m Slope of tunnel = 6500/54.05 = 1:120.25 Say1:120 Now V1 = Q/A = 75/20.63 = 3.63m/sec. V2 = 1/4 R 2/3 S½ = 1/0.014x1.27 2/3(1/120)½ = 7.46m/sec. V2>V1 Hence O.K. PRESSURE SHAFT (Ref. Drawing No. Gharopa-FR-6.) Parameters Design discharge = 75 cumecs Design net head H = 160m Length of penstock = ± 350m Efficiency of turbine = 94% Rated HP of turbine P =1000x75x160x0.94/75 = 150400 H.P. No. of pressure shaft = 1 No.

Page 88: Bajoli Holi

Hydraulic Design Economical dia of Pressure shaft a) By DOLOND’s FORMULA Diameter = D = 0.176 (P/H)0.466

= 0.176 (150400/160)0.466 = 4.27m b) As per R.S. Nigam’s Hand Book D ≤ [ 1xfxc1xk2xQ3xt/ 1100xK1xH]1/7

Where H = 160+20% Water hammer effect = 192m c1 = 2444 kg/cm2-Allowable stress insteel (0.2x1347+0.8x2728) f = 0.0085 = Friction factor K1 = 75x0.1250 = 9.37 Rs./kg. = Annual cost of pressure shaft per kg. K2 = 2.00 = Value of KWH at generator terminal in same unit t = 365x24x0.50 = 4380 hrs. = Annual duration of operation in hrs. D = [1x0.02x2444x2.00x(75)3x4380/ 1100x9.37x192]1/7= 5.11m Taking average dia of (a) & (b) Average diameter = 4.27+5.11/2 = 4.69m Say 4.70m Velocity in pressure shaft

V = 75/ Π/4(4.70)² = 4.32m/sec. Dia of Branch penstock (3 units) Discharge = 75/3 = 25 cumecs V = 4.32m/sec.

Page 89: Bajoli Holi

D = √25x4/4.32 x 4/Π = 2.71m Say 2.70m CALCULATIONS FOR GROSS HEAD & NET HEAD F.R.L. in reservoir = 3421.00m MD.D.L = 3413.50m Normal water level = 3413.50+7.50x2/3 = 3413.50+5 = 3418.50m Min. tail water level = 3239.50m Normal tail water level = 3240.00m Max. tail water level = 3247m Max. gross head = Normal reservoir level-Min. tail water level = 3418.50-3239.50 = 179m Min. Gross head = Max. reservoir level -Max. tail water level

= 3421-3247 = 174m Design gross head = 174+2/3 (179-174)

= 177.33m

Total losses from intake to power house = 17.33m

Design Net Head = 180.83-17.33 = 160m TAIL RACE TUNNEL (Ref. Drawing No. Gharopa-FR-7( Sheet 2 of 3). Data Design discharge = 75 cumecs Size shape = 6m, D-shaped Length of tunnel = 1150m Assumed value of Rugosity co-efficient= 0.014

Page 90: Bajoli Holi

Hydraulic design i) Under normal conditions the TRT will behave as a free flow tunnel V = 1/0.014x( 12.60/10.20)2/3 (1/182.50).5 = 6.08m/sec. Discharge passed = 12.60/6.08 = 76.69cum/sec. ii) Under HFL conditions the TRT will behave as a pressurized conduit Gross cross sectional area of tunnel = [(6x3)+(Π/4x6²/2)] = 32.13 Sqm. Velocity in tail race tunnel = 75/32.13 = 2.33m/sec. Fixation of crest level of T.R.T.

i) Crest level at outfall will behave as a broad crested weir Now Q = CLH3/2 75 = 1.71x6xH3/2 H = [ 75/1.71x6] 3/2 = 3.76 m Crest level at outfall = 3240.00-3.76 = 3236.24m

Page 91: Bajoli Holi

CHAPTER – VII

POWER POTENTIAL STUDIES

7.0 GENERAL

Bajoli-Holi Hydro-electric Project has been proposed as a run- of- the

river development for generation of hydro-power on Ravi river in

Himachal Pradesh. As a peaking station to operate in western part of

Northern Regional Grid. Installed capacity of the project has been

presently kept as 180 MW comprising 3 units of 60 MW each with

overall efficiency of generation as 0.92.

7.1 PATTERN OF FLOWS IN 90% DEPENDABLE AND 50% MEAN

YEAR

31 years discharge data from June 1972 to May, 2003 in respect of Ravi

river at Kutehr Dam site has been used to develop a flow series for Bajoli-

Holi HEP for power generation. Energy generation has been worked out

for all the years as appended in Table 7.1. .Pattern of flows in 90%

dependable and 50% mean years has been worked out on the basis of

energy generation in 31 years by using Welbull’s relationship P= n/m+1,

where P is percentage exceeding of occurrence, n is the event no. in

descending order and m is total no. of events, presented in Table 7.2.

Flows in 90% dependable and 50% mean years, so worked out are given

in Table 7.3.

Page 92: Bajoli Holi

7.2 HEAD FOR POWER GENERATION

7.2.1 DESIGN HEAD

Gross head for power generation has been worked as 308.00 m between

Normal water level at diversion site El. 2008 and minimum tail water level

El. 1700. Losses in water conductor system corresponding to design

discharge of 71.74 cumecs from diversion site to generating units has been

worked out as 30.00 m. Design net head therefore has been taken as 278

m. The calculations are as follows:

FRL = 2015 m

MDDL = 1994 m

Normal water level

MDDL + 2/3( (FRL-MDDL) = 1994+2/3(2015-1994) = 2008

Normal Reservoir level at = ± 2008.00 m

Diversion Site

Min. tail water level = ± 1700.00 m

Gross Head = 2008.00 – 1700.00 = 308.00 m

Losses = 30.00 m

Net Head = Gross Head – Losses

= 308 – 30 = 278.00 m

7.3 POWER GENERATION IN A 90% DEPENDABLE YEAR AND

50% MEAN YEAR

Power generation studies in a 90% dependable year corresponding to

installed capacity varying from 90 MW to 210 MW are given in Table 7.4

The energy generation in 90% dependable year corresponding to the

Page 93: Bajoli Holi

installed capacity of 180 MW is 762.98 GWH. The energy generation in

90% dependable year corresponding to 95% machine availability works

out to be 754.13GWH as shown in Table 7.5.

Power generation studies in a 50% mean year corresponding to installed

capacity varying from 90 MW to 210 MW are given in Table 7.6 The

energy generation in 50% mean year corresponding to the installed

capacity of 180 MW is 861.37 GWH.

7.4 INSTALLED CAPACITY STUDIES

Power generation studies for 90% dependable and 50% mean year pattern

of flows with installed capacity varying from 90 MW to 210 MW have

been done. From the study, the incremental increase v/s installed capacity

curve & total energy v/s installed capacity curve have been drawn as

shown in Plate 7.1 and Plate 7.2 respectively.

It is seen from the curve that there is uniform decline in incremental

increase until we reach at installed capacity of 180 MW. Moreover the

overall plant load factor and .% utilization at 180 MW is 0.48 and 99.36%

respectively.

The project has also been planned as a peaking station for 3 hrs to meet

with the peaking power shortage in the country. Hence keeping in view

the overall PLF of 48% and.% age utilization of 99.36% the installed

capacity has been fixed to be 180 MW.

Page 94: Bajoli Holi
Page 95: Bajoli Holi

PARA DESCRIPTION PAGE

7.0 GENERAL VII-1

7.1 PATTERN OF FLOWS IN 90% AND 50% YEARS VII-1

7.2 HEAD FOR POWER GENERATION VII-2

7.2.1 DESIGN HEAD VII-2

7.3 POWER GENERATION IN A 90% DEPENDABLE

YEAR AND 50% MEAN YEAR

VII-2 TO

VII-3

7.4 INSTALLED CAPACITY STUDIES VII-3

TABLE 7.1 UNRESTRICTED ENERGY GENERATION FOR ALL

THE YEARS.

VII-4 TO

VII-7

TABLE 7.2 COMPUTATION FOR DEPENDABLE YEAR ON THE

BASIS OF ENERGY.

VII-8

TABLE 7.3 90% DEPENDABLE AND 50% MEAN YEAR

DISCHARGES

VII-9

TABLE 7.4 ENERGY GENERATION IN 90% DEPENDABLE YEAR

(1987-88).

VII-10 TO

VII-13

TABLE 7.5 ENERGY GENERATION IN 90% DEPENDABLE

CORRESPONDING TO 95% M/C AVAILABILITY.

VII- 14

TABLE 7.6 ENERGY GENERATION IN 50% MEAN YEAR

(1977-78).

VII- 15 TO

VII-19

PLATE-7.1 INSTALLED CAPACITY CURVE - 90% YEAR VII- 20

PLATE-7.2 TOTAL ENERGY V/S INSTALLED CAPACITY CURVE

90% YEAR

VII- 21

TABLE -7.7 SUMMARY TABLE VII- 22

TABLE -7.8 SUMMARY TABLE VII- 23

ANNEX-7.1 COMMENTS OF CEA ON DRAFT PFR AND REPLIES

THEREOF

VII- 24 TO

VII-28

Page 96: Bajoli Holi

REPLIES TO THE COMMENTS RAISED BY THE DIRECTOR (HP&I), NEW DELHI VIDE HIS LETTER NO. 7/9(HPSEB)/HP&I/2004/1315 DATED 19.7.04 IN RESPECT OF BAJOLI-HOLI HEP (180 MW) ARE DETAILED AS BELOW:-

GENERAL

1. Initial Environmental studies carried out by HPSEB, Conservator Cell, and the

studies done by NRSA, Hydrabad, have been collected and incorporated to the

PFR.

2. Financial Parameters have been adopted as per guidelines furnished vide letter No.

7/9/HPI-2003/1118-1123 dated 21.10.2003.

3. Cost estimate has been prepared as per the guidelines. Tariff calculation by

considering IDC & without free power to home state shall be carried out at DPR

stage.

4. Action shall be taken during DPR stage.

5. Approval of Hydrology is under process with CWC.

6. Action shall be taken during DPR stage.

7. Matter shall be taken up by the Chief Engineer (SP), HPSEB, Shimla with SP &

PA division of CEA.

8. Executive Summary as desired shall be sent separately.

9. Report of GSI has been incorporated to the PFR.

POWER POTENTIAL STUDIES

1. The power potential study has been carried out as per the data available and the

installed capacity of 180 MW has been fixed by keeping inview the curve drawn

between Installed capacity versis incremental increase in energy. The review of

installation in view of peaking operation and higher load factor during lean season

shall be carried during detailed study for preparation of DPR.

2. Detailed study shall be carried out of DPR stage.

Page 97: Bajoli Holi

3. Area capacity curve has been incorporated as Plate 5.3 under Chapter No.V

Hydrology.

4&5 The summary of studies indicating load factor yearly inflows, annual energy

generation & incremental increase in energy shall be presented in tabular form in

DPR.

6. Recommendation for further studies required for preparation of DPR is as under.

i) The consistency of the observed data will be got checked at the DPR stage,

as the concurrent data of other sites in the basin is being collected. ii) The layout of the project has been finalized on the SOI sheet in the scale of

1:50,000. The detailed surveys on the larger scale will be carried out and any change in gross head/layout will be taken care of.

Page 98: Bajoli Holi

HIMACHAL PRADESH STATE ELECTRICITY BOARD NO.HPSEB/DP/BAJOLI-HOLI/2004- Dated____/8/04 To The Chief Engineer (HP & I), Central Electricity Authority, Room No. 407 (N), Sewa Bhawan, R.K.Puram, New Delhi-66. Sub: PFR of BAJOLI-HOLI HEP – Submission thereof. Ref: This office letter No. HPSEB/DP/BAJOLI-HOLI/04-724-27 dated 30.6.04 Sir, In continuation to this office letter under reference, enclosed please find herewith PFR of Bajoli Holi HEP (25 copies) for kind reference at your end, please. It is further added that the replies to the comments conveyed by your office in respect of hydrology, power studies and general, have been attended and replies thereof appended in PFR. This is for your kind information. DA: As above (25 Copies) Yours faithfully, Alternate Nodal Officer-Cum

Director Planning, Circle No.1, HPSEB, Sundernagar (HP).

Copy to above for kind information forwarded to : i) Nodal Officer -Cum Chief Engineer (I&P), HPSEB, Sundernagar ii) Chief Engineer (P&M), HPSEB, Vidyut Bhawan, Shimla-4. iii) Chief Engineer (SP), HPSEB, Vidyut Bhawan, Shimla-4.

Alternate Nodal Officer-Cum Director Planning, Circle No.1, HPSEB, Sundernagar (HP).

Page 99: Bajoli Holi

I -

1

CHAPTER – VIII

POWER EVACUATION 8.0 ELECTRO MECHANICAL WORKS

8.1 GENERAL

Bajoli Holi Hydel Project utilizes the flows of Ravi river and is located in

Chamba Distt. of Himachal Pradesh . A net head of 278 Mts. has been

utilized to generate 180 MW of power at Barola power house .

The salient features of Bajoli Holi HEP are as under:-

Net Head 278 Meters

Installed capacity 180 MW

No. and size of units 3 units of 60 MW each.

Type of Power House Underground.

Cost of Electrical Works:-

P-production Rs. 16560.00 Lacs.

T- Transmission Rs. 3602.54 Lacs.

8.1.2 SCOPE

This project report incorporates the detailed abstract of cost under the

heading P- production (generating plant Equipment) and T- transmission

(Transmission lines for evacuation of power). Detailed analysis in the form

of various Annexures have been attached to this report. The cost estimates

are based on the rates prevailing during the current year i.e. 2004-2005.

Page 100: Bajoli Holi

I -

2

8.2 POWER HOUSE

The underground power house ( 50 m (L) x 13 m(W) x 35 m(H)) will have

3 generating units of 60 MW each along with all the auxiliary facilities

such as cooling water / potable water supply system, fire protection system,

compressed air supply , oil system, ventilation and Air conditioning system

etc.

The control room , LT room, Battery room, air conditioning Plant, Offices,

cable spreading area will be accommodated in different floors adjacent to

the machine hall and will increase the length of power house cavity by 15

m. The service bay shall be located on the opposite end of the machine hall.

Provision for the lubricating oil handling plant, the water treatment and

filtration plant and store etc. has also been made. The generator

transformers will be located in a separate cavity and will be connected to

generating units through 11 kV bus ducts. On a floor just above the

transformers , 220 kV GIS equipment shall be accommodated.

8.2.1 MECHANICAL EQUIPMENT

8.2.1.1 TURBINES

The vertical shaft , Francis turbine of 61.22 MW capacity with a rated

synchronous speed of 500 rpm has been found to be suitable in view of the

over all economy of the power house. Each turbine shall be provided with

suitable oil pressure unit, Electro hydraulic governor and other requisite

control equipment.

8.2.1.2 GOVERNOR

Since Bajoli Holi power house will be connected with Kutehr pooling point,

and shall also be operated as peaking station in tandem with other up

stream projects, it is of great importance that the governor accuracy and

Page 101: Bajoli Holi

I -

3

sensitivity is of high order so as to ensure that all the regulators behave in

the same way for any change in the system load. Thus to avoid mutual

hunting and over regulation, it is proposed to provide Electro Hydraulic

governor. The governing system for each unit will have an individual oil

pressure system consisting of oil to air mixer and an oil tank with two

pumps as well as the automatic control equipment. Speed etc. would be

indicated both on the governor cubicle and on the unit control board to

facilitate supervision of operation of the unit. The controls would include

provision for emergency shut down of unit in case of : -

Loss of Pressure in the oil pressure vessel of Governor oil system.

Excessive temperature rise in Bearing.

Excessive speed rise of the unit.

Electrical faults.

8.2.1.3 MAIN INLET VALVES

A main inlet valve of the butterfly type would be provided at each turbine

inlet for maintenance of the turbine and for emergency isolation of the

turbine in the event of governor failure. Each valve shall be actuated by

means of servomotor which shall be fed from an independent oil pressure

unit.

Each valve unit shall constitute a complete independent unit with its own

operating system for opening and closing, which will be connected to the

automatic start and stop sequence of the respective turbine unit.

8.2.1.4 COOLING WATER AND FIRE PROTECTION SYSTEM

A pumping system would be provided to supply adequate quantity of water

from the tail race for cooling of the turbine and generator bearings,

generator air coolers and selected plant services.

Page 102: Bajoli Holi

I -

4

Water for fire protection would be taken from an elevated reservoir

providing both reliable operation and ample capacity to fight fire in the

power house. A back up water supply to this reservoir would also be

provided.

8.2.1.5 POTABLE WATER AND SANITARY DRAINAGE

Water from the cooling water system would be used to supply the plant’s

potable and sanitary water needs. The potable water would be filtered and

chemically treated as required. Sanitary sewerage would be treated in a

septic system before discharge in to tail race of power plant.

8.2.1.6 COMPRESSED AIR SYSTEM

A high pressure compressed air plant would be installed to meet the

requirements of the governor oil system and the oil pressure system of the

spherical valves.

A low pressure compressed air plant would also be installed to meet the

requirements of the station pneumatic tools and other general purpose in the

power house.

8.2.1.7 OIL SYSTEM

A portable dehydration unit comprising of oil heaters, Filters, tank etc.

would be provided in the power station for the treatment of governor/

Bearings and switch gear oils.

8.2.1.8 VENTILATION AND AIR CONDITIONING

Power house would be provided with ventilation system as required for the

underground power house work areas and offices. An air conditioning

system would be provided to maintain the control room at the selected

Page 103: Bajoli Holi

I -

5

design temperature and humidity levels. The temperature and humidity

level would be selected to suit the requirements of equipment and staff.

8.2.1.9 POWER HOUSE CRANE

In order to expedite the completion of various construction activities of the

power house, 1 Nos. electric over head travelling bridge crane with capacity

of 130/30 tonnes would be installed in the power house primarily for

erection, maintenance and repair of the generating units. The cranes would

be equipped with motor control system providing suitable procedure for

equipment erection.

8.2.2 ELECTRICAL EQUIPMENT

8.2.2.1 GENERATOR

Each generator shall be of vertical shaft, salient pole type, Synchronous

generator directly coupled to the hydro turbine and having a rated out put of

66.67 MVA with 0.9 lag power factor. The generator bearing arrangement

shall be of conventional type i.e. suspended type. It is proposed to equip the

generators with dynamic braking in addition to the friction brakes. The

generator shall have class-F insulation in line with modern practice and

temperature restricted to class-B insulation.

The generator will be air cooled with a closed ventilation system using air

water heat exchanger placed around the stator frame. The generators are

proposed to be equipped with the following electrical protection equipment

High speed differential protection for generator.

Generator Over Voltage protection.

Back up over current protection.

Stator earth fault relay protection.

Negative Phase Sequence Current protection.

Rotor Field Circuit earth Fault Relay & protection.

Page 104: Bajoli Holi

I -

6

Loss of excitation relay schemes.

Generator thermal relay protection.

Phase balance relay.

8.2.2.2 EXCITATION SYSTEM

The excitation system of the generator will be of static type and will include

static type voltage regulator of latest design, field suppression equipment

and the associated accessories.

The power for the excitation system will be taken from the generator main

bus by means of a dry type or epoxy encased step down transformer. The

excitation system will be self contained requiring only an external power

source for field flashing at unit starting. The field flashing supply will be

taken from the station battery.

The excitation system including the voltage regulator will be placed in the

cubicles adjacent to the generator pit.

8.2.2.3 GENERATOR SWITCH GEAR AND CONNECTING CABLES

Each generator shall be connected to its step up transformer by means of 11

kV bus ducts. Current transformers required for protection, control and

metering will be located and form part of the bus ducts assemblies.

The generator switch gear will be of the metal enclosed type placed in a

separate room close to the generator. It will include the generator phase

equipment. The equipment for the generator neutral side will be placed in a

cubicle adjacent to the generator pit.

8.2.2.4 GENERATOR TRANSFORMERS

10 Nos. Indoor generator transformers of 25 MVA , 11/ 220/√3 kV , single

phase , 50 Hz rating will be provided and placed in a separate underground

Page 105: Bajoli Holi

I -

7

cavity ( 80 m(L) x 16 m(W) ) on the down stream side of power house

cavity. The OFWF type of cooling is proposed for generator transformers.

8.2.2.5 CONTROL AND MONITORING EQUIPMENT

The plant will be designed to be operated as an attended type. Unit control

will be provided locally while central control will be from various control

panels located in the control and relay room of the power house. Control

equipment will include metering and control panels, protections for

supervision and operation of the generator turbine, 11 kV switch gear ,

auxiliary power system, transformers and 220 kV switch gear.

The control equipment will also include the PLC and Telecommunication

equipment required for the transmission lines. Provision for connection to

the state load dispatch center will also be provided.

8.2.2.6 STATION SERVICE/ AUXILIARY SUPPLY

The station service supply is proposed to be taken through 33 kV Local

Distribution system. In addition, for reliability, 2X250 KVA DG sets shall

also be provided for the black start capability. This arrangement will also

feed local area , Colony, head works etc. The unit auxiliaries shall be fed

through 11/0.415 kV, 500 KVA transformers connected to each generator.

The auxiliaries can also be fed from 2 Nos., 33/0.415 kV, 500 KVA station

auxiliary transformers, which are connected to 33 kV bus connected to 33

kV local supply.

8.2.2.7 POWER PLANT GROUNDING

The power station will be provided with a complete earthing system. All

exposed conductive parts and equipment in the powerhouse and switchyard

Page 106: Bajoli Holi

I -

8

will be connected to the grounding system. The grounding system will be

designed to minimize the “Safe” and “Touch” potential within acceptable

limits.

8.2.2.8 LIGHTING

The power plant lighting, following normal practice, will comprise of

interior and exterior lights as appropriate. While the majority of the

illuminaries will be AC powered, emergency lighting will be DC supplied

from station battery system. The emergency lighting will be provided only

for essential locations e.g. control room, exits etc.

8.2.2.9 SWITCH YARD AND SWITCHING SCHEME

The project is proposed to be interfaced with the 220 kV Kutehr HEP. The

evacuation arrangement has been made after taking in to consideration the

constraints on right of way, reliability and the quantum of power that shall

be injected in to 220 kV Kutehar HEP. Schematic diagram showing the

interconnection of Bajoli Holi with other identified projects is as per Annex.

A. Due to space constraints, 220 kV Gas Insulated Switchgear has been

proposed and shall be housed on a floor located just above the transformers

in the transformer cavern. Single breaker double bus bar arrangement has

been proposed after giving due consideration to its reliability, stability, easy

maintenance and accessibility. The GIS switchyard has 3 generator

transformer bays, one bus coupler bay and two feeder bays. The connection

of the Pot yard with the underground GIS switchyards shall be made via

220 kV, XLPE cables. In addition to this, space for 2 Nos. 220 kV feeder

bays shall be kept for up stream projects i.e. Bara Bangal (200 MW).

Page 107: Bajoli Holi

I -

9

8.3 TRANSMISSION OF POWER

Considering the amount of power to be evacuated and the distance

involved, it has been proposed to inject the power generated at Bajoli Holi

power house in to 220 kV Kutehar HEP. For wheeling of power that shall

be accumulated at Kutehar HEP, 220 kV D/C line from Kutehar to

Hamirpur 2x0.5 or 4x0.5 conductor depending upon total firmed up

capacities of projects up stream of Kutehar HEP(as per decision taken

during the 16th standing committee on Transmission System Planning) in

Northern Region held in NREB on 24.3.2004) shall be laid.

8.4 ESTABLISHMENT

The electrical works of the project are proposed to be completed with in 5

years time. Accordingly, the provision of regular establishment required for

to do electrical works in this time frame has been made in the estimate. The

design procurement, inspection, erection and commissioning of electrical

works of the project shall be done departmentally.

The provision of staff has been made as per the CEA’s norms intimated

from time to time

Page 108: Bajoli Holi

I -

10

PARA DESCRIPTION PAGE

8.0 ELECTRO-MECHANICAL WORKS. VIII-1

8.1 GENERAL VIII-1

8.1.2 SCOPE VIII-1

8.2 POWER HOUSE. VIII-2

8.2.1 MECHANICAL EQUIPMENT VIII-2

8.2.1.1 TURBINES VIII-2

8.2.1.2 GOVERNOR VIII-2 TO VIII-3

8.2.1.3 MAIN INLET VALVES VIII-3

8.2.1.4 COOLING WATER AND FIRE PROTECTION

SYSTEM.

VIII-3 TO VIII-4

8.2.1.5 POTABLE WATER AND SANITARY DRAINAGE VIII-4

8.2.1.6 COMPRESSED AIR SYSTEM VIII-4

8.2.1.7 OIL SYSTEM VIII-4

8.2.1.8 VENTILATION AND AIR CONDITIONING VIII-4

8.2.1.9 POWER HOUSE CRANE VIII-5

8.2.2 ELECTRICAL EQUIPMENT VIII-5

8.2.2.1 GENERATOR VIII-5

8.2.2.2 EXCITATION SYSTEM VIII-6

8.2.2.3 GENERATOR SWITCH GEAR AND

CONNECTING CABLES.

VIII-6

8.2.2.4 GENERATOR TRANSFORMERS VIII-6

8.2.2.5 CONTROL AND MONITORING EQUIPMENT VIII-7

8.2.2.6 STATION SERVICE/AUXILIARY SUPPLY VIII-7

8.2.2.7 POWER PLANT GROUNDING VIII-7

8.2.2.8 LIGHTING VIII-8

8.2.2.9 SWITCH YARD AND SWITCHING SCHEME VIII-8

8.3 TRANSMISSION OF POWER VIII-8 TO VIII-9

8.4 ESTABLISHMENT VIII-9

Page 109: Bajoli Holi

I -

11

Page 110: Bajoli Holi

CHAPTER - IX

ENVIRONMENTAL ASPECTS

9.0 DESCRIPTION OF THE PROJECT

The proposed Bajoli Holi HEP is a run of the river scheme on Ravi

river to harness the power potential between village Bajoli and Barola.

The scheme envisages diversion of 71.74 cumecs discharge of Ravi,

near 200 m down stream of the confluence of Channi nallah with river

Ravi by constructing a diversion structure (about 30 m high) through

an underground desilting structure, a 5 m dia 14.6 km long HRT, surge

shaft and a 4 m dia 475 m long pressure shaft to generate 180 MW of

power in an underground power house near village Barola by utilising

a gross head of about 308 m. The water will be further discharged to

Kuther reservoir.

9.1 DESCRIPTION OF ENVIRONMENT

9.1.1 PHYSICAL RESOURCE

9.1.1.1 HYDROLOGY

The area in question is drained mainly by Ravi river. A large number

of nallah drain directly in to the Ravi river. In the propose project area,

Sarontha Nallah and Sal nallah drains into the Ravi river

9.1.1.2 GEOLOGY

Most of the area of the area is as yet geologically unmapped. A great

mass of the mountain is formed of ancient rock of silurian age, resting

on a central mass of granite or granitoid gneiss. Nearly all the hill

ranges of the Himalayas follow a definite pattern of strata. They

Page 111: Bajoli Holi

IX -

2

usually lie in the east-west direction with some variations. The strata

dip to the north barring some variations due to orogenic movements

and local disturbances. This east-west sweep of the ranges has given

rise to markedly south and north exposed slopes, and hence to

different rock weathering conditions and vegetative cover due to the

varying duration of light.

All over the tract, schist occurs in different forms such as shales, slates,

gneisses, argillaceous clay, etc. The schists provide easily worked

building stones, while slates provides excellent roofing material of

good quality. Underlying rock of Dhauladhar range are granite and

gneiss almost uniform in character throughout. At the lower elevations

the rock system, mainly on the northern and eastern slopes, is very

unstable, weak and friable nature, readily prone to disintegration. The

terrain in such parts is highly susceptible to landslides, land-slips and

erosion. The sub-soil is fairly hard, generally argillaceous shale, which

is often fissured, and easily subject to disintegration near the surface

when exposed. The soil depth is inversely proportional to the slopes.

On ridges and spurs, and precipitous and southern aspects, the soil

tends to be shallow and dry with numerous out-crops of bare rocks.

9.1.2 ECOLOGICAL RESOURCE

9.1.2.1 FORESTS

The composition of the forest vegetation and its evolution is influenced

by the character of the rocks/soil underlying. The main forests in the

area are of Kail and Chilgoza. The density varies from good to sparse

and scattered. In some areas which were earlier shown to have Kail

forests are now having Chilgoza trees.

Page 112: Bajoli Holi

IX -

3

9.1.2.2 FLORA AND FAUNA

9.1.2.3 FLORA

The main parts are located on the right bank of the river which is

almost barren. Very few patches of Kail trees are seen. On higher

elevations the vegetation is better. However, the right bank has

moderate tree cover of various species. The composition and condition

of the crop varies with altitude and aspect. In the lower area Kail and

Deodar are found mixed with Oaks whereas further upward Spruce and

Fir forests are found as mixed crop or in pure form. Kail is prominent

on southern aspects whereas Deodar, Spruce and Fir are mostly

confined to the cooler aspects.

The right bank in particular has a good stock of medicinal plants on

higher altitudes.

Page 113: Bajoli Holi

IX -

4

Scientific name Common Name English Name

Abies pindrow

Acer caesium

Aesculus indica

Alnus nepalensis

Alnus nitida

Cedrus deodara

Celtis australis

Corylus colurna

Cupressus torulosa

Ficus bengalensis

Ficus religiosa

Ficus roxburghii

Fraxinus excelsior

Fraxinus floribunda

Grewia vestita

Juglans regia

Litsaea glutinosa

Litsaea umbrosa

Machilus odoratissima

Morus alba

Morus serrata

Myrica nagi

Rai

Mandar

Goon

Piak

-do-

Diyar

Khirak

Thangi

Devidiyar

Bar

Pipal

Trambal

Sanooh

-do-

Dhaman

Akhrot

Chirindi

-do-

-do-

Karun

-do-

Kaphal

Silver Fir

Mapple

Horse Chest Nut

Alder

-do-

Deodar

Nettle Tree

Hazlnut

Cyprus

Ash

-do-

Walnut

Mulberry

-do-

Olea cuspidata

Picea smithiana

Pinus gerardiana

Pinus roxburghii

Pinus wallichiana

Populus alba

Populus ciliata

Punia granatum

Kahu

Tosh

Neoza

Chir, Chil

Kail

Pahari Pipal

Chaloon

Daru

Wild Olive

Spruce

Chilgoza Pine

Chil Pine

Blue Pine

Poplar

-do-

Wild Pomegranate

Page 114: Bajoli Holi

IX -

5

Pyrus communis

Pyrus malus

Quercus dilatata

Quercus incana

Quercus semicarpifolia

Rhododendron arboreum

Robinia pseudoacacia

Salix alba

Salix babilonica

Taxus baccata

Nakh

Seo

Moru

Ban

Kharsu

Cheo

----

Badha

Badha ( Majnu )

Barmi

Pear

Apple

Green Oak (Middla Zone)

White Oak ( Low Level)

Brown Oak (High Level)

Red Rhododendron

----

Willow

-do-

Yew

B. SHRUBS

Agave americana

Ainslea aptera

Berberis aristuta

Chenopodium album

Cotoneaster acuminata

Cotoneaster bacillaris

Cotoneaster microphylla

Cotoneaster vulgaris

Daphne cannabina

Dendrocalamus strictus

Desmodium tiliaefolium

Deutzia corymbosa

Ramban

Mukh Nihani

Kemal/Kasmal

Bathu

Rheuns

-do-

-do-

-do-

Niggi

Bans

Pre

Batti

Century Plant

Airon's Rod

----

----

----

----

----

----

----

----

----

Wild Syringe

Eurphobia royleana

Fragaria vesca

Galium asperifolium

Galium ptunifolium

Girardiana heterophylla

Hamiltonia suaveolens

Ilex dipyrena

----

Strawberry

-do-

----

----

Ain

Padara

----

strawberry

-do-

----

----

----

----

Page 115: Bajoli Holi

IX -

6

Indigofera gerardiana

Indigofera hersuta

Indigofera pulchella

Juniperus communis

Juniperus recurva

Lonicera angustifolia

Lonicera quinquilocularis

Mimosa rubicaulis

Oxalis corniculata

Parrotia jacquemontiana

Plantago lanceolata

Plantago tibetica

Pletranthus rugosus

Potentilla Spp.

Primulla Spp.

Prinsepia utilis

Pteris aquilina

Rhamnus purpurea

Rhus cotinus

Rhus parviflora

Rosa macrophylla

Rubus biflorus

Rubus niveus

Kanderu

Kathi

----

----

Bither

-do-

Kantias

Bakhru

----

Malori

Killar

Isabgol

----

Kuthal

----

----

Kangora

Lingar

Luhish

Tung

Tungla

Karer, Bangulab

Akhre

The Holly

----

----

----

Cedar

-do-

Honey Suckle

-do-

----

----

Wych hazel

----

----

----

----

----

----

----

----

----

----

----

Raspberry Red

Sarcococca pruniformis

Sarcococca saligna

Staphylea emodi

Strobilanthus dalhousianus

Trifolium repens

Viburnum cotinifolium

Viburnum foetens

Viburnum nervosum

Diun

-do-

Nagdaun, Chitra

----

----

Talanj

-do-

-do-

----

----

Snake wood

----

Clover white

----

----

----

Page 116: Bajoli Holi

IX -

7

Viburnum stellulatum

Woodfordia floribunda

Woodfordia fruticosa

-do-

Dhawa

-do-

----

----

----

C. CLIMBERS

Vitex negundo

Hedera helix

Smilex parviflora

Vitis Latifolia

Vitis semocordata

Bannah

Kural

----

Panibel

-do-

----

Ivy

----

The Virginian Creeper

-do-

D. MEDICINAL PLANTS

Aconitum heterophyllum

Aconitum chesmanthum

Arisaema flavum

Arisaema helleberifolium

Arisaema wallichiana

Asparagus racemosus

Atropa acuminata

Atropa belladona

Cinnamomum tamala

Digitalis purpurea

Dioscorea bulbifera

Dioscorea deltoidea

Patis

Mohri

Samp-ki-makki

Ki-kukri

-do

Satawar

----

Shafoo

Tejpat

----

Khildri

-do-

Medicinal herb

-do-

----

Cobra Plant

-do-

----

----

Belladona

----

----

----

----

Hydrocolyle asiatica

Jurinea macrocephala

Mentha acquatica

Ocimum Spp.

Brahmi-Buti

Dhup

Pudina

----

----

----

Mint

----

Page 117: Bajoli Holi

IX -

8

Onosrna bracteatum

Picrohiza kurrooa

Podophyllum emodi

Rumex nepalensis

Salvia glutinosa

Saussurea lappa

Saxifraga ligulata

Taraxacum officinale

Thalictrum foliolosum

Verbascum thapsus

Valeriana wallichii

Viola odorata

Viola serpens

Withania somnifera

Rarra (Rattanjot)

Kaur

Ban Kakru

Amlora

Makhiar

Kuth

Pathartor

Dudhali

Machhar Mar

Giddar Tamaku

Smak, Nihani

Banafsha

-do-

Ashawgandha

----

Medicinal Plant

----

----

Dog Flower

----

----

----

----

----

----

----

----

----

9.1.2.4 FAUNA

Although the wild Life’s presence on the right bank is very rare, the

most common animals and birds found in vicinity are as follows.

1. GHORAL (Nemorthaedus Goral)

2. KAKKAR- Muntjac or barking deer (Muntiacus muntjak)

3. KASTURA (Moschus moschiferus)

4. BAGHERA OR LEOPARD (Panthera pardus)

5. KALA BHALU OR HIMALAYAN BLACK BEAR

(SELENARCIOS THIBETANUS)

6. LAL BHALU OR HIMALAYAN BROWN BEAR (Ursus

arctos)

7. GORTHU OR THE HIMALAYAN PINE MARTIN (Martes

flavigula)

8. THE INDIAN PORCUPINE (Hystrix indica)

9. EAN OR FLYING SQUIRREL (Hylopetes)

10. CHUKOR (Alectoris gracca)

Page 118: Bajoli Holi

IX -

9

11. RED JUNGLE FOWL (Gallus gallus)

12. KALESHA (Genuocus albicratatus)

13. CHEER PHEASANT (Caterus wallichi)

14. KOKLAS PHEASANT (Varasis macrolopha)

15. BLACK PATRIDGE (Francolinus francolinus)

16. DOVE OR GHUGI (Chalcuphaps indica)

17. GREY QUAIL (Coturnix conurnix)

9.2 BASELINE ENVIRONMENTAL STATUS

9.2.1 CLIMATE AND TEMPERATURE

The climate is markedly temperate and varies with the altitude.

Since most of the area of the tract lies on higher elevations and

northern aspects, so cool weather prevails during most part of the

year.

Seasons are well marked. The spring season is cool bright and free of

haze and mist or dust and snow deposits still persists above 1830

meters. April slowly gives way to the much steadier months of May

and June when the sun shines, the light brightest and warmest, with

occasional light showers and the weather is tolerably warm. The

monsoon generally starts in the first week of July and lasts upto the

end of August. There are occasionally very heavy rains, which bring in

devastating floods in the streams and nullahs and landslides or land

slips (locally called ghaars). September and October is cool bright and

free of haze and dust, with occasional light rains. November is cool

and dry and by the middle of this month rain, hail, sleet and light

snowfall begin to visit the area above 1800 meters. Snowfall is almost

a regular feature from December to middle of March. It accumulates as

much as 9 meters at 2700 meters elevation and above and does not

persist longer below 1800 meters of elevations and southern slopes.

Page 119: Bajoli Holi

IX -

10

9.2.1.1 TEMPERATURE, RAINFALL AND SNOWFALL DATA

TEMPERATURE OF BHARMOUR

Maximum Minimum

January 17 -3

February 14 -5

March 22 1

April 24 1

May 27 10

June 31 14

July 28 15

Aug 26 15

Sep 28 13

Oct 23 9

Nov 20 5

Dec 7 1

RAINFALL

Details of average monthly rainfall for meteorological station Holi

(Elevation 6000 feet) for the last ten years are given below:-

Rainfall (in mm) and Snowfall ( in cm ) during the

month

January February March

Rainfa

ll

Snowfa

ll

Rainfa

ll

Snowfa

ll

Rainf

all

Snowfa

ll

45.84 10.55 68.46 28.36 176.18 6.55

Page 120: Bajoli Holi

IX -

11

Rainfall (in mm) and Snowfall ( in cm ) during the

month of

April May June

Rainfa

ll

Snowfa

ll

Rainfa

ll

Snowfa

ll

Rainf

all

Snowfa

ll

85.59 0.18 102.73 ---- 32.73 ----

Rainfall (in mm) and Snowfall ( in cm ) during the

month of

July August September

Rainfa

ll

Snowfa

ll

Rainfa

ll

Snowfa

ll

Rainf

all

Snowfa

ll

107.60 ---- 89.91 ---- 67.37 ----

Rainfall (in mm) and Snowfall ( in cm ) during the

month of

October November December

Rainfa

ll

Snowfa

ll

Rainfa

ll

Snowfa

ll

Rainf

all

Snowfa

ll

24.36 ---- 22.29 1.27 87.02 13.05

The bulk of the precipitation is received in the form of sleet and snow

from the mid of November to middle of March. Rainfall is also good

during monsoon from middle of July to end of August. The difference

in the distribution of the snowfall is less pronounced. Generally, the

inner valleys experience a heavy snow fall , where it stays longer.

Droughts occur from April to middle of June and during middle of

Page 121: Bajoli Holi

IX -

12

September to November. Prolonged severe droughts are common and

that have adverse effect on the establishment of regeneration.

Air, Water, Soil and Sound data will be collected at the time of

doing detailed EIA.

Since this is pre feasibility report, this has not been done at this stage.

9.3 ENVIRONMENT IMPACT ASSESSMENT AND EVALUATION

9.3.1 IMPACT IDENTIFICATION

Environmental impacts both direct and indirect on various

environmental attributes due to Bajoli Holi Hydropower project in the

surrounding environment, during construction & operational Phase are

discussed.

9.3.2 IMPACT IDENTIFICATION DURING CONSTRUCTION

PHASE

The impacts due to the construction of Bajoli Holi HEP and power

house installation commence from the exploration activities,

construction of barrage, tunnels and approach roads, etc., and may

continue up to generation of hydel power, with the nature and extent of

impacts varying throughout the stage of project development.

Activities like site preparation, approach roads, excavation, drilling,

blasting, foundations, tunneling, deployment of machinery, erection,

transportation, dumping are taken up during construction phase. The

likely impacts on the environment due to these activities are listed in

the table.

Tunneling and foundation works will involve land excavation, filling

and concrete works affecting environment by noise and dust pollution.

Page 122: Bajoli Holi

IX -

13

Deployment of machinery, approach roads construction and erection

work will also result in dust, noise pollution and vehicular traffic.

Material handling and transportation may significantly increase noise

pollution. The Muck produced will be in huge quantity and it will pose

an environmental threat unless properly managed.

The labour for various activities during the construction phase shall be

engaged. Some essential services are also required to be provided. This

will have an impact on drinking water supply and sanitary facilities.

Economy of the nearby area will be improved due to increased job

opportunities with corresponding increase in income. Other associated

business activities like transport, hotels, consumer goods etc., will also

be benefited.

The major environmental parameters likely to be effected during

construction phase are muck, noise, dust pollution and sanitation.

Water spraying during high dust will minimise the dust level to some

extent. A proper temporary housing with water supply and sanitation

for workers should be planned. The effect due to construction phase is

however, of temporary in nature and has no permanent effect on

environment.

Construction

Phase

Activity Potential Environmental

Impact

Clearing and grading Negligible

Temporary facilities, such

as, sheds approach roads,

sanitary facilities.

Muck, Dust emission and

change in traffic intensity.

Earth work comprising of

excavation and trenches.

Muck, Soil erosion, run off,

increase in traffic, Dust

emission

Site work /

providing other

facilities.

Foundation work, piling and

construction of check dams.

Muck, Dust, visual and

noise pollution

Page 123: Bajoli Holi

IX -

14

Construction of permanent

structures like roads, colony

etc

Muck, Dust and noise

pollution

Mechanical erection and

utility systems.

Dust, noise and visual

impact.

Excavation Muck, Dust, soil erosion,

wastewater generation and

noise

Drilling and blasting Muck, Dust, noise and

health hazards

Dumping Dust, noise and visual

Construction of

approach roads,

tunneling works

and construction

of under ground

Power Station Transportation Dust, noise and visual

9.3.3 IMPACT IDENTIFICATION DURING OPERATIONAL PHASE

There would be little environmental and ecological changes during the

operational phase. The main activities that may cause environmental

impact on the surrounding environment during project completion and

after during operation are:

i. Transportation of excessive solid waste material (muck)

ii. Dumping of solid waste material

iii. Removal of temporary facilities, cleaning etc.

During the project completion the likely potential environmental

impacts are due to dust and noise.

Page 124: Bajoli Holi

IX -

15

Operation Phase Activity Potential Environmental

Impact

Down stream erosion of

River bank and bottom

Release of water Down stream flow variation

Impairment of water quality

Silting in the area behind

barrage

Accumulation of back water Dumping of solid waste

Ecological hazard

9.4 PREDICTION OF IMPACTS

The impact during the construction of Bajoli Holi HEP on environment

(air, water, noise, land etc. are predicted in this section. The

construction activity may cause some adverse impacts on the

surrounding environment unless proper environmental management

plan is adopted.

9.4.1 IMPACT ON AIR ENVIRONMENT.

Considerable amount of air pollution will be caused during different

stages of construction of tunnels, barrage, roads and other operations

such as excavation, drilling, blasting, loading and transportation of

material. Suspended Particulate Matter (SPM) is the main pollutant

during construction. Most of the dust arises from drilling, blasting,

excavation, crushing and transportation operations. Large quantities of

dust become wind borne and are carried away from overburden dumps.

The fugitive dust released during the construction activities may cause

immediate effect on the construction workers who are directly exposed

to the fugitive dust. Vegetation will also be adversely affected as

deposition of dust on the leaves will choke the photosynthesis activity,

which, in turn, will have adverse effect on the health of the plants.

Page 125: Bajoli Holi

IX -

16

However, the dust does not travel to longer distance because the

project site is located in between hills and V-shaped valleys.

9.4.2 IMPACT ON NOISE ENVIRONMENT

The noise will be generated at the time of construction of barrage,

powerhouse, tunnel boring machine operations, pumps, drilling

machines, dumpers, etc. Continuous exposure of workers to high level

of noise may result in annoyance, fatigue, and may cause temporary

shift of threshold limit of hearing and even permanent loss of hearing.

During operational phase, noise level will be increased due trouncing

machinery and vehicular movement in the area. However, these

impacts are only localised.

9.4.3 IMPACT ON WATER ENVIRONMENT.

During the construction of barrage, tunnel, and power house surface

water (river water) may get polluted due to the generation of large

quantities of suspended particulate matter at the time of transportation

of muck and waste water (sewage) coming from temporary

arrangements like offices, labour camp sheds, etc.,

9.4.4 IMPACTS ON FLORA AND FAUNA

The various plant and animal species available in the region have

already been described. There are no endangered species in the region.

There are no Wild Life Sanctuary or National Park in the area.

Every Plant species and wild life species whether mammal, bird,

reptile, aquatic or amphibian plays an important role in the

maintenance of balance of nature and is useful to mankind in many

ways. Every individual animal, bird or insect has been endowed with

Page 126: Bajoli Holi

IX -

17

certain specific protective measures so that it can protect itself and

reproduce, thus ensuring the existence of the species. However, the

project activities will not have any significant effect on the Forest and

Wild Life except for removal of bare minimum number of trees.

However, Compensatory afforestation will be done as per the general

stipulations given by the Govt of India MoEF at the time of sanction of

diversion of Forestland

9.4.5 E. R & R ASPECTS

Since the Project is a run-of-the-river type and there is no storage,

therefore, there is no submergence. Hence, no dwellings, houses or

hamlets will be submerged. So, there is no displacement and

resettlement is involved.

9.4.6 ENVIRONMENTAL MANAGEMENT PLAN (MITIGATION

MEASURES)

Environmental Management Plan (EMP) aims at the preservation of

ecological system by considering certain mitigating measures at the

proposed site. The mitigation measures are used to minimize or

prevent adverse impacts on environment due to the proposed

development activity . Some of the major criteria governing the

environmental measures will be adopted, and the same is described in

the following paragraphs.

9.4.6.1 ENVIRONMENTAL MANAGEMENT

The EMP is required to ensure sustainable development in the study

area of 10 Km radius of the proposed Bajoli Holi HEP site.

Government regulating agencies like Pollution Control Board working

Page 127: Bajoli Holi

IX -

18

in the region and more importantly the people living in the area need to

extend their co-operation and contribution in this direction.

It has been evaluated that the study area shall not be affected adversely

with the proposed activity and likely to get new economical fillip due

to hydel power generation, not only for the study area but also for the

region as a whole.

The majority of the environmental impact pertains to the construction

phase. It is planned to take corrective measures to ensure that these

effects are kept to bare minimum. The EMP will therefore, be initiated

during planning stage itself.

Catchment Area Treatment Plan, which will be prepared at a later stage

will form part of the Environmental Management Plan

9.4.7 ENVIRONMENTAL MANAGEMENT AT CONSTRUCTION STAGE

9.4.7.1 SITE PREPARATION

Dust emission (fugitive) and solid waste will be generated during

initial site preparation activity and there will be slight increase in the

noise levels around the site. The environmental impacts during the

clearing or clearing for site preparation will be temporary, localised

and negligible. Water sprays at appropriate location will be provided

for dust suppression, hence reducing the impacts. Solid waste will be

disposed off along with the muck at the designated sites.

9.4.7.2 CONSTRUCTION

9.4.7.2.1 AIR ENVIRONMENT

As discussed earlier, construction of Bajoli Holi HEP and powerhouse

activities will generate large quantities of dust during drilling, blasting,

Page 128: Bajoli Holi

IX -

19

loading and transportation operations. The following measures are

required be taken to mitigate the fugitive dust from different

operations.

To avoid the dust generation from the drilling operations, wet-

drilling methods will be adopted.

Ceasing dust -generating activities during high winds

Covering of vehicles carrying solid waste (muck).

Watering of haul roads and other roads at regular intervals

Plantation near muck disposal places and dumping yards.

9.4.7.2.2 NOISE ENVIRONMENT

The major noise-generating sources from the proposed activity are

working machinery, blasting and movement of vehicles. The following

control measures are to be undertaken to bring down the noise levels.

Traffic (vehicular movement) to be managed to produce a

smooth flow instead of a noisier stop -and start flow.

Ensuring timely preventive maintenance of the equipment

involved. Since a well maintained equipment is generally

quieter than poorly maintained equipment.

Ensuring usage of personal protective devices i.e., earmuffs and

earplugs by workers, working in high noise activity centers.

Page 129: Bajoli Holi

IX -

20

Plantation in the vicinity of the construction area will further

reduce the noise levels.

9.4.7.2.3 WATER ENVIRONMENT

During construction phase the wastewater (sewage) coming from

temporary arrangements like offices, labour camp sheds, canteens etc.,

and impact due to soil erosion during monsoon period may cause

surface water pollution.

Some of the control measures adopted for controlling water pollution

are as follows:

Establishing septic tanks followed by soak pits to treat the

domestic waste water generated from the offices, canteens ,

labour camp sheds.

Construction of Check dams /rock fill dams, wherever

necessary to reduce siltation and suspended solids.

9.4.8 GREEN BELT DEVELOPMENT (COMPENSATORY

AFFORESTATION)

Afforestation is proposed to be done in open areas with moderate

slope. This has to be supplemented with engineering/vegetative works

like gully plugging and check dams etc where ever required. The

planting area should be closed to grazing, lopping quarrying etc. For

proper protection, it is necessary that the area is fenced and the fence is

maintained properly. Plants need to be protected till they attain a

height, which is above grazing level.

Page 130: Bajoli Holi

IX -

21

9.4.8.1 DISPOSAL OF MUCK

By constructing the tunnel, underground power house and other items,

huge quantity of muck will be generated. It is expected that 30-35 % of

this will be used for making aggregates. The rest will require to be

disposed off and managed in a planned manner.

This is the most important aspect to be dealt with. It is proposed that at

different locations dumping sites will be identified at suitable places.

Retaining walls will be constructed. After the filling is done,

rehabilitation of this site will be done to ensure that neither it flows in

to the water stream nor it poses any other environmental threat.

Plantation, wherever possible, will also be done on these sites so that

these get stabilised over a period of time and do not pose any

environmental problem. When detailed EIA/EMP is done detailed

design for each and every dumping site will have to be prepared.

9.5 REPORT OF SATELLITE DATA ANALYSIS BY NRSA

9.5.1 STUDY BACKGROUND

Central Electricity Authority (CEA) under Ministry of Power, Govt. of

India has earlier identified 399 potential hydroelectric sites in the

country with an installed capacity of 1,07,000 Megawatt (MW). With

a view to preparing an action plan to develop this hydroelectric

potential and prioritizing the implementation of hydro-electric

projects, a Ranking Study was taken up by the CEA in 2001. This

Ranking Study identified 162 most potential sites with a total installed

capacity of 50,560 MW for development.

Preparation of Pre-Feasibility Reports (PFR) of these 162 sites has

been initiated by the CEA in 2002 with works entrusted to a number of

Consultants, namely, National Hydroelectric Power Corporation

Page 131: Bajoli Holi

IX -

22

(NHPC), North Eastern Electric Power Corporation (NEEPCO), Water

And Power Consultancy Services India Limited (WAPCOS), Satluj Jal

Vidut Nigam Limited ( SVJNL) , Himachal Pradesh State Electricity

Board ( HPSEB), Uttaranchal Jal Vidut Nigam Limited ( UJVNL) and

Kerala Power Corporation Limited ( KPCL) with time target of

completion of the whole exercise by September 2003. To oversee the

progress of the PFRs preparation in time and with full cooperation of

the Central Government agencies, a Central Coordination Committee

consisting of Central Electricity Authority (CEA), Central Water

Commission (CWC), India Meteorological Department (IMD),

Ministry of Environment & Forest, Survey of India, Geological Survey

of India (GSI) and National Remote Sensing Agency (NRSA) was

constituted by the CEA with Member (Hydro-power) as its Chairman.

The Committee is sitting periodically in presence of the representatives

of the Consultants to take stock of the completion of the studies. One

of the mandates of PFR preparation is “Initial Environmental Study”

with respect to each of the 162 proposed sites using satellite remote

sensing data.

As is well known in India and elsewhere in the world, space

technology plays a very important role in terrain mapping and

scientific assessment of the ground condition at speed, and is ideally

suitable for inaccessible mountainous regions where majority of these

hydroelectric dam/diversion sites are located. Computer processing of

satellite digital data of the dam / diversion sites and their immediate

environ provides wealth of information for preparation of the Pre-

Feasibility Reports. The Potential of this technology was amply

demonstrated in the preliminary ranking study of the 81 proposed

hydro-electric sites in Indus Basin completed by NRSA in October

2001 on behalf of CEA. In view of this, NRSA has been approached

by a number of consultants, namely, NHPC and HPSEB to take up

Initial Environmental Studies in respect of 37 proposed hydro-power

Page 132: Bajoli Holi

IX -

23

sites located in the States of Arunachal Pradesh, Himachal Pradesh,

Jammu & Kashmir and Madhya Pradesh using most recent satellite

remote sensing data.

NRSA in the recent month 9 Jan-May 2004) has completed initial

environmental studies with respect to 6 hydro-electric schemes located

in Chenab river basin for HPSEB, Sundernagar. Further, HPSEB has

requested NRSA for similar studies for additional two sites viz.

Chamba and Bajoli holi in Ravi river basin.

This Report deals with Bajoli-Holi hydro-power site.

9.5.2 OBJECTIVE

Principal objective of the satellite based study is to acquire Indian

Remote Sensing satellites (IRS 1C/1D) LISS-III and PAN sensor

digital data of the hydro-power sites and to make quick analysis of

these data in terms of estimation of the submergence area at proposed

Full Reservoir Level (FRL) and mapping of land use - land cover

information within and in immediate surrounding of the proposed

submergence area as inputs for Initial Environmental Study (IES) of

the Pre-Feasibility Report.

The specific objectives and scope of the study are:

• To estimate the area of submergence at proposed FRL of the

proposed hydro-power sites

• To analyse the satellite data for identifying broad landuse -

landcover categories like agricultural land, forest land, barren

land, scrub land, water bodies, settlements, infrastructural features

(roads and bridges) and to estimate the area under each of the

Page 133: Bajoli Holi

IX -

24

categories within and in immediate surrounding of the proposed

submergence area at FRL.

9.5.3 SALIENT FEATURES OF THE BAJOLI-HOLI HYDRO-

POWER SITE

Proposed hydro-power site is located at Bajoli-Holi in Ravi River

Basin in Himachal Pradesh falling in Survey of India topo sheets

No.52 D/11. The proposed project scheme at Bajoli-Holi envisages

construction of a diversion structure on Ravi river, and a power house.

The Head-Race Tunnel from the dam to the power house is proposed

to be 15 km in length. The river water will be diverted through the

Head-Race tunnel to the Power House for hydro-power generation.

The geographic location of Dam and Power House for this hydro-

power site is given here :

Dam Power House

Latitude : 32° 16’ 53” N 32° 20’ 31” N

Longitude: 76° 40’ 45”E 76° 32’ 37” E

9.5.4 SATELLITE DATA USED

Indian Remote Sensing Satellite, IRS-IC LISS III and PAN sensors

data of 27th September 2002 covering the study site were procured

from the NRSA Data Centre (NDC) after intensive browsing of the

available satellite data for cloud-free and radiometric suitability. IRS-

1C covers the study site by satellite geo-reference number Path 94 and

Row 48. These data are geometrically and radiometrically corrected

digital data products which can be used readily in Window based

image analysis platform.

Page 134: Bajoli Holi

IX -

25

9.5.5 BRIEF METHODOLOGY OF SATELLITE DATA ANALYSIS

Image processing and analysis was done using ERDAS Imagine

image analysis software in Windows platform. Satellite data of IRS

1D LISS III sensor provides 23.5 m spatial resolution and PAN

sensor provides 5.8m spatial resolution. The two sensor data were

geocoded and digitally merged using IHS transformation technique .

Baseline information layers (like rivers/ streams) and infrastructural

features (like roads and bridges), settlements / villages were initially

interpreted on the digital image scene. Subsequently, image

classification technique was performed to obtain the land use-land

cover categories of the study area.

Output maps were composed in the image processing system which

provide the landuse / landcover information along with other

interpreted information such as roads, settlements etc., within the 7

Km radius from the dam site. The location of the diversion structure

and power house from the index map provided by HPSEB,

Sundernagar was superimposed on the satellite data as well as on the

land use - land cover map. Area statistics of different landuse-

landcover categories were generated within the 7 km radius circle

from the diversion point on the river.

9.5.6 OUTPUTS PROVIDED

Based on the analysis of satellite data and other available ancillary

information, the following outputs were generated:

• Map 1 (a) Shows IRS 1 C PAN + LISS III merged satellite image

of 27th September 2002 on 1:50,000 scale covering 7 km radius

from the dam site overlaid with FRL , location of dam site and

power house.

Page 135: Bajoli Holi

IX -

26

• Map 1(b) Shows satellite derived landuse-landcover map on

1:50,000 scale covering 7 km radius from the dam site overlaid

with FRL , location of dam site and power house. Land use /land

cover map shows the following categories: Forest (Medium and

Low Dense Forest), Agricultural Land, Open Scrub, Barren,

Snow, River Course/ Dry River Bed.

• Map 1(c) Shows the land use- land cover classes and their

corresponding area statistics in hectares within the submergence

area on 1:25000 scale overlaid with FRL, location of dam site and

power house.

• Map 1 (d) Shows the location of the National parks / Wildlife

Sanctuaries vis-à-vis the location of the dam/ Power House and 7

km radius from the location of diversion structure .

• Table.1 Land use-land cover Information within the

Submergence Area ( 11.79 ha.)

S.No Land use-land cover

Category

Area under

submergence (Ha)

% of the total

submergence area

1 High Dense Forest Nil Nil

2. Medium Dense Forest 5.09 43.16

3. Low Dense Forest 0.83 7.04

4. Open Scrub 2.93 24.87

5. Barren / Rock Outcrop 0.21 1.80

6. Agricultural Land Nil Nil

7. Human Settlements Nil Nil

8. River Course including

dry river bed

2.73

23.13

9. Water Bodies Nil Nil

10. Snow Nil Nil

11. Cloud / Shadow Nil Nil

Total 11.79 100.00

Page 136: Bajoli Holi

IX -

27

• Table.2 Landuse-landcover Information within the 7 Km

Radius from the Diversion structure at Bajoli Holi

S.No Landuse-landcover Category Total Area

( ha)

% of the total

area

1 High Dense Forest Nil Nil

2 Medium Dense Forest 5640.78 36.65

3 Low Dense Forest 1812.96 11.78

4. Open Scrub 6216.38 40.38

5. Barren 948.69 6.16

6. Agricultural Area 141.45 0.92

7. Human Settlements 3.33 0.02

8. River Course including dry

river bed

105.32

0.68

9. Water Bodies Nil NIl

10. Snow 383.32 2.49

11. Cloud /Shadow 141.77 0.92

Total area 15394.00 100.00

9.5.7. CRITICAL ANALYSIS OF SATELLITE BASED INITIAL

ENVIRONMENTAL STUDY

• Total area under submergence at proposed FRL (2017 m. above

MSL) is estimated to be 11.79 ha (Table.1). The small

submergence area is a positive sign for the development of the

preset hydro-power site.

• It is observed from Table 1 and Figure 1c that the area under

vegetation cover class is estimated to be 5.92 ha. Which constitutes

50% of the total submergence area.

• Forest vegetation is classified as medium dense forest and low

dense forest. Area statistics of the forest density categories are

estimated as 5.09 ha and 0.83 ha respectively. There is no high

Page 137: Bajoli Holi

IX -

28

dense forest class is present in the submergence area and its

immediate environs.

• Hence, the presence of forest vegetation cover , which is only to

the extent of 6 ha. will pose least environmental concern in

developing the proposed hydro-power site.

• It is also observed that percent distribution of vegetation cover

class under forest category in the immediate surrounding (7 km

radius circle) of the proposed hydro-power site (table 2) is same (

approx. 50%) as that of submergence area.

• Land areas under other land use categories like barren / rock-

outcrop and open scrub together is around 3.14 ha., which is 32%

of the submergence area. Whereas, it is observed that this category

is predominant (approx. 50%) in the immediate environs of the

proposed hydro-power site (Table 2).

• It is found that there is no agricultural land present within the

proposed submergence area. This is a welcome positive indicator

of insignificant environmental cost, should the proposed hydro-

power project is developed at this site.

• There are no surface water bodies other than the river course.

• It is observed that there are no settlements existing within the

submergence area. This is a positive indicator so far as socio-

economic and demographic factor is concerned with respect to the

proposed hydro-power development project.

• It is observed from the Table 2 that snow cover is present to an

extent of 383 ha in the 7 km radius circle of the proposed dam with

few isolated settlements and few agricultural lands.

• In the absence of available information from other sources about

the existence and spatial extent of national parks and wildlife

sanctuaries, best efforts were made to collect information from the

Internet. The information available in website of United Nations

Environment programme World Conservation Monitoring Center

Page 138: Bajoli Holi

IX -

29

(http://www.unep-wcmc.org), National Informatics Centre, www.

wildarunachal.org and www.arunachalbhawan.com regarding

Arunachal Pradesh State and its National Parks / Wildlife

Sanctuaries, were browsed through. Based on these Internet

websites, following information is gathered.

- Great Himalayan National Park with an areal extent of 62,000 ha is

the only nearest National park (Fig 1(d)) is located at 83 km away

from the dam site in south eastern direction. However, exact

boundary / shape of this National Park is not available from these

websites. It is unlikely to have any significant impact on Great

Himalayan National Park. The Fig. 1d also shows that there are ten

sanctuaries located around the proposed dam site within 90 km

radius, of which Kugti, manali and Kais are located within 50 km

distance from the proposed dam site, whose areal extents are

37,886 ha, 3180 ha, 1419 ha respectively.

- Though the exact boundaries are not available , since Kugti

sanctuary is close to the proposed site (26 km away from the dam

site), it may likely to have impact on it. Hence, a detailed impact

assessment and habitat analysis may be carried out. However, exact

spatial extent (boundaries) of this park may be superimposed for

verifying the likely impact.

- Similarly, Manali sanctuary and kais sanctuary are situated at an

aerial distance of 42 and 54 kms from the dam site and their spatial

extents are 3180 ha and 1914 ha. which are unlikely to have any

impact by the proposed hydro electric scheme..

- Since 7 Km radius around the dam site was considered as the area

of study, efforts were made to check whether the geo-coordinates

of this National Park/ Wildlife Sanctuary is falling within the area

Page 139: Bajoli Holi

IX -

30

of study. The map No. 1(d) explains the location of the sanctuary

vis-à-vis the dam site and the power house.

9.5.8 CONCLUSION & RECOMMENDATION

1. Satellite based study has provided insight into the land use-land

cover pattern and their spatial extent within the submergence area

at FRL (2017m. above MSL) and within the 7 Km radius vicinity

of the proposed dam site. Such detail information on a scale of

1:25,000 is not available from any other sources at present.

2. It is observed that, there are no settlements within the submergence

area. This is a positive indicator of this hydro-power site. Within

the 7 Km radius of the dam site, there are small pockets of human

settlement (3.33 ha). However, Socio-economic and demographic

data of this and others not identified need to be verified on the

ground.

3. There is no agricultural land within submergence area. The

environmental cost on this score therefore is absolutely nil.

4. The proposed dam site and the power house locale is endowed with

good medium dense forest vegetation. However, since the

submergence area at FRL is confined within the river gorge, forest

vegetation of the spatial extent of 5.92 hectares will be affected due

to submergence. This is very insignificant. Species types of these

forest vegetation need to be identified from local Forest

Department and by field visit to the area.

5. Since the proposed dam is located on the gorge, the submergence

area mostly confines to the river course. The river course including

Page 140: Bajoli Holi

IX -

31

the dry river bed constitutes 23% of the proposed submergence

area (11.79 ha.).

6. Kugti, Manali and Kais sanctuaries are situated at an aerial distance

of 26, 42 and 54 kms respectively, away from the proposed dam

site, according to the information collected from several websites.

The location and wildlife of these sanctuaries will in no way be

affected by the hydro-electric project, since the fetch distance of

the reservoir submergence is around 0.6 km only. However, since

Kugti sanctuary is only 20 km away from the dam site, whose

exact spatial distribution need to be ascertained for evaluating the

impact by the proposed scheme.

7. Great Himalayan National park, which is located 83 km away

from the dam site. Though, the exact boundary / shape of this

National Park is not available from these websites, the present

hydro electric scheme with less ponding area and small fetch

distance, is unlikely to have any significant impact on this National

Park directly.

Page 141: Bajoli Holi

IX -

32

Page 142: Bajoli Holi

IX -

33

PARA DESCRIPTION PAGE

9.0 DESCRIPTION OF THE PROJECT IX-I

9.1 DESCRIPTION OF ENVIRONMENT IX-I TO IX-9

9.2 BASE LINE ENVIRONMENTAL STATUS IX-9 TO IX-12

9.3 ENVIRONMENT IMPACT ASSESMENT AND

EVALUATION

IX-12 TO IX-15

9.4 PREDICTION OF IMPACTS IX-15 TO IX-21

9.5 REPORT OF SATELLITE DATA ANALYSIS BY

NRSA

IX-21 TO IX-31

PLATE 9.1 IRS 1C PAN +LISS III MERGED SATELLITE

IMAGE OF 27TH SEPT. 2002

IX-32

PLATE 9.2 LANDUSE- LAND COVER MAP SHOWING THE

SURROUNDINGS OF PROPOSED DIVERSION

SITE AT BAJOLI-HOLI

IX-33

PLATE 9.3 MAP OF NATIONAL PARKS/ SANCTUARIES

AND THE LOCATION OF BAJOLI-HOLI

HYDROPOWER SITE AND 7 KM RADIUS

CIRCLE FROM DIVERSION SITE

IX-34

PLATE 9.4 SATELITE DERIVED LAND USE – LAND

COVER MAP OF PROPOSED DIVERSION SITE

AND ITS SURROUNDINGS

IX-35

Page 143: Bajoli Holi

IX -

34

Page 144: Bajoli Holi

CHAPTER – X INFRASTRUCTURE

10.0 IDENTIFICATION OF THE BROAD INFRASTRUCTURAL

REQUIREMENT FOR IMPLEMENTATION OF THE PROJECT

Bajoli-Holi Hydel Project is situated in Chamba Distt. of Himachal

Pradesh. The diversion barrage is about 22 km. from village Holi and 102

Km from Chamba, which is approachable through all weather road up to

Naya Gaon by state highway. Power House site is approachable by RCC

bridge on river Ravi near village Holi.

Adequate provision for residential and non-residential accommodation with

necessary amenities has been made for construction and design staff

proposed for the project. Workshop, stores, POL pumps, explosive

magazine and other infrastructural facilities have also been provided in the

estimate. Necessary provision for telecommunication, medical , educational

facilities and safety /security measures have also been made in the report.

All infrastructure facilities proposed for this project have been shown in

Drg. No. Bajoli-Holi-PR-12.

10.1 ROADS

10.1.1 GENERAL

A total of about 17 km. length of (5/7m. wide) road shall be needed to

connect the existing motorable road with the various project components

and job facilities. The widening of existing roads in the total length of 10

kms. has also been proposed.

Page 145: Bajoli Holi

10.1.2 PROJECT ROADS

Approach road 5/7 m. wide, 17 Km. long will connect different work sites

of the project with the existing motorable road.

The following roads have been proposed.

1. Proposed road to barrage site, = 3.00 km.

2. Surge shaft, pressure shaft and power house = 5.00 km

3. Proposed road to adit of HRT = 9.00 km

Total = 17.00 km.

4. Widening of existing motorable road from

Holi to Naya Gaon (Bajoli) to diversion site) = 10.00 km.

Total = 10.00 km.

5. Provision of R..C.C. bridge on river Ravi

near power house site = 1 No.

Provision of suspension bridge = 2 No.

10.2 BUILDINGS

It is proposed to construct residential and non-residential colonies for this

project at village Naya Gaon in private land/Govt. land. The existing HPSEB

workshop, offices and other buildings at Holi will also be available for use in

this project.

10.2.1 COLONY AT SUNDERNAGAR

A permanent residential/non-residential complex for design organization

will be constructed at Sundernagar. The same can be used for

monitoring/planning liaison purpose after the completion of the project.

Page 146: Bajoli Holi

10.2.2 COLONY AT VILLAGE NAYA GAON

Residential / non-residential colony for the construction of the project is

proposed to be constructed at village Naya Gaon which is about 15 km

from Holi and 7.00 km. from diversion barrage. Labour huts , stores and

field offices will be constructed near the project components on the small

terraces available.

10.2.3 OFFICE COMPLEX FOR OUTLET SIDE WORKS

Office complex for the construction of power house complex, penstock, surge

shaft and tunnel from outlet end is proposed on the terrace available near

village Holi.

10.2.4 SCHOOL & HOSPITAL

Adequate provision of buildings for Hospital, school etc. has been made in the

project estimate under Sub-Head K-buildings to cater for construction force.

First aid posts shall be provided at all project sites.

10.2.5 FIELD HOSTEL & REST HOUSE

Field hostel is constructed in the Holi project area near residential colony be

upgraded.

10.3 DUMP AREA

The muck of open & underground excavation shall be dumped in dump areas

identified at each project component site. The dumping station for power

house muck may be proposed at 1.0 km upstream from power house. Dump

areas chosen are located much above the river/nallah banks and are provided

with suitable retaining walls etc. Bull dozers shall be deployed in dump areas

for spreading and compaction of dumped material.

Page 147: Bajoli Holi

10.4 JOB FACILTIES

Flat terraces available near the project components wherever possible shall be

utilized for job facilities like stacking of construction material, D.G. sets, truck,

trailers, cement carriers, road rollers and site office stores etc.

10.5 QUARRY SITES

The material in the river bed may be suitable for aggregate. Rock from

different quarries in the vicinity of the project will also be tested, to assess

their suitability for manufacturing aggregate.

10.6 TELECOMMUNICATION

10.6.1 INTERNAL TELEPHONE SYSTEM

It is proposed to have an independent telephone exchange for this project. All

important work sites, offices within the project area will be connected by

telephones. A 80-lines capacity private automatic exchange (PBX) for the

project will be provided .

10.6.2 EXTERNAL TELEPHONE SYSTEM

Telecommunication link between project sites and outside places will be

provided by existing communication net work of Post & Telegraph

Department connected to the nearest P&T exchange at Holi. This system

would be operated and maintained by P&T Department on rental basis.

Power Line Communication Carrier (PLCC) system is also proposed for the

project.

Page 148: Bajoli Holi

10.7 WIRELESS SYSTEM

On the pattern of other ongoing hydel projects in H.P., fixed type VHF

Wireless link is proposed to be provided between project sites and design

office at Sundernagar, which will be further connected to existing wireless

system of HPSEB at Shimla.

10.8 PLANT AREAS

Plant area for different sites of work have been provided near respective sites.

It is proposed to install a central aggregate crushing, processing and

classification plant near quarry site proposed at power house site which will

fulfill the requirements of aggregates for diversion barrage, intake works and

powerhouse site to cater for the requirements of works of HRT from outlet

end, surge shaft, pressure shaft and powerhouse and appurtenant works. An

adequate capacity batching and mixing plant will be installed near intake to

cater the requirements of concrete for all inlet side works including tunnel

lining. Other batching and mixing plants of requisite capacity will be provided

near power house site for concreting work in power house complex , pressure

shaft, head race tunnel and surge shaft.

Central compressor houses will be located near tunnel portal to meet up the

requirements of the compressed air.

10.9 FIELD WORKSHOP

The HPSEB workshop be proposed at Holi will be utilized for this project on

job order basis. More workshops/repair shops are proposed to be established

near diversion site & power house site.

Page 149: Bajoli Holi

10.10 CONSTRUCTION POWER

Requirement of construction power will be met from existing transmission net

work in the area by suitably augmenting the same to meet requirement of the

project at various sites. Necessary provision for providing power lines and

distribution system has been made in the project estimate.

Adequate provision for stand by diesel generating sets has been made in the

project estimate to meet up power requirements in the event of power failures,

shutdowns / breakdown.

10.11 SAFETY

Safety is an essential job requirement for a highly mechanized work set up.

Adequate provision for fire fighting arrangements and security arrangements

has been made in the project estimate by way of police post/check-post and

check barriers etc.

Adequate safety/preventive measures against accidents are proposed to be

taken in accordance with the following Indian Standard Codes:

IS: 4756 For safety in tunneling work.

IS 3996 For scaffolds and ladders.

(Part I&II)

IS: 3764 For excavation work.

IS: 4081 For blasting and related drilling operations.

IS: 4138 For working in compressed air.

Page 150: Bajoli Holi
Page 151: Bajoli Holi

PARA DESCRIPTION PAGE

10.0 IDENTIFICATION OF THE BROAD

INFRASTRUCTURAL REQUIREMENT FOR

IMPLEMENTATION OF PROJECT

X-1

10.1 ROADS X-1

10.1.1 GENERAL X-1

10.1.2 PROJECT ROADS X-2

10.2 BUILDINGS X-2

10.2.1 COLONY AT SUNDERNAGAR X-2

10.2.2 COLONY AT VILLAGE NAYA GAON X-3

10.2.3 OFFICE COMPLEX FOR OUTLET SIDE WORKS X-3

10.2.4 SCHOOL & HOSPITAL X-3

10.2.5 FIELD HOSTEL AND REST HOUSE X-3

10.3 DUMP AREA X-3

10.4 JOB FACILITIES X-4

10.5 QUARRY SITES X-4

10.6 TELECOMMUNICATION X-4

10.6.1 INTERNAL TELEPHONE SYSTEM X-4

10.6.2 EXTERNAL TELEPHONE SYSTEM X-4

10.7 WIRELESS SYSTEM X-5

10.8 PLANT AREA X-5

10.9 FIELD WORKSHOP X-5

10.10 CONSTRUCTION POWER X-6

10.11 SAFETY X-6

Page 152: Bajoli Holi

CHAPTER – XI CONSTRUCTION PLANNING & SCHEDULE

11.0 CONSTRUCTION PLANNING & SCHEDULE

11.1 GENERAL APPROACH FOR CONSTRUCTION PLANNING AND

EXECUTION OF PROJECT COMPONENTS

11.1.1 CONSTRUCTION METHODOLOGY & EQUIPMENT PLANNING

11.1.2 GENERAL

Bajoli-Holi Hydel Project is a 180 MW capacity run of the river scheme in

Chamba District of H.P envisages utilization of 71.74 cumecs of design

discharge and 308 m of gross head. Diversion barrage has been proposed

at about 22 km. u/s of Holi village and the power house at about 1.00 km

d/s of Holi village. The project comprises following main civil structures:

Diversion Barrage

Intake structure

Desanding basin

Head Race Tunnel

Surge Shaft

Pressure Shaft

Power House

Tail race tunnel

11.1.3 COMPLETION TIME AND AVAILABLE WORKING SEASON

Construction programme, selection of methodology and equipment have

been planned with the aim of commissioning of the project in four and

half years. Available working season in a year shall be of 12 months for all

works, and eight months for the works in the river bed.

Page 153: Bajoli Holi

XI - 2

11.1.4 APPROACH ROAD AND THE LOCATION OF THE PROJECT

A total of about 17 Km road (5/7 m wide) shall be needed to connect the

existing motorable road with the project components i.e. barrage,HRT,

surge shaft area, power house, colony area, dump areas and other facilities.

11.1.5 CONSTRUCTION MATERIAL

11.1.5.1 CEMENT

ACC cement factory located at Barmana in Distt. Bilaspur (HP), on NH-

21 and at a distance of 415 Kms from the project site shall be the main

source of cement for meeting the entire cement requirement of the project.

Bagged cement shall be transported in trucks and stored in project stores at

different sites.

11.1.5.2 STEEL

SAIL stockyard at Jalandhar, 315 Kms. from main project store, shall be

the main source of structural and reinforcement/ tor. steel. Sizeable

quantities of reinforcement steel and structural steel shall have to be

stocked and replenished regularly. Penstock steel plates if not available

indigenously however, may have to be imported to suit the design

specifications.

11.1.5.3 AGGREGATE

The material in the river bed may be suitable for aggregate, however, the

same has to be got tested at detailed investigation stage.

Rock from different quarries in the vicinity of the project may also be got

identified, to assess their suitability for manufacturing aggregate. Rock

extracted from the quarries as well as from tunnel will be crushed and

classified to various sizes of aggregate in batching and mixing plant one

Page 154: Bajoli Holi

XI - 3

near the intake site and other near power house ( for excavated material

from tunnel).

11.1.6 STORES, LUBRICATION & WORK SHOP

The Petrol/diesel pumps, explosives magazine, workshops and other

construction facilities shall be provided to facilitate execution of the

project. While central stores for storage of cement, T&P articles, steel yard

as well as timber yard and main workshop shall be provided . Site stores

and field workshops will be established near respective sites. Petrol/diesel

pump shall be established near the power house site.

11.1.7 AGGREGATE PROCESSING PLANTS

Two aggregate crushing classification and sand manufacturing plants shall

be installed near each site of work and 2 nos. batching and mixing plants

shall be located near Power house& Diversion site.

11.1.8 PLANT AREAS

Plant areas for locating air compressor house, cement, aggregate, T&P,

stores and water storage tanks etc., shall be located near each site of work

and 2 nos. batching and mixing plants shall be located near Power house &

diversion site.

11.1.9 DUMP AREAS

The muck of underground excavation shall be dumped in dump areas

located within 1 km to 3.0 km from each portal. Dump areas for surface

excavation in surge shaft shall be at a maximum distance of 1 km and

power house area at a distance of 1.50 km.. Dump areas chosen are located

much above the river/nallah banks and are provided with suitable retaining

Page 155: Bajoli Holi

XI - 4

walls etc. Bull dozers shall be deployed in dump areas for spreading and

compaction of dumped material.

11.1.10 PRE-CONSTRUCTION FACILITIES

Pre construction facilities such as land acquisition for labour huts, plant

areas, stores, residential and non residential buildings, approach roads,

construction of bridges and explosive magazine in the valley shall be made

available to facilitate construction of the project.

11.1.11 EQUIPMENT PROVISION

Since main works of the project are proposed to be executed on contract

basis except the required infrastructural facilities, as such, the necessary

provision of machinery like material trucks, trailors, cement carriers, motor

grader and road rollers etc. has been made under Q-special-T&P, for

carrying out the works of infrastructural facilities. Provisions for personal

carriers, ambulance and field workshop equipment have also been made

under project estimate.

11.2 CONSTRUCTION SCHEDULE

The project has been proposed to be completed in 4½ years. Method of

execution of various components and selection of equipments have been

done with the object of commissioning first hydro unit by the end of 3rd

month of the fifth year, the second unit by the end of 5th month of fifth year

and the third unit by the end of 6th month of fifth year.

11.2.1 INFRASTRUCTURAL WORKS

It is proposed that all infrastructural works on the project comprising roads,

buildings, adits, workshops, stores, utility works, surveys, development of

Page 156: Bajoli Holi

XI - 5

quarries, leveling of area for installation of equipment and plants, pre-

qualification of tenders, award of contracts, detailed design of components

and other preliminary works shall be continued up to 4th year of project

execution.

11.2.2 DIVERSION BARRAGE

i) Coffer dam:- During 8th month of project construction.

ii) Excavation of barrage Const. Ist stage

From 9th month to 15th month of project construction.

iii) Concreting of barrage Ist stage

From 12th month to 15nd month.

From 18th month to 22nd month.

iv) Coffer dam 2nd stage

During 18th month.

v) Excavation of barrage 2nd stage

From 19th month to 25th month.

vi) Concreting of barrage 2nd stage

From 24th month to 27th month.

From 30th month to 36th month.

11.2.3 INTAKE STRUCTURE & FEEDER TUNNELS

Excavation:- From 9th month to 15th month.

Concreting:- From 18th month to 27th .

11.2.4 DESILTING TANK

Excavation:- From 9th month to 24th month.

Concreting:- From 21th month to 33rd month.

11.2.5 MECHANICAL WORKS FOR THE ABOVE FEATURES

Page 157: Bajoli Holi

XI - 6

From 20th to 45th months.

11.2.6 HEAD RACE TUNNEL

Excavation:- From 7th month to 36th month.

Concreting:- From 21st month to 46th month.

Grouting & cleanup :- From 42nd month to 48th month

11.2.7 SURGE SHAFT

Excavation from 12th month to 24th month.

Concreting:- From 24th month to 35th month.

Grouting & Clean up:- From 35th month to 38th month.

11.2.8 PRESSURE SHAFT

Excavation:- From 15th month to 27th month.

Concreting& liner:- From 27th month to 39th months.

11.2.6 POWER HOUSE

Excavation:- From 12th month to 27th month.

Concreting:- From 21st month to 42nd months.

11.2.10 TAIL RACE TUNNEL

Excavation:- From 19th month to 25th month. ; Concreting:- In 41st month.

11.2.8 INSTALLATION, TESTING AND COMMISSIONING

Installation of hydro units shall be started from the 32nd month. A period of

3 months for testing and commissioning of each unit has been provided

with first unit proposed to be commissioned in 51st month and second unit

Page 158: Bajoli Holi

XI - 7

in 53rd month of construction and 3rd unit in 54th month thus completing

the construction of the project as a whole in 54 month duration.

Page 159: Bajoli Holi

XI - 8

PARA DESCRIPTION PAGE

11.0 CONSTRUCTION PLANNING & SCHEDULE XI-1

11.1 GENERAL APPROACH FOR CONSTRUCTION PLANNING AND

EXECUTION OF PROJECT COMPONENTS

XI- 1

11.1.1 CONSTRUCTION METHODOLOGY & EQUIPMENT PLANNING XI-1

11.1.2 GENERAL XI-1

11.1.3 COMPLETION TIME AND AVAILABLE WORKING SEASON XI-1

11.1.4 APPROACH ROAD AND THE LOCATION OF THE PROJECT XI- 2

11.1.5 CONSTRUCTION MATERIAL XI- 2

11.1.5.1 CEMENT XI- 2

11.1.5.2 STEEL XI-2

11.1.5.3 AGGREGATE XI- 2 TO XI-3

11.1.6 STORES, LUBRICATION& WORK SHOP XI- 3

11.1.7 AGGREGATE PROCESSING PLANTS. XI- 3

11.1.8 PLANT AREAS XI-3

11.1.9 DUMP AREAS XI-3 TO XI-4

11.1.10 PRE-CONSTRUCTION FACILITIES XI-4

11.1.11 EQUIPMENT PROVISION XI- 4

11.2 CONSTRUCTION SCHEDULE XI- 4

11.2.1 INFRASTRUCTURAL WORKS XI-4 TO XI-5

11.2.2 DIVERSION BARRAGE XI-5

11.2.3 INTAKE STRUCTURE AND FEEDER TUNNEL XI-5

11.2.4 DESILTING TANK XI-5

11.2.5 MECHANICAL WORKS FOR THE ABOVE FEATURES XI-5

11.2.6 HEAD RACE TUNNEL XI-6

11.2.7 SURGE SHAFT XI- 6

11.2.8 PRESSURE SHAFT XI-6

11.2.9 POWER HOUSE XI-6

11.2.10 TAIL RACE TUNNEL XI-6

11.2.11 INSTALLATION TESTING AND COMMISSIONING XI-6

Page 160: Bajoli Holi

XI - 9

Page 161: Bajoli Holi

CHAPTER – XII

COST ESTIMATE

12.0 GENERAL

12.1 BASIS OF ESTIMATE

The estimate of Unit-I Civil Works has been prepared to arrive at the

capital cost of the Chamba Hydro Electric Project basis of June., 2004

price level. It is presumed that major civil works will be executed on

contract basis. The cost estimate does not include following items:-

- Escalation after June, 2004

- Interest during construction.

Detailed estimate of cost for Unit-I civil works is based mainly upon

various designs/drawings finalized for appurtenant structures and the rates

for principal items of works as per guide lines furnished by CEA vide

letter dt. 24th Oct. 2003. A provision of 3% has been made for

contingencies for C-works under Unit-I works. Guidelines for preparation

of project estimate issued by CWC during March, 1997 have been

generally followed for formulation of the estimate.

12.2 DESCRIPTION OF ITEMS

12.2.1 UNIT-I CIVIL WORKS

Under the head, civil works provision as made for various components of

the project is detailed here under:

Page 162: Bajoli Holi

A-Preliminary

Under this sub-head, provision of Rs. 958.55 lac has been made for

surveys and investigations conducted or to be conducted to arrive at the

optimum designs of project components.

B- Land

This covers the provision for acquisition of land for construction of the

project components, colonies, offices and store complexes and

compensation for trees and standing crops. Provision for forest trees in the

project area has also been included. A provision for Rs. 797.38 lac has

been made under this sub-head.

J Power Plant civil works

This covers the cost of civil engineering structures comprising intake

structure, head race tunnel, surge shaft, pressure shaft/ surge shaft, surface

power house complex and tail race channel. The total cost works to be Rs.

13365.95 lac.

K- Buildings

Buildings both residential and non- residential have been grouped

separately under permanent and temporary categories Under the

permanent categories, all those buildings have been included which will

be subsequently utilized for the operation and maintenance of project.

Whereas, under the temporary category, credit to the extent of 15% has

been given to the project on account of resale thereof. The cost has been

worked out on basis of plinth area rates as notified by HPPWD.. A

provision of Rs.1378.14 lac has been made under this sub-head.

Page 163: Bajoli Holi

X-Environment & Ecology

A provision of Rs. 502 lac has been made under this sub-head for

maintaining and improving the environmental status of the project area

and fir afforestation of affected area.

II-Establishment

A provision under this head has been made for Rs. 1468.68 lac @ 8% of I-

Works.

V-Receipts & Recoveries

This provision covers estimated recoveries by way of resale or transfer of

special T&P and temporary buildings. The amount thus works out to Rs.

293.02 lac only.

M-Plantation

This covers the cost of plantation and protection of plants to be planted

along project roads, colonies and in project area. Accordingly a provision

of 25.00 lac has been made under this sub-head.

O- Miscellaneous

A provision of Rs. 995.70 lac has been made for meeting cost of various

items listed therein.

Page 164: Bajoli Holi

Q-Special T&P

As the major civil works have been proposed to be got done on contract

basis. Machinery required for departmental activities like infrastructural

works, there subsequent repair/ maintenance and supervision works has

mainly been included under this sub-head. A provision of Rs. 496.71 lac

has been made under this sub-head.

R-Communication

A provision of Rs. 429.40 lac under this sub-head covers the cost of

roads. The road width have been planned to cater to the anticipated traffic

including movement of heavy trailors. Cost of roads is based on the rates

as notified by State HPPWD .

Thus a provision of Rs. 22481.73 Lac. has been made to cover the costs

under this unit (civil works)

12.2.2 UNIT-III ELECTRICAL WORKS

12.2.2.1 P-PRODUCTION

Cost of generating plants and equipments is based on current budgetory

prices. Prices of auxiliary equipments and services are based on historical

prices. Excise duty has been considered @ 16% of the component. CST,

Insurance and transport to site has been taken @ 6% of the cost of

respective component. Erection and commissioning charges have also

been taken @ 10% as per experience gained on similar installations in the

state. A provision of Rs. 14131.38 lacs has been made to cover the costs

under this sub-head.

Page 165: Bajoli Holi

12.2.2.2 T-TRANSMISSION

The cost based on detailed analysis on actual requirement under this sub

head amounts to Rs. 1178.47 lacs.

12.3 DETAILED ESTIMATE OF COST

Detailed estimate of cost as explained in above paras is given in

succeeding paras :

Page 166: Bajoli Holi
Page 167: Bajoli Holi

PARA DESCRIPTION PAGE

12.0 GENERAL XII-1

12.1 BASIS OF THE ESTIMATE XII-1

12.2 DESCRIPTION OF ITEMS XII-1

12.2.1 UNIT-I CIVIL WORKS XII-1 TO XII-4

12.2.2 UNIT-III ELECTRICAL WORKS XII-4

12.2.2.1 P-PRODUCTION XII-4

12.2.2.2 T-TRANSMISSION XII-5

12.3 DETAILED ESTIMATE OF COST XII-5 TO XII-36

Page 168: Bajoli Holi
Page 169: Bajoli Holi

CHAPTER-XIII

ECONOMIC EVALUATION

13.0 GENERAL

Bajoli-Holi Hydro-electric Project has been contemplated as a run of the

river development on Ravi river in tribal areas of Chamba district of

Himachal Pradesh. This project is estimated to cost Rs. 616.64 Cr. at price

level of June, 2004. The cost at power bus bar worksout to Rs. 580.62 Cr.

Abstract of cost estimate of Civil works, P-Production and T-Transmission

have been given as per Annexure13.1-(a) to13.1-(c). Year wise phasing of

expenditure for capital required on this project is given as per Annexure-

13.2. Interest during construction has been considered as per Annexure-

13.3. Depreciation on Civil and Electrical works has been worked out as

3.00% as per Annexure-13.4.The levelised tariff of energy generated at

power house bus bars has been worked out as Rs. 1.60 per unit during 90%

dependable year as per Annexure-13.5. The cost of energy in the Ist year of

operation works out to Rs. 2.03 per unit.

13.1 CAPITAL COST OF THE PROJECT

Abstract of the capital cost of the project, to the price level of June, 2004 is

as under: -

Page 170: Bajoli Holi

XIII - 2

S.No. Description Amount

(Rs. in lac.)

1. Unit-I Civil works 41501.13

2. P-Production (Electrical works) 16560.59

Total Generation Cost 58061.72

3. Transmission 3602.54

Grand total 61664.26

13.2 ECONOMIC JUSTIFICATION

Bajoli-Holi HEP has been conceived as an upstream development of Kutehr

HEP (260MW) and power therefrom is has been proposed to evacuated

through 400 KV D/C line up to PGCIL substations in the Northern grid

As laid down in CEA and CERC Guidelines, economic justification of a

hydel project is to be done by comparing cost of alternative sources of

energy in that region. The levellized tariff of this project in 90% dependable

year works out as Rs. 1.60/ unit at power house bus bars as per Annex.-

13.5.This project will provide power at cheaper rates in comparison to

thermal power, rate which , at present is more than Rs.3.75 / unit.

Additionally this project will provide pollution free power for years together

at much cheaper rates considering the escalation in coal prices for Thermal

Power.

13.3 CAPITAL STRUCTURE

Capital structure has been assumed as 70% debt from Financial Institutions

and 30% equity from Govt.

Page 171: Bajoli Holi

XIII - 3

13.4 REVENUE ANTICIPATION

Power tariff for supply of power at powerhouse bus bars has been assumed

as Rs. 2.75 per unit. Revenue has been assessed accordingly for 90%

dependable year as Rs. 199.3 Cr.

13.5 REPAYMENT PERIOD

Normally, the leading financial institutions in India prescribe a repayment

period of 15 years including 3 to 4 years moratorium period. A period of 12

years has therefore been taken into account, as repayment period in fixation

of tariff.

.

13.6 COST PER MW

The estimated cost of the project at June, 2004 price level is Rs. 616.64 Cr.

including transmission and Rs. 580.62 Cr. at power bus bar for an installed

capacity of 180 MW. This gives a capital cost of Rs. 3.43 Cr.per MW of

installed capacity including cost of transmission and Rs. 3.23 Cr. per MW

for generation. At present price level, the cost of medium hydro-electric

project at Rs. 6.00 crore per MW is considered to be reasonable. From this

criterion, the cost per MW for Bajoli - Holi Hydel Project is reasonable

making the project suitable for exploitation.

13.7 INTEREST DURING CONSTRUCTION

The detail of expenditure during the construction period and the calculation

of interest during construction have been shown in Annexure-13.3. It is

seen that IDC @ 10.00 % on loan works out to Rs. 68.60 crores at power

house bus bars.

Page 172: Bajoli Holi

XIII - 4

13.8 ENERGY AVAILABLE FOR SALE

As per power studies of the project, the total energy generation in 90%

dependable year has been arrived at 724.83 MUs. As per Govt. of India

Guide Lines, an auxiliary consumption @ 0.7% and transformation losses

@ 0.5% have been considered at power house bus bars .

13.9 RATE OF DEPRECIATION

As per the revised guidelines circulated by Govt. of India, Ministry of

Power, Vide notification dated 29th March, 1994, the weighted rate of

depreciation has been worked out on the basis of straight line formula. The

rate of depreciation works out to 3.00% of the project cost as per

Annexure-13.4.

13.10 OPERATION AND MAINTENANCE CHARGES

As per the guide lines of Ministry of Power, Govt. of India, the Operation

and Maintenance charges inclusive of insurance have been taken as 1.50 %

of the capital cost.

13.11 CALCULATION OF TARIFF

Calculation of tariff for primary energy during 35 years of operation for

90% dependable year has been worked out as per GOI notification shown in

Annexure-13.5 comprising the following.

i) Interest on loan from PFC @ 10.00 % p.a.

Page 173: Bajoli Holi

XIII - 5

ii) Interest on working capital @ 9.75 % required for 2 months of

average billing for sale of electricity and operation and maintenance

expenses for one month.

iii) O&M charges including insurance charges @ 1.5% p.a.

iv) Income tax @ 35% and surcharge @ 10% on income tax has been

considered.

v) Discounting rate @ 12% for tariff calculation .

At power house bus bar, it will be seen that sale rate of power shall be Rs.

2.03 per unit during Ist year of operation and Rs. 0.97 per unit during 13th

year i.e after repayment of loan. The levelised tariff rate works out to Rs.

1.60 per unit at power house bus bars.

13.12 INDIRECT BENEFITS

Beside providing pollution free power at a cheaper rate to the Northern

Grid; discussed as in preceding paras, this project, located in tribal areas of

Chamba district of HP, will help in the overall development of the people of

the area.. Employment to skilled/non-skilled labour of the area, industrial

and economic development are additional benefits from this project.

Keeping these points in view, this project merits consideration for an early

implementation.

13.13 MERITS OF THE PROJECT

Bajoli - Holi HEP (180 MW) is an up stream development of proposed

Kutehr HEP (260 MW). Following are the strengths and weaknesses of the

project.

i) Project sites are located on the right bank of river Ravi.

Page 174: Bajoli Holi

XIII - 6

ii) No major resettlement of people is required for construction of

project.

iii) Construction material will be locally available.

iv) Almost all the major sites of the project viz. intake, inlet portal and

adit portals of HRT and power house will be connected with

motorable road.

v) The levellised tariff works out to be Rs. 1.60 per unit at power

house bus bar which is on lower side.

13.14 CONSTRUCTION SCHEDULE

The construction of the project has been proposed to be completed in four

and half years period. The construction schedule has been presented in

drawing No. Bajoli - Holi-PR-11 .

Page 175: Bajoli Holi

XIII - 7

Page 176: Bajoli Holi

XIII - 8

PARA DESCRIPTION PAGE

13.0 GENERAL XIII-1

13.1 CAPITAL COST OF THE PROJECT XIII-1 TO XIII-2

13.2 ECONOMIC JUSTIFICATION XIII-2

13.3 CAPITAL STRUCTURE XIII-2

13.4 REVENUE ANTICIPATION XIII-3

13.5 REPAYMENT PERIOD XIII-3

13.6 COST PER MW XIII-3

13.7 INTEREST DURING CONSTRUCTION XIII-3

13.8 ENERGY AVAILABLE FOR SALE XIII-4

13.9 RATE OF DEPRECIATION XIII-4

13.10 OPERATION AND MAINTENANCE

CHARGES

XIII-4

13.11 CALCULATION OF TARIFF XIII-4 TO XIII-5

13.12 INDIRECT BENEFIT XIII-5

13.13 MERITS OF THE PROJECT XIII-5 TO XIII-6

13.14 CONSTRUCTION SCHEDULE XIII-6

ANNEXURE-13.1-(a)

TO 13.1(c)

ABSTRACT OF COST OF CIVIL

WORKS, P-PRODUCTION & T-

TRANSMISSION

XIII-7 TO XIII-9

ANNEXURE-13.2 YEARWISE PHASING OF FUNDS XIII-10

ANNEXURE-13.3 CALCULATION OF INTEREST DURING

CONSTRUCTION AT POWER HOUSE

BUS BARS

XIII-11

ANNEXURE-13.4 WEIGHTED AVERAGE DEPRECIATION

XIII-12

ANNEXURE-13.5 LEVELLISED TARIFF OF ENERGY FOR

90% DEPENDABLE YEAR AT POWER

XIII-13 TO XIII-

14

Page 177: Bajoli Holi

XIII - 9

HOUSE BUS BARS.

Page 178: Bajoli Holi

EXECUTIVE SUMMARY

1. INTRODUCTION

As a part of an exercise to assess the balance hydro potential of the

country Central Electricity Authority (CEA )identified more than

399 Hydro-electric Projects with probable installed capacity of 50,000

MW. After carrying out ranking studies, 162 projects have been

identified for preparation of Preliminary Feasibility Reports. Bajoli

Holi in Ravi basin has been identified as one of these projects for

preparation of PFR by HPSEB so that it could be taken up for further

development during the 10th & 11th Plans. Bajoli Holi HEP is

located in Ravi basin between the longitude 76°40'45" - 76°32'37" and

latitude 32°16'53" to 32°20'31" in the Chamba district of Himachal

Pradesh.

Consequently site visits were made to the area by Engineers of

HPSEB and Geologists of GSI for identification/selection of suitable

site. The diversion site of the project is located near village Bajoli

and underground power house site is located near village Borola

(Opposite to village Holi) on Chamba-Holi road and all sites of the

project will be well connected with roads.

2. SCOPE OF THE PROJECT

The project has been contemplated as an upstream development of

Kutehr HEP (260 MW). It envisages the construction of barrage

across the river Ravi near village Bajoli, intake structure, two no.

feeder tunnels and underground desilting arrangement to divert

Page 179: Bajoli Holi

71.74 cumecs of water through a 5 m dia modified horse shoe

concrete lined tunnel 14600 long, a surge shaft 12 m dia ± 96 m

heigh, a pressure shaft 4 m dia trifurcating near power house to 2.30

m dia each to generate 180 MW power in an underground power

house near village Barola. The annual power generation from the

project in 90% dependable year will be 762.98 Gwh.

3. HYDROLOGY

River Ravi originates from Bara Banghal in Kangra district as a joint

stream formed by the glacier fed Bhadal & Tantgari at an elevation

of 4229 m above mean sea level. High peaks of the catchment remain

covered with snow for about 9 months in a year. The catchment

area of Bajoli Holi diversion site measures 760 Sq.Km. The entire

catchment comprises of mountainous terrain with steep hill slopes.

Out of total catchment area of 760 Sq.km., about 30% area is under

permanent cover of snow. The principal tributaries of the Ravi upto

Bajoli Holi diversion site are Tanetar Gol nallah and Sandrali nallah,

Dera nallah and Raula ka nallah. The project area receives

precipitation due to the South-West Monsoon as well as the

Western disturbances that pass over the North–West part of the

country during winter. There are thirteen non recording type rain

gauge station in the catchment area of the river Ravi. The normal

annual rainfall and annual rainfall has been recorded in millimeters

at all these stations for the period 1960 to 2000 by the office of

Director land records, revenue department (HP). The river run off

has been derived from melting of the snow/ice/glacier bound area

of the catchment and the other which is directly derived from

rainfall. Discharge data is available for hydrological studies at

Bagga, Durgathi, Banthu, Tiyari and Kutehr. The design discharge

Page 180: Bajoli Holi

of 71.74 cumecs has been proposed for carrying out the hydrological

and power potential studies. Design flood at diversion site has been

computed based on “Flood Estimation Report for Western

Himalayan Zone-7”. Design flood of 3050 cumecs has been worked

out.

4. POWER POTENTIAL STUDIES

Bajoli Holi HEP has been contemplated as a peaking station to

operate North Regional Grid. Installed capacity of the projet has

been presently kept as 180MW comprising 3 units of 60 MW each.

The project will generate 762.98 Gwh in 90% dependable year with

48% plant load factor.

5. POWER EVACUATION ASPECTS

The Bajoli Holi HEP is being developed as an up stream

development of Kutehr HEP (260 MW). The power from Bajoli Holi

HEP (180MW) has to be evacuated through LILO of 400 KV Kutehr

(260MW) and Hibra HEP (231MW) transmission line.

6. ENVIRONMENTAL ASPECTS

Environmental Management Plan (EMP) aims at the preservation of

ecological system by considering certain mitigating measures at the

proposed site. The EMP is required to ensure sustainable

development in the study area of 10 km. radius of the proposed

Bajoli Holi HEP site. Government regulating agencies like H.P.

Pollution Control Board working in the region and more

Page 181: Bajoli Holi

importantly the people living in the area need to extend their co-

operation and contribution in this direction.

It has been evaluated that the study area shall not be affected

adversely with the proposed activity, but is likely to get new

economical fillip due to hydel power generation, not only for the

study area but also for the region as whole.

7. ESTIMATES OF COST

The estimates of cost has been prepared on the basis of “CEA

Guidelines for Rates and Cost of Civil and Electrical works for

Preliminary Feasibility Reports of Hydro-electric Projects” received

during Oct. 2003. Accordingly cost of project works out to be Rs

41501 lac for civil works, Rs.16561 lac for electrical works and

Rs.3603 lac for transmission works based on June, 2004 price level.

8. FINANCIAL ASPECTS

The financial & economic evaluation has been carried out as per

CEA guide lines considering Interest During Construction (IDC)

@10% and interest on working capital @ 9.75%. The life of hydro-

electric project has been considered as 35 years. The 762.98 GWH

energy units are available at power house bus bars in 90%

dependable year and cost per unit at power house bus bars works

out to Rs 2.03 per Kwh in first year. The levelised tariff rate of

energy works out to be Rs.1.60 per Kwh at power house bus bars.

Page 182: Bajoli Holi

9. CONCLUSION

The economy of the Himachal Pradesh is predominantly dependent

on agricultural and allied sectors. The electric power being a vital

and essential infrastructure has a significant role to play in economic

upliftment of the state. The construction of project will provide

employment to the local people. The project will be completed

within four and half years period. Being an attractive project, it

deserves to be taken up for execution on priority.

Page 183: Bajoli Holi

BAJOLI-HOLI HYDRO ELECTRIC PROJECT (3X60 =180 MW) HIMACHAL PRADESH

1. INTRODUCTION The Bajoli-Holi Hydroelectric Project located in Chamba District of

Himachal Pradesh envisages utilization of the waters of the river Ravi for power generation on a run of river type development, harnessing a head of about 308m.

The project with a proposed installation of 180 MW (3x60 MW) would

afford net annual energy generation of 762.98 GWh, in a 90 % dependable year. The tariff at present day cost would be Rs 1.60/unit (levellised) at power house bus bars and Rs.1.93/unit (levellised) at purchase center.

The project is located between Latitude 32o16' North and 32o20' North,

Longitude 76o40' East and 76o32' East. The barrage site is approachable from Pathankot by road being at a distance of 222 kms approx. The nearest rail head is located at Pathankot and nearest airport is located at Jammu.

2. SCOPE OF WORKS The Bajoli-Holi HE project envisages construction of :

a 33m high diversion barrage across river Ravi to provide a net live storage of 79.95 hacm. with FRL at 2015.00 m and MDDL at 1993.00m;

two numbers desilting chambers of length 380m(L) and size 13m (W)x19.60m(H) to remove silt particles of size 0.20 mm and above;

a 14.60 km long and 5.0m dia. modified horse shoe shaped head race tunnel terminating in a surge shaft;

a 96m high ,12.0m dia surge shaft;

440m long, 4.0m dia pressure shaft;

a surface power house having an installation of 3 Francis driven generating units of 60 MW each operating under a net head of 278 m; and

450m long tail race tunnel to carry the power house releases back to the river Ravi;

Page 184: Bajoli Holi

The power generated from the project would be evacuated through. 220 KV single circuit line 35 Km long upto Kutehr power house to feed power to the power grid .

The Salient features of the project are given at Annex-I and a layout map

at Plate-I 3. HYDROLOGY The river Ravi drains a catchment area of about 760 sq.km. at the

proposed barrage site. The water availability for the project has been considered on the basis of 10-daily discharge series at Kutehr discharge site for the period 1972 to 1997. The discharge observations recorded on Ravi river at Bajoli just down stream of barrage site since June 1997 to May, 2003 has been used for determining a co-relation by regression analysis between the discharges at Kutehr & Bajoli. The design flood has been assessed as approx. 3050 cumecs.

4. POWER POTENTIAL STUDIES The computed inflow series for 31 years viz 1972-73 to 2002-03 has been

considered in the assessment of a power benefits from the project. As per GOI notification for tariff, the year 1987-88 corresponds to 90% dependable year. An installation of 180 MW comprising 3 generating units of 60 MW each has been proposed. The energy availability from the project in a dependable and an average year has been summarized below:

Particulars Dep. Yr. Avr. Yr.

Annual Energy Generation

Gross annual Energy Generation (GWh)

762.98 861.37

Annual Load Factor (%) 48 55

Generation during Lean Flow Season (Nov.-Feb.)

Energy Output (GWH) 44.64

Load Factor (%) 11 The design energy at 95 % machine availability in a 90% dependable year

has been worked out at 754.13 GWh. A net live pondage of 79.95 ham. has been provided in the diversion

barrage, which would enable the station to operate as peaking station. The

Page 185: Bajoli Holi

pondage is equivalent to 557.20 MWH which is sufficient to operate the station for 3.65 hours.

5. POWER EVACUATION ASPECTS It has been proposed to inject the power generated at Bajoli-Holi power

house into 220 Kv Kutehr HEP. For wheeling of power that shall be accumulated at Kutehr HEP, 220 Kv D/c line from Kutehr to Hamirpur with 2x0.5 or 4x0.5 conductor depending upon total firmed up capacities of projects up stream of Kutehr HEP, shall be laid.

6. ENVIRONMENTAL ASPECTS The project is located in tribal area of Chamba Distt. The total land

requirement for the construction of various components is 117.15 ha.,out of which private land is 25 ha. Based on assessment of environmental impacts, management plans have to be formulated for Catchment Area Treatment , compensatory afforestation and other environmental issues. These issues would be addressed during investigations for preparation of DPR.

7. ESTIMATES OF THE COST The project is estimated to cost Rs. 649.22 crores at power house bus bars

and Rs 668.35 crores at purchase center including IDC at June, 2004 price level. The preliminary cost estimate of the project has been prepared as per guidelines of CEA / CWC. The break down of the cost estimates is given below: Civil works : Rs. 415.01 Crores Electro Mechanical works : Rs. 165.61 Crores Sub total (Generation) : Rs. 580.62 Crores Transmission works : Rs. 36.03 Crores Total Cost : Rs. 616.64 Crores On Generation works Interest During Construction : Rs. 68.60 Crores Total : Rs. 649.22 Crores At purchase center Interest During Construction : Rs. 71.70 Crores Total : Rs. 688.35 Crores

Page 186: Bajoli Holi

8. FINANCIAL ASPECTS As indicated above, the Bajoli-Holi HE project with an estimated cost of

Rs. 649.22 (including IDC of Rs.68.60 crores) at power house bus bars and cost of Rs. 688.35 crores (including IDC of Rs.71.70 crores ) at purchase center with net energy of 762.98 GWH in a 90% dependable year. The project is proposed to be completed in a period of 4½ years. The tariff has been worked out considering a debt-equity ratio of 70:30, 16% return on equity, annual interest rate on loan at 10% and the tariff for first year and levellised tariff have been work out Rs. 2.03 /Kwh & Rs. 1.60/Kwh respectively at power house bus bars and Rs. 2.51 /Kwh & Rs. 1.93/Kwh respectively at purchase center.

9. CONCLUSIONS Bajoli-Holi HE project involves simple civil works and could be

completed in 4½ years. The project would afford a design energy of 762.98 Gwh in a 90% dependable year. The cost per MW installed capacity works out Rs. 3.23 crores. The Preliminary Feasibility Report indicates that the scheme merits consideration for taking up for Survey & Investigation and preparation of DPR.

Page 187: Bajoli Holi

Annexure-1

GENERAL PROJECT FEATURES

LOCATION

State Himachal Pradesh

District Chamba

River Ravi

Diversion barrage Near village Bajoli

Power house site Near village Barola

HYDROLOGY

Catchment Area at intake site 760 Sq. km.

Snow catchment 372 Sq. km. above El. 4000m

Mean annual rainfall at Bharmour 899 mm

Design flood 3050 cumecs

DIVERSION STRUCTURE

Type Gated Barrage

Length of Barrage at top ±100.00 m

Max. height from R.B.L 33.00 m

Top El. of Barrage 2018.00 m

Average River Bed level. 1985.00 m

FRL 2015.00 m

MDDL 1993.00 m

SPILLWAY

Design flood 3050 cumecs

Page 188: Bajoli Holi

Type Gated spillways with radial gates

Nos. of spillways, Crest elevation 6 Nos , El 1987.00

Size of gated spillway 6m x 8m, each.

Energy dissipation Stilling basin

Down stream bed level El. 1975m

INTAKE STRUCTURE

Type Semi circular

Crest level El. 1990.00 m

No. & size of opening 8 No., 5.50 mx3.0 m

FEEDER TUNNEL

No. 1

Size and type 6.00m dia, Circular concrete lined

Velocity 3.17m/sec

Length ± 300m

Design discharge from intake 89.67 cumecs

DESANDING BASIN

Type Underground.

No. of basins 2 nos.

Length of each basin 380m

Size of basins Width 13.00m, Depth 19.60m

Minimum particle size to be removed 0.2mm

Flushing tunnel, size 4.00m, D-Shaped

Flushing tunnel, length ± 1000 m

Page 189: Bajoli Holi

HEAD RACE TUNNEL

No. One

Size & Shape 5m diameter, modified

Horse shoe concrete lined

Length ±14600 m

Design discharge 71.74 cumecs

Slope 1 in 409 m

Velocity 3.65m/sec

SURGE SHAFT

Type Open to sky, Restricted orifice type

Size 12.00 m dia cricular

Orifice 2.15 m dia

Maximum upsurge level El.± 2043 m

Minimum down surge level El.± 1960 m

Bottom level El±.1954 m

Top level El.± 2050 m

PRESSURE SHAFT

Type Underground

Size:

Main 1 No., 4m dia, ± 440 m long

Branches 3 Nos., 2.30 m dia, ± 20 m long each

Velocity 5.74 m/sec.

POWER HOUSE

Type Underground

Page 190: Bajoli Holi

Installed capacity 180 MW

No. and capacity of unit 3 Nos. 60 MW

Size of machine hall 50 m x 17 m x 35 m

Type of turbine Francis turbine

Speed of turbine 500 RPM

Gross Head 308 m

Normal tail water level 1700 m

Net operating head for design discharge 278 m

Peaking duration 3 hrs .

TAIL RACE TUNNEL

Shape D-Shaped

Dia 5.00 m

Length ± 450 m

SWITCH YARD

Type Surface

Size 170 (L) x 35 m (W)

TRANSMISSION LINE

No. of circuits S/C Line

Length of each 35 km.

Voltage 220 KV

POWER GENERATION

Installed capacity 3x60 MW

Page 191: Bajoli Holi

Annual energy generation

90% dep. Year 762.98 GWH

50% mean year 861.37 GWH

COST ESTIMATE & FINANCIAL ASPECTS

COST ESTIMATE

Capital cost of the project (At Price level June. 2004):

Civil works Rs. 415.01 Crore

Electrical works

(P-Production) Rs. 165.61Crore

T-Transmission Rs. 36.03 Crore

Total Rs 616.64

Capital cost of Generation Rs. 649.22 Crore

(Including IDC Rs. 68.60Crore)

Loan 70% Rs. 454.45Crore

Equity 30% Rs. 194.76Crore

Capital cost at purchase center Rs. 688.35 Crore

(Including IDC Rs. 71.70Crore)

Loan 70% Rs. 481.84Crore

Equity 30% Rs. 206.50Crore

FINANCIAL ASPECTS

Cost of generation per MW of

Installed capacity Rs. 3.23Crore

Page 192: Bajoli Holi

Levelized tariff at PH Rs. 1.60/Kwh

Bus bars in 90% dep. Year

Levelized tariff at purchase center Rs. 1.93/Kwh

in 90% dep. Year

Energy available for sale in 90% dep. Year 753.82GWH

(Auxiliary consumption @ 0 .7% &

Transformation losses @ 0.5%).

at power house bus bars

Page 193: Bajoli Holi